HARGA JUMLAH
NO. URAIAN DAN JENIS PEKERJAAN VOLUME SAT
SATUAN HARGA
1. 2 3. 4 5. 6.
I PEKERJAAN PENDAHULUAN
1 Papan Nama Proyek 1.00 Ls 335,000.00 335,000.00
2 Pengadaan Air kerja dan P3K 1.00 Ls 500,000.00 500,000.00
3 Pembuatan Gudang Semen & Barak Kerja 1.00 Ls 1,800,000.00 1,800,000.00
4 Pembongkaran Bangunan Lama 1.00 Ls 3,650,000.00 3,650,000.00
5 Pembuatan laporan dan As Build Drawing 1.00 Ls 2,000,000.00 2,000,000.00
SUB TOTAL 8,285,000.00
II PEKERJAAN GALIAN TANAH
1 Pek. Galian Tahan 153.67 M3 68,887.50 10,585,942.13
2 Pek. Urugan Tanah Kembali 91.83 M3 49,775.00 4,570,987.58
3 Pek. Urugan Pasir Bawah Pondasi 13.47 M3 284,295.00 3,830,590.83
SUB TOTAL 18,987,520.53
III PEKERJAAN BATU DAN PASANGAN
1 Pas. Batu Kosong 45.33 M3 475,259.40 21,543,508.60
2 Pas. Pondasi Batu gunung 1 : 5 98.07 M3 830,621.00 81,459,001.47
3 Pas. Dinding bata 1 : 5 432.10 M2 124,855.72 53,950,156.61
SUB TOTAL 156,952,666.68
IV PEKERJAAN BETON
A Pek. Beton Poor Plat P1
a. Pek. Beton K 250 17.25 M3. 1,250,087.58 21,564,010.74
b. Pek. Pembesian Polos 3,345.22 Kg 15,771.25 52,758,285.28
c. Pek. Bekisting 92.40 M2 157,102.00 14,516,224.80
B Pek. Beton Sloof 20/15
a. Pek. Beton K 250 7.62 M3. 1,250,087.58 9,530,667.71
b. Pek. Pembesian Polos 3,064.06 Kg 15,771.25 48,323,996.82
c. Pek. Bekisting 64.16 M2 165,902.00 10,644,272.32
C Pek. Beton Kolom 20/25
a. Pek. Beton K 250 9.59 M3. 1,250,087.58 11,985,214.67
b. Pek. Pembesian Polos 2,955.71 Kg 15,771.25 46,615,169.93
c. Pek. Bekisting 161.70 M2 298,661.00 48,293,483.70
D Pek. Beton Kolom 15/25
a. Pek. Beton K 250 1.50 M3. 1,250,087.58 1,875,131.37
b. Pek. Pembesian Polos 122.05 Kg 15,771.25 1,924,889.89
c. Pek. Bekisting 32.00 M2 15,771.25 504,680.00
E Pek. Beton Kolom 25/25
a. Pek. Beton K 250 0.44 M3. 1,250,087.58 546,913.32
b. Pek. Pembesian Polos 29.52 Kg 15,771.25 465,536.07
c. Pek. Bekisting 1.82 M2 298,661.00 543,563.02
F Pek. Beton Kolom 15/15
a. Pek. Beton K 250 0.11 M3. 1,250,087.58 140,634.85
b. Pek. Pembesian Polos 25.65 Kg 15,771.25 404,475.79
c. Pek. Bekisting 0.26 M2 303,941.00 78,416.78
G Pek. Beton Balok25/30
a. Pek. Beton K 250 0.42 M3. 1,250,087.58 525,036.78
b. Pek. Pembesian Polos 55.97 Kg 15,771.25 882,794.33
c. Pek. Bekisting 3.36 M2 303,941.00 1,021,241.76
H Pek. Beton Ringbalk RB1 15/15
a. Pek. Beton K 250 5.03 M3. 1,250,087.58 6,281,690.09
b. Pek. Pembesian Polos 1,195.47 Kg 15,771.25 18,854,087.78
c. Pek. Bekisting 150.00 M2 303,941.00 45,591,150.00
SUB TOTAL 343,871,567.79
V PEKERJAAN PLESTERAN
1 Pek. Plesteran dinding tembok, 1 : 5 864.20 M2. 63,253.26 54,663,463.84
3 Pek. Plesteran Pondasi,Sloof, Kolom, dan Ringbalk 1 : 3 36.50 M2. 63,253.26 2,308,743.84
3 Pek. Profil Kolom, dan Dinding 1.00 Ls 2,500,000.00 2,500,000.00
SUB TOTAL 59,472,207.68
V PEKERJAAN BESI
1 Pek. Besi Hollow 2/4 550.00 M1 14,166.67 7,791,666.67
1 Pek. Besi Hollow 4/4 226.00 M1 20,833.33 4,708,333.33
SUB TOTAL 12,500,000.00
VI PEKERJAAN KERAMIK, HURUF DAN PINTU
1 Pas. Keramik Dinding 30 x 30 cm 6.84 M2 397,014.93 2,715,582.14
2 Pas. Huruf Timbul Stainless Steel 1.00 Ls 4,500,000.00 4,500,000.00
5 Pek. Pintu Gerbang 2.00 Buah 6,000,000.00 12,000,000.00
SUB TOTAL 19,215,582.14
VII PEKERJAAN CAT DAN FINISHING
1 Pek. Cat plafond 900.70 M2. 18,968.95 17,085,333.27
SUB TOTAL 17,085,333.27
RENCANA ANGGARAN BIAYA
HARGA JUMLAH
NO. URAIAN DAN JENIS PEKERJAAN VOLUME SAT
SATUAN HARGA
1. 2 3. 4 5. 6.
