IV PEKERJAAN DINDING
6.11 A. Pasangan Tembok ½ Bata 1Pc:4Ps (Trasraam) (m ²)
SNI 03-2835-2002 Bahan
Bata Merah 5 X 11 X 22 cm Bh 70.000 500.00 35,000.00
Semen Portland Kg 11.500 1,300.00 14,950.00
Pasir Pasang M³ 0.043 75,000.00 3,225.00
Tenaga
Pekerja Oh 0.320 100,000.00 32,000.00
Tukang Batu Oh 0.100 100,000.00 10,000.00
Kepala Tukang Oh 150,000.00 -
Mandor Oh 150,000.00 -
Sub Total 95,175.00
6.15 B. Pasangan Tembok ½ Bata 1Pc:3Kp:10Ps (m ²)
SNI 03-2835-2002 Bahan
Bata Merah 5 X 11 X 22 cm Bh 70.000 500.00 35,000.00
Semen Portland Kg 4.500 1,300.00 5,850.00
Pasir Pasang M³ 0.050 75,000.00 3,750.00
Kapur Padam M³ 0.015 15,000.00 225.00
Tenaga
Pekerja Oh 0.320 100,000.00 32,000.00
Tukang Batu Oh 0.100 100,000.00 10,000.00
Kepala Tukang Oh 150,000.00 -
Mandor Oh 150,000.00 -
Sub Total 86,825.00
IX PEKERJAAN PLAFON
6.19 A. Pasang List Langit-langit Kayu Profil (m ¹)
SNI 03-2835-2002 Bahan
Kayu Profil M¹ 1.100 10,000.00 11,000.00
Paku plafon Kg 0.010 10,000.00
Tenaga
Pekerja Oh 0.050 100,000.00 5,000.00
Tukang Kayu Oh 0.050 100,000.00 5,000.00
Kepala Tukang Oh 0.005 100,000.00 500.00
Mandor Oh 0.003 150,000.00 450.00
Sub Total 21,950.00
6.1 B. Langit-langit Asbes (m ²)
SNI 03-2835-2002 Bahan
Pelat Asbes tebal 6mm M² 1.100 12,500.00 13,750.00
Paku plafon Kg 0.010 10,000.00
Tenaga
Pekerja Oh 0.030 100,000.00 3,000.00
Tukang Kayu Oh 0.070 100,000.00 7,000.00
Kepala Tukang Oh 100,000.00 -
Mandor Oh 150,000.00 -
Sub Total 23,750.00
I PEKERJAAN KONSTRUKSI
A PEKERJAAN PERSIAPAN Rp 63,379,690.00
B PEKERJAAN TANAH DAN PONDASI Rp 687,210,106.00
C STRUKTUR BETON Rp 5,200,448,480.00
D PEKERJAAN ATAP Rp 338,557,500.00
E PEKERJAAN PLAFOND Rp 288,509,400.00
F PEKERJAAN PASANGAN Rp 1,951,326,905.50
G PEKERJAAN KUSEN PINTU & JENDELA Rp 1,603,200,000.00
H PEKERJAAN PENGECATAN Rp 297,663,260.00
I PEKERJAAN PLUMBING&SANITAIR Rp 280,197,600.00
J PEKERJAAN INSTALASI LISTRIK Rp 466,680,000.00
K PEKERJAAN LAIN-LAIN 643,350,000.00
JUMLAH PEKERJAAN KONSTRUKSI Rp 11,820,522,941.50
II PENGADAAN
A PENGADAAN MEUBELAIR Rp 480,000,000.00
B PENGADAAN ASESORIS KAMAR Rp 450,000,000.00
C PENGADAAN ASESORIS CAFÉ Rp 240,000,000.00
D PENGADAAN ALAT-ALAT DAPUR Rp 400,000,000.00
E PENGADAAN ALAT-ALAT KEBUN Rp 100,000,000.00
G PERSIAPAN AWAL OPERASIONAL Rp 500,000,000.00
TERBILANG :
TIGA BELAS MILYAR SEMBILAN RATUS SEMBILAN PULUH JUTA RUPIAH