PEKERJAAN : Penyusunan Rencana Tapak (Site Plan) dan Detail Engineering Design (DED)
Peremajaan/Pemugaran Permukiman Kumuh dengan Luas 10 (Sepuluh) Ha sampai dengan di
Bawah 15 (Lima Belas) Ha di Kab. Manggarai Timur
LOKASI : Kawasan Peot, RT.08 RW.03, Kel. Satar Peot, Kec. Borong
PROVINSI : NUSA TENGGARA TIMUR
TAHUN ANGGARAN : 2023
INDIKATOR : PENGOLAHAN AIR LIMBAH (SANITASI)
II PEKERJAAN RESAPAN
A. PEKERJAAN TANAH DAN PASANGAN
1 Galian Tanah M3 1.50 85,250.00 127,875.00
2 Urugan Pasir M3 0.07 311,270.00 22,411.44
3 Pasangan Batako kosong M2 5.40 85,673.00 462,634.20
4 Urugan Batu Pecah 5/7 M3 0.19 311,270.00 59,763.84
SUB TOTAL II A 672,684.48
B. PEKERJAAN BETON
1 a Plat Beton Penutup M3 0.10 1,128,298.00 112,829.80
b Besi Ǿ 10 Kg 4.32 20,023.00 86,432.62
c Besi Ǿ 6 Kg 1.55 20,023.00 31,115.74
SUB TOTAL II B 230,378.16
TOTAL II 903,062.64
HARGA SATUAN TOTAL
No. URAIAN PEKERJAAN SAT. VOL.
(Rp) (BAHAN+UPAH)
III PEKERJAAN PIPA DAN ACCESORIS
C PEKERJAAN PEMASANGAN PIPA PVC
1 a Pipa PVC AW Ø 4" M1 4.00 244,238.00 976,952.00
b Tee Ø 4" Bh 3.00 38,000.00 114,000.00
c Elbow Ø 4" Bh 2.00 32,000.00 64,000.00
2 a Pipa PVC D Ø 3" M1 4.00 172,958.00 691,832.00
b Elbow Ø 3" Bh 2.00 25,000.00 50,000.00
3 Pemasangan Floor Drain dim3" bh 1.00 40,397.00 40,397.00
4 Pemasangan Closed jongkok Bh 1.00 795,533.00 795,533.00
5 Pipa Hawa Septik T. 2 m D 2ˮ Ls 2.00 133,166.67 266,333.34
SUB TOTAL III.C 2,999,047.34
TOTAL III 2,999,047.34
IV BANGUNAN WC
A PEKERJAAN GALIAN TANAH DAN URUGAN
1 Galian Pondasi M3 0.93 85,250.00 79,112.00
2 Urugan Tanah kembali M3 0.19 60,500.00 11,228.80
3 Urugan Pasir bawah Pondasi M3 0.12 311,270.00 36,107.32
4 Urugan Pasir lantai M3 0.08 311,270.00 26,146.68
5 Urugan Tanah Peninggi Lantai M3 0.23 60,500.00 14,084.40
SUB TOTAL IV.A 166,679.20
B PEKERJAAN BETON
1 a Kolom Beton Bertulang Uk. 15/15 M3 0.21 1,128,298.00 239,650.50
b Besi Ǿ 10 Kg 24.27 20,023.00 485,998.26
c Besi Ǿ 6 Kg 5.41 20,023.00 108,371.68
d Begisting Kolom M2 5.66 193,674.00 1,096,969.54
2 a Sloof 15/15 M3 0.12 1,128,298.00 132,010.87
b Besi Ǿ 10 Kg 16.38 20,023.00 327,950.04
c Besi Ǿ 6 Kg 3.06 20,023.00 61,253.56
3 a Ring Balk beton bertulang uk 15/15 M3 0.12 1,128,298.00 132,518.60
b Besi Ǿ 10 Kg 16.43 20,023.00 328,937.84
c Besi Ǿ 6 Kg 3.06 20,023.00 61,253.56
SUB TOTAL IV.B 2,974,914.45