RENCANA USULAN

ENGINEERING ESTIMATE ( E E )

PEKERJAAN :
PEMBANGUNAN TOILET

BIAYA :
Rp. 102.150.000,00

TAHUN ANGGARAN
2022
RENCANA USULAN
REKAPITULASI
DAFTAR KUANTITAS DAN HARGA

JUMLAH HARGA
NO ITEM PEKERJAAN
Rp

I PEKERJAAN PERSIAPAN 2,750,000.00


II PEK. TANAH DAN URUGAN 2,987,098.00
III PEK. PASANGAN DAN PLESTERAN 28,948,088.00
IV PEK. BETON BERTULANG 1 PC : 2 PSR : 3 KRKL 14,044,307.00
V PEK. KUSEN PINTU DAN JENDELA 8,845,756.00
VI PEKERJAAN ATAP DAN PLAFOND 9,957,520.00
VII PEK. PENGANTUNG DAN PENGUNCI 1,429,534.00
VIII PEKERJAAN LISTRIK -
IX PEK. LANTAI DAN PASANGAN KERAMIK 1,419,787.00
X PEK. SEPTICTANK DAN PERESAPAN (1 UNIT) 12,787,423.00
XI PEK. PLUMBING/SANITAIR WARE 3,993,425.00
XII PEKERJAAN PENGECATAN 4,864,221.00
I JUMLAH I S/D XI 92,027,159.00
II PPN 11% x I 10,122,987.00
III TOTAL ( I + II ) 102,150,146.00
IV DIBULATKAN 102,150,000.00
TERBILANG : SERATUS DUA JUTA LIMA RATUS RIBU RUPIAH
RENCANA USULAN
DAFTAR KUANTITAS DAN HARGA

