IV PEKERJAAN BETON
1 Pek. Lantai Beton Tumbuk 1:2:3 M³ 11.76 1,864,856.00
2 Pek. Kolom 25/25 M³ 2.75 2,671,486.59
3 Pek. Sloef 25/25 M³ 2.31 2,671,486.59
4 Pek. Ring Balk 25/25 M³ 2.31 2,671,486.59
v PEKERJAAN BEKESTING
1 Bekisting Pekerjaan Kolom M² 51.04 381,371.20
2 Bekisting Pekerjaan Ring Balk M² 27.75 391,451.20
3 Bekisting Pekerjaan Sloef M² 18.50 302,803.20
VI PEKERJAAN PEMBESIAN
1 Pek. Pembesian Besi Polos Ø8 Kg 694.19 29,191.08
2 Pek. Pembesian Besi Polos Ø12 Kg 1,245.67 35,263.69
XV PEKERJAAN AKHIR
1 Pembershan Akhir Ls 1.00 3,000,000.00
JUMLAH HARGA
1,100,000.00
2,500,000.00
3,928,512.00
1,200,000.00
8,728,512.00
3,994,152.96
8,388,878.40
9,737,172.00
63,613.09
3,823,344.00
1,257,455.36
27,264,615.81
6,454,893.31
35,892,511.20
4,568,382.00
29,237,644.80
8,622,213.60
22,785,162.40
107,560,807.31
21,930,706.56
7,346,588.12
6,171,134.02
6,171,134.02
41,619,562.73
19,465,186.05
10,862,770.80
5,601,859.20
35,929,816.05
20,264,155.83
43,926,920.72
64,191,076.55
1,824,345.60
14,252,700.00
12,995,841.60
2,488,180.80
7,237,130.26
2,880,729.60
41,678,927.86
41,135,963.68
23,304,601.60
64,440,565.28
52,655,625.79
3,006,976.00
1,182,899.20
56,845,500.99
262,752.00
431,054.40
927,393.60
1,391,090.40
76,451.20
591,057.60
3,679,799.20
33,867,792.00
6,356,750.40
17,931,317.04
2,643,158.34
9,735,313.22
70,534,331.00
18,195,268.00
2,701,961.14
9,031,790.88
29,929,020.02
304,640.00
1,666,560.00
308,000.00
120,000.00
90,000.00
146,720.00
6,199,200.00
120,000.00
15,000.00
8,970,120.00
500,000.00
500,000.00
350,000.00
700,000.00
1,500,000.00
1,500,000.00
5,050,000.00
3,000,000.00
3,000,000.00
REKAPITULASI RKB SMA YPK EBENHEYZER SARMI
626,210,000
154,920