Anda di halaman 1dari 3

REKAPITULASI

KEGIATAN : PEMBANGUNAN 1 RUANG KELAS BARU


LOKASI : MI DDI BABUSSALAM
KAB. - PROPINSI : BIAK NUMFOR - PAPUA
TAHUN ANGGARAN : 2018

NO URAIAN PEKERJAAN HARGA

A PEKERJAAN PERSIAPAN Rp. 2,523,360.00


B PEKERJAAN TANAH Rp. 1,657,468.40
C PEKERJAAN PASANGAN Rp. 33,860,641.50
D PEKERJAAN PLESTERAN Rp. 19,127,322.10
E PEKERJAAN BETON Rp. 57,760,060.07
F PEKERJAAN KUSEN, PINTU/JENDELA Rp. 20,076,639.00
G PEKERJAAN RANGKA ATAP/KAP Rp. 54,504,650.33
H PEKERJAAN PLAFON Rp. 30,719,510.00
I PEKERJAAN LANTAI Rp. 24,421,485.00
J PEKERJAAN PENUTUP ATAP / SENG Rp. 12,352,200.00
K PEK. PENGGANTUNG DAN PENGUNCI Rp. 2,033,900.00
L PEKERJAAN INSTALASI LISTRIK Rp. 2,746,000.00
M PEKERJAAN PENGECETAN Rp. 18,220,124.80

JUMLAH Rp. 280,003,361.20


DI BULATKAN Rp. 280,000,000.00

Terbilang : "Dua ratus delapan puluh juta rupiah"

Biak, 30 Oktober 2017


KEPALA MADRASAH

M. SAIFUDDIN RAMADAN, S.Th. I


RENCANA ANGGARAN BIAYA ( RAB )