Harga Satuan Jumlah Harga


No. Item Pekerjaan Sat Volume
Rp Rp
I PEKERJAAN PERSIAPAN
1 Pengukuran,Pembersihan Lahan dan Pemasangan Bouwplank Ls 1.000 750,000.00 750,000.00
2 Penyediaan Air Bersih + Air Kerja Ls 1.000 1,000,000.00 1,000,000.00
3 Papan Nama Proyek Ls 1.000 250,000.00 250,000.00
4 Pembuatan Barak Kerja Gudang Sementara Ls. 1.000 750,000.00 750,000.00
JUMLAH 2,750,000.00
II PEK. TANAH DAN URUGAN
1 Pek. Galian Tanah Pondasi m³ 9.750 75,784.50 738,898.88
2 Pek. Urugan Tanah Kembali Bekas Galian m³ 3.250 55,649.00 180,859.25
3 Pek. Urugan Pasir dibawah Lantai m³ 1.711 388,165.80 664,248.73
4 Pek. Urugan Tanah Pilihan m³ 5.795 242,121.00 1,403,091.20
JUMLAH 2,987,098.00
III PEK. PASANGAN DAN PLESTERAN
1 Pek. Pasangan Anstamping/ Batu Kosong m³ 2.250 531,459.06 1,195,782.89
2 Pek. Pas. Batu Pondasi Camp. 1Ps : 4 Psr m³ 10.895 937,499.20 10,213,585.03
3 Pek. Pas. Tembok Bata Camp. 1Ps : 5 Psr m³ 51.346 120,411.28 6,182,589.42
4 Pek. Plesteran Dinding Tembok 1Pc : 5 Psr ( t= 15 mm ) m² 102.691 69,739.21 7,161,602.96
5 Pek. Acian Dinding Tembok + Kolom m² 102.691 40,846.03 4,194,527.32
JUMLAH 28,948,088.00
IV PEK. BETON BERTULANG 1 PC : 2 PSR : 3 KRKL
1 Pek. Coran Sloof 15/20 cm m³ 0.990 4,309,390.18 4,266,296.28
2 Pek. Coran Ring Balk 12/20 cm m³ 0.600 5,073,400.25 3,044,040.15
3 Pek. Coran Balok Gewel 12/20 cm m³ 0.288 5,073,400.25 1,461,139.27
4 Pek. Coran Kolom Praktis 12/12 cm m1 21.00 106,499.58 2,236,491.18
5 Pek. Kolom Teras 20/20 cm m³ 0.336 5,471,927.38 1,838,567.60
6 Pek. Balok Teras 15/20 cm m³ 0.240 4,990,719.12 1,197,772.59
JUMLAH 14,044,307.00
V PEK. KUSEN PINTU DAN JENDELA
1 Pek. Kusen Pintu, Jendela dan Boven 6/12 cm Kayu Jati Lokal m³ 0.258 11,092,328.50 2,859,158.59
2 Pek. Daun Pintu Panil Papan Jati Lokal m² 3.280 830,720.00 2,724,761.60
3 Pek. Daun Pintu Panil Papan Jati Lokal (Lapis Sing Plat) m² 3.280 867,351.10 2,844,911.61
4 Pek. Pas. Kaca Mati /Ventilasi Bening 5 mm m² 1.126 370,401.74 416,924.19
JUMLAH 8,845,756.00
VI PEKERJAAN ATAP DAN PLAFOND
1 Pek. Kuda - Kuda 6/12 cm (Kayu Mahoni) m³ 0.217 7,414,572.00 1,612,224.54
2 Pek. Gording 6/8 cm (Kayu Mahoni) m³ 0.348 6,449,330.80 2,247,462.80
3 Pek. Lisplank 3/20 cm (Kayu Mahoni) m' 25.200 90,410.98 2,278,356.70
4 Pek. Atap Seng Gelombang BJLS 0.20 mm (Gajah Duduk Fumira) m² 43.500 72,542.36 3,155,592.66
5 Pek. Atap Bubungan Zing Plat BJLS 0.20 m' 5.800 62,738.50 363,883.30
6 Pas. Besi Angker Ls 1.000 100,000.00 100,000.00
7 Pas. Mur Baut Ls 1.000 100,000.00 100,000.00
8 Pas. Beugel Besi Ls 1.000 100,000.00 100,000.00
JUMLAH 9,957,520.00
VII PEK. PENGANTUNG DAN PENGUNCI
1 Pas. Hengsel Pintu Psg 6.000 45,514.52 273,087.14
2 Pas. Grendel Pintu KM/WC Bh 4.000 27,037.89 108,151.56
3 Pas. Kunci Tanam Dua Kali Putar (KM/WC) Bh 4.000 262,073.90 1,048,295.60
JUMLAH 1,429,534.00
VIII PEK. LANTAI DAN PASANGAN KERAMIK
1 Pek. Rabat Lantai Camp 1Pc : 3 Psr 5Krl, t = 5 cm m³ 1.198 1,185,254.95 1,419,787.27
