HARGA SATUAN JUMLAH HARGA


NO URAIAN PEKERJAAN SAT VOL
(Rp) (Rp)

A. PEKERJAAN PERSIAPAN 3,977,452.50

1. Papan Nama Proyek Bh 1.00 150,000.00 150,000.00


2. Pengukuran & Pasang Bowplank Ls 1.00 1,123,952.50 1,123,952.50
3. Penggunaan Air Kerja & Listrik Kerja Ls 1.00 990,000.00 990,000.00
4. Sewa Rumah Ls 1.00 916,000.00 916,000.00
5. K3 & Keselamatan Kerja Ls 1.00 797,500.00 797,500.00

B. PEMBANGUNAN PAGAR DEPAN; 42,95 M 106,433,494.49


I. Pekerjaan Tanah 2,939,395.67
1. Pek. Galian Tanah Untuk Pondasi Jalur M3 20.62 91,987.50 1,896,414.30
2. Pek. Galian Tanah Pondasi Telapak M3 5.12 112,172.50 574,323.20
3. Pek. Urugan Tanah Kembali M3 6.43 25,001.90 160,862.22
4. Pek. Urugan Pasir Dibawah Pondasi M3 1.97 155,925.00 307,795.95

II. Pekerjaan Pondasi 13,453,512.33


1. Pek. Aanstamping Batu Kali / Belah M3 5.15 398,744.50 2,055,129.15
2. Pek. Pondasi Batu Kali / Belah sp. 1:5 M3 11.39 871,744.50 9,925,464.94
3. Pek. Cor Lantai Kerja Ad. 1 : 3 : 5 M3 0.26 719,632.10 184,225.82
4. Pek. Rolag Bata Cor Depan Pagar M2 8.59 150,022.40 1,288,692.42

III. Pekerjaan Beton 42,540,299.01


Pek. Cor Beton Telapak Ad. 1 : 2 : 3 M3 1.02 3,754,899.45 3,845,017.03
1. Pek. Cor Beton Sloef (15x20) Cm M3 1.29 6,073,781.95 7,826,068.04
2. Pek. Cor Kolom Utama (20x20) Cm K1 M3 1.26 6,360,908.35 8,014,744.52
3. Pek. Cor Beton Kolom (15x30) K2 M3 2.54 4,703,377.20 11,958,336.52
4. Pek. Cor Beton Kolom (20x30) K3 M3 0.34 4,993,253.60 1,677,733.21
5. Pek. Cor Beton Bertulang Kolom Praktis (12x12) Cm Ad M3 0.04 7,325,010.13 297,454.01
6. Pek. Cor Beton Ring Balok (11x20) Cm M3 0.94 6,560,416.20 6,198,937.26
7. Pek. Cor Beton Depan Pagar, Lebar 0,89 m t = 10 Cm M3 3.78 719,632.10 2,722,008.42

IV. Pekerjaan Dinding & Plesteran 41,116,926.60


1. Pas. Dinding Batu ½ Bata sp. 1 : 5 M2 31.94 150,022.40 4,792,090.51
2. Pas. Penebalan Kolom Dinding Batu ½ Bata sp. 1 : 5 M2 45.60 150,022.40 6,841,021.44
3. Pek. Plesteran Dinding, Beton dan Pondasi sp. 1 : 5 M2 140.30 75,178.62 10,547,372.44
4. Pek. Penebalan Plester Kolom sp. 1 : 5 M2 3.00 75,178.62 225,535.86
5. Pek. Acian Semen M2 140.30 45,402.50 6,369,857.24
6. Pek. Keramik Dinding 40 x 40 cm M2 12.11 159,401.00 1,929,549.11
7. Pas. Huruf Acrilic L 10,5 Cm, T = 11,5 Cm Ls 1.00 7,249,000.00 7,249,000.00
8. Pas. Huruf Acrilic L 6,6 Cm, T = 10,2 Cm & Logo Ls 1.00 3,162,500.00 3,162,500.00
V. Pekerjaan Finishing 6,383,360.88
1. Pek. Pengecatan Dinding & Beton Ex Dulux M2 140.30 45,498.75 6,383,360.88

