ANALISA HARGA SATUAN PEKERJAAN

WILAYAH KOTA TASIKMALAYA


TAHUN ANGGARAN 2009
Keuntungan 10 % 0.1000
HARGA HARGA HARGA SATUAN
KODE JENIS PEKERJAAN KOEFISIEN SATUAN UPAH BAHAN PEKERJAAN
( Rp ) ( Rp ) ( Rp ) ( Rp )
a b c d e f=(cxe) g=(cxe) h

A PEKERJAAN PERSIAPAN
A-01 1 m' PAGAR SEMENTARA DARI KAYU, tinggi=2 METER
Dolken Kayu D 8-10/400 Cm 1.2500 Btg 14,000.00 17,500.00
Semen Portland 2.5000 kg 1,030.00 2,575.00
Pasir Beton 0.0050 m3 125,000.00 625.00
Koral Beton 0.0090 m3 125,000.00 1,125.00
Kayu 5/7 0.0720 m3 1,400,000.00 100,800.00
Paku biasa 2"-5" 0.0600 Kg 9,000.00 540.00
Residu 0.4000 Lt 1,100.00 440.00
Tukang Kayu 0.2000 HOK 42,000.00 8,400.00
Pekerja 0.4000 HOK 30,000.00 12,000.00
Kepala Tukang 0.0200 HOK 42,000.00 840.00
Mandor 0.0200 HOK 41,000.00 820.00
Total 22,060.00 123,605.00
Total Harga 145,665.00
Keuntungan 14,566.50
Jumlah Total 160,231.50

A-02 1 m' PAGAR SEMENTARA /PENGAMAN PROYEK DARI SENG GELOMBANG, tinggi=2 METER
Dolken Kayu D 8-10/400 Cm 1.2500 Btg 14,000.00 17,500.00
Semen Portland 2.5000 Kg 1,030.00 2,575.00
Seng gelombang 3"-5" 1.2000 lbr 39,900.00 47,880.00
Pasir Beton 0.0050 m3 125,000.00 625.00
Koral Beton 0.0090 m3 125,000.00 1,125.00
Kayu 5/7 0.0720 m3 2,117,000.00 152,424.00
Paku biasa 2"-5" 0.0600 Kg 9,000.00 540.00
Meni besi 0.4500 Kg 18,000.00 8,100.00
Tukang kayu 0.2000 HOK 42,000.00 8,400.00
Pekerja 0.4000 HOK 30,000.00 12,000.00
Kepala tukang 0.0200 HOK 42,000.00 840.00
Mandor 0.0200 HOK 41,000.00 820.00
Total 22,060.00 230,769.00
Total Harga 252,829.00
Keuntungan 25,282.90
Jumlah Total 278,111.90

A-03 1 m' PAGAR SEMENTARA DARI KAWAT DURI TINGGI 1,8 METER
Dolken Kayu D 8-10/400 Cm 1.0000 Btg 14,000.00 14,000.00
Semen Portland 2.0000 Kg 1,030.00 2,060.00
Kawat Duri 25.0000 Kg 2,500.00 62,500.00
Pasir Beton 0.0050 m3 125,000.00 625.00
Koral Beton 0.0090 m3 125,000.00 1,125.00
Paku biasa 2"-5" 0.0600 Kg 9,000.00 540.00
Tukang kayu 0.2000 HOK 42,000.00 8,400.00
Pekerja 0.3000 HOK 30,000.00 9,000.00
Kepala tukang 0.0200 HOK 42,000.00 840.00
Mandor 0.0200 HOK 41,000.00 820.00
Total 19,060.00 80,850.00
Total Harga 99,910.00
Keuntungan 9,991.00
a b c d e f=(cxe) g=(cxe) h
Jumlah Total 109,901.00

A-04 1 m' PENGUKURAN DAN PEMASANGAN BOUWPLANK


Kayu 5/7 0.0120 m3 1,400,000.00 16,800.00
Paku biasa 2"-5" 0.0200 Kg 9,000.00 180.00
Kayu papan 3/20 0.0070 m3 1,400,000.00 9,800.00
Tukang kayu 0.1000 HOK 42,000.00 4,200.00
Pekerja 0.1000 HOK 30,000.00 3,000.00
Kepala tukang 0.0100 HOK 42,000.00 420.00
Mandor 0.0050 HOK 41,000.00 205.00
Total 7,825.00 26,780.00
Total Harga 34,605.00
Keuntungan 3,460.50
Jumlah Total 38,065.50

A-05 1 m2 PEMBUATAN KANTOR SEMENTARA /DIREKSI DENGAN LANTAI PLESTERAN


Dolken Kayu D 8-10/400 Cm 1.2500 Btg 14,000.00
Kayu 0.1800 m3 1,400,000.00 252,000.00
Paku biasa 0.8500 Kg 9,000.00 7,650.00
Besi strip 1.1000 Kg 12,000.00 13,200.00
Semen Portland 35.0000 kg 1,030.00 36,050.00
Pasir Pasang 0.1500 m3 65,000.00 9,750.00
Pasir Beton 0.1000 m3 125,000.00 12,500.00
Koral Beton 0.1500 m3 90,000.00 13,500.00
Bata Merah 30.0000 Bh 400.00 12,000.00
Seng Plat 0.2500 Lbr 39,900.00 9,975.00
Jendela nako 2.0000 Bh
Kaca Polos 0.0800 m2
Kunci tanam 0.1500 Bh
Plywood 4 mm 0.0600 Lbr
Tukang kayu 2.0000 HOK 42,000.00 84,000.00
Tukang Batu 1.0000 HOK 38,500.00 38,500.00
Pekerja 2.0000 HOK 30,000.00 60,000.00
Kepala Tukang 0.3000 HOK 42,000.00 12,600.00
Mandor 0.0500 HOK 41,000.00 2,050.00
Total 197,150.00 366,625.00
Total Harga 563,775.00
Keuntungan 56,377.50
Jumlah Total 620,152.50

A-06 1 m2 PEMBUATAN GUDANG SEMEN DAN ALAT-ALAT


Dolken Kayu D 8-10/400 Cm 1.7000 Btg 14,000.00 23,800.00
Kayu 0.2100 m3 1,400,000.00 294,000.00
Paku biasa 0.3000 Kg 9,000.00 2,700.00
Semen Portland 10.5000 Kg 1,030.00 10,815.00
Pasir Beton 0.0300 m3 125,000.00 3,750.00
Koral Beton 0.0500 m3 125,000.00 6,250.00
Seng gelombang BJLS 32 1.5000 Lbr 39,900.00 59,850.00
Tukang kayu 2.0000 HOK 42,000.00 84,000.00
Pekerja 1.0000 HOK 30,000.00 30,000.00
Kepala tukang 0.2000 HOK 42,000.00 8,400.00
Mandor 0.0500 HOK 41,000.00 2,050.00
Total 124,450.00 401,165.00
Total Harga 525,615.00
Keuntungan 52,561.50
Jumlah Total 578,176.50
A-07 1 m2 PEMBUATAN RUMAH JAGA / KOSTRUKSI KAYU
Dolken Kayu D 8-10/400 Cm 3.0000 Btg 14,000.00 42,000.00
a b c d e f=(cxe) g=(cxe) h
Kayu 0.2760 m3 1,400,000.00 386,400.00
Paku biasa 0.7000 Kg 9,000.00 6,300.00
Seng gelombang BJLS 32 1.5000 Lbr 39,900.00 59,850.00
Tukang kayu 1.5000 HOK 42,000.00 63,000.00
Pekerja 1.0000 HOK 30,000.00 30,000.00
Kepala tukang 0.1500 HOK 42,000.00 6,300.00
Mandor 0.0500 HOK 41,000.00 2,050.00
Total 101,350.00 494,550.00
Total Harga 595,900.00
Keuntungan 59,590.00
Jumlah Total 655,490.00

A-08 1 m2 PEKERJAAN MEMBERSIHKAN LAPANGAN DAN PERATAAN


Pekerja 0.1000 HOK 30,000.00 3,000.00
Mandor 0.0500 HOK 41,000.00 2,050.00
Total 5,050.00
Total Harga 5,050.00
Keuntungan 505.00
Jumlah Total 5,555.00

A-09 1 m2 PEMBUATAN BEDENG BURUH


Dolken Kayu D 8-10/400 Cm 1.2500 Btg 14,000.00 17,500.00
Kayu 0.1860 m3 1,400,000.00 260,400.00
Paku biasa 0.3000 Kg 9,000.00 2,700.00
Semen Portland 18.0000 Kg 1,030.00 18,540.00
Pasir Beton 0.0300 m3 125,000.00 3,750.00
Koral Beton 0.0500 m3 125,000.00 6,250.00
Seng gelombang BJLS 32 1.5000 Lbr 39,900.00 59,850.00
Plywood 4mm 1.3500 Lbr 48,000.00 64,800.00
Tukang kayu 2.0000 HOK 42,000.00 84,000.00
Pekerja 1.0000 HOK 30,000.00 30,000.00
Kepala tukang 0.2000 HOK 42,000.00 8,400.00
Mandor 0.0500 HOK 41,000.00 2,050.00
Total 124,450.00 433,790.00
Total Harga 558,240.00
Keuntungan 55,824.00
Jumlah Total 614,064.00

A-10 1 m2 PEMBUATAN BAK ADUKAN, UKURAN (40 x 50 x 20) cm


Kayu terentang 0.0360 m3 1,400,000.00 50,400.00
Paku biasa 0.0800 Kg 9,000.00 720.00
Kaso 5/7 1.0000 Btg 7,000.00 7,000.00
Tukang kayu 0.3000 HOK 42,000.00 12,600.00
Mandor 0.0015 HOK 41,000.00 61.50
Total 12,661.50 58,120.00
Total Harga 70,781.50
Keuntungan 7,078.15
Jumlah Total 77,859.65

A-11 1 m2 PEMBUATAN STEGGER DARI BAMBU, UKURAN (40 x 50 x 20) cm


Bambu Ø 6-8/600 cm 1.0000 Btg 0.00 0.00
Tali ijuk 0.2500 Kg 7,000.00 1,750.00
Tukang kayu 0.0170 HOK 42,000.00 714.00
Kepala tukang 0.0020 HOK 42,000.00 84.00
Pekerja 0.2500 HOK 30,000.00 7,500.00
Mandor 0.0130 HOK 41,000.00 533.00
Total 8,831.00 1,750.00
Total Harga 10,581.00
a b c d e f=(cxe) g=(cxe) h
Keuntungan 1,058.10
Jumlah Total 11,639.10

A-12 1 m2 PEMBUATAN JALAN SEMENTARA


Batu belah 15/20 0.1500 m3 67,000.00 10,050.00
Batu Pecah 5/7 0.0900 m3 98,000.00 8,820.00
Pasir pasang 0.0100 m3 95,000.00 950.00
Pekerja 1.0000 HOK 30,000.00 30,000.00
Mandor 0.0500 HOK 41,000.00 2,050.00
Total 32,050.00 19,820.00
Total Harga 51,870.00
Keuntungan 5,187.00
Jumlah Total 57,057.00

A-13 1 m3 BONGKARAN BETON BERTULANG


Pekerja 6.6670 HOK 30,000.00 200,010.00
Mandor 0.3330 HOK 41,000.00 13,653.00
Total 213,663.00
Total Harga 213,663.00
Keuntungan 21,366.30
Jumlah Total 235,029.30

A-14 1 m3 BONGKARAN DINDING TEMBOK BATA MERAH


Pekerja 0.6667 HOK 30,000.00 20,001.00
Mandor 0.0333 HOK 41,000.00 1,365.30
Total 21,366.30
Total Harga 21,366.30
Keuntungan 2,136.63
Jumlah Total 23,502.93

A-15 1 M' PASANG PAGAR KAWAT JARING GALVANIS, TINGGI 1M


A-16 1 M' PASANG PAGAR BETON PRACETAK (5X50X213)CM

Dihitung 1 m2 BONGKARAN PLESTERAN DINDING (A144 Kep.Gub)


Pekerja 0.0500 HOK 30,000.00 1,500.00
Mandor 0.0250 HOK 41,000.00 1,025.00
Total 2,525.00
Total Harga 2,525.00
Keuntungan 252.50
Jumlah Total 2,777.50

Dihitung 1 m2 BONGKARAN GENTENG (A146 Kep.Gub)


Pekerja 0.4000 HOK 30,000.00 12,000.00
Mandor 0.1000 HOK 41,000.00 4,100.00
Total 16,100.00
Total Harga 16,100.00
Keuntungan 1,610.00
Jumlah Total 17,710.00

Dihitung 1 m2 BONGKARAN RANGKA ATAP /RENG+KASO (A147)


Pekerja 0.1000 HOK 30,000.00 3,000.00
Tukang kayu 0.0250 HOK 42,000.00 1,050.00
Kepala tukang kayu 0.0025 HOK 42,000.00 105.00
Mandor 0.0050 HOK 41,000.00 205.00
Total 4,360.00
Total Harga 4,360.00
Keuntungan 436.00
Jumlah Total 4,796.00
a b c d e f=(cxe) g=(cxe) h

Dihitung 1 m3 BONGKARAN KUDA-KUDA, GORDING /BALOK (A150)


Pekerja 4.0000 HOK 30,000.00 120,000.00
Tukang kayu 3.0000 HOK 42,000.00 126,000.00
Mandor 0.2000 HOK 41,000.00 8,200.00
Total 254,200.00
Total Harga 254,200.00
Keuntungan 25,420.00
Jumlah Total 279,620.00

Dihitung 1 m2 BONGKARAN PLAFOND (A162)


Pekerja 0.1250 HOK 30,000.00 3,750.00
Mandor 0.0050 HOK 41,000.00 205.00
Total 3,955.00
Total Harga 3,955.00
Keuntungan 395.50
Jumlah Total 4,350.50

B PEKERJAAN TANAH
B-01 1 m3 GALIAN TANAH BIASA SEDALAM 1 METER
Pekerja 0.4000 HOK 30,000.00 12,000.00
Mandor 0.0400 HOK 41,000.00 1,640.00
Total 13,640.00
Total Harga 13,640.00
Keuntungan 1,364.00
Jumlah Total 15,004.00

B-02 1 m3 GALIAN TANAH BIASA SEDALAM 2 METER


Pekerja 0.5260 HOK 30,000.00 15,780.00
Mandor 0.0520 HOK 41,000.00 2,132.00
Total 17,912.00
Total Harga 17,912.00
Keuntungan 1,791.20
Jumlah Total 19,703.20

B-03 1 m3 GALIAN TANAH BIASA SEDALAM 3 METER


Pekerja 0.7350 HOK 30,000.00 22,050.00
Mandor 0.0730 HOK 41,000.00 2,993.00
Total 25,043.00
Total Harga 25,043.00
Keuntungan 2,504.30
Jumlah Total 27,547.30

B-04 1 m3 GALIAN TANAH KERAS SEDALAM 1 METER


Pekerja 0.6250 HOK 30,000.00 18,750.00
Mandor 0.0620 HOK 41,000.00 2,542.00
Total 21,292.00
Total Harga 21,292.00
Keuntungan 2,129.20
Jumlah Total 23,421.20

B-05 1 m3 GALIAN TANAH CADAS SEDALAM 1 METER


Pekerja 1.2500 HOK 30,000.00 37,500.00
Mandor 0.1250 HOK 41,000.00 5,125.00
Total 42,625.00
Total Harga 42,625.00
Keuntungan 4,262.50
a b c d e f=(cxe) g=(cxe) h
Jumlah Total 46,887.50

B-06 1 m3 GALIAN TANAH LUMPUR SEDALAM 1 METER


Pekerja 0.8230 HOK 30,000.00 24,690.00
Mandor 0.0830 HOK 41,000.00 3,403.00
Total 28,093.00
Total Harga 28,093.00
Keuntungan 2,809.30
Jumlah Total 30,902.30

B-07 1 m2 PEKERJAAN STRIPPING SETINGGI 1 METER


Pekerja 0.0500 HOK 30,000.00 1,500.00
Mandor 0.0050 HOK 41,000.00 205.00
Total 1,705.00
Total Harga 1,705.00
Keuntungan 170.50
Jumlah Total 1,875.50

B-08 1 m3 PEMBUANGAN TANAH SEJAUH 150 METER


Pekerja 0.5160 HOK 30,000.00 15,480.00
Mandor 0.0500 HOK 41,000.00 2,050.00
Total 17,530.00
Total Harga 17,530.00
Keuntungan 1,753.00
Jumlah Total 19,283.00

B-09 1 m3 URUGAN KEMBALI


Pekerja 0.1920 HOK 30,000.00 5,760.00
Mandor 0.0190 HOK 41,000.00 779.00
Total 6,539.00
Total Harga 6,539.00
Keuntungan 653.90
Jumlah Total 7,192.90

B-10 1 m3 PEMADATAN TANAH


Pekerja 0.5000 HOK 30,000.00 15,000.00
Mandor 0.0500 HOK 41,000.00 2,050.00
Total 17,050.00
Total Harga 17,050.00
Keuntungan 1,705.00
Jumlah Total 18,755.00

B-11 1 m3 URUGAN PASIR


Pasir urug 1.2000 m3 50,000.00 60,000.00
Pekerja 0.3000 HOK 30,000.00 9,000.00
Mandor 0.0100 HOK 41,000.00 410.00
Total 9,410.00 60,000.00
Total Harga 69,410.00
Keuntungan 6,941.00
Jumlah Total 76,351.00

B-12 1 m3 LAPISAN PUDEL CAMPURAN 1 KP : 3 PS : 7 TL


B-13 1 m3 LAPISAN PUDEL CAMPURAN 1 KP : 5 TL

B-14 1 m3 PEMASANGAN LAPISAN IJUK


Ijuk 1.2000 m3 7,000.00 8,400.00
Pekerja 0.1500 HOK 30,000.00 4,500.00
Mandor 0.0150 HOK 41,000.00 615.00
a b c d e f=(cxe) g=(cxe) h
Total 5,115.00 8,400.00
Total Harga 13,515.00
Keuntungan 1,351.50
Jumlah Total 14,866.50

B-15 1 m3 URUGAN SIRTU


Sirtu 1.2000 m3 70,000.00 84,000.00
Pekerja 0.2500 HOK 30,000.00 7,500.00
Mandor 0.0250 HOK 41,000.00 1,025.00
Total 8,525.00 84,000.00
Total Harga 92,525.00
Keuntungan 9,252.50
Jumlah Total 101,777.50

B-16 1 m2 PEMBUATAN JALAN SEMENTARA TEBAL 25 CM


Batu Belah 0.2750 m3 67,000.00 18,425.00
Kerikil 0.0300 m3 125,000.00 3,750.00
Pasir 0.0500 m3 50,000.00 2,500.00
Pekerja 1.0000 HOK 30,000.00 30,000.00
Mandor 0.1000 HOK 41,000.00 4,100.00
Total 34,100.00 24,675.00
Total Harga 58,775.00
Keuntungan 5,877.50
Jumlah Total 64,652.50
Dihitung 1 m3 URUGAN TANAH
Tanah Urugan 1.2000 m3 30,000.00 36,000.00
Pekerja 0.3000 HOK 30,000.00 9,000.00
Mandor 0.0100 HOK 41,000.00 410.00
Total 9,410.00 36,000.00
Total Harga 45,410.00
Keuntungan 4,541.00
Jumlah Total 49,951.00

C PEKERJAAN PONDASI
C-01 1 m3 PASANGAN PONDASI BATU KALI, 1 Pc : 1 Ps
Batu belah 15/20 cm 1.1000 m3 67,000.00 73,700.00
Semen Portland 392.0000 Kg 1,030.00 403,760.00
Pasir pasang 0.3140 m3 95,000.00 29,830.00
Pekerja 1.5000 HOK 30,000.00 45,000.00
Tukang batu 0.6000 HOK 38,500.00 23,100.00
Kepala tukang 0.0600 HOK 42,000.00 2,520.00
Mandor 0.0750 HOK 41,000.00 3,075.00
Total 73,695.00 507,290.00
Total Harga 580,985.00
Keuntungan 58,098.50
Jumlah Total 639,083.50

C-02 1 m3 PASANGAN PONDASI BATU KALI, 1 Pc : 2 Ps


Batu belah 15/20 cm 1.1000 m3 67,000.00 73,700.00
Semen Portland 267.0000 Kg 1,030.00 275,010.00
Pasir pasang 0.4270 m3 95,000.00 40,565.00
Pekerja 1.5000 HOK 30,000.00 45,000.00
Tukang batu 0.6000 HOK 38,500.00 23,100.00
Kepala tukang 0.0600 HOK 42,000.00 2,520.00
Mandor 0.0750 HOK 41,000.00 3,075.00
Total 73,695.00 389,275.00
Total Harga 462,970.00
a b c d e f=(cxe) g=(cxe) h
Keuntungan 46,297.00
Jumlah Total 509,267.00

C-04 1 m3 PASANGAN PONDASI BATU KALI, 1 Pc : 3 Ps


Batu belah 15/20 cm 1.1000 m3 67,000.00 73,700.00
Semen Portland 202.0000 Kg 1,030.00 208,060.00
Pasir pasang 0.4850 m3 95,000.00 46,075.00
Pekerja 1.5000 HOK 30,000.00 45,000.00
Tukang batu 0.6000 HOK 38,500.00 23,100.00
Kepala tukang 0.0600 HOK 42,000.00 2,520.00
Mandor 0.0750 HOK 41,000.00 3,075.00
Total 73,695.00 327,835.00
Total Harga 401,530.00
Keuntungan 40,153.00
Jumlah Total 441,683.00

C-05 1 m3 PASANGAN PONDASI BATU KALI, 1 Pc : 4 Ps


Batu belah 15/20 cm 1.1000 m3 67,000.00 73,700.00
Semen Portland 163.0000 Kg 1,030.00 167,890.00
Pasir pasang 0.5200 m3 95,000.00 49,400.00
Pekerja 1.5000 HOK 30,000.00 45,000.00
Tukang batu 0.6000 HOK 38,500.00 23,100.00
Kepala tukang 0.0600 HOK 42,000.00 2,520.00
Mandor 0.0750 HOK 41,000.00 3,075.00
Total 73,695.00 290,990.00
Total Harga 364,685.00
Keuntungan 36,468.50
Jumlah Total 401,153.50

C-06 1 m3 PASANGAN PONDASI BATU KALI, 1 Pc : 5 Ps


Batu belah 15/20 cm 1.1000 m3 67,000.00 73,700.00
Semen Portland 136.0000 Kg 1,030.00 140,080.00
Pasir pasang 0.5440 m3 95,000.00 51,680.00
Pekerja 1.5000 HOK 30,000.00 45,000.00
Tukang batu 0.6000 HOK 38,500.00 23,100.00
Kepala tukang 0.0600 HOK 42,000.00 2,520.00
Mandor 0.0750 HOK 41,000.00 3,075.00
Total 73,695.00 265,460.00
Total Harga 339,155.00
Keuntungan 33,915.50
Jumlah Total 373,070.50

C-07 1 m3 PASANGAN PONDASI BATU KALI, 1 Pc : 6 Ps


Batu belah 15/20 cm 1.1000 m3 67,000.00 73,700.00
Semen Portland 117.0000 Kg 1,030.00 120,510.00
Pasir pasang 0.5610 m3 95,000.00 53,295.00
Pekerja 1.5000 HOK 30,000.00 45,000.00
Tukang batu 0.6000 HOK 38,500.00 23,100.00
Kepala tukang 0.0600 HOK 42,000.00 2,520.00
Mandor 0.0750 HOK 41,000.00 3,075.00
Total 73,695.00 247,505.00
Total Harga 321,200.00
Keuntungan 19,272.00
Jumlah Total 340,472.00

C-08 1 m3 PASANGAN PONDASI BATU KALI, 1 Pc : 8 Ps


Batu belah 15/20 cm 1.1000 m3 67,000.00 73,700.00
Semen Portland 91.0000 Kg 1,030.00 93,730.00
a b c d e f=(cxe) g=(cxe) h
Pasir pasang 0.5610 m3 95,000.00 53,295.00
Pekerja 1.5000 HOK 30,000.00 45,000.00
Tukang batu 0.6000 HOK 38,500.00 23,100.00
Kepala tukang 0.0600 HOK 42,000.00 2,520.00
Mandor 0.0750 HOK 41,000.00 3,075.00
Total 73,695.00 220,725.00
Total Harga 294,420.00
Keuntungan 29,442.00
Jumlah Total 323,862.00

C-09 1 m3 PASANGAN PONDASI BATU KALI, 1 Kp : 1 Sm : 1 Ps


C-10 1 m3 PASANGAN PONDASI BATU KALI, 1 Kp : 1 Sm : 2 Ps
C-11 1 m3 PASANGAN PONDASI BATU KALI, 1 Pc : 1/4 Kp : 4 Ps
C-12 1 m3 PASANGAN PONDASI BATU KALI, 1 Pc : 3 Kp : 10 Ps
C-13 1 m3 PASANGAN PONDASI BATU KALI, 1/4 Pc : 1 Kp : 4 Ps

C-014 1 m3 PASANGAN PONDASI BATU KOSONG


Batu belah 15/20 cm 1.2000 m3 67,000.00 80,400.00
Pasir urug 0.3000 m3 50,000.00 15,000.00
Pekerja 0.7800 HOK 30,000.00 23,400.00
Tukang batu 0.3900 HOK 38,500.00 15,015.00
Kepala tukang 0.0390 HOK 42,000.00 1,638.00
Mandor 0.0390 HOK 41,000.00 1,599.00
Total 41,652.00 95,400.00
Total Harga 137,052.00
Keuntungan 13,705.20
Jumlah Total 150,757.20

C-015 1 m3 PASANGAN PONDASI SIKLOP 40% BATU KALI


Besi beton 75.0000 Kg 8,000.00 600,000.00
Semen Portland 202.0000 Kg 1,030.00 208,060.00
Pasir beton 0.3200 m3 125,000.00 40,000.00
Koral beton 0.4900 m3 125,000.00 61,250.00
Kawat beton 0.8000 Kg 11,000.00 8,800.00
Pekerja 3.0000 HOK 30,000.00 90,000.00
Tukang batu 0.8500 HOK 38,500.00 32,725.00
Kepala tukang 0.0850 HOK 42,000.00 3,570.00
Mandor 0.1500 HOK 41,000.00 6,150.00
Total 132,445.00 918,110.00
Total Harga 1,050,555.00
Keuntungan 105,055.50
Jumlah Total 1,155,610.50

C-016 1 m3 PASANGAN PONDASI SUMURAN DIAMETER 100 cm


Batu belah 15/20 cm 0.4500 m3 67,000.00 30,150.00
Semen Portland 280.0000 Kg 1,030.00 288,400.00
Pasir beton 0.4500 m3 125,000.00 56,250.00
Koral beton 0.6700 m3 125,000.00 83,750.00
Pekerja 2.3800 HOK 30,000.00 71,400.00
Tukang batu 0.3000 HOK 38,500.00 11,550.00
Kepala tukang 0.0300 HOK 42,000.00 1,260.00
Mandor 0.0800 HOK 41,000.00 3,280.00
Total 87,490.00 458,550.00
Total Harga 546,040.00
Keuntungan 54,604.00
Jumlah Total 600,644.00

C-017 1 m3 PEMBUATAN TIANG PANCANG BETON BERTULANG ( 40x40 ) cm,


a b c d e f=(cxe) g=(cxe) h
Pasir urug darat 0.0190 m3 50,000.00 950.00
Pasir beton 0.0940 m3 125,000.00 11,750.00
Koral beton 0.1500 m3 125,000.00 18,750.00
Semen Portland 60.5000 Kg 1,030.00 62,315.00
Besi beton 45.0000 Kg 8,000.00 360,000.00
Kawat beton 0.9000 Kg 11,000.00 9,900.00
Kayu kaso 5/7 0.0320 m3 1,400,000.00 44,800.00
Paku 0.1200 Kg 9,000.00 1,080.00
Minyak bekisting 0.0900 Lt 0.00 0.00
Plamir tembok 0.2400 Kg 22,500.00 5,400.00
Pekerja 1.0000 HOK 30,000.00 30,000.00
Tukang batu 0.6700 HOK 38,500.00 25,795.00
Kepala tukang 0.0670 HOK 42,000.00 2,814.00
Mandor 0.0500 HOK 41,000.00 2,050.00
Total 60,659.00 514,945.00
Total Harga 575,604.00
Keuntungan 57,560.40
Jumlah Total 633,164.40

C-018 1 m3 PEMBUATAN TIANG PANCANG BETON BERTULANG ( 35x35 ) cm,


Pasir urug darat 0.0160 m3 50,000.00 800.00
Pasir beton 0.0800 m3 125,000.00 10,000.00
Koral beton 0.1250 m3 125,000.00 15,625.00
Semen Portland 49.0000 Kg 1,030.00 50,470.00
Besi beton 34.5000 Kg 8,000.00 276,000.00
Kawat beton 0.7000 Kg 11,000.00 7,700.00
Kayu kaso 5/7 0.0270 m3 1,400,000.00 37,800.00
Paku 0.1200 Kg 9,000.00 1,080.00
Minyak bekisting 0.0900 Lt 0.00 0.00
Plamuur tembok 0.2000 Kg 22,500.00 4,500.00
Pekerja 0.8000 HOK 30,000.00 24,000.00
Tukang batu 0.5000 HOK 38,500.00 19,250.00
Kepala tukang 0.0500 HOK 42,000.00 2,100.00
Mandor 0.0400 HOK 41,000.00 1,640.00
Total 46,990.00 403,975.00
Total Harga 450,965.00
Keuntungan 45,096.50
Jumlah Total 496,061.50

D PEKERJAAN DINDING
D-01 1 m2 PASANGAN BATA MERAH TEBAL 1 BATA, 1 PC : 1 Ps
Bata merah ( 5x11x22 ) cm 140.0000 Bh 400.00 56,000.00
Semen Portland 64.0300 Kg 1,030.00 65,950.90
Pasir pasang 0.0590 m3 65,000.00 3,835.00
Pekerja 0.6500 HOK 30,000.00 19,500.00
Tukang batu 0.2000 HOK 38,500.00 7,700.00
Kepala tukang 0.0200 HOK 42,000.00 840.00
Mandor 0.0300 HOK 41,000.00 1,230.00
Total 29,270.00 125,785.90
Total Harga 155,055.90
Keuntungan 15,505.59
Jumlah Total 170,561.49

D-02 1 m2 PASANGAN BATA MERAH TEBAL 1 BATA, 1 PC : 2 Ps


Bata merah ( 5x11x22 ) cm 140.0000 Bh 400.00 56,000.00
Semen Portland 43.5000 Kg 1,030.00 44,805.00
Pasir pasang 0.0800 m3 65,000.00 5,200.00
a b c d e f=(cxe) g=(cxe) h
Pekerja 0.6500 HOK 30,000.00 19,500.00
Tukang batu 0.2000 HOK 38,500.00 7,700.00
Kepala tukang 0.0200 HOK 42,000.00 840.00
Mandor 0.0300 HOK 41,000.00 1,230.00
Total 29,270.00 106,005.00
Total Harga 135,275.00
Keuntungan 13,527.50
Jumlah Total 148,802.50

D-03 1 m2 PASANGAN BATA MERAH TEBAL 1 BATA, 1 PC : 3 Ps


Bata merah ( 5x11x22 ) cm 140.0000 Bh 400.00 56,000.00
Semen Portland 32.9500 Kg 1,030.00 33,938.50
Pasir pasang 0.0910 m3 65,000.00 5,915.00
Pekerja 0.6500 HOK 30,000.00 19,500.00
Tukang batu 0.2000 HOK 38,500.00 7,700.00
Kepala tukang 0.0200 HOK 42,000.00 840.00
Mandor 0.0300 HOK 41,000.00 1,230.00
Total 29,270.00 95,853.50
Total Harga 125,123.50
Keuntungan 12,512.35
Jumlah Total 137,635.85

D-04 1 m2 PASANGAN BATA MERAH TEBAL 1 BATA, 1 PC : 4 Ps


Bata merah ( 5x11x22 ) cm 140.0000 Bh 400.00 56,000.00
Semen Portland 26.5500 Kg 1,030.00 27,346.50
Pasir pasang 0.0930 m3 65,000.00 6,045.00
Pekerja 0.6500 HOK 30,000.00 19,500.00
Tukang batu 0.2000 HOK 38,500.00 7,700.00
Kepala tukang 0.0200 HOK 42,000.00 840.00
Mandor 0.0300 HOK 41,000.00 1,230.00
Total 29,270.00 89,391.50
Total Harga 118,661.50
Keuntungan 11,866.15
Jumlah Total 130,527.65

D-05 1 m2 PASANGAN BATA MERAH TEBAL 1 BATA, 1 PC : 5 Ps


Bata merah ( 5x11x22 ) cm 140.0000 Bh 400.00 56,000.00
Semen Portland 22.2000 Kg 1,030.00 22,866.00
Pasir pasang 0.1020 m3 65,000.00 6,630.00
Pekerja 0.6500 HOK 30,000.00 19,500.00
Tukang batu 0.2000 HOK 38,500.00 7,700.00
Kepala tukang 0.0200 HOK 42,000.00 840.00
Mandor 0.0300 HOK 41,000.00 1,230.00
Total 29,270.00 85,496.00
Total Harga 114,766.00
Keuntungan 11,476.60
Jumlah Total 126,242.60

D-06 1 m2 PASANGAN BATA MERAH TEBAL 1 BATA, 1 PC : 6 Ps


D-07 1 m2 PASANGAN BATA MERAH TEBAL 1 BATA, 1 PC : 3 Kp : 10 Ps
D-08 1 m2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 PC : 1 Ps

D-09 1 m2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 PC : 2 Ps


Bata merah ( 5x11x22 ) cm 70.0000 Bh 400.00 28,000.00
Semen Portland 18.9500 Kg 1,030.00 19,518.50
Pasir pasang 0.0380 m3 65,000.00 2,470.00
Pekerja 0.3200 HOK 30,000.00 9,600.00
Tukang batu 0.1000 HOK 38,500.00 3,850.00
a b c d e f=(cxe) g=(cxe) h
Kepala tukang 0.0100 HOK 42,000.00 420.00
Mandor 0.0150 HOK 41,000.00 615.00
Total 14,485.00 49,988.50
Total Harga 64,473.50
Keuntungan 6,447.35
Jumlah Total 70,920.85

D-010 1 m2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 PC : 3 Ps


Bata merah ( 5x11x22 ) cm 70.0000 Bh 400.00 28,000.00
Semen Portland 14.3700 Kg 1,030.00 14,801.10
Pasir pasang 0.0400 m3 65,000.00 2,600.00
Pekerja 0.3200 HOK 30,000.00 9,600.00
Tukang batu 0.1000 HOK 38,500.00 3,850.00
Kepala tukang 0.0100 HOK 42,000.00 420.00
Mandor 0.0150 HOK 41,000.00 615.00
Total 14,485.00 45,401.10
Total Harga 59,886.10
Keuntungan 5,988.61
Jumlah Total 65,874.71

D-011 1 m2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 PC : 4 Ps


Bata merah ( 5x11x22 ) cm 70.0000 Bh 400.00 28,000.00
Semen Portland 11.5000 Kg 1,030.00 11,845.00
Pasir pasang 0.0430 m3 65,000.00 2,795.00
Pekerja 0.3200 HOK 30,000.00 9,600.00
Tukang batu 0.1000 HOK 38,500.00 3,850.00
Kepala tukang 0.0100 HOK 42,000.00 420.00
Mandor 0.0150 HOK 41,000.00 615.00
Total 14,485.00 42,640.00
Total Harga 57,125.00
Keuntungan 5,712.50
Jumlah Total 62,837.50
D-012 1 m2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 PC : 5 Ps
Bata merah ( 5x11x22 ) cm 70.0000 Bh 400.00 28,000.00
Semen Portland 9.6800 Kg 1,030.00 9,970.40
Pasir pasang 0.0450 m3 65,000.00 2,925.00
Pekerja 0.3200 HOK 30,000.00 9,600.00
Tukang batu 0.1000 HOK 38,500.00 3,850.00
Kepala tukang 0.0100 HOK 42,000.00 420.00
Mandor 0.0150 HOKK 41,000.00 615.00
Total 14,485.00 40,895.40
Total Harga 55,380.40
Keuntungan 5,538.04
Jumlah Total 60,918.44