JUMLAH 1,419,787.00
IX PEK. SEPTICTANK DAN PERESAPAN (1 UNIT)
1 Pek. Galian Tanah m³ 7.243 93,248.10 675,349.36
2 Pek. Pasangan Batu 1pc : 5psr m³ 2.736 937,499.20 2,564,997.81
3 Pek. Pas. Batako 1pc : 5psr m² 16.358 120,411.28 1,969,627.51
4 Pek. Beton Penutup Septictank + Resapan 1pc : 2psr : 3klr T 12 cm m³ 0.693 6,327,270.66 4,384,798.57
5 Pek. Coran Beton Kolom 15/15 cm 1pc : 2psr : 3klr m³ 0.018 6,896,876.04 124,143.77
6 Pek. Coran Beton Balok 15/15 cm 1pc : 2psr : 3klr m³ 0.030 4,990,719.12 151,593.09
7 Pek. Coran Rabat Beton 1pc : 3psr : 5krl m³ 0.270 1,185,254.95 320,018.84
8 Pek. Plesteran 1pc : 5psr m³ 20.040 69,739.21 1,397,573.73
9 Pek. Acian m³ 20.040 40,846.03 818,554.34
10 Pek. Urugan Sirtu m³ 0.365 388,165.80 141,486.43
11 Pek. Urugan Batu m³ 0.365 531,459.06 193,716.83
12 Pek. Lapisan Ijuk m³ 0.365 125,000.00 45,562.50
JUMLAH 12,787,423.00
X PEK. PLUMBING/SANITAIR WARE
1 Pas. Pipa Limbah PVC 4" M 8.000 102,495.09 819,960.68
2 Pas. Pipa Air Bersih PVC 1/2" M 20.000 44,124.96 882,499.20
3 Pas. Pipa Hawa GIP 2'' (Komplit Angker) Bh 1.000 250,000.00 250,000.00
4 Pas. Kran Air 1/2 " Bh 3.000 30,845.65 92,536.95
5 Pas. Floor Drain Alumenium KM/WC Bh 3.000 41,226.90 123,680.70
6 Pas. Pipa PVC 2.5" Dari Floor Drain M 3.000 59,531.84 178,595.51
7 Pas. Kloset Jongkok Bh 2.000 688,076.00 1,376,152.00
8 Pengadaan Tong Air Bh 2.000 85,000.00 170,000.00
9 Tambahan Material Kecil Bh 1.000 100,000.00 100,000.00
JUMLAH 3,993,425.00
XI PEKERJAAN PENGECATAN
1 Pek. Cat Lisplank & List Plafont m² 6.048 33,506.55 202,647.61
2 Pek. Cat Tembok+ Plamir (Cat Ex.Paragon Cream Susu) m² 108.421 30,515.19 3,308,493.30
3 Pek. Politur Kusen m² 18.032 75,037.71 1,353,079.99
JUMLAH 4,864,221.00
JUMLAH TOTAL 92,027,159.00
B DAFTAR HARGA SATUAN BAHAN
SA Harga Lokasi
NO TU Proyek
NAMA BAHAN
AN Dibulatkan
(Rp)
A BAHAN LOKAL
1 Batu Belah 10 - 15 cm M3 191,900.00
2 Batu Belah 2 - 3 cm M3 466,700.00
3 Bataco Bh 3,300.00
4 Bata Merah Bh 1,500.00
5 Bata Bunga/ Loster Uk. 10 x 30 cm Bh 30,200.00
6 Batu Kali/Batu Gunung 15/20 M3 188,800.00
7 Kayu Dolken Btg 15,200.00
8 Paving Blok Segi Enam Tbl 6 cm Bh 3,700.00
9 Kayu Kelas I Kayu Jati Lokal M3 5,875,500.00
10 List Plafon Profil Kayu Rimba Campuran M' 10,100.00
11 Kayu Kelas II Kayu Mahoni M3 4,172,800.00
12 Kayu Rimba Campuran (Ngancar, Nara, Aseng, Rumung, Munting, Loi, Natu, M3 3,983,800.00
Maras dan Pante)
13 Kayu Klas IV (Kayu Kapuk, Waek, Sita) M3 2,521,200.00
14 Pasir Beton M3 263,600.00
15 Pasir Pasang M3 263,600.00
16 Pasir Urug M3 263,600.00
17 Krikil Hasil Ayakan M3 263,600.00
18 Sirtu M3 263,600.00
19 Ijuk Lbr 25,000.00
20 Urugan Pilihan / Tanah Cadas M3 133,100.00
21 Timbunan Tanah M3 97,100.00
B BAHAN NON LOKAL
1 Angker Bh 10,000.00
2 Besi Strip Kg 15,000.00
3 Batu Hias Alam M2 246,200.00
4 Besi Polos Kg 12,000.00
5 Besi Ulir Kg 13,500.00
6 Cat Kayu Kwalitas Baik (Cat Plibest No. 924 M) Kg 55,000.00
