HARGA
NO. URAIAN PEKERJAAN SATUAN VOLUME SATUAN JUMLAH
(Rp) (Rp)
a b c d e f
I. PEKERJAAN PERSIAPAN
1 Pembersihan lokasi M2 49.00 30,000.00 1,470,000.00
2 Barak kerja/direksi keet & gudang M2 30.00 520,000.00 15,600,000.00
3 Papan nama kegiatan Bh 1.00 1,578,000.00 1,578,000.00
Rp 18,648,000.00
II. PEKERJAAN KAYU
1 Pasang bouwplank M' 42.00 115,240.00 4,840,080.00
2 Kolom kayu besi 10/10 cm M3 0.98 6,729,400.00 6,589,428.48
3 Pondasi kayu besi 15/15 M3 2.14 6,729,400.00 14,391,494.84
4 Ring balok kayu besi 5/10 cm M3 0.30 6,729,400.00 1,998,631.80
5 Dinding papan kayu besi t = 2 cm M2 165.20 301,311.16 49,776,603.46
6 Pasang top gavel M2 0.70 301,311.16 210,917.81
7 Kuda - kuda kayu Besi 5/10 M3 1.35 8,500,600.00 11,475,810.00
8 Balok Ikatan Angin kayu Besi 5/10 M3 0.14 8,500,600.00 1,224,086.40
9 Gording kayu matoa 5/10 M3 0.96 5,817,680.00 5,584,972.80
10 Kusen pintu, jendela dan ventilasi ky bs 5/10 cm M3 0.33 10,317,600.00 3,357,347.04
11 Jalusi kayu besi M2 8.00 788,100.00 6,304,800.00
12 Jendela ungkit kaca ky besi M2 7.56 733,230.00 5,543,218.80
14 Pintu panel kayu besi M2 8.40 980,740.00 8,238,216.00
15 Pembuatan pagar kayu(relling) M3 0.45 10,317,600.00 4,642,920.00
16 Balok Skor Pondasi kayu besi 5/10 M3 1.08 6,729,400.00 7,267,752.00
17 Tangga kayu M3 0.15 10,317,600.00 1,547,640.00
Rp 132,993,919.43
III. PEKERJAAN BETON
1 Pek. Pas. Pondasi batu karang M3 8.75 2,091,408.00
1 Pek. Cor Lantai KM/WC M3 0.32 3,026,228.00 953,261.82
2 Floor Lantai KM/WC M2 4.50 46,725.60 210,265.20
Rp 1,163,527.02
IV. PEKERJAAN ATAP
1 Atap metal soka M2 168.00 196,699.55 33,045,523.76
2 Nok genteng metal soka M' 10.00 193,198.29 1,931,982.86
3 Lisplank ky besi 2 x 2,5/30 M' 55.92 101,200.00 5,659,104.00
4 Plafond triplek 3 mm M2 78.50 258,832.00 20,318,312.00
5 List plafond kayu matoa diprofil M' 60.00 71,132.00 4,267,920.00
Rp 65,222,842.62
V. PEKERJAAN LANTAI
1 Lantai papan kayu besi t = 3 cm M2 65.25 300,340.00 19,597,185.00
2 Pasang balok lantai kayu besi 5/15 dan 5/10 cm M2 65.25 333,213.24 21,742,163.95
Rp 41,339,348.95
VI. PEKERJAAN PENGECATAN
1 Cat dinding M2 165.20 83,078.00 13,724,485.60
2 Cat plafond M2 78.50 21,438.60 1,682,930.10
3 Cat kusen pintu / jendela, daun pintu, daun jendela ,
jalusi dan lisplank M2 89.64 83,078.00 7,447,278.08
Rp 22,854,693.78
a b c d e f
VII. PEKERJAAN ALAT GANTUNG
1 Kunci tanam 2 SLAGG Bh 4.00 399,896.00 1,599,584.00
