A PEKERJAAN PERSIAPAN
A-01 1 m' PAGAR SEMENTARA DARI KAYU, tinggi=2 METER
Dolken Kayu D 8-10/400 Cm 1.2500 Btg 14,000.00 17,500.00
Semen Portland 2.5000 kg 1,030.00 2,575.00
Pasir Beton 0.0050 m3 125,000.00 625.00
Koral Beton 0.0090 m3 125,000.00 1,125.00
Kayu 5/7 0.0720 m3 1,400,000.00 100,800.00
Paku biasa 2"-5" 0.0600 Kg 9,000.00 540.00
Residu 0.4000 Lt 1,100.00 440.00
Tukang Kayu 0.2000 HOK 42,000.00 8,400.00
Pekerja 0.4000 HOK 30,000.00 12,000.00
Kepala Tukang 0.0200 HOK 42,000.00 840.00
Mandor 0.0200 HOK 41,000.00 820.00
Total 22,060.00 123,605.00
Total Harga 145,665.00
Keuntungan 14,566.50
Jumlah Total 160,231.50
A-02 1 m' PAGAR SEMENTARA /PENGAMAN PROYEK DARI SENG GELOMBANG, tinggi=2 METER
Dolken Kayu D 8-10/400 Cm 1.2500 Btg 14,000.00 17,500.00
Semen Portland 2.5000 Kg 1,030.00 2,575.00
Seng gelombang 3"-5" 1.2000 lbr 39,900.00 47,880.00
Pasir Beton 0.0050 m3 125,000.00 625.00
Koral Beton 0.0090 m3 125,000.00 1,125.00
Kayu 5/7 0.0720 m3 2,117,000.00 152,424.00
Paku biasa 2"-5" 0.0600 Kg 9,000.00 540.00
Meni besi 0.4500 Kg 18,000.00 8,100.00
Tukang kayu 0.2000 HOK 42,000.00 8,400.00
Pekerja 0.4000 HOK 30,000.00 12,000.00
Kepala tukang 0.0200 HOK 42,000.00 840.00
Mandor 0.0200 HOK 41,000.00 820.00
Total 22,060.00 230,769.00
Total Harga 252,829.00
Keuntungan 25,282.90
Jumlah Total 278,111.90
A-03 1 m' PAGAR SEMENTARA DARI KAWAT DURI TINGGI 1,8 METER
Dolken Kayu D 8-10/400 Cm 1.0000 Btg 14,000.00 14,000.00
Semen Portland 2.0000 Kg 1,030.00 2,060.00
Kawat Duri 25.0000 Kg 2,500.00 62,500.00
Pasir Beton 0.0050 m3 125,000.00 625.00
Koral Beton 0.0090 m3 125,000.00 1,125.00
Paku biasa 2"-5" 0.0600 Kg 9,000.00 540.00
Tukang kayu 0.2000 HOK 42,000.00 8,400.00
Pekerja 0.3000 HOK 30,000.00 9,000.00
Kepala tukang 0.0200 HOK 42,000.00 840.00
Mandor 0.0200 HOK 41,000.00 820.00
Total 19,060.00 80,850.00
Total Harga 99,910.00
Keuntungan 9,991.00
a b c d e f=(cxe) g=(cxe) h
Jumlah Total 109,901.00
B PEKERJAAN TANAH
B-01 1 m3 GALIAN TANAH BIASA SEDALAM 1 METER
Pekerja 0.4000 HOK 30,000.00 12,000.00
Mandor 0.0400 HOK 41,000.00 1,640.00
Total 13,640.00
Total Harga 13,640.00
Keuntungan 1,364.00
Jumlah Total 15,004.00
C PEKERJAAN PONDASI
C-01 1 m3 PASANGAN PONDASI BATU KALI, 1 Pc : 1 Ps
Batu belah 15/20 cm 1.1000 m3 67,000.00 73,700.00
Semen Portland 392.0000 Kg 1,030.00 403,760.00
Pasir pasang 0.3140 m3 95,000.00 29,830.00
Pekerja 1.5000 HOK 30,000.00 45,000.00
Tukang batu 0.6000 HOK 38,500.00 23,100.00
Kepala tukang 0.0600 HOK 42,000.00 2,520.00
Mandor 0.0750 HOK 41,000.00 3,075.00
Total 73,695.00 507,290.00
Total Harga 580,985.00
Keuntungan 58,098.50
Jumlah Total 639,083.50
D PEKERJAAN DINDING
D-01 1 m2 PASANGAN BATA MERAH TEBAL 1 BATA, 1 PC : 1 Ps
Bata merah ( 5x11x22 ) cm 140.0000 Bh 400.00 56,000.00
Semen Portland 64.0300 Kg 1,030.00 65,950.90
Pasir pasang 0.0590 m3 65,000.00 3,835.00
Pekerja 0.6500 HOK 30,000.00 19,500.00
Tukang batu 0.2000 HOK 38,500.00 7,700.00
Kepala tukang 0.0200 HOK 42,000.00 840.00
Mandor 0.0300 HOK 41,000.00 1,230.00
Total 29,270.00 125,785.90
Total Harga 155,055.90
Keuntungan 15,505.59
Jumlah Total 170,561.49
F PEKERJAAN KAYU
F-01 1 m3 PASANG KUSEN PINTU DAN JENDELA KAYU JATI
Kayu jati, balok 1.1000 m3 8,470,000.00 9,317,000.00
Pekerja 6.0000 HOK 30,000.00 180,000.00
Tukang kayu 20.0000 HOK 42,000.00 840,000.00
Kepala tukang 2.0000 HOK 42,000.00 84,000.00
Mandor 0.3000 HOK 41,000.00 12,300.00
Total 1,116,300.00 9,317,000.00
Total Harga 10,433,300.00
a b c d e f=(cxe) g=(cxe) h
Keuntungan 1,043,330.00
Jumlah Total 11,476,630.00
F-09 1 m2 PASANG PINTU DAN JENDELA KACA KAYU JATI (TANPA KACA)
Kayu jati, papan 0.0350 m3 8,470,000.00 296,450.00
Pekerja 0.8000 HOK 30,000.00 24,000.00
Tukang kayu 2.0000 HOK 42,000.00 84,000.00
Kepala tukang 0.2000 HOK 42,000.00 8,400.00
Mandor 0.0400 HOK 41,000.00 1,640.00
Total 118,040.00 296,450.00
Total Harga 414,490.00
Keuntungan 41,449.00
Jumlah Total 455,939.00
F-10 1 m2 PASANG PINTU DAN JENDELA KACA KAYU KAMPER (TANPA KACA)
Kayu kamper, papan 0.0350 m3 5,720,000.00 200,200.00
Pekerja 0.8000 HOK 30,000.00 24,000.00
Tukang kayu 2.0000 HOK 42,000.00 84,000.00
Kepala tukang 0.2000 HOK 42,000.00 8,400.00
Mandor 0.0400 HOK 41,000.00 1,640.00
Total 118,040.00 200,200.00
Total Harga 318,240.00
Keuntungan 31,824.00
Jumlah Total 350,064.00
F-11 1 m2 PASANG PINTU DAN JENDELA KACA KAYU BORNEO (TANPA KACA)
Kayu Borneo, papan 0.0350 m3 4,290,000.00 150,150.00
Pekerja 0.8000 HOK 30,000.00 24,000.00
Tukang kayu 2.0000 HOK 42,000.00 84,000.00
Kepala tukang 0.2000 HOK 42,000.00 8,400.00
Mandor 0.0400 HOK 41,000.00 1,640.00
Total 118,040.00 150,150.00
Total Harga 268,190.00
Keuntungan 26,819.00