I PEKERJAAN TANAH DAN PASIR
1 Papan Nama Proyek 1.00 Ls 325,000.00 325,000.00
2 Pengadaan Air kerja dan P3K 1.00 Ls 500,000.00 500,000.00
3 Pembuatan Gudang Semen & Barak Kerja 1.00 Ls 1,500,000.00 1,500,000.00
4 Pembongkaran Bangunan Lama 1.00 Ls 3,500,000.00 3,500,000.00
5 Pembuatan laporan dan As Build Drawing 1.00 Ls 2,000,000.00 2,000,000.00
SUB TOTAL 7,825,000.00
III PEKERJAAN BETON
1 Pek. Beton Sloof 20/15
a. Pek. Beton K 250 0.25 M3. 1,250,087.58 313,146.94
b. Pek. Pembesian Polos 3,139.06 Kg 15,771.25 49,506,840.57
c. Pek. Bekisting 64.16 M2 165,902.00 10,644,272.32
2 Pek. Beton Kolom K1 15/15
a. Pek. Beton K 250 0.16 M3. 1,250,087.58 196,888.79
b. Pek. Pembesian Polos 3,005.71 Kg 15,771.25 47,403,732.43
c. Pek. Bekisting 161.70 M2 298,661.00 48,293,483.70
3 Pek. Beton Ringbalk RB1 15/15
a. Pek. Beton K 250 0.19 M3. 1,250,087.58 234,860.20
b. Pek. Pembesian Polos 40.64 Kg 15,771.25 640,943.60
c. Pek. Bekisting 6.60 M2 303,941.00 2,006,010.60
SUB TOTAL 159,240,179.16
IV PEKERJAAN PLESTERAN
1 Pas. Dinding bata 1 : 5 19.05 M2 124,855.72 2,378,501.47
1 Pek. Plesteran dinding tembok, 1 : 5 38.10 M2. 63,253.26 2,409,949.05
3 Pek. Plesteran Sloof & Pondasi 1 : 3 1.87 M2. 63,253.26 118,283.59
SUB TOTAL 2,409,949.05
VII PEKERJAAN LANTAI
1 Pas. Lantai Lantai Keramik 30 X 30 (Anti Slip) 13.70 M2 200,131.00 2,741,794.70
3 Pas. Dinding Keramik 20 x 20 cm 25.50 M2 301,442.90 7,686,793.95
SUB TOTAL 10,428,588.65
VIII PEKERJAAN SANITAIR
1 Pek. Pas. Kloset Duduk 2.00 Bh 1,370,792.50 2,741,585.00
4 Pek. Pas. Floor Drain Stainless 2.00 Bh 40,672.50 81,345.00
7 Pek. Pas. Keran Air 2.00 Bh 87,010.00 174,020.00
10 Pek. Pas. Pipa Air Bersih Ø 1/2 " 25.00 M1 27,028.65 675,716.25
11 Pek. Pas. Pipa Air Kotor Ø 2 " 15.00 M1 44,078.65 661,179.75
12 Pek. Pas. Pipa Air Kotor Ø 3 " 10.00 M1 89,474.00 894,740.00
SUB TOTAL 5,228,586.00
X PEKERJAAN INSTALASI LISTRIK
1 Pemasangan Kabel NYM 2 x 2.5 mm 15.00 M1 11,000.00 165,000.00
2 Pek. Pipa Instalasi Listrik 5/8" 15.00 M1 2,875.00 43,125.00
3 Pek. Instalasi Penerangan 4.00 Titik 175,000.00 700,000.00
8 Pek. Pas. Lampu ESS 14 Watt (KM/WC) 6.00 Bh 65,000.00 390,000.00
9 Pek. Pas. Saklar Ganda 1.00 Bh 23,000.00 23,000.00
SUB TOTAL 1,321,125.00
XI PEKERJAAN CAT DAN FINISHING
2 Pek. Cat tembok 39.97 M2. 18,968.95 758,188.93
SUB TOTAL 758,188.93
RENCANA ANGGARAN BIAYA
HARGA JUMLAH
NO. URAIAN DAN JENIS PEKERJAAN VOLUME SAT
SATUAN HARGA
1. 2 3. 4 5. 6.
V PEKERJAAN KUSEN PINTU & JENDELA
1 Pek. Kusen Pintu & Jendela Kayu Kelas I 0.07 M3 9,221,575.00 604,197.59
3 Pek. Bingkai Jendela Kayu Kelas II 0.47 M2 470,030.00 219,974.04
4 Pek. Kaca Bening 5 mm 1.80 M2 214,064.13 385,315.43
7 Pas. Grendel Jendela 6.00 Bh 31,465.50 188,793.00
SUB TOTAL 1,398,280.06
VII PEKERJAAN LANTAI
1 Pas. Lantai Lantai Keramik 30 X 30 13.70 M2 200,131.00 2,741,794.70
SUB TOTAL 2,741,794.70
X PEKERJAAN INSTALASI LISTRIK
1 Pemasangan Kabel NYM 2 x 2.5 mm 5.00 M1 11,000.00 55,000.00
2 Pek. Pipa Instalasi Listrik 5/8" 5.00 M1 2,875.00 14,375.00
3 Pek. Instalasi Penerangan 1.00 Titik 175,000.00 175,000.00
4 Pek. Instalasi Stop Kontak 1.00 Titik 175,000.00 175,000.00
8 Pek. Pas. Lampu ESS 14 Watt (KM/WC) 1.00 Bh 65,000.00 65,000.00
10 Pek. Pas. Saklar Tunggal 1.00 Bh 20,000.00 20,000.00
11 Pek. Pas. Stop Kontak 1.00 Bh 17,000.00 17,000.00
SUB TOTAL 521,375.00
DAFTAR ANALISA SATUAN PEKERJAAN
A. PEKERJAAN PERSIAPAN
1 Anl 1 M3 PEMBONGKARAN DINDING TEMBOK
No. Uraian Satuan Harga Kwantitas Jumlah
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 80,000.00 6.6670 533,360.00
2 Mandor Org/Hari 105,000.00 0.3330 34,965.00
Jumlah 568,325.00
B BAHAN
Jumlah
C Harga Satuan A + B 568,325.00
D Overhead & Provit(10%) 10% X C 56,832.50
E Harga Satuan C + D 625,157.50
7
Jumlah
