ENGINEER ESTIMATE ( EE )

KEGIATAN : PEMBANGUNAN GEDUNG RUANG KELAS BARU MADRASAH IBTIDAIYAH NEGERI (MIN) YAMUETI KOKODA
KABUPATEN SORONG SELATAN
LOKASI : DISTRIK KOKODA - KABUPATEN SORONG SELATAN
SUMBER DANA : SBSN
TAHUN ANGGARAN : 2021

HARGA SATUAN JUMLAH HARGA


NO URAIAN PEKERJAAN VOLUME SATUAN
( Rp ) ( Rp )
I PEKERJAAN PERSIAPAN
1 Pembersihan Lokasi 1,656.00 M2 19,250.00 31,878,000.000
2 Pengukuran Dan Pemasangan Bouwplank 202.00 M1 66,770.00 13,487,540.000
3 Papan Nama Proyek 1.00 Ls 750,000.00 750,000.000
4 Direksi Keet 1.00 Ls 15,000,000.00 15,000,000.000
5 Listrik Dan Air Kerja 1.00 Ls 10,000,000.00 10,000,000.000
6 P 3 K & Peralatan Keselamatan Kerja 1.00 Ls 5,500,000.00 5,500,000.000
7 Biaya Mobilisasi dan Demobilisasi 1.00 Ls 220,000,000.00 220,000,000.000
Sub Total I 296,615,540.000
II PEKERJAAN TANAH
1 Urugan Tanah Dipadatkan 828.00 M3 463,925.00 384,129,900.000
2 Galian Tanah Pondasi 123.86 M3 86,625.00 10,729,372.500
3 Urugan Tanah Kembali 24.78 M3 28,875.00 715,522.500
4 Urugan Tanah Peninggi Lantai 125.28 M3 463,925.00 58,120,524.000
5 Urugan Pasir Bawah Pondasi 21.38 M3 826,650.00 17,673,777.000
6 Urugan Pasir Bawah Lantai 47.37 M3 826,650.00 39,158,410.500
7 Urugan Pasir Bawah Rabat Beton Halaman 18.70 M3 826,650.00 15,458,355.000
Sub Total II 525,985,861.500
III PEKERJAAN PASANGAN DAN BETON
1 Aastamping Batu Kali 42.75 M3 1,622,626.500 69,367,282.875
2 Pasangan Pondasi Batu Kali Camp. 1:4 90.00 M3 2,560,662.500 230,459,625.000
3 Pasangan Kayu Cerucuk Mangi-mangi Dia 10-15 cm 200.00 Batang 156,568.500 31,313,700.000
4 Cor Lantai Kerja Beton Rabat Camp. 1:3:5, t= 5 cm 1.60 M3 2,389,612.500 3,823,380.000
5 Pondasi Foot Plate 13.16 M3 7,688,710.280 101,183,427.285
6 Coor Sloof Beton 15/20, Camp. 1:2:3 6.30 M3 9,201,071.530 57,966,750.639
7 Coor Kolom Beton 25/25, Camp. 1:2:3 13.44 M3 15,443,217.050 207,556,837.152
8 Coor Kolom Beton 15/15, Camp. 1:2:3 0.85 M3 15,443,217.050 13,126,734.493
9 Coor Balok Beton 15/25 Camp. 1:2:3 1.92 M3 15,443,217.050 29,650,976.736
10 Coor Balok Beton 15/20 Camp. 1:2:3 6.42 M3 12,151,931.530 78,015,400.423
11 Coor Balok Beton 15/15 Camp. 1:2:3 1.25 M3 12,151,931.530 15,189,914.413
12 Coor Beton Talang Air Camp 1:2:3 0.34 M3 12,151,931.530 4,131,656.720
13 Coor Beton Plat Injak, t 10 cm 0.19 M3 12,151,931.530 2,308,866.991
Sub Total III 844,094,552.725
IV PEKERJAAN DINDING DAN LANTAI
1 Pasangan Dinding Batu Tela Camp. 1:4 611.67 M2 278,943.500 170,621,370.645