Jumlah Total 295,009.00
DIHITUNG 1 m' PASANG LISTPLANK UKURAN 2 x ( 2x20 ) cm, KAYU GUNUNG KELAS II
Kayu Gunung Kls II, papan 0.0088 m3 1,400,000.00 12,320.00
Paku biasa 2"-5" 0.0600 Kg 9,000.00 540.00
Pekerja 0.1000 HOK 30,000.00 3,000.00
Tukang kayu 0.1000 HOK 42,000.00 4,200.00
Kepala tukang 0.0100 HOK 42,000.00 420.00
Mandor 0.0500 HOK 41,000.00 2,050.00
Total 9,670.00 12,860.00
Total Harga 22,530.00
Keuntungan 2,253.00
Jumlah Total 24,783.00
N PEKERJAAN PENGECATAN
N-01 1 m2 MENGIKIS / MENGEROK PERMUKAAN CAT TEMBOK LAMA
Soda api 0.0500 Kg 0.00 0.00
Pekerja 0.1500 HOK 30,000.00 4,500.00
Mandor 0.0025 HOK 41,000.00 102.50
Total 4,602.50 0.00
Total Harga 4,602.50
Keuntungan 460.25
Jumlah Total 5,062.75
N-03 1 m2 MENGEROK KARAT CAT LAMA PERMUKAAN BAJA DENGAN CARA MANUAL
Sabun 0.0500 Kg 1,500.00 75.00
Pekerja 0.1500 HOK 30,000.00 4,500.00
Mandor 0.0025 HOK 41,000.00 102.50
Total 4,602.50 75.00
Total Harga 4,677.50
Keuntungan 467.75
Jumlah Total 5,145.25
N-08 1 m2 PENGECATAN BIDANG KAYU BARU (1 Lapis Plamir; 1 Lapis Cat dasar; 2 Lapis Cat Penutup)
Cat meni 0.2000 Kg 18,000.00 3,600.00
Plamir 0.1500 Kg 12,000.00 1,800.00
Cat dasar 0.1700 Kg 35,000.00 5,950.00
Cat Penutup ( 2 kali ) 0.2600 Kg 35,000.00 9,100.00
Pekerja 0.0700 HOK 30,000.00 2,100.00
Tukang cat 0.0090 HOK 35,500.00 319.50
Kepala tukang 0.0060 HOK 42,000.00 252.00
Mandor 0.0025 HOK 41,000.00 102.50
Total 2,774.00 20,450.00
Total Harga 23,224.00
Keuntungan 2,322.40
Jumlah Total 25,546.40
N-09 1 m2 PENGECATAN BIDANG KAYU BARU (1 Lapis Plamir; 1 Lapis Cat dasar; 3 Lapis Cat Penutup)
Cat meni 0.2000 Kg 18,000.00 3,600.00
Plamir 0.1500 Kg 12,000.00 1,800.00
Cat dasar 0.1700 Kg 35,000.00 5,950.00
Cat Penutup ( 3 kali ) 0.3500 Kg 35,000.00 12,250.00
Pekerja 0.0700 HOK 30,000.00 2,100.00
Tukang cat 0.1050 HOK 35,500.00 3,727.50
Kepala tukang 0.0040 HOK 42,000.00 168.00
Mandor 0.0025 HOK 41,000.00 102.50
Total 6,098.00 23,600.00
Total Harga 29,698.00
Keuntungan 2,969.80
Jumlah Total 32,667.80
a b c d e f=(cxe) g=(cxe) h
N-14 1 m2 PENGECATAN BIDANG TEMBOK BARU (1 Lapis Plamir; 1 Lapis Cat dasar; 2 Lapis Cat Penutup)
Plamir 0.1000 Kg 12,000.00 1,200.00
Cat dasar 0.1000 Kg 12,000.00 1,200.00
Cat Penutup ( 2 kali ) 0.2600 Kg 12,000.00 3,120.00
Pekerja 0.0200 HOK 30,000.00 600.00
Tukang cat 0.0630 HOK 35,500.00 2,236.50
Kepala tukang 0.0063 HOK 42,000.00 264.60
Mandor 0.0025 HOK 41,000.00 102.50
Total 3,203.60 5,520.00
Total Harga 8,723.60
Keuntungan 872.36
Jumlah Total 9,595.96
N-15 1 m2 PENGECATAN BIDANG TEMBOK LAMA ( 1 Lapis Cat dasar; 2 Lapis Cat Penutup )
Cat dasar 0.1200 Kg 12,000.00 1,440.00
Cat Penutup ( 2 kali ) 0.1800 Kg 12,000.00 2,160.00
Pekerja 0.0280 HOK 30,000.00 840.00
Tukang cat 0.0420 HOK 35,500.00 1,491.00
Kepala tukang 0.0042 HOK 42,000.00 176.40
Mandor 0.0025 HOK 41,000.00 102.50
Total 2,609.90 3,600.00
Total Harga 6,209.90
Keuntungan 620.99
a b c d e f=(cxe) g=(cxe) h
Jumlah Total 6,830.89
N-22 1 m2 PENGECATAN PERMUKAAN BAJA LAPIS SENG GALBANI SECARA MANUAL (4 lapis cat konvensional, tebal 200 um)
Cat dasar 0.1100 Kg 0.00
Cat antara 0.1700 Kg 0.00
Cat penutup 0.0800 Kg 0.00
Pekerja 0.5000 HOK 0.00
Tukang cat 0.8000 HOK 0.00
Kepala tukang 0.3000 HOK 0.00
Mandor 0.2000 HOK 0.00
Total 0.00 0.00
Total Harga -
N-23 1 m2 PENGECATAN PERMUKAAN BAJA LAPIS GALBANI SECARA MANUAL (1 lapis cat mutakhir, tebal 200 um)
Cat 0.3000 Kg 0.00
Pekerja 0.0060 HOK 0.00
Tukang cat 0.0600 HOK 0.00
Kepala tukang 0.0120 HOK 0.00
Mandor 0.0060 HOK 0.00
Total 0.00 0.00
Total Harga -
a b c d e f=(cxe) g=(cxe) h
A-02 1 m' PAGAR SEMENTARA /PENGAMAN PROYEK DARI SENG GELOMBANG, tinggi=2 METER
Dolken Kayu D 8-10/400 Cm 1.2500 Btg 15,000.00 18,750.00
Semen Portland 2.5000 Kg 1,090.00 2,725.00
Seng gelombang 3"-5" 1.2000 lbr 0.00 0.00
Pasir Beton 0.0050 m3 125,000.00 625.00
Koral Beton 0.0090 m3 125,000.00 1,125.00
Kayu 5/7 0.0720 m3 2,100,000.00 151,200.00
Paku biasa 2"-5" 0.0600 Kg 11,000.00 660.00
Meni besi 0.4500 Kg 15,000.00 6,750.00
Tukang kayu 0.2000 HOK 45,000.00 9,000.00
Pekerja 0.4000 HOK 35,000.00 14,000.00
Kepala tukang 0.0200 HOK 50,000.00 1,000.00
Mandor 0.0200 HOK 50,000.00 1,000.00
Total 25,000.00 181,835.00
Total Harga 206,835.00
Keuntungan 31,025.25
Jumlah Total 237,860.25
A-03 1 m' PAGAR SEMENTARA DARI KAWAT DURI TINGGI 1,8 METER
Dolken Kayu D 8-10/400 Cm 1.0000 Btg 15,000.00 15,000.00
Semen Portland 2.0000 Kg 1,090.00 2,180.00
Kawat Duri 25.0000 Kg 0.00 0.00
Pasir Beton 0.0050 m3 125,000.00 625.00
Koral Beton 0.0090 m3 125,000.00 1,125.00
Paku biasa 2"-5" 0.0600 Kg 11,000.00 660.00
Tukang kayu 0.2000 HOK 45,000.00 9,000.00
Pekerja 0.3000 HOK 35,000.00 10,500.00