7 Cat Plafont Setara Viteks Kg 12,500.00
8 Cat Dinding Tembok Cat Paragon No………….. Kg 21,800.00
9 Dumpul/plamir Kg 20,000.00
10 Gerendel Jendela Bh 7,500.00
11 Gerendel Pintu Bh 12,000.00
12 Hengsel 110 x 55 Psg 25,000.00
13 Hengsel 88 x 55 Psg 45,000.00
14 Hendel Jendela. Bh 7,500.00
15 Kaca Bening 3 mm M2 125,800.00
16 Kaca Bening 5 mm M2 165,800.00
17 Kaca Reben 3 mm M2 163,800.00
18 Kaca Reben 5 mm M2 198,300.00
19 Kait Angin Psg 14,000.00
20 Kawat Beton/ikat Kg 24,500.00
21 Kawat Las Kg 50,000.00
22 Kunci Tanam "Jangkar" Set 285,000.00
23 Kunci Tanam "Paori" Set 255,000.00
24 Kunci Tanam "Yalle " Set 175,000.00
25 Kwas Kayu 4 inch BH 7,500.00
26 Roll Kuas BH 22,600.00
27 Lem Kayu Kg 17,500.00
28 Menie Kg 20,000.00
29 Minyak Bekisting Ltr 7,700.00
30 Minyak Cat Ltr 10,500.00
31 Paku Seng Kg 40,000.00
32 Paku Ukuran 1 cm Kg 26,700.00
33 Paku Ukuran 1,5 cm Kg 26,700.00
34 Paku Ukuran 2 cm Kg 26,700.00
35 Paku Ukuran 2,5 cm Kg 26,700.00
36 Paku Ukuran 3 cm Kg 22,700.00
37 Paku Ukuran 5-10 cm Kg 18,700.00
38 Pipa 5/8 " Btg 9,500.00
39 Politur Kg 56,000.00
40 Semen (40 Kg) Zak 55,800.00
41 Semen warna Kg 2,500.00
42 Seng Gelomban BJLS 0.2 Lbr 65,000.00
43 Seng Plat BJLS 0.2 M' 25,000.00
44 Tripleks 3 mm Lbr 55,000.00
45 Tripleks 5 mm ( 4.7 mm ) Lbr 90,000.00
46 Tripleks 9 mm Lbr 155,000.00
47 Teak Oil Liter 5,000.00
48 Viber Glas 1100 LTR Bh 2,224,400.00
49 Wastafel KIA Komplit Bh 651,200.00
50 Bak Cuci Satinless Steel M' 350,400.00
51 Pipa GIP 1/2" Medium B M' 17,500.00
52 Pipa GIP 3/4 " Medium B M' 24,200.00
53 Pipa GIP 1" Medium B M' 42,600.00
54 Pipa GIP 2 " Medium B M' 87,600.00
55 Keramik Uk 40 x 40 cm (Polos) Dos/M2 75,700.00
56 Keramik Uk 40 x 40 cm (Anti Slip) Dos/M2 75,700.00
57 Keramik Uk 20 x 20 cm Dos/M2 75,700.00
58 Keramik Uk 20 x 25 cm Dos/M2 75,700.00
59 Keramik Uk 10 x 40 cm Bh 12,600.00
60 Kloset Jongkok ( INA STANDAR ) Bh 301,200.00
61 Kloset Duduk (Tampa Tabung) Bh 651,700.00
62 Floor Draine Standar Bh 20,000.00
63 Floor Drain Alumenium KM/WC Bh 22,000.00
64 Kran Air Biasa Ø 3/4" Bh 12,500.00
65 Pipa PVC 1/2" Btg 22,000.00
66 Pipa PVC 3/4" Btg 42,000.00
67 Pipa PVC 1 3/4" Btg 55,000.00
68 Pipa PVC 4" Btg 210,100.00
69 Pipa PVC 2 " Btg 125,500.00
70 Isolasi Pipa/Seal Tape BH 2,000.00
71 Pipa Hawa GIP 2'' Tg 1.5 m (Komplit Angker) Bh 250,000.00
72 Socket Boog PVC 4" Bh 22,000.00
73 Socket Boog PVC 2" Bh 15,000.00
74 Socket Boog PVC 1.25" Bh 9,000.00
75 Socket Tee PVC 2"-4" Bh 22,000.00
76 Socket Tee PVC 1.25"-4" Bh 20,000.00
77 Socket Boog PVC 3/4" Bh 4,500.00
78 Socket Tee PVC 3/4" Bh 4,500.00
79 Bak Air Viber Glas Bh 450,800.00
80 Tong Air Bh 85,000.00
81 Dinamo Isap Air Unit 750,400.00
82 Wood Filler Kg 28,000.00
83 Sending Sealer Kg 43,000.00
84 Thinner Kg 25,000.00
85 Melamic Paint Kg
86 Amplas Lbr 5,000.00
87 Wood Stain M2 47,700.00
88 Embousdos ( Listrik ) Bh 6,000.00