2 Engsel pintu ring nylon Bh 12.00 76,574.00 918,888.00
3 Grendel pintu Bh 4.00 70,032.00 280,128.00
4 Engsel jendela ring nylon Bh 18.00 62,316.00 1,121,688.00
5 Grendel jendela Bh 9.00 70,032.00 630,288.00
6 Hak angin/kait angin Bh 9.00 73,974.00 665,766.00
7 Hendle tarikan Bh 9.00 131,580.00 1,184,220.00
8 Baut dia. 12 mm Bh 60.00 37,520.00 2,251,200.00
Rp 8,651,762.00
VIII. PENGADAAN PERABOT
1 Meja guru Bh 9.00 4,500,000.00 40,500,000.00
2 Kursi guru Bh 9.00 1,200,000.00 10,800,000.00
3 Papan white board Bh 3.00 3,000,000.00 9,000,000.00
4 Lemari buku Bh 5.00 4,800,000.00 24,000,000.00
5 Tempat sampah Bh 2.00 800,000.00 1,600,000.00
Rp 85,900,000.00
IX. PEKERJAAN LISTRIK
1 Pasang lampu Philips SL 40 watt Bh 6.00 563,740.00 3,382,440.00
2 Pasang lampu Philips SL 25 wat Bh 2.00 453,240.00 906,480.00
3 Pasang stop kontak Bh 3.00 324,540.00 973,620.00
4 Pas. Box Limit Bh 1.00 427,240.00 427,240.00
Rp 5,689,780.00
X. PEKERJAAN SANITASI
1 Pek. Pas. Klosed Jongkok bh 1.00 1,834,500.00 1,834,500.00
2 Pek. Pas. Bak Air Fiber KM/WC bh 1.00 900,000.00 900,000.00
3 Pek. Pas. Pipa PVC 4" m' 4.00 124,075.20 496,300.80
4 Pek. Pas. Pipa PVC 1 1/2" m' 4.00 57,637.35 230,549.40
5 Pek. Pas. Pipa PVC 1/2" m' 4.00 33,094.35 132,377.40
6 Pek. Pas. Kran Air 1/2" bh 1.00 82,565.00 82,565.00
7 Pek. Pas. Septictank unit 1.00 8,000,000.00 8,000,000.00
Rp 11,676,292.60
XI. PEKERJAAN AKHIR
1 Pekerjaan Pembersihan Akhir Ls 1.00 2,273,000.00 2,273,000.00
2 Foto dokumentasi dan pelaporan Ls 1.00 1,560,000.00 1,560,000.00
Rp 3,833,000.00
a b c d e f
R E K A P I T U L A S I
Pekerjaan : Pembangunan Ruang Guru/ TU Beserta Perabotnya SD Negeri Persiapan Burgena
Lokasi : Burgena, Distrik Pantai Barat, Kabupaten Sarmi
Tahun : 2022
TERBILANG : EMPAT RATUS EMPAT PULUH SATU JUTA TUJUH RATUS LIMA PULUH RIBU RUPIAH
Sarmi, 2022
DAFTAR ANALISA HARGA SATUAN
Pekerjaan : Pembangunan Ruang Guru/ TU Beserta Perabotnya SD Negeri Persiapan Burgena
Lokasi : Burgena, Distrik Pantai Barat, Kabupaten Sarmi
Tahun : 2022
ANALISA
No. URAIAN PEKERJAAN SATUAN HARGA SATUAN JUMLAH HARGA
SATUAN
a b d e f g
1 1 M' PENGUKURAN DAN PASANG BOUWPLANK
Kayu 5/7 0.0120 M3 3,500,000.00 42,000.00
Paku biasa 2"-5" 0.0200 Kg 26,000.00 520.00
Kayu papan 3/20 0.0070 M3 3,000,000.00 21,000.00
Tukang kayu 0.1000 Oh 192,000.00 19,200.00
Pekerja 0.1000 Oh 144,000.00 14,400.00