Kepala tukang 0.0200 HOK 50,000.00 1,000.00
Mandor 0.0200 HOK 50,000.00 1,000.00
Total 21,500.00 19,590.00
Total Harga 41,090.00
Keuntungan 6,163.50
Jumlah Total 47,253.50
B PEKERJAAN TANAH
B-01 1 m3 GALIAN TANAH BIASA SEDALAM 1 METER
Pekerja 0.4000 HOK 35,000.00 14,000.00
Mandor 0.0400 HOK 50,000.00 2,000.00
Total 16,000.00
Total Harga 16,000.00
Keuntungan
Jumlah Total 16,000.00
C PEKERJAAN PONDASI
C-01 1 m3 PASANGAN PONDASI BATU KALI, 1 Pc : 1 Ps
Batu belah 15/20 cm 1.1000 m3 80,000.00 88,000.00
Semen Portland 392.0000 Kg 1,090.00 427,280.00
Pasir pasang 0.3140 m3 85,000.00 26,690.00
Pekerja 1.5000 HOK 35,000.00 52,500.00
Tukang batu 0.6000 HOK 45,000.00 27,000.00
Kepala tukang 0.0600 HOK 50,000.00 3,000.00
Mandor 0.0750 HOK 50,000.00 3,750.00
Total 86,250.00 541,970.00
Total Harga 628,220.00
Keuntungan 94,233.00
Jumlah Total 722,453.00
D PEKERJAAN DINDING
D-01 1 m2 PASANGAN BATA MERAH TEBAL 1 BATA, 1 PC : 1 Ps
Bata merah ( 5x11x22 ) cm 140.0000 Bh 550.00 77,000.00
Semen Portland 64.0300 Kg 1,090.00 69,792.70
Pasir pasang 0.0590 m3 85,000.00 5,015.00
Pekerja 0.6500 HOK 35,000.00 22,750.00
Tukang batu 0.2000 HOK 45,000.00 9,000.00
Kepala tukang 0.0200 HOK 50,000.00 1,000.00
Mandor 0.0300 HOK 50,000.00 1,500.00
Total 34,250.00 151,807.70
Total Harga 186,057.70
Keuntungan 27,908.66
Jumlah Total 213,966.36
E PEKERJAAN PLESTERAN
E-01 1 m2 PLESTERAN 1 PC : 1 Ps, TEBAL 15 mm
Semen Portland 12.9200 kg 1,090.00 14,082.80
Pasir pasang 0.0130 m3 85,000.00 1,105.00
Pekerja 0.2000 HOK 35,000.00 7,000.00
Tukang batu 0.1500 HOK 45,000.00 6,750.00
Kepala tukang 0.0150 HOK 50,000.00 750.00
Mandor 0.0100 HOK 50,000.00 500.00
Total 15,000.00 15,187.80
Total Harga 30,187.80
Keuntungan 4,528.17
Jumlah Total 34,715.97
F PEKERJAAN KAYU
F-01 1 m3 PASANG KUSEN PINTU DAN JENDELA KAYU JATI
Kayu jati, balok 1.1000 m3 5,692,500.00 6,261,750.00
Pekerja 6.0000 HOK 35,000.00 210,000.00
Tukang kayu 20.0000 HOK 45,000.00 900,000.00
Kepala tukang 2.0000 HOK 50,000.00 100,000.00
Mandor 0.3000 HOK 50,000.00 15,000.00
Total 1,225,000.00 6,261,750.00
Total Harga 7,486,750.00
Keuntungan 1,123,012.50
Jumlah Total 8,609,762.50
F-09 1 m2 PASANG PINTU DAN JENDELA KACA KAYU JATI (TANPA KACA)
Kayu jati, papan 0.0350 m3 5,692,500.00 199,237.50
Pekerja 0.8000 HOK 35,000.00 28,000.00
Tukang kayu 2.0000 HOK 45,000.00 90,000.00
Kepala tukang 0.2000 HOK 50,000.00 10,000.00
Mandor 0.0400 HOK 50,000.00 2,000.00
Total 130,000.00 199,237.50
Total Harga 329,237.50
Keuntungan 49,385.63
Jumlah Total 378,623.13
F-10 1 m2 PASANG PINTU DAN JENDELA KACA KAYU KAMPER (TANPA KACA)
Kayu kamper, papan 0.0350 m3 10,626,000.00 371,910.00
Pekerja 0.8000 HOK 35,000.00 28,000.00
Tukang kayu 2.0000 HOK 45,000.00 90,000.00
Kepala tukang 0.2000 HOK 50,000.00 10,000.00
Mandor 0.0400 HOK 50,000.00 2,000.00
Total 130,000.00 371,910.00
Total Harga 501,910.00
Keuntungan 75,286.50
Jumlah Total 577,196.50
F-11 1 m2 PASANG PINTU DAN JENDELA KACA KAYU BORNEO (TANPA KACA)
Kayu Borneo, papan 0.0350 m3 5,217,300.00 182,605.50
Pekerja 0.8000 HOK 35,000.00 28,000.00
Tukang kayu 2.0000 HOK 45,000.00 90,000.00
Kepala tukang 0.2000 HOK 50,000.00 10,000.00
Mandor 0.0400 HOK 50,000.00 2,000.00
Total 130,000.00 182,605.50
Total Harga 312,605.50
Keuntungan 46,890.83
Jumlah Total 359,496.33
DIHITUNG 1 m2 PASANG PINTU DAN JENDELA KACA KAYU KELAS II (TANPA KACA)
Kayu KELAS ii, papan 0.0350 m3 2,200,000.00 77,000.00
Pekerja 0.8000 HOK 35,000.00 28,000.00
Tukang kayu 2.0000 HOK 45,000.00 90,000.00
Kepala tukang 0.2000 HOK 50,000.00 10,000.00
Mandor 0.0400 HOK 50,000.00 2,000.00
Total 130,000.00 77,000.00
Total Harga 207,000.00
Keuntungan
Jumlah Total 207,000.00
F-12 1 m2 PASANG PINTU DAN JENDELA JALUSI KAYU JATI
Kayu jati, papan 0.0640 m3 5,692,500.00 364,320.00
Pekerja 1.0000 HOK 35,000.00 35,000.00
Tukang kayu 3.0000 HOK 45,000.00 135,000.00
Kepala tukang 0.3000 HOK 50,000.00 15,000.00
Mandor 0.3000 HOK 50,000.00 15,000.00
Total 200,000.00 364,320.00
Total Harga 564,320.00
Keuntungan 84,648.00
Jumlah Total 648,968.00
DHT 1 m2 PASANG PINTU DAN JENDELA KACA KAYU GUNUNG KLAS II (TANPA KACA)
Kayu Lokal Kls II, papan 0.0350 m3 2,200,000.00 77,000.00
Pekerja 0.8000 HOK 35,000.00 28,000.00
Tukang kayu 2.0000 HOK 45,000.00 90,000.00
Kepala tukang 0.2000 HOK 50,000.00 10,000.00
Mandor 0.0400 HOK 50,000.00 2,000.00
Total 130,000.00 77,000.00
Total Harga 207,000.00
Keuntungan 31,050.00
Jumlah Total 238,050.00
F-16 1 m2 PASANG JALUSI MATI KUSEN KAYU JATI
Kayu jati, papan 0.0600 m3 5,692,500.00 341,550.00
Paku biasa 1/2"-1" 0.1500 Kg 11,000.00 1,650.00
Pekerja 0.5000 HOK 35,000.00 17,500.00
Tukang kayu 2.0000 HOK 45,000.00 90,000.00
