PEMBANGUNAN RUKO
TYPE 108/78
HARGA
JUMLAH HARGA
NO. VOLUME SATUAN SATUAN
URAIAN PEKERJAAN
( Rp ) ( Rp )
1 1 2 3,00 4
A. PEKERJAAN PERSIAPAN
1 Bouwplang 54,00 M1 15.000,00 810.000,00
2 Galian Pondasi 23,87 M3 39.875,00 951.736,50
3 Pondasi Batu Kali 17,77 M3 502.000,00 8.919.736,80
Jumlah Sub Total - A. 10.681.473,30
B. PEKERJAAN BETON
1 Pek. Sloof
a. Cor Beton 2,45 M3 625.000,00 1.530.000,00
b. Pembesian 278,75 Kg 11.000,00 3.066.201,60
c. Bekisting 16,32 M2 55.200,00 900.864,00
2 Pek. Kolom
a. Cor Beton 1,00 M3 625.000,00 624.750,00
b. Pembesian 333,64 Kg 11.000,00 3.670.062,00
c. Bekisting 29,99 M2 55.200,00 1.655.337,60
3 Pek. Ring Balok
a. Cor Beton 2,63 M3 625.000,00 1.644.750,00
b. Pembesian 303,49 Kg 11.000,00 3.338.398,80
c. Bekisting 16,32 M2 55.200,00 900.864,00
4 Pek. Kolom
a. Cor Beton 0,12 M3 625.000,00 76.500,00
b. Pembesian 83,91 Kg 11.000,00 922.957,20
c. Bekisting 3,67 M2 55.200,00 202.694,40
Jumlah Sub Total - B. 18.533.379,60
C. PEKERJAAN DINDING
1 Pasang Bata Hebel Bangunan 226,44 M2 72.000,00 16.303.680,00
2 Pasang Bata Hebel Ampight 36,72 M2 72.000,00 2.643.840,00
3 Plester dan Acian Halus 489,60 M2 21.000,00 10.281.600,00
Jumlah Sub Total - C. 29.229.120,00
E. PEKERJAAN PLAFOND
1 73,44 M3dan Konsol
Pekerjaan Rangka Plafond Besi Hollow Ruangan 48.700,00 3.576.528,00
2 73,44 M2
Pasang Plafong Gypsum Ruangan dan Konsol 42.775,00 3.141.396,00
3 List Profil Plafond 126,48 M1 14.500,00 1.833.960,00
Jumlah Sub Total - E. 8.551.884,00
F. PEKERJAAN LANTAI
1 Pasang Keramik Lantai 97,20 M2 73.000,00 7.095.600,00
2 Pasang Keramik Lantai Kamar Mandi 5,51 M2 121.485,00 669.139,38
Jumlah Sub Total - F. 7.764.739,38
G PEKERJAAN LANTAI II
1 Wiremesh 150 Batang 84.000,00 12.600.000,00
2 Cor Beton 11 M3 1.400.000,00 15.400.000,00
3 Spandek 14 Lembar 600.000,00 8.400.000,00
4 Dolken 2 M3 3.000.000,00 6.000.000,00
5 Pasang Keramik Lantai 54 M2 75.000,00 4.050.000,00
Jumlah Sub Total - G 46.450.000,00
H PEKERJAAN TANGGA
1 BESI 14 MM 14 200.000,00 2.800.000,00
2 PAPAN &DOLKEN 0,5 M3 3.000.000,00 1.500.000,00
3 COR BETON 3,6 M3 1.400.000,00 5.040.000,00
HARGA
JUMLAH HARGA
NO. VOLUME SATUAN SATUAN
URAIAN PEKERJAAN
( Rp ) ( Rp )
1 1 2 3,00 4
4 KERAMIK TANGGA 30 M2 75.000,00 2.250.000,00
5 RAILINK TANGGA 12 M2 750.000,00 9.000.000,00
Jumlah Sub Total - H 20.590.000,00
I PEKERJAAN PENGECATAN
1 Cat Dinding 272,00 M2 13.000,00 3.536.000,00
2 Cat Plafond 40,80 M2 15.340,00 625.872,00
3 Cat Listplang 7,93 M2 15.340,00 121.697,33
Jumlah Sub Total - I. 4.283.569,33
J PEKERJAAN ACCESSOIES
1 Pasang Kran 3,00 Bh 35.000,00 105.000,00
2 Pasang Kloset duduk 1,00 Bh 350.000,00 350.000,00
3 Pasang Shower 1,00 Bh 342.000,00 342.000,00
4 Pasang Floordrain 1,00 Bh 36.000,00 36.000,00
Jumlah Sub Total - J. 833.000,00
N PEKERJAAN DAPUR
Pasang Meja Dapur 1,00 Set 80.000,00 80.000,00
Pasang Keramik Dinding Dapur 2,00 M2 95.000,00 190.000,00
Jumlah Sub Total - N. 270.000,00
Jumlah Total 193.044.280,61