C. PEMBANGUNAN PINTU GERBANG; 6 M 48,223,067.23


1. Pek. Galian Tanah Telapak M3 1.20 112,172.50 134,607.00
2. Pek. Urugan Tanah Kembali M3 0.30 25,001.90 7,500.57
3. Pek. Cor Lantai Kerja Ad. 1 : 3 : 5 M3 0.24 719,632.10 172,711.70
4. Pek. Cor Beton Telapak M3 0.48 3,754,899.45 1,802,351.73
5. Pek. Cor Beton Sloef (15/20) Cm M3 0.08 6,073,781.95 510,197.68
6. Pek. Cor Beton Kolom K1 (40/60) Cm M3 2.38 3,496,582.05 8,307,878.94
7. Pek. Cor Beton Kolom K2 (10/30) Cm M3 0.53 7,743,792.05 4,070,137.10
8. Pek. Balok 20/30 Cm M3 0.17 4,561,899.05 766,399.04
9. Pas. Penebalan Kolom Dinding Batu ½ Bata sp. 1 : 5 M2 53.65 150,022.40 8,048,701.76
10. Pek. Plesteran Dinding, Beton sp. 1 : 5 M2 53.65 75,178.62 4,033,332.96
11. Pek. Profil M1 26.32 76,653.50 2,017,520.12
11. Pek. Acian Semen M2 53.65 45,402.50 2,435,844.13
12. Pas. Logo Basarnas Ls 2.00 1,045,000.00 2,090,000.00
13. Pek. Batu Alam M2 8.83 385,273.90 3,400,581.55
14. Pek. Pintu Pagar Besi Kotak Tinggi = 1,60 M M2 10.00 798,429.50 7,984,295.00
15. Pek. Pengecatan Dinding & Beton Ex Dulux M2 53.65 45,498.75 2,441,007.94

D. PEKERJAAN PLAT DUICKER; 6 M x 1,5 M 15,275,077.42


1. Pek. Galian Tanah Pondasi Plat Duicker M3 9.24 91,987.50 849,964.50
2. Pek. Urugan Tanah Kembali M3 2.31 25,001.90 57,754.39
3. Pek. Aanstamping Batu Kali / Belah M3 1.09 398,744.50 435,428.99
4. Pek. Pondasi Batu Kali/Belah Sp.1 : 5 M3 5.41 871,744.50 4,717,881.23
5. Pek. Cor Beton Plat Duicker T = 20 Cm Ad. 1 : 2 : 3 M3 1.80 3,754,899.45 6,758,819.00
6. Pek. Cor Beton Ad. 1 : 2 : 3 M3 1.20 719,632.10 863,558.52
7. Pek. Plesteran Pondasi Duicker Sp.1 : 5 M2 13.20 75,178.62 992,357.78
8. Pek. Acian Semen M2 13.20 45,402.50 599,313.00

E. PEKERJAAN TIANG BENDERA 1,068,122.04


1. Pek. Galian Tanah M3 0.26 91,987.50 23,548.80
2. Pek. Cor Beton 0,8 x 0,8 x 0,8 Ad. 1 : 2 : 3 M3 0.51 719,632.10 368,451.64
3. Pipa Galvanis 1" M 7.00 96,588.80 676,121.60

F. PEKERJAAN LAIN-LAIN 2,295,800.00

1. Administrasi / Dokumentasi Ls 1.00 1,000,000.00 1,000,000.00


2. Pembersihan Akhir Ls 1.00 1,295,800.00 1,295,800.00

Gorontalo, Nopember 2021


Dibuat Oleh :
KONSULTAN PERENCANA
CV. NUROSANA PERSADA

RISMAN GANI, ST
Direktur
REKAPITULASI
ENGINEER ESTIMATE (EE)

PROGRAM : PENINGKATAN SARANA DAN PRASARANA APARATUR BADAN SAR NASIONAL

KEGIATAN : PENGELOLAAN SARANA DAN PRASARANA APARATUR

PEMBANGUNAN PAGAR DAN DUICKER POS PENCARIAN DAN


PEKERJAAN :
PERTOLONGAN MARISA

LOKASI : Kompleks Block Plan Perkantoran Kab. Pohuwato

THN. ANGGARAN : 2021

NO KOMPONEN PEKERJAAN JUMLAH

A. PEKERJAAN PERSIAPAN Rp. 3,977,452.50

B. PEMBANGUNAN PAGAR DEPAN; 42,95 M Rp. 106,433,494.49

C. PEMBANGUNAN PINTU GERBANG; 6 M Rp. 48,223,067.23

D. PEKERJAAN PLAT DUICKER; 6 M x 1,5 M Rp. 15,275,077.42

E. PEKERJAAN TIANG BENDERA Rp. 1,068,122.04

F. PEKERJAAN LAIN-LAIN Rp. 2,295,800.00

JUMLAH Rp. 177,273,013.67

PAJAK PERTAMBAHAN NILAI (PPN) 10% Rp. 17,727,301.37

TOTAL Rp. 195,000,315.04

DIBULATKAN Rp. 195,000,000.00

Terbilang : Seratus Sembilan Puluh Lima Juta Rupiah

Gorontalo, Nopember 2021


Menyetujui : Dibuat Oleh :
PEJABAT PEMBUAT KOMITMEN KONSULTAN PERENCANA
(PPK) CV. NUROSANA PERSADA

TANTI C. HAMADA, S.Sos, M.Si RISMAN GANI, ST


NIP 197710082008122001 Direktur