Kepala tukang 0.2000 HOK 50,000.00 10,000.00
Mandor 0.0250 HOK 50,000.00 1,250.00
Total 118,750.00 343,200.00
Total Harga 461,950.00
Keuntungan 69,292.50
Jumlah Total 531,242.50
DIHITUNG 1 m' PASANG LISTPLANK UKURAN 2 x ( 2x20 ) cm, KAYU GUNUNG KELAS II
Kayu Gunung Kls II, papan 0.0088 m3 2,100,000.00 18,480.00
Paku biasa 2"-5" 0.0600 Kg 11,000.00 660.00
Pekerja 0.1000 HOK 35,000.00 3,500.00
Tukang kayu 0.1000 HOK 45,000.00 4,500.00
Kepala tukang 0.0100 HOK 50,000.00 500.00
Mandor 0.0500 HOK 50,000.00 2,500.00
Total 11,000.00 19,140.00
Total Harga 30,140.00
Keuntungan
Jumlah Total 30,140.00
a b c d e f=(cxe) g=(cxe) h 5495470000
G PEKERJAAN BETON
G-01 1 m3 MEMBUAT BETON TUMBUK, 1 PC : 3 Ps : 5 Kr
Semen portland 218.0000 kg 1,090.00 237,620.00
Pasir beton 0.5200 m3 125,000.00 65,000.00
Koral beton 0.8700 m3 125,000.00 108,750.00
Pekerja 1.6500 HOK 35,000.00 57,750.00
Tukang batu 0.2500 HOK 45,000.00 11,250.00
Kepala tukang 0.0250 HOK 50,000.00 1,250.00
Mandor 0.0800 HOK 50,000.00 4,000.00
Total 74,250.00 411,370.00
Total Harga 485,620.00
Keuntungan
Jumlah Total 485,620.00
2,152,269.37 2,152,269.37
G-B Membuat 1 M3 Pondasi Plat Selasar (P2)
Beton Site Mix 1PC : 2Ps :3Kr 1.0000 M3 489,630.00 489,630.00
Bekisting 2XPAKAI 5.0000 M2 59,355.00 296,775.00
Besi beton polos 189.5368 KG 9,174.95 1,738,990.30
2,525,395.30 2,525,395.30
G-C Membuat 1 M3 Pondasi Plat Tangga
Beton Site Mix 1PC : 2Ps :3Kr 1.0000 M3 489,630.00 489,630.00
Bekisting 2XPAKAI 5.6250 M2 59,355.00 333,871.88
Besi beton polos 205.0726 KG 9,174.95 1,881,530.48
2,705,032.36 2,705,032.36
G-D Membuat 1 M3 Sloof Beton 20/30
Beton Site Mix 1PC : 2Ps :3Kr 1.0000 M3 489,630.00 489,630.00
Bekisting 2XPAKAI 10.0000 M2 55,488.55 554,885.50
Besi beton polos 137.5216 KG 9,174.95 1,261,753.80
a b c d e f=(cxe) g=(cxe) h 5495470000
2,306,269.30 2,306,269.30
G-E Membuat 1 M3 Sloof Beton 15/20
Beton Site Mix 1PC : 2Ps :3Kr 1.0000 M3 489,630.00 489,630.00
Bekisting 2XPAKAI 13.3333 M2 55,488.55 739,847.33
Besi beton polos 155.1490 KG 9,174.95 1,423,483.97
2,652,961.30 2,652,961.30
3,807,033.45 3,807,033.45
G-G Membuat 1 M3 Kolom 15/20
Beton Site Mix 1PC : 2Ps :3Kr 1.0000 M3 489,630.00 489,630.00
Bekisting 2XPAKAI 33.3333 M2 104,275.13 3,475,837.50
Besi beton polos 159.3649 KG 9,174.95 1,462,164.64
5,427,632.14 5,427,632.14
G-H Membuat 1 M3 Kolom 20/20
Beton Site Mix 1PC : 2Ps :3Kr 1.0000 M3 489,630.00 489,630.00
Bekisting 2XPAKAI 20.0000 M2 104,275.13 2,085,502.50
Besi beton polos 126.3147 KG 9,174.95 1,158,930.83
3,734,063.33 3,734,063.33
G-I Membuat 1 M3 Kolom Selasar 25/25 (KS)
Beton Site Mix 1PC : 2Ps :3Kr 1.0000 M3 489,630.00 489,630.00
Bekisting 2XPAKAI 16.0000 M2 104,275.13 1,668,402.00
Besi beton polos 128.6221 KG 9,174.95 1,180,100.99
3,338,132.99 3,338,132.99
G-J Membuat 1 M3 Kolom Selasar 20/20 (KS2)
Beton Site Mix 1PC : 2Ps :3Kr 1.0000 M3 489,630.00 489,630.00
Bekisting 2XPAKAI 20.0000 M2 104,275.13 2,085,502.50
Besi beton polos 126.3147 KG 9,174.95 1,158,930.83
3,734,063.33 3,734,063.33
G-K Membuat 1 M3 Kolom Struktur 25/35 (K1)
Beton Site Mix 1PC : 2Ps :3Kr 1.0000 M3 489,630.00 489,630.00
Bekisting 2XPAKAI 13.7143 M2 104,275.13 1,430,058.86
Besi beton polos 159.9749 KG 9,174.95 1,467,761.96
3,387,450.81 3,387,450.81
G-L Membuat 1 M3 Kolom Struktur 20/30 (KS)
Beton Site Mix 1PC : 2Ps :3Kr 1.0000 M3 489,630.00 489,630.00
Bekisting 2XPAKAI 16.6667 M2 104,275.13 1,737,918.75
Besi beton polos 133.9691 KG 9,174.95 1,229,159.55
3,456,708.30 3,456,708.30
G-L.2 Membuat 1 M3 Kolom Struktur 25/30 (KE)
Beton Site Mix 1PC : 2Ps :3Kr 1.0000 M3 489,630.00 489,630.00
Bekisting 2XPAKAI 14.6667 M2 104,275.13 1,529,368.50
Besi beton polos 139.1909 KG 9,174.95 1,277,069.34
3,296,067.84 3,296,067.84
G-L.3 Membuat 1 M3 Kolom Struktur 25/35 (KE)
Beton Site Mix 1PC : 2Ps :3Kr 1.0000 M3 489,630.00 489,630.00
Bekisting 2XPAKAI 13.7143 M2 104,275.13 1,430,058.86
Besi beton polos 159.9749 KG 9,174.95 1,467,761.96
3,387,450.81 3,387,450.81
G-M Membuat 1 M3 Kolom Struktur 20/25(K2)
Beton Site Mix 1PC : 2Ps :3Kr 1.0000 M3 489,630.00 489,630.00
Bekisting 2XPAKAI 18.0000 M2 104,275.13 1,876,952.25
Besi beton polos 131.6539 KG 9,174.95 1,207,917.59
a b c d e f=(cxe) g=(cxe) h 5495470000
3,574,499.84 3,574,499.84
G-N Membuat 1 M3 Ring Balok 15/20
Beton Site Mix 1PC : 2Ps :3Kr 1.0000 M3 489,630.00 489,630.00
Bekisting 2XPAKAI 13.3333 M2 115,624.97 1,541,666.23
Besi beton polos 134.7214 KG 9,174.95 1,236,062.42
3,267,358.65 3,267,358.65
G-O Membuat 1 M3 Balok 25/35
Beton Site Mix 1PC : 2Ps :3Kr 1.0000 M3 489,630.00 489,630.00
Bekisting 2XPAKAI 8.1143 M2 115,624.97 938,214.02
Besi beton polos 100.1559 KG 9,174.95 918,925.70
