II PEKERJAAN TANAH
6.1 A. Galian Tanah Biasa sedalam 1 m (m³)
SNI 03-2835-2002 Tenaga
Pekerja Oh 0.400 94,000.00 37,600.00
Mandor Oh 0.040 124,000.00 4,960.00
Sub Total 42,560.00
6.9 B. Urugan Kembali (m³)
SNI 03-2835-2002 Tenaga
Pekerja Oh 0.192 94,000.00 18,048.00
Mandor Oh 0.019 124,000.00 2,356.00
Sub Total 20,404.00
6.11 C. Urugan Pasir Bawah Pondasi (m³)
SNI 03-2835-2002 Bahan
Pasir Urug M³ 1.200 279,000.00 334,800.00
Tenaga
Pekerja Oh 0.300 94,000.00 28,200.00
Mandor Oh 0.010 124,000.00 1,240.00
Sub Total 364,240.00
IV PEKERJAAN DINDING
6.11 A. Pasangan Tembok ½ Bata 1Pc:4Ps (Trasraam) (m²)
SNI 03-2835-2002 Bahan
Bata Merah 5 X 11 X 22 cm Bh 70.000 1,000.00 70,000.00
Semen Portland Kg 11.500 1,300.00 14,950.00
Pasir Pasang M³ 0.043 300,000.00 12,900.00
Tenaga
Pekerja Oh 0.320 94,000.00 30,080.00
Tukang Batu Oh 0.100 109,000.00 10,900.00
Kepala Tukang Oh 0.010 117,000.00 1,170.00
Mandor Oh 0.015 124,000.00 1,860.00
Sub Total 141,860.00
6.15 B. Pasangan Tembok ½ Bata 1Pc:3Kp:10Ps (m²)
SNI 03-2835-2002 Bahan
Bata Merah 5 X 11 X 22 cm Bh 70.000 1,000.00 70,000.00
Semen Portland Kg 4.500 1,300.00 5,850.00
Pasir Pasang M³ 0.050 300,000.00 15,000.00
Kapur Padam M³ 0.015 60,000.00 900.00
Tenaga
Pekerja Oh 0.320 94,000.00 30,080.00
Tukang Batu Oh 0.100 109,000.00 10,900.00
Kepala Tukang Oh 0.010 117,000.00 1,170.00
Mandor Oh 0.015 124,000.00 1,860.00
Sub Total 135,760.00
VI PEKERJAAN KAYU
6.1 A. Pasang Kusen Pintu dan Jendela Kayu Jati (m³)
SNI 03-2835-2002 Bahan
Kayu jati, balok M³ 1.100 17,000,000.00 18,700,000.00
Tenaga
Pekerja Oh 6.000 94,000.00 564,000.00
Tukang Kayu Oh 20.000 109,000.00 2,180,000.00
Kepala Tukang Oh 2.000 117,000.00 234,000.00
Mandor Oh 0.300 124,000.00 37,200.00
Sub Total 21,715,200.00
6.7 B. Pasang Pintu Panel Kayu Jati (m²)
SNI 03-2835-2002 Bahan
Kayu Jati, papan M³ 0.040 20,000,000.00 800,000.00
Tenaga
Pekerja Oh 1.000 94,000.00 94,000.00
Tukang Kayu Oh 2.500 109,000.00 272,500.00
Kepala Tukang Oh 0.250 117,000.00 29,250.00
Mandor Oh 0.050 124,000.00 6,200.00
Sub Total 1,201,950.00
ALS C. Pasang Nook, Gording, Murplat, Nook Kayu Bengkirai (m³)
Bahan
Kayu Bengkirai, balok M³ 1.100 10,000,000.00 11,000,000.00
Tenaga
Pekerja Oh 2.000 94,000.00 188,000.00
Tukang Kayu Oh 8.000 109,000.00 872,000.00
Kepala Tukang Oh 1.200 117,000.00 140,400.00
Mandor Oh 0.200 124,000.00 24,800.00
Sub Total 12,225,200.00
6.35 D. Pasang Kaso+Reng Genteng Beton Kayu Borneo (m²)
SNI 03-2835-2002 Bahan
Kayu Borneo, balok M³ 0.014 10,000,000.00 140,000.00
Paku Biasa 2"-5" Kg 0.150 20,700.00 3,105.00
Tenaga
Pekerja Oh 0.100 94,000.00 9,400.00
Tukang Kayu Oh 0.100 109,000.00 10,900.00
Kepala Tukang Oh 0.010 117,000.00 1,170.00
Mandor Oh 0.005 124,000.00 620.00
Sub Total 165,195.00
6.53 E. Pasang Listplank, Reuter 2X (2X20) cm, kayu borneo (m³)
SNI 03-2835-2002 Bahan
Kayu Borneo,Papan M³ 0.009 10,000,000.00 88,000.00
Paku Biasa 2"-5" Kg 0.060 20,700.00 1,242.00
Tenaga
Pekerja Oh 0.100 94,000.00 9,400.00
Tukang Kayu Oh 0.100 109,000.00 10,900.00
Kepala Tukang Oh 0.010 117,000.00 1,170.00
Mandor Oh 0.050 124,000.00 6,200.00
Sub Total 116,912.00
6.40 F. Pasang Rangka Langit-langit 1X1 m Kayu Borneo (m²)
SNI 03-2835-2002 Bahan
Kayu borneo, balok M³ 0.012 10,000,000.00 120,000.00
Paku biasa 2"-5" Kg 0.100 20,700.00 2,070.00
Tenaga
Pekerja Oh 0.150 94,000.00 14,100.00
Tukang Kayu Oh 0.250 109,000.00 27,250.00
Kepala Tukang Oh 0.025 117,000.00 2,925.00
Mandor Oh 0.075 124,000.00 9,300.00
Sub Total 175,645.00
IX PEKERJAAN PLAFON
6.19 A. Pasang List Langit-langit Kayu Profil (m¹)
SNI 03-2835-2002 Bahan
Kayu Profil M¹ 1.100 5,000.00 5,500.00
Paku plafon Kg 0.010 20,700.00
Tenaga
Pekerja Oh 0.050 94,000.00 4,700.00
Tukang Kayu Oh 0.050 109,000.00 5,450.00
Kepala Tukang Oh 0.005 117,000.00 585.00
Mandor Oh 0.003 124,000.00 372.00
Sub Total 16,607.00
6.1 B. Langit-langit Asbes (m²)
SNI 03-2835-2002 Bahan
Pelat Asbes tebal 6mm M² 1.100 32,000.00 35,200.00
Paku plafon Kg 0.010 20,700.00
Tenaga
Pekerja Oh 0.030 94,000.00 2,820.00
Tukang Kayu Oh 0.070 109,000.00 7,630.00
Kepala Tukang Oh 0.007 117,000.00 819.00
Mandor Oh 0.002 124,000.00 186.00
Sub Total 46,655.00