RENCANA ANGGARAN BIAYA (RAB)

PEKERJAAN : PEMBANGUNAN RUMAH MASYARAKAT SEMI PERMANEN TYPE 45 KAMPUNG RAWA BIRU (5 UNIT)
LOKASI : DISTRIK SOTA
KAB / PROVINSI : MERAUKE - PAPUA
T.A : 2020
HARGA JUMLAH
No. URAIAN PEKERJAAN SAT KUANTITAS SATUAN HARGA
( Rp. ) ( Rp. )
1 2 3 4 5 6
A PEKERJAAN RUMAH

I PEKERJAAN PENDAHULUAN
1 Pembersihan Lapangan Ls 1,00 9.847.500,00 9.847.500,00
2 Pengukuran dan Pasang Bowplank M' 90,00 85.864,00 7.727.760,00
3 Papan Nama Proyek Ls 1,00 707.000,00 707.000,00
JUMLAH I . 18.282.260,00
II PEKERJAAN TANAH DAN PONDASI
1 Galian Tanah Pondasi M3 13,05 83.035,00 1.083.606,75
2 Urugan Tanah Kembali M3 4,35 25.536,00 111.081,60
3 Urugan Pasir Bawah Pondasi M3 3,25 362.700,00 1.178.775,00
4 Urugan Pasir Bawah Lantai + Rabat M3 17,48 362.700,00 6.339.996,00
5 Urugan Tanah Peninggian Lantai + Rabat M3 81,18 359.650,00 29.196.387,00
JUMLAH II . 37.909.846,35
III PEKERJAAAN PASANGAN DAN BETON
1 Pondasi Batu Bata Uk 20 x 40 cm, 1pc : 3ps (Pasir Lokal) M3 14,00 2.166.153,50 30.326.149,00
2 Pondasi Batu Bata Uk 20 x 35 cm, 1pc : 3ps (Pasir Lokal) M3 2,98 2.166.153,50 6.455.137,43
3 Rollag Batu Rabat 1pc : 3 ps (Pasir Lokal) M3 3,77 2.166.153,50 8.166.398,70
4 Cor Lantai Ruangan + Rabat 1pc : 3ps (Pasir Lokal) M3 24,47 2.964.780,00 72.548.166,60
5 Acian Lantai M2 349,64 48.080,00 16.810.691,20
6 Pasangan Dinding 1/4 Bata, 1pc : 3ps (Pasir Lokal) M2 435,88 205.938,80 89.764.604,14
7 Plesteran, 1 Pc : 3 Ps (Pasir Lokal) M2 871,76 95.019,00 82.833.763,44
JUMLAH III . 306.904.910,51
IV PEKERJAAN KAYU
1 Rangka Kolom Dinding , Kayu Kelas III M3 4,22 7.345.840,00 30.999.444,80
2 Kusen Pintu dan Jendela uk 4/8 cm, Kayu Kls III M3 1,20 7.065.390,00 8.478.468,00
3 Rangka Plafond (60 x 120) cm, Kayu Kelas III M2 246,25 129.405,00 31.865.981,25
4 Langit-langit Tripleks Tebal 4mm M2 246,25 68.201,00 16.794.496,25
5 Kuda-kuda Uk. 5/8 cm, Kayu Kls III M3 3,76 5.847.420,00 21.986.299,20
6 Goording uk. 5/8 cm, Kayu Kelas III M3 2,80 4.812.250,00 13.474.300,00
7 Lisplank Kayu uk. 2x(2/18) cm, Kayu Kelas III M1 193,60 105.922,50 20.506.596,00
8 Manumata papan, Kayu Kls III M2 45,33 396.370,00 17.967.452,10
JUMLAH IV . 162.073.037,60
V PEKERJAAN ATAP
1 Atap Zincalume M2 461,69 86.053,00 39.729.809,57
2 Bubungan / Nok Atap Alumunium Gelombang M1 50,20 125.474,00 6.298.794,80
JUMLAH V . 46.028.604,37
VI PEKERJAAN PASANG - MEMASANG
1 Pintu Double Tripleks Uk. 80 x 210 cm Unit 10,00 1.115.137,00 11.151.370,00
2 Pintu Panel Uk. 80 x 210 cm Unit 10,00 3.243.521,20 32.435.212,00
3 Jendela Ungkit Uk.70 x 100 cm, Kaca Polos 5 mm Unit 30,00 734.841,50 22.045.245,00
4 Jalusi Kayu + Lapih Has Nyamuk M2 14,00 396.370,00 5.549.180,00
JUMLAH VI . 71.181.007,00
VII PEKERJAAN PENGECATAN
1 Cat Ter/Residu (Kuda-kuda dan Goording) M2 426,35 17.611,25 7.508.556,44
2 Cat Many Kusen, Rangka Dinding dan Lisplank M2 389,01 27.870,00 10.841.708,70
3 Cat Kilap Kusen Pintu Jendela dan Lisplank M2 134,34 33.115,00 4.448.669,10
4 Cat Manumata M2 45,33 33.115,00 1.501.102,95
5 Cat Dinding M2 871,76 18.042,00 15.728.293,92