2,346,769.72 2,346,769.72
G-P Membuat 1 M3 Balok 25/50
Beton Site Mix 1PC : 2Ps :3Kr 1.0000 M3 489,630.00 489,630.00
Bekisting 2XPAKAI 8.0800 M2 115,624.97 934,249.74
Besi beton polos 123.3346 KG 9,174.95 1,131,588.97
2,555,468.71 2,555,468.71
G-Q Membuat 1 M3 Balok 25/60
Beton Site Mix 1PC : 2Ps :3Kr 1.0000 M3 489,630.00 489,630.00
Bekisting 2XPAKAI 8.0667 M2 115,624.97 932,708.07
Besi beton polos 106.0081 KG 9,174.95 972,619.36
2,394,957.43 2,394,957.43
G-R Membuat 1 M3 Plat Dak T=12Cm
Beton Site Mix 1PC : 2Ps :3Kr 1.0000 M3 489,630.00 489,630.00
Bekisting PAKAI 10.5733 M2 137,770.14 1,456,689.65
Besi beton polos 86.9817 KG 9,174.95 798,052.67
2,744,372.32 2,744,372.32
G-S Membuat 1 M3 Plat Dak T=8Cm
Beton Site Mix 1PC : 2Ps :3Kr 1.0000 M3 489,630.00 489,630.00
Bekisting PAKAI 14.6600 M2 137,770.14 2,019,710.31
Besi beton polos 111.8578 KG 9,174.95 1,026,289.36
3,535,629.66 3,535,629.66
G-T Membuat 1 M3 Plat Dak T=10Cm
Beton Site Mix 1PC : 2Ps :3Kr 1.0000 M3 489,630.00 489,630.00
Bekisting PAKAI 12.2000 M2 137,770.14 1,680,795.75
Besi beton polos 106.5312 KG 9,174.95 977,418.43
3,147,844.19 3,147,844.19
G-U Membuat 1 M3 Balok 20/30
Beton Site Mix 1PC : 2Ps :3Kr 1.0000 M3 489,630.00 489,630.00
Bekisting 2XPAKAI 9.3333 M2 115,624.97 1,079,166.36
Besi beton polos 138.0839 KG 9,174.95 1,266,913.26
2,835,709.62 2,835,709.62
G-V Membuat 1 M3 Balok 15/20
Beton Site Mix 1PC : 2Ps :3Kr 1.0000 M3 489,630.00 489,630.00
Bekisting 2XPAKAI 13.3333 M2 115,624.97 1,541,666.23
Besi beton polos 159.3649 KG 9,174.95 1,462,164.64
3,493,460.87 3,493,460.87
Pekerja 0.1500 HOK 35,000.00 5,250.00
Tukang kayu 0.0750 HOK 45,000.00 3,375.00
Kepala tukang 0.0080 HOK 50,000.00 400.00
Mandor 0.0080 HOK 50,000.00 400.00
Total 9,425.00 3,147,844.19
Total Harga 3,157,269.19
Keuntungan 473,590.38
Jumlah Total 3,630,859.57
a b c d e f=(cxe) g=(cxe) h 5495470000
I PEKERJAAN LANGIT-LANGIT
I-02 1 m2 LANGIT-LANGIT ASBES (1.00X1.00 ) m, TEBAL 5 mm
Plat asbes 5mm 1.1000 Lbr 8,000.00 8,800.00
Paku 0.0100 Kg 11,000.00 110.00
Pekerja 0.0300 HOK 35,000.00 1,050.00
Tukang kayu 0.0700 HOK 45,000.00 3,150.00
Kepala tukang 0.0070 HOK 50,000.00 350.00
Mandor 0.0015 HOK 50,000.00 75.00
Total 4,625.00 8,910.00
Total Harga 13,535.00
Keuntungan
Jumlah Total 13,535.00
J PEKERJAAN SANITASI
J-01 MEMASANG 1 BUAH KLOSET DUDUK /MONOBLOK
Kloset duduk /monoblok 1.0000 Unit *) 1,566,600.00 1,566,600.00
Perlengkapan 6.00% Harga Kloset 1,566,600.00 93,996.00
Pekerja 3.3000 HOK 35,000.00 115,500.00
Tukang batu 1.1000 HOK 45,000.00 49,500.00
Kepala tukang 0.0010 HOK 50,000.00 50.00
Mandor 0.1600 HOK 50,000.00 8,000.00
Total 173,050.00 1,660,596.00
Total Harga 1,833,646.00
Keuntungan 275,046.90
Jumlah Total 2,108,692.90
J-16 MEMASANG 1 BUAH BAK KONTROL PASANGAN BATU BATA (30X30) CM TINGGI 35 CM
Batu bata 0.1450 m3 0.00
Semen Portland 44.0000 Kg 0.00
Pasir Pasang 0.0700 m3 0.00
Batu kerikil 0.0700 m3 0.00
Besi beton 1.6000 Kg 0.00
Pasir beton 0.0600 m3 0.00
Pekerja 3.2000 HOK 0.00
Tukang batu 1.0150 HOK 0.00
Kepala tukang 0.0015 HOK 0.00
Mandor 0.0160 HOK 0.00
Total 0.00 0.00
Total Harga -
Keuntungan -
Jumlah Total -
J-17 MEMASANG 1 BUAH BAK KONTROL PASANGAN BATU BATA (45X45) CM TINGGI 50 CM
Batu bata 0.2500 m3 0.00 0.00
Semen Portland 77.0000 Kg 0.00 0.00
Pasir Pasang 0.1300 m3 0.00 0.00
a b c d e f=(cxe) g=(cxe) h 5495470000
Batu kerikil 0.0200 m3 0.00 0.00
Besi beton 2.6000 Kg 0.00 0.00
Pasir beton 0.0900 m3 0.00 0.00
Pekerja 1.4200 HOK 0.00 0.00
Tukang batu 0.4730 HOK 0.00 0.00
Kepala tukang 0.0470 HOK 0.00 0.00
Mandor 0.0710 HOK 0.00 0.00
Total 0.00 0.00
Total Harga -
Keuntungan -
Jumlah Total -
J-18 MEMASANG 1 BUAH BAK KONTROL PASANGAN BATU BATA (60x60) CM TINGGI 65 CM
Batu bata 0.3710 m3 0.00
Semen Portland 114.0000 Kg 0.00
Pasir Pasang 0.1840 m3 0.00
Batu koral 0.0330 m3 0.00
Besi beton 4.8500 Kg 0.00
Pasir beton 0.1200 m3 0.00
Pekerja 2.1600 HOK 0.00
Tukang batu 0.7200 HOK 0.00
Tukang gali 0.1000 HOK 0.00
Kepala tukang 0.0720 HOK 0.00
Mandor 0.1080 HOK 0.00
Total 0.00 0.00
Total Harga -
Keuntungan -
Jumlah Total -
DIHITUNG 1 UNIT SEPTICTANK 1.5 x 1.0 X 1.5 m (TYPE KECIL) + REMBESAN (A082)
Galian Tanah 2.2500 m3 0.00
Pasir urug 0.1071 m3 0.00
Lantai kerja 1 : 3 : 5 1.1250 m3 0.00
Pasangan bata + Plesteran 1 : 3 7.5000 m2 0.00
Plat beton penutup + balok 0.1500 m3 0.00
Pipa PVC 4" AW + sambungan 9.0000 m' 0.00
Pipa GIF 1 1/2" 0.6000 m' 0.00
Galian tanah untuk rembesan 1.6875 m3 0.00
Pasangan ijuk 2.7000 kg 0.00
Urugan kerikil 3.5 cm 0.5250 m3 0.00
Pipa PVC 4" AW berlobang 9.0000 m' 0.00
Urugan kembali perataan tanah 0.5625 m3 0.00
Tambahan upah kerja 0.0850 Ls 0.00