D-013 1 m2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 PC : 6 Ps


D-014 1 m2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 PC : 8 Ps
D-015 1 m2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 PC : 3 Kp : 10 Ps
D-016 1 m2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 Kp : 1 Sm : 1 Ps
D-017 1 m2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 Kp : 1 Sm : 2 Ps

D-018 1 m2 PASANGAN DINDING HOKLLOWBLOCK /BATAKO (HB-20)


Hollow block (HB-20) 12.5000 Bh 2,000.00 25,000.00
Semen Portland 13.5000 Kg 1,030.00 13,905.00
Pasir pasang 0.0480 m3 95,000.00 4,560.00
Besi beton polos 1.9500 Kg 8,000.00 15,600.00
Pekerja 0.3500 HOK 30,000.00 10,500.00
a b c d e f=(cxe) g=(cxe) h
Tukang batu 0.1500 HOK 38,500.00 5,775.00
Kepala tukang 0.0150 HOK 42,000.00 630.00
Mandor 0.0170 HOK 41,000.00 697.00
Total 17,602.00 59,065.00
Total Harga 76,667.00
Keuntungan 7,666.70
Jumlah Total 84,333.70

D-019 1 m2 PASANGAN DINDING HOKLLOWBLOCK /BATAKO (HB-15)


Hollow block (HB-15) 12.5000 Bh 2,000.00 25,000.00
Semen Portland 10.4500 Kg 1,030.00 10,763.50
Pasir pasang 0.0380 m3 95,000.00 3,610.00
Besi beton polos 1.9500 Kg 8,000.00 15,600.00
Pekerja 0.3200 HOK 30,000.00 9,600.00
Tukang batu 0.1200 HOK 38,500.00 4,620.00
Kepala tukang 0.0120 HOK 42,000.00 504.00
Mandor 0.0150 HOK 41,000.00 615.00
Total 15,339.00 54,973.50
Total Harga 70,312.50
Keuntungan 7,031.25
Jumlah Total 77,343.75

D-020 1 m2 PASANGAN DINDING HOKLLOWBLOCK /BATAKO (HB-10)

D-021 1 m2 PASANGAN DINDING CONBLOCK (CB-20)


Concrete block (CB-20) 12.5000 Bh 4,000.00 50,000.00
Semen Portland 14.0500 Kg 1,030.00 14,471.50
Pasir beton 0.0040 m3 125,000.00 500.00
Pasir pasang 0.0420 m3 95,000.00 3,990.00
Besi beton polos 3.8700 Kg 8,000.00 30,960.00
Paku biasa 2"-5" 0.0060 Kg 9,000.00 54.00
Kayu terentang 0.0010 m3 1,400,000.00 1,400.00
Kawat beton 0.0300 Kg 11,000.00 330.00
Koral beton 0.0050 m3 125,000.00 625.00
Pekerja 0.3700 HOK 30,000.00 11,100.00
Tukang batu 0.1570 HOK 38,500.00 6,044.50
Tukang besi 0.0070 HOK 41,000.00 287.00
Kepala tukang 0.0164 HOK 42,000.00 688.80
Mandor 0.0185 HOK 41,000.00 758.50
Total 18,878.80 102,330.50
Total Harga 121,209.30
Keuntungan 12,120.93
Jumlah Total 133,330.23

D-022 1 m2 PASANGAN DINDING CONBLOCK (CB-15)


Concrete block (CB-15) 12.5000 Bh 4,000.00 50,000.00
Semen Portland 10.4600 Kg 1,030.00 10,773.80
Pasir beton 0.0030 m3 125,000.00 375.00
Pasir pasang 0.0320 m3 95,000.00 3,040.00
Besi beton polos Ø 8 mm 0.8700 Kg 8,000.00 6,960.00
Paku biasa 2"-5" 0.0040 Kg 9,000.00 36.00
Kayu terentang 0.0010 m3 1,400,000.00 1,400.00
Kawat beton 0.0200 Kg 11,000.00 220.00
Koral beton 0.0040 m3 125,000.00 500.00
Pekerja 0.3400 HOK 30,000.00 10,200.00
Tukang batu 0.1300 HOK 38,500.00 5,005.00
Tukang besi 0.0070 HOK 41,000.00 287.00
Kepala tukang 0.0137 HOK 42,000.00 575.40
a b c d e f=(cxe) g=(cxe) h
Mandor 0.0170 HOK 41,000.00 697.00
Total 16,764.40 73,304.80
Total Harga 90,069.20
Keuntungan 9,006.92
Jumlah Total 99,076.12

D-023 1 m2 PASANGAN DINDING CONBLOCK (CB-10)


Concrete block (CB-10) 12.5000 Bh 4,000.00 50,000.00
Semen Portland 7.2000 Kg 1,030.00 7,416.00
Pasir beton 0.0020 m3 125,000.00 250.00
Pasir pasang 0.0210 m3 95,000.00 1,995.00
Besi beton polos 2.5400 Kg 8,000.00 20,320.00
Paku biasa 2"-5" 0.0030 Kg 9,000.00 27.00
Kayu terentang 0.0010 m3 1,400,000.00 1,400.00
Kawat beton 0.0150 Kg 11,000.00 165.00
Koral beton 0.0030 m3 125,000.00 375.00
Pekerja 0.3400 HOK 30,000.00 10,200.00
Tukang batu 0.1070 HOK 38,500.00 4,119.50
Tukang besi 0.0070 HOK 41,000.00 287.00
Kepala tukang 0.0114 HOK 42,000.00 478.80
Mandor 0.0170 HOK 41,000.00 697.00
Total 15,782.30 81,948.00
Total Harga 97,730.30
Keuntungan 9,773.03
Jumlah Total 107,503.33

D-024 1 m2 PASANGAN DINDING LATAI

D-025 1 m2 PASANGAN DINDING ROSTER /TERAWANG (12X11X24) cm


Roster /Terawang 36.0000 Bh 3,500.00 126,000.00
Semen Portland 12.8000 Kg 1,030.00 13,184.00
Pasir pasang 0.0350 m3 95,000.00 3,325.00
Pekerja 0.3000 HOK 30,000.00 9,000.00
Tukang batu 0.1000 HOK 38,500.00 3,850.00
Kepala tukang 0.0100 HOK 42,000.00 420.00
Mandor 0.0150 HOK 41,000.00 615.00
Total 13,885.00 142,509.00
Total Harga 156,394.00
Keuntungan 15,639.40
Jumlah Total 172,033.40

D-026 1 m2 PASANGAN BATA BERONGGA UKURAN (5X11X24)CM

D-027 1 m2 PASANGAN DINDING ANYAMAN BAMBU, RANGKA KAYU


Bilik bambu 1.5000 m2 9,000.00 13,500.00
Kayu 5/7 0.0140 m3 1,400,000.00 19,600.00
Paku 0.0120 Kg 9,000.00 108.00
List kayu 2/4 0.0030 m3 8,000.00 24.00
Pekerja 0.1000 HOK 30,000.00 3,000.00
Tukang kayu 0.0500 HOK 38,500.00 1,925.00
Kepala tukang 0.0050 HOK 42,000.00 210.00
Mandor 0.0020 HOK 41,000.00 82.00
Total 5,241.00 33,208.00
Total Harga 38,449.00
Keuntungan 3,844.90
Jumlah Total 42,293.90
a b c d e f=(cxe) g=(cxe) h
E PEKERJAAN PLESTERAN
E-01 1 m2 PLESTERAN 1 PC : 1 Ps, TEBAL 15 mm
Semen Portland 12.9200 kg 1,030.00 13,307.60
Pasir pasang 0.0130 m3 95,000.00 1,235.00
Pekerja 0.2000 HOK 30,000.00 6,000.00
Tukang batu 0.1500 HOK 38,500.00 5,775.00
Kepala tukang 0.0150 HOK 42,000.00 630.00
Mandor 0.0100 HOK 41,000.00 410.00
Total 12,815.00 14,542.60
Total Harga 27,357.60
Keuntungan 2,735.76
Jumlah Total 30,093.36

E-02 1 m2 PLESTERAN 1 PC : 2 Ps, TEBAL 15 mm


Semen Portland 8.5200 kg 1,030.00 8,775.60
Pasir pasang 0.0170 m3 95,000.00 1,615.00
Pekerja 0.2000 HOK 30,000.00 6,000.00
Tukang batu 0.1500 HOK 38,500.00 5,775.00
Kepala tukang 0.0150 HOK 42,000.00 630.00
Mandor 0.0100 HOK 41,000.00 410.00
Total 12,815.00 10,390.60
Total Harga 23,205.60
Keuntungan 2,320.56
Jumlah Total 25,526.16

E-03 1 m2 PLESTERAN 1 PC : 3 Ps, TEBAL 15 mm


Semen Portland 6.4800 kg 1,030.00 6,674.40
Pasir pasang 0.0190 m3 95,000.00 1,805.00
Pekerja 0.2000 HOK 30,000.00 6,000.00
Tukang batu 0.1500 HOK 38,500.00 5,775.00
Kepala tukang 0.0150 HOK 42,000.00 630.00
Mandor 0.0100 HOK 41,000.00 410.00
Total 12,815.00 8,479.40
Total Harga 21,294.40
Keuntungan 2,129.44
Jumlah Total 23,423.84

E-04 1 m2 PLESTERAN 1 PC : 4 Ps, TEBAL 15 mm


Semen Portland 5.2000 kg 1,030.00 5,356.00
Pasir pasang 0.0200 m3 95,000.00 1,900.00
Pekerja 0.2000 HOK 30,000.00 6,000.00
Tukang batu 0.1500 HOK 38,500.00 5,775.00
Kepala tukang 0.0150 HOK 42,000.00 630.00
Mandor 0.0100 HOK 41,000.00 410.00
Total 12,815.00 7,256.00
Total Harga 20,071.00
Keuntungan 2,007.10
Jumlah Total 22,078.10

E-05 1 m2 PLESTERAN 1 PC : 5 Ps, TEBAL 15 mm


Semen Portland 4.3200 kg 1,030.00 4,449.60
Pasir pasang 0.0220 m3 95,000.00 2,090.00
Pekerja 0.2000 HOK 30,000.00 6,000.00
Tukang batu 0.1500 HOK 38,500.00 5,775.00
Kepala tukang 0.0150 HOK 42,000.00 630.00
Mandor 0.0100 HOK 41,000.00 410.00
Total 12,815.00 6,539.60
Total Harga 19,354.60
a b c d e f=(cxe) g=(cxe) h
Keuntungan 1,935.46
Jumlah Total 21,290.06

E-06 1 m2 PLESTERAN 1 PC : 6 Ps, TEBAL 15 mm


Semen Portland 3.6800 kg 1,030.00 3,790.40
Pasir pasang 0.0230 m3 95,000.00 2,185.00
Pekerja 0.2000 HOK 30,000.00 6,000.00
Tukang batu 0.1500 HOK 38,500.00 5,775.00
Kepala tukang 0.0150 HOK 42,000.00 630.00
Mandor 0.0100 HOK 41,000.00 410.00
Total 12,815.00 5,975.40
Total Harga 18,790.40
Keuntungan 1,879.04
Jumlah Total 20,669.44

E-07 1 m2 PLESTERAN 1 PC : 8 Ps, TEBAL 15 mm


Semen Portland 2.8800 kg 1,030.00 2,966.40
Pasir pasang 0.0240 m3 95,000.00 2,280.00
Pekerja 0.2000 HOK 30,000.00 6,000.00
Tukang batu 0.1500 HOK 38,500.00 5,775.00
Kepala tukang 0.0150 HOK 42,000.00 630.00
Mandor 0.0100 HOK 41,000.00 410.00
Total 12,815.00 5,246.40
Total Harga 18,061.40
Keuntungan 1,806.14
Jumlah Total 19,867.54

E-08 1 m2 PLESTERAN 1 PC : 0.5 Kp : 3 Ps, TEBAL 15 mm


E-09 1 m2 PLESTERAN 1 PC : 3 Kp: 10 Ps, TEBAL 15 mm
E-10 1 m2 PLESTERAN 0.5 PC : 1 Kp: 4 Ps, TEBAL 15 mm
E-11 1 m2 PLESTERAN 1 PC : 1 Kp: 1 Ps, TEBAL 15 mm
E-12 1 m2 PLESTERAN 1 PC : 1 Kp: 2 Ps, TEBAL 15 mm

E-13 1 m2 PLESTERAN 1 PC : 2 Ps, TEBAL 20 mm


Semen Portland 14.2800 kg 1,030.00 14,708.40
Pasir pasang 0.0230 m3 95,000.00 2,185.00
Pekerja 0.2500 HOK 30,000.00 7,500.00
Tukang batu 0.2000 HOK 38,500.00 7,700.00
Kepala tukang 0.0200 HOK 42,000.00 840.00
Mandor 0.0125 HOK 41,000.00 512.50
Total 16,552.50 16,893.40
Total Harga 33,445.90
Keuntungan 3,344.59
Jumlah Total 36,790.49

E-14 1 m2 PLESTERAN 1 PC : 3 Ps, TEBAL 20 mm


Semen Portland 10.8000 kg 1,030.00 11,124.00
Pasir pasang 0.0260 m3 95,000.00 2,470.00
Pekerja 0.2500 HOK 30,000.00 7,500.00
Tukang batu 0.2000 HOK 38,500.00 7,700.00
Kepala tukang 0.0200 HOK 42,000.00 840.00
Mandor 0.0125 HOK 41,000.00 512.50
Total 16,552.50 13,594.00
Total Harga 30,146.50
Keuntungan 3,014.65
Jumlah Total 33,161.15

E-15 1 m2 PLESTERAN 1 PC : 4 Ps, TEBAL 20 mm


a b c d e f=(cxe) g=(cxe) h
Semen Portland 8.6800 kg 1,030.00 8,940.40
Pasir pasang 0.0280 m3 95,000.00 2,660.00
Pekerja 0.2500 HOK 30,000.00 7,500.00
Tukang batu 0.2000 HOK 38,500.00 7,700.00
Kepala tukang 0.0200 HOK 42,000.00 840.00
Mandor 0.0125 HOK 41,000.00 512.50
Total 16,552.50 11,600.40
Total Harga 28,152.90
Keuntungan 2,815.29
Jumlah Total 30,968.19

E-16 1 m2 PLESTERAN 1 PC : 5 Ps, TEBAL 20 mm


Semen Portland 7.2900 kg 1,030.00 7,508.70
Pasir pasang 0.0280 m3 95,000.00 2,660.00
Pekerja 0.2500 HOK 30,000.00 7,500.00
Tukang batu 0.2000 HOK 38,500.00 7,700.00
Kepala tukang 0.0200 HOK 42,000.00 840.00
Mandor 0.0125 HOK 41,000.00 512.50
Total 16,552.50 10,168.70
Total Harga 26,721.20
Keuntungan 2,672.12
Jumlah Total 29,393.32

E-17 1 m2 PLESTERAN 1 PC : 6 Ps, TEBAL 20 mm


E-18 1 m2 PLESTERAN 1 Kp : 1 Sm : 2 Ps TEBAL 20 mm

E-19 1 m2 PLESTERAN 1 PC : 2 Ps, TEBAL 25 mm


Semen Portland 15.5000 kg 1,030.00 15,965.00
Pasir pasang 0.0130 m3 95,000.00 1,235.00
Pekerja 0.3000 HOK 30,000.00 9,000.00
Tukang batu 0.2000 HOK 38,500.00 7,700.00
Kepala tukang 0.0200 HOK 42,000.00 840.00
Mandor 0.0130 HOK 41,000.00 533.00
Total 18,073.00 17,200.00
Total Harga 35,273.00
Keuntungan 3,527.30
Jumlah Total 38,800.30

E-20 1 m2 PLESTERAN 1 PC : 3 Ps, TEBAL 25 mm


Semen Portland 11.7500 kg 1,030.00 12,102.50
Pasir pasang 0.0350 m3 95,000.00 3,325.00
Pekerja 0.3000 HOK 30,000.00 9,000.00
Tukang batu 0.2000 HOK 38,500.00 7,700.00
Kepala tukang 0.0200 HOK 42,000.00 840.00
Mandor 0.0130 HOK 41,000.00 533.00
Total 18,073.00 15,427.50
Total Harga 33,500.50
Keuntungan 3,350.05
Jumlah Total 36,850.55

E-21 1 m2 PLESTERAN 1 PC : 4 Ps, TEBAL 25 mm


Semen Portland 9.4800 kg 1,030.00 9,764.40
Pasir pasang 0.0380 m3 95,000.00 3,610.00
Pekerja 0.3000 HOK 30,000.00 9,000.00
Tukang batu 0.2000 HOK 38,500.00 7,700.00
Kepala tukang 0.0200 HOK 42,000.00 840.00
Mandor 0.0130 HOK 41,000.00 533.00
Total 18,073.00 13,374.40
a b c d e f=(cxe) g=(cxe) h
Total Harga 31,447.40
Keuntungan 3,144.74
Jumlah Total 34,592.14

E-22 1 m2 PLESTERAN 1 PC : 5 Ps, TEBAL 25 mm


Semen Portland 7.9400 kg 1,030.00 8,178.20
Pasir pasang 0.0390 m3 95,000.00 3,705.00
Pekerja 0.3000 HOK 30,000.00 9,000.00
Tukang batu 0.2000 HOK 38,500.00 7,700.00
Kepala tukang 0.0200 HOK 42,000.00 840.00
Mandor 0.0130 HOK 41,000.00 533.00
Total 18,073.00 11,883.20
Total Harga 29,956.20
Keuntungan 2,995.62
Jumlah Total 32,951.82

E-23 1 m2 PLESTERAN 1 PC : 2 Ps, TEBAL 30 mm


Semen Portland 18.6500 kg 1,030.00 19,209.50
Pasir pasang 0.0350 m3 95,000.00 3,325.00
Pekerja 0.3200 HOK 30,000.00 9,600.00
Tukang batu 0.2500 HOK 38,500.00 9,625.00
Kepala tukang 0.0250 HOK 42,000.00 1,050.00
Mandor 0.0150 HOK 41,000.00 615.00
Total 20,890.00 22,534.50
Total Harga 43,424.50
Keuntungan 4,342.45
Jumlah Total 47,766.95

E-24 1 m2 PLESTERAN 1 PC : 3 Ps, TEBAL 30 mm


Semen Portland 14.1500 kg 1,030.00 14,574.50
Pasir pasang 0.0390 m3 95,000.00 3,705.00
Pekerja 0.3200 HOK 30,000.00 9,600.00
Tukang batu 0.2500 HOK 38,500.00 9,625.00
Kepala tukang 0.0250 HOK 42,000.00 1,050.00
Mandor 0.0150 HOK 41,000.00 615.00
Total 20,890.00 18,279.50
Total Harga 39,169.50
Keuntungan 3,916.95
Jumlah Total 43,086.45

E-25 1 m2 PLESTERAN 1 PC : 4 Ps, TEBAL 30 mm


Semen Portland 11.3800 kg 1,030.00 11,721.40
Pasir pasang 0.0420 m3 95,000.00 3,990.00
Pekerja 0.3200 HOK 30,000.00 9,600.00
Tukang batu 0.2500 HOK 38,500.00 9,625.00
Kepala tukang 0.0250 HOK 42,000.00 1,050.00
Mandor 0.0150 HOK 41,000.00 615.00
Total 20,890.00 15,711.40
Total Harga 36,601.40
Keuntungan 3,660.14
Jumlah Total 40,261.54

E-26 1 m2 PLESTERAN 1 PC : 5 Ps, TEBAL 30 mm


Semen Portland 8.1900 kg 1,030.00 8,435.70
Pasir pasang 0.0450 m3 95,000.00 4,275.00
Pekerja 0.3200 HOK 30,000.00 9,600.00
Tukang batu 0.2500 HOK 38,500.00 9,625.00
Kepala tukang 0.0250 HOK 42,000.00 1,050.00
a b c d e f=(cxe) g=(cxe) h
Mandor 0.0150 HOK 41,000.00 615.00
Total 20,890.00 12,710.70
Total Harga 33,600.70
Keuntungan 3,360.07
Jumlah Total 36,960.77

E-27 1 m2 BERAPEN 1 PC : 3 Ps, TEBAL 30 mm


E-28 1 m2 BERAPEN 1 PC : 5 Ps, TEBAL 15 mm

E-29 1 m2 PLESTERAN BETON 1 PC : 2 Ps, TEBAL 15 mm


Semen Portland 9.3000 kg 1,030.00 9,579.00
Pasir pasang 0.0180 m3 95,000.00 1,710.00
Pekerja 0.2600 HOK 30,000.00 7,800.00
Tukang batu 0.2000 HOK 38,500.00 7,700.00
Kepala tukang 0.0200 HOK 42,000.00 840.00
Mandor 0.0130 HOK 41,000.00 533.00
Total 16,873.00 11,289.00
Total Harga 28,162.00
Keuntungan 2,816.20
Jumlah Total 30,978.20

E-30 1 m2 PLESTERAN BETON 1 PC : 3 Ps, TEBAL 15 mm


Semen Portland 7.0700 kg 1,030.00 7,282.10
Pasir pasang 0.0210 m3 95,000.00 1,995.00
Pekerja 0.2600 HOK 30,000.00 7,800.00
Tukang batu 0.2000 HOK 38,500.00 7,700.00
Kepala tukang 0.0200 HOK 42,000.00 840.00
Mandor 0.0130 HOK 41,000.00 533.00
Total 16,873.00 9,277.10
Total Harga 26,150.10
Keuntungan 2,615.01
Jumlah Total 28,765.11

E-31 1 m2 PLESTERAN SKONING 1 PC : 2 Ps


Semen Portland 0.5000 kg 1,030.00 515.00
Pasir pasang 0.0020 m3 95,000.00 190.00
Pekerja 0.0570 HOK 30,000.00 1,710.00
Tukang batu 0.0380 HOK 38,500.00 1,463.00
Kepala tukang 0.0380 HOK 42,000.00 1,596.00
Mandor 0.0200 HOK 41,000.00 820.00
Total 5,589.00 705.00
Total Harga 6,294.00
Keuntungan 629.40
Jumlah Total 6,923.40

E-32 1 m2 PLESTERAN GRANITO, 1 PC WARNA : 2 GRANITO, TEBAL 10 MM


Semen Warna 0.1440 kg 1,030.00 148.32
Batu Granito 15.0000 kg 95,000.00 1,425,000.00
Pekerja 0.0500 HOK 30,000.00 1,500.00
Tukang batu 0.0200 HOK 38,500.00 770.00
Kepala tukang 0.0020 HOK 42,000.00 84.00
Mandor 0.0050 HOK 41,000.00 205.00
Total 2,559.00 1,425,148.32
Total Harga 1,427,707.32
Keuntungan 142,770.73
Jumlah Total 1,570,478.05

E-33 1 m2 PLESTERAN TERASO, 1 PC WARNA : 2 BATU TERASO, TEBAL 10 MM


a b c d e f=(cxe) g=(cxe) h
Semen Warna 0.4400 kg 1,030.00 453.20
Batu Teraso 11.5000 kg 95,000.00 1,092,500.00
Pekerja 0.4500 HOK 30,000.00 13,500.00
Tukang batu 0.2000 HOK 38,500.00 7,700.00
Kepala tukang 0.0200 HOK 42,000.00 840.00
Mandor 0.0250 HOK 41,000.00 1,025.00
Total 23,065.00 1,092,953.20
Total Harga 1,116,018.20
Keuntungan 111,601.82
Jumlah Total 1,227,620.02

E-34 1 m2 PLESTERAN CIPRAT 1 PC : 2 Ps


Semen Portland 4.3200 kg 1,030.00 4,449.60
Pasir pasang 0.0160 m3 95,000.00 1,520.00
Pekerja 0.2500 HOK 30,000.00 7,500.00
Tukang batu 0.1000 HOK 38,500.00 3,850.00
Kepala tukang 0.0100 HOK 42,000.00 420.00
Mandor 0.0150 HOK 41,000.00 615.00
Total 12,385.00 5,969.60
Total Harga 18,354.60
Keuntungan 1,835.46
Jumlah Total 20,190.06

E-35 1 m2 PLESTERAN SIAR ADUKAN 1 PC : 2 Ps


Semen Portland 4.3200 kg 1,030.00 4,449.60
Pasir pasang 0.0160 m3 95,000.00 1,520.00
Pekerja 0.1500 HOK 30,000.00 4,500.00
Tukang batu 0.0700 HOK 38,500.00 2,695.00
Kepala tukang 0.0070 HOK 42,000.00 294.00
Mandor 0.0080 HOK 41,000.00 328.00
Total 7,817.00 5,969.60
Total Harga 13,786.60
Keuntungan 1,378.66
Jumlah Total 15,165.26

E-36 1 m2 PLESTERAN WATERPROOF BATACOTE 3 LAPIS

DIHITUNG 1 m2 ACIAN PLESTERAN (A077)


Semen PC (50 kg) 0.0800 Zak 51,500.00 4,120.00
Pekerja 0.1430 HOK 30,000.00 4,290.00
Tukang batu 0.1070 HOK 38,500.00 4,119.50
Kepala tukang 0.0105 HOK 42,000.00 441.00
Mandor 0.0100 HOK 41,000.00 410.00
Total 9,260.50 4,120.00
Total Harga 13,380.50
Keuntungan 1,338.05
Jumlah Total 14,718.55

F PEKERJAAN KAYU
F-01 1 m3 PASANG KUSEN PINTU DAN JENDELA KAYU JATI
Kayu jati, balok 1.1000 m3 8,470,000.00 9,317,000.00
Pekerja 6.0000 HOK 30,000.00 180,000.00
Tukang kayu 20.0000 HOK 42,000.00 840,000.00
Kepala tukang 2.0000 HOK 42,000.00 84,000.00
Mandor 0.3000 HOK 41,000.00 12,300.00
Total 1,116,300.00 9,317,000.00
Total Harga 10,433,300.00
a b c d e f=(cxe) g=(cxe) h
Keuntungan 1,043,330.00
Jumlah Total 11,476,630.00

F-02 1 m3 PASANG KUSEN PINTU DAN JENDELA KAYU KAMPER


Kayu kamper, balok 1.2000 m3 5,720,000.00 6,864,000.00
Pekerja 6.0000 HOK 30,000.00 180,000.00
Tukang kayu 18.0000 HOK 42,000.00 756,000.00
Kepala tukang 2.0000 HOK 42,000.00 84,000.00
Mandor 0.3000 HOK 41,000.00 12,300.00
Total 1,032,300.00 6,864,000.00
Total Harga 7,896,300.00
Keuntungan 789,630.00
Jumlah Total 8,685,930.00

F-03 1 m3 PASANG KUSEN PINTU DAN JENDELA KAYU BORNEO


Kayu Borneo, balok 1.2000 m3 4,290,000.00 5,148,000.00
Pekerja 6.0000 HOK 30,000.00 180,000.00
Tukang kayu 18.0000 HOK 42,000.00 756,000.00
Kepala tukang 2.0000 HOK 42,000.00 84,000.00
Mandor 0.3000 HOK 41,000.00 12,300.00
Total 1,032,300.00 5,148,000.00
Total Harga 6,180,300.00
Keuntungan 618,030.00
Jumlah Total 6,798,330.00

F-04 1 m3 PASANG KUSEN PINTU DAN JENDELA KAYU DAMAR LAUT


Kayu Borneo damar laut, balok 1.2000 m3 4,290,000.00 5,148,000.00
Pekerja 6.0000 HOK 30,000.00 180,000.00
Tukang kayu 18.0000 HOK 42,000.00 756,000.00
Kepala tukang 2.0000 HOK 42,000.00 84,000.00
Mandor 0.3000 HOK 41,000.00 12,300.00
Total 1,032,300.00 5,148,000.00
Total Harga 6,180,300.00
Keuntungan 618,030.00
Jumlah Total 6,798,330.00

F-05 1 m2 PASANG PINTU KLAMP KAYU KAMPER


Kayu kamper, papan 0.0360 m3 5,720,000.00 205,920.00
Paku biasa 2"-5" 0.0500 Kg 9,000.00 450.00
Pekerja 0.3500 HOK 30,000.00 10,500.00
Tukang kayu 1.0500 HOK 42,000.00 44,100.00
Kepala tukang 0.1050 HOK 42,000.00 4,410.00
Mandor 0.0180 HOK 41,000.00 738.00
Total 59,748.00 206,370.00
Total Harga 266,118.00
Keuntungan 26,611.80
Jumlah Total 292,729.80

F-06 1 m2 PASANG PINTU KLAMP KAYU BORNEO


Kayu Borneo, papan 0.0360 m3 4,290,000.00 154,440.00
Paku biasa 2"-5" 0.0500 Kg 9,000.00 450.00
Pekerja 0.3500 HOK 30,000.00 10,500.00
Tukang kayu 1.0500 HOK 42,000.00 44,100.00
Kepala tukang 0.1050 HOK 42,000.00 4,410.00
Mandor 0.0180 HOK 41,000.00 738.00
Total 59,748.00 154,890.00
Total Harga 214,638.00
Keuntungan 21,463.80
a b c d e f=(cxe) g=(cxe) h
Jumlah Total 236,101.80

F-07 1 m2 PASANG PINTU PANEL KAYU JATI


Kayu jati, papan 0.0400 m3 8,470,000.00 338,800.00
Pekerja 1.0000 HOK 30,000.00 30,000.00
Tukang kayu 2.5000 HOK 42,000.00 105,000.00
Kepala tukang 0.2500 HOK 42,000.00 10,500.00
Mandor 0.0500 HOK 41,000.00 2,050.00
Total 147,550.00 338,800.00
Total Harga 486,350.00
Keuntungan 48,635.00
Jumlah Total 534,985.00

F-08 1 m2 PASANG PINTU PANEL KAYU KAMPER


Kayu kamper, papan 0.0400 m3 5,720,000.00 228,800.00
Pekerja 1.0000 HOK 30,000.00 30,000.00
Tukang kayu 2.5000 HOK 42,000.00 105,000.00
Kepala tukang 0.2500 HOK 42,000.00 10,500.00
Mandor 0.0500 HOK 41,000.00 2,050.00
Total 147,550.00 228,800.00
Total Harga 376,350.00
Keuntungan 37,635.00
Jumlah Total 413,985.00

F-09 1 m2 PASANG PINTU DAN JENDELA KACA KAYU JATI (TANPA KACA)
Kayu jati, papan 0.0350 m3 8,470,000.00 296,450.00
Pekerja 0.8000 HOK 30,000.00 24,000.00
Tukang kayu 2.0000 HOK 42,000.00 84,000.00
Kepala tukang 0.2000 HOK 42,000.00 8,400.00
Mandor 0.0400 HOK 41,000.00 1,640.00
Total 118,040.00 296,450.00
Total Harga 414,490.00
Keuntungan 41,449.00
Jumlah Total 455,939.00

F-10 1 m2 PASANG PINTU DAN JENDELA KACA KAYU KAMPER (TANPA KACA)
Kayu kamper, papan 0.0350 m3 5,720,000.00 200,200.00
Pekerja 0.8000 HOK 30,000.00 24,000.00
Tukang kayu 2.0000 HOK 42,000.00 84,000.00
Kepala tukang 0.2000 HOK 42,000.00 8,400.00
Mandor 0.0400 HOK 41,000.00 1,640.00
Total 118,040.00 200,200.00
Total Harga 318,240.00
Keuntungan 31,824.00
Jumlah Total 350,064.00

F-11 1 m2 PASANG PINTU DAN JENDELA KACA KAYU BORNEO (TANPA KACA)
Kayu Borneo, papan 0.0350 m3 4,290,000.00 150,150.00
Pekerja 0.8000 HOK 30,000.00 24,000.00
Tukang kayu 2.0000 HOK 42,000.00 84,000.00
Kepala tukang 0.2000 HOK 42,000.00 8,400.00
Mandor 0.0400 HOK 41,000.00 1,640.00
Total 118,040.00 150,150.00
Total Harga 268,190.00
Keuntungan 26,819.00
Jumlah Total 295,009.00

F-12 1 m2 PASANG PINTU DAN JENDELA JALUSI KAYU JATI


a b c d e f=(cxe) g=(cxe) h
Kayu jati, papan 0.0640 m3 8,470,000.00 542,080.00
Pekerja 1.0000 HOK 30,000.00 30,000.00
Tukang kayu 3.0000 HOK 42,000.00 126,000.00
Kepala tukang 0.3000 HOK 42,000.00 12,600.00
Mandor 0.3000 HOK 41,000.00 12,300.00
Total 180,900.00 542,080.00
Total Harga 722,980.00
Keuntungan 72,298.00
Jumlah Total 795,278.00

F-13 1 m2 PASANG PINTU DAN JENDELA JALUSI KAYU KAMPER


Kayu kamper, papan 0.0640 m3 5,720,000.00 366,080.00
Pekerja 1.0000 HOK 30,000.00 30,000.00
Tukang kayu 3.0000 HOK 42,000.00 126,000.00
Kepala tukang 0.3000 HOK 42,000.00 12,600.00
Mandor 0.5000 HOK 41,000.00 20,500.00
Total 189,100.00 366,080.00
Total Harga 555,180.00
Keuntungan 55,518.00
Jumlah Total 610,698.00

F-14 1 m2 PASANG PINTU PLYWOOD RANGKAP, RANGKA KAYU JATI


Kayu jati, papan 0.0196 m3 8,470,000.00 166,012.00
Paku biasa 1/2"-1" 0.0300 Kg 9,000.00 270.00
Lem kayu 0.3000 Lt 18,000.00 5,400.00
Plywood 4'x3'x4 mm 1.0000 Lbr 48,000.00 48,000.00
Pekerja 0.6000 HOK 30,000.00 18,000.00
Tukang kayu 2.0000 HOK 42,000.00 84,000.00
Kepala tukang 0.2000 HOK 42,000.00 8,400.00
Mandor 0.0300 HOK 41,000.00 1,230.00
Total 111,630.00 219,682.00
Total Harga 331,312.00
Keuntungan 33,131.20
Jumlah Total 364,443.20

F-15 1 m2 PASANG PINTU PLYWOOD RANGKAP, RANGKA KAYU KAMPER


Kayu kamper, papan 0.0196 m3 5,720,000.00 112,112.00
Paku biasa 1/2"-1" 0.0300 Kg 9,000.00 270.00
Lem kayu 0.3000 Lt 18,000.00 5,400.00
Plywood 4'x3'x4 mm 1.0000 Lbr 48,000.00 48,000.00
Pekerja 0.6000 HOK 30,000.00 18,000.00
Tukang kayu 2.0000 HOK 42,000.00 84,000.00
Kepala tukang 0.2000 HOK 42,000.00 8,400.00
Mandor 0.0300 HOK 41,000.00 1,230.00
Total 111,630.00 165,782.00
Total Harga 277,412.00
Keuntungan 27,741.20
Jumlah Total 305,153.20

F-16 1 m2 PASANG JALUSI MATI KUSEN KAYU JATI


Kayu jati, papan 0.0600 m3 8,470,000.00 508,200.00
Paku biasa 1/2"-1" 0.1500 Kg 9,000.00 1,350.00
Pekerja 0.5000 HOK 30,000.00 15,000.00
Tukang kayu 2.0000 HOK 42,000.00 84,000.00
Kepala tukang 0.2000 HOK 42,000.00 8,400.00
Mandor 0.0250 HOK 41,000.00 1,025.00
Total 108,425.00 509,550.00
Total Harga 617,975.00
a b c d e f=(cxe) g=(cxe) h
Keuntungan 61,797.50
Jumlah Total 679,772.50

F-17 1 m2 PASANG JELUSI MATI KUSEN KAYU KAMPER


Kayu kamper, papan 0.0600 m3 5,720,000.00 343,200.00
Paku biasa 1/2"-1" 0.1500 Kg 9,000.00 1,350.00
Pekerja 0.5000 HOK 30,000.00 15,000.00
Tukang kayu 2.0000 HOK 42,000.00 84,000.00
Kepala tukang 0.2000 HOK 42,000.00 8,400.00
Mandor 0.0250 HOK 41,000.00 1,025.00
Total 108,425.00 344,550.00
Total Harga 452,975.00
Keuntungan 45,297.50
Jumlah Total 498,272.50

