RENCANA ANGGARAN BIAYA

(RAB)

PEKERJAAN : PEMBANGUNAN LABORATORIUM KOMPUTER SMP 22 HALUT


LOKASI : DESA ……………….. KEC. KAO BARAT KAB. HALMAHERA UTARA
T.A : 2023

HARGA JUMLAH
NO URAIAN PEKERJAAN VOL SAT SATUAN HARGA
(Rp) (Rp)
1 2 3 4 5 6
I PEKERJAAN PERSIAPAN / PENDAHULUAN
1 Pembersihan Lokasi/ Akhir 1.00 Ls 2,000,000.00 2,000,000.00
2 Papan Nama Proyek 1.00 Ls 500,000.00 500,000.00
3 Pemasangan Bowplank 1.00 Ls 1,500,000.00 1,500,000.00
4 Dokumentasi dan pelaporan 1.00 Ls 3,227,000.00 3,227,000.00
5 K3 1.00 Ls 1,000,000.00 1,000,000.00
Jumlah I 8,227,000.00
II PEKERJAAN PONDASI
1 Galian Tanah Pondasi 35.84 M3 68,550.00 2,456,832.00
2 Urugan Tanah Kembali Pondasi 8.96 M3 49,100.00 439,936.00
3 Urugan Pasir di bawah Pondasi 2.56 M3 514,500.00 1,317,120.00
4 Urugan Tanah di bawah Lantai 36.00 M3 49,100.00 1,767,600.00
5 Urugan Pasir di bawah Lantai 6.00 M3 514,500.00 3,087,000.00
6 Anstramping/Batu Kosong 7.68 M3 904,225.80 6,944,454.14
7 Pondasi Batu Belah Camp. 1 PC : 4 PS 18.24 M3 1,438,823.00 26,244,131.52
Jumlah II 42,257,073.66
III PEKERJAAN STRUKTUR
I. PEKERJAAN STRUKTUR LT.1
1 Pek. Sloof 15/20 (S1)
- Bekisting Sloof Beton 2 x pakai 25.20 M2 230,398.00 5,806,029.60
- Tulangan Besi Ø 10 mm 155.60 Kg 22,637.26 3,522,461.32
- Tulangan Besi Ø 6 mm 55.93 Kg 22,637.26 1,266,076.43
- Beton 1.92 M3 2,091,264.00 4,015,226.88
2 Pek. Kolom 15/15 (K1)
- Bekisting Kolom Beton 2 x pakai 42.18 M2 405,059.00 17,085,388.62
- Tulangan Besi Ø 10 mm 197.42 Kg 22,637.26 4,468,956.72
- Tulangan Besi Ø 6 mm 57.00 Kg 22,637.26 1,290,412.68
- Beton 1.58 M3 2,091,264.00 3,307,856.83
3 Pek. Reng Beton 15/20 (RB)
- Bekisting Balok Beton 2 x pakai 25.60 M2 416,309.00 10,657,510.40
- Tulangan Besi Ø 10 mm 155.60 Kg 22,637.26 3,522,461.32
- Tulangan Besi Ø 6 mm 55.93 Kg 22,637.26 1,266,076.43
- Beton 1.92 M3 2,091,264.00 4,015,226.88
Jumlah III 60,223,684.10
IV PEKERJAAN ARSITEKTURAL
I PEKERJAAN PASANGAN DAN PLESTERAN
1 Pek. Pasangan Dinding Batu Bata Press Camp. 1 : 4 162.87 M2 182,318.70 29,693,335.08
2 Pek. Plesteran Dinding Camp. 1 : 4 308.13 M2 85,002.60 26,191,851.14
3 Pek. Acian Dinding 308.13 M2 48,217.50 14,857,258.28
Sub Total I 70,742,444.49
II PEKERJAAN PENUTUP ATAP
1 Pek. Kuda-Kuda Kayu kls I 1.03 M3 9,665,600.00 9,993,457.15
2 Pek. Gording Atap kayu Kls II 1.92 M3 6,051,360.00 11,606,121.19
3 Pek. Penutup Atap Seng Gelombang BJLS 0.25 189.42 M2 140,960.00 26,700,643.20
4 Pek. Balok Bubungan kayu kls II 0.10 M3 7,976,360.00 804,017.09
5 Pek. Seng Plat 0.20 14.00 m 98,125.00 1,373,750.00
6 Pek.Lisplang Kayu Kls II 13.21 M1 97,530.00 1,288,800.43
Sub Total II 51,766,789.06
III PEKERJAAN LANGIT-LANGIT/PLAFOND
1 Rangka Plafond Kayu Kls II 160.41 M2 153,825.00 24,675,068.25
2 Penutup Plafond Tripleks 5 mm 160.41 M2 88,005.00 14,116,882.05
3 List Plafond SK5 59.00 M1 27,261.00 1,608,399.00
Sub Total III 40,400,349.30
IV PEKERJAAN LANTAI DAN KERAMIK
1 Pek. Rabat Beton Tbl. 5 cm 4.80 M3 1,880,803.93 9,027,858.86
2 Pek. Pasangan Keramik Lantai Uk. 40/40 cm 96.00 M2 317,350.50 30,465,648.00
Sub Total IV 39,493,506.86
V PEKERJAAN PINTU DAN VENTILASI
1 Pintu P1 (daun panel) 2 Unit
Kusen Pintu 0.09 M3 11,532,050.00 1,087,702.96
Daun Pintu 4.47 M2 1,104,900.00 4,942,438.68
Jalusi Ventilasi Pintu 0.67 M2 1,036,900.00 698,041.08
Kunci Pintu Biasa 2.00 Set 423,660.00 847,320.00
Engsel Pintu 9.00 Bh 116,755.00 1,050,795.00
2 Jendela Ventilasi (JV1)
Kusen Jendela 0.51 M3 11,532,050.00 5,908,468.88
Bingkai Jenela 4.74 M2 764,420.00 3,624,598.33
Jalusi Ventilasi Jendela 4.91 M2 1,036,900.00 5,091,593.76
Engsel Jendela 36.00 Bh 71,610.00 2,577,960.00
Tarikan Jendela 18.00 Bh 20,000.00 360,000.00
Kait Angin Jendela 36.00 Bh 42,610.00 1,533,960.00
Grendel Jendela 18.00 Bh 54,610.00 982,980.00
Kaca Jendela 5 mm 4.68 M2 417,072.00 1,951,896.96
3 VENTILASI
Kusen Ventilasi 0.05 M3 11,532,050.00 528,075.63
Ventilasi Jalusi 1.01 M2 1,036,900.00 1,043,639.85
Sub Total V 32,229,471.13
VI PEKERJAAN PENGECATAN
1 Pengecatan Dinding 308.13 M2 53,022.00 16,337,668.86
2 Pengecatan Plafond 160.41 M2 34,180.00 5,482,813.80
3 Pengecatan Kusen Pint, Jendela dan Ventilasi 19.03 M2 48,774.00 928,178.97
4 Pengecata Daun Pintu 8.95 M2 48,774.00 436,351.71
5 Pengecatan Bingkai Jendela 9.48 M2 48,774.00 462,536.72
6 Pengecatan Jalusi Ventilasi Pintu 1.35 M2 48,774.00 65,669.31
7 Pengecatan Jalusi Ventilasi Jendela 9.82 M2 48,774.00 478,999.70
8 Pencatan Jalusi Ventilasi 2.01 M2 48,774.00 98,182.06
9 Pengecatan Listplank 45.46 M2 48,774.00 2,217,305.06
Sub Total VI 26,507,706.20
VII PEKERJAAN ELEKRIKAL
1 Pek. Titik Nyala Instalasi Lampu 7.00 Titik 150,000.00 1,050,000.00
2 Pek. Pipa Instalasi Listrik 16.00 Titik 22,266.00 356,256.00
3 MCB 4 Ampere 2.00 Bh 75,000.00 150,000.00
4 Kabel NYM 3 x 2,5 mm di dalam Pipa Conduit 20 mm 138.00 M1 17,000.00 2,346,000.00
5 Kabel NYM 2 x 1,5 mm 138.00 M1 13,000.00 1,794,000.00
6 Lampu Jari-Jari 18 Watt Lengkap dengan Viting Tempel 7.00 Bh 196,240.00 1,373,680.00
7 Stop Kontak 8.00 Bh 41,000.00 328,000.00
8 Pek. Pemasangan Saklar Ganda 6.00 Bh 138,240.00 829,440.00
Jumlah VI 8,227,376.00
PEKERJAAN MEBELER Bh
1 Kursi Guru 1.00 Bh 504,500.00 504,500.00
2 Meja guru 1.00 Bh 996,965.00 996,965.00
3 kursi siswa 15.00 Bh 538,250.00 8,073,750.00
4 Komputer 15.00 Bh 550,000.00 8,250,000.00
5 Papan Tulis WhiteBoard 0.00 Bh 970,000.00 0.00
Jumlah VI 17,825,215.00
REKAPITULASI
PEKERJAAN : PEMBANGUNAN LABORATORIUM KOMPUTER SMP 22 HALUT
LOKASI : DESA ……………….. KEC. KAO BARAT KAB. HALMAHERA UTARA
T.A : 2023