6 Cat Plafond M2 246,25 25.065,00 6.172.256,25
JUMLAH VII . 46.200.587,36
VIII PEKERJAAN INSTALASI LISTRIK
1 Instalasi Lampu SL 23 VA + Vitting Titik 35,00 118.425,00 4.144.875,00
2 Instalasi Lampu SL 14 VA + Vitting Titik 5,00 105.675,00 528.375,00
3 Instalasi Stop Kontak Titik 25,00 68.550,00 1.713.750,00
4 Instalasi Saklar Tunggal Titik 10,00 64.300,00 643.000,00
5 Instalasi Saklar Ganda Titik 15,00 67.700,00 1.015.500,00
6 MCB Unit 5,00 296.247,50 1.481.237,50
6 Pengadaan Sambungan Listrik Baru Ls 1,00 22.500.000,00 22.500.000,00
JUMLAH VIII . 32.026.737,50
IX PEKERJAAN FINISHING
1 Pembersihan Akhir Ls 1,00 5.000.000,00 5.000.000,00
JUMLAH IX . 5.000.000,00
HARGA JUMLAH
No. URAIAN PEKERJAAN SAT KUANTITAS SATUAN HARGA
( Rp. ) ( Rp. )
1 2 3 4 5 6
B PEKERJAAN DAPUR DAN KM/WC
I PEKERJAAN PENDAHULUAN
1 Pembersihan Lapangan Ls 1,00 3.535.000,00 3.535.000,00
2 Pengukuran dan Pasang Bowplank M' 42,50 85.864,00 3.649.220,00
JUMLAH I . 7.184.220,00
II PEKERJAAN TANAH DAN PONDASI
1 Galian Tanah Pondasi M3 3,75 2.166.153,50 8.123.075,63
2 Urugan Tanah Kembali M3 1,25 - -
3 Urugan Pasir Bawah Pondasi M3 0,94 906.780,00 852.373,20
4 Urugan Pasir Bawah Lantai + Rabat M3 1,56 906.780,00 1.414.576,80
5 Urugan Tanah Peninggian Lantai + Rabat M3 7,81 15.000,00 117.150,00
JUMLAH II . 10.507.175,63
III PEKERJAAAN PASANGAN DAN BETON
1 Pondasi Batu Bata Uk 20 x 40 cm, 1pc : 3ps (Pasir Lokal) M3 5,00 2.166.153,50 10.830.767,50
2 Cor Lantai Ruangan + Rabat 1pc : 3ps (Pasir Lokal) M3 2,19 2.964.780,00 6.492.868,20
3 Acian Lantai M2 31,25 48.080,00 1.502.500,00
4 Pasangan Dinding 1/4 Bata, 1pc : 3ps (Pasir Lokal) M2 153,94 205.938,80 31.702.218,87
5 Plesteran, 1 Pc : 3 Ps (Pasir Lokal) M2 307,87 95.019,00 29.253.499,53
JUMLAH III . 79.781.854,10
IV PEKERJAAN KAYU
1 Rangka Kolom Dinding , Kayu Kelas III M3 1,61 7.345.840,00 11.826.802,40
2 Kusen Pintu dan Jendela uk 4/8 cm, Kayu Kls III M3 0,32 7.065.390,00 2.260.924,80
3 Rangka Plafond (60 x 120) cm, Kayu Kelas III M2 31,25 129.405,00 4.043.906,25
4 Langit-langit Tripleks Tebal 4mm M2 31,25 68.201,00 2.131.281,25
5 Kuda-kuda Uk. 5/8 cm, Kayu Kls III M3 0,81 5.847.420,00 4.736.410,20
6 Goording uk. 5/8 cm, Kayu Kelas III M3 0,69 4.812.250,00 3.320.452,50
7 Lisplank Kayu uk. 2x(2/18) cm, Kayu Kelas III M1 26,00 105.922,50 2.753.985,00
8 Manumata papan, Kayu Kls III M2 8,09 396.370,00 3.206.633,30
JUMLAH IV . 34.280.395,70
V PEKERJAAN ATAP
1 Atap Zincalume M2 99,36 86.053,00 8.550.226,08
2 Bubungan / Nok Atap Alumunium Gelombang M1 19,75 125.474,00 2.478.111,50
JUMLAH V . 11.028.337,58
VI PEKERJAAN PASANG - MEMASANG
1 Pintu Double Tripleks Uk. 80 x 210 cm Unit 5,00 1.115.137,00 5.575.685,00
2 Pintu Panel Uk. 80 x 210 cm Unit 5,00 3.243.521,20 16.217.606,00
3 Jendela Ungkit Uk.70 x 100 cm, Kaca Polos 5 mm Unit 5,00 734.841,50 3.674.207,50
4 Jalusi Kayu + Lapih Has Nyamuk M2 7,00 396.370,00 2.774.590,00
JUMLAH VI . 28.242.088,50
VII PEKERJAAN PENGECATAN
1 Cat Ter/Residu (Kuda-kuda dan Goording) M2 97,53 17.611,25 1.717.625,21