F-18 1 m2 PASANG PINTU PLYWOOD RANGKAP, RANGKA KAYU BORNEO


Kayu Borneo, papan 0.0196 m3 4,290,000.00 84,084.00
Paku biasa 1/2"-1" 0.0300 Kg 9,000.00 270.00
Lem kayu 0.3000 Lt 18,000.00 5,400.00
Plywood 4'x3'x4 mm 1.0000 Lbr 48,000.00 48,000.00
Pekerja 0.6000 HOK 30,000.00 18,000.00
Tukang kayu 2.0000 HOK 42,000.00 84,000.00
Kepala tukang 0.2000 HOK 42,000.00 8,400.00
Mandor 0.0300 HOK 41,000.00 1,230.00
Total ` 111,630.00 137,754.00
Total Harga 249,384.00
Keuntungan 24,938.40
Jumlah Total 274,322.40

F-19 1 m2 PASANG PINTU DOUBLE-TEAKWOOD, RANGKA KAYU JATI


Kayu jati, papan 0.0196 m3 8,470,000.00 166,012.00
Paku biasa 1/2"-1" 0.3000 Kg 9,000.00 2,700.00
Lem kayu 0.3000 Lt 18,000.00 5,400.00
Teakwood 4'x8'x4 mm 1.0000 Lbr 48,000.00 48,000.00
Pekerja 0.6000 HOK 30,000.00 18,000.00
Tukang kayu 2.0000 HOK 42,000.00 84,000.00
Kepala tukang 0.2000 HOK 42,000.00 8,400.00
Mandor 0.0300 HOK 41,000.00 1,230.00
Total 111,630.00 222,112.00
Total Harga 333,742.00
Keuntungan 33,374.20
Jumlah Total 367,116.20

F-20 1 m2 PASANG PINTU DOUBLE-TEAKWOOD, RANGKA KAYU KAMPER


Kayu kamper, papan 0.0196 m3 5,720,000.00 112,112.00
Paku biasa 1/2"-1" 0.3000 Kg 9,000.00 2,700.00
Lem kayu 0.3000 Lt 18,000.00 5,400.00
Teakwood 4'x8'x4 mm 1.0000 Lbr 48,000.00 48,000.00
Pekerja 0.6000 HOK 30,000.00 18,000.00
Tukang kayu 2.0000 HOK 42,000.00 84,000.00
Kepala tukang 0.2000 HOK 42,000.00 8,400.00
Mandor 0.0300 HOK 41,000.00 1,230.00
Total 111,630.00 168,212.00
Total Harga 279,842.00
Keuntungan 27,984.20
Jumlah Total 307,826.20

F-21 1 m2 PASANG PINTU PLYWOOD DAN FORMIKA, RANGKA KAYU JATI


a b c d e f=(cxe) g=(cxe) h
Kayu jati, papan 0.0196 m3 8,470,000.00 166,012.00
Paku biasa 1/2"-1" 0.3000 Kg 9,000.00 2,700.00
Lem kayu 0.8000 Lt 18,000.00 14,400.00
Plywood 4'x8'x4 mm 1.0000 Lbr 48,000.00 48,000.00
Formika 0.5000 Lbr 65,000.00 32,500.00
Pekerja 0.8000 HOK 30,000.00 24,000.00
Tukang kayu 2.5000 HOK 42,000.00 105,000.00
Kepala tukang 0.2500 HOK 42,000.00 10,500.00
Mandor 0.0400 HOK 41,000.00 1,640.00
Total 141,140.00 263,612.00
Total Harga 404,752.00
Keuntungan 40,475.20
Jumlah Total 445,227.20

F-22 1 m2 PASANG PINTU PLYWOOD DAN FORMIKA, RANGKA KAYU KAMPER


Kayu kamper, papan 0.0196 m3 5,720,000.00 112,112.00
Paku biasa 1/2"-1" 0.3000 Kg 9,000.00 2,700.00
Lem kayu 0.8000 Lt 18,000.00 14,400.00
Plywood 4'x8'x4 mm 1.0000 Lbr 48,000.00 48,000.00
Formika 4'x3' 0.5000 Lbr 65,000.00 32,500.00
Pekerja 0.8000 HOK 30,000.00 24,000.00
Tukang kayu 2.5000 HOK 42,000.00 105,000.00
Kepala tukang 0.2500 HOK 42,000.00 10,500.00
Mandor 0.0400 HOK 41,000.00 1,640.00
Total 141,140.00 209,712.00
Total Harga 350,852.00
Keuntungan 35,085.20
Jumlah Total 385,937.20

F-23 1 m2 PASANG PINTU TEAKWOOD DAN FORMIKA, RANGKA KAYU JATI


Kayu jati, papan 0.0196 m3 8,470,000.00 166,012.00
Paku biasa 1/2"-1" 0.3000 Kg 9,000.00 2,700.00
Lem kayu 0.8000 Lt 18,000.00 14,400.00
Teakwood 4'x8'x4 mm 0.5000 Lbr 48,000.00 24,000.00
Formika 4'x8' 0.5000 Lbr 65,000.00 32,500.00
Pekerja 0.8000 HOK 30,000.00 24,000.00
Tukang kayu 2.5000 HOK 42,000.00 105,000.00
Kepala tukang 0.2500 HOK 42,000.00 10,500.00
Mandor 0.0400 HOK 41,000.00 1,640.00
Total 141,140.00 239,612.00
Total Harga 380,752.00
Keuntungan 38,075.20
Jumlah Total 418,827.20

F-24 1 m2 PASANG PINTU TEAKWOOD DAN FORMIKA, RANGKA KAYU KAMPER


Kayu kamper, papan 0.0196 m3 5,720,000.00 112,112.00
Paku biasa 1/2"-1" 0.3000 Kg 9,000.00 2,700.00
Lem kayu 0.8000 Lt 18,000.00 14,400.00
Teakwood 4'x8'x4 mm 0.5000 Lbr 48,000.00 24,000.00
Formika 4'x8' 0.5000 Lbr 65,000.00 32,500.00
Pekerja 0.8000 HOK 30,000.00 24,000.00
Tukang kayu 2.5000 HOK 42,000.00 105,000.00
Kepala tukang 0.2500 HOK 42,000.00 10,500.00
Mandor 0.0400 HOK 41,000.00 1,640.00
Total 141,140.00 185,712.00
Total Harga 326,852.00
Keuntungan 32,685.20
Jumlah Total 359,537.20
a b c d e f=(cxe) g=(cxe) h

F-25 1 m2 PASANG PINTU FORMIKA RANGKAP, RANGKA KAYU JATI


Kayu Jati, papan 0.0196 m3 8,470,000.00 166,012.00
Paku biasa 1/2"-1" 0.3000 Kg 9,000.00 2,700.00
Lem kayu 1.2000 Lt 18,000.00 21,600.00
Plywood 4'x8'x4 mm 1.0000 Lbr 48,000.00 48,000.00
Formika 4'x8' 1.0000 Lbr 65,000.00 65,000.00
Pekerja 1.0000 HOK 30,000.00 30,000.00
Tukang kayu 2.6000 HOK 42,000.00 109,200.00
Kepala tukang 0.2600 HOK 42,000.00 10,920.00
Mandor 0.0500 HOK 41,000.00 2,050.00
Total 152,170.00 303,312.00
Total Harga 455,482.00
Keuntungan 45,548.20
Jumlah Total 501,030.20

F-26 1 m2 PASANG PINTU FORMIKA RANGKAP, RANGKA KAYU KAMPER


Kayu Kamper, papan 0.0196 m3 5,720,000.00 112,112.00
Paku biasa 1/2"-1" 0.3000 Kg 9,000.00 2,700.00
Lem kayu 1.2000 Lt 18,000.00 21,600.00
Plywood 4'x8'x4 mm 1.0000 Lbr 48,000.00 48,000.00
Formika 4'x8' 1.0000 Lbr 65,000.00 65,000.00
Pekerja 1.0000 HOK 30,000.00 30,000.00
Tukang kayu 2.6000 HOK 42,000.00 109,200.00
Kepala tukang 0.2600 HOK 42,000.00 10,920.00
Mandor 0.0500 HOK 41,000.00 2,050.00
Total 152,170.00 249,412.00
Total Harga 401,582.00
Keuntungan 40,158.20
Jumlah Total 441,740.20

F-27 1 m3 PASANG KONSTRUKSI KUDA-KUDA KAYU JATI


F-28 1 m3 PASANG KONSTRUKSI KUDA-KUDA KAYU KAMPER
Kayu kamper, balok 1.1000 m3 5,720,000.00 6,292,000.00
Besi strip 15.0000 Kg 12,000.00 180,000.00
Paku biasa 2"-5" 0.8000 Kg 9,000.00 7,200.00
Pekerja 4.0000 HOK 30,000.00 120,000.00
Tukang kayu 12.0000 HOK 42,000.00 504,000.00
Kepala tukang 1.2000 HOK 42,000.00 50,400.00
Mandor 0.2000 HOK 41,000.00 8,200.00
Total 682,600.00 6,479,200.00
Total Harga 7,161,800.00
Keuntungan 716,180.00
Jumlah Total 7,877,980.00

F-29 1 m3 PASANG KONSTRUKSI KUDA-KUDA KAYU BORNEO


Kayu borneo, balok 1.1000 m3 4,290,000.00 4,719,000.00
Besi strip 15.0000 Kg 12,000.00 180,000.00
Paku biasa 2"-5" 0.8000 Kg 9,000.00 7,200.00
Pekerja 4.0000 HOK 30,000.00 120,000.00
Tukang kayu 12.0000 HOK 42,000.00 504,000.00
Kepala tukang 1.2000 HOK 42,000.00 50,400.00
Mandor 0.2000 HOK 41,000.00 8,200.00
Total 682,600.00 4,906,200.00
Total Harga 5,588,800.00
Keuntungan 558,880.00
Jumlah Total 6,147,680.00
a b c d e f=(cxe) g=(cxe) h
F-30 1 m3 PASANG KONSTRUKSI KUDA-KUDA KAYU KRUING
Kayu kruing, balok 1.1000 m3 5,720,000.00 6,292,000.00
Besi strip 15.0000 Kg 12,000.00 180,000.00
Paku biasa 2"-5" 0.8000 Kg 9,000.00 7,200.00
Pekerja 4.0000 HOK 30,000.00 120,000.00
Tukang kayu 12.0000 HOK 42,000.00 504,000.00
Kepala tukang 1.2000 HOK 42,000.00 50,400.00
Mandor 0.2000 HOK 41,000.00 8,200.00
Total 682,600.00 6,479,200.00
Total Harga 7,161,800.00
Keuntungan 716,180.00
Jumlah Total 7,877,980.00

F-31 1 m2 PASANG KASO + RENG GENTENG KODOK KAYU KAMPER


Kayu kamper, balok 0.0120 m3 5,720,000.00 68,640.00
Paku biasa 2"-5" 0.1500 Kg 9,000.00 1,350.00
Pekerja 0.1000 HOK 30,000.00 3,000.00
Tukang kayu 0.1000 HOK 42,000.00 4,200.00
Kepala tukang 0.0100 HOK 42,000.00 420.00
Mandor 0.0050 HOK 41,000.00 205.00
Total 7,825.00 69,990.00
Total Harga 77,815.00
Keuntungan 7,781.50
Jumlah Total 85,596.50

F-32 1 m2 PASANG KASO + RENG GENTENG KODOK KAYU BORNEO


Kayu borneo, balok 0.0120 m3 4,290,000.00 51,480.00
Paku biasa 2"-5" 0.1500 Kg 9,000.00 1,350.00
Pekerja 0.1000 HOK 30,000.00 3,000.00
Tukang kayu 0.1000 HOK 42,000.00 4,200.00
Kepala tukang 0.0100 HOK 42,000.00 420.00
Mandor 0.0050 HOK 41,000.00 205.00
Total 7,825.00 52,830.00
Total Harga 60,655.00
Keuntungan 6,065.50
Jumlah Total 66,720.50

F-33 1 m2 PASANG KASO + RENG GENTENG MONIER KAYU JATI


F-34 1 m2 PASANG KASO + RENG GENTENG MONIER KAYU KAMPER
Kayu kamper, balok 0.0140 m3 5,720,000.00 80,080.00
Paku biasa 2"-5" 0.1500 Kg 9,000.00 1,350.00
Pekerja 0.1000 HOK 30,000.00 3,000.00
Tukang kayu 0.1000 HOK 42,000.00 4,200.00
Kepala tukang 0.0100 HOK 42,000.00 420.00
Mandor 0.0050 HOK 41,000.00 205.00
Total 7,825.00 81,430.00
Total Harga 89,255.00
Keuntungan 8,925.50
Jumlah Total 98,180.50

F-35 1 m2 PASANG KASO + RENG GENTENG BETON KAYU BORNEO


Kayu borneo, balok 0.0140 m3 4,290,000.00 60,060.00
Paku biasa 2"-5" 0.1500 Kg 9,000.00 1,350.00
Pekerja 0.1000 HOK 30,000.00 3,000.00
Tukang kayu 0.1000 HOK 42,000.00 4,200.00
Kepala tukang 0.0100 HOK 42,000.00 420.00
Mandor 0.0050 HOK 41,000.00 205.00
Total 7,825.00 61,410.00
a b c d e f=(cxe) g=(cxe) h
Total Harga 69,235.00
Keuntungan 6,923.50
Jumlah Total 76,158.50

F-36 1 m2 PASANG KASO + RENG ATAP SIRAP KAYU KAMPER


Kayu kamper, balok 0.1650 m3 5,720,000.00 943,800.00
Paku biasa 2"-5" 0.2000 Kg 9,000.00 1,800.00
Pekerja 0.1200 HOK 30,000.00 3,600.00
Tukang kayu 0.1200 HOK 42,000.00 5,040.00
Kepala tukang 0.0120 HOK 42,000.00 504.00
Mandor 0.0060 HOK 41,000.00 246.00
Total 9,390.00 945,600.00
Total Harga 954,990.00
Keuntungan 95,499.00
Jumlah Total 1,050,489.00

F-37 1 m2 PASANG KASO + RENG ATAP SIRAP KAYU BORNEO


Kayu borneo, balok 0.1650 m3 4,290,000.00 707,850.00
Paku biasa 2"-5" 0.2000 Kg 9,000.00 1,800.00
Pekerja 0.1200 HOK 30,000.00 3,600.00
Tukang kayu 0.1200 HOK 42,000.00 5,040.00
Kepala tukang 0.0120 HOK 42,000.00 504.00
Mandor 0.0060 HOK 41,000.00 246.00
Total 9,390.00 709,650.00
Total Harga 719,040.00
Keuntungan 71,904.00
Jumlah Total 790,944.00

F-39 1 m2 PASANG RANGKA LANGIT-LANGIT ( 1X1 ) m, KAYU KAMPER


Kayu kamper, balok 0.0120 m3 5,720,000.00 68,640.00
Paku biasa 2"-5" 0.1000 Kg 9,000.00 900.00
Pekerja 0.1500 HOK 30,000.00 4,500.00
Tukang kayu 0.2500 HOK 42,000.00 10,500.00
Kepala tukang 0.0250 HOK 42,000.00 1,050.00
Mandor 0.0750 HOK 41,000.00 3,075.00
Total 19,125.00 69,540.00
Total Harga 88,665.00
Keuntungan 8,866.50
Jumlah Total 97,531.50

F-40 1 m2 PASANG RANGKA LANGIT-LANGIT ( 1x1 ) m, KAYU BORNEO


Kayu borneo, balok 0.0120 m3 4,290,000.00 51,480.00
Paku biasa 2"-5" 0.1000 Kg 9,000.00 900.00
Pekerja 0.1500 HOK 30,000.00 4,500.00
Tukang kayu 0.2500 HOK 42,000.00 10,500.00
Kepala tukang 0.0250 HOK 42,000.00 1,050.00
Mandor 0.0750 HOK 41,000.00 3,075.00
Total 19,125.00 52,380.00
Total Harga 71,505.00
Keuntungan 7,150.50
Jumlah Total 78,655.50

F-41 1 m2 PASANG RANGKA LANGIT-LANGIT ( 0.3X0.6 ) m, KAYU JATI


F-42 1 m2 PASANG RANGKA LANGIT-LANGIT ( 0.3X0.6 ) m, KAYU KAMPER
Kayu kamper, balok 0.0230 m3 5,720,000.00 131,560.00
Paku biasa 2"-5" 0.1500 Kg 9,000.00 1,350.00
Pekerja 0.2000 HOK 30,000.00 6,000.00
Tukang kayu 0.3000 HOK 42,000.00 12,600.00
a b c d e f=(cxe) g=(cxe) h
Kepala tukang 0.0300 HOK 42,000.00 1,260.00
Mandor 0.0100 HOK 41,000.00 410.00
Total 20,270.00 132,910.00
Total Harga 153,180.00
Keuntungan 15,318.00
Jumlah Total 168,498.00

F-43 1 m2 PASANG RANGKA LANGIT-LANGIT ( 0.3X0.6 ) m, KAYU BORNEO


Kayu Borneo, balok 0.0230 m3 4,290,000.00 98,670.00
Paku biasa 2"-5" 0.1500 Kg 9,000.00 1,350.00
Pekerja 0.2000 HOK 30,000.00 6,000.00
Tukang kayu 0.3000 HOK 42,000.00 12,600.00
Kepala tukang 0.0300 HOK 42,000.00 1,260.00
Mandor 0.0100 HOK 41,000.00 410.00
Total 20,270.00 100,020.00
Total Harga 120,290.00
Keuntungan 12,029.00
Jumlah Total 132,319.00

F-44 1 m2 PASANG RANGKA LANGIT-LANGIT ( 0.3X0.3 ) m, KAYU JATI


F-45 1 m2 PASANG RANGKA LANGIT-LANGIT ( 0.3X0.3 ) m, KAYU KAMPER
F-46 1 m2 PASANG RANGKA LANGIT-LANGIT ( 0.3X0.3 ) m, KAYU BORNEO
F-47 1 m' PASANG LISTPLANK UKURAN ( 3x20 ) cm, KAYU JATI
F-48 1 m' PASANG LISTPLANK UKURAN ( 3x20 ) cm, KAYU KAMPER
Kayu kamper, papan 0.0072 m3 5,720,000.00 41,184.00
Paku biasa 2"-5" 0.0500 Kg 9,000.00 450.00
Pekerja 0.1000 HOK 30,000.00 3,000.00
Tukang kayu 0.2000 HOK 42,000.00 8,400.00
Kepala tukang 0.0200 HOK 42,000.00 840.00
Mandor 0.0050 HOK 41,000.00 205.00
Total 12,445.00 41,634.00
Total Harga 54,079.00
Keuntungan 5,407.90
Jumlah Total 59,486.90

F-49 1 m' PASANG LISTPLANK UKURAN ( 3x30 ) cm, KAYU JATI


F-50 1 m' PASANG LISTPLANK UKURAN ( 3x30 ) cm, KAYU KAMPER
Kayu kamper, papan 0.0110 m3 5,720,000.00 62,920.00
Paku biasa 2"-5" 0.0500 Kg 9,000.00 450.00
Pekerja 0.1100 HOK 30,000.00 3,300.00
Tukang kayu 0.2200 HOK 42,000.00 9,240.00
Kepala tukang 0.0220 HOK 42,000.00 924.00
Mandor 0.0050 HOK 41,000.00 205.00
Total 13,669.00 63,370.00
Total Harga 77,039.00
Keuntungan 7,703.90
Jumlah Total 84,742.90

F-51 1 m' PASANG LISTPLANK UKURAN 2 x ( 3x20 ) cm, KAYU KAMPER


Kayu kamper, papan 0.0145 m3 5,720,000.00 82,940.00
Paku biasa 2"-5" 0.0600 Kg 9,000.00 540.00
Pekerja 0.1500 HOK 30,000.00 4,500.00
Tukang kayu 0.2500 HOK 42,000.00 10,500.00
Kepala tukang 0.0250 HOK 42,000.00 1,050.00
Mandor 0.0750 HOK 41,000.00 3,075.00
Total 19,125.00 83,480.00
Total Harga 102,605.00
Keuntungan 10,260.50
a b c d e f=(cxe) g=(cxe) h
Jumlah Total 112,865.50

F-52 1 m' PASANG LISTPLANK UKURAN 2 x ( 2x20 ) cm, KAYU KAMPER


Kayu kamper, papan 0.0086 m3 5,720,000.00 49,192.00
Paku biasa 2"-5" 0.0600 Kg 9,000.00 540.00
Pekerja 0.1000 HOK 30,000.00 3,000.00
Tukang kayu 0.1000 HOK 42,000.00 4,200.00
Kepala tukang 0.0100 HOK 42,000.00 420.00
Mandor 0.0500 HOK 41,000.00 2,050.00
Total 9,670.00 49,732.00
Total Harga 59,402.00
Keuntungan 5,940.20
Jumlah Total 65,342.20

F-53 1 m' PASANG LISTPLANK UKURAN 2 x ( 2x20 ) cm, KAYU BORNEO


Kayu borneo, papan 0.0088 m3 4,290,000.00 37,752.00
Paku biasa 2"-5" 0.0600 Kg 9,000.00 540.00
Pekerja 0.1000 HOK 30,000.00 3,000.00
Tukang kayu 0.1000 HOK 42,000.00 4,200.00
Kepala tukang 0.0100 HOK 42,000.00 420.00
Mandor 0.0500 HOK 41,000.00 2,050.00
Total 9,670.00 38,292.00
Total Harga 47,962.00
Keuntungan 4,796.20
Jumlah Total 52,758.20

F-54 1 m2 PASANG RANGKA DINDING PEMISAH KAYU KAMPER


Kayu kamper, balok 0.0195 m3 5,720,000.00 111,540.00
Kayu kamper, papan 0.0070 m3 5,720,000.00 40,040.00
Paku biasa 2"-5" 0.1000 Kg 9,000.00 900.00
Pekerja 0.1500 HOK 30,000.00 4,500.00
Tukang kayu 0.4500 HOK 42,000.00 18,900.00
Kepala tukang 0.0450 HOK 42,000.00 1,890.00
Mandor 0.0750 HOK 41,000.00 3,075.00
Total 28,365.00 152,480.00
Total Harga 180,845.00
Keuntungan 18,084.50
Jumlah Total 198,929.50

F-55 1 m2 PASANG RANGKA DINDING PEMISAH KAYU BORNEO


Kayu borneo, balok 0.0195 m3 4,290,000.00 83,655.00
Kayu borneo, papan 0.0070 m3 4,290,000.00 30,030.00
Paku biasa 2"-5" 0.1000 Kg 9,000.00 900.00
Pekerja 0.1500 HOK 30,000.00 4,500.00
Tukang kayu 0.4500 HOK 42,000.00 18,900.00
Kepala tukang 0.0450 HOK 42,000.00 1,890.00
Mandor 0.0750 HOK 41,000.00 3,075.00
Total 28,365.00 114,585.00
Total Harga 142,950.00
Keuntungan 14,295.00
Jumlah Total 157,245.00

F-56 1 m2 PASANG DINDING PEMISAH TEAKWOOD RANGKAP, RANGKA KAYU KAMPER


Kayu kamper, balok 0.0195 m3 5,720,000.00 111,540.00
Kayu kamper, papan 0.0070 m3 5,720,000.00 40,040.00
Paku biasa 2"-5" 0.1000 Kg 9,000.00 900.00
Teakwood 4'x8'x4 mm 1.0000 Lbr 102,000.00 102,000.00
Pekerja 0.1500 HOK 30,000.00 4,500.00
a b c d e f=(cxe) g=(cxe) h
Tukang kayu 0.4500 HOK 42,000.00 18,900.00
Kepala tukang 0.0450 HOK 42,000.00 1,890.00
Mandor 0.0750 HOK 41,000.00 3,075.00
Total 28,365.00 254,480.00
Total Harga 282,845.00
Keuntungan 28,284.50
Jumlah Total 311,129.50

F-57 1 m2 PASANG DINDING PEMISAH PLYWOOD RANGKAP, RANGKA KAYU KAMPER


Kayu kamper, balok 0.0195 m3 5,720,000.00 111,540.00
Kayu kamper, papan 0.0070 m3 5,720,000.00 40,040.00
Paku biasa 2"-5" 0.1000 Kg 9,000.00 900.00
Lem kayu 0.5600 Lt 18,000.00 10,080.00
Plywood 4'x8'x4 mm 1.0000 Lbr 48,000.00 48,000.00
Pekerja 0.2000 HOK 30,000.00 6,000.00
Tukang kayu 0.6000 HOK 42,000.00 25,200.00
Kepala tukang 0.0600 HOK 42,000.00 2,520.00
Mandor 0.0100 HOK 41,000.00 410.00
Total 34,130.00 210,560.00
Total Harga 244,690.00
Keuntungan 24,469.00
Jumlah Total 269,159.00

F-58 1 m2 PASANG DINDING LAMBRIZIRING DARI PAPAN JATI


F-59 1 m' PASANG PLYWOOD TEBAL 4 mm, UNTUK DINDING
Plywood 4' x 8' x 4 mm 0.4000 lbr 48,000.00 19,200.00
Paku biasa 1/2"-1" 0.0500 kg 9,000.00 450.00
Pekerja 0.0250 HOK 30,000.00 750.00
Tukang kayu 0.0750 HOK 42,000.00 3,150.00
Kepala tukang 0.0075 HOK 42,000.00 315.00
Mandor 0.0013 HOK 41,000.00 53.30
Total 4,268.30 19,650.00
Total Harga 23,918.30
Keuntungan 2,391.83
Jumlah Total 26,310.13

F-60 1 m' PASANG LIST PLAFOND KAYU PROFIL


Kayu profil 1.0500 m' 8,000.00 8,400.00
Pekerja 0.0210 HOK 30,000.00 630.00
Tukang kayu 0.0210 HOK 42,000.00 882.00
Kepala tukang 0.0020 HOK 42,000.00 84.00
Mandor 0.0010 HOK 41,000.00 41.00
Total 1,637.00 8,400.00
Total Harga 10,037.00
Keuntungan 1,003.70
Jumlah Total 11,040.70

DIHITUNG 1 m3 PASANG KONSTRUKSI KUDA-KUDA KAYU GUNUNG KELAS II


Kayu gunung kelas II, balok 1.1000 m3 1,800,000.00 1,980,000.00
Besi strip 15.0000 Kg 12,000.00 180,000.00
Paku biasa 2"-5" 0.8000 Kg 9,000.00 7,200.00
Pekerja 4.0000 HOK 30,000.00 120,000.00
Tukang kayu 12.0000 HOK 42,000.00 504,000.00
Kepala tukang 1.2000 HOK 42,000.00 50,400.00
Mandor 0.2000 HOK 41,000.00 8,200.00
Total 682,600.00 2,167,200.00
Total Harga 2,849,800.00
Keuntungan 284,980.00
a b c d e f=(cxe) g=(cxe) h
Jumlah Total 3,134,780.00

DIHITUNG 1 m2 PASANG KASO + RENG KAYU GUNUNG KELAS II GENTENG PALENTONG


Kayu gunung kelas II, balok 0.0120 m3 1,800,000.00 21,600.00
Paku biasa 2"-5" 0.1500 Kg 9,000.00 1,350.00
Pekerja 0.1000 HOK 30,000.00 3,000.00
Tukang kayu 0.1000 HOK 42,000.00 4,200.00
Kepala tukang 0.0100 HOK 42,000.00 420.00
Mandor 0.0050 HOK 41,000.00 205.00
Total 7,825.00 22,950.00
Total Harga 30,775.00
Keuntungan 3,077.50
Jumlah Total 33,852.50

DIHITUNG 1 m2 PASANG RANGKA LANGIT-LANGIT ( 1x1 ) m, KAYU GUNUNG KELAS II


Kayu gunung kelas II, balok 0.0120 m3 1,800,000.00 21,600.00
Paku biasa 2"-5" 0.1000 Kg 9,000.00 900.00
Pekerja 0.1500 HOK 30,000.00 4,500.00
Tukang kayu 0.2500 HOK 42,000.00 10,500.00
Kepala tukang 0.0250 HOK 42,000.00 1,050.00
Mandor 0.0750 HOK 41,000.00 3,075.00
Total 19,125.00 22,500.00
Total Harga 41,625.00
Keuntungan 4,162.50
Jumlah Total 45,787.50

DIHITUNG 1 m3 PASANG KUSEN PINTU DAN JENDELA KAYU GUNUNG KELAS II


Kayu gunung kelasII, balok 1.1000 m3 1,800,000.00 1,980,000.00
Pekerja 6.0000 HOK 30,000.00 180,000.00
Tukang kayu 20.0000 HOK 42,000.00 840,000.00
Kepala tukang 2.0000 HOK 42,000.00 84,000.00
Mandor 0.3000 HOK 41,000.00 12,300.00
Total 1,116,300.00 1,980,000.00
Total Harga 3,096,300.00
Keuntungan 309,630.00
Jumlah Total 3,405,930.00

DIHITUNG 1 m' PASANG LISTPLANK UKURAN 2 x ( 2x20 ) cm, KAYU GUNUNG KELAS II
Kayu Gunung Kls II, papan 0.0088 m3 1,400,000.00 12,320.00
Paku biasa 2"-5" 0.0600 Kg 9,000.00 540.00
Pekerja 0.1000 HOK 30,000.00 3,000.00
Tukang kayu 0.1000 HOK 42,000.00 4,200.00
Kepala tukang 0.0100 HOK 42,000.00 420.00
Mandor 0.0500 HOK 41,000.00 2,050.00
Total 9,670.00 12,860.00
Total Harga 22,530.00
Keuntungan 2,253.00
Jumlah Total 24,783.00

Dihitung 1 Kg SARINGAN BESI


Besi Beton 1.0500 Kg 8,000.00 8,400.00
Pekerja 0.0600 Kg #REF! #REF!
Tukang Besi Profil Terampil 0.0040 HOK #REF! #REF!
Kepala Tukang Besi Profil 0.0010 HOK #REF! #REF!
Mandor 0.0002 HOK #REF! #REF!
Peralatan (O2,Solar, Elpiji, kawat las dll) 0.1250 HOK #REF! #REF!

Total #REF! 8,400.00


a b c d e f=(cxe) g=(cxe) h
Total Harga #REF!
Keuntungan #REF!
Jumlah Total #REF!
L PEKERJAAN KUNCI DAN KACA
L-01 1 BUAH PASANG KUNCI TANAM ANTIK
Kunci tanam antik 1.0000 bh 24,000.00 24,000.00
Pekerja 0.0600 HOK 30,000.00 1,800.00
Tukang kayu 0.6000 HOK 42,000.00 25,200.00
Kepala tukang 0.0600 HOK 42,000.00 2,520.00
Mandor 0.0030 HOK 41,000.00 123.00
Total 29,643.00 24,000.00
Total Harga 53,643.00
Keuntungan 5,364.30
Jumlah Total 59,007.30

L-02 1 BUAH PASANG KUNCI TANAM BIASA


Kunci tanam biasa 1.0000 bh 78,000.00 78,000.00
Pekerja 0.0100 HOK 30,000.00 300.00
Tukang kayu 0.5000 HOK 42,000.00 21,000.00
Kepala tukang 0.0100 HOK 42,000.00 420.00
Mandor 0.0050 HOK 41,000.00 205.00
Total 21,925.00 78,000.00
Total Harga 99,925.00
Keuntungan 9,992.50
Jumlah Total 109,917.50

L-03 1 BUAH PASANG KUNCI TANAM KAMAR MANDI


Kunci tanam kamar mandi 1.0000 bh 78,000.00 78,000.00
Pekerja 0.0050 HOK 30,000.00 150.00
Tukang kayu 0.5000 HOK 42,000.00 21,000.00
Kepala tukang 0.0050 HOK 42,000.00 210.00
Mandor 0.0025 HOK 41,000.00 102.50
Total 21,462.50 78,000.00
Total Harga 99,462.50
Keuntungan 9,946.25
Jumlah Total 109,408.75

L-04 1 BUAH PASANG KUNCI SILINDER


Kunci silinder 1.0000 bh 24,000.00 24,000.00
Pekerja 0.0050 HOK 30,000.00 150.00
Tukang kayu 0.5000 HOK 42,000.00 21,000.00
Kepala tukang 0.0050 HOK 42,000.00 210.00
Mandor 0.00025 HOK 41,000.00 10.25
Total 21,370.25 24,000.00
Total Harga 45,370.25
Keuntungan 4,537.03
Jumlah Total 49,907.28

L-05 1 BUAH PASANG ENGSEL PINTU


Engsel pintu 1.0000 bh 12,500.00 12,500.00
Pekerja 0.0150 HOK 30,000.00 450.00
Tukang kayu 0.1500 HOK 42,000.00 6,300.00
Kepala tukang 0.0150 HOK 42,000.00 630.00
Mandor 0.00075 HOK 41,000.00 30.75
Total 7,410.75 12,500.00
Total Harga 19,910.75
Keuntungan 1,991.08
Jumlah Total 21,901.83
a b c d e f=(cxe) g=(cxe) h

L-06 1 BUAH PASANG ENGSEL JENDELA KUPU-KUPU


Engsel jendela 1.0000 bh 7,200.00 7,200.00
Pekerja 0.0100 HOK 30,000.00 300.00
Tukang kayu 0.1000 HOK 42,000.00 4,200.00
Kepala tukang 0.0100 HOK 42,000.00 420.00
Mandor 0.0005 HOK 41,000.00 20.50
Total 4,940.50 7,200.00
Total Harga 12,140.50
Keuntungan 1,214.05
Jumlah Total 13,354.55

L-07 1 BUAH PASANG ENGSEL ANGIN


Engsel angin 1.0000 bh 7,200.00 7,200.00
Pekerja 0.0200 HOK 30,000.00 600.00
Tukang kayu 0.2000 HOK 42,000.00 8,400.00
Kepala tukang 0.0200 HOK 42,000.00 840.00
Mandor 0.01000 HOK 41,000.00 410.00
Total 10,250.00 7,200.00
Total Harga 17,450.00
Keuntungan 1,745.00
Jumlah Total 19,195.00

L-09 1 BUAH PASANG KAIT ANGIN


Kait angin 1.0000 bh 0.00 0.00
Pekerja 0.0150 HOK 30,000.00 450.00
Tukang kayu 0.1500 HOK 42,000.00 6,300.00
Kepala tukang 0.0150 HOK 42,000.00 630.00
Mandor 0.00075 HOK 41,000.00 30.75
Total 7,410.75 0.00
Total Harga 7,410.75
Keuntungan 741.08
Jumlah Total 8,151.83

L-11 1 BUAH PASANG KUNCI SELOT


Kunci selot 1.0000 bh 3,500.00 3,500.00
Pekerja 0.0200 HOK 30,000.00 600.00
Tukang kayu 0.2000 HOK 42,000.00 8,400.00
Kepala tukang 0.0200 HOK 42,000.00 840.00
Mandor 0.0010 HOK 41,000.00 41.00
Total 9,881.00 3,500.00
Total Harga 13,381.00
Keuntungan 1,338.10
Jumlah Total 14,719.10

L-12 1 BUAH PASANG PEGANGAN PINTU / DOOR HOLDER


Door holder 1.0000 bh 36,000.00 36,000.00
Pekerja 0.0500 HOK 30,000.00 1,500.00
Tukang kayu 0.5000 HOK 42,000.00 21,000.00
Kepala tukang 0.0500 HOK 42,000.00 2,100.00
Mandor 0.0025 HOK 41,000.00 102.50
Total 24,702.50 36,000.00
Total Harga 60,702.50
Keuntungan 6,070.25
Jumlah Total 66,772.75

L-14 1 BUAH PASANG REL PINTU DORONG


Rel pintu dorong 1.0000 bh 302,000.00 302,000.00
a b c d e f=(cxe) g=(cxe) h
Pekerja 0.0600 HOK 30,000.00 1,800.00
Tukang kayu 0.6000 HOK 42,000.00 25,200.00
Kepala tukang 0.0600 HOK 42,000.00 2,520.00
Mandor 0.0030 HOK 41,000.00 123.00
Total 29,643.00 302,000.00
Total Harga 331,643.00
Keuntungan 33,164.30
Jumlah Total 364,807.30