NO JENIS PEKERJAAN TOTAL HARGA

I PEKERJAAN PERSIAPAN / PENDAHULUAN 8,227,000.00


II PEKERJAAN PONDASI 42,257,073.66
III PEKERJAAN STRUKTUR
I PEKERJAAN STRUKTUR LT 1 60,223,684.10
IV PEKERJAAN ARSITEKTURAL
I PEKERJAAN PASANGAN DAN PLESTERAN 70,742,444.49
II PEKERJAAN PENUTUP ATAP 51,766,789.06
III PEKERJAAN LANGIT-LANGIT/PLAFOND 40,400,349.30
IV PEKERJAAN LANTAI DAN KERAMIK 39,493,506.86
V PEKERJAAN PINTU DAN VENTILASI 32,229,471.13
VI PEKERJAAN PENGECATAN 26,507,706.20
VII PEKERJAAN ELEKRIKAL 8,227,376.00
PEKERJAAN MEBELER 17,825,215.00

I JUMLAH 397,900,615.81
DIBULATKAN 397,900,000.00
TERBILANG : TIGA RATUS TIGA JUTA SERATUS DELAPAN PULUH LIMA RIBU RUPIAH

Mengetahui : Menyetujui :
Kepala Dinas Pendidikan dan Kebudayaan TIMTEKNIS
KABUPATEN HALMAHERA UTARA DISNAS PENDIDIKAN DAN KEBUDAYAAN

HERTJE MANUEL,S.Pd.,MM FERDINAN MANGAIR AMD.TEK


Nip. 19740622 200501 1 009