KEGIATAN : PEMBANGUNAN 1 RUANG KELAS BARU


LOKASI : MI DDI BABUSSALAM
KAB. - PROVINSI : BIAK NUMFOR - PAPUA
TAHUN ANGGARAN : 2018

NO URAIAN PEKERJAAN VOL. SATUAN HARGA JUMLAH


SATUAN HARGA
A PEKERJAAN PERSIAPAN
1 Pembersihan lapangan dan peralatan 14.000 m2 7,500.00 105,000.00
2 Uitzeit Bouwplank 42.000 m' 57,580.00 2,418,360.00
Jumlah 2,523,360.00
B PEKERJAAN TANAH
1 Galian tanah pondasi 1.280 m3 31,750.00 40,640.00
2 Urugan tanah kembali 1.280 m3 10,580.00 13,542.40
3 Urugan tanah baru m3 67,000.00 -
4 Urugan pasir bawah pondasi 0.080 m3 96,700.00 7,736.00
5 Urugan pasir bawah lantai 16.500 m3 96,700.00 1,595,550.00
Jumlah 1,657,468.40
C PEKERJAAN PASANGAN
1 Aanstampeng 0.240 m3 209,610.00 50,306.40
2 Pondasi batu kali 1pc : 3 Kpr : 10 ps 1.280 m3 420,180.00 537,830.40
3 Pasangan trasram 1pc : 4ps 18.490 m2 506,430.00 9,363,890.70
4 Pas. Bata merah 1pc : 3kpr : 10 ps 227.600 m2 63,660.00 14,489,016.00
5 Pas. Bata rollag 1pc : 4ps (teras) 18.600 m2 506,430.00 9,419,598.00
Jumlah 33,860,641.50
D PEKERJAAN PLESTERAN
1 Plesteran dinding 1pc : 2 Kpr : 8 ps 455.200 m2 30,420.00 13,847,184.00
2 Plesteran trasram 1pc : 4ps 36.980 m2 32,120.00 1,187,797.60
3 Plesteran beton 1pc : 2ps 44.550 m2 36,910.00 1,644,340.50
4 Benangan 306.000 m' 8,000.00 2,448,000.00
Jumlah 19,127,322.10
E PEKERJAAN BETON
1 Sloof 15/20 2.280 m3 4,214,480.00 9,609,014.40
2 Kolom 15/25 1.793 m3 6,780,330.00 12,153,741.53
3 Kolom 15/15 1.170 m3 6,780,330.00 7,932,986.10
4 Balok latai 12/15 0.585 m3 5,133,780.00 3,003,261.30
5 Ring balok 15/20 1.688 m3 5,133,780.00 8,663,253.75
6 Beton gevel + konsol 15/20 1.260 m3 6,780,330.00 8,543,215.80
7 Plat tangga 1.158 m3 6,780,330.00 7,854,587.19
Jumlah 57,760,060.07
F PEKERJAAN KUSEN, PINTU/JENDELA
1 Kusen kamper 6/15 1.280 m3 10,646,350.00 13,627,328.00
3 Daun pintu panil kamper 3.066 m2 552,500.00 1,693,965.00
4 Daun jendela rangka kaca ky. Kamper 5.200 m2 381,180.00 1,982,136.00
5 Jalusi kayu kamper 1.900 m2 653,400.00 1,241,460.00
6 Kaca polos 5 mm 27.850 m2 55,000.00 1,531,750.00
Jumlah 20,076,639.00
G PEKERJAAN RANGKA ATAP/KAP
1 Kuda-kuda, konsol ikatan angin ky. Krui 1.983 m3 7,183,910.00 14,245,693.53
2 Gording 8/12 , nok, jurai ky. Kruing 1.920 m3 6,777,540.00 13,012,876.80
3 Usuk kruing 5/7 reng kamper 2/3 260.000 m2 69,280.00 18,012,800.00
4 Papan lisplank 3/25 kamper 66.000 m2 103,880.00 6,856,080.00
5 Papan reuter 2/20 20.000 m' 26,360.00 527,200.00
6 Pas. papan kompres lapis seng 26.000 m' 50,000.00 1,300,000.00
7 Mur baut 1.000 ls 550,000.00 550,000.00
Jumlah 54,504,650.33
H PEKERJAAN PLAFON
1 Pasangan rangka plafond 233.000 m2 75,000.00 17,475,000.00
2 Pasangan kalsiboard 3.5 mm 233.000 m2 33,970.00 7,915,010.00
3 Pasangan list gypsum 190.000 m' 28,050.00 5,329,500.00
Jumlah 30,719,510.00
I PEKERJAAN LANTAI
1 Rabat beton t. 5 Cm 11.500 m3 503,030.00 5,784,845.00
2 Keramik lantai 30x30 polos 176.000 m2 105,890.00 18,636,640.00
Jumlah 24,421,485.00
NO URAIAN PEKERJAAN VOL. SATUAN HARGA JUMLAH
SATUAN HARGA
J PEKERJAAN PENUTUP ATAP
1 Pas. Seng gelombang 260.000 m2 41,950.00 10,907,000.00
2 Pas. seng Plat 20.000 m' 72,260.00 1,445,200.00
Jumlah 12,352,200.00
K PEK. PENGGANTUNG & PENGUNCI
1 Pas. Kunci tanam 2 x putar 2.000 buah 72,590.00 145,180.00
2 Pas. Engsel pintu 6.000 buah 22,220.00 133,320.00
3 Pas. Grendel pintu tanam 4.000 buah 29,400.00 117,600.00
4 Pas. Engsel jendela 40.000 buah 13,610.00 544,400.00
5 Pas. Grendel jendela 20.000 buah 17,720.00 354,400.00
6 Pas. Hak angin 40.000 buah 18,475.00 739,000.00
Jumlah 2,033,900.00
L PEKERJAAN LISTRIK
1 Penyambungan listrik (overspaneng) 1.000 ls 250,000.00 250,000.00
2 Pasangan instalasi titik lampu 16.000 titik 128,000.00 2,048,000.00
3 Pasangan Instalasi + stopkontak 2.000 titik 34,250.00 68,500.00
4 Pasangan Lampu SL 18 W ex. Philips 8.000 buah 23,990.00 191,920.00
5 MCB 1.000 unit 187,580.00 187,580.00
Jumlah 2,746,000.00
M PEKERJAAN PENGECATAN
1 Cat dinding exterior 168.060 m2 22,220.00 3,734,293.20
2 Cat dinding interior 341.250 m2 15,960.00 5,446,350.00
3 Cat kayu 166.920 m2 29,480.00 4,920,801.60
4 Cat plafond 233.000 m2 15,960.00 3,718,680.00
5 Ter rangka atap 1.000 ls 400,000.00 400,000.00
Jumlah 18,220,124.80

Biak, 30 Oktober 2017


KEPALA MADRASAH

M. SAIFUDDIN RAMADAN, S.Th. I