L-15 1 BUAH PASANG KUNCI LEMARI


Kunci lemari 1.0000 Bh 9,000.00 9,000.00
Pekerja 0.0250 HOK 30,000.00 750.00
Tukang kayu 0.2500 HOK 42,000.00 10,500.00
Kepala tukang 0.0250 HOK 42,000.00 1,050.00
Mandor 0.00125 HOK 41,000.00 51.25
Total 12,351.25 9,000.00
Total Harga 21,351.25
Keuntungan 2,135.13
Jumlah Total 23,486.38

L-16 1 m2 PASANG KACA TEBAL 3 mm


Kaca 1.1000 M2 37,500.00 41,250.00
Pekerja 0.0150 HOK 30,000.00 450.00
Tukang kayu 0.1500 HOK 42,000.00 6,300.00
Kepala tukang 0.0150 HOK 42,000.00 630.00
Mandor 0.00075 HOK 41,000.00 30.75
Total 7,410.75 41,250.00
Total Harga 48,660.75
Keuntungan 4,866.08
Jumlah Total 53,526.83

L-17 1 m2 BUAH PASANG KACA TEBAL 5 mm


Kaca 1.1000 bh 47,500.00 52,250.00
Pekerja 0.0150 HOK 30,000.00 450.00
Tukang kayu 0.1500 HOK 42,000.00 6,300.00
Kepala tukang 0.0150 HOK 42,000.00 630.00
Mandor 0.00075 HOK 41,000.00 30.75
Total 7,410.75 52,250.00
Total Harga 59,660.75
Keuntungan 5,966.08
Jumlah Total 65,626.83

L-18 1 m2 BUAH PASANG KACA TEBAL 8 mm


Kaca polos 1.1000 bh 0.00
Pekerja 0.0165 HOK 0.00
Tukang kayu 0.1650 HOK 0.00
Kepala tukang 0.0165 HOK 0.00
Mandor 0.00080 HOK 0.00
Total 0.00 0.00
Total Harga -

L-20 1 m2 BUAH PASANG KACA CERMIN TEBAL 3 mm


Kaca cermin 1.1000 bh 0.00
Pekerja 0.0150 HOK 0.00
Tukang kayu 0.1500 HOK 0.00
Kepala tukang 0.0150 HOK 0.00
Mandor 0.00075 HOK 0.00
Total 0.00 0.00
a b c d e f=(cxe) g=(cxe) h
Total Harga -

L-23 1 m2 BUAH PASANG KACA WIREGLASS TEBAL 5 mm


Kaca wireglass 1.1000 bh 0.00
Pekerja 0.0150 HOK 0.00
Tukang kayu 0.1500 HOK 0.00
Kepala tukang 0.0150 HOK 0.00
Mandor 0.00075 HOK 0.00
Total 0.00 0.00
Total Harga -

L-24 1 m2 BUAH PASANG KACA PATRI TEBAL 5 mm


Kaca wireglass 1.1000 bh 0.00
Pekerja 0.0150 HOK 0.00
Tukang kayu 0.1500 HOK 0.00
Kepala tukang 0.0150 HOK 0.00
Mandor 0.00075 HOK 0.00
Total 0.00 0.00
Total Harga -

M PEKERJAAN PENUTUP LANTAI DAN DINDING

M-02 1 m2 PASANG LANTAI UBIN PC ABU-ABU UKURAN 30X30 cm


Ubin abu-abu 30x30 cm 11.8700 bh 1,700.00 20,179.00
Semen Portland 10.0000 Kg 1,030.00 10,300.00
Pasir pasang 0.0215 m3 65,000.00 1,397.50
Pekerja 0.2600 HOK 30,000.00 7,800.00
Tukang batu 0.1250 HOK 38,500.00 4,812.50
Kepala tukang 0.0125 HOK 42,000.00 525.00
Mandor 0.0130 HOK 41,000.00 533.00
Total 13,670.50 31,876.50
Total Harga 45,547.00
Keuntungan 4,554.70
Jumlah Total 50,101.70

M-03 1 m2 PASANG LANTAI UBIN PC ABU-ABU UKURAN 20X20 cm


Ubin abu-abu 20x20 cm 26.5000 bh 0.00
Semen Portland 10.4000 Kg 0.00
Pasir pasang 0.0135 m3 0.00
Pekerja 0.2700 HOK 0.00
Tukang batu 0.1300 HOK 0.00
Kepala tukang 0.0130 HOK 0.00
Mandor 0.0135 HOK 0.00
Total 0.00 0.00
Total Harga -
Keuntungan -
Jumlah Total -

M-05 1 m2 PASANG LANTAI UBIN PC WARNA UKURAN 30X30 cm


Ubin warna 30x30 cm 11.8700 bh 0.00
Semen Portland 8.3600 Kg 0.00
Pasir pasang 0.0230 m3 0.00
Semen warna 0.9000 Kg 0.00
Pekerja 0.2500 HOK 0.00
Tukang batu 0.1200 HOK 0.00
Kepala tukang 0.0120 HOK 0.00
Mandor 0.0125 HOK 0.00
a b c d e f=(cxe) g=(cxe) h
Total 0.00 0.00
Total Harga -
Keuntungan -
Jumlah Total -

M-06 1 m2 PASANG LANTAI UBIN PC WARNA UKURAN 20X20 cm


Ubin warna 20x20 cm 26.5000 bh 0.00
Semen Portland 8.7600 Kg 0.00
Pasir pasang 0.0230 m3 0.00
Semen warna 0.9000 Kg 0.00
Pekerja 0.2700 HOK 0.00
Tukang batu 0.1300 HOK 0.00
Kepala tukang 0.0130 HOK 0.00
Mandor 0.0135 HOK 0.00
Total 0.00 0.00
Total Harga -
Keuntungan -
Jumlah Total -

M-09 1 m2 PASANG LANTAI UBIN GRANITO UKURAN 40X40 cm


Ubin granito 40x40 cm 6.9300 bh 0.00
Semen Portland 9.8000 Kg 0.00
Pasir pasang 0.0215 m3 0.00
Semen warna 1.3000 Kg 0.00
Pekerja 0.2500 HOK 0.00
Tukang batu 0.1200 HOK 0.00
Kepala tukang 0.0120 HOK 0.00
Mandor 0.0125 HOK 0.00
Total 0.00 0.00
Total Harga -
Keuntungan -
Jumlah Total -

M-10 1 m2 PASANG LANTAI UBIN GRANITO UKURAN 30X30 cm


Ubin granito 30x30 cm 11.8700 bh 0.00
Semen Portland 10.0000 Kg 0.00
Pasir pasang 0.0215 m3 0.00
Semen warna 1.5000 Kg 0.00
Pekerja 0.2600 HOK 0.00
Tukang batu 0.1250 HOK 0.00
Kepala tukang 0.0125 HOK 0.00
Mandor 0.0130 HOK 0.00
Total 0.00 0.00
Total Harga -
Keuntungan -
Jumlah Total -

M-16 1 m2 PASANG PLINT UBIN PC ABU-ABU UKURAN 15X20 cm


Plin ubint 15x20 cm 5.3000 bh 0.00
Semen Portland 1.5600 Kg 0.00
Pasir pasang 0.0040 m3 0.00
Pekerja 0.0600 HOK 0.00
Tukang batu 0.0300 HOK 0.00
Kepala tukang 0.0030 HOK 0.00
Mandor 0.0030 HOK 0.00
Total 0.00 0.00
Total Harga -
a b c d e f=(cxe) g=(cxe) h
Keuntungan -
Jumlah Total -

M-17 1 m' PASANG PLINT UBIN PC ABU-ABU UKURAN 10X30 cm


Plint ubin 10x30 cm 3.5300 bh 0.00
Semen Portland 1.5600 Kg 0.00
Pasir pasang 0.0030 m3 0.00
Pekerja 0.0600 HOK 0.00
Tukang batu 0.0300 HOK 0.00
Kepala tukang 0.0030 HOK 0.00
Mandor 0.0030 HOK 0.00
Total 0.00 0.00
Total Harga -
Keuntungan -
Jumlah Total -

M-19 1 m2 PASANG PLINT UBIN PC WARNA UKURAN 10X20 cm


Plin ubin pc warna 10x20 cm 5.3000 bh 0.00
Semen Portland 1.2000 Kg 0.00
Pasir pasang 0.0030 m3 0.00
Semen warna 0.1900 Kg
Pekerja 0.0600 HOK 0.00
Tukang batu 0.0300 HOK 0.00
Kepala tukang 0.0030 HOK 0.00
Mandor 0.0030 HOK 0.00
Total 0.00 0.00
Total Harga -
Keuntungan -
Jumlah Total -

M-25 1 m2 PASANG PLINT UBIN GRANITO UKURAN 10X30 cm


Plin ubin granito 10x30 cm 3.3300 bh 0.00
Semen Portland 1.6500 Kg 0.00
Pasir pasang 0.0032 m3 0.00
Semen warna 0.1000 Kg
Pekerja 0.9000 HOK 0.00
Tukang batu 0.0900 HOK 0.00
Kepala tukang 0.0090 HOK 0.00
Mandor 0.0045 HOK 0.00
Total 0.00 0.00
Total Harga -
Keuntungan -
Jumlah Total -

M-37 1 m' PASANG PLINT KERAMIK ARTISTIK UKURAN 10X20 cm


Plint keramik artistik 10x20 cm 5.0000 bh 0.00
Semen Portland 1.6500 Kg 0.00
Pasir pasang 0.0032 m3 0.00
Semen warna 0.1000 Kg 0.00
Pekerja 0.0900 HOK 0.00
Tukang batu 0.0900 HOK 0.00
Kepala tukang 0.0090 HOK 0.00
Mandor 0.0045 HOK 0.00
Total 0.00 0.00
Total Harga -
Keuntungan -
Jumlah Total -
a b c d e f=(cxe) g=(cxe) h

M-42 1 m2 PASANG LANTAI KERAMIK 10X20 cm, WARNA ( Anti Selip )


Ubin keramik artistik 10x20 cm, anti selip 50.0000 bh 720.00 36,000.00
Semen Portland 0.2276 Kg 1,030.00 234.43
Pasir pasang 0.0420 m3 95,000.00 3,990.00
Semen warna 1.5000 Kg 7,000.00 10,500.00
Pekerja 0.6200 HOK 30,000.00 18,600.00
Tukang batu 0.3500 HOK 38,500.00 13,475.00
Kepala tukang 0.0350 HOK 42,000.00 1,470.00
Mandor 0.0300 HOK 41,000.00 1,230.00
Total 34,775.00 50,724.43
Total Harga 85,499.43
Keuntungan 8,549.94
Jumlah Total 94,049.37

M-43 1 m2 PASANG LANTAI KERAMIK 15X15 cm


Ubin keramik15x15 cm 44.0000 bh 818.18 36,000.00
Semen Portland 11.3800 Kg 1,030.00 11,721.40
Pasir pasang 0.0420 m3 95,000.00 3,990.00
Semen warna 1.5000 Kg 7,000.00 10,500.00
Pekerja 0.6200 HOK 30,000.00 18,600.00
Tukang batu 0.3500 HOK 38,500.00 13,475.00
Kepala tukang 0.0350 HOK 42,000.00 1,470.00
Mandor 0.0300 HOK 41,000.00 1,230.00
Total 34,775.00 62,211.40
Total Harga 96,986.40
Keuntungan 9,698.64
Jumlah Total 106,685.04

M-44 1 m2 PASANG LANTAI KERAMIK 20X20 cm


Ubin keramik 20x20 cm 25.0000 bh 1,560.00 39,000.00
Semen Portland 11.3800 Kg 1,030.00 11,721.40
Pasir pasang 0.0420 m3 95,000.00 3,990.00
Semen warna 1.5000 Kg 7,000.00 10,500.00
Pekerja 0.6200 HOK 30,000.00 18,600.00
Tukang batu 0.3500 HOK 38,500.00 13,475.00
Kepala tukang 0.0350 HOK 42,000.00 1,470.00
Mandor 0.0300 HOK 41,000.00 1,230.00
Total 34,775.00 65,211.40
Total Harga 99,986.40
Keuntungan 9,998.64
Jumlah Total 109,985.04

M-47 1 m2 PASANG LANTAI KERAMIK 33X33 cm


Ubin keramik 33x33 cm 10.0000 bh 3,000.00 30,000.00
Semen Portland 11.3800 Kg 1,030.00 11,721.40
Pasir pasang 0.0420 m3 95,000.00 3,990.00
Semen warna 1.5000 Kg 7,000.00 10,500.00
Pekerja 0.6200 HOK 30,000.00 18,600.00
Tukang batu 0.3500 HOK 38,500.00 13,475.00
Kepala tukang 0.0350 HOK 42,000.00 1,470.00
Mandor 0.0300 HOK 41,000.00 1,230.00
Total 34,775.00 56,211.40
Total Harga 90,986.40
Keuntungan 9,098.64
Jumlah Total 100,085.04

M-59 1 m2 PASANG DINDING PORSELIN 11X11 cm, WARNA


a b c d e f=(cxe) g=(cxe) h
Porselin 11x11 cm, warna 83.0000 bh 469.88 39,000.00
Semen Abu-abu 9.3000 Kg 1,030.00 9,579.00
Pasir pasang 0.0180 m3 95,000.00 1,710.00
Semen warna 1.5000 Kg 7,000.00 10,500.00
Pekerja 0.6200 HOK 30,000.00 18,600.00
Tukang batu 0.5000 HOK 38,500.00 19,250.00
Kepala tukang 0.0500 HOK 42,000.00 2,100.00
Mandor 0.0300 HOK 41,000.00 1,230.00
Total 41,180.00 60,789.00
Total Harga 101,969.00
Keuntungan 10,196.90
Jumlah Total 112,165.90

M-62 1 m2 PASANG DINDING PORSELIN 10X20 cm, WARNA


Keramik 10x20 cm warna 50.0000 bh 720.00 36,000.00
Semen Abu-abu 9.3000 Kg 1,030.00 9,579.00
Pasir pasang 0.0180 m3 95,000.00 1,710.00
Semen warna 1.5000 Kg 7,000.00 10,500.00
Pekerja 0.6000 HOK 30,000.00 18,000.00
Tukang batu 0.4500 HOK 38,500.00 17,325.00
Kepala tukang 0.0450 HOK 42,000.00 1,890.00
Mandor 0.0300 HOK 41,000.00 1,230.00
Total 38,445.00 57,789.00
Total Harga 96,234.00
Keuntungan 9,623.40
Jumlah Total 105,857.40

M-64 1 m2 PASANG DINDING KERAMIK 10X20 cm


Keramik 10x20 cm 50.0000 bh 720.00 36,000.00
Semen Abu-abu 9.3000 Kg 1,030.00 9,579.00
Pasir pasang 0.0180 m3 95,000.00 1,710.00
Semen warna 1.5000 Kg 7,000.00 10,500.00
Pekerja 0.6000 HOK 30,000.00 18,000.00
Tukang batu 0.4500 HOK 38,500.00 17,325.00
Kepala tukang 0.0450 HOK 42,000.00 1,890.00
Mandor 0.0300 HOK 41,000.00 1,230.00
Total 38,445.00 57,789.00
Total Harga 96,234.00
Keuntungan 9,623.40
Jumlah Total 105,857.40

M-67 1 m2 PASANG DINDING KERAMIK 15X15 cm


Keramik 15x15 cm 45.0000 bh 0.00
Semen Abu-abu 9.3000 Kg 0.00
Pasir pasang 0.0180 m3 0.00
Semen warna 1.5000 Kg 0.00
Pekerja 0.6000 HOK 0.00
Tukang batu 0.0450 HOK 0.00
Kepala tukang 0.0450 HOK 0.00
Mandor 0.0300 HOK 0.00
Total 0.00 0.00
Total Harga -
Keuntungan -
Jumlah Total -

M-68 1 m2 PASANG DINDING KERAMIK 20X20 cm


Keramik 20x20 cm 25.0000 bh 0.00
Semen Abu-abu 9.3000 Kg 0.00
a b c d e f=(cxe) g=(cxe) h
Pasir pasang 0.0180 m3 0.00
Semen warna 1.5000 Kg 0.00
Pekerja 0.6000 HOK 0.00
Tukang batu 0.1000 HOK 0.00
Kepala tukang 0.0450 HOK 0.00
Mandor 0.0300 HOK 0.00
Total 0.00 0.00
Total Harga -
Keuntungan -
Jumlah Total -

M-70 1 m2 PASANG DINDING MARMER


Marmer 1.0200 bh 0.00 0.00
Pacu Pancing 60 x 230 2.0000 bh 0.00 0.00
Semen Abu-abu 12.4400 Kg 0.00 0.00
Pasir pasang 0.0250 m3 0.00 0.00
Semen warna 1.5000 Kg 0.00 0.00
Pekerja 0.7200 HOK 0.00 0.00
Tukang batu 0.6500 HOK 0.00 0.00
Kepala tukang 0.0650 HOK 0.00 0.00
Mandor 0.0350 HOK 0.00 0.00
Total 0.00 0.00
Total Harga -
Keuntungan -
Jumlah Total -

M-74 1 m2 PASANG DINDING BATU TEMPEL HITAM


Batu tempel hitam 1.0500 m2 0.00
Semen Abu-abu 11.7500 Kg 0.00
Pasir pasang 0.0350 m3 0.00
Pekerja 0.6200 HOK 0.00
Tukang batu 0.3500 HOK 0.00
Kepala tukang 0.0350 HOK 0.00
Mandor 0.0300 HOK 0.00
Total 0.00 0.00
Total Harga -
Keuntungan -
Jumlah Total -

M-79 1 m2 PASANG WALL COVERING, LEBAR 50 cm


Vinyil wal covering, lebar 50 cm 1.1000 m2 0.00
Lem 0.2500 Kg 0.00
Pekerja 0.7500 HOK 0.00
Tukang batu 0.1700 HOK 0.00
Kepala tukang 0.0170 HOK 0.00
Mandor 0.0085 HOK 0.00
Total 0.00 0.00
Total Harga -
Keuntungan -
Jumlah Total -

M-82 1 m2 PLINT KAYU 2X10 cm


Kayu jati, papan 0.0024 m2 0.00
Paku skrup 3.5" 0.0500 Kg 0.00
Pekerja 0.1200 HOK 0.00
Tukang kayu 0.1200 HOK 0.00
Kepala tukang 0.0120 HOK 0.00
Mandor 0.0060 HOK 0.00
a b c d e f=(cxe) g=(cxe) h
Total 0.00 0.00
Total Harga -
Keuntungan -
Jumlah Total -

DIHITUNG 1 m2 PASANG LANTAI KERAMIK 30X30 cm putih (polos)


Ubin keramik 30x30 cm 11.0000 bh 2,700.00 29,700.00
Semen Portland 11.3800 Kg 1,030.00 11,721.40
Pasir pasang 0.0420 m3 95,000.00 3,990.00
Semen warna 1.5000 Kg 7,000.00 10,500.00
Pekerja 0.6200 HOK 30,000.00 18,600.00
Tukang batu 0.3500 HOK 38,500.00 13,475.00
Kepala tukang 0.0350 HOK 42,000.00 1,470.00
Mandor 0.0300 HOK 41,000.00 1,230.00
Total 34,775.00 55,911.40
Total Harga 90,686.40
Keuntungan 9,068.64
Jumlah Total 99,755.04

DIHITUNG 1 m2 PASANG LANTAI KERAMIK 30X30 cm warna


Ubin keramik 30x30 cm 11.0000 bh 3,240.00 35,640.00
Semen Portland 11.3800 Kg 1,030.00 11,721.40
Pasir pasang 0.0420 m3 95,000.00 3,990.00
Semen warna 1.5000 Kg 7,000.00 10,500.00
Pekerja 0.6200 HOK 30,000.00 18,600.00
Tukang batu 0.3500 HOK 38,500.00 13,475.00
Kepala tukang 0.0350 HOK 42,000.00 1,470.00
Mandor 0.0300 HOK 41,000.00 1,230.00
Total 34,775.00 61,851.40
Total Harga 96,626.40
Keuntungan 9,662.64
Jumlah Total 106,289.04

DIHITUNG 1 m2 PASANG LANTAI KERAMIK 40X40 cm putih (polos)


Ubin keramik 40x40 cm 6.9300 bh 6,080.00 42,134.40
Semen Portland 11.3800 Kg 1,030.00 11,721.40
Pasir pasang 0.0420 m3 95,000.00 3,990.00
Semen warna 1.5000 Kg 7,000.00 10,500.00
Pekerja 0.6200 HOK 30,000.00 18,600.00
Tukang batu 0.3500 HOK 38,500.00 13,475.00
Kepala tukang 0.0350 HOK 42,000.00 1,470.00
Mandor 0.0300 HOK 41,000.00 1,230.00
Total 34,775.00 68,345.80
Total Harga 103,120.80
Keuntungan 10,312.08
Jumlah Total 113,432.88

DIHITUNG 1 m2 PASANG LANTAI KERAMIK 40X40 cm warna


Ubin keramik 40x40 cm 6.9300 bh 6,560.00 45,460.80
Semen Portland 11.3800 Kg 1,030.00 11,721.40
Pasir pasang 0.0420 m3 95,000.00 3,990.00
Semen warna 1.5000 Kg 7,000.00 10,500.00
Pekerja 0.6200 HOK 30,000.00 18,600.00
Tukang batu 0.3500 HOK 38,500.00 13,475.00
Kepala tukang 0.0350 HOK 42,000.00 1,470.00
Mandor 0.0300 HOK 41,000.00 1,230.00
Total 34,775.00 71,672.20
Total Harga 106,447.20
a b c d e f=(cxe) g=(cxe) h
Keuntungan 10,644.72
Jumlah Total 117,091.92

DIHITUNG 1 m2 PASANG LANTAI KERAMIK 30X30 cm ANTI SELIP


Ubin keramik 30x30 cm anti selip 11.0000 bh 3,272.73 36,000.00
Semen Portland 11.3800 Kg 1,030.00 11,721.40
Pasir pasang 0.0420 m3 95,000.00 3,990.00
Semen warna 1.5000 Kg 7,000.00 10,500.00
Pekerja 0.6200 HOK 30,000.00 18,600.00
Tukang batu 0.3500 HOK 38,500.00 13,475.00
Kepala tukang 0.0350 HOK 42,000.00 1,470.00
Mandor 0.0300 HOK 41,000.00 1,230.00
Total 34,775.00 62,211.40
Total Harga 96,986.40
Keuntungan 9,698.64
Jumlah Total 106,685.04

DIHITUNG 1 m2 PASANG LANTAI KERAMIK 40X40 cm ANTI SELIP


Ubin keramik 40x40 cm anti selip 7.0000 bh 5,857.14 41,000.00
Semen Portland 11.3800 Kg 1,030.00 11,721.40
Pasir pasang 0.0420 m3 95,000.00 3,990.00
Semen warna 1.5000 Kg 7,000.00 10,500.00
Pekerja 0.6200 HOK 30,000.00 18,600.00
Tukang batu 0.3500 HOK 38,500.00 13,475.00
Kepala tukang 0.0350 HOK 42,000.00 1,470.00
Mandor 0.0300 HOK 41,000.00 1,230.00
Total 34,775.00 67,211.40
Total Harga 101,986.40
Keuntungan 10,198.64
Jumlah Total 112,185.04

DIHITUNG 1 m2 PASANG PAVING BLOCK 6 cm, WARNA (A139)


Paving block 6 cm, warna 1.0100 m2 25,000.00 25,250.00
Pasir pasang kali 0.1000 m3 95,000.00 9,500.00
Pekerja 0.2500 HOK 30,000.00 7,500.00
Tukang batu 0.5000 HOK 38,500.00 19,250.00
Kepala tukang 0.0250 HOK 42,000.00 1,050.00
Mandor 0.0030 HOK 41,000.00 123.00
Peralatan 0.0000 Ls 3,000.00 0.00
Total 27,923.00 34,750.00
Total Harga 62,673.00
Keuntungan 6,267.30
Jumlah Total 68,940.30

DIHITUNG 1 m2 PASANG PAVING BLOCK 6 cm, NATURAL (A141)


Paving block 6 cm, Natural 1.0100 m2 28,000.00 28,280.00
Pasir pasang kali 0.1000 m3 95,000.00 9,500.00
Pekerja 0.2500 HOK 30,000.00 7,500.00
Tukang batu 0.5000 HOK 38,500.00 19,250.00
Kepala tukang 0.0250 HOK 42,000.00 1,050.00
Mandor 0.0030 HOK 41,000.00 123.00
Peralatan 0.0000 Ls 3,000.00 0.00
Total 27,923.00 37,780.00
Total Harga 65,703.00
Keuntungan 6,570.30
Jumlah Total 72,273.30

DIHITUNG 1 m2 PASANG PAVING BLOCK 8 cm, WARNA (A140)


a b c d e f=(cxe) g=(cxe) h
Paving block 8 cm, warna 1.0100 m2 38,000.00 38,380.00
Pasir pasang kali 0.1000 m3 95,000.00 9,500.00
Pekerja 0.2500 HOK 30,000.00 7,500.00
Tukang batu 0.5000 HOK 38,500.00 19,250.00
Kepala tukang 0.0250 HOK 42,000.00 1,050.00
Mandor 0.0030 HOK 41,000.00 123.00
Peralatan 0.0000 Ls 3,000.00 0.00
Total 27,923.00 47,880.00
Total Harga 75,803.00
Keuntungan 7,580.30
Jumlah Total 83,383.30

DIHITUNG 1 m2 PASANG PAVING BLOCK 8 cm, NATURAL (A142)


Paving block 8 cm, NATURAL 1.0100 m2 35,000.00 35,350.00
Pasir pasang kali 0.1000 m3 95,000.00 9,500.00
Pekerja 0.2500 HOK 30,000.00 7,500.00
Tukang batu 0.5000 HOK 38,500.00 19,250.00
Kepala tukang 0.0250 HOK 42,000.00 1,050.00
Mandor 0.0030 HOK 41,000.00 123.00
Peralatan 0.0000 Ls 3,000.00 0.00
Total 27,923.00 44,850.00
Total Harga 72,773.00
Keuntungan 7,277.30
Jumlah Total 80,050.30

N PEKERJAAN PENGECATAN
N-01 1 m2 MENGIKIS / MENGEROK PERMUKAAN CAT TEMBOK LAMA
Soda api 0.0500 Kg 0.00 0.00
Pekerja 0.1500 HOK 30,000.00 4,500.00
Mandor 0.0025 HOK 41,000.00 102.50
Total 4,602.50 0.00
Total Harga 4,602.50
Keuntungan 460.25
Jumlah Total 5,062.75

N-02 1 m2 MENCUCI BIDANG PERMUKAAN TEMBOK YANG PERNAH DI CAT


Sabun 0.0500 Kg 1,500.00 75.00
Pekerja 0.1500 HOK 30,000.00 4,500.00
Mandor 0.0025 HOK 41,000.00 102.50
Total 4,602.50 75.00
Total Harga 4,677.50
Keuntungan 467.75
Jumlah Total 5,145.25

N-03 1 m2 MENGEROK KARAT CAT LAMA PERMUKAAN BAJA DENGAN CARA MANUAL
Sabun 0.0500 Kg 1,500.00 75.00
Pekerja 0.1500 HOK 30,000.00 4,500.00
Mandor 0.0025 HOK 41,000.00 102.50
Total 4,602.50 75.00
Total Harga 4,677.50
Keuntungan 467.75
Jumlah Total 5,145.25

N-04 1 m2 MENYABUN PERMUKAAN TEMBOK LAMA


Sabun 0.0500 Kg 1,500.00 75.00
Pekerja 0.1500 HOK 30,000.00 4,500.00
Mandor 0.0025 HOK 41,000.00 102.50
a b c d e f=(cxe) g=(cxe) h
Total 4,602.50 75.00
Total Harga 4,677.50
Keuntungan 467.75
Jumlah Total 5,145.25

N-06 1 m2 MENDEMPUL DAN MENGGOSOK KAYU


Dempul jadi 0.0800 Kg 12,000.00 960.00
Minyak cat 0.0200 Kg 6,000.00 120.00
Batu apung 0.0100 Kg 1,500.00 15.00
Pekerja 0.0400 HOK 30,000.00 1,200.00
Tukang cat 0.0400 HOK 35,500.00 1,420.00
Kepala tukang 0.0040 HOK 42,000.00 168.00
Mandor 0.0025 HOK 41,000.00 102.50
Total 2,890.50 1,095.00
Total Harga 3,985.50
Keuntungan 398.55
Jumlah Total 4,384.05

N-07 1 m2 PENGECATAN BIDANG KAYU LAMA


Plamir 0.1500 Kg 12,000.00 1,800.00
Cat dasar 0.1700 Kg 35,000.00 5,950.00
Cat Penutup 0.1700 Kg 35,000.00 5,950.00
Pekerja 0.0700 HOK 30,000.00 2,100.00
Tukang cat 0.0750 HOK 35,500.00 2,662.50
Kepala tukang 0.0075 HOK 42,000.00 315.00
Mandor 0.0025 HOK 41,000.00 102.50
Total 5,180.00 13,700.00
Total Harga 18,880.00
Keuntungan 1,888.00
Jumlah Total 20,768.00

N-08 1 m2 PENGECATAN BIDANG KAYU BARU (1 Lapis Plamir; 1 Lapis Cat dasar; 2 Lapis Cat Penutup)
Cat meni 0.2000 Kg 18,000.00 3,600.00
Plamir 0.1500 Kg 12,000.00 1,800.00
Cat dasar 0.1700 Kg 35,000.00 5,950.00
Cat Penutup ( 2 kali ) 0.2600 Kg 35,000.00 9,100.00
Pekerja 0.0700 HOK 30,000.00 2,100.00
Tukang cat 0.0090 HOK 35,500.00 319.50
Kepala tukang 0.0060 HOK 42,000.00 252.00
Mandor 0.0025 HOK 41,000.00 102.50
Total 2,774.00 20,450.00
Total Harga 23,224.00
Keuntungan 2,322.40
Jumlah Total 25,546.40

N-09 1 m2 PENGECATAN BIDANG KAYU BARU (1 Lapis Plamir; 1 Lapis Cat dasar; 3 Lapis Cat Penutup)
Cat meni 0.2000 Kg 18,000.00 3,600.00
Plamir 0.1500 Kg 12,000.00 1,800.00
Cat dasar 0.1700 Kg 35,000.00 5,950.00
Cat Penutup ( 3 kali ) 0.3500 Kg 35,000.00 12,250.00
Pekerja 0.0700 HOK 30,000.00 2,100.00
Tukang cat 0.1050 HOK 35,500.00 3,727.50
Kepala tukang 0.0040 HOK 42,000.00 168.00
Mandor 0.0025 HOK 41,000.00 102.50
Total 6,098.00 23,600.00
Total Harga 29,698.00
Keuntungan 2,969.80
Jumlah Total 32,667.80
a b c d e f=(cxe) g=(cxe) h

N-11 1 m2 PELABURAN BIDANG KAYU DENGAN POLITUR


Politur 0.1500 Ltr 12,600.00 1,890.00
Politur jadi 0.3720 Ltr 27,000.00 10,044.00
Ampelas 2.0000 Lbr 6,000.00 12,000.00
Tukang cat 0.0600 HOK 35,500.00 2,130.00
Kepala tukang 0.0160 HOK 42,000.00 672.00
Mandor 0.0025 HOK 41,000.00 102.50
Total 2,904.50 23,934.00
Total Harga 26,838.50
Keuntungan 2,683.85
Jumlah Total 29,522.35

N-12 1 m2 PELABURAN BIDANG KAYU DENGAN CAT RESIDU DAN TER


Residu atau ter 0.3500 Ltr 1,100.00 385.00
Pekerja 0.1000 HOK 30,000.00 3,000.00
Mandor 0.0060 HOK 41,000.00 246.00
Total 3,246.00 385.00
Total Harga 3,631.00
Keuntungan 363.10
Jumlah Total 3,994.10

N-13 1 m2 PELABURAN BIDANG KAYU DENGAN VERNIS


Vernis 0.1500 Ltr 12,000.00 1,800.00
Dempul 0.0500 Kg 12,000.00 600.00
Ampelas 0.1000 Lbr 6,000.00 600.00
Kuas 0.0100 Bh 9,000.00 90.00
Pekerja 0.1600 HOK 30,000.00 4,800.00
Tukang cat 0.1600 HOK 35,500.00 5,680.00
Kepala tukang 0.0160 HOK 42,000.00 672.00
Mandor 0.0025 HOK 41,000.00 102.50
Total 11,254.50 3,090.00
Total Harga 14,344.50
Keuntungan 1,434.45
Jumlah Total 15,778.95

N-14 1 m2 PENGECATAN BIDANG TEMBOK BARU (1 Lapis Plamir; 1 Lapis Cat dasar; 2 Lapis Cat Penutup)
Plamir 0.1000 Kg 12,000.00 1,200.00
Cat dasar 0.1000 Kg 12,000.00 1,200.00
Cat Penutup ( 2 kali ) 0.2600 Kg 12,000.00 3,120.00
Pekerja 0.0200 HOK 30,000.00 600.00
Tukang cat 0.0630 HOK 35,500.00 2,236.50
Kepala tukang 0.0063 HOK 42,000.00 264.60
Mandor 0.0025 HOK 41,000.00 102.50
Total 3,203.60 5,520.00
Total Harga 8,723.60
Keuntungan 872.36
Jumlah Total 9,595.96

N-15 1 m2 PENGECATAN BIDANG TEMBOK LAMA ( 1 Lapis Cat dasar; 2 Lapis Cat Penutup )
Cat dasar 0.1200 Kg 12,000.00 1,440.00
Cat Penutup ( 2 kali ) 0.1800 Kg 12,000.00 2,160.00
Pekerja 0.0280 HOK 30,000.00 840.00
Tukang cat 0.0420 HOK 35,500.00 1,491.00
Kepala tukang 0.0042 HOK 42,000.00 176.40
Mandor 0.0025 HOK 41,000.00 102.50
Total 2,609.90 3,600.00
Total Harga 6,209.90
Keuntungan 620.99
a b c d e f=(cxe) g=(cxe) h
Jumlah Total 6,830.89

N-19 1 m2 PEMASANGAN WALL PAPER


Wall paper 1.2000 m3 0.00
Perekat 0.2000 Kg 0.00
Pekerja 0.0200 HOK 0.00
Tukang cat 0.2000 HOK 0.00
Kepala tukang 0.0020 HOK 0.00
Mandor 0.0025 HOK 0.00
Total 0.00 0.00
Total Harga -
Keuntungan -
Jumlah Total -

N-20 1 m2 PENGECATAN PERMUKAAN BAJA DENGAN MENI BESI


Meni besi 0.1000 Kg 18,000.00 1,800.00
Kuas 0.0100 Bh 9,000.00 90.00
Pekerja 0.0200 HOK 30,000.00 600.00
Tukang cat 0.2000 HOK 35,500.00 7,100.00
Kepala tukang 0.0200 HOK 42,000.00 840.00
Mandor 0.0100 HOK 41,000.00 410.00
Total 8,950.00 1,890.00
Total Harga 10,840.00
Keuntungan 1,084.00
Jumlah Total 11,924.00

N-21 1 m2 PENGECATAN PERMUKAAN BAJA DENGAN MENI BESI DAN PERANCAH


Meni besi 0.1000 Kg 18,000.00 1,800.00
Kuas 0.0100 Bh 9,000.00 90.00
Perancah kayu 0.0020 m3 1,400,000.00 2,800.00
Pekerja 0.2500 HOK 30,000.00 7,500.00
Tukang cat 0.2250 HOK 35,500.00 7,987.50
Kepala tukang 0.0225 HOK 42,000.00 945.00
Mandor 0.0075 HOK 41,000.00 307.50
Total 16,740.00 4,690.00
Total Harga 21,430.00
Keuntungan 2,143.00
Jumlah Total 23,573.00