C Harga Satuan A + B 62,625.00
D Overhead & Provit(10%) 10% X C 6,262.50
E Harga Satuan C + D 68,887.50
Jumlah
C Harga Satuan A + B 45,250.00
D Overhead & Provit(10%) 10% X C 4,525.00
E Harga Satuan C + D 49,775.00
8
4 Mandor Org/Hari 105,000.00 0.0750 7,875.00
Jumlah 207,750.00
B BAHAN
1 Batu Gunung Moramo M3 200,000.00 1.2000 240,000.00
2 Semen Portland Kg 1,460.00 136.0000 198,560.00
3 Pasir Pasang M3 200,000.00 0.5440 108,800.00
Jumlah 547,360.00
C Harga Satuan A + B 755,110.00
D Overhead & Provit(10%) 10% X C 75,511.00
E Harga Satuan C + D 830,621.00
9
3 Anl 1 M3 PEK. PASANGAN PONDASI BATU KOSONG
No. Uraian Satuan Harga Kwantitas Jumlah
Satuan Harga
A TENAGA KERJA
1 Tukang Batu Org/Hari 95,000.00 0.3900 37,050.00
2 Kepala Tukang Org/Hari 115,000.00 0.0390 4,485.00
3 Pekerja Org/Hari 80,000.00 0.7800 62,400.00
4 Mandor Org/Hari 105,000.00 0.0390 4,095.00
Jumlah 108,030.00
B BAHAN
1 Batu Gunung Moramo M3 200,000.00 1.2000 240,000.00
2 Pasir Urug M3 194,500.00 0.4320 84,024.00
Jumlah 324,024.00
C Harga Satuan A + B 432,054.00
D Overhead & Provit(10%) 10% X C 43,205.40
E Harga Satuan C + D 475,259.40
10
No. Uraian Satuan Harga Kwantitas Jumlah
Satuan Harga
A TENAGA KERJA
1 Tukang Batu Org/Hari 95,000.00 0.1500 14,250.00
2 Kepala Tukang Org/Hari 115,000.00 0.0150 1,725.00
3 Pekerja Org/Hari 80,000.00 0.3000 24,000.00
4 Mandor Org/Hari 105,000.00 0.0150 1,575.00
Jumlah 41,550.00
B BAHAN
1 Semen Kg 1,460.00 7.7760 11,352.96
2 Pasir Pasang M3 200,000.00 0.0230 4,600.00
Jumlah 15,952.96
C Harga Satuan A + B 57,502.96
D Overhead & Provit(10%) 10% X C 5,750.30
E Harga Satuan C + D 63,253.26
D. PEKERJAAN BETON
1 Anl 1 M3 MEMBUAT BETON LANTAI KERJA K 100
No. Uraian Kwantitas Jumlah
Harga
11
A TENAGA KERJA
1 Tukang Batu Org/Hari 95,000.00 0.2000 19,000.00
2 Kepala Tukang Org/Hari 115,000.00 0.0200 2,300.00
3 Pekerja Org/Hari 80,000.00 1.2000 96,000.00
4 Mandor Org/Hari 105,000.00 0.0600 6,300.00
Jumlah 123,600.00
B BAHAN
1 Semen Kg 1,460.00 230.0000 335,800.00
2 Pasir pasang M3 200,000.00 0.6379 127,571.43
3 Kerikil Beton M3 276,900.00 0.7607 210,649.11
4 Air Ltr 85.00 200.0000 17,000.00
Jumlah 674,020.54
C Harga Satuan A + B 797,620.54
D Overhead & Provit(10%) 10% X C 79,762.05
E Harga Satuan C + D 877,382.59
12
Satuan Harga
A TENAGA KERJA
1 Tukang kayu Org/Hari 95,000.00 0.2600 24,700.00
2 Kepala tukang Org/Hari 115,000.00 0.0260 2,990.00
3 Pekerja Org/Hari 80,000.00 0.5200 41,600.00
4 Mandor Org/Hari 105,000.00 0.0260 2,730.00
Jumlah 72,020.00
B BAHAN
1 Kayu papan bekisting M3 1,600,000.00 0.0450 72,000.00
2 Paku campur Kg 20,000.00 0.3000 6,000.00
3 Minyak bekisting Ltr 8,000.00 0.1000 800.00
Jumlah 78,800.00
C Harga Satuan A + B 150,820.00
D Overhead & Provit(10%) 10% X C 15,082.00
E Harga Satuan C + D 165,902.00
13
D Overhead & Provit(10%) 10% X C 27,631.00
E Harga Satuan C + D 303,941.00
E. PEKERJAAN BESI
1 Anl. 1 KG PEK. RANGKA BAJA WF
No. Uraian Satuan Harga Kwantitas Jumlah
Satuan Harga
A TENAGA KERJA
1 Tukang Besi Org/Hari 95,000.00 0.0600 5,700.00
2 Kepala Tukang Org/Hari 115,000.00 0.0060 690.00
3 Pekerja Org/Hari 80,000.00 0.0600 4,800.00
4 Mandor Org/Hari 105,000.00 0.0030 315.00
Jumlah 11,505.00
B BAHAN
1 Besi Baja WF Kg 17,000.00 1.1500 19,550.00
Jumlah 19,550.00
C Harga Satuan A + B 31,055.00
D Overhead & Provit(10%) 10% X C 3,105.50
E Harga Satuan C + D 34,160.50
14
Jumlah 5,786.00
C Harga Satuan A + B 5,967.40
D Overhead & Provit(10%) 10% X C 596.74
E Harga Satuan C + D 6,564.14
15
C Harga Satuan A + B 19,587.50
D Overhead & Provit(10%) 10% X C 1,958.75
E Harga Satuan C + D 21,546.25
17
A TENAGA KERJA
1 Tukang Kayu Org/Hari 95,000.00 0.1500 14,250.00
2 Kepala Tukang Org/Hari 115,000.00 0.0150 1,725.00
3 Pekerja Org/Hari 80,000.00 0.0150 1,200.00
