Anda di halaman 1dari 2

RENCANA ANGGARAN BIAYA

PEKERJAAN : RUMAH TINGGAL BANTUAN PLN


LOKASI : KOTA KUPANG, NUSA TENGGARA TIMUR
TAHUN ANGGARAN : 2021

HARGA JUMLAH
NO URAIAN PEKERJAAN SATUAN VOLUME SATUAN HARGA
(Rp) (Rp)
1. 2. 3 4 5. 6.

I. PEKERJAAN PERSIAPAN
1 Pek. Pembersihan Lokasi Ls 1.00 150,000.00 150,000.00
2 pemasangan Bowplank M 40.00 3,182.50 127,300.00
3 Penyediaan Papan Cor Ls 1.00 250,000.00 250,000.00
4 Pek. Pengadaan Air Kerja Ls 1.00 150,000.00 150,000.00
5 Pemasangan Papan Proyek Ls 1.00 150,000.00 150,000.00
Total 827,300.00
II. PEKERJAAN GALIAN
1 Pek. Galian Tanah Pondasi M3 25.07 22,275.00 558,523.35
2 Pek. Urugan Kembali M3 6.27 5,830.00 36,545.36
3 Pek. Urugan Tanah Bawah Lantai M3 17.00 76,945.00 1,308,065.00
Total 1,903,133.71
III. PEKERJAAN PONDASI DAN BETON
1 Pek. Urugan Pasir M3 2.79 223,036.00 621,378.30
2 Pek. Aanstamping M3 5.57 60,126.00 335,022.07
3 Pek. Pondasi Batu Karang M3 15.67 421,855.50 6,611,003.00
4 Pek. Sloof 15/20 M3 1.39 2,746,101.71 3,825,319.68
3
5 Pek. Kolom Praktis 15/15 M 0.03 6,343,012.50 202,976.40
6 Pek. Ring Balk 15/20 M3 1.39 2,746,101.71 3,825,319.68
7 Pek.Plat Teras M3 0.50 1,059,538.70 533,159.87
8 Pek.Kolom Teras M3 0.54 1,575,211.00 850,613.94
Total 16,804,792.95
IV. PEKERJAAN PASANGAN
1 Pek. Pasangan Dinding Bata Faba + Gewel M2 195.06 35,898.50 7,002,361.41
2 Pek. Lubang Angin Bh 74.00 11,110.00 822,140.00
3 Pek. Plesteran M2 412.16 26,482.50 10,915,027.20
4 Pek. Acian M2 412.16 21,664.50 8,929,240.32
5 Pek. Urugan Pasir Peninggi Lantai 5cm M3 3.40 224,675.00 763,895.00
6 Pek. Keramik 40/40 M2 65.20 102,509.00 6,683,074.26
7 Pas. Keramik 20/20 M2 2.81 108,751.50 305,047.96
Total 35,420,786.14
V. PEKERJAAN KUSEN KAYU
1 Pek. Kusen Pintu Type P1 Unit 6.00 351,481.35 2,108,888.10
2 Pek. Pintu Type P2 Unit 1.00 340,481.35 340,481.35
3 Pek. Kusen Jendela Type j1 & j2 Unit 10.00 332,858.35 3,328,583.50
4 Pek. Daun Pintu Type P1 Unit 6.00 910,358.35 5,462,150.10
5 Pek. Daun Jendela + Kaca 5mm Unit 10.00 340,481.35 3,404,813.50
Total 14,644,916.55
VI. PEKERJAAN ATAP & PLAFOND
1 Pek. Balok Tarik 6/12 M3 0.24 3,089,821.35 744,819.98
2 Pek. Gording 6/12 M3 0.97 3,089,821.35 3,003,306.35
3 Pek. Seng Bjls 0.20 M2 100.80 65,820.00 6,634,656.00
4 Pek.List Plank GRC 0.2 M 40.32 61,094.00 2,463,310.08
5 Pek. Plafond M2 68.00 74,162.00 5,043,016.00
6 Pek. List Plafond M 81.90 18,071.35 1,480,043.57
Total 19,369,151.97
VII. PEKERJAAN INSTLS. AIR & LISTRIK
1 Pek. Pipa PVC 3/4" M 1.00 254,959.10 254,959.10
2 Pek. Kran Air 3/4" Bh 12.00 34,959.10 419,509.20
3 Pek. Instalasi Kabel NYA 2.5 M 1.00 150,403.00 150,403.00
4 Pek. Lampu Phillips SL 18 Watt Titik 10.00 78,210.00 782,100.00
5 Pek. Stop Kontak Bh 8.00 39,710.00 317,680.00
6 Pek. Saklar Tunggal Bh 3.00 39,710.00 119,130.00
7 Pek. Saklar Ganda Bh 3.00 50,710.00 152,130.00
8 Pek. Meteran Unit 1.00 227,623.00 227,623.00
9 Pek. MCB Unit 1.00 100,210.00 100,210.00
10 Pek. Pemasangan Closet Jongkok + Bak Air fiber Unit 1.00
Total 2,523,744.30
VIII. PEKERJAAN FINISHING
1 Pek. Plamir Tembok M2 412.16 3,333.00 1,373,729.28
2 Pek. Pengacatan Pondasi NoDrop (warna abu- M2 7.64 14,158.10 108,167.88
abu tua)
3 Pek. Pengacatan Tembok matex (Warna M2 412.16 7,287.50 3,003,616.00
putih)
4 Pek. Pengacatan kusen M2 8.00 11,253.00 90,024.00

5 Pek. Pengecatan Plafond M2 68.00 14,080.00 957,440.00


Total 5,532,977.16
IX. PEKERJAAN LAIN-LAIN
1 Pek. Septic Tank & Resapan Unit 1.00 1,426,294.49 1,426,294.49
2 Pek. Pembersihan Lokasi Kembali Ls 1.00 250,000.00 250,000.00
Total 1,676,294.49
JUMLAH TOTAL 98,703,097.27