N-22 1 m2 PENGECATAN PERMUKAAN BAJA LAPIS SENG GALBANI SECARA MANUAL (4 lapis cat konvensional, tebal 200 um)
Cat dasar 0.1100 Kg 0.00
Cat antara 0.1700 Kg 0.00
Cat penutup 0.0800 Kg 0.00
Pekerja 0.5000 HOK 0.00
Tukang cat 0.8000 HOK 0.00
Kepala tukang 0.3000 HOK 0.00
Mandor 0.2000 HOK 0.00
Total 0.00 0.00
Total Harga -

N-23 1 m2 PENGECATAN PERMUKAAN BAJA LAPIS GALBANI SECARA MANUAL (1 lapis cat mutakhir, tebal 200 um)
Cat 0.3000 Kg 0.00
Pekerja 0.0060 HOK 0.00
Tukang cat 0.0600 HOK 0.00
Kepala tukang 0.0120 HOK 0.00
Mandor 0.0060 HOK 0.00
Total 0.00 0.00
Total Harga -
a b c d e f=(cxe) g=(cxe) h

Dihitung 1 KG. PEKERJAAN BESI


Besi Profil 1.0500 kg 0.00 0.00
Pekerja 0.0600 HOK 0.00 0.00
Tukang Besi Profil Terampil 0.0040 HOK 0.00 0.00
Kepala Tukang Besi Profil 0.0010 HOK 0.00 0.00
Mandor 0.0002 HOK 0.00 0.00
Peralatan (O2,Solar, Elpiji, kawat las dll) 0.1250 Lot 0.00 0.00
Total 0.00 0.00
Total Harga -
Keuntungan -
Jumlah Total -
O-01 1 M2 HOTMIX TANGAN T=3 CM
Screen 0.0450 M3 185,000.00 8,325.00
Aspal Panas 5.0000 Kg 10,800.00 54,000.00
Kayu Bakar 0.0080 M3 150,000.00 1,200.00
Pekerja Setengah Terampil 0.0800 HOK 55,000.00 4,400.00
Pekerja Terampil 0.0300 HOK 80,000.00 2,400.00
Mandor 0.0300 HOK 90,000.00 2,700.00
Peralatan 0.2500 Lot 63,525.00 15,881.25
Total 25,381.25 63,525.00 88,906.25
Keuntungan 13,335.94
Total Harga 102,242.19
ANALISA HARGA SATUAN PEKERJAAN
WILAYAH KOTA TASIKMALAYA
TAHUN ANGGARAN 2011
Keuntungan 10 % 0.1500
HARGA HARGA HARGA SATUAN
KODE JENIS PEKERJAAN KOEFISIEN SATUAN UPAH BAHAN PEKERJAAN
6101721836
( Rp ) ( Rp ) ( Rp ) ( Rp4977932000
)
a b c d e f=(cxe) g=(cxe) h 5495470000
5336458000
A PEKERJAAN PERSIAPAN ###
A-01 1 m' PAGAR SEMENTARA DARI KAYU, tinggi=2 METER
Dolken Kayu D 8-10/400 Cm 1.2500 Btg 15,000.00 18,750.00
Semen Portland 2.5000 kg 1,090.00 2,725.00
Pasir Beton 0.0050 m3 125,000.00 625.00 ###
Koral Beton 0.0090 m3 125,000.00 1,125.00 ###
Kayu 5/7 0.0720 m3 1,300,000.00 93,600.00 ###
Paku biasa 2"-5" 0.0600 Kg 11,000.00 660.00 ###
Residu 0.4000 Lt 1,200.00 480.00 ###
Tukang Kayu 0.2000 HOK 45,000.00 9,000.00
Pekerja 0.4000 HOK 35,000.00 14,000.00
Kepala Tukang 0.0200 HOK 50,000.00 1,000.00
Mandor 0.0200 HOK 50,000.00 1,000.00
Total 25,000.00 117,965.00
Total Harga 142,965.00
Keuntungan 21,444.75
Jumlah Total 164,409.75

A-02 1 m' PAGAR SEMENTARA /PENGAMAN PROYEK DARI SENG GELOMBANG, tinggi=2 METER
Dolken Kayu D 8-10/400 Cm 1.2500 Btg 15,000.00 18,750.00
Semen Portland 2.5000 Kg 1,090.00 2,725.00
Seng gelombang 3"-5" 1.2000 lbr 0.00 0.00
Pasir Beton 0.0050 m3 125,000.00 625.00
Koral Beton 0.0090 m3 125,000.00 1,125.00
Kayu 5/7 0.0720 m3 2,100,000.00 151,200.00
Paku biasa 2"-5" 0.0600 Kg 11,000.00 660.00
Meni besi 0.4500 Kg 15,000.00 6,750.00
Tukang kayu 0.2000 HOK 45,000.00 9,000.00
Pekerja 0.4000 HOK 35,000.00 14,000.00
Kepala tukang 0.0200 HOK 50,000.00 1,000.00
Mandor 0.0200 HOK 50,000.00 1,000.00
Total 25,000.00 181,835.00
Total Harga 206,835.00
Keuntungan 31,025.25
Jumlah Total 237,860.25

A-03 1 m' PAGAR SEMENTARA DARI KAWAT DURI TINGGI 1,8 METER
Dolken Kayu D 8-10/400 Cm 1.0000 Btg 15,000.00 15,000.00
Semen Portland 2.0000 Kg 1,090.00 2,180.00
Kawat Duri 25.0000 Kg 0.00 0.00
Pasir Beton 0.0050 m3 125,000.00 625.00
Koral Beton 0.0090 m3 125,000.00 1,125.00
Paku biasa 2"-5" 0.0600 Kg 11,000.00 660.00
Tukang kayu 0.2000 HOK 45,000.00 9,000.00
Pekerja 0.3000 HOK 35,000.00 10,500.00
Kepala tukang 0.0200 HOK 50,000.00 1,000.00
Mandor 0.0200 HOK 50,000.00 1,000.00
Total 21,500.00 19,590.00
Total Harga 41,090.00
Keuntungan 6,163.50
Jumlah Total 47,253.50

A-04 1 m' PENGUKURAN DAN PEMASANGAN BOUWPLANK


Kayu 5/7 0.0120 m3 1,300,000.00 15,600.00
Paku biasa 2"-5" 0.0200 Kg 11,000.00 220.00
Kayu papan 3/20 0.0070 m3 1,300,000.00 9,100.00
Tukang kayu 0.1000 HOK 45,000.00 4,500.00
Pekerja 0.1000 HOK 35,000.00 3,500.00
Kepala tukang 0.0100 HOK 50,000.00 500.00
a b c d e f=(cxe) g=(cxe) h 5495470000
Mandor 0.0050 HOK 50,000.00 250.00
Total 8,750.00 24,920.00
Total Harga 33,670.00
Keuntungan 5,050.50
Jumlah Total 38,720.50

A-05 1 m2 PEMBUATAN KANTOR SEMENTARA /DIREKSI DENGAN LANTAI PLESTERAN


Dolken Kayu D 8-10/400 Cm 1.2500 Btg 15,000.00
Kayu 0.1800 m3 1,300,000.00 234,000.00
Paku biasa 0.8500 Kg 11,000.00 9,350.00
Besi strip 1.1000 Kg 11,000.00 12,100.00
Semen Portland 35.0000 kg 1,090.00 38,150.00
Pasir Pasang 0.1500 m3 85,000.00 12,750.00
Pasir Beton 0.1000 m3 125,000.00 12,500.00
Koral Beton 0.1500 m3 100,000.00 15,000.00
Bata Merah 30.0000 Bh 550.00 16,500.00
Seng Plat 0.2500 Lbr 0.00 0.00
Jendela nako 2.0000 Bh
Kaca Polos 0.0800 m2
Kunci tanam 0.1500 Bh
Plywood 4 mm 0.0600 Lbr
Tukang kayu 2.0000 HOK 45,000.00 90,000.00
Tukang Batu 1.0000 HOK 45,000.00 45,000.00
Pekerja 2.0000 HOK 35,000.00 70,000.00
Kepala Tukang 0.3000 HOK 50,000.00 15,000.00
Mandor 0.0500 HOK 50,000.00 2,500.00
Total 222,500.00 350,350.00
Total Harga 572,850.00
Keuntungan 85,927.50
Jumlah Total 658,777.50

A-06 1 m2 PEMBUATAN GUDANG SEMEN DAN ALAT-ALAT


Dolken Kayu D 8-10/400 Cm 1.7000 Btg 15,000.00 25,500.00
Kayu 0.2100 m3 1,300,000.00 273,000.00
Paku biasa 0.3000 Kg 11,000.00 3,300.00
Semen Portland 10.5000 Kg 1,090.00 11,445.00
Pasir Beton 0.0300 m3 125,000.00 3,750.00
Koral Beton 0.0500 m3 125,000.00 6,250.00
Seng gelombang BJLS 32 1.5000 Lbr 0.00 0.00
Tukang kayu 2.0000 HOK 45,000.00 90,000.00
Pekerja 1.0000 HOK 35,000.00 35,000.00
Kepala tukang 0.2000 HOK 50,000.00 10,000.00
Mandor 0.0500 HOK 50,000.00 2,500.00
Total 137,500.00 323,245.00
Total Harga 460,745.00
Keuntungan 69,111.75
Jumlah Total 529,856.75
A-07 1 m2 PEMBUATAN RUMAH JAGA / KOSTRUKSI KAYU
Dolken Kayu D 8-10/400 Cm 3.0000 Btg 15,000.00 45,000.00
Kayu 0.2760 m3 1,300,000.00 358,800.00
Paku biasa 0.7000 Kg 11,000.00 7,700.00
Seng gelombang BJLS 32 1.5000 Lbr 0.00 0.00
Tukang kayu 1.5000 HOK 45,000.00 67,500.00
Pekerja 1.0000 HOK 35,000.00 35,000.00
Kepala tukang 0.1500 HOK 50,000.00 7,500.00
Mandor 0.0500 HOK 50,000.00 2,500.00
Total 112,500.00 411,500.00
Total Harga 524,000.00
Keuntungan 78,600.00
Jumlah Total 602,600.00

A-08 1 m2 PEKERJAAN MEMBERSIHKAN LAPANGAN DAN PERATAAN


Pekerja 0.1000 HOK 35,000.00 3,500.00
Mandor 0.0500 HOK 50,000.00 2,500.00
Total 6,000.00
Total Harga 6,000.00
Keuntungan 900.00
a b c d e f=(cxe) g=(cxe) h 5495470000
Jumlah Total 6,900.00

A-09 1 m2 PEMBUATAN BEDENG BURUH


Dolken Kayu D 8-10/400 Cm 1.2500 Btg 15,000.00 18,750.00
Kayu 0.1860 m3 1,300,000.00 241,800.00
Paku biasa 0.3000 Kg 11,000.00 3,300.00
Semen Portland 18.0000 Kg 1,090.00 19,620.00
Pasir Beton 0.0300 m3 125,000.00 3,750.00
Koral Beton 0.0500 m3 125,000.00 6,250.00
Seng gelombang BJLS 32 1.5000 Lbr 0.00 0.00
Plywood 4mm 1.3500 Lbr 63,800.00 86,130.00
Tukang kayu 2.0000 HOK 45,000.00 90,000.00
Pekerja 1.0000 HOK 35,000.00 35,000.00
Kepala tukang 0.2000 HOK 50,000.00 10,000.00
Mandor 0.0500 HOK 50,000.00 2,500.00
Total 137,500.00 379,600.00
Total Harga 517,100.00
Keuntungan 77,565.00
Jumlah Total 594,665.00

A-10 1 m2 PEMBUATAN BAK ADUKAN, UKURAN (40 x 50 x 20) cm


Kayu terentang 0.0360 m3 1,300,000.00 46,800.00
Paku biasa 0.0800 Kg 11,000.00 880.00
Kaso 5/7 1.0000 Btg 17,160.00 17,160.00
Tukang kayu 0.3000 HOK 45,000.00 13,500.00
Mandor 0.0015 HOK 50,000.00 75.00
Total 13,575.00 64,840.00
Total Harga 78,415.00
Keuntungan 11,762.25
Jumlah Total 90,177.25

A-11 1 m2 PEMBUATAN STEGGER DARI BAMBU, UKURAN (40 x 50 x 20) cm


Bambu Ø 6-8/600 cm 1.0000 Btg 0.00 0.00
Tali ijuk 0.2500 Kg 8,400.00 2,100.00
Tukang kayu 0.0170 HOK 45,000.00 765.00
Kepala tukang 0.0020 HOK 50,000.00 100.00
Pekerja 0.2500 HOK 35,000.00 8,750.00
Mandor 0.0130 HOK 50,000.00 650.00
Total 10,265.00 2,100.00
Total Harga 12,365.00
Keuntungan 1,854.75
Jumlah Total 14,219.75

A-12 1 m2 PEMBUATAN JALAN SEMENTARA


Batu belah 15/20 0.1500 m3 80,000.00 12,000.00
Batu Pecah 5/7 0.0900 m3 105,000.00 9,450.00
Pasir pasang 0.0100 m3 85,000.00 850.00
Pekerja 1.0000 HOK 35,000.00 35,000.00
Mandor 0.0500 HOK 50,000.00 2,500.00
Total 37,500.00 22,300.00
Total Harga 59,800.00
Keuntungan 8,970.00
Jumlah Total 68,770.00

A-13 1 m3 BONGKARAN BETON BERTULANG


Pekerja 6.6670 HOK 35,000.00 233,345.00
Mandor 0.3330 HOK 50,000.00 16,650.00
Total 249,995.00
Total Harga 249,995.00
Keuntungan 37,499.25
Jumlah Total 287,494.25

A-14 1 m3 BONGKARAN DINDING TEMBOK BATA MERAH


Pekerja 0.6667 HOK 35,000.00 23,334.50
Mandor 0.0333 HOK 50,000.00 1,665.00
Total 24,999.50
Total Harga 24,999.50
a b c d e f=(cxe) g=(cxe) h 5495470000
Keuntungan 3,749.93
Jumlah Total 28,749.43

A-15 1 M' PASANG PAGAR KAWAT JARING GALVANIS, TINGGI 1M


A-16 1 M' PASANG PAGAR BETON PRACETAK (5X50X213)CM

Dihitung 1 m2 BONGKARAN PLESTERAN DINDING (A144 Kep.Gub)


Pekerja 0.0500 HOK 35,000.00 1,750.00
Mandor 0.0250 HOK 50,000.00 1,250.00
Total 3,000.00
Total Harga 3,000.00
Keuntungan 450.00
Jumlah Total 3,450.00

Dihitung 1 m2 BONGKARAN GENTENG (A146 Kep.Gub)


Pekerja 0.4000 HOK 35,000.00 14,000.00
Mandor 0.1000 HOK 50,000.00 5,000.00
Total 19,000.00
Total Harga 19,000.00
Keuntungan 2,850.00
Jumlah Total 21,850.00

Dihitung 1 m2 BONGKARAN RANGKA ATAP /RENG+KASO (A147)


Pekerja 0.1000 HOK 35,000.00 3,500.00
Tukang kayu 0.0250 HOK 45,000.00 1,125.00
Kepala tukang kayu 0.0025 HOK 50,000.00 125.00
Mandor 0.0050 HOK 50,000.00 250.00
Total 5,000.00
Total Harga 5,000.00
Keuntungan 750.00
Jumlah Total 5,750.00

Dihitung 1 m3 BONGKARAN KUDA-KUDA, GORDING /BALOK (A150)


Pekerja 4.0000 HOK 35,000.00 140,000.00
Tukang kayu 3.0000 HOK 45,000.00 135,000.00
Mandor 0.2000 HOK 50,000.00 10,000.00
Total 285,000.00
Total Harga 285,000.00
Keuntungan 42,750.00
Jumlah Total 327,750.00

Dihitung 1 m2 BONGKARAN PLAFOND (A162)


Pekerja 0.1250 HOK 35,000.00 4,375.00
Mandor 0.0050 HOK 50,000.00 250.00
Total 4,625.00
Total Harga 4,625.00
Keuntungan 693.75
Jumlah Total 5,318.75

B PEKERJAAN TANAH
B-01 1 m3 GALIAN TANAH BIASA SEDALAM 1 METER
Pekerja 0.4000 HOK 35,000.00 14,000.00
Mandor 0.0400 HOK 50,000.00 2,000.00
Total 16,000.00
Total Harga 16,000.00
Keuntungan
Jumlah Total 16,000.00

B-02 1 m3 GALIAN TANAH BIASA SEDALAM 2 METER


Pekerja 0.5260 HOK 35,000.00 18,410.00
Mandor 0.0520 HOK 50,000.00 2,600.00
Total 21,010.00
Total Harga 21,010.00
Keuntungan 3,151.50
Jumlah Total 24,161.50
a b c d e f=(cxe) g=(cxe) h 5495470000
B-03 1 m3 GALIAN TANAH BIASA SEDALAM 3 METER
Pekerja 0.7350 HOK 35,000.00 25,725.00
Mandor 0.0730 HOK 50,000.00 3,650.00
Total 29,375.00
Total Harga 29,375.00
Keuntungan 4,406.25
Jumlah Total 33,781.25

B-04 1 m3 GALIAN TANAH KERAS SEDALAM 1 METER


Pekerja 0.6250 HOK 35,000.00 21,875.00
Mandor 0.0620 HOK 50,000.00 3,100.00
Total 24,975.00
Total Harga 24,975.00
Keuntungan 3,746.25
Jumlah Total 28,721.25

B-05 1 m3 GALIAN TANAH CADAS SEDALAM 1 METER


Pekerja 1.2500 HOK 35,000.00 43,750.00
Mandor 0.1250 HOK 50,000.00 6,250.00
Total 50,000.00
Total Harga 50,000.00
Keuntungan 7,500.00
Jumlah Total 57,500.00

B-06 1 m3 GALIAN TANAH LUMPUR SEDALAM 1 METER


Pekerja 0.8230 HOK 35,000.00 28,805.00
Mandor 0.0830 HOK 50,000.00 4,150.00
Total 32,955.00
Total Harga 32,955.00
Keuntungan 4,943.25
Jumlah Total 37,898.25

B-07 1 m2 PEKERJAAN STRIPPING SETINGGI 1 METER


Pekerja 0.0500 HOK 35,000.00 1,750.00
Mandor 0.0050 HOK 50,000.00 250.00
Total 2,000.00
Total Harga 2,000.00
Keuntungan 300.00
Jumlah Total 2,300.00

B-08 1 m3 PEMBUANGAN TANAH SEJAUH 150 METER


Pekerja 0.5160 HOK 35,000.00 18,060.00
Mandor 0.0500 HOK 50,000.00 2,500.00
Total 20,560.00
Total Harga 20,560.00
Keuntungan
Jumlah Total 20,560.00

B-09 1 m3 URUGAN KEMBALI


Pekerja 0.1920 HOK 35,000.00 6,720.00
Mandor 0.0190 HOK 50,000.00 950.00
Total 7,670.00
Total Harga 7,670.00
Keuntungan
Jumlah Total 7,670.00

B-10 1 m3 PEMADATAN TANAH


Pekerja 0.5000 HOK 35,000.00 17,500.00
Mandor 0.0500 HOK 50,000.00 2,500.00
Total 20,000.00
Total Harga 20,000.00
Keuntungan
Jumlah Total 20,000.00

B-11 1 m3 URUGAN PASIR


Pasir urug 1.2000 m3 45,000.00 54,000.00
Pekerja 0.3000 HOK 35,000.00 10,500.00
a b c d e f=(cxe) g=(cxe) h 5495470000
Mandor 0.0100 HOK 50,000.00 500.00
Total 11,000.00 54,000.00
Total Harga 65,000.00
Keuntungan
Jumlah Total 65,000.00

B-12 1 m3 LAPISAN PUDEL CAMPURAN 1 KP : 3 PS : 7 TL


B-13 1 m3 LAPISAN PUDEL CAMPURAN 1 KP : 5 TL

B-14 1 m3 PEMASANGAN LAPISAN IJUK


Ijuk 1.2000 m3 8,400.00 10,080.00
Pekerja 0.1500 HOK 35,000.00 5,250.00
Mandor 0.0150 HOK 50,000.00 750.00
Total 6,000.00 10,080.00
Total Harga 16,080.00
Keuntungan 2,412.00
Jumlah Total 18,492.00

B-15 1 m3 URUGAN SIRTU


Sirtu 1.2000 m3 75,000.00 90,000.00
Pekerja 0.2500 HOK 35,000.00 8,750.00
Mandor 0.0250 HOK 50,000.00 1,250.00
Total 10,000.00 90,000.00
Total Harga 100,000.00
Keuntungan 15,000.00
Jumlah Total 115,000.00

B-16 1 m2 PEMBUATAN JALAN SEMENTARA TEBAL 25 CM


Batu Belah 0.2750 m3 80,000.00 22,000.00
Kerikil 0.0300 m3 125,000.00 3,750.00
Pasir 0.0500 m3 45,000.00 2,250.00
Pekerja 1.0000 HOK 35,000.00 35,000.00
Mandor 0.1000 HOK 50,000.00 5,000.00
Total 40,000.00 28,000.00
Total Harga 68,000.00
Keuntungan 10,200.00
Jumlah Total 78,200.00
Dihitung 1 m3 URUGAN TANAH
Tanah Urugan 1.2000 m3 45,000.00 54,000.00
Pekerja 0.3000 HOK 35,000.00 10,500.00
Mandor 0.0100 HOK 50,000.00 500.00
Total 11,000.00 54,000.00
Total Harga 65,000.00
Keuntungan 9,750.00
Jumlah Total 74,750.00

C PEKERJAAN PONDASI
C-01 1 m3 PASANGAN PONDASI BATU KALI, 1 Pc : 1 Ps
Batu belah 15/20 cm 1.1000 m3 80,000.00 88,000.00
Semen Portland 392.0000 Kg 1,090.00 427,280.00
Pasir pasang 0.3140 m3 85,000.00 26,690.00
Pekerja 1.5000 HOK 35,000.00 52,500.00
Tukang batu 0.6000 HOK 45,000.00 27,000.00
Kepala tukang 0.0600 HOK 50,000.00 3,000.00
Mandor 0.0750 HOK 50,000.00 3,750.00
Total 86,250.00 541,970.00
Total Harga 628,220.00
Keuntungan 94,233.00
Jumlah Total 722,453.00

C-02 1 m3 PASANGAN PONDASI BATU KALI, 1 Pc : 2 Ps


Batu belah 15/20 cm 1.1000 m3 80,000.00 88,000.00
Semen Portland 267.0000 Kg 1,090.00 291,030.00
Pasir pasang 0.4270 m3 85,000.00 36,295.00
Pekerja 1.5000 HOK 35,000.00 52,500.00
Tukang batu 0.6000 HOK 45,000.00 27,000.00
a b c d e f=(cxe) g=(cxe) h 5495470000
Kepala tukang 0.0600 HOK 50,000.00 3,000.00
Mandor 0.0750 HOK 50,000.00 3,750.00
Total 86,250.00 415,325.00
Total Harga 501,575.00
Keuntungan 75,236.25
Jumlah Total 576,811.25

C-04 1 m3 PASANGAN PONDASI BATU KALI, 1 Pc : 3 Ps


Batu belah 15/20 cm 1.1000 m3 80,000.00 88,000.00
Semen Portland 202.0000 Kg 1,090.00 220,180.00
Pasir pasang 0.4850 m3 85,000.00 41,225.00
Pekerja 1.5000 HOK 35,000.00 52,500.00
Tukang batu 0.6000 HOK 45,000.00 27,000.00
Kepala tukang 0.0600 HOK 50,000.00 3,000.00
Mandor 0.0750 HOK 50,000.00 3,750.00
Total 86,250.00 349,405.00
Total Harga 435,655.00
Keuntungan 65,348.25
Jumlah Total 501,003.25

C-05 1 m3 PASANGAN PONDASI BATU KALI, 1 Pc : 4 Ps


Batu belah 15/20 cm 1.1000 m3 80,000.00 88,000.00
Semen Portland 163.0000 Kg 1,090.00 177,670.00
Pasir pasang 0.5200 m3 85,000.00 44,200.00
Pekerja 1.5000 HOK 35,000.00 52,500.00
Tukang batu 0.6000 HOK 45,000.00 27,000.00
Kepala tukang 0.0600 HOK 50,000.00 3,000.00
Mandor 0.0750 HOK 50,000.00 3,750.00
Total 86,250.00 309,870.00
Total Harga 396,120.00
Keuntungan 59,418.00
Jumlah Total 455,538.00

C-06 1 m3 PASANGAN PONDASI BATU KALI, 1 Pc : 5 Ps


Batu belah 15/20 cm 1.1000 m3 80,000.00 88,000.00
Semen Portland 136.0000 Kg 1,090.00 148,240.00
Pasir pasang 0.5440 m3 85,000.00 46,240.00
Pekerja 1.5000 HOK 35,000.00 52,500.00
Tukang batu 0.6000 HOK 45,000.00 27,000.00
Kepala tukang 0.0600 HOK 50,000.00 3,000.00
Mandor 0.0750 HOK 50,000.00 3,750.00
Total 86,250.00 282,480.00
Total Harga 368,730.00
Keuntungan
Jumlah Total 368,730.00
a b c d e f=(cxe) g=(cxe) h 5495470000

C-07 1 m3 PASANGAN PONDASI BATU KALI, 1 Pc : 6 Ps


Batu belah 15/20 cm 1.1000 m3 80,000.00 88,000.00
Semen Portland 117.0000 Kg 1,090.00 127,530.00
Pasir pasang 0.5610 m3 85,000.00 47,685.00
Pekerja 1.5000 HOK 35,000.00 52,500.00
Tukang batu 0.6000 HOK 45,000.00 27,000.00
Kepala tukang 0.0600 HOK 50,000.00 3,000.00
Mandor 0.0750 HOK 50,000.00 3,750.00
Total 86,250.00 263,215.00
Total Harga 349,465.00
Keuntungan 20,967.90
Jumlah Total 370,432.90

C-08 1 m3 PASANGAN PONDASI BATU KALI, 1 Pc : 8 Ps


Batu belah 15/20 cm 1.1000 m3 80,000.00 88,000.00
Semen Portland 91.0000 Kg 1,090.00 99,190.00
Pasir pasang 0.5610 m3 85,000.00 47,685.00
Pekerja 1.5000 HOK 35,000.00 52,500.00
Tukang batu 0.6000 HOK 45,000.00 27,000.00
Kepala tukang 0.0600 HOK 50,000.00 3,000.00
Mandor 0.0750 HOK 50,000.00 3,750.00
Total 86,250.00 234,875.00
Total Harga 321,125.00
Keuntungan 48,168.75
Jumlah Total 369,293.75

C-09 1 m3 PASANGAN PONDASI BATU KALI, 1 Kp : 1 Sm : 1 Ps


C-10 1 m3 PASANGAN PONDASI BATU KALI, 1 Kp : 1 Sm : 2 Ps
C-11 1 m3 PASANGAN PONDASI BATU KALI, 1 Pc : 1/4 Kp : 4 Ps
C-12 1 m3 PASANGAN PONDASI BATU KALI, 1 Pc : 3 Kp : 10 Ps
C-13 1 m3 PASANGAN PONDASI BATU KALI, 1/4 Pc : 1 Kp : 4 Ps

C-014 1 m3 PASANGAN PONDASI BATU KOSONG


Batu belah 15/20 cm 1.2000 m3 80,000.00 96,000.00
Pasir urug 0.3000 m3 45,000.00 13,500.00
Pekerja 0.7800 HOK 35,000.00 27,300.00
Tukang batu 0.3900 HOK 45,000.00 17,550.00
Kepala tukang 0.0390 HOK 50,000.00 1,950.00
Mandor 0.0390 HOK 50,000.00 1,950.00
Total 48,750.00 109,500.00
Total Harga 158,250.00
Keuntungan 23,737.50
Jumlah Total 181,987.50

C-015 1 m3 PASANGAN PONDASI SIKLOP 40% BATU KALI


Besi beton 75.0000 Kg 8,000.00 600,000.00
Semen Portland 202.0000 Kg 1,090.00 220,180.00
Pasir beton 0.3200 m3 125,000.00 40,000.00
Koral beton 0.4900 m3 125,000.00 61,250.00
Kawat beton 0.8000 Kg 12,000.00 9,600.00
Pekerja 3.0000 HOK 35,000.00 105,000.00
Tukang batu 0.8500 HOK 45,000.00 38,250.00
Kepala tukang 0.0850 HOK 50,000.00 4,250.00
Mandor 0.1500 HOK 50,000.00 7,500.00
Total 155,000.00 931,030.00
Total Harga 1,086,030.00
Keuntungan 162,904.50
Jumlah Total 1,248,934.50

C-016 1 m3 PASANGAN PONDASI SUMURAN DIAMETER 100 cm


Batu belah 15/20 cm 0.4500 m3 80,000.00 36,000.00
Semen Portland 280.0000 Kg 1,090.00 305,200.00
Pasir beton 0.4500 m3 125,000.00 56,250.00
Koral beton 0.6700 m3 125,000.00 83,750.00
Pekerja 2.3800 HOK 35,000.00 83,300.00
Tukang batu 0.3000 HOK 45,000.00 13,500.00
a b c d e f=(cxe) g=(cxe) h 5495470000
Kepala tukang 0.0300 HOK 50,000.00 1,500.00
Mandor 0.0800 HOK 50,000.00 4,000.00
Total 102,300.00 481,200.00
Total Harga 583,500.00
Keuntungan 87,525.00
Jumlah Total 671,025.00

C-017 1 m3 PEMBUATAN TIANG PANCANG BETON BERTULANG ( 40x40 ) cm,


Pasir urug darat 0.0190 m3 45,000.00 855.00
Pasir beton 0.0940 m3 125,000.00 11,750.00
Koral beton 0.1500 m3 125,000.00 18,750.00
Semen Portland 60.5000 Kg 1,090.00 65,945.00
Besi beton 45.0000 Kg 8,000.00 360,000.00
Kawat beton 0.9000 Kg 12,000.00 10,800.00
Kayu kaso 5/7 0.0320 m3 1,300,000.00 41,600.00
Paku 0.1200 Kg 11,000.00 1,320.00
Minyak bekisting 0.0900 Lt 0.00 0.00
Plamir tembok 0.2400 Kg 26,400.00 6,336.00
Pekerja 1.0000 HOK 35,000.00 35,000.00
Tukang batu 0.6700 HOK 45,000.00 30,150.00
Kepala tukang 0.0670 HOK 50,000.00 3,350.00
Mandor 0.0500 HOK 50,000.00 2,500.00
Total 71,000.00 517,356.00
Total Harga 588,356.00
Keuntungan 88,253.40
Jumlah Total 676,609.40

C-018 1 m3 PEMBUATAN TIANG PANCANG BETON BERTULANG ( 35x35 ) cm,


Pasir urug darat 0.0160 m3 45,000.00 720.00
Pasir beton 0.0800 m3 125,000.00 10,000.00
Koral beton 0.1250 m3 125,000.00 15,625.00
Semen Portland 49.0000 Kg 1,090.00 53,410.00
Besi beton 34.5000 Kg 8,000.00 276,000.00
Kawat beton 0.7000 Kg 12,000.00 8,400.00
Kayu kaso 5/7 0.0270 m3 1,300,000.00 35,100.00
Paku 0.1200 Kg 11,000.00 1,320.00
Minyak bekisting 0.0900 Lt 0.00 0.00
Plamuur tembok 0.2000 Kg 26,400.00 5,280.00
Pekerja 0.8000 HOK 35,000.00 28,000.00
Tukang batu 0.5000 HOK 45,000.00 22,500.00
Kepala tukang 0.0500 HOK 50,000.00 2,500.00
Mandor 0.0400 HOK 50,000.00 2,000.00
Total 55,000.00 405,855.00
Total Harga 460,855.00
Keuntungan 69,128.25
Jumlah Total 529,983.25

D PEKERJAAN DINDING
D-01 1 m2 PASANGAN BATA MERAH TEBAL 1 BATA, 1 PC : 1 Ps
Bata merah ( 5x11x22 ) cm 140.0000 Bh 550.00 77,000.00
Semen Portland 64.0300 Kg 1,090.00 69,792.70
Pasir pasang 0.0590 m3 85,000.00 5,015.00
Pekerja 0.6500 HOK 35,000.00 22,750.00
Tukang batu 0.2000 HOK 45,000.00 9,000.00
Kepala tukang 0.0200 HOK 50,000.00 1,000.00
Mandor 0.0300 HOK 50,000.00 1,500.00
Total 34,250.00 151,807.70
Total Harga 186,057.70
Keuntungan 27,908.66
Jumlah Total 213,966.36

D-02 1 m2 PASANGAN BATA MERAH TEBAL 1 BATA, 1 PC : 2 Ps


Bata merah ( 5x11x22 ) cm 140.0000 Bh 550.00 77,000.00
Semen Portland 43.5000 Kg 1,090.00 47,415.00
Pasir pasang 0.0800 m3 85,000.00 6,800.00
Pekerja 0.6500 HOK 35,000.00 22,750.00
a b c d e f=(cxe) g=(cxe) h 5495470000
Tukang batu 0.2000 HOK 45,000.00 9,000.00
Kepala tukang 0.0200 HOK 50,000.00 1,000.00
Mandor 0.0300 HOK 50,000.00 1,500.00
Total 34,250.00 131,215.00
Total Harga 165,465.00
Keuntungan 24,819.75
Jumlah Total 190,284.75

D-03 1 m2 PASANGAN BATA MERAH TEBAL 1 BATA, 1 PC : 3 Ps


Bata merah ( 5x11x22 ) cm 140.0000 Bh 550.00 77,000.00
Semen Portland 32.9500 Kg 1,090.00 35,915.50
Pasir pasang 0.0910 m3 85,000.00 7,735.00
Pekerja 0.6500 HOK 35,000.00 22,750.00
Tukang batu 0.2000 HOK 45,000.00 9,000.00
Kepala tukang 0.0200 HOK 50,000.00 1,000.00
Mandor 0.0300 HOK 50,000.00 1,500.00
Total 34,250.00 120,650.50
Total Harga 154,900.50
Keuntungan 23,235.08
Jumlah Total 178,135.58

D-04 1 m2 PASANGAN BATA MERAH TEBAL 1 BATA, 1 PC : 4 Ps


Bata merah ( 5x11x22 ) cm 140.0000 Bh 550.00 77,000.00
Semen Portland 26.5500 Kg 1,090.00 28,939.50
Pasir pasang 0.0930 m3 85,000.00 7,905.00
Pekerja 0.6500 HOK 35,000.00 22,750.00
Tukang batu 0.2000 HOK 45,000.00 9,000.00
Kepala tukang 0.0200 HOK 50,000.00 1,000.00
Mandor 0.0300 HOK 50,000.00 1,500.00
Total 34,250.00 113,844.50
Total Harga 148,094.50
Keuntungan 22,214.18
Jumlah Total 170,308.68

D-05 1 m2 PASANGAN BATA MERAH TEBAL 1 BATA, 1 PC : 5 Ps


Bata merah ( 5x11x22 ) cm 140.0000 Bh 550.00 77,000.00
Semen Portland 22.2000 Kg 1,090.00 24,198.00
Pasir pasang 0.1020 m3 85,000.00 8,670.00
Pekerja 0.6500 HOK 35,000.00 22,750.00
Tukang batu 0.2000 HOK 45,000.00 9,000.00
Kepala tukang 0.0200 HOK 50,000.00 1,000.00
Mandor 0.0300 HOK 50,000.00 1,500.00
Total 34,250.00 109,868.00
Total Harga 144,118.00
Keuntungan 21,617.70
Jumlah Total 165,735.70

D-06 1 m2 PASANGAN BATA MERAH TEBAL 1 BATA, 1 PC : 6 Ps


D-07 1 m2 PASANGAN BATA MERAH TEBAL 1 BATA, 1 PC : 3 Kp : 10 Ps
D-08 1 m2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 PC : 1 Ps