4 Mandor Org/Hari 105,000.00 0.0008 84.00
Jumlah 17,259.00
B BAHAN
1 Engsel Pintu Bh 11,200.00 1.0000 11,200.00
Jumlah 11,200.00
C Harga Satuan A + B 28,459.00
D Overhead & Provit(10%) 10% X C 2,845.90
E Harga Satuan C + D 31,304.90
18
1 Kait Angin Bh 9,400.00 1.0000 9,400.00
Jumlah 9,400.00
C Harga Satuan A + B 27,415.00
D Overhead & Provit(10%) 10% X C 2,741.50
E Harga Satuan C + D 30,156.50
D. PEKERJAAN KAYU
1 1 M3 PAS. KUSEN KAYU KELAS I
No. Uraian Satuan Harga Kwantitas Jumlah
Satuan Harga
A TENAGA KERJA
1 Tukang Kayu Org/Hari 95,000.00 21.000 1,995,000.00
2 Kepala Tukang Org/Hari 115,000.00 2.100 241,500.00
3 Pekerja Org/Hari 80,000.00 7.000 560,000.00
4 Mandor Org/Hari 105,000.00 0.350 36,750.00
Jumlah 2,833,250.00
B BAHAN
1 Balok Kayu Kelas I M3 5,000,000.00 1.1000 5,500,000.00
2 Lem Kayu Kg 25,000.00 1.0000 25,000.00
3 Paku Kg 20,000.00 1.2500 25,000.00
Jumlah 5,550,000.00
C Harga Satuan A + B 8,383,250.00
D Overhead & Provit(10%) 10% X C 838,325.00
E Harga Satuan C + D 9,221,575.00
21
Jumlah 4,830,000.00
C Harga Satuan A + B 7,541,825.00
D Overhead & Provit(10%) 10% X C 754,182.50
E Harga Satuan C + D 8,296,007.50
22
C Harga Satuan A + B 75,025.00
D Overhead & Provit(10%) 10% X C 7,502.50
E Harga Satuan C + D 82,527.50
F. PEKERJAAN ATAP
1 Anl 1 M2. PAS. ATAP GENTENG ASPAL
No. Uraian Satuan Harga Kwantitas Jumlah
Satuan Harga
A TENAGA KERJA
1 Tukang Kayu Org/Hari 95,000.00 0.3000 28,500.00
2 Kepala Tukang Org/Hari 115,000.00 0.0030 345.00
3 Pekerja Org/Hari 80,000.00 0.2000 16,000.00
4 Mandor Org/Hari 105,000.00 0.0100 1,050.00
Jumlah 45,895.00
B BAHAN
1 Genteng Aspal Bh 30,000.00 6.9000 207,000.00
2 Multipleks 6 mm Lbr 119,100.00 0.3500 41,685.00
3 Paku Campur Kg 20,000.00 0.0300 600.00
4 Plastic Aerator Bh 30,000.00 0.5000 15,000.00
Jumlah 264,285.00
C Harga Satuan A + B 310,180.00
D Overhead & Provit(10%) 10% X C 31,018.00
E Harga Satuan C + D 341,198.00
F. PEKERJAAN PLAFOND
1 1 M2 PASANG RANGKA LANGIT-LANGIT, METAL HOLLOW 1 X 20.40.2 MM, MODUL 60 X 60 CM
No. Uraian Satuan Harga Kwantitas Jumlah
Satuan Harga
A TENAGA KERJA
1 Tukang Besi Org/Hari 95,000.00 0.3500 33,250.00
2 Kepala Tukang Org/Hari 115,000.00 0.0350 4,025.00
3 Pekerja Org/Hari 80,000.00 0.3500 28,000.00
4 Mandor Org/Hari 105,000.00 0.0175 1,837.50
Jumlah 67,112.50
B BAHAN
1 Rangka Metal Hollow 20.40.2 mm M1 20,000.00 4.0000 80,000.00
23
2 Assesories (Perkuatan, las dll) Ls 80,000.00 1.0000 80,000.00
Jumlah 160,000.00
C Harga Satuan A + B 227,112.50
D Overhead & Provit(10%) 10% X C 22,711.25
E Harga Satuan C + D 249,823.75
24
D Overhead & Provit(10%) 10% X C 3,291.00
E Harga Satuan C + D 36,201.00
25
D Overhead & Provit(10%) 10% X C 19,382.33
E Harga Satuan C + D 213,205.67
G. PEKERJAAN LANTAI
1 Anl 1M2 PAS. LANTAI GRANIT 60 x 60 Cm
No. Uraian Satuan Harga Kwantitas Jumlah
Satuan Harga
A TENAGA KERJA
1 Tukang Batu Org/Hari 95,000.00 0.1200 11,400.00
2 Kepala Tukang Org/Hari 115,000.00 0.0120 1,380.00
3 Pekerja Org/Hari 80,000.00 0.2400 19,200.00
4 Mandor Org/Hari 105,000.00 0.0120 1,260.00
Jumlah 33,240.00
B BAHAN
1 Lantai Granit 60 x 60 Cm Bh 86,666.67 3.1000 268,666.67
2 Semen warna Kg 24,000.00 1.5000 36,000.00
3 Semen portland Kg 1,460.00 9.6000 14,016.00
4 Pasir Pasang M3 200,000.00 0.0450 9,000.00
Jumlah 327,682.67
26
C Harga Satuan A + B 360,922.67
D Overhead & Provit(10%) 10% X C 36,092.27
E Harga Satuan C + D 397,014.93
27
3 Semen portland Kg 1,460.00 10.0000 14,600.00
4 Pasir Pasang M3 200,000.00 0.0450 9,000.00
Jumlah 145,927.27
C Harga Satuan A + B 181,937.27
D Overhead & Provit(10%) 10% X C 18,193.73
E Harga Satuan C + D 200,131.00
H. PEKERJAAN PENGECATAN
1 Anl 1 M2 PEK. CAT TEMBOK/PLAFOND (1 x PLAMIR, 1 X CAT DASAR, 2 X CAT PENUTUP)
No. Uraian Satuan Harga Kwantitas Jumlah
Satuan Harga