Total 0.00 0.00
Total Harga -
Keuntungan -
Jumlah Total -
K-20 1 m' PASANG TALANG 1/2 LINGKARAN Ø10 cm, SENG BJLS 28
Seng plat 3' x 6' BJLS 28 0.3000 Lbr 0.00 0.00
Paku biasa 1/2" - 1" 0.1000 Kg 11,000.00 1,100.00
Kayu borneo, papan 0.0190 m3 2,200,000.00 41,800.00
Besi strip 0.5000 Kg 11,000.00 5,500.00
Pekerja 0.1500 HOK 35,000.00 5,250.00
Tukang kayu 0.2500 HOK 45,000.00 11,250.00
Kepala tukang 0.0250 HOK 50,000.00 1,250.00
Mandor 0.00125 HOK 50,000.00 62.50
Total 17,812.50 48,400.00
Total Harga 66,212.50
Keuntungan 9,931.88
Jumlah Total 76,144.38
Dihitung 1 Kg BESI
Besi Profil 1.0500 Kg 12,500.00 13,125.00
Pekerja 0.0600 Kg 35,000.00 2,100.00
Tukang Besi Profil Terampil 0.0040 HOK 43,500.00 174.00
Kepala Tukang Besi Profil 0.0010 HOK 44,500.00 44.50
Mandor 0.0002 HOK 50,000.00 10.00
Peralatan (O2,Solar, Elpiji, kawat las dll) 0.1250 HOK 23,187.50 2,898.44
N PEKERJAAN PENGECATAN
N-01 1 m2 MENGIKIS / MENGEROK PERMUKAAN CAT TEMBOK LAMA
Soda api 0.0500 Kg 0.00 0.00
Pekerja 0.1500 HOK 35,000.00 5,250.00
Mandor 0.0025 HOK 50,000.00 125.00
Total 5,375.00 0.00
Total Harga 5,375.00
Keuntungan 806.25
Jumlah Total 6,181.25
N-03 1 m2 MENGEROK KARAT CAT LAMA PERMUKAAN BAJA DENGAN CARA MANUAL
Sabun 0.0500 Kg 1,500.00 75.00
Pekerja 0.1500 HOK 35,000.00 5,250.00
Mandor 0.0025 HOK 50,000.00 125.00
Total 5,375.00 75.00
Total Harga 5,450.00
Keuntungan 817.50
Jumlah Total 6,267.50
N-08 1 m2 PENGECATAN BIDANG KAYU BARU (1 Lapis Plamir; 1 Lapis Cat dasar; 2 Lapis Cat Penutup)
Cat meni 0.2000 Kg 15,000.00 3,000.00
Plamir 0.1500 Kg 12,000.00 1,800.00
Cat dasar 0.1700 Kg 35,000.00 5,950.00
Cat Penutup ( 2 kali ) 0.2600 Kg 35,000.00 9,100.00
Pekerja 0.0700 HOK 35,000.00 2,450.00
Tukang cat 0.0090 HOK 40,000.00 360.00
Kepala tukang 0.0060 HOK 50,000.00 300.00
Mandor 0.0025 HOK 50,000.00 125.00
Total 3,235.00 19,850.00
Total Harga 23,085.00
Keuntungan
Jumlah Total 23,085.00
N-09 1 m2 PENGECATAN BIDANG KAYU BARU (1 Lapis Plamir; 1 Lapis Cat dasar; 3 Lapis Cat Penutup)
a b c d e f=(cxe) g=(cxe) h 5495470000
Cat meni 0.2000 Kg 15,000.00 3,000.00
Plamir 0.1500 Kg 12,000.00 1,800.00
Cat dasar 0.1700 Kg 35,000.00 5,950.00
Cat Penutup ( 3 kali ) 0.3500 Kg 35,000.00 12,250.00
Pekerja 0.0700 HOK 35,000.00 2,450.00
Tukang cat 0.1050 HOK 40,000.00 4,200.00
Kepala tukang 0.0040 HOK 50,000.00 200.00
Mandor 0.0025 HOK 50,000.00 125.00
Total 6,975.00 23,000.00
Total Harga 29,975.00
Keuntungan 4,496.25
Jumlah Total 34,471.25
N-14 1 m2 PENGECATAN BIDANG TEMBOK BARU (1 Lapis Plamir; 1 Lapis Cat dasar; 2 Lapis Cat Penutup)
Plamir 0.1000 Kg 12,000.00 1,200.00
Cat dasar 0.1000 Kg 12,000.00 1,200.00
Cat Penutup ( 2 kali ) 0.2600 Kg 12,000.00 3,120.00
Pekerja 0.0200 HOK 35,000.00 700.00
Tukang cat 0.0630 HOK 40,000.00 2,520.00
Kepala tukang 0.0063 HOK 50,000.00 315.00
Mandor 0.0025 HOK 50,000.00 125.00
Total 3,660.00 5,520.00
Total Harga 9,180.00
Keuntungan
Jumlah Total 9,180.00
N-15 1 m2 PENGECATAN BIDANG TEMBOK LAMA ( 1 Lapis Cat dasar; 2 Lapis Cat Penutup )
Cat dasar 0.1200 Kg 12,000.00 1,440.00
Cat Penutup ( 2 kali ) 0.1800 Kg 12,000.00 2,160.00
Pekerja 0.0280 HOK 35,000.00 980.00
Tukang cat 0.0420 HOK 40,000.00 1,680.00
Kepala tukang 0.0042 HOK 50,000.00 210.00
Mandor 0.0025 HOK 50,000.00 125.00
a b c d e f=(cxe) g=(cxe) h 5495470000
Total 2,995.00 3,600.00
Total Harga 6,595.00
Keuntungan 989.25
Jumlah Total 7,584.25
N-22 1 m2 PENGECATAN PERMUKAAN BAJA LAPIS SENG GALBANI SECARA MANUAL (4 lapis cat konvensional, tebal 200 um)
Cat dasar 0.1100 Kg 0.00
Cat antara 0.1700 Kg 0.00
Cat penutup 0.0800 Kg 0.00
Pekerja 0.5000 HOK 0.00
Tukang cat 0.8000 HOK 0.00
Kepala tukang 0.3000 HOK 0.00
Mandor 0.2000 HOK 0.00
Total 0.00 0.00
Total Harga -
N-23 1 m2 PENGECATAN PERMUKAAN BAJA LAPIS GALBANI SECARA MANUAL (1 lapis cat mutakhir, tebal 200 um)
Cat 0.3000 Kg 45,000.00 13,500.00
Pekerja 0.0060 HOK 85,000.00 510.00
Tukang cat 0.0600 HOK 105,000.00 6,300.00
Kepala tukang 0.0120 HOK 110,000.00 1,320.00
Mandor 0.0060 HOK 120,000.00 720.00
Total 8,850.00 13,500.00
Total Harga 22,350.00
Keuntungan 3,352.50
Jumlah Total 25,702.50
O-01 1 M2 HOTMIX TANGAN T=3 CM (JADI) UNTUK HALAMAN & JALAN KLS 6 TON KE BAWAH
Abu Batu 0.0360 M3 115,000.00 4,140.00
Aspal Penetrasi 5.0000 M3 8,064.52 40,322.58
a b c d e f=(cxe) g=(cxe) h 5495470000
Kayu Bakar 0.0080 Kg 90,000.00 720.00
Pekerja setengah terampil 0.0800 M3 85,000.00 6,800.00
Pekerja Terampil 0.0300 Ls 105,000.00 3,150.00
Mandor 0.0100 HOK 120,000.00 1,200.00
Peralatan 0.0980 Lot 56,332.58 5,520.59
Total 16,670.59 45,182.58 61,853.17
Keuntungan 9,277.98
Total Harga 71,131.15
isi pada cell berwarna biru saja, pami teu ngartos, tataros nyak..