D-09 1 m2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 PC : 2 Ps


Bata merah ( 5x11x22 ) cm 70.0000 Bh 550.00 38,500.00
Semen Portland 18.9500 Kg 1,090.00 20,655.50
Pasir pasang 0.0380 m3 85,000.00 3,230.00
Pekerja 0.3200 HOK 35,000.00 11,200.00
Tukang batu 0.1000 HOK 45,000.00 4,500.00
Kepala tukang 0.0100 HOK 50,000.00 500.00
Mandor 0.0150 HOK 50,000.00 750.00
Total 16,950.00 62,385.50
Total Harga 79,335.50
Keuntungan 11,900.33
Jumlah Total 91,235.83

D-010 1 m2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 PC : 3 Ps


Bata merah ( 5x11x22 ) cm 70.0000 Bh 550.00 38,500.00
Semen Portland 14.3700 Kg 1,090.00 15,663.30
a b c d e f=(cxe) g=(cxe) h 5495470000
Pasir pasang 0.0400 m3 85,000.00 3,400.00
Pekerja 0.3200 HOK 35,000.00 11,200.00
Tukang batu 0.1000 HOK 45,000.00 4,500.00
Kepala tukang 0.0100 HOK 50,000.00 500.00
Mandor 0.0150 HOK 50,000.00 750.00
Total 16,950.00 57,563.30
Total Harga 74,513.30
Keuntungan 11,177.00
Jumlah Total 85,690.30

D-011 1 m2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 PC : 4 Ps


Bata merah ( 5x11x22 ) cm 70.0000 Bh 550.00 38,500.00
Semen Portland 11.5000 Kg 1,090.00 12,535.00
Pasir pasang 0.0430 m3 85,000.00 3,655.00
Pekerja 0.3200 HOK 35,000.00 11,200.00
Tukang batu 0.1000 HOK 45,000.00 4,500.00
Kepala tukang 0.0100 HOK 50,000.00 500.00
Mandor 0.0150 HOK 50,000.00 750.00
Total 16,950.00 54,690.00
Total Harga 71,640.00
Keuntungan 10,746.00
Jumlah Total 82,386.00
D-012 1 m2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 PC : 5 Ps
Bata merah ( 5x11x22 ) cm 70.0000 Bh 550.00 38,500.00
Semen Portland 9.6800 Kg 1,090.00 10,551.20
Pasir pasang 0.0450 m3 85,000.00 3,825.00
Pekerja 0.3200 HOK 35,000.00 11,200.00
Tukang batu 0.1000 HOK 45,000.00 4,500.00
Kepala tukang 0.0100 HOK 50,000.00 500.00
Mandor 0.0150 HOKK 50,000.00 750.00
Total 16,950.00 52,876.20
Total Harga 69,826.20
Keuntungan
Jumlah Total 69,826.20

D-013 1 m2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 PC : 6 Ps


D-014 1 m2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 PC : 8 Ps
D-015 1 m2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 PC : 3 Kp : 10 Ps
D-016 1 m2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 Kp : 1 Sm : 1 Ps
D-017 1 m2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 Kp : 1 Sm : 2 Ps

D-018 1 m2 PASANGAN DINDING HOKLLOWBLOCK /BATAKO (HB-20)


Hollow block (HB-20) 12.5000 Bh 2,400.00 30,000.00
Semen Portland 13.5000 Kg 1,090.00 14,715.00
Pasir pasang 0.0480 m3 85,000.00 4,080.00
Besi beton polos 1.9500 Kg 8,000.00 15,600.00
Pekerja 0.3500 HOK 35,000.00 12,250.00
Tukang batu 0.1500 HOK 45,000.00 6,750.00
Kepala tukang 0.0150 HOK 50,000.00 750.00
Mandor 0.0170 HOK 50,000.00 850.00
Total 20,600.00 64,395.00
Total Harga 84,995.00
Keuntungan 12,749.25
Jumlah Total 97,744.25

D-019 1 m2 PASANGAN DINDING HOKLLOWBLOCK /BATAKO (HB-15)


Hollow block (HB-15) 12.5000 Bh 2,400.00 30,000.00
Semen Portland 10.4500 Kg 1,090.00 11,390.50
Pasir pasang 0.0380 m3 85,000.00 3,230.00
Besi beton polos 1.9500 Kg 8,000.00 15,600.00
Pekerja 0.3200 HOK 35,000.00 11,200.00
Tukang batu 0.1200 HOK 45,000.00 5,400.00
Kepala tukang 0.0120 HOK 50,000.00 600.00
Mandor 0.0150 HOK 50,000.00 750.00
Total 17,950.00 60,220.50
Total Harga 78,170.50
a b c d e f=(cxe) g=(cxe) h 5495470000
Keuntungan 11,725.58
Jumlah Total 89,896.08

D-020 1 m2 PASANGAN DINDING HOKLLOWBLOCK /BATAKO (HB-10)

D-021 1 m2 PASANGAN DINDING CONBLOCK (CB-20)


Concrete block (CB-20) 12.5000 Bh 0.00 0.00
Semen Portland 14.0500 Kg 1,090.00 15,314.50
Pasir beton 0.0040 m3 125,000.00 500.00
Pasir pasang 0.0420 m3 85,000.00 3,570.00
Besi beton polos 3.8700 Kg 8,000.00 30,960.00
Paku biasa 2"-5" 0.0060 Kg 11,000.00 66.00
Kayu terentang 0.0010 m3 1,300,000.00 1,300.00
Kawat beton 0.0300 Kg 12,000.00 360.00
Koral beton 0.0050 m3 125,000.00 625.00
Pekerja 0.3700 HOK 35,000.00 12,950.00
Tukang batu 0.1570 HOK 45,000.00 7,065.00
Tukang besi 0.0070 HOK 45,000.00 315.00
Kepala tukang 0.0164 HOK 50,000.00 820.00
Mandor 0.0185 HOK 50,000.00 925.00
Total 22,075.00 52,695.50
Total Harga 74,770.50
Keuntungan 11,215.58
Jumlah Total 85,986.08

D-022 1 m2 PASANGAN DINDING CONBLOCK (CB-15)


Concrete block (CB-15) 12.5000 Bh 0.00 0.00
Semen Portland 10.4600 Kg 1,090.00 11,401.40
Pasir beton 0.0030 m3 125,000.00 375.00
Pasir pasang 0.0320 m3 85,000.00 2,720.00
Besi beton polos Ø 8 mm 0.8700 Kg 8,000.00 6,960.00
Paku biasa 2"-5" 0.0040 Kg 11,000.00 44.00
Kayu terentang 0.0010 m3 1,300,000.00 1,300.00
Kawat beton 0.0200 Kg 12,000.00 240.00
Koral beton 0.0040 m3 125,000.00 500.00
Pekerja 0.3400 HOK 35,000.00 11,900.00
Tukang batu 0.1300 HOK 45,000.00 5,850.00
Tukang besi 0.0070 HOK 45,000.00 315.00
Kepala tukang 0.0137 HOK 50,000.00 685.00
Mandor 0.0170 HOK 50,000.00 850.00
Total 19,600.00 23,540.40
Total Harga 43,140.40
Keuntungan 6,471.06
Jumlah Total 49,611.46

D-023 1 m2 PASANGAN DINDING CONBLOCK (CB-10)


Concrete block (CB-10) 12.5000 Bh 0.00 0.00
Semen Portland 7.2000 Kg 1,090.00 7,848.00
Pasir beton 0.0020 m3 125,000.00 250.00
Pasir pasang 0.0210 m3 85,000.00 1,785.00
Besi beton polos 2.5400 Kg 8,000.00 20,320.00
Paku biasa 2"-5" 0.0030 Kg 11,000.00 33.00
Kayu terentang 0.0010 m3 1,300,000.00 1,300.00
Kawat beton 0.0150 Kg 12,000.00 180.00
Koral beton 0.0030 m3 125,000.00 375.00
Pekerja 0.3400 HOK 35,000.00 11,900.00
Tukang batu 0.1070 HOK 45,000.00 4,815.00
Tukang besi 0.0070 HOK 45,000.00 315.00
Kepala tukang 0.0114 HOK 50,000.00 570.00
Mandor 0.0170 HOK 50,000.00 850.00
Total 18,450.00 32,091.00
Total Harga 50,541.00
Keuntungan 7,581.15
Jumlah Total 58,122.15

D-024 1 m2 PASANGAN DINDING LATAI


a b c d e f=(cxe) g=(cxe) h 5495470000
D-025 1 m2 PASANGAN DINDING ROSTER /TERAWANG (12X11X24) cm
Roster /Terawang 36.0000 Bh 0.00 0.00
Semen Portland 12.8000 Kg 1,090.00 13,952.00
Pasir pasang 0.0350 m3 85,000.00 2,975.00
Pekerja 0.3000 HOK 35,000.00 10,500.00
Tukang batu 0.1000 HOK 45,000.00 4,500.00
Kepala tukang 0.0100 HOK 50,000.00 500.00
Mandor 0.0150 HOK 50,000.00 750.00
Total 16,250.00 16,927.00
Total Harga 33,177.00
Keuntungan 4,976.55
Jumlah Total 38,153.55

D-026 1 m2 PASANGAN BATA BERONGGA UKURAN (5X11X24)CM

D-027 1 m2 PASANGAN DINDING ANYAMAN BAMBU, RANGKA KAYU


Bilik bambu 1.5000 m2 12,100.00 18,150.00
Kayu 5/7 0.0140 m3 1,300,000.00 18,200.00
Paku 0.0120 Kg 11,000.00 132.00
List kayu 2/4 0.0030 m3 7,000.00 21.00
Pekerja 0.1000 HOK 35,000.00 3,500.00
Tukang kayu 0.0500 HOK 45,000.00 2,250.00
Kepala tukang 0.0050 HOK 50,000.00 250.00
Mandor 0.0020 HOK 50,000.00 100.00
Total 6,121.00 36,482.00
Total Harga 42,603.00
Keuntungan 6,390.45
Jumlah Total 48,993.45

E PEKERJAAN PLESTERAN
E-01 1 m2 PLESTERAN 1 PC : 1 Ps, TEBAL 15 mm
Semen Portland 12.9200 kg 1,090.00 14,082.80
Pasir pasang 0.0130 m3 85,000.00 1,105.00
Pekerja 0.2000 HOK 35,000.00 7,000.00
Tukang batu 0.1500 HOK 45,000.00 6,750.00
Kepala tukang 0.0150 HOK 50,000.00 750.00
Mandor 0.0100 HOK 50,000.00 500.00
Total 15,000.00 15,187.80
Total Harga 30,187.80
Keuntungan 4,528.17
Jumlah Total 34,715.97

E-02 1 m2 PLESTERAN 1 PC : 2 Ps, TEBAL 15 mm


Semen Portland 8.5200 kg 1,090.00 9,286.80
Pasir pasang 0.0170 m3 85,000.00 1,445.00
Pekerja 0.2000 HOK 35,000.00 7,000.00
Tukang batu 0.1500 HOK 45,000.00 6,750.00
Kepala tukang 0.0150 HOK 50,000.00 750.00
Mandor 0.0100 HOK 50,000.00 500.00
Total 15,000.00 10,731.80
Total Harga 25,731.80
Keuntungan 3,859.77
Jumlah Total 29,591.57

E-03 1 m2 PLESTERAN 1 PC : 3 Ps, TEBAL 15 mm


Semen Portland 6.4800 kg 1,090.00 7,063.20
Pasir pasang 0.0190 m3 85,000.00 1,615.00
Pekerja 0.2000 HOK 35,000.00 7,000.00
Tukang batu 0.1500 HOK 45,000.00 6,750.00
Kepala tukang 0.0150 HOK 50,000.00 750.00
Mandor 0.0100 HOK 50,000.00 500.00
Total 15,000.00 8,678.20
Total Harga 23,678.20
Keuntungan 3,551.73
Jumlah Total 27,229.93
a b c d e f=(cxe) g=(cxe) h 5495470000
E-04 1 m2 PLESTERAN 1 PC : 4 Ps, TEBAL 15 mm
Semen Portland 5.2000 kg 1,090.00 5,668.00
Pasir pasang 0.0200 m3 85,000.00 1,700.00
Pekerja 0.2000 HOK 35,000.00 7,000.00
Tukang batu 0.1500 HOK 45,000.00 6,750.00
Kepala tukang 0.0150 HOK 50,000.00 750.00
Mandor 0.0100 HOK 50,000.00 500.00
Total 15,000.00 7,368.00
Total Harga 22,368.00
Keuntungan 3,355.20
Jumlah Total 25,723.20

E-05 1 m2 PLESTERAN 1 PC : 5 Ps, TEBAL 15 mm


Semen Portland 4.3200 kg 1,090.00 4,708.80
Pasir pasang 0.0220 m3 85,000.00 1,870.00
Pekerja 0.2000 HOK 35,000.00 7,000.00
Tukang batu 0.1500 HOK 45,000.00 6,750.00
Kepala tukang 0.0150 HOK 50,000.00 750.00
Mandor 0.0100 HOK 50,000.00 500.00
Total 15,000.00 6,578.80
Total Harga 21,578.80
Keuntungan
Jumlah Total 21,578.80

E-06 1 m2 PLESTERAN 1 PC : 6 Ps, TEBAL 15 mm


Semen Portland 3.6800 kg 1,090.00 4,011.20
Pasir pasang 0.0230 m3 85,000.00 1,955.00
Pekerja 0.2000 HOK 35,000.00 7,000.00
Tukang batu 0.1500 HOK 45,000.00 6,750.00
Kepala tukang 0.0150 HOK 50,000.00 750.00
Mandor 0.0100 HOK 50,000.00 500.00
Total 15,000.00 5,966.20
Total Harga 20,966.20
Keuntungan 3,144.93
Jumlah Total 24,111.13

E-07 1 m2 PLESTERAN 1 PC : 8 Ps, TEBAL 15 mm


Semen Portland 2.8800 kg 1,090.00 3,139.20
Pasir pasang 0.0240 m3 85,000.00 2,040.00
Pekerja 0.2000 HOK 35,000.00 7,000.00
Tukang batu 0.1500 HOK 45,000.00 6,750.00
Kepala tukang 0.0150 HOK 50,000.00 750.00
Mandor 0.0100 HOK 50,000.00 500.00
Total 15,000.00 5,179.20
Total Harga 20,179.20
Keuntungan 3,026.88
Jumlah Total 23,206.08

E-08 1 m2 PLESTERAN 1 PC : 0.5 Kp : 3 Ps, TEBAL 15 mm


E-09 1 m2 PLESTERAN 1 PC : 3 Kp: 10 Ps, TEBAL 15 mm
E-10 1 m2 PLESTERAN 0.5 PC : 1 Kp: 4 Ps, TEBAL 15 mm
E-11 1 m2 PLESTERAN 1 PC : 1 Kp: 1 Ps, TEBAL 15 mm
E-12 1 m2 PLESTERAN 1 PC : 1 Kp: 2 Ps, TEBAL 15 mm

E-13 1 m2 PLESTERAN 1 PC : 2 Ps, TEBAL 20 mm


Semen Portland 14.2800 kg 1,090.00 15,565.20
Pasir pasang 0.0230 m3 85,000.00 1,955.00
Pekerja 0.2500 HOK 35,000.00 8,750.00
Tukang batu 0.2000 HOK 45,000.00 9,000.00
Kepala tukang 0.0200 HOK 50,000.00 1,000.00
Mandor 0.0125 HOK 50,000.00 625.00
Total 19,375.00 17,520.20
Total Harga 36,895.20
Keuntungan 5,534.28
Jumlah Total 42,429.48

E-14 1 m2 PLESTERAN 1 PC : 3 Ps, TEBAL 20 mm


a b c d e f=(cxe) g=(cxe) h 5495470000
Semen Portland 10.8000 kg 1,090.00 11,772.00
Pasir pasang 0.0260 m3 85,000.00 2,210.00
Pekerja 0.2500 HOK 35,000.00 8,750.00
Tukang batu 0.2000 HOK 45,000.00 9,000.00
Kepala tukang 0.0200 HOK 50,000.00 1,000.00
Mandor 0.0125 HOK 50,000.00 625.00
Total 19,375.00 13,982.00
Total Harga 33,357.00
Keuntungan 5,003.55
Jumlah Total 38,360.55

E-15 1 m2 PLESTERAN 1 PC : 4 Ps, TEBAL 20 mm


Semen Portland 8.6800 kg 1,090.00 9,461.20
Pasir pasang 0.0280 m3 85,000.00 2,380.00
Pekerja 0.2500 HOK 35,000.00 8,750.00
Tukang batu 0.2000 HOK 45,000.00 9,000.00
Kepala tukang 0.0200 HOK 50,000.00 1,000.00
Mandor 0.0125 HOK 50,000.00 625.00
Total 19,375.00 11,841.20
Total Harga 31,216.20
Keuntungan 4,682.43
Jumlah Total 35,898.63

E-16 1 m2 PLESTERAN 1 PC : 5 Ps, TEBAL 20 mm


Semen Portland 7.2900 kg 1,090.00 7,946.10
Pasir pasang 0.0280 m3 85,000.00 2,380.00
Pekerja 0.2500 HOK 35,000.00 8,750.00
Tukang batu 0.2000 HOK 45,000.00 9,000.00
Kepala tukang 0.0200 HOK 50,000.00 1,000.00
Mandor 0.0125 HOK 50,000.00 625.00
Total 19,375.00 10,326.10
Total Harga 29,701.10
Keuntungan 4,455.17
Jumlah Total 34,156.27

E-17 1 m2 PLESTERAN 1 PC : 6 Ps, TEBAL 20 mm


E-18 1 m2 PLESTERAN 1 Kp : 1 Sm : 2 Ps TEBAL 20 mm

E-19 1 m2 PLESTERAN 1 PC : 2 Ps, TEBAL 25 mm


Semen Portland 15.5000 kg 1,090.00 16,895.00
Pasir pasang 0.0130 m3 85,000.00 1,105.00
Pekerja 0.3000 HOK 35,000.00 10,500.00
Tukang batu 0.2000 HOK 45,000.00 9,000.00
Kepala tukang 0.0200 HOK 50,000.00 1,000.00
Mandor 0.0130 HOK 50,000.00 650.00
Total 21,150.00 18,000.00
Total Harga 39,150.00
Keuntungan 5,872.50
Jumlah Total 45,022.50

E-20 1 m2 PLESTERAN 1 PC : 3 Ps, TEBAL 25 mm


Semen Portland 11.7500 kg 1,090.00 12,807.50
Pasir pasang 0.0350 m3 85,000.00 2,975.00
Pekerja 0.3000 HOK 35,000.00 10,500.00
Tukang batu 0.2000 HOK 45,000.00 9,000.00
Kepala tukang 0.0200 HOK 50,000.00 1,000.00
Mandor 0.0130 HOK 50,000.00 650.00
Total 21,150.00 15,782.50
Total Harga 36,932.50
Keuntungan 5,539.88
Jumlah Total 42,472.38

E-21 1 m2 PLESTERAN 1 PC : 4 Ps, TEBAL 25 mm


Semen Portland 9.4800 kg 1,090.00 10,333.20
Pasir pasang 0.0380 m3 85,000.00 3,230.00
Pekerja 0.3000 HOK 35,000.00 10,500.00
Tukang batu 0.2000 HOK 45,000.00 9,000.00
a b c d e f=(cxe) g=(cxe) h 5495470000
Kepala tukang 0.0200 HOK 50,000.00 1,000.00
Mandor 0.0130 HOK 50,000.00 650.00
Total 21,150.00 13,563.20
Total Harga 34,713.20
Keuntungan 5,206.98
Jumlah Total 39,920.18

E-22 1 m2 PLESTERAN 1 PC : 5 Ps, TEBAL 25 mm


Semen Portland 7.9400 kg 1,090.00 8,654.60
Pasir pasang 0.0390 m3 85,000.00 3,315.00
Pekerja 0.3000 HOK 35,000.00 10,500.00
Tukang batu 0.2000 HOK 45,000.00 9,000.00
Kepala tukang 0.0200 HOK 50,000.00 1,000.00
Mandor 0.0130 HOK 50,000.00 650.00
Total 21,150.00 11,969.60
Total Harga 33,119.60
Keuntungan 4,967.94
Jumlah Total 38,087.54

E-23 1 m2 PLESTERAN 1 PC : 2 Ps, TEBAL 30 mm


Semen Portland 18.6500 kg 1,090.00 20,328.50
Pasir pasang 0.0350 m3 85,000.00 2,975.00
Pekerja 0.3200 HOK 35,000.00 11,200.00
Tukang batu 0.2500 HOK 45,000.00 11,250.00
Kepala tukang 0.0250 HOK 50,000.00 1,250.00
Mandor 0.0150 HOK 50,000.00 750.00
Total 24,450.00 23,303.50
Total Harga 47,753.50
Keuntungan 7,163.03
Jumlah Total 54,916.53

E-24 1 m2 PLESTERAN 1 PC : 3 Ps, TEBAL 30 mm


Semen Portland 14.1500 kg 1,090.00 15,423.50
Pasir pasang 0.0390 m3 85,000.00 3,315.00
Pekerja 0.3200 HOK 35,000.00 11,200.00
Tukang batu 0.2500 HOK 45,000.00 11,250.00
Kepala tukang 0.0250 HOK 50,000.00 1,250.00
Mandor 0.0150 HOK 50,000.00 750.00
Total 24,450.00 18,738.50
Total Harga 43,188.50
Keuntungan 6,478.28
Jumlah Total 49,666.78

E-25 1 m2 PLESTERAN 1 PC : 4 Ps, TEBAL 30 mm


Semen Portland 11.3800 kg 1,090.00 12,404.20
Pasir pasang 0.0420 m3 85,000.00 3,570.00
Pekerja 0.3200 HOK 35,000.00 11,200.00
Tukang batu 0.2500 HOK 45,000.00 11,250.00
Kepala tukang 0.0250 HOK 50,000.00 1,250.00
Mandor 0.0150 HOK 50,000.00 750.00
Total 24,450.00 15,974.20
Total Harga 40,424.20
Keuntungan 6,063.63
Jumlah Total 46,487.83

E-26 1 m2 PLESTERAN 1 PC : 5 Ps, TEBAL 30 mm


Semen Portland 8.1900 kg 1,090.00 8,927.10
Pasir pasang 0.0450 m3 85,000.00 3,825.00
Pekerja 0.3200 HOK 35,000.00 11,200.00
Tukang batu 0.2500 HOK 45,000.00 11,250.00
Kepala tukang 0.0250 HOK 50,000.00 1,250.00
Mandor 0.0150 HOK 50,000.00 750.00
Total 24,450.00 12,752.10
Total Harga 37,202.10
Keuntungan 5,580.32
Jumlah Total 42,782.42
a b c d e f=(cxe) g=(cxe) h 5495470000
E-27 1 m2 BERAPEN 1 PC : 3 Ps, TEBAL 30 mm
E-28 1 m2 BERAPEN 1 PC : 5 Ps, TEBAL 15 mm

E-29 1 m2 PLESTERAN BETON 1 PC : 2 Ps, TEBAL 15 mm


Semen Portland 9.3000 kg 1,090.00 10,137.00
Pasir pasang 0.0180 m3 85,000.00 1,530.00
Pekerja 0.2600 HOK 35,000.00 9,100.00
Tukang batu 0.2000 HOK 45,000.00 9,000.00
Kepala tukang 0.0200 HOK 50,000.00 1,000.00
Mandor 0.0130 HOK 50,000.00 650.00
Total 19,750.00 11,667.00
Total Harga 31,417.00
Keuntungan 4,712.55
Jumlah Total 36,129.55

E-30 1 m2 PLESTERAN BETON 1 PC : 3 Ps, TEBAL 15 mm


Semen Portland 7.0700 kg 1,090.00 7,706.30
Pasir pasang 0.0210 m3 85,000.00 1,785.00
Pekerja 0.2600 HOK 35,000.00 9,100.00
Tukang batu 0.2000 HOK 45,000.00 9,000.00
Kepala tukang 0.0200 HOK 50,000.00 1,000.00
Mandor 0.0130 HOK 50,000.00 650.00
Total 19,750.00 9,491.30
Total Harga 29,241.30
Keuntungan 4,386.20
Jumlah Total 33,627.50

E-31 1 m2 PLESTERAN SKONING 1 PC : 2 Ps


Semen Portland 0.5000 kg 1,090.00 545.00
Pasir pasang 0.0020 m3 85,000.00 170.00
Pekerja 0.0570 HOK 35,000.00 1,995.00
Tukang batu 0.0380 HOK 45,000.00 1,710.00
Kepala tukang 0.0380 HOK 50,000.00 1,900.00
Mandor 0.0200 HOK 50,000.00 1,000.00
Total 6,605.00 715.00
Total Harga 7,320.00
Keuntungan 1,098.00
Jumlah Total 8,418.00

E-32 1 m2 PLESTERAN GRANITO, 1 PC WARNA : 2 GRANITO, TEBAL 10 MM


Semen Warna 0.1440 kg 1,090.00 156.96
Batu Granito 15.0000 kg 85,000.00 1,275,000.00
Pekerja 0.0500 HOK 35,000.00 1,750.00
Tukang batu 0.0200 HOK 45,000.00 900.00
Kepala tukang 0.0020 HOK 50,000.00 100.00
Mandor 0.0050 HOK 50,000.00 250.00
Total 3,000.00 1,275,156.96
Total Harga 1,278,156.96
Keuntungan 191,723.54
Jumlah Total 1,469,880.50

E-33 1 m2 PLESTERAN TERASO, 1 PC WARNA : 2 BATU TERASO, TEBAL 10 MM


Semen Warna 0.4400 kg 1,090.00 479.60
Batu Teraso 11.5000 kg 85,000.00 977,500.00
Pekerja 0.4500 HOK 35,000.00 15,750.00
Tukang batu 0.2000 HOK 45,000.00 9,000.00
Kepala tukang 0.0200 HOK 50,000.00 1,000.00
Mandor 0.0250 HOK 50,000.00 1,250.00
Total 27,000.00 977,979.60
Total Harga 1,004,979.60
Keuntungan 150,746.94
Jumlah Total 1,155,726.54

E-34 1 m2 PLESTERAN CIPRAT 1 PC : 2 Ps


Semen Portland 4.3200 kg 1,090.00 4,708.80
Pasir pasang 0.0160 m3 85,000.00 1,360.00
Pekerja 0.2500 HOK 35,000.00 8,750.00
a b c d e f=(cxe) g=(cxe) h 5495470000
Tukang batu 0.1000 HOK 45,000.00 4,500.00
Kepala tukang 0.0100 HOK 50,000.00 500.00
Mandor 0.0150 HOK 50,000.00 750.00
Total 14,500.00 6,068.80
Total Harga 20,568.80
Keuntungan 3,085.32
Jumlah Total 23,654.12

E-35 1 m2 PLESTERAN SIAR ADUKAN 1 PC : 2 Ps


Semen Portland 4.3200 kg 1,090.00 4,708.80
Pasir pasang 0.0160 m3 85,000.00 1,360.00
Pekerja 0.1500 HOK 35,000.00 5,250.00
Tukang batu 0.0700 HOK 45,000.00 3,150.00
Kepala tukang 0.0070 HOK 50,000.00 350.00
Mandor 0.0080 HOK 50,000.00 400.00
Total 9,150.00 6,068.80
Total Harga 15,218.80
Keuntungan 2,282.82
Jumlah Total 17,501.62

E-36 1 m2 PLESTERAN WATERPROOF BATACOTE 3 LAPIS

DIHITUNG 1 m2 ACIAN PLESTERAN (A077)


Semen PC (50 kg) 0.0800 Zak 54,500.00 4,360.00
Pekerja 0.1430 HOK 35,000.00 5,005.00
Tukang batu 0.1070 HOK 45,000.00 4,815.00
Kepala tukang 0.0105 HOK 50,000.00 525.00
Mandor 0.0100 HOK 50,000.00 500.00
Total 10,845.00 4,360.00
Total Harga 15,205.00
Keuntungan
Jumlah Total 15,205.00

F PEKERJAAN KAYU
F-01 1 m3 PASANG KUSEN PINTU DAN JENDELA KAYU JATI
Kayu jati, balok 1.1000 m3 5,692,500.00 6,261,750.00
Pekerja 6.0000 HOK 35,000.00 210,000.00
Tukang kayu 20.0000 HOK 45,000.00 900,000.00
Kepala tukang 2.0000 HOK 50,000.00 100,000.00
Mandor 0.3000 HOK 50,000.00 15,000.00
Total 1,225,000.00 6,261,750.00
Total Harga 7,486,750.00
Keuntungan 1,123,012.50
Jumlah Total 8,609,762.50

F-02 1 m3 PASANG KUSEN PINTU DAN JENDELA KAYU KAMPER


Kayu kamper, balok 1.2000 m3 10,246,500.00 12,295,800.00
Pekerja 6.0000 HOK 35,000.00 210,000.00
Tukang kayu 18.0000 HOK 45,000.00 810,000.00
Kepala tukang 2.0000 HOK 50,000.00 100,000.00
Mandor 0.3000 HOK 50,000.00 15,000.00
Total 1,135,000.00 12,295,800.00
Total Harga 13,430,800.00
Keuntungan 2,014,620.00
Jumlah Total 15,445,420.00

F-03 1 m3 PASANG KUSEN PINTU DAN JENDELA KAYU BORNEO


Kayu Borneo, balok 1.2000 m3 5,313,000.00 6,375,600.00
Pekerja 6.0000 HOK 35,000.00 210,000.00
Tukang kayu 18.0000 HOK 45,000.00 810,000.00
Kepala tukang 2.0000 HOK 50,000.00 100,000.00
Mandor 0.3000 HOK 50,000.00 15,000.00
Total 1,135,000.00 6,375,600.00
Total Harga 7,510,600.00
Keuntungan 1,126,590.00
Jumlah Total 8,637,190.00
a b c d e f=(cxe) g=(cxe) h 5495470000

F-04 1 m3 PASANG KUSEN PINTU DAN JENDELA KAYU DAMAR LAUT


Kayu Borneo damar laut, balok 1.2000 m3 5,313,000.00 6,375,600.00
Pekerja 6.0000 HOK 35,000.00 210,000.00
Tukang kayu 18.0000 HOK 45,000.00 810,000.00
Kepala tukang 2.0000 HOK 50,000.00 100,000.00
Mandor 0.3000 HOK 50,000.00 15,000.00
Total 1,135,000.00 6,375,600.00
Total Harga 7,510,600.00
Keuntungan 1,126,590.00
Jumlah Total 8,637,190.00

F-05 1 m2 PASANG PINTU KLAMP KAYU KAMPER


Kayu kamper, papan 0.0360 m3 10,626,000.00 382,536.00
Paku biasa 2"-5" 0.0500 Kg 11,000.00 550.00
Pekerja 0.3500 HOK 35,000.00 12,250.00
Tukang kayu 1.0500 HOK 45,000.00 47,250.00
Kepala tukang 0.1050 HOK 50,000.00 5,250.00
Mandor 0.0180 HOK 50,000.00 900.00
Total 65,650.00 383,086.00
Total Harga 448,736.00
Keuntungan 67,310.40
Jumlah Total 516,046.40

F-06 1 m2 PASANG PINTU KLAMP KAYU BORNEO


Kayu Borneo, papan 0.0360 m3 5,217,300.00 187,822.80
Paku biasa 2"-5" 0.0500 Kg 11,000.00 550.00
Pekerja 0.3500 HOK 35,000.00 12,250.00
Tukang kayu 1.0500 HOK 45,000.00 47,250.00
Kepala tukang 0.1050 HOK 50,000.00 5,250.00
Mandor 0.0180 HOK 50,000.00 900.00
Total 65,650.00 188,372.80
Total Harga 254,022.80
Keuntungan 38,103.42
Jumlah Total 292,126.22

F-07 1 m2 PASANG PINTU PANEL KAYU JATI


Kayu jati, papan 0.0400 m3 5,692,500.00 227,700.00
Pekerja 1.0000 HOK 35,000.00 35,000.00
Tukang kayu 2.5000 HOK 45,000.00 112,500.00
Kepala tukang 0.2500 HOK 50,000.00 12,500.00
Mandor 0.0500 HOK 50,000.00 2,500.00
Total 162,500.00 227,700.00
Total Harga 390,200.00
Keuntungan 58,530.00
Jumlah Total 448,730.00
Dihitung 1 m2 PASANG PINTU PANEL KAYU GUNUNG KELAS II
Kayu KELAS II, papan 0.0400 m3 2,200,000.00 88,000.00
Pekerja 1.0000 HOK 35,000.00 35,000.00
Tukang kayu 2.5000 HOK 45,000.00 112,500.00
Kepala tukang 0.2500 HOK 50,000.00 12,500.00
Mandor 0.0500 HOK 50,000.00 2,500.00
Total 162,500.00 88,000.00
Total Harga 250,500.00
Keuntungan
Jumlah Total 250,500.00

F-08 1 m2 PASANG PINTU PANEL KAYU KAMPER


Kayu kamper, papan 0.0400 m3 10,626,000.00 425,040.00
Pekerja 1.0000 HOK 35,000.00 35,000.00
Tukang kayu 2.5000 HOK 45,000.00 112,500.00
Kepala tukang 0.2500 HOK 50,000.00 12,500.00
Mandor 0.0500 HOK 50,000.00 2,500.00
Total 162,500.00 425,040.00
Total Harga 587,540.00
Keuntungan 88,131.00
Jumlah Total 675,671.00
a b c d e f=(cxe) g=(cxe) h 5495470000

F-09 1 m2 PASANG PINTU DAN JENDELA KACA KAYU JATI (TANPA KACA)
Kayu jati, papan 0.0350 m3 5,692,500.00 199,237.50
Pekerja 0.8000 HOK 35,000.00 28,000.00
Tukang kayu 2.0000 HOK 45,000.00 90,000.00
Kepala tukang 0.2000 HOK 50,000.00 10,000.00
Mandor 0.0400 HOK 50,000.00 2,000.00
Total 130,000.00 199,237.50
Total Harga 329,237.50
Keuntungan 49,385.63
Jumlah Total 378,623.13

F-10 1 m2 PASANG PINTU DAN JENDELA KACA KAYU KAMPER (TANPA KACA)
Kayu kamper, papan 0.0350 m3 10,626,000.00 371,910.00
Pekerja 0.8000 HOK 35,000.00 28,000.00
Tukang kayu 2.0000 HOK 45,000.00 90,000.00
Kepala tukang 0.2000 HOK 50,000.00 10,000.00
Mandor 0.0400 HOK 50,000.00 2,000.00
Total 130,000.00 371,910.00
Total Harga 501,910.00
Keuntungan 75,286.50
Jumlah Total 577,196.50

F-11 1 m2 PASANG PINTU DAN JENDELA KACA KAYU BORNEO (TANPA KACA)
Kayu Borneo, papan 0.0350 m3 5,217,300.00 182,605.50
Pekerja 0.8000 HOK 35,000.00 28,000.00
Tukang kayu 2.0000 HOK 45,000.00 90,000.00
Kepala tukang 0.2000 HOK 50,000.00 10,000.00
Mandor 0.0400 HOK 50,000.00 2,000.00
Total 130,000.00 182,605.50
Total Harga 312,605.50
Keuntungan 46,890.83
Jumlah Total 359,496.33

DIHITUNG 1 m2 PASANG PINTU DAN JENDELA KACA KAYU KELAS II (TANPA KACA)
Kayu KELAS ii, papan 0.0350 m3 2,200,000.00 77,000.00
Pekerja 0.8000 HOK 35,000.00 28,000.00
Tukang kayu 2.0000 HOK 45,000.00 90,000.00
Kepala tukang 0.2000 HOK 50,000.00 10,000.00
Mandor 0.0400 HOK 50,000.00 2,000.00
Total 130,000.00 77,000.00
Total Harga 207,000.00
Keuntungan
Jumlah Total 207,000.00
F-12 1 m2 PASANG PINTU DAN JENDELA JALUSI KAYU JATI
Kayu jati, papan 0.0640 m3 5,692,500.00 364,320.00
Pekerja 1.0000 HOK 35,000.00 35,000.00
Tukang kayu 3.0000 HOK 45,000.00 135,000.00
Kepala tukang 0.3000 HOK 50,000.00 15,000.00
Mandor 0.3000 HOK 50,000.00 15,000.00
Total 200,000.00 364,320.00
Total Harga 564,320.00
Keuntungan 84,648.00
Jumlah Total 648,968.00