A TENAGA KERJA
1 Tukang Cat Org/Hari 95,000.00 0.0630 5,985.00
2 Kepala Tukang Org/Hari 115,000.00 0.0063 724.50
3 Pekerja Org/Hari 80,000.00 0.0200 1,600.00
4 Mandor Org/Hari 105,000.00 0.0030 315.00
Jumlah 8,624.50
B BAHAN
1 Plamir Kg 6,000.00 0.1000 600.00
2 Cat dasar Kg 10,000.00 0.1000 1,000.00
3 Cat tembok/penutup 2 X Kg 27,000.00 0.2600 7,020.00
Jumlah 8,620.00
C Harga Satuan A + B 17,244.50
D Overhead & Provit(10%) 10% X C 1,724.45
E Harga Satuan C + D 18,968.95
28
Jumlah 23,162.50
B BAHAN
1 Menie Besi Kg 13,000.00 0.1000 1,300.00
2 Kuas Bh 10,000.00 0.0100 100.00
Jumlah 1,400.00
C Harga Satuan A + B 24,562.50
D Overhead & Provit(10%) 10% X C 2,456.25
E Harga Satuan C + D 27,018.75
29
4 Mandor Hari/Org 105,000.00 0.003 262.50
Jumlah 30,102.50
B BAHAN
1 Vernis ltr 9,700.00 0.150 1,455.00
2 Dempul kg 16,300.00 0.050 815.00
3 Ampelas Lbr 4,500.00 0.160 720.00
4 Kuas bh 10,000.00 0.010 100.00
Jumlah 3,090.00
C Harga Satuan A + B 33,192.50
D Overhead & Provit(10%) 10% X C 3,319.25
E Harga Satuan C + D 36,511.75
30
Jumlah 35,555.00
B BAHAN
1 Staenlies steel 2 " M1 66,666.67 1.2000 80,000.00
2 Perlengkapan Ls 23,333.33 1.0000 23,333.33
Jumlah 103,333.33
C Harga Satuan A + B 138,888.33
D Overhead & Provit(10%) 10% X C 13,888.83
E Harga Satuan C + D 152,777.17
J. PEKERJAAN SANITAIR
1 Anl. MEMASANG 1 BH KLOSED DUDUK
No. Uraian Satuan Harga Kwantitas Jumlah
Satuan Harga
A TENAGA KERJA
1 Tukang Batu Org/Hari 95,000.00 1.1000 104,500.00
2 Kepala Tukang Org/Hari 115,000.00 0.0010 115.00
3 Pekerja Org/Hari 80,000.00 3.3000 264,000.00
4 Mandor Org/Hari 105,000.00 0.1600 16,800.00
Jumlah 385,415.00
B BAHAN
1 Klosed Duduk Bh 850,000.00 1.0000 850,000.00
2 Semen portland Kg 1,460.00 6.0000 8,760.00
3 Pasir pasang M3 200,000.00 0.0100 2,000.00
Jumlah 860,760.00
C Harga Satuan A + B 1,246,175.00
D Overhead & Provit(10%) 10% X C 124,617.50
E Harga Satuan C + D 1,370,792.50
31
B BAHAN
1 Klosed Duduk Bh - 1.0000 -
2 Semen portland Kg 1,460.00 6.0000 8,760.00
3 Pasir pasang M3 200,000.00 0.0100 2,000.00
Jumlah 10,760.00
C Harga Satuan A + B 267,310.00
D Overhead & Provit(10%) 10% X C 26,731.00
E Harga Satuan C + D 294,041.00
32
2 Kepala Tukang Org/Hari 115,000.00 0.0750 8,625.00
3 Pekerja Org/Hari 80,000.00 0.0750 6,000.00
4 Mandor Org/Hari 105,000.00 0.0030 315.00
Jumlah 86,190.00
B BAHAN
1 Shower Closet Bh 167,000.00 1.0000 167,000.00
2 Perlengkapan Ls 50,100.00 1.0000 50,100.00
Jumlah 217,100.00
C Harga Satuan A + B 303,290.00
D Overhead & Provit(10%) 10% X C 30,329.00
E Harga Satuan C + D 333,619.00
33
Jumlah 43,925.00
B BAHAN
1 Keran Air Bh 35,000.00 1.0000 35,000.00
2 Sealtape Bh 7,000.00 0.0250 175.00
Jumlah 35,175.00
C Harga Satuan A + B 79,100.00
D Overhead & Provit(10%) 10% X C 7,910.00
E Harga Satuan C + D 87,010.00
34
2 Perlengkapan Ls 210,000.00 1.0000 210,000.00
Jumlah 910,000.00
C Harga Satuan A + B 996,190.00
D Overhead & Provit(10%) 10% X C 99,619.00
E Harga Satuan C + D 1,095,809.00
F. PEKERJAAN PIPA
1 Anl MEMASANG 1 M1 PIPA PVC 1/2"
No. Uraian Satuan Harga Kwantitas Jumlah
Satuan Harga
A TENAGA KERJA
1 Tukang Batu Org/Hari 95,000.00 0.0600 5,700.00
2 Kepala Tukang Org/Hari 115,000.00 0.0060 690.00
3 Pekerja Org/Hari 80,000.00 0.0360 2,880.00
4 Mandor Org/Hari 105,000.00 0.0018 189.00
Jumlah 9,459.00
B BAHAN
1 Pipa PVC AW 1/2" M1 9,750.00 1.2000 11,700.00
2 Perlengkapan ls 3,412.50 1.0000 3,412.50
Jumlah 15,112.50
C Harga Satuan A + B 24,571.50
D Overhead & Provit(10%) 10% X C 2,457.15
E Harga Satuan C + D 27,028.65
35
2 Perlengkapan ls 6,912.50 1.0000 6,912.50
Jumlah 30,612.50
C Harga Satuan A + B 40,071.50
D Overhead & Provit(10%) 10% X C 4,007.15
E Harga Satuan C + D 44,078.65
36
DAFTAR HARGA BAHAN DAN UPAH KERJA
HARGA
NO. URAIAN JENIS TENAGA / BAHAN SATUAN
('Rp.)