Kepala tukang 0.0100 Oh 252,000.00 2,520.00
Mandor 0.0500 Oh 312,000.00 15,600.00
115,240.00
2 1 M2 PEMBUATAN GUDANG DAN ALAT-ALAT
Dolken kayu dia. 8-10/400 cm 1.7000 Btg 50,000.00 85,000.00
Kayu 0.2100 M3 4,500,000.00 945,000.00
Paku biasa campuran 0.3000 Kg 26,000.00 7,800.00
Semen portland 10.5000 Kg 3,450.00 36,225.00
Pasir beton 0.0300 M3 700,000.00 21,000.00
Koral beton 0.0500 M3 1,900,000.00 95,000.00
Seng gelombang bjls 0,32 1.5000 Lbr 195,000.00 292,500.00
Tukang kayu 2.0000 Oh 192,000.00 384,000.00
Pekerja 1.0000 Oh 144,000.00 144,000.00
Kepala tukang 0.2000 Oh 252,000.00 50,400.00
Mandor 0.0500 Oh 312,000.00 15,600.00
2,076,525.00
3 1 M2 PEMBERSIHAN LAPANGAN DAN PERATAAN
Pekerja 0.1000 Oh 144,000.00 14,400.00
Mandor 0.0500 Oh 312,000.00 15,600.00
30,000.00
4 1 M3 PASANG KUSEN PINTU DAN JENDELA KAYU BESI
Balok kayu besi 1.2000 M3 4,500,000.00 5,400,000.00
Pekerja 6.0000 Oh 144,000.00 864,000.00
Tukang kayu 18.0000 Oh 192,000.00 3,456,000.00
Kepala tukang 2.0000 Oh 252,000.00 504,000.00
Mandor 0.3000 Oh 312,000.00 93,600.00
10,317,600.00
5 1 M2 PASANG JENDELA KACA KAYU BESI
Papan kayu besi 0.0350 M3 4,500,000.00 157,500.00
Lem kayu 0.3000 Ltr 45,500.00 13,650.00
Pekerja 0.8000 Oh 144,000.00 115,200.00
Tukang kayu 2.0000 Oh 192,000.00 384,000.00
Kepala tukang 0.2000 Oh 252,000.00 50,400.00
Mandor 0.0400 Oh 312,000.00 12,480.00
733,230.00
6 1 M2 PASANG JALUSI MATI KAYU BESI
Papan kayu besi 0.0600 M3 4,500,000.00 270,000.00
Paku biasa campuran 0.1500 Kg 26,000.00 3,900.00
Pekerja 0.5000 Oh 144,000.00 72,000.00
Tukang kayu 2.0000 Oh 192,000.00 384,000.00
Kepala tukang 0.2000 Oh 252,000.00 50,400.00
Mandor 0.0250 Oh 312,000.00 7,800.00
788,100.00
a b d e f g
21 1 BH PASANG GRENDEL
Grendel 1.0000 Bh 23,400.00 23,400.00
Pekerja 0.0200 Oh 144,000.00 2,880.00
Tukang kayu 0.2000 Oh 192,000.00 38,400.00
Kepala tukang 0.0200 Oh 252,000.00 5,040.00
Mandor 0.0010 Oh 312,000.00 312.00
70,032.00
22 1 BH PASANG PEGANGAN
Pegangan/handle 1.0000 Bh 15,000.00 15,000.00
Pekerja 0.0500 Oh 144,000.00 7,200.00
Tukang kayu 0.5000 Oh 192,000.00 96,000.00
Kepala tukang 0.0500 Oh 252,000.00 12,600.00
Mandor 0.0025 Oh 312,000.00 780.00
131,580.00
23 1 M2 PASANG KACA BENING/POLOS
Kaca bening/polos 5 mm 1.1000 M2 643,890.00 708,279.00
Pekerja 0.0150 Oh 144,000.00 2,160.00
Tukang kayu 0.1500 Oh 192,000.00 28,800.00
Kepala tukang 0.0150 Oh 252,000.00 3,780.00