2 Plesteran Dinding 1,223.34 M2 117,526.200 143,774,501.508
3 Acian Dinding 1,223.34 M2 45,017.500 55,071,708.450
4 Pasangan Almunium Compisite Panel (ACP) 190.42 M2 973,252.500 185,326,741.050
5 Cutting Laser Ornamen ACP 51.84 M2 550,000.000 28,512,000.000
6 Cor Lantai Beton t= 5 cm, Camp. 1:3:5 21.72 M3 2,389,612.500 51,902,383.500
7 Pasangan Lantai Keramik Interior 40/40 322.64 M2 362,596.720 116,988,205.741
8 Pasangan Lantai Keramik Exterior 40/40 Anti Slip 110.28 M2 368,898.750 40,682,154.150
9 Rabat Keliling Bangunan t= 5 cm, Camp. 1:3:5 9.14 M3 2,389,612.500 21,841,058.250
HARGA SATUAN JUMLAH HARGA
NO URAIAN PEKERJAAN VOLUME SATUAN
( Rp ) ( Rp )
10 Rabat Halaman Sekolah t= 15 cm, Camp. 1:3:5 56.10 M3 2,389,612.500 134,057,261.250
11 Saluran Keliling 128.80 M1 264,289.300 34,040,461.840
12 Pasang Hand Railing, Pipa GIV 3" 48.50 M1 313,120.500 15,186,344.250
13 Pasang Profil Besi Hollow 50x50 tebal 2,7 mm 210.50 M1 114,020.500 24,001,315.250
14 Pasangan Logo dan Nama Sekolah 1.00 Ls 8,000,000.000 8,000,000.000
Sub Total IV 1,030,005,505.884
V PEKERJAAN KUSEN, DAUN PINTU DAN JENDELA
1 Pasang Kusen Pintu Dan Jendela, Kayu Kls I 2.33 M3 10,278,180.000 23,948,159.400
2 Pasang Daun Jendela Jadi Kaca Bening 5 mm 42.00 Bh 600,000.000 25,200,000.000
3 Pasang Daun Pintu Panil Jadi Type 1 6.00 Bh 1,250,000.000 7,500,000.000
4 Pasang Daun Pintu Panil Jadi Type 2 6.00 Bh 750,000.000 4,500,000.000
5 Pasang Daun Pintu Panil Jadi Type 3 2.00 Bh 1,000,000.000 2,000,000.000
6 Pasang Kaca Mati 6 mm 3.60 M2 545,172.670 1,962,621.612
7 Pasang Papan Jalusi 2.12 M2 719,675.000 1,525,711.000
Sub Total V 66,636,492.012
VI PEKERJAAN ATAP DAN PLAFOND
1 Pek Kuda-kuda 5/10 kayu kls II 1.91 M3 8,712,000.000 16,639,920.000
2 Pas. Skor Angin 2 (5/10) 0.52 M3 6,305,200.000 3,278,704.000
3 Pek. Gording 5/10 kayu klas II 3.90 M3 7,732,120.000 30,155,268.000
4 Pek. Penutup Atap Seng Gelombang BJLS 0,3mm 666.56 M2 87,681.000 58,444,647.360
5 Pas. List Plank 3/30 126.40 M1 105,765.000 13,368,696.000
6 Pas. Plafond Tripleks 4 mm + Rangka Kayu Kls II 535.40 M2 196,812.500 105,373,412.500
7 Pas. List Plafond 3/3 530.42 M1 23,773.750 12,610,072.475
Sub Total VI 239,870,720.335
VII PEKERJAAN PENGUNCI DAN PENGGANTUNG
1 Pas. Kunci Tanam 2 Slag 8.00 Bh 234,410.000 1,875,280.000
2 Pas. Engsel Pintu 42.00 Bh 51,529.500 2,164,239.000
3 Pas. Engsel Jendela 84.00 Bh 38,142.500 3,203,970.000
4 Pas. Grendel Pintu 12.00 Bh 51,535.000 618,420.000