1 2 3 4
I UPAH TENAGA KERJA :
1 Pekerja Hari 80,000.00
2 Mandor Hari 105,000.00
3 Tukang Batu Hari 95,000.00
4 Tukang Kayu Hari 95,000.00
5 Tukang Besi Hari 95,000.00
6 Tukang Cat Hari 95,000.00
7 Kepala Tukang Batu, Kayu, Besi, Cat Hari 115,000.00
II HARGA BAHAN
A. Bahan Tanah, Pasir dan Batu
1 Tanah Urugan (didatangkan) M3 115,000.00
2 Timbunan Pilihan M3 138,000.00
3 Pasir Urug M3 194,500.00
4 Pasir Pasangan M3 200,000.00
5 Pasir Beton M3 200,000.00
6 Kerikil Beton M3 276,900.00
7 Batu Pecah/Suplit 1/2 M3 375,000.00
8 Batu Gunung M3 200,000.00
9 Batu bata Bh 690.00
B. Bahan Semen
1 Portland Cemen ( PC ) Kg 1,460.00
2 Portland Cemen ( PC ) Zak 73,000.00
3 Semen Warna Kg 24,000.00
C. Bahan Kayu
1 Balok Kayu Kls I M3 5,000,000.00
2 Balok Kayu Kls II M3 4,200,000.00
3 Kaso 5/7 Kls II M3 4,200,000.00
4 Papan Kayu Kls I (Jati) M3 4,700,000.00
5 Papan Kayu Kls II M3 4,000,000.00
6 Kayu dolken diameter 8 - 10 cm btg 8,000.00
7 Papan Kayu Kelas III M3 3,500,000.00
8 Listplafond kayu profil M1 5,200.00
9 List kaca 1 x 1 cm M1 2,000.00
10 Tripleks 3 mm Lbr 67,900.00
11 Papan Bekisting M3 1,600,000.00
12 Balok Bekisting M3 1,600,000.00
13 Multipleks 4 mm Lbr 107,000.00
14 Multipleks 6 mm Lbr 119,100.00
15 Multipleks 9 mm Lbr 190,000.00
16 Gypsumboard 9 mm Lbr 80,000.00
17 Kalsiboard 4.5 mm Lbr 75,000.00
17 List Gypsum Profil M1 18,000.00
37
1 2 3 4
D. Bahan Lantai
1 Granit 60 x 60 Cm Bh 86,666.67
2 Granit 60 x 60 Cm (Anti Slip) Bh 93,333.33
3 Tegel Keramik 20 x 20 Cm Bh 5,500.00
4 Tegel Keramik 30 x 30 Cm (Anti Slip) Bh 7,272.73
5 Plin Granit 10 x 60 Cm Bh 4,705.88
I. Bahan Atap
1 Genteng Aspal Bh 30,000.00
2 Bumbungan Genteng Aspal Bh 35,000.00
3 Plastic Aerator Bh 30,000.00
E. Bahan Besi
1 Besi Beton Polos Kg 12,000.00
2 Besi Beton Ulir Kg 17,000.00
3 Jaring Kawat Baja(Wire Mesh) Kg 17,000.00
4 Besi Baja WF Kg 17,000.00
5 Kawat Bindrat Kg 26,000.00
6 Paku Campur Kg 20,000.00
7 Paku tripleks Kg 26,100.00
8 Paku Seng Kg 28,200.00
9 Paku Sakura Roof Kg 26,100.00
10 Paku sekrup Kg 26,100.00
11 Angker/Baut/plat pengikat kuda-kuda Kg 10,000.00
12 Seng Gelombang Lbr 70,000.00
13 Seng Plat Lbr 65,000.00
14 Baut Ø 11 Bh 22,300.00
15 Baut Angkur Ø 16 Bh 34,000.00
16 Skrup Fixer Bh 1,800.00
F. Bahan Pengunci/Penggantung
1 Kunci Tanam 2 x putar Bh 150,000.00
2 Handle Pintu Kaca Bh 80,000.00
3 Engsel Pintu Type H Bh 18,800.00
4 Engsel Pintu Type Kupu Kupu Bh 11,200.00
5 Engsel Jendela Type Kupu Kupu Bh 5,000.00
6 Grendel Jendela Bh 5,600.00
7 Kait-kait Angin Bh 9,400.00
38
G. Bahan Cat/Finishing
1 Cat Meny Seng/Besi Kg 18,000.00
2 Meny kayu Kg 19,500.00
3 Minyak cat Ltr 3,400.00
4 Minyak bekisting Ltr 8,000.00
5 Kuas Bh 10,000.00
6 Cat Dasar Kg 19,500.00
7 Cat Kilap Kayu Kg 45,700.00
8 Cat Vernis Kayu Kg 9,700.00
9 Amplas Kayu Lbr 4,500.00
10 Dempul Kayu Kg 16,300.00
11 Cat Kilap Besi Kg 13,000.00
12 Cat Tembok Kg 27,000.00
13 Cat No Drop atau sejenis Kg 47,000.00
14 Lem Kayu Merk Fox Kg 25,000.00
15 Lem HPL Kg 50,000.00
16 Lem Wallpaper Kg 45,000.00
17 Kapur Tonasa Kg 6,000.00
18 Plamir Tembok Kg 8,800.00
19 Sealant Aluminium Composite Panel Hitam Tube 40,000.00
20 Sealant Kaca Tube 27,000.00
21 Profil Kaca M1 5,000.00
22 HPL (High Pressur Laminate) Lbr 260,000.00