Pot. A-A 1.00 0.50 0.30 129.50 97.13 84.18 0.00 129.50 51.80 25.90 Galian Tipe 2
Pot. B-B 0.00 0.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Galian Tipe 2
Pot. C-C 0.40 0.00 0.00 0.00 0.00 0.00 0.00 Galian Tipe 2
Pot. D-D 0.40 0.00 0.00 0.00 0.00 0.00 0.00 Galian Tipe 2
Pot. E-E 0.40 0.00 0.00 0.00 0.00 0.00 0.00 Galian Tipe 2
Lantai 1.00 0.30 0.00 0.00 0.00 0.00
Jumlah 129.50 97.13 84.18 0.00 129.50 51.80 25.90
4,000,000,000
Rehabilitasi Irigasi Desa Citapen, Kecamatan Sadananya
PAS Bro!!
no Uraian
I. Pekerjaan Persiapan
1 Pengukuran Kembali/Uitzet
2 Informasi Kegiatan
3 Direksikeet
1 1 1 ls
1 1 1 ls
1 1 1 Sewa
2764.43 m3
2056.90 0.8 0.6 1 987.3125
2056.90 0.6 1.8 0.79998 1777.118
3208.77 m3
2056.90 0.8 0.6 1 987.3125
2056.90 0.6 1.8 1 2221.453
10 0.83
1
0
0
0
0
0
0
0
0
0
0
LUSSAN PAVING
LEBAR
2.7 2.9 2.59 1.42 1.31 0.41
1.888333
36
67.98
PERHITUNGAN VOLUME PERENCANAAN
A. PEKERJAAN PASANGAN
1. PEK. PAS. SAL. Tinggi 1 m POT. A-A
PASANGAN SALURAN 1. Perhitungan Volume Galian Tanah Bi Perhitungan Volume Galian Tanah
Ba
a = 0.3 m A galian = ((a+0,5)/2) x b x p A galian = cxdxp
b = 1.0 m 4,000,000,000.00 = ( (0.3 + 0,5)/ 2) x 1 x 186 = ( 0.4 + 0.7 ) x 186
c = 0.4 m = 74.40 m3 = 52.08 m3
d = 0.7 m 93
e = d - a - 0,20 = 0.2 m 2. Perhitungan Urugan Tanah
p = 186.00 m A urugan = e/2 x b x p
a e = 0.2/2 x 1 x 186
= 18.60 m3
3. Perhitungan Volume Pas. Batu Kali 1PC : 4Ps
Pen I
AI = (a+0,5)/2 x b
= (0.3 + 0,5)/2 x 1 = 0.4 m2
Pen II
A II = c x d = 0.4 x 0.7 = 0.28 m2 +
b
a = 0.2/2 x 1.2 x 45
e
= 5.40 m3
3. Perhitungan Volume Pas. Batu Kali 1PC : 4Ps
Pen I
AI = (a+0,5)/2 x b
= (0.3 + 0,5)/2 x 1.2 = 0.48 m2
b
Pen II
I
A II = c x d = 0.4 x 0.7 = 0.28 m2 +
Luas Total Pen (A I + A II) 0.8 m2
0.76 x 45.00 = 34.2 m3
V plesteran = (a + 0,1) x p
= ( 0.3 + 0,1 ) x 45
d
= 18.00 m2
5. Perhitungan Volume Pas. Siaran 1PC : 2Ps
V siaran = (b-0,05) x p
= (1.2 - 0,05)x 45
= 51.75 m2
ANALISA HARGA SATUAN JARAK ANGKUT 200 M'
HARGA PERKIRAAN PERENCANA
TAHUN ANGGARAN 2021
HARGA JUMLAH
KODE BIAYA
URAIAN PEKERJAAN VOLUME SATUAN SATUAN BIAYA
ANALISIS
( Rp ) ( Rp ) ( Rp )
I. Pekerjaan Persiapan
JUMLAH BOBOT I II
No. URAIAN PEKERJAAN Keterangan
BIAYA (%) 1 2 3 4 5 6 7 8
I. PEKERJAAN PERSIAPAN
100%
1 Pengukuran Kembali/Uitzet 750,000.00 #REF! #REF! #REF!
2 Informasi Kegiatan 300,000.00 #REF! #REF!
3 Direksikeet 500,000.00 #REF! #REF!
II PEKERJAAN PELAKSANAAN
1 #REF! #REF! #REF! #REF!
2 PEKERJAAN PASANGAN 0.00 #REF! #REF!
3 #REF! #REF! #REF! #REF! #REF! #REF! #REF!
4 Pasangan batu dengan mortar tipe N 3,248,438,871.56 #REF! #REF! #REF! 50%
5 Plesteran tebal 1,5 cm dengan mortar tipe S 68,532,314.91 #REF! #REF! #REF!
6 #REF! #REF! #REF! #REF!
III PEKERJAAN PEMBANTU
1 Profil / Esteger 11,007,162.88 #REF! #REF! #REF! #REF! #REF! #REF! #REF!
2 Kistdam pasir/tanah 0.00 #REF! #REF! #REF! #REF! #REF! #REF! #REF!
3 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
II BAHAN/MATERIAL
1 Semen Portland/PC (50 kg) zak M.01 56,000.00 T.15a.6) Mengangkut 1 m³ material dengan jarak angkut 100 m 2,481.00 58,481.00
2 Batu Belah m³ M.02 142,000.00 T.15a.6) Mengangkut 1 m³ material dengan jarak angkut 100 m 46,658.00 188,658.00
3 Pasir Pasang m³ M.03 142,000.00 T.15a.6) Mengangkut 1 m³ material dengan jarak angkut 100 m 63,534.00 205,534.00
4 Pasir Beton m³ M.04 200,000.00 T.15a.6) Mengangkut 1 m³ material dengan jarak angkut 100 m 59,563.00 259,563.00
5 Batu Pecah 2/3 m³ M.05 190,000.00 T.15a.6) Mengangkut 1 m³ material dengan jarak angkut 100 m 62,541.00 252,541.00
6 Kerikil m³ M.06 160,000.00 T.15a.6) Mengangkut 1 m³ material dengan jarak angkut 100 m 62,541.00 222,541.00
7 Tanah Urug m³ M.07 50,000.00 T.21a Mengangkut 1 m³ material dengan jarak angkut 100 m 62,541.00 112,541.00
8 Pipa PVC AW Ø 1,5" m' M.08 9,500.00 9,500.00
9 Ijuk kg M.09 7,000.00 7,000.00
10 Paku Ukuran 10cm, 7cm dan 5cm kg M.10 14,000.00 14,000.00
11 Paku Beton Ukuran 7cm kg M.11 14,000.00 14,000.00
12 Besi Beton kg M.12 11,000.00 11,000.00
13 Kawat Beton kg M.13 14,000.00 14,000.00
14 Kayu Gunung Kls II m³ M.14 2,500,000.00 2,500,000.00
15 Papan Albasiah m³ M.15 2,000,000.00 2,000,000.00
16 Kaso Albasiah m³ M.16 2,000,000.00 2,000,000.00
17 Kayu Dolken m' M.17 6,000.00 6,000.00
18 Bambu m' M.18 1,400.00 1,400.00
19 Multiflex 18 mm lbr M.19 249,600.00 249,600.00
20 Karung Plastik (Bagor) buah M.20 2,000.00 2,000.00
21 Tali Plastik (Rapia) m' M.21 500.00 500.00
Harga Satuan HSD Lokasi
Biaya Angkutan Material ke Lokasi Pekerjaan
NO. URAIAN SATUAN KODE Dasar Pekerjaan KET.
( Rp ) Kode Deskripsi (Rp.) (Rp.)
1 2 3 4 5 6 7
22 Minyak Pelumas L M.22 6,000.00 6,000.00
23 Solar L M.23 6,900.00 6,900.00
24 Minyak Tanah L M.24 8,000.00 8,000.00
25 Air L M.25 200.00 200.00
26 Bronjong Kawat Ø3mm buah M.26 300,000.00 300,000.00
27 Bronjong Kawat Ø4mm buah M.27 350,000.00 350,000.00
28 Bronjong Kawat Ø5mm buah M.28 500,000.00 500,000.00
29 Buis Beton Ø=20cm; L=100cm buah M.29 25,000.00 25,000.00
30 Buis Beton Ø=30cm; L=100cm buah M.30 35,000.00 35,000.00
31 Buis Beton Ø=40cm; L=100cm buah M.31 60,000.00 60,000.00
32 Buis Beton Ø=60cm; L=50cm buah M.32 60,000.00 60,000.00
33 Buis Beton Ø=80cm; L=50cm buah M.33 80,000.00 80,000.00
Lampiran A.1
Pekerjaan Tanah
Pekerjaan tanah ini meliputi pekerjaan galian dan timbunan tanah serta houling yang dapat dilaksanakan baik secara manual dengan tenaga
manusia dan juga secara mekanisasi.