F-13 1 m2 PASANG PINTU DAN JENDELA JALUSI KAYU KAMPER


Kayu kamper, papan 0.0640 m3 10,626,000.00 680,064.00
Pekerja 1.0000 HOK 35,000.00 35,000.00
Tukang kayu 3.0000 HOK 45,000.00 135,000.00
Kepala tukang 0.3000 HOK 50,000.00 15,000.00
Mandor 0.5000 HOK 50,000.00 25,000.00
Total 210,000.00 680,064.00
Total Harga 890,064.00
Keuntungan 133,509.60
Jumlah Total 1,023,573.60

F-14 1 m2 PASANG PINTU PLYWOOD RANGKAP, RANGKA KAYU JATI


a b c d e f=(cxe) g=(cxe) h 5495470000
Kayu jati, papan 0.0196 m3 5,692,500.00 111,573.00
Paku biasa 1/2"-1" 0.0300 Kg 11,000.00 330.00
Lem kayu 0.3000 Lt 0.00 0.00
Plywood 4'x3'x4 mm 1.0000 Lbr 63,800.00 63,800.00
Pekerja 0.6000 HOK 35,000.00 21,000.00
Tukang kayu 2.0000 HOK 45,000.00 90,000.00
Kepala tukang 0.2000 HOK 50,000.00 10,000.00
Mandor 0.0300 HOK 50,000.00 1,500.00
Total 122,500.00 175,703.00
Total Harga 298,203.00
Keuntungan 44,730.45
Jumlah Total 342,933.45

F-15 1 m2 PASANG PINTU PLYWOOD RANGKAP, RANGKA KAYU KAMPER


Kayu kamper, papan 0.0196 m3 10,626,000.00 208,269.60
Paku biasa 1/2"-1" 0.0300 Kg 11,000.00 330.00
Lem kayu 0.3000 Lt 0.00 0.00
Plywood 4'x3'x4 mm 1.0000 Lbr 63,800.00 63,800.00
Pekerja 0.6000 HOK 35,000.00 21,000.00
Tukang kayu 2.0000 HOK 45,000.00 90,000.00
Kepala tukang 0.2000 HOK 50,000.00 10,000.00
Mandor 0.0300 HOK 50,000.00 1,500.00
Total 122,500.00 272,399.60
Total Harga 394,899.60
Keuntungan 59,234.94
Jumlah Total 454,134.54

DHT 1 m2 PASANG PINTU DAN JENDELA KACA KAYU GUNUNG KLAS II (TANPA KACA)
Kayu Lokal Kls II, papan 0.0350 m3 2,200,000.00 77,000.00
Pekerja 0.8000 HOK 35,000.00 28,000.00
Tukang kayu 2.0000 HOK 45,000.00 90,000.00
Kepala tukang 0.2000 HOK 50,000.00 10,000.00
Mandor 0.0400 HOK 50,000.00 2,000.00
Total 130,000.00 77,000.00
Total Harga 207,000.00
Keuntungan 31,050.00
Jumlah Total 238,050.00
F-16 1 m2 PASANG JALUSI MATI KUSEN KAYU JATI
Kayu jati, papan 0.0600 m3 5,692,500.00 341,550.00
Paku biasa 1/2"-1" 0.1500 Kg 11,000.00 1,650.00
Pekerja 0.5000 HOK 35,000.00 17,500.00
Tukang kayu 2.0000 HOK 45,000.00 90,000.00
Kepala tukang 0.2000 HOK 50,000.00 10,000.00
Mandor 0.0250 HOK 50,000.00 1,250.00
Total 118,750.00 343,200.00
Total Harga 461,950.00
Keuntungan 69,292.50
Jumlah Total 531,242.50

F-17 1 m2 PASANG JELUSI MATI KUSEN KAYU KAMPER


Kayu kamper, papan 0.0600 m3 10,626,000.00 637,560.00
Paku biasa 1/2"-1" 0.1500 Kg 11,000.00 1,650.00
Pekerja 0.5000 HOK 35,000.00 17,500.00
Tukang kayu 2.0000 HOK 45,000.00 90,000.00
Kepala tukang 0.2000 HOK 50,000.00 10,000.00
Mandor 0.0250 HOK 50,000.00 1,250.00
Total 118,750.00 639,210.00
Total Harga 757,960.00
Keuntungan 113,694.00
Jumlah Total 871,654.00

F-18 1 m2 PASANG PINTU PLYWOOD RANGKAP, RANGKA KAYU BORNEO


Kayu Borneo, papan 0.0196 m3 5,217,300.00 102,259.08
Paku biasa 1/2"-1" 0.0300 Kg 11,000.00 330.00
Lem kayu 0.3000 Lt 0.00 0.00
Plywood 4'x3'x4 mm 1.0000 Lbr 63,800.00 63,800.00
Pekerja 0.6000 HOK 35,000.00 21,000.00
a b c d e f=(cxe) g=(cxe) h 5495470000
Tukang kayu 2.0000 HOK 45,000.00 90,000.00
Kepala tukang 0.2000 HOK 50,000.00 10,000.00
Mandor 0.0300 HOK 50,000.00 1,500.00
Total ` 122,500.00 166,389.08
Total Harga 288,889.08
Keuntungan 43,333.36
Jumlah Total 332,222.44

F-19 1 m2 PASANG PINTU DOUBLE-TEAKWOOD, RANGKA KAYU JATI


Kayu jati, papan 0.0196 m3 5,692,500.00 111,573.00
Paku biasa 1/2"-1" 0.3000 Kg 11,000.00 3,300.00
Lem kayu 0.3000 Lt 0.00 0.00
Teakwood 4'x8'x4 mm 1.0000 Lbr 63,800.00 63,800.00
Pekerja 0.6000 HOK 35,000.00 21,000.00
Tukang kayu 2.0000 HOK 45,000.00 90,000.00
Kepala tukang 0.2000 HOK 50,000.00 10,000.00
Mandor 0.0300 HOK 50,000.00 1,500.00
Total 122,500.00 178,673.00
Total Harga 301,173.00
Keuntungan 45,175.95
Jumlah Total 346,348.95

F-20 1 m2 PASANG PINTU DOUBLE-TEAKWOOD, RANGKA KAYU KAMPER


Kayu kamper, papan 0.0196 m3 10,626,000.00 208,269.60
Paku biasa 1/2"-1" 0.3000 Kg 11,000.00 3,300.00
Lem kayu 0.3000 Lt 0.00 0.00
Teakwood 4'x8'x4 mm 1.0000 Lbr 63,800.00 63,800.00
Pekerja 0.6000 HOK 35,000.00 21,000.00
Tukang kayu 2.0000 HOK 45,000.00 90,000.00
Kepala tukang 0.2000 HOK 50,000.00 10,000.00
Mandor 0.0300 HOK 50,000.00 1,500.00
Total 122,500.00 275,369.60
Total Harga 397,869.60
Keuntungan 59,680.44
Jumlah Total 457,550.04

F-21 1 m2 PASANG PINTU PLYWOOD DAN FORMIKA, RANGKA KAYU JATI


Kayu jati, papan 0.0196 m3 5,692,500.00 111,573.00
Paku biasa 1/2"-1" 0.3000 Kg 11,000.00 3,300.00
Lem kayu 0.8000 Lt 0.00 0.00
Plywood 4'x8'x4 mm 1.0000 Lbr 63,800.00 63,800.00
Formika 0.5000 Lbr 94,600.00 47,300.00
Pekerja 0.8000 HOK 35,000.00 28,000.00
Tukang kayu 2.5000 HOK 45,000.00 112,500.00
Kepala tukang 0.2500 HOK 50,000.00 12,500.00
Mandor 0.0400 HOK 50,000.00 2,000.00
Total 155,000.00 225,973.00
Total Harga 380,973.00
Keuntungan 57,145.95
Jumlah Total 438,118.95

F-22 1 m2 PASANG PINTU PLYWOOD DAN FORMIKA, RANGKA KAYU KAMPER


Kayu kamper, papan 0.0196 m3 10,626,000.00 208,269.60
Paku biasa 1/2"-1" 0.3000 Kg 11,000.00 3,300.00
Lem kayu 0.8000 Lt 0.00 0.00
Plywood 4'x8'x4 mm 1.0000 Lbr 63,800.00 63,800.00
Formika 4'x3' 0.5000 Lbr 94,600.00 47,300.00
Pekerja 0.8000 HOK 35,000.00 28,000.00
Tukang kayu 2.5000 HOK 45,000.00 112,500.00
Kepala tukang 0.2500 HOK 50,000.00 12,500.00
Mandor 0.0400 HOK 50,000.00 2,000.00
Total 155,000.00 322,669.60
Total Harga 477,669.60
Keuntungan 71,650.44
Jumlah Total 549,320.04

F-23 1 m2 PASANG PINTU TEAKWOOD DAN FORMIKA, RANGKA KAYU JATI


a b c d e f=(cxe) g=(cxe) h 5495470000
Kayu jati, papan 0.0196 m3 5,692,500.00 111,573.00
Paku biasa 1/2"-1" 0.3000 Kg 11,000.00 3,300.00
Lem kayu 0.8000 Lt 0.00 0.00
Teakwood 4'x8'x4 mm 0.5000 Lbr 63,800.00 31,900.00
Formika 4'x8' 0.5000 Lbr 94,600.00 47,300.00
Pekerja 0.8000 HOK 35,000.00 28,000.00
Tukang kayu 2.5000 HOK 45,000.00 112,500.00
Kepala tukang 0.2500 HOK 50,000.00 12,500.00
Mandor 0.0400 HOK 50,000.00 2,000.00
Total 155,000.00 194,073.00
Total Harga 349,073.00
Keuntungan 52,360.95
Jumlah Total 401,433.95

F-24 1 m2 PASANG PINTU TEAKWOOD DAN FORMIKA, RANGKA KAYU KAMPER


Kayu kamper, papan 0.0196 m3 10,626,000.00 208,269.60
Paku biasa 1/2"-1" 0.3000 Kg 11,000.00 3,300.00
Lem kayu 0.8000 Lt 0.00 0.00
Teakwood 4'x8'x4 mm 0.5000 Lbr 63,800.00 31,900.00
Formika 4'x8' 0.5000 Lbr 94,600.00 47,300.00
Pekerja 0.8000 HOK 35,000.00 28,000.00
Tukang kayu 2.5000 HOK 45,000.00 112,500.00
Kepala tukang 0.2500 HOK 50,000.00 12,500.00
Mandor 0.0400 HOK 50,000.00 2,000.00
Total 155,000.00 290,769.60
Total Harga 445,769.60
Keuntungan 66,865.44
Jumlah Total 512,635.04

F-25 1 m2 PASANG PINTU FORMIKA RANGKAP, RANGKA KAYU JATI


Kayu Jati, papan 0.0196 m3 5,692,500.00 111,573.00
Paku biasa 1/2"-1" 0.3000 Kg 11,000.00 3,300.00
Lem kayu 1.2000 Lt 0.00 0.00
Plywood 4'x8'x4 mm 1.0000 Lbr 63,800.00 63,800.00
Formika 4'x8' 1.0000 Lbr 94,600.00 94,600.00
Pekerja 1.0000 HOK 35,000.00 35,000.00
Tukang kayu 2.6000 HOK 45,000.00 117,000.00
Kepala tukang 0.2600 HOK 50,000.00 13,000.00
Mandor 0.0500 HOK 50,000.00 2,500.00
Total 167,500.00 273,273.00
Total Harga 440,773.00
Keuntungan 66,115.95
Jumlah Total 506,888.95

F-26 1 m2 PASANG PINTU FORMIKA RANGKAP, RANGKA KAYU KAMPER


Kayu Kamper, papan 0.0196 m3 10,626,000.00 208,269.60
Paku biasa 1/2"-1" 0.3000 Kg 11,000.00 3,300.00
Lem kayu 1.2000 Lt 0.00 0.00
Plywood 4'x8'x4 mm 1.0000 Lbr 63,800.00 63,800.00
Formika 4'x8' 1.0000 Lbr 94,600.00 94,600.00
Pekerja 1.0000 HOK 35,000.00 35,000.00
Tukang kayu 2.6000 HOK 45,000.00 117,000.00
Kepala tukang 0.2600 HOK 50,000.00 13,000.00
Mandor 0.0500 HOK 50,000.00 2,500.00
Total 167,500.00 369,969.60
Total Harga 537,469.60
Keuntungan 80,620.44
Jumlah Total 618,090.04

F-27 1 m3 PASANG KONSTRUKSI KUDA-KUDA KAYU JATI


F-28 1 m3 PASANG KONSTRUKSI KUDA-KUDA KAYU KAMPER
Kayu kamper, balok 1.1000 m3 10,246,500.00 11,271,150.00
Besi strip 15.0000 Kg 11,000.00 165,000.00
Paku biasa 2"-5" 0.8000 Kg 11,000.00 8,800.00
Pekerja 4.0000 HOK 35,000.00 140,000.00
Tukang kayu 12.0000 HOK 45,000.00 540,000.00
Kepala tukang 1.2000 HOK 50,000.00 60,000.00
a b c d e f=(cxe) g=(cxe) h 5495470000
Mandor 0.2000 HOK 50,000.00 10,000.00
Total 750,000.00 11,444,950.00
Total Harga 12,194,950.00
Keuntungan 1,829,242.50
Jumlah Total 14,024,192.50

F-29 1 m3 PASANG KONSTRUKSI KUDA-KUDA KAYU BORNEO


Kayu borneo, balok 1.1000 m3 5,313,000.00 5,844,300.00
Besi strip 15.0000 Kg 11,000.00 165,000.00
Paku biasa 2"-5" 0.8000 Kg 11,000.00 8,800.00
Pekerja 4.0000 HOK 35,000.00 140,000.00
Tukang kayu 12.0000 HOK 45,000.00 540,000.00
Kepala tukang 1.2000 HOK 50,000.00 60,000.00
Mandor 0.2000 HOK 50,000.00 10,000.00
Total 750,000.00 6,018,100.00
Total Harga 6,768,100.00
Keuntungan 1,015,215.00
Jumlah Total 7,783,315.00

F-30 1 m3 PASANG KONSTRUKSI KUDA-KUDA KAYU KRUING


Kayu kruing, balok 1.1000 m3 9,867,000.00 10,853,700.00
Besi strip 15.0000 Kg 11,000.00 165,000.00
Paku biasa 2"-5" 0.8000 Kg 11,000.00 8,800.00
Pekerja 4.0000 HOK 35,000.00 140,000.00
Tukang kayu 12.0000 HOK 45,000.00 540,000.00
Kepala tukang 1.2000 HOK 50,000.00 60,000.00
Mandor 0.2000 HOK 50,000.00 10,000.00
Total 750,000.00 11,027,500.00
Total Harga 11,777,500.00
Keuntungan 1,766,625.00
Jumlah Total 13,544,125.00

F-31 1 m2 PASANG KASO + RENG GENTENG KODOK KAYU KAMPER


Kayu kamper, balok 0.0120 m3 10,246,500.00 122,958.00
Paku biasa 2"-5" 0.1500 Kg 11,000.00 1,650.00
Pekerja 0.1000 HOK 35,000.00 3,500.00
Tukang kayu 0.1000 HOK 45,000.00 4,500.00
Kepala tukang 0.0100 HOK 50,000.00 500.00
Mandor 0.0050 HOK 50,000.00 250.00
Total 8,750.00 124,608.00
Total Harga 133,358.00
Keuntungan 20,003.70
Jumlah Total 153,361.70

F-32 1 m2 PASANG KASO + RENG GENTENG KODOK KAYU BORNEO


Kayu borneo, balok 0.0120 m3 5,313,000.00 63,756.00
Paku biasa 2"-5" 0.1500 Kg 11,000.00 1,650.00
Pekerja 0.1000 HOK 35,000.00 3,500.00
Tukang kayu 0.1000 HOK 45,000.00 4,500.00
Kepala tukang 0.0100 HOK 50,000.00 500.00
Mandor 0.0050 HOK 50,000.00 250.00
Total 8,750.00 65,406.00
Total Harga 74,156.00
Keuntungan 11,123.40
Jumlah Total 85,279.40

F-33 1 m2 PASANG KASO + RENG GENTENG MONIER KAYU JATI


F-34 1 m2 PASANG KASO + RENG GENTENG MONIER KAYU KAMPER
Kayu kamper, balok 0.0140 m3 10,246,500.00 143,451.00
Paku biasa 2"-5" 0.1500 Kg 11,000.00 1,650.00
Pekerja 0.1000 HOK 35,000.00 3,500.00
Tukang kayu 0.1000 HOK 45,000.00 4,500.00
Kepala tukang 0.0100 HOK 50,000.00 500.00
Mandor 0.0050 HOK 50,000.00 250.00
Total 8,750.00 145,101.00
Total Harga 153,851.00
Keuntungan 23,077.65
a b c d e f=(cxe) g=(cxe) h 5495470000
Jumlah Total 176,928.65

F-35 1 m2 PASANG KASO + RENG GENTENG BETON KAYU BORNEO


Kayu borneo, balok 0.0140 m3 5,313,000.00 74,382.00
Paku biasa 2"-5" 0.1500 Kg 11,000.00 1,650.00
Pekerja 0.1000 HOK 35,000.00 3,500.00
Tukang kayu 0.1000 HOK 45,000.00 4,500.00
Kepala tukang 0.0100 HOK 50,000.00 500.00
Mandor 0.0050 HOK 50,000.00 250.00
Total 8,750.00 76,032.00
Total Harga 84,782.00
Keuntungan 12,717.30
Jumlah Total 97,499.30

F-36 1 m2 PASANG KASO + RENG ATAP SIRAP KAYU KAMPER


Kayu kamper, balok 0.1650 m3 10,246,500.00 1,690,672.50
Paku biasa 2"-5" 0.2000 Kg 11,000.00 2,200.00
Pekerja 0.1200 HOK 35,000.00 4,200.00
Tukang kayu 0.1200 HOK 45,000.00 5,400.00
Kepala tukang 0.0120 HOK 50,000.00 600.00
Mandor 0.0060 HOK 50,000.00 300.00
Total 10,500.00 1,692,872.50
Total Harga 1,703,372.50
Keuntungan 255,505.88
Jumlah Total 1,958,878.38

F-37 1 m2 PASANG KASO + RENG ATAP SIRAP KAYU BORNEO


Kayu borneo, balok 0.1650 m3 5,313,000.00 876,645.00
Paku biasa 2"-5" 0.2000 Kg 11,000.00 2,200.00
Pekerja 0.1200 HOK 35,000.00 4,200.00
Tukang kayu 0.1200 HOK 45,000.00 5,400.00
Kepala tukang 0.0120 HOK 50,000.00 600.00
Mandor 0.0060 HOK 50,000.00 300.00
Total 10,500.00 878,845.00
Total Harga 889,345.00
Keuntungan 133,401.75
Jumlah Total 1,022,746.75

F-39 1 m2 PASANG RANGKA LANGIT-LANGIT ( 1X1 ) m, KAYU KAMPER


Kayu kamper, balok 0.0120 m3 10,246,500.00 122,958.00
Paku biasa 2"-5" 0.1000 Kg 11,000.00 1,100.00
Pekerja 0.1500 HOK 35,000.00 5,250.00
Tukang kayu 0.2500 HOK 45,000.00 11,250.00
Kepala tukang 0.0250 HOK 50,000.00 1,250.00
Mandor 0.0750 HOK 50,000.00 3,750.00
Total 21,500.00 124,058.00
Total Harga 145,558.00
Keuntungan 21,833.70
Jumlah Total 167,391.70

F-40 1 m2 PASANG RANGKA LANGIT-LANGIT ( 1x1 ) m, KAYU BORNEO


Kayu borneo, balok 0.0120 m3 5,313,000.00 63,756.00
Paku biasa 2"-5" 0.1000 Kg 11,000.00 1,100.00
Pekerja 0.1500 HOK 35,000.00 5,250.00
Tukang kayu 0.2500 HOK 45,000.00 11,250.00
Kepala tukang 0.0250 HOK 50,000.00 1,250.00
Mandor 0.0750 HOK 50,000.00 3,750.00
Total 21,500.00 64,856.00
Total Harga 86,356.00
Keuntungan 12,953.40
Jumlah Total 99,309.40

F-41 1 m2 PASANG RANGKA LANGIT-LANGIT ( 0.3X0.6 ) m, KAYU JATI


F-42 1 m2 PASANG RANGKA LANGIT-LANGIT ( 0.3X0.6 ) m, KAYU KAMPER
Kayu kamper, balok 0.0230 m3 10,246,500.00 235,669.50
Paku biasa 2"-5" 0.1500 Kg 11,000.00 1,650.00
Pekerja 0.2000 HOK 35,000.00 7,000.00
a b c d e f=(cxe) g=(cxe) h 5495470000
Tukang kayu 0.3000 HOK 45,000.00 13,500.00
Kepala tukang 0.0300 HOK 50,000.00 1,500.00
Mandor 0.0100 HOK 50,000.00 500.00
Total 22,500.00 237,319.50
Total Harga 259,819.50
Keuntungan 38,972.93
Jumlah Total 298,792.43

F-43 1 m2 PASANG RANGKA LANGIT-LANGIT ( 0.3X0.6 ) m, KAYU BORNEO


Kayu Borneo, balok 0.0230 m3 5,313,000.00 122,199.00
Paku biasa 2"-5" 0.1500 Kg 11,000.00 1,650.00
Pekerja 0.2000 HOK 35,000.00 7,000.00
Tukang kayu 0.3000 HOK 45,000.00 13,500.00
Kepala tukang 0.0300 HOK 50,000.00 1,500.00
Mandor 0.0100 HOK 50,000.00 500.00
Total 22,500.00 123,849.00
Total Harga 146,349.00
Keuntungan 21,952.35
Jumlah Total 168,301.35

F-44 1 m2 PASANG RANGKA LANGIT-LANGIT ( 0.3X0.3 ) m, KAYU JATI


F-45 1 m2 PASANG RANGKA LANGIT-LANGIT ( 0.3X0.3 ) m, KAYU KAMPER
F-46 1 m2 PASANG RANGKA LANGIT-LANGIT ( 0.3X0.3 ) m, KAYU BORNEO
F-47 1 m' PASANG LISTPLANK UKURAN ( 3x20 ) cm, KAYU JATI
F-48 1 m' PASANG LISTPLANK UKURAN ( 3x20 ) cm, KAYU KAMPER
Kayu kamper, papan 0.0072 m3 10,626,000.00 76,507.20
Paku biasa 2"-5" 0.0500 Kg 11,000.00 550.00
Pekerja 0.1000 HOK 35,000.00 3,500.00
Tukang kayu 0.2000 HOK 45,000.00 9,000.00
Kepala tukang 0.0200 HOK 50,000.00 1,000.00
Mandor 0.0050 HOK 50,000.00 250.00
Total 13,750.00 77,057.20
Total Harga 90,807.20
Keuntungan 13,621.08
Jumlah Total 104,428.28

F-49 1 m' PASANG LISTPLANK UKURAN ( 3x30 ) cm, KAYU JATI


F-50 1 m' PASANG LISTPLANK UKURAN ( 3x30 ) cm, KAYU KAMPER
Kayu kamper, papan 0.0110 m3 10,626,000.00 116,886.00
Paku biasa 2"-5" 0.0500 Kg 11,000.00 550.00
Pekerja 0.1100 HOK 35,000.00 3,850.00
Tukang kayu 0.2200 HOK 45,000.00 9,900.00
Kepala tukang 0.0220 HOK 50,000.00 1,100.00
Mandor 0.0050 HOK 50,000.00 250.00
Total 15,100.00 117,436.00
Total Harga 132,536.00
Keuntungan 19,880.40
Jumlah Total 152,416.40

F-51 1 m' PASANG LISTPLANK UKURAN 2 x ( 3x20 ) cm, KAYU KAMPER


Kayu kamper, papan 0.0145 m3 10,626,000.00 154,077.00
Paku biasa 2"-5" 0.0600 Kg 11,000.00 660.00
Pekerja 0.1500 HOK 35,000.00 5,250.00
Tukang kayu 0.2500 HOK 45,000.00 11,250.00
Kepala tukang 0.0250 HOK 50,000.00 1,250.00
Mandor 0.0750 HOK 50,000.00 3,750.00
Total 21,500.00 154,737.00
Total Harga 176,237.00
Keuntungan 26,435.55
Jumlah Total 202,672.55

F-52 1 m' PASANG LISTPLANK UKURAN 2 x ( 2x20 ) cm, KAYU KAMPER


Kayu kamper, papan 0.0086 m3 10,626,000.00 91,383.60
Paku biasa 2"-5" 0.0600 Kg 11,000.00 660.00
Pekerja 0.1000 HOK 35,000.00 3,500.00
Tukang kayu 0.1000 HOK 45,000.00 4,500.00
Kepala tukang 0.0100 HOK 50,000.00 500.00
a b c d e f=(cxe) g=(cxe) h 5495470000
Mandor 0.0500 HOK 50,000.00 2,500.00
Total 11,000.00 92,043.60
Total Harga 103,043.60
Keuntungan 15,456.54
Jumlah Total 118,500.14

F-53 1 m' PASANG LISTPLANK UKURAN 2 x ( 2x20 ) cm, KAYU BORNEO


Kayu borneo, papan 0.0088 m3 5,217,300.00 45,912.24
Paku biasa 2"-5" 0.0600 Kg 11,000.00 660.00
Pekerja 0.1000 HOK 35,000.00 3,500.00
Tukang kayu 0.1000 HOK 45,000.00 4,500.00
Kepala tukang 0.0100 HOK 50,000.00 500.00
Mandor 0.0500 HOK 50,000.00 2,500.00
Total 11,000.00 46,572.24
Total Harga 57,572.24
Keuntungan 8,635.84
Jumlah Total 66,208.08

F-54 1 m2 PASANG RANGKA DINDING PEMISAH KAYU KAMPER


Kayu kamper, balok 0.0195 m3 10,246,500.00 199,806.75
Kayu kamper, papan 0.0070 m3 10,626,000.00 74,382.00
Paku biasa 2"-5" 0.1000 Kg 11,000.00 1,100.00
Pekerja 0.1500 HOK 35,000.00 5,250.00
Tukang kayu 0.4500 HOK 45,000.00 20,250.00
Kepala tukang 0.0450 HOK 50,000.00 2,250.00
Mandor 0.0750 HOK 50,000.00 3,750.00
Total 31,500.00 275,288.75
Total Harga 306,788.75
Keuntungan 46,018.31
Jumlah Total 352,807.06

F-55 1 m2 PASANG RANGKA DINDING PEMISAH KAYU BORNEO


Kayu borneo, balok 0.0195 m3 5,313,000.00 103,603.50
Kayu borneo, papan 0.0070 m3 5,217,300.00 36,521.10
Paku biasa 2"-5" 0.1000 Kg 11,000.00 1,100.00
Pekerja 0.1500 HOK 35,000.00 5,250.00
Tukang kayu 0.4500 HOK 45,000.00 20,250.00
Kepala tukang 0.0450 HOK 50,000.00 2,250.00
Mandor 0.0750 HOK 50,000.00 3,750.00
Total 31,500.00 141,224.60
Total Harga 172,724.60
Keuntungan 25,908.69
Jumlah Total 198,633.29

F-56 1 m2 PASANG DINDING PEMISAH TEAKWOOD RANGKAP, RANGKA KAYU KAMPER


Kayu kamper, balok 0.0195 m3 10,246,500.00 199,806.75
Kayu kamper, papan 0.0070 m3 10,626,000.00 74,382.00
Paku biasa 2"-5" 0.1000 Kg 11,000.00 1,100.00
Teakwood 4'x8'x4 mm 1.0000 Lbr 148,500.00 148,500.00
Pekerja 0.1500 HOK 35,000.00 5,250.00
Tukang kayu 0.4500 HOK 45,000.00 20,250.00
Kepala tukang 0.0450 HOK 50,000.00 2,250.00
Mandor 0.0750 HOK 50,000.00 3,750.00
Total 31,500.00 423,788.75
Total Harga 455,288.75
Keuntungan 68,293.31
Jumlah Total 523,582.06

F-57 1 m2 PASANG DINDING PEMISAH PLYWOOD RANGKAP, RANGKA KAYU KAMPER


Kayu kamper, balok 0.0195 m3 10,246,500.00 199,806.75
Kayu kamper, papan 0.0070 m3 10,626,000.00 74,382.00
Paku biasa 2"-5" 0.1000 Kg 11,000.00 1,100.00
Lem kayu 0.5600 Lt 0.00 0.00
Plywood 4'x8'x4 mm 1.0000 Lbr 63,800.00 63,800.00
Pekerja 0.2000 HOK 35,000.00 7,000.00
Tukang kayu 0.6000 HOK 45,000.00 27,000.00
Kepala tukang 0.0600 HOK 50,000.00 3,000.00
a b c d e f=(cxe) g=(cxe) h 5495470000
Mandor 0.0100 HOK 50,000.00 500.00
Total 37,500.00 339,088.75
Total Harga 376,588.75
Keuntungan 56,488.31
Jumlah Total 433,077.06

F-58 1 m2 PASANG DINDING LAMBRIZIRING DARI PAPAN JATI


F-59 1 m' PASANG PLYWOOD TEBAL 4 mm, UNTUK DINDING
Plywood 4' x 8' x 4 mm 0.4000 lbr 63,800.00 25,520.00
Paku biasa 1/2"-1" 0.0500 kg 11,000.00 550.00
Pekerja 0.0250 HOK 35,000.00 875.00
Tukang kayu 0.0750 HOK 45,000.00 3,375.00
Kepala tukang 0.0075 HOK 50,000.00 375.00
Mandor 0.0013 HOK 50,000.00 65.00
Total 4,690.00 26,070.00
Total Harga 30,760.00
Keuntungan 4,614.00
Jumlah Total 35,374.00

F-60 1 m' PASANG LIST PLAFOND KAYU PROFIL


Kayu profil 1.0500 m' 7,000.00 7,350.00
Pekerja 0.0210 HOK 35,000.00 735.00
Tukang kayu 0.0210 HOK 45,000.00 945.00
Kepala tukang 0.0020 HOK 50,000.00 100.00
Mandor 0.0010 HOK 50,000.00 50.00
Total 1,830.00 7,350.00
Total Harga 9,180.00
Keuntungan 1,377.00
Jumlah Total 10,557.00
a b c d e f=(cxe) g=(cxe) h 5495470000

DIHITUNG 1 m3 PASANG KONSTRUKSI KUDA-KUDA KAYU GUNUNG KELAS II


Kayu gunung kelas II, balok 1.1000 m3 2,200,000.00 2,420,000.00
Besi strip 15.0000 Kg 11,000.00 165,000.00
Paku biasa 2"-5" 0.8000 Kg 11,000.00 8,800.00
Pekerja 4.0000 HOK 35,000.00 140,000.00
Tukang kayu 12.0000 HOK 45,000.00 540,000.00
Kepala tukang 1.2000 HOK 50,000.00 60,000.00
Mandor 0.2000 HOK 50,000.00 10,000.00
Total 750,000.00 2,593,800.00
Total Harga 3,343,800.00
Keuntungan
Jumlah Total 3,343,800.00

DIHITUNG 1 m2 PASANG KASO + RENG KAYU GUNUNG KELAS II GENTENG MORANDO


Kayu gunung kelas II, balok 0.0120 m3 2,200,000.00 26,400.00
Paku biasa 2"-5" 0.1500 Kg 11,000.00 1,650.00
Pekerja 0.1000 HOK 35,000.00 3,500.00
Tukang kayu 0.1000 HOK 45,000.00 4,500.00
Kepala tukang 0.0100 HOK 50,000.00 500.00
Mandor 0.0050 HOK 50,000.00 250.00
Total 8,750.00 28,050.00
Total Harga 36,800.00
Keuntungan
Jumlah Total 36,800.00

DIHITUNG 1 m2 PASANG RANGKA LANGIT-LANGIT ( 1x1 ) m, KAYU GUNUNG KELAS III


Kayu gunung kelas III, balok 0.0120 m3 1,300,000.00 15,600.00
Paku biasa 2"-5" 0.1000 Kg 11,000.00 1,100.00
Pekerja 0.1500 HOK 35,000.00 5,250.00
Tukang kayu 0.2500 HOK 45,000.00 11,250.00
Kepala tukang 0.0250 HOK 50,000.00 1,250.00
Mandor 0.0750 HOK 50,000.00 3,750.00
Total 21,500.00 16,700.00
Total Harga 38,200.00
Keuntungan
Jumlah Total 38,200.00

DIHITUNG 1 m3 PASANG KUSEN PINTU DAN JENDELA KAYU GUNUNG KELAS II


Kayu gunung kelasII, balok 1.1000 m3 2,200,000.00 2,420,000.00
Pekerja 6.0000 HOK 35,000.00 210,000.00
Tukang kayu 20.0000 HOK 45,000.00 900,000.00
Kepala tukang 2.0000 HOK 50,000.00 100,000.00
Mandor 0.3000 HOK 50,000.00 15,000.00
Total 1,225,000.00 2,420,000.00
Total Harga 3,645,000.00
Keuntungan
Jumlah Total 3,645,000.00

DIHITUNG 1 m' PASANG LISTPLANK UKURAN 2 x ( 2x20 ) cm, KAYU GUNUNG KELAS II
Kayu Gunung Kls II, papan 0.0088 m3 2,100,000.00 18,480.00
Paku biasa 2"-5" 0.0600 Kg 11,000.00 660.00
Pekerja 0.1000 HOK 35,000.00 3,500.00
Tukang kayu 0.1000 HOK 45,000.00 4,500.00
Kepala tukang 0.0100 HOK 50,000.00 500.00
Mandor 0.0500 HOK 50,000.00 2,500.00
Total 11,000.00 19,140.00
Total Harga 30,140.00
Keuntungan
Jumlah Total 30,140.00
a b c d e f=(cxe) g=(cxe) h 5495470000

G PEKERJAAN BETON
G-01 1 m3 MEMBUAT BETON TUMBUK, 1 PC : 3 Ps : 5 Kr
Semen portland 218.0000 kg 1,090.00 237,620.00
Pasir beton 0.5200 m3 125,000.00 65,000.00
Koral beton 0.8700 m3 125,000.00 108,750.00
Pekerja 1.6500 HOK 35,000.00 57,750.00
Tukang batu 0.2500 HOK 45,000.00 11,250.00
Kepala tukang 0.0250 HOK 50,000.00 1,250.00
Mandor 0.0800 HOK 50,000.00 4,000.00
Total 74,250.00 411,370.00
Total Harga 485,620.00
Keuntungan
Jumlah Total 485,620.00

G-02 1 m3 MEMBUAT BETON TUMBUK, 1 PC : 3 Ps : 6 Kr


Semen portland 197.0000 kg 1,090.00 214,730.00
Pasir beton 0.4700 m3 125,000.00 58,750.00
Koral beton 0.9400 m3 125,000.00 117,500.00
Pekerja 1.6500 HOK 35,000.00 57,750.00
Tukang batu 0.2500 HOK 45,000.00 11,250.00
Kepala tukang 0.0250 HOK 50,000.00 1,250.00
Mandor 0.0800 HOK 50,000.00 4,000.00
Total 74,250.00 390,980.00
Total Harga 465,230.00
Keuntungan 69,784.50
Jumlah Total 535,014.50

G-03 1 m3 MEMBUAT BETON TUMBUK, 1 PC : 4 Ps : 6 Kr


Semen portland 173.0000 kg 1,090.00 188,570.00
Pasir beton 0.5700 m3 125,000.00 71,250.00
Koral beton 0.8700 m3 125,000.00 108,750.00
Pekerja 1.6500 HOK 35,000.00 57,750.00
Tukang batu 0.2500 HOK 45,000.00 11,250.00
Kepala tukang 0.0250 HOK 50,000.00 1,250.00
Mandor 0.0800 HOK 50,000.00 4,000.00
Total 74,250.00 368,570.00
Total Harga 442,820.00
Keuntungan 66,423.00
Jumlah Total 509,243.00

