RENCANA ANGGARAN BIAYA

KEGIATAN : PENGADAAN GENSET DAN RUMAH GENSET KAPASITAS 50 KVA


PEKERJAAN : PENGADAAN GENSET DAN RUMAH GENSET KAPASITAS 50 KVA
LOKASI : KOTA BAUBAU
TAHUN ANGGARAN : 2022

ANALISA JUMLAH HARGA


NO. URAIAN SATUAN VOLUME HARGA SATUAN (Rp)
SNI PASAL (Rp)
1 2 3 4 5 6 7
A PEKERJAAN PERSIAPAN
1 - Pengukuran dan Pemasangan Bowplank Ls 1.00 750,000.00 750,000.00
2 - Papan Nama Proyek Ls 1.00 350,000.00 350,000.00
3 - Administrasi dan Dokumentasi Ls 1.00 2,500,000.00 2,500,000.00
4 - Penyediaan Air Kerja Ls 1.00 1,000,000.00 1,000,000.00
5 - P3k Ls 1.00 5,000,000.00 5,000,000.00
Sub Total 9,600,000.00
B PEKERJAAN RUMAH GARDU
PEKERJAAN TANAH DAN PONDASI
1 Galian Tanah Keras M3 6.50 83,996.00 545,974.00
2 Pek. Pas. Batu Gunung 1 Pc : 5 Ps M3 6.50 897,833.75 5,835,919.38
3 Urugan Tanah di datangkan M3 17.50 98,756.25 6,962,710.65
4 Urugan Pasir Bawah Lantai M3 0.50 404,742.50 202,371.25
Sut Total 13,546,975.28
PEKERJAAN BETON
1 Pek. Lantai Kerja 1 Pc : 3 Ps : 5 Kr M3 0.13 1,009,096.25 131,182.51
2 Pondasi Poer Plat 1 Pc : 2 Ps : 3 Kr M3 0.35 4,900,581.25 1,715,203.44
3 Pek. Kolom (K1) 25 x 25 cm, 1 Pc : 2 Ps : 3 Kr M3 0.22 6,223,840.25 1,369,244.86
4 Pek. Sloof 15 x 25 cm, 1 Pc : 2 Ps : 3 Kr M3 0.55 6,022,935.25 3,312,614.39
5 Pek. Kolom (K2) 20 x 20 cm, 1 Pc : 2 Ps : 3 Kr M3 0.66 7,031,485.25 4,640,780.27
6 Pek. Kolom (K3) 15 x 15 cm, 1 Pc : 2 Ps : 3 Kr M3 0.19 6,936,265.25 1,317,890.40
7 Pek. Plat Lantai Beton T = 10 cm, 1 Pc : 2 Ps : 3 Kr M3 2.45 6,864,206.25 16,817,305.31
8 Rabat Lantai Keliling 1 : 3 : 5 M3 0.40 1,116,575.25 446,630.10
9 Pek. Ring Balok (RB1) 15 x 25 cm, 1 Pc : 2 Ps : 3 Kr M3 0.40 7,349,604.00 2,939,841.60
10 Pek. Dak Beton T = 12 cm, 1 Pc : 2 Ps : 3 Kr M3 2.41 6,864,206.25 16,542,737.06
Sub Total 49,233,429.93
PEKERJAAN DINDING
1 Pek. Pas. Batu Bata 1/2 Bata 1 : 5 M2 35.50 128,593.00 4,565,051.50
2 Pek. Plesteran Dinding 1 Pc : 5 Ps M2 50.00 60,203.65 3,010,182.50
3 Pek. Plesteran Pondasi 1 Pc : 5 Ps M2 12.50 63,726.10 796,576.25
4 Pek. Acian Tembok M2 86.50 34,298.75 2,966,841.88
Sub Total 11,338,652.13
PEKERJAAN PINTU DAN VENTILASI
1 Besi Siku 50/50/5 Kg 90.20 35,862.75 3,234,820.05
2 Pipa Air Hujan PVC dia 2" Btg 4.00 63,000.00 252,000.00
3 Pas. Pintu Plat Baja 2mm M2 4.00 874,672.75 3,498,691.00
4 Pas. Ventilasi Besi M2 3.15 645,748.00 2,034,106.20
Sub Total 9,019,617.25
PEKERJAAN PENGECETAN
1 Cat Dinding Luar Dalam M2 176.20 15,070.75 2,655,466.15
Sub Total 2,655,466.15
JUMLAH 85,794,140.73
C Material NON MDU
1 Generator Set 50 KVA Unit 1.00 32,000,000.00 32,000,000.00
2 Motor Rizer 50 KVA Set 1.00 25,000,000.00 25,000,000.00
3 Kabel NYY 4 x 25mm Mtr 80.00 275,000.00 22,000,000.00
Sub Total 93,200,600.00
REKAPITULASI ANGGARAN BIAYA

KEGIATAN : PENGADAAN GENSET DAN RUMAH GENSET KAPASITAS 50 KVA


PEKERJAAN : PENGADAAN GENSET DAN RUMAH GENSET KAPASITAS 50 KVA

LOKASI : KOTA BAUBAU


TAHUN ANGGARAN : 2022

NO. URAIAN PEKERJAAN JUMLAH HARGA (Rp)

I PEKERJAAN PERSIAPAN 9,600,000.00

II PEKERJAAN RUMAH GARDU 85,794,140.73

III Material NON MDU 93,200,600.00

JUMLAH ( I + II + III + IV) 188,594,740.73

PPN 11% 20,745,421.48

TOTAL NILAI 209,340,162.21

DIBULATKAN 209,300,000.00

Terbilang : Dua Ratus Sembilan Juta Tiga Ratus Ribu Rupiah