A Tenaga Kerja
1 Pekerja L.01 OH 0.0600 85,000.00 5,100.00
2 Tukang kayu L.02 OH 0.0200 105,000.00 2,100.00
3 Mandor L.04 OH 0.0060 120,000.00 720.00
4 Juru Ukur L.05 OH 0.0200 100,000.00 2,000.00
5 Pembantu Juru Ukur L.06 OH 0.0200 50,000.00 1,000.00
Jumlah Harga Tenaga Kerja 10,920.00
B Bahan
1 Kaso 4/6 cm M.16 m3 0.0025 2,000,000.00 5,000.00
2 Papan 2/20 M.15 m 3
0.0042 2,000,000.00 8,400.00
3 Paku M.10 kg 0.2000 14,000.00 2,800.00
Jumlah Harga Bahan 16,200.00
C Peralatan
1 Waterpass E.02 Sewa-hari 0.0040 200,000.00 800.00
Jumlah Harga Peralatan 800.00
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 27,920.00
E Overhead + Profit 15% x D 4,188.00
F Harga Satuan Pekerjaan per - m1 (D+E) 32,108.00
A Tenaga Kerja
1 Pekerja L.01 OH 0.5630 85,000.00 47,855.00
2 Mandor L.04 OH 0.0563 120,000.00 6,756.00
Jumlah Harga Tenaga Kerja 54,611.00
B Bahan
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 54,611.00
E Overhead + Profit 15% x D 8,191.65
F Harga Satuan Pekerjaan per - m3 (D+E) 62,802.65
T.14 Timbunan dan Pemadatan
T.14a 1 m3 Timbunan tanah atau urugan tanah kembali termasuk perataan dan perapihan
Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 0.3300 85,000.00 28,050.00
2 Mandor L.04 OH 0.0330 120,000.00 3,960.00
Jumlah Harga Tenaga Kerja 32,010.00
B Bahan
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 32,010.00
E Overhead + Profit 15% x D 4,801.50
F Harga Satuan Pekerjaan per - m3 (D+E) 36,811.50
T.15 BIAYA ANGKUTAN SECARA MANUAL (BIAYA ANGKUTAN DIMASUKKAN DALAM HSD - BAHAN)
Perhitungan konversi berbagai jenis material dengan jarak angkut, naik dan turun; seperti pada tabel di bawah. Kode pekerjaan T.15a.5) s.d T.15a.10)
untuk mengangkut 1 m³ berbagai jenis material dengan jarak horizontal termasuk juga pelandaian turun < 20° serta pelandaian naik < 15° yang dihitung
sebagai panjang lintasannya. Material dengan tingkat kemudahan seperti besi beton dan pasir/koral/tanah/plastik, maka angkutan jarak horizontal datar,
vertikal turun dan naik, dikalikan lagi koefisien AHSP-nya besi beton x 0,7 dan pasir/koral/tanah/plastik x 1,0.
A Tenaga Kerja
1 Pekerja L.01 OH 1.9500 85,000.00 165,750.00
2 Mandor L.04 OH 0.0975 120,000.00 11,700.00
Jumlah Harga Tenaga Kerja 177,450.00
B Bahan
1 Tanah Urug M.06 m3 1.00 112,541.00 112,541.00
Berbagai jenis pekerjaan pasangan batu yang termasuk lapisan penutup batu muka dan lainnya. Pasangan batu dapat berupa pasangan batu
dengan mortar ataupun tanpa mortar. Sesuai dengan SNI 03-6882-2002, "Spesifikasi Mortar untuk Pekerjaan Pasangan" diklasifikasikan
berdasarkan kekuatan tekan mortarnya PC-PP. Untuk kedua jenis tersebut terbagi pula menjadi empat tipe mortar yaitu mortar tipe M (17,2 MPa);
tipe S (12,5 MPa); tipe N (5,2 MpPa) dan tipe O (2,4 MPa). Sehubungan dengan hal tersebut, maka AHSP untuk berbagai jenis pasangan tersebut
adalah sebagai berikut:
A Tenaga Kerja
1 Pekerja L.01 OH 0.3000 85,000.00 25,500.00
2 Tukang batu L.02 OH 0.1500 105,000.00 15,750.00
3 Kepala Tukang L.03 OH 0.0150 110,000.00 1,650.00
4 Mandor L.04 OH 0.0300 120,000.00 3,600.00
Jumlah Harga Tenaga Kerja 46,500.00
B Bahan
1 Pasir Pasang M.03 m3 0.0120 205,534.00 2,466.41
2 Portland Cement M.01 kg 6.3400 1,169.62 7,415.39
Jumlah Harga Bahan 9,881.80
C Peralatan
Jumlah Harga Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 56,381.80
E Overhead + Profit 15% x D 8,457.27
F Harga Satuan Pekerjaan per - m2 (D+E) 64,839.07
P.04e Plesteran tebal 1,5 cm, dengan mortar jenis PC-PP tipe S (mutu PP tertentu setara dengan campuran 1 PC:3 PP)
Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 0.3840 85,000.00 32,640.00
2 Tukang batu L.02 OH 0.1920 105,000.00 20,160.00
3 Kepala Tukang L.03 OH 0.0190 110,000.00 2,090.00
4 Mandor L.04 OH 0.0190 120,000.00 2,280.00
Jumlah Harga Tenaga Kerja 57,170.00
B Bahan
1 Pasir Pasang M.03 m3 0.0300 205,534.00 6,166.02
2 Portland Cement M.01 kg 7.7760 1,169.62 9,094.97
Jumlah Harga Bahan 15,260.99
C Peralatan
Jumlah Harga Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 72,430.99
E Overhead + Profit 15% x D 10,864.65
F Harga Satuan Pekerjaan per - m2 (D+E) 83,295.63
Berbagai jenis pekerjaan yang dikelompokkan dalam pekerjaan dewatering meliputi pembuatan dan pemasangan kistdam dan pemompaan air pada
daerah kerja yang analisanya sebagai berikut:
A Tenaga Kerja
1 Pekerja L.01 OH 0.0400 85,000.00 3,400.00
2 Mandor L.04 OH 0.0040 120,000.00 480.00
Jumlah Harga Tenaga Kerja 3,880.00
B Bahan
1 Karung plastik / bagor M.20 bh 1.0000 2,000.00 2,000.00
2 Tali rapia / plastik M.21 m 2.0000 500.00 1,000.00
3 Sewa pasir * M.03 m3 0.0600 205,534.00 12,332.04
Jumlah Harga Bahan 15,332.04
C Peralatan
Jumlah Harga Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 19,212.04
E Overhead + Profit 15% x D 2,881.81
F Harga Satuan Pekerjaan per - buah (D+E) 22,093.85
* Koef. dihitung 50%, jika penggunaan kistdam selesai, pasir dimanfaatkan kembali, gunakan HS pasir 100%
D.05 Pengoperasian per hari selama 24 jam 1 buah pompa air diesel daya 10 kW dengan suction head max. 3m dan discharge head max. 20m
(kapasitas 1 m3/s pada suction head 1m dan discharge head 10m)
Pengoperasian pompa diasumsikan akan beroperasi 24 jam dan disediakan 20% pompa cadangan (misalkan untuk 5 buah pompa
dioperasikan dan 1 cadangan), maka biaya operasi per 1 bh pompa:
HARGA JUMLAH
KODE BIAYA
URAIAN PEKERJAAN VOLUME SATUAN SATUAN BIAYA
ANALISIS
( Rp ) ( Rp ) ( Rp )
I. Pekerjaan Persiapan
Sub Total
II. Pekerjaan Pelaksanaan
Sub Total
III. Pekerjaan Pembantu
1 Profil / Esteger T.05.a 27.00 m'
2 Kistdam pasir/tanah D.01a 12.00 bh
Sub Total
Jumlah Sub.
PPN 10%
Jumlah Total
Dibulatkan
Terbilang :
Tasikmalaya, 2019
Mengetahui, Penawar
Kepala Bidang SDA PT/CV