2 Cat Many Kusen, Rangka Dinding dan Lisplank M2 124,16 27.870,00 3.460.339,20
3 Cat Kilap Kusen Pintu Jendela dan Lisplank M2 30,42 33.115,00 1.007.358,30
4 Cat Manumata M2 8,09 33.115,00 267.900,35
5 Cat Dinding M2 307,87 18.042,00 5.554.590,54
6 Cat Plafond M2 31,25 25.065,00 783.281,25
JUMLAH VII . 12.791.094,85
VIII PEKERJAAN SANITAIR
1 Septictank Uk (2x1x1,5)m, Pas Batu 1Pc : 4 Ps Unit 5,00 7.266.181,40 36.330.907,00
2 Bak Peresapan Uk. 1 x 1 M, Jarak 4 dari Septictank Unit 5,00 1.998.413,40 9.992.067,00
3 Pekerjaan Sumur + Rabat Unit 5,00 13.649.966,40 68.249.832,00
4 Closed Jongkok Porselin Unit 5,00 1.102.621,00 5.513.105,00
5 Instalasi Pipa Air Bersih Ls 1,00 3.500.000,00 3.500.000,00
6 Instalasi Pipa Air Kotor Ls 1,00 2.500.000,00 2.500.000,00
7 Floor Drain Bh 5,00 100.000,00 500.000,00
8 Kran Air Dia 3/4 Bh 5,00 77.000,00 385.000,00
9 Gentong Air Green Leaf 120 L Bh 5,00 311.000,00 1.555.000,00
10 Pengadaan dan Pemasangan Mesin Pompa Air Unit 5,00 1.321.000,00 6.605.000,00
JUMLAH VIII . 135.130.911,00
IX PEKERJAAN FINISHING
1 Pembersihan Akhir Ls 1,00 2.500.000,00 2.500.000,00
JUMLAH IX . 2.500.000,00
HARGA JUMLAH
No. URAIAN PEKERJAAN SAT KUANTITAS SATUAN HARGA
( Rp. ) ( Rp. )
1 2 3 4 5 6
C UMUM (KESELAMATAN DAN KESEHATAN KERJA)
I PENYIAPAN RK3K
1 Pembuatan Kartu Identitas Pekerja Ls 12,00 10.000,00 120.000,00
JUMLAH I . 120.000,00
II ALAT PELINDUNG KERJA
1 Topi Pelindung (Safety Halmet) Bb 12,00 100.000,00 1.200.000,00
2 Sarung Tangan ( Safety Gloves) Pasang 12,00 9.100,00 109.200,00
3 Pelindung Mata (Spectaclas) Bh 12,00 56.000,00 672.000,00
4 Pelindung Pernafasan (Masker) Bh 12,00 9.800,00 117.600,00
5 Sepatu Keselamatan ( Safety Shoes) Pasang 6,00 200.000,00 1.200.000,00
JUMLAH II . 3.298.800,00
III ASURANSI DAN PERIJINAN
1 BPJS Ketenaga Kerjaan dan Kesehatan Kerja Berdasarkan Ls 1,00 2.000.000,00 2.000.000,00
KEPMENAKER No.KEP-196/MEN/199 untuk Harian Proyek -
JUMLAH III . 2.000.000,00
IV PERSONIL K3
1 Petugas K3 OB 4,00 2.000.000,00 8.000.000,00
JUMLAH IV . 8.000.000,00
V FASILITAS SARANA KESEHATAN DAN KESELAMATAN
1 Peralatan P3K ( Alat P3K, Tandu, Tabung Oksigen, Obat Luka dll)Ls 1,00 1.700.000,00 1.700.000,00
2 Rambu Larangan Bh 1,00 204.000,00 204.000,00
3 Rambu Peringatan Bh 1,00 204.000,00 204.000,00
JUMLAH V . 1.904.000,00
VI LAIN-LAIN TERKAIT PENGENDALIAN RESIKO K3
1 Alat Pemadam Api Ringan (APAR) 10 kg Unit 5,00 396.370,00 1.981.850,00
JUMLAH VI . 1.981.850,00
REKAPITULASI AKHIR
PEKERJAAN : PEMBANGUNAN RUMAH MASYARAKAT SEMI PERMANEN TYPE 45 KAMPUNG RAWA BIRU (5 UNIT)
LOKASI : DISTRIK SOTA
KAB / PROVINSI MERAUKE - PAPUA
T.A : 2020
No. JENIS KEGIATAN JUMLAH HARGA
A PEKERJAAN RUMAH
I PEKERJAAN PENDAHULUAN Rp 18.282.260,00
II PEKERJAAN TANAH DAN PONDASI Rp 37.909.846,35
III PEKERJAAAN PASANGAN DAN BETON Rp 306.904.910,51
IV PEKERJAAN KAYU Rp 162.073.037,60
V PEKERJAAN ATAP Rp 46.028.604,37
VI PEKERJAAN PASANG - MEMASANG Rp 71.181.007,00
VII PEKERJAAN PENGECATAN Rp 46.200.587,36
VIII PEKERJAAN INSTALASI LISTRIK Rp 32.026.737,50
IX PEKERJAAN FINISHING Rp 5.000.000,00