Mandor 0.0008 Oh 312,000.00 234.00
743,253.00
24 1 M2 MENGECAT KAYU BARU, 1 LAPIS PLAMIR,
1 LAPIS CAT DASAR, 3 LAPIS CAT PENUTUP
Cat meni 0.2000 Kg 45,500.00 9,100.00
Plamir 0.1500 Kg 31,800.00 4,770.00
Cat dasar/cat kayu 0.1700 Kg 71,500.00 12,155.00
Cat penutup/cat kayu 0.3500 Kg 71,500.00 25,025.00
Pekerja 0.0700 Oh 144,000.00 10,080.00
Tukang cat 0.1050 Oh 192,000.00 20,160.00
Kepala tukang 0.0040 Oh 252,000.00 1,008.00
Mandor 0.0025 Oh 312,000.00 780.00
83,078.00
a b d e f g
NILAI KEMAJUAN
NO. URAIAN PEKERJAAN REALISASI
VOLUME SAT BOBOT PEKERJAA
BOBOT (%)
(%) N (%)
a b c d e f g
I. PEKERJAAN PERSIAPAN
1 Pembersihan lokasi 49.00 M2 0.369 100 0.37
2 Barak kerja/direksi keet & gudang 30.00 M2 3.920 100 3.92
3 Papan nama kegiatan 1.00 Bh 0.397 100 0.40
V. PEKERJAAN LANTAI
1 Lantai papan kayu besi t = 3 cm 65.25 M2 4.924 100 4.92
2 Pasang balok lantai kayu besi 5/15 dan 5/10 cm 65.25 M2 5.463 100 5.46
Kemajuan pekerjaan sampai saat ini sebesar 75.79 % (tujuh lima koma tujuh sembilan persen)
Demikian bobot prestasi kemajuan pekerjaan ini dibuat untuk dipergunakan sebagaimana mestinya.
Setuju dibuat, Dibuat Oleh :
KONTRAKTOR PELAKSANA KONSULTAN PENGAWAS
CV. CITRA NARANSOM PERKASA CV. FURIATAMA CONSULTANT
NILAI KEMAJUAN
NO. URAIAN PEKERJAAN REALISASI
VOLUME SAT BOBOT PEKERJAA
BOBOT (%)
(%) N (%)
a b c d e f g
I. PEKERJAAN PERSIAPAN
1 Pembersihan lokasi 49.00 M2 0.37 100 0.37
2 Barak kerja/direksi keet & gudang 30.00 M2 3.92 100 3.92
3 Papan nama kegiatan 1.00 Bh 0.40 100 0.40
V. PEKERJAAN LANTAI
1 Lantai papan kayu besi t = 3 cm 65.25 M2 4.92 0 0.00
2 Pasang balok lantai kayu besi 5/15 dan 5/10 cm 65.25 M2 5.46 0 0.00
Kemajuan pekerjaan sampai saat ini sebesar 55.26 % (Lima lima koma dua enam persen)
Demikian bobot prestasi kemajuan pekerjaan ini dibuat untuk dipergunakan sebagaimana mestinya.
Setuju dibuat, Dibuat Oleh :
KONTRAKTOR PELAKSANA KONSULTAN PENGAWAS
CV. CITRA NARANSOM PERKASA CV. FURIATAMA CONSULTANT
NILAI KEMAJUAN
NO. URAIAN PEKERJAAN REALISASI
VOLUME SAT BOBOT PEKERJAA
BOBOT (%)
(%) N (%)
a b c d e f g
I. PEKERJAAN PERSIAPAN
1 Pembersihan lokasi 49.00 M2 0.369 100 0.37
2 Barak kerja/direksi keet & gudang 30.00 M2 3.920 100 3.92
3 Papan nama kegiatan 1.00 Bh 0.397 100 0.40
V. PEKERJAAN LANTAI
1 Lantai papan kayu besi t = 3 cm 65.25 M2 4.924 100 4.92
2 Pasang balok lantai kayu besi 5/15 dan 5/10 cm 65.25 M2 5.463 100 5.46