23 Wallpaper M1 31,818.18
H. Bahan Kaca
1 Kaca Bening 8 mm M2 253,000.00
2 Kaca Bening 5 mm M2 160,000.00
39
J. Bahan Listrik
1 Saklar Ganda Bh 23,000.00
2 Saklar Tunggal Bh 20,000.00
3 Stop Kontak Bh 17,000.00
4 Lampu TL. 2 x 20 Watt + Cover Bh 350,000.00
5 Downlight Lampu Bh 64,000.00
6 Lampu ESS 14 Watt (Km/Wc) Bh 65,000.00
7 Lampu PLC
Lampu 36 Watt HIAS
TLD(1X18W) Bh 65,000.00
8 Bh 35,000.00
9 Exhause Fan 6" Bh 179,000.00
10 Inst. Penerangan NYM 2 x 2,5 mm2 clipsall 3/4 coud Titik 175,000.00
11 Inst. Stop Kontak NYM 2 x 2,5 mm2 clipsall 3/4 coud Titik 175,000.00
12 MCB Bh 50,000.00
13 Kabel NYM 2 x 2.5 mm M1 11,000.00
14 Pek. Pipa Instalasi Listrik 5/8" M1 2,875.00
K. Bahan Sanitair
1 Pipa PVC dia 3/4 Inci M1 9,750.00
2 Pipa PVC dia 1 Inci M1 12,250.00
3 Pipa PVC dia 1½ Inci M1 14,750.00
4 Pipa PVC dia 2 Inci M1 19,750.00
5 Pipa PVC dia 3 Inci (RR z-join) M1 38,750.00
6 Pipa PVC dia 4 Inci (RR z-join) M1 64,000.00
7 Pipa PVC dia 6 Inci (RR z-join) M1 149,000.00
8 Kloset Duduk Toto Buah 850,000.00
9 Wastafel Buah 360,000.00
10 Kran Air Buah 35,000.00
11 Sealtape Bh 7,000.00
12 Floor Drain Buah 25,000.00
13 Rak Handuk Bh 150,000.00
14 Shower Kloset Bh 167,000.00
15 Shower Mandi Bh 169,000.00
L. Bahan Lainnya
1 Pompa Air Ps-130 Unit 700,000.00
2 Tandon Air 1200 Liter Bh 1,500,000.00
3 Sewa Alat Las Jam 100,000.00
4 Sewa Alat Perakit Baja Jam 700,000.00
5 Solar Liter 15,000.00
6 Minyak Pelumas Liter 36,000.00
7 Air Liter 85.00
40
'Pek. Pembongkaran Dinding Tembok
TEMBOK
V = P x L x T x BH
V = 4.4 x 3.5 x 0.13 x 6
V = 12.012 M3
BUKAAN JENDELA
V = P x L x T x BH
V = 2.5 x 1.5 x 0.12 x 6
V = 2.7 M3
V = 9.312 M3
BATU GUNUNG
V = P x L x T
V = 11 x 0.25 x 0.2
V = 0.55 M3
V TOTAL = 23.05 M3
BATU GUNUNG
V = 1/3 x GALIAN
V = 0.33333333 x 0.55
V = 0.18333333 M3
V TOTAL = 16.6833333 M3
BUKAAN
V = P x T x BH
V = 0.6 x 2.1 x 22
V = 27.72 M2
V TOTAL = 146.16 M2
PIRAMIDA UTUH
V = (1/3) x P x L x T x BH
V = 0.33333333 x 1 x 1 x 0.17 x 9
V = 0.51 M3
PIRAMIDA PENGURANGAN
V = (1/3) x P x L x T x BH
V = 0.33333333 x 0.3 x 0.3 x 0.07 x 9
V = 0.0189 M3
HASIL PENGURANGAN
V = 0.4911 M3
V = KUBUS + PIRAMIDA
V = 2.25 + 0.491
V = 2.7411 M3
LUAS KESELURUHAN
V = LUAS x BH
V = 1.2 x 9
V = 10.8 M2
Pek. Beton Poor Plat 55 x 100 Cm K 250
SETENGAH
KUBUS
V = P x L x T x BH
V = 1 x 0.55 x 0.25 x 6
V = 0.825 M3
PIRAMIDA UTUH
V = (1/3) x P x L x T x BH
V = 0.33333333 x 0.55 x 1 x 0.17 x 6
V = 0.187 M3
PIRAMIDA PENGURANGAN
V = (1/3) x P x L x T x BH
V = 0.33333333 x 0.3 x 0.3 x 0.07 x 6
V = 0.0126 M3
HASIL PENGURANGAN
V = 0.1744 M3
V = KUBUS + PIRAMIDA
V = 0.825 + 0.174
V = 0.9994 M3
LUAS KESELURUHAN
V = LUAS x BH
V = 0.93 x 6
V = 5.58 M2
TENGAH
SISI ATAS FLOOR DEK SISI BAWAH FLOOR DEK
V = P x L x T V = P x L x T
V = 7.1 x 9.9 x 0.07 V = 7.1 x 9.9 x 0.07
V = 4.9203 V = 4.9203
V = 4.9203 : 2
V = 2.46015
V = ATAS + BAWAH
V = 4.9203 + 2.46
V = 7.38045 M3
KANAN
SISI ATAS FLOOR DEK SISI BAWAH FLOOR DEK
V = P x L x T V = P x L x T
V = 6.6 x 11.35 x 0.07 V = 6.6 x 11.35 x 0.07
V = 5.2437 V = 5.2437
V = 5.2437 : 2
V = 2.62185
V = ATAS + BAWAH
V = 5.2437 + 2.622
V = 7.86555 M3
LANTAI
INDUK
SISI ATAS FLOOR DEK SISI BAWAH FLOOR DEK
V = P x L x T V = P x L x T
V = 25.1 x 6.1 x 0.07 V = 25.1 x 6.1 x 0.07
V = 10.7177 V = 10.7177