5 Pas. Grendel Jendela 42.00 Bh 51,535.000 2,164,470.000
6 Pas. Hak Angin Jendela 86.00 Bh 44,401.500 3,818,529.000
Sub Total VII 13,844,908.000
VIII PEKERJAAN INSTALASI LISTRIK
1 Pas. Instalasi Listrik Kabel Utama 3x2,5 NYM 303.00 M 41,030.000 12,432,090.000
2 Pas. MCB + Box MCB 1.00 Unit 867,185.000 867,185.000
3 Pas. Lampu RM LED 2x18 Watt (Gloss M4) 36.00 Titik 617,485.000 22,229,460.000
4 Pas. Lampu DL RD 100 LED 10 Watt 20.00 Titik 292,985.000 5,859,700.000
5 Pas. Saklar Ganda 2.00 Titik 160,270.000 320,540.000
6 Pas. Saklar Tunggal 21.00 Titik 165,770.000 3,481,170.000
7 Pas. Stop Kontak 18.00 Titik 127,160.000 2,288,880.000
Sub Total VIII 47,479,025.000
IX PEKERJAAN PENGECATAN
1 Cat Dinding Tembok 1,039.84 M2 38,395.530 39,925,207.915
2 Cat Kusen, Daun Pintu dan Jendela 166.99 M2 42,422.230 7,084,088.188
3 Cat List Plank Papan 51.16 M2 42,422.230 2,170,321.287
4 Cat Plafond 535.40 M2 38,395.530 20,556,966.762
5 Cat List Plafond 530.42 M1 42,422.230 22,501,599.237
Sub Total IX 92,238,183.388
X PEKERJAAN SANITASI
1 Bak Mandi 2.00 Bh 2,500,000.000 5,000,000.000
2 Kloset Duduk 2.00 Bh 1,006,412.000 2,012,824.000
3 Pas. Keramik Dinding 20 x 25 14.46 M2 319,355.960 4,617,887.182
4 Pas. Keramik Lantai 20 x 20 3.87 M2 319,619.850 1,236,928.820
HARGA SATUAN JUMLAH HARGA
NO URAIAN PEKERJAAN VOLUME SATUAN
( Rp ) ( Rp )
5 Kran Air 1/2" 2.00 Bh 40,507.500 81,015.000
6 Pipa PVC 1/2" 14.00 M1 50,891.500 712,481.000
7 Pipa PVC 2" 4.00 M1 71,276.650 285,106.600
8 Pipa PVC 3" 4.00 M1 130,594.830 522,379.320
9 Pipa PVC 4" 11.00 M1 184,408.890 2,028,497.790
10 Floor Drain 2.00 Bh 90,860.000 181,720.000
11 Sumur Bor + Jet Pump 1.00 Ls 35,000,000.000 35,000,000.000
12 Menara Air Kayu Besi Untuk Profil Tank 1.00 LS 8,000,000.000 8,000,000.000
13 Profil Tank 2200 Liter 1.00 Unit 6,500,000.000 6,500,000.000
14 Septick Tank + Resapan 1.00 Ls 30,000,000.000 30,000,000.000
Sub Total X 96,178,839.711
XI PEKERJAAN JEMBATAN
1 Urugan Pasir Bawah Pondasi 0.57 M3 826,650.000 471,190.500
2 Aastamping Batu Kali 1.14 M3 1,622,626.500 1,849,794.210
3 Pasangan Pondasi Batu Kali Camp. 1:4 2.40 M3 2,560,662.500 6,145,590.000
4 Coor Plat Beton Camp. 1:2:3. tebal 12 cm 0.62 M3 12,151,931.530 7,534,197.549
5 Coor Kanstin Beton Camp. 1:2:3 0.09 M3 12,151,931.530 1,093,673.838
Sub Total XI 17,094,446.096
XII PEKERJAAN PEMBERSIHAN
1 Pek. Finishing 1.00 Ls 2,500,000.000 2,500,000.000
Sub Total XII 2,500,000.000