B PEKERJAAN DAPUR DAN KM/WC


I PEKERJAAN PENDAHULUAN Rp 7.184.220,00
II PEKERJAAN TANAH DAN PONDASI Rp 10.507.175,63
III PEKERJAAAN PASANGAN DAN BETON Rp 79.781.854,10
IV PEKERJAAN KAYU Rp 34.280.395,70
V PEKERJAAN ATAP Rp 11.028.337,58
VI PEKERJAAN PASANG - MEMASANG Rp 28.242.088,50
VII PEKERJAAN PENGECATAN Rp 12.791.094,85
VIII PEKERJAAN SANITAIR Rp 135.130.911,00
IX PEKERJAAN FINISHING Rp 2.500.000,00

C UMUM (KESEAMATAN DAN KESEHATAN KERJA)


I PENYIAPAN RK3K Rp 120.000,00
II ALAT PELINDUNG KERJA Rp 3.298.800,00
III ASURANSI DAN PERJANJIAN Rp 2.000.000,00
IV PERSONIL K3 Rp 8.000.000,00
V FASILITAS SARANA KESEHATAN DAN KESELAMATAN Rp 1.904.000,00
VI LAIN-LAIN TERKAIT PENGENDALIAN RSIKO K3 Rp 1.981.850,00
REAL COST UNTUK 5 UNIT Rp 1.064.357.718,05
PPN 10% Rp 106.435.771,80
REAL COST + PPN 10% Rp 1.170.793.489,85
DIBULATKAN Rp 1.170.700.000,00
TERBILANG: SATU MILYARD SERATUS TUJUH PULUH JUTA TUJUH RATUS RIBU RUPIAH

Merauke, 2020
KONTRAKTOR PELAKSANA