V = 10.7177 : 2
V = 5.35885
V = ATAS + BAWAH
V = 10.7177 + 5.359
V = 16.07655 M3
TAMBAHAN TERAS
SISI ATAS FLOOR DEK SISI BAWAH FLOOR DEK
V = P x L x T V = P x L x T
V = 10.1 x 0.5 x 0.07 V = 10.1 x 0.5 x 0.07
V = 0.3535 V = 0.3535
V = 0.3535 : 2
V = 0.17675
V = ATAS + BAWAH
V = 0.3535 + 0.177
V = 0.53025 M3
V TOTAL = 36.0801 M3
Pek. Pembesian 20 x 20 Cm
PANJANG TULANGAN POKOK KILOGRAM BESI TULANGAN POKOK
V = P x JMLH BESI V = Ø x Ø x P x MASSA JENIS
V = 3 x 4 V = 12 x 12 x 12 x 0.006165
V = 12 M1 V = 10.65312 KG
SISI TENGAH
V = P x L x T x BH
V = 0.2 x 0.2 x 4.2 x 2
V = 0.336 M3
V TOTAL = 3.344 M3
V TOTAL = 66.88 M2
Pek. Plesteran Pondasi Batu gunung 1 : 3 Pek. Rangka kolom Struktur Baja WF 148.100.6.9
V = P x L TIANG PADA POOR PLAT
V = 11 x 0.8 V = T x BH
V = 8.8 M2 V = 4.9 x 9
V = 44.1 M1
Pek. Plesteran Dak Beton Top Floor 1 : 3 TIANG TIDAK PADA POOR PLAT
KIRI V = T x BH
V = P x L V = 4.7 x 4
V = 6.6 x 6.1 V = 18.8 M1
V = 40.26 M2
TIANG TENGAH
TENGAH V = T x BH + LEBIH
V = P x L V = 4.35 x 2 + 0.25
V = 7.1 x 9.9 V = 8.95 M1
V = 70.29 M2
P TOTAL = 71.85
KANAN
V = P x L V = P x MASSA
V = 6.6 x 11.35 V = 71.85 x 21.1
V = 74.91 M2 TOTAL WF = 1516.035 KG
V TOTAL = 185.46 M2
Pek. Rangka Struktur Kolom Baja WF 100.100.6.8 Pek. Rangka Struktur Balok Baja WF 200.100.5,5.8
TIANG PADA POOR PLAT BALOK ATAP SAYAP VERTIKAL
V = T x BH V = P x BH
V = 4.9 x 2 V = 6.4 x 3
V = 9.8 M1 V = 19.2 M1
V = P x MASSA V = P x MASSA
V = 14.5 x 17.17 V = 33.9 x 21.3333
TOTAL WF = 248.916667 KG TOTAL WF = 723.2 KG
Pek. Rangka atap Struktur Baja WF 350.175.7.11 Pek. Rangka lantai Struktur Baja WF 250.125.6.9
BALOK ATAP SAYAP VERTIKAL BALOK LANTAI SAYAP VERTIKAL
V = P x BH V = P x BH
V = 6.4 x 5 V = 5.9 x 4
V = 32 M1 V = 23.6 M1
P TOTAL = 135.6 M1
P TOTAL = 123.7 M1
V = P x MASSA
V = 135.6 x 49.6 V = P x MASSA
TOTAL WF = 6725.76 KG V = 123.7 x 29.6
TOTAL WF = 3661.52 KG
Pek. Rangka lantai Struktur WF 250.125.6.9 lanjutan BAUT lanjutan
BALOK LANTAI SAYAP VERTIKAL BAUT Ø 11 PLAT SIMPUL 25x30
V = P x BH V = BH x TITIK
V = 5.9 x 2 V = 6 x 10
V = 11.8 M1 V = 60 BH
TOTAL = 150 BH
P TOTAL = 26.5 M1
V = P x MASSA
V = 26.5 x 29.6
TOTAL WF = 784.4 KG
V = ∆ - ∆ x BH
V = 0.03 - 3E-05 x 18
V = 0.539424 M2
PLAT 125X250
V = P x L x BH
V = 0.25 x 0.125 x 10
V = 0.3125 M2
PLAT 100X200
V = P x L x BH
V = 0.2 x 0.1 x 21
V = 0.42 M2
KEBUTUHAN PLAT SIMPUL = 1.801 M2
LUAS PER 1 M2
V = 1 : 2.972
V = 0.33648259 LEMBAR
BERAT PER 1 M2
V = 233 x 0.336
V = 78.4004425 KG
PLAT 175X350
V = P x BH PLAT 125X250
V = 1.05 x 49 V = P x L x BH
V = 51.45 M1 V = 0.25 x 0.125 x 38
V = 5145 CM V = 1.1875 M2
V TOTAL = 57.792 M2
HALL BUKAAN
V = P x L V = T x L x BH
V = 9.9 x 7.2 V = 2.1 x 1.85 x 2
V = 71.28 V = 7.77 M2
TULANGAN PENDEK
HORISONTAL ATAS VERTIKAL ATAS
V = P x BH V = P x BH
V = 13.6 x 21 V = 3.2 x 84
V = 285.554667 M1 V = 268.8 M1
TAMBAHAN TERAS
TULANGAN LURUS TULANGAN PENDEK
HORISONTAL ATAS VERTIKAL ATAS
V = P x BH V = P x BH
V = 10.1 x 3 V = 0.6 x 34
V = 30.3033667 M1 V = 20.4 M1
TULANGAN LURUS
VERTIKAL ATAS
V = P x BH
V = 0.55 x 34
V = 18.7 M1
V TOTAL = 185.46 M2
Baja WF 250.125.6.9
V = P x L
V = 26.5 x 1.235
V = 32.7275 M2
Baja WF 200.100.5,5.8
V = P x L
V = 33.9 x 0.987
V = 33.44235 M2
V TOTAL = 74.66685 M2