89 Baja Ringan / Main truss C - 75 - 75 Klas A M' 16,700.00
90 Plat Diagrama Bh 36,000.00
91 Roof Bottom/Reng 33 - 0.45 Klas A M' 8,300.00
92 Top Plat/Mur Plate Bh 2,500.00
93 Dinabolt/Ramset dia 12 x 120 mm Klas A Bh 3,000.00
94 Self drilling screw dia 6 x 20 mm ( truss screw ) Klas A Bh 1,000.00
95 Self drilling screw dia 4 x 16 mm ( Roof bottom ) Klas A Bh 500.00
96 Alat bantu ( Mesin Bor Listrik) Genset Jam 7,500.00
97 Alumanium Foil/Sisalation Klas A M' 50,000.00
98 Papan Kalsiplang Board tebal 12 MM M' 35,400.00
99 Papan Kalsiumboard Dinding Partisi tebal 4 mm Lbr 80,200.00
100 Gypsum Elephant tebal 9 MM Lbr 85,200.00
101 Paku skrup Gypsum Kg 100,000.00
102 Paku skrup Gypsum Bh 100.00
103 List Gypsum TYPE 12/15 cm M' 16,000.00
104 List Gypsum TYPE 5/7 cm M' 14,000.00
105 List Gypsum TYPE B5 ( 3/5 ) cm M' 14,000.00
106 Cedowline ( ending plafond ) M' 20,000.00
107 Hollow 40/40 Zincoromate M' 12,500.00
108 Hollow 20/40 Zincoromate M' 7,500.00
109 Conctrete Bracket/ Angle Clip M' 3,700.00
110 Rod Hanger dm 5 mm Bh 5,000.00
111 Ramset/Dinabolt Bh 3,000.00
112 Skrup Metal Bh 100.00
113 Compon Kg 11,500.00
114 Colton Plaster Bh 14,000.00
115 Tepung Gypsum Kg 2,200.00
116 Wall Flashing ( rainbow roof ) M' 80,000.00
117 Kusen Aluminium Alexindo/setara 5/10 '' M' 113,400.00
118 Profil Kaca ( aluminium ) M' 80,000.00
119 Rangka Alumunium 30/70 -100 MM M' 96,700.00
120 Rangka metal stud (MS 100) uk.100 x 34 mm M' 96,700.00
121 Rangka U runner (U 100) uk.100 x 30 mm M' 100,100.00
122 Paku rivet Bh 500.00
123 Sekrup F i s e r 3" Bh 1,000.00
124 Alat Sambung Bh 2,500.00
125 Silikon/sealant Bh 40,000.00
126 Biaya Pemasangan Instalasi kabel NYM Titik 150,000.00
127 KabelListrik NYM 3 x 2.5 mm ( Standart PLN ) M' 15,700.00
128 Kabel Listrik NYM 2 x 2.5 mm ( Standart PLN ) M' 12,700.00
129 Saklar Tunggal Bronco Super Bh 13,500.00
130 Saklar Ganda Bronco Super Bh 15,000.00
131 Stop Contak Bronco Super Bh 15,000.00
132 Fitting Tanam Bh 70,000.00
133 Lampu Jari 18 Watt (Phillips) Bh 45,000.00
134 Fiting Gantung/Tempel Bh 7,700.00
135 Sikring 6 - 16 A MCB Broco Bh 17,500.00
136 Lampu Jari 11 Watt (Philips) Bh 45,000.00
137 Saklar Tunggal Bh 15,000.00
138 Saklar Ganda Bh 17,500.00
139 Stop Contak Bh 12,500.00
140 L Bow Bh 10,000.00
141 Las dop Bh 2,000.00
142 MCB 25 Amper + Box Bh 170,000.00
143 Meni Besi Kg 10,000.00
144 Solar Ltr 6,400.00
145 Bensin Ltr 7,300.00
146 Pelumas Ltr 30,000.00
Harga Tersebut Sudah Termasuk Ongkos Angkut dan Pungutan Pajak Resmi Lainnya
A DAFTAR HARGA SATUAN UPAH

NO UPAH SATUAN HARGA SATUAN ( RP )

1 Mandor Lapangan OH 139,800.00


2 Kepala Tukang OH 139,800.00
3 Tukang Besi Konstruksi OH 125,100.00
4 Tukang Tulangan OH 125,100.00
5 Tukang Cat OH 125,100.00
6 Tukang Batu OH 125,100.00
7 Tukang Listrik OH 125,100.00
8 Pekerja OH 87,200.00
9 Sopir Jam 19,971.43
10 Pembatu Sopir Jam 17,871.43
11 Mekanik Jam 19,971.43
12 Pembantu Mekanaik Jam 17,871.43