G-04 1 m2 MEMBUAT LANTAI KERJA BETON TUMBUK, 1 PC : 3 Ps : 5 Kr


Semen portland 10.0000 kg 1,090.00 10,900.00
Pasir beton 0.0260 m3 125,000.00 3,250.00
Koral beton 0.0440 m3 125,000.00 5,500.00
Pekerja 1.1500 HOK 35,000.00 40,250.00
Tukang batu 0.0200 HOK 45,000.00 900.00
Kepala tukang 0.0020 HOK 50,000.00 100.00
Mandor 0.0060 HOK 50,000.00 300.00
Total 41,550.00 19,650.00
Total Harga 61,200.00
Keuntungan 9,180.00
Jumlah Total 70,380.00

G-05 1 m3 MEMBUAT BETON TUMBUK, 1 PC : 2 Ps : 3 Kr


Semen portland 232.0000 kg 1,090.00 252,880.00
Pasir beton 0.5200 m3 125,000.00 65,000.00
Koral beton 0.7800 m3 125,000.00 97,500.00
Pekerja 1.6500 HOK 35,000.00 57,750.00
Tukang batu 0.2500 HOK 45,000.00 11,250.00
Kepala tukang 0.0250 HOK 50,000.00 1,250.00
Mandor 0.0800 HOK 50,000.00 4,000.00
Total 74,250.00 415,380.00
Total Harga 489,630.00
Keuntungan
Jumlah Total 489,630.00
a b c d e f=(cxe) g=(cxe) h 5495470000
G-19 1 m' MEMASANG PVC WATERSTOP LEBAR 150 mm
Waterstop lebar 150 mm 1.0500 m' 0.00 0.00
Pekerja 0.0500 HOK 35,000.00 1,750.00
Tukang batu 0.0300 HOK 45,000.00 1,350.00
Kepala tukang 0.0030 HOK 50,000.00 150.00
Mandor 0.0020 HOK 50,000.00 100.00
Total 3,350.00 0.00
Total Harga 3,350.00
Keuntungan 502.50
Jumlah Total 3,852.50

G-20 1 m' MEMASANG PVC WATERSTOP LEBAR 200 mm


Waterstop lebar 200 mm 1.0500 m' 0.00 0.00
Pekerja 0.0500 HOK 35,000.00 1,750.00
Tukang batu 0.0350 HOK 45,000.00 1,575.00
Kepala tukang 0.0035 HOK 50,000.00 175.00
Mandor 0.0020 HOK 50,000.00 100.00
Total 3,600.00 0.00
Total Harga 3,600.00
Keuntungan 540.00
Jumlah Total 4,140.00

G-21 1 m' MEMASANG PVC WATERSTOP LEBAR 230 mm


Waterstop lebar 230 mm 1.0500 m' 0.00 0.00
Pekerja 0.5500 HOK 35,000.00 19,250.00
Tukang batu 0.0350 HOK 45,000.00 1,575.00
Mandor 0.0030 HOK 50,000.00 150.00
Total 20,975.00 0.00
Total Harga 20,975.00
Keuntungan 3,146.25
Jumlah Total 24,121.25

G-22 1 m' MEMASANG PVC WATERSTOP LEBAR 250 mm


Waterstop lebar 250 mm 1.0500 m' 0.00 0.00
Pekerja 0.5500 HOK 35,000.00 19,250.00
Tukang batu 0.0350 HOK 45,000.00 1,575.00
Mandor 0.0030 HOK 50,000.00 150.00
Total 20,975.00 0.00
Total Harga 20,975.00
Keuntungan 3,146.25
Jumlah Total 24,121.25

G-23 1 m' MEMASANG PVC WATERSTOP LEBAR 300 mm


Waterstop lebar 300 mm 1.0500 m' 0.00 0.00
Pekerja 0.5500 HOK 35,000.00 19,250.00
Tukang batu 0.0350 HOK 45,000.00 1,575.00
Mandor 0.0030 HOK 50,000.00 150.00
Total 20,975.00 0.00
Total Harga 20,975.00
Keuntungan 3,146.25
Jumlah Total 24,121.25

G-24 1 m' MEMASANG PVC WATERSTOP LEBAR 320 mm


Waterstop lebar 320 mm 1.0500 m' 0.00 0.00
Pekerja 0.5500 HOK 35,000.00 19,250.00
Tukang batu 0.0350 HOK 45,000.00 1,575.00
Mandor 0.0030 HOK 50,000.00 150.00
Total 20,975.00 0.00
Total Harga 20,975.00
Keuntungan 3,146.25
Jumlah Total 24,121.25

G-25 1 Kg PEMBESIAN DENGAN BESI POLOS ATAU ULIR


Besi beton ( polos /ulir ) 1.0500 Kg 8,000.00 8,400.00
Kawat beton 0.0150 Kg 12,000.00 180.00
Pekerja 0.0070 HOK 35,000.00 245.00
Tukang besi 0.0070 HOK 43,500.00 304.50
a b c d e f=(cxe) g=(cxe) h 5495470000
Kepala tukang 0.0007 HOK 43,500.00 30.45
Mandor 0.0003 HOK 50,000.00 15.00
Total 594.95 8,580.00
Total Harga 9,174.95
Keuntungan
Jumlah Total 9,174.95

G-26 1 Kg KABEL PRESSTRESSED POLOS /STRANDS


Besi presstressed polos 1.0500 Kg 8,000.00 8,400.00
Kawat beton 0.0100 Kg 12,000.00 120.00
Pekerja 0.0050 HOK 35,000.00 175.00
Tukang besi 0.0050 HOK 43,500.00 217.50
Kepala tukang 0.0005 HOK 43,500.00 21.75
Mandor 0.0003 HOK 50,000.00 15.00
Total 429.25 8,520.00
Total Harga 8,949.25
Keuntungan 1,342.39
Jumlah Total 10,291.64

G-27 1 Kg JARING KAWAT BAJA


Besi jaring kawat baja 1.0200 Kg 8,000.00 8,160.00
Kawat beton 0.8050 Kg 12,000.00 9,660.00
Pekerja 0.0250 HOK 35,000.00 875.00
Tukang besi 0.0250 HOK 43,500.00 1,087.50
Kepala tukang 0.0025 HOK 43,500.00 108.75
Mandor 0.0015 HOK 50,000.00 75.00
Total 2,146.25 17,820.00
Total Harga 19,966.25
Keuntungan 2,994.94
Jumlah Total 22,961.19

G-28 1 m2 PASANG BEKISTING UNTUK PONDASI


Kayu terentang 0.0400 m3 1,300,000.00 52,000.00
Paku biasa 2'-5" 0.3000 Kg 11,000.00 3,300.00
Minyak bekisting 0.1000 Ltr 900.00 90.00
Pekerja 0.3000 HOK 35,000.00 10,500.00
Tukang kayu 0.2600 HOK 45,000.00 11,700.00
Kepala tukang 0.0260 HOK 50,000.00 1,300.00
Mandor 0.0050 HOK 50,000.00 250.00
Total 23,750.00 55,390.00
Total Harga 79,140.00
Keuntungan
Jumlah Total 79,140.00

G-29 1 m2 PASANG BEKISTING UNTUK SLOOF


Kayu terentang 0.0450 m3 1,300,000.00 58,500.00
Paku biasa 2'-5" 0.3000 Kg 11,000.00 3,300.00
Minyak bekisting 0.1000 Ltr 900.00 90.00
Pekerja 0.3000 HOK 35,000.00 10,500.00
Tukang kayu 0.2600 HOK 44,500.00 11,570.00
Kepala tukang 0.0260 HOK 44,500.00 1,157.00
Mandor 0.0050 HOK 50,000.00 250.00
Total 23,477.00 61,890.00
Total Harga 85,367.00
Keuntungan
Jumlah Total 85,367.00
a b c d e f=(cxe) g=(cxe) h 5495470000
G-30 1 m2 PASANG BEKISTING UNTUK KOLOM
Kayu terentang 0.0400 m3 1,300,000.00 52,000.00
Paku biasa 2'-5" 0.4000 Kg 11,000.00 4,400.00
Minyak bekisting 0.2000 Ltr 900.00 180.00
Balok kayu Kelas III 0.0150 m3 1,300,000.00 19,500.00
papan Cor 0.0200 M3 1,300,000.00 26,000.00
bambu 2.0000 Btg 5,000.00 10,000.00
Pekerja 0.3000 HOK 35,000.00 10,500.00
Tukang kayu 0.3300 HOK 44,500.00 14,685.00
Kepala tukang 0.0330 HOK 44,500.00 1,468.50
Mandor 0.0060 HOK 50,000.00 300.00
Total 26,953.50 112,080.00
Total Harga 139,033.50
Keuntungan
Jumlah Total 139,033.50

G-31 1 m2 PASANG BEKISTING UNTUK BALOK


Kayu terentang 0.0400 m3 1,300,000.00 52,000.00
Paku biasa 2'-5" 0.4000 Kg 11,000.00 4,400.00
Minyak bekisting 0.2000 Ltr 900.00 180.00
Balok kayu ALBASIAH 0.0180 m3 1,300,000.00 23,400.00
Papan Cor 0.0200 M3 1,300,000.00 26,000.00
Bambu 2.0000 Btg 5,000.00 10,000.00
Pekerja 0.3200 HOK 35,000.00 11,200.00
Tukang kayu 0.3300 HOK 44,500.00 14,685.00
Kepala tukang 0.0330 HOK 44,500.00 1,468.50
Mandor 0.0060 HOK 50,000.00 300.00
Total 27,653.50 115,980.00
Total Harga 143,633.50
Keuntungan 21,545.03
Jumlah Total 165,178.53

G-32 1 m2 PASANG BEKISTING UNTUK LANTAI


Kayu terentang 0.0400 m3 1,300,000.00 52,000.00
Paku biasa 2'-5" 0.4000 Kg 11,000.00 4,400.00
Minyak bekisting 0.2000 Ltr 900.00 180.00
Balok kayu Kelas III 0.0150 m3 1,300,000.00 19,500.00
Papan Cor 0.0200 M3 1,300,000.00 26,000.00
Bambu 6.0000 Btg 5,000.00 30,000.00
Pekerja 0.3200 HOK 35,000.00 11,200.00
Tukang batu 0.3300 HOK 44,500.00 14,685.00
Kepala tukang 0.0330 HOK 44,500.00 1,468.50
Mandor 0.0060 HOK 50,000.00 300.00
Total 27,653.50 132,080.00
Total Harga 159,733.50
Keuntungan 23,960.03
Jumlah Total 183,693.53

G-33 1 m2 PASANG BEKISTING UNTUK DINDING


Kayu terentang 0.0300 m3 1,300,000.00 39,000.00
Paku biasa 2'-5" 0.4000 Kg 11,000.00 4,400.00
Minyak bekisting 0.2000 Ltr 900.00 180.00
Balok kayu Kelas III 0.0200 m3 1,300,000.00 26,000.00
Plywood tebal 9 mm 0.3500 Lbr 1,300,000.00 455,000.00
Dolken kayu galam q 8 - 10/4 m 3.0000 Btg 5,000.00 15,000.00
Formtie /spacer /penjaga jarak bekisting 4.0000 Bh 0.00 0.00
Pekerja 0.3200 HOK 35,000.00 11,200.00
Tukang batu 0.3300 HOK 44,500.00 14,685.00
Kepala tukang 0.0330 HOK 44,500.00 1,468.50
Mandor 0.0060 HOK 50,000.00 300.00
Total 27,653.50 539,580.00
Total Harga 567,233.50
Keuntungan 85,085.03
Jumlah Total 652,318.53

G-34 1 m2 PASANG BEKISTING UNTUK TANGGA


Kayu terentang 0.0300 m3 1,300,000.00 39,000.00
a b c d e f=(cxe) g=(cxe) h 5495470000
Paku biasa 2'-5" 0.4000 Kg 11,000.00 4,400.00
Minyak bekisting 0.1500 Ltr 900.00 135.00
Balok kayu KELAS III 0.0150 m3 1,300,000.00 19,500.00
Plywood tebal 9 mm 0.3500 Lbr 1,300,000.00 455,000.00
Dolken kayu galam q 8 - 10/4 m 2.0000 Btg 5,000.00 10,000.00
Pekerja 0.3200 HOK 35,000.00 11,200.00
Tukang batu 0.3300 HOK 44,500.00 14,685.00
Kepala tukang 0.0330 HOK 44,500.00 1,468.50
Mandor 0.0060 HOK 50,000.00 300.00
Total 27,653.50 528,035.00
Total Harga 555,688.50
Keuntungan 83,353.28
Jumlah Total 639,041.78

G-35 1 m3 MEMBUAT BETON DENGAN MUTU K-225


Semen Portland 388.0000 Kg 1,090.00 422,920.00
Pasir beton 0.6500 m3 125,000.00 81,250.00
Koral beton 0.6500 m3 125,000.00 81,250.00
Pekerja 6.0000 HOK 35,000.00 210,000.00
Tukang batu 1.0000 HOK 45,000.00 45,000.00
Kepala tukang 0.1000 HOK 50,000.00 5,000.00
Mandor 0.3000 HOK 50,000.00 15,000.00
Total 275,000.00 585,420.00
Total Harga 860,420.00
Keuntungan 129,063.00
Jumlah Total 989,483.00

G-36 1 m3 MEMBUAT BETON DENGAN MUTU K 275


Semen Portland 400.0000 Kg 1,090.00 436,000.00
Pasir beton 0.4000 m3 125,000.00 50,000.00
Koral beton 0.8200 m3 125,000.00 102,500.00
Pekerja 6.0000 HOK 35,000.00 210,000.00
Tukang batu 1.0000 HOK 45,000.00 45,000.00
Kepala tukang 0.1000 HOK 50,000.00 5,000.00
Mandor 0.3000 HOK 50,000.00 15,000.00
Total 275,000.00 588,500.00
Total Harga 863,500.00
Keuntungan 129,525.00
Jumlah Total 993,025.00

G-37 1 m2 PASANG JEMBATAN COR


Kayu terentang 0.0264 m3 1,300,000.00 34,320.00
Paku biasa 2"-5" 0.6000 Kg 11,000.00 6,600.00
Dolken kayu Ø 8-10/400 cm 0.5000 Btg 5,000.00 2,500.00
Pekerja 0.1500 HOK 35,000.00 5,250.00
Tukang batu 0.0500 HOK 45,000.00 2,250.00
Kepala tukang 0.0050 HOK 50,000.00 250.00
Mandor 0.0070 HOK 50,000.00 350.00
Total 8,100.00 43,420.00
Total Harga 51,520.00
Keuntungan 7,728.00
Jumlah Total 59,248.00

G-38 1 m3 MEMBUAT PONDASI BETON BERTULANG (150 Kg Besi + Bekisting)


Kayu terentang 0.2000 m3 1,300,000.00 260,000.00
Paku biasa 2"-5" 1.5000 Kg 11,000.00 16,500.00
Minyak bekisting 0.4000 Ltr 900.00 360.00
Besi beton polos 150.0000 Kg 8,000.00 1,200,000.00
Kawat beton 2.2500 Kg 12,000.00 27,000.00
Semen Portland 323.0000 Kg 1,090.00 352,070.00
Pasir beton 0.5200 m3 125,000.00 65,000.00
Koral beton 0.7800 m3 125,000.00 97,500.00
Pekerja 3.9000 HOK 35,000.00 136,500.00
Tukang batu 0.3500 HOK 45,000.00 15,750.00
Tukang kayu 1.0400 HOK 45,000.00 46,800.00
Tukang besi 1.0500 HOK 45,000.00 47,250.00
Kepala tukang 0.2450 HOK 50,000.00 12,250.00
a b c d e f=(cxe) g=(cxe) h 5495470000
Mandor 0.1650 HOK 50,000.00 8,250.00
Total 266,800.00 2,018,430.00
Total Harga 2,285,230.00
Keuntungan 342,784.50
Jumlah Total 2,628,014.50

G-39 1 m3 MEMBUAT SLOOF BETON BERTULANG (200 Kg Besi + Bekisting)


Kayu terentang 0.2700 m3 1,300,000.00 351,000.00
Paku biasa 2"-5" 2.0000 Kg 11,000.00 22,000.00
Minyak bekisting 0.6000 Ltr 900.00 540.00
Besi beton polos 200.0000 Kg 8,000.00 1,600,000.00
Kawat beton 3.0000 Kg 12,000.00 36,000.00
Semen Portland 323.0000 Kg 1,090.00 352,070.00
Pasir beton 0.5200 m3 125,000.00 65,000.00
Koral beton 0.7800 m3 125,000.00 97,500.00
Pekerja 4.8500 HOK 35,000.00 169,750.00
Tukang batu 0.3500 HOK 45,000.00 15,750.00
Tukang kayu 1.5600 HOK 45,000.00 70,200.00
Tukang besi 1.4000 HOK 45,000.00 63,000.00
Kepala tukang 0.3310 HOK 50,000.00 16,550.00
Mandor 0.1700 HOK 50,000.00 8,500.00
Total 343,750.00 2,524,110.00
Total Harga 2,867,860.00
Keuntungan 430,179.00
Jumlah Total 3,298,039.00

G-40 1 m3 MEMBUAT KOLOM BETON BERTULANG ( 300 Kg Besi + Bekisting )


Kayu terentang 0.4000 m3 1,300,000.00 520,000.00
Paku biasa 2"-5" 4.0000 Kg 11,000.00 44,000.00
Minyak bekisting 2.0000 Ltr 900.00 1,800.00
Besi beton polos 300.0000 Kg 8,000.00 2,400,000.00
Kawat beton 4.5000 Kg 12,000.00 54,000.00
Semen Portland 323.0000 Kg 1,090.00 352,070.00
Pasir beton 0.5200 m3 125,000.00 65,000.00
Koral beton 0.7800 m3 125,000.00 97,500.00
Kayu Kelas III 0.1500 m3 1,300,000.00 195,000.00
Plywood 9 mm 3.5000 Lbr 97,500.00 341,250.00
Dolken kayu Ø 8 cm /4.00 m 20.0000 Btg 5,000.00 100,000.00
Pekerja 7.3000 HOK 35,000.00 255,500.00
Tukang batu 0.3500 HOK 45,000.00 15,750.00
Tukang kayu 3.3000 HOK 45,000.00 148,500.00
Tukang besi 2.1000 HOK 45,000.00 94,500.00
Kepala tukang 0.5700 HOK 50,000.00 28,500.00
Mandor 0.2500 HOK 50,000.00 12,500.00
Total 555,250.00 4,170,620.00
Total Harga 4,725,870.00
Keuntungan 708,880.50
Jumlah Total 5,434,750.50

G-41 1 m3 MEMBUAT BALOK BETON BERTULANG ( 200 Kg Besi + Bekisting )


Kayu terentang 0.3200 m3 1,300,000.00 416,000.00
Paku biasa 2"-5" 3.2000 Kg 11,000.00 35,200.00
Minyak bekisting 1.6000 Ltr 900.00 1,440.00
Besi beton polos 200.0000 Kg 8,000.00 1,600,000.00
Kawat beton 3.0000 Kg 12,000.00 36,000.00
Semen Portland 323.0000 Kg 1,090.00 352,070.00
Pasir beton 0.5200 m3 125,000.00 65,000.00
Koral beton 0.7800 m3 125,000.00 97,500.00
Kayu Kelas III 0.1400 m3 1,300,000.00 182,000.00
Plywood 9 mm 2.8000 Lbr 97,500.00 273,000.00
Dolken kayu Ø 8 cm /4.00 m 16.0000 Btg 5,000.00 80,000.00
Pekerja 5.9600 HOK 35,000.00 208,600.00
Tukang batu 0.3500 HOK 45,000.00 15,750.00
Tukang kayu 2.8000 HOK 45,000.00 126,000.00
Tukang besi 1.4000 HOK 45,000.00 63,000.00
Kepala tukang 0.4550 HOK 50,000.00 22,750.00
Mandor 0.2080 HOK 50,000.00 10,400.00
a b c d e f=(cxe) g=(cxe) h 5495470000
Total 446,500.00 3,138,210.00
Total Harga 3,584,710.00
Keuntungan 537,706.50
Jumlah Total 4,122,416.50

G-42 1 m3 MEMBUAT BALOK BETON BERTULANG ( 150 Kg Besi + Bekisting )


Kayu terentang 0.3200 m3 1,300,000.00 416,000.00
Paku biasa 2"-5" 3.2000 Kg 11,000.00 35,200.00
Minyak bekisting 1.6000 Ltr 900.00 1,440.00
Besi beton polos 150.0000 Kg 8,000.00 1,200,000.00
Kawat beton 2.2500 Kg 12,000.00 27,000.00
Semen Portland 323.0000 Kg 1,090.00 352,070.00
Pasir beton 0.5200 m3 125,000.00 65,000.00
Koral beton 0.7800 m3 125,000.00 97,500.00
Kayu Kelas III 0.1200 m3 1,300,000.00 156,000.00
Plywood 9 mm 2.8000 Lbr 97,500.00 273,000.00
Dolken kayu Ø 8 cm /4.00 m 32.0000 Btg 5,000.00 160,000.00
Pekerja 5.8000 HOK 35,000.00 203,000.00
Tukang batu 0.3500 HOK 45,000.00 15,750.00
Tukang kayu 2.8000 HOK 45,000.00 126,000.00
Tukang besi 1.0500 HOK 45,000.00 47,250.00
Kepala tukang 0.4200 HOK 50,000.00 21,000.00
Mandor 0.1850 HOK 50,000.00 9,250.00
Total 422,250.00 2,783,210.00
Total Harga 3,205,460.00
Keuntungan 480,819.00
Jumlah Total 3,686,279.00

G-43 1 m3 MEMBUAT DINDING BETON BERTULANG ( 150 Kg Besi + Bekisting )


Kayu terentang 0.2400 m3 1,300,000.00 312,000.00
Paku biasa 2"-5" 3.2000 Kg 11,000.00 35,200.00
Minyak bekisting 1.6000 Ltr 900.00 1,440.00
Besi beton polos 150.0000 Kg 8,000.00 1,200,000.00
Kawat beton 2.2500 Kg 12,000.00 27,000.00
Semen Portland 323.0000 Kg 1,090.00 352,070.00
Pasir beton 0.5200 m3 125,000.00 65,000.00
Koral beton 0.7800 m3 125,000.00 97,500.00
Kayu kelas III 0.1600 m3 1,300,000.00 208,000.00
Plywood 9 mm 2.8000 Lbr 97,500.00 273,000.00
Dolken kayu Ø 8 cm /4.00 m 24.0000 Btg 5,000.00 120,000.00
Pekerja 5.6000 HOK 35,000.00 196,000.00
Tukang batu 0.3500 HOK 45,000.00 15,750.00
Tukang kayu 2.6400 HOK 45,000.00 118,800.00
Tukang besi 1.0500 HOK 45,000.00 47,250.00
Kepala tukang 0.4000 HOK 50,000.00 20,000.00
Mandor 0.1930 HOK 50,000.00 9,650.00
Total 407,450.00 2,691,210.00
Total Harga 3,098,660.00
Keuntungan 464,799.00
Jumlah Total 3,563,459.00

G-44 1 m3 MEMBUAT TANGGA BETON BERTULANG ( 200 Kg Besi + Bekisting )


Kayu terentang 0.2500 m3 1,300,000.00 325,000.00
Paku biasa 2"-5" 3.0000 Kg 11,000.00 33,000.00
Minyak bekisting 1.2000 Ltr 900.00 1,080.00
Besi beton polos 200.0000 Kg 8,000.00 1,600,000.00
Kawat beton 3.0000 Kg 12,000.00 36,000.00
Semen Portland 323.0000 Kg 1,090.00 352,070.00
Pasir beton 0.5200 m3 125,000.00 65,000.00
Koral beton 0.7800 m3 125,000.00 97,500.00
Kayu Kelas III 0.1050 m3 1,300,000.00 136,500.00
Plywood 9 mm 2.5000 Lbr 97,500.00 243,750.00
Dolken kayu Ø 8 cm /4.00 m 14.0000 Btg 5,000.00 70,000.00
Pekerja 5.6000 HOK 35,000.00 196,000.00
Tukang batu 0.3500 HOK 45,000.00 15,750.00
Tukang kayu 2.3000 HOK 45,000.00 103,500.00
Tukang besi 1.4000 HOK 45,000.00 63,000.00
a b c d e f=(cxe) g=(cxe) h 5495470000
Kepala tukang 0.4050 HOK 50,000.00 20,250.00
Mandor 0.2020 HOK 50,000.00 10,100.00
Total 408,600.00 2,959,900.00
Total Harga 3,368,500.00
Keuntungan 505,275.00
Jumlah Total 3,873,775.00

G-45 1 m' MEMBUAT KOLOM PENGUAT BETON BERTULANG ( 11x11 ) cm


Kayu terentang 0.0020 m3 1,300,000.00 2,600.00
Paku biasa 2"-5" 0.0100 Kg 11,000.00 110.00
Besi beton polos 3.0000 Kg 8,000.00 24,000.00
Kawat beton 0.4500 Kg 12,000.00 5,400.00
Semen Portland 4.0000 Kg 1,090.00 4,360.00
Pasir beton 0.0060 m3 125,000.00 750.00
Koral beton 0.0090 m3 125,000.00 1,125.00
Pekerja 0.0600 HOK 35,000.00 2,100.00
Tukang batu 0.0200 HOK 45,000.00 900.00
Tukang kayu 0.0200 HOK 45,000.00 900.00
Tukang besi 0.0200 HOK 45,000.00 900.00
Kepala tukang 0.0060 HOK 50,000.00 300.00
Mandor 0.0030 HOK 50,000.00 150.00
Total 5,250.00 38,345.00
Total Harga 43,595.00
Keuntungan 6,539.25
Jumlah Total 50,134.25

G-46 1 m' MEMBUAT RING BALOK BETON BERTULANG ( 10x15 ) cm


Kayu albasiah 0.0030 m3 1,300,000.00 3,900.00
Paku biasa 2"-5" 0.0200 Kg 11,000.00 220.00
Besi beton polos 3.6000 Kg 8,000.00 28,800.00
Kawat beton 0.0500 Kg 12,000.00 600.00
Semen Portland 5.5000 Kg 1,090.00 5,995.00
Pasir beton 0.0090 m3 125,000.00 1,125.00
Koral beton 0.0150 m3 125,000.00 1,875.00
Pekerja 0.1000 HOK 35,000.00 3,500.00
Tukang batu 0.0330 HOK 45,000.00 1,485.00
Tukang kayu 0.0330 HOK 45,000.00 1,485.00
Tukang besi 0.0330 HOK 45,000.00 1,485.00
Kepala tukang 0.0100 HOK 50,000.00 500.00
Mandor 0.0050 HOK 50,000.00 250.00
Total 8,705.00 42,515.00
Total Harga 51,220.00
Keuntungan 7,683.00
Jumlah Total 58,903.00

G-A Membuat 1 M3 Pondasi Plat Utama (P1)


Beton Site Mix 1PC : 2Ps :3Kr 1.0000 M3 489,630.00 489,630.00
Bekisting 2XPAKAI 4.0000 M2 59,355.00 237,420.00
Besi beton polos 155.3381 KG 9,174.95 1,425,219.37

2,152,269.37 2,152,269.37
G-B Membuat 1 M3 Pondasi Plat Selasar (P2)
Beton Site Mix 1PC : 2Ps :3Kr 1.0000 M3 489,630.00 489,630.00
Bekisting 2XPAKAI 5.0000 M2 59,355.00 296,775.00
Besi beton polos 189.5368 KG 9,174.95 1,738,990.30

2,525,395.30 2,525,395.30
G-C Membuat 1 M3 Pondasi Plat Tangga
Beton Site Mix 1PC : 2Ps :3Kr 1.0000 M3 489,630.00 489,630.00
Bekisting 2XPAKAI 5.6250 M2 59,355.00 333,871.88
Besi beton polos 205.0726 KG 9,174.95 1,881,530.48

2,705,032.36 2,705,032.36
G-D Membuat 1 M3 Sloof Beton 20/30
Beton Site Mix 1PC : 2Ps :3Kr 1.0000 M3 489,630.00 489,630.00
Bekisting 2XPAKAI 10.0000 M2 55,488.55 554,885.50
Besi beton polos 137.5216 KG 9,174.95 1,261,753.80
a b c d e f=(cxe) g=(cxe) h 5495470000

2,306,269.30 2,306,269.30
G-E Membuat 1 M3 Sloof Beton 15/20
Beton Site Mix 1PC : 2Ps :3Kr 1.0000 M3 489,630.00 489,630.00
Bekisting 2XPAKAI 13.3333 M2 55,488.55 739,847.33
Besi beton polos 155.1490 KG 9,174.95 1,423,483.97

2,652,961.30 2,652,961.30

G-F Membuat 1 M3 Kolom Praktis 15/15


Beton Site Mix 1PC : 2Ps :3Kr 1.0000 M3 489,630.00 489,630.00
Bekisting 2XPAKAI 13.3333 M2 104,275.13 1,390,335.00
Besi beton polos 210.0359 KG 9,174.95 1,927,068.45

3,807,033.45 3,807,033.45
G-G Membuat 1 M3 Kolom 15/20
Beton Site Mix 1PC : 2Ps :3Kr 1.0000 M3 489,630.00 489,630.00
Bekisting 2XPAKAI 33.3333 M2 104,275.13 3,475,837.50
Besi beton polos 159.3649 KG 9,174.95 1,462,164.64

5,427,632.14 5,427,632.14
G-H Membuat 1 M3 Kolom 20/20
Beton Site Mix 1PC : 2Ps :3Kr 1.0000 M3 489,630.00 489,630.00
Bekisting 2XPAKAI 20.0000 M2 104,275.13 2,085,502.50
Besi beton polos 126.3147 KG 9,174.95 1,158,930.83

3,734,063.33 3,734,063.33
G-I Membuat 1 M3 Kolom Selasar 25/25 (KS)
Beton Site Mix 1PC : 2Ps :3Kr 1.0000 M3 489,630.00 489,630.00
Bekisting 2XPAKAI 16.0000 M2 104,275.13 1,668,402.00
Besi beton polos 128.6221 KG 9,174.95 1,180,100.99

3,338,132.99 3,338,132.99
G-J Membuat 1 M3 Kolom Selasar 20/20 (KS2)
Beton Site Mix 1PC : 2Ps :3Kr 1.0000 M3 489,630.00 489,630.00
Bekisting 2XPAKAI 20.0000 M2 104,275.13 2,085,502.50
Besi beton polos 126.3147 KG 9,174.95 1,158,930.83

3,734,063.33 3,734,063.33
G-K Membuat 1 M3 Kolom Struktur 25/35 (K1)
Beton Site Mix 1PC : 2Ps :3Kr 1.0000 M3 489,630.00 489,630.00
Bekisting 2XPAKAI 13.7143 M2 104,275.13 1,430,058.86
Besi beton polos 159.9749 KG 9,174.95 1,467,761.96

3,387,450.81 3,387,450.81
G-L Membuat 1 M3 Kolom Struktur 20/30 (KS)
Beton Site Mix 1PC : 2Ps :3Kr 1.0000 M3 489,630.00 489,630.00
Bekisting 2XPAKAI 16.6667 M2 104,275.13 1,737,918.75
Besi beton polos 133.9691 KG 9,174.95 1,229,159.55

3,456,708.30 3,456,708.30
G-L.2 Membuat 1 M3 Kolom Struktur 25/30 (KE)
Beton Site Mix 1PC : 2Ps :3Kr 1.0000 M3 489,630.00 489,630.00
Bekisting 2XPAKAI 14.6667 M2 104,275.13 1,529,368.50
Besi beton polos 139.1909 KG 9,174.95 1,277,069.34

3,296,067.84 3,296,067.84
G-L.3 Membuat 1 M3 Kolom Struktur 25/35 (KE)
Beton Site Mix 1PC : 2Ps :3Kr 1.0000 M3 489,630.00 489,630.00
Bekisting 2XPAKAI 13.7143 M2 104,275.13 1,430,058.86
Besi beton polos 159.9749 KG 9,174.95 1,467,761.96

3,387,450.81 3,387,450.81
G-M Membuat 1 M3 Kolom Struktur 20/25(K2)
Beton Site Mix 1PC : 2Ps :3Kr 1.0000 M3 489,630.00 489,630.00
Bekisting 2XPAKAI 18.0000 M2 104,275.13 1,876,952.25
Besi beton polos 131.6539 KG 9,174.95 1,207,917.59
a b c d e f=(cxe) g=(cxe) h 5495470000

3,574,499.84 3,574,499.84
G-N Membuat 1 M3 Ring Balok 15/20
Beton Site Mix 1PC : 2Ps :3Kr 1.0000 M3 489,630.00 489,630.00
Bekisting 2XPAKAI 13.3333 M2 115,624.97 1,541,666.23
Besi beton polos 134.7214 KG 9,174.95 1,236,062.42

3,267,358.65 3,267,358.65
G-O Membuat 1 M3 Balok 25/35
Beton Site Mix 1PC : 2Ps :3Kr 1.0000 M3 489,630.00 489,630.00
Bekisting 2XPAKAI 8.1143 M2 115,624.97 938,214.02
Besi beton polos 100.1559 KG 9,174.95 918,925.70

2,346,769.72 2,346,769.72
G-P Membuat 1 M3 Balok 25/50
Beton Site Mix 1PC : 2Ps :3Kr 1.0000 M3 489,630.00 489,630.00
Bekisting 2XPAKAI 8.0800 M2 115,624.97 934,249.74
Besi beton polos 123.3346 KG 9,174.95 1,131,588.97

2,555,468.71 2,555,468.71
G-Q Membuat 1 M3 Balok 25/60
Beton Site Mix 1PC : 2Ps :3Kr 1.0000 M3 489,630.00 489,630.00
Bekisting 2XPAKAI 8.0667 M2 115,624.97 932,708.07
Besi beton polos 106.0081 KG 9,174.95 972,619.36

2,394,957.43 2,394,957.43
G-R Membuat 1 M3 Plat Dak T=12Cm
Beton Site Mix 1PC : 2Ps :3Kr 1.0000 M3 489,630.00 489,630.00
Bekisting PAKAI 10.5733 M2 137,770.14 1,456,689.65
Besi beton polos 86.9817 KG 9,174.95 798,052.67

2,744,372.32 2,744,372.32
G-S Membuat 1 M3 Plat Dak T=8Cm
Beton Site Mix 1PC : 2Ps :3Kr 1.0000 M3 489,630.00 489,630.00
Bekisting PAKAI 14.6600 M2 137,770.14 2,019,710.31
Besi beton polos 111.8578 KG 9,174.95 1,026,289.36

3,535,629.66 3,535,629.66
G-T Membuat 1 M3 Plat Dak T=10Cm
Beton Site Mix 1PC : 2Ps :3Kr 1.0000 M3 489,630.00 489,630.00
Bekisting PAKAI 12.2000 M2 137,770.14 1,680,795.75
Besi beton polos 106.5312 KG 9,174.95 977,418.43

3,147,844.19 3,147,844.19
G-U Membuat 1 M3 Balok 20/30
Beton Site Mix 1PC : 2Ps :3Kr 1.0000 M3 489,630.00 489,630.00
Bekisting 2XPAKAI 9.3333 M2 115,624.97 1,079,166.36
Besi beton polos 138.0839 KG 9,174.95 1,266,913.26

2,835,709.62 2,835,709.62
G-V Membuat 1 M3 Balok 15/20
Beton Site Mix 1PC : 2Ps :3Kr 1.0000 M3 489,630.00 489,630.00
Bekisting 2XPAKAI 13.3333 M2 115,624.97 1,541,666.23
Besi beton polos 159.3649 KG 9,174.95 1,462,164.64

3,493,460.87 3,493,460.87
Pekerja 0.1500 HOK 35,000.00 5,250.00
Tukang kayu 0.0750 HOK 45,000.00 3,375.00
Kepala tukang 0.0080 HOK 50,000.00 400.00
Mandor 0.0080 HOK 50,000.00 400.00
Total 9,425.00 3,147,844.19
Total Harga 3,157,269.19
Keuntungan 473,590.38
Jumlah Total 3,630,859.57
a b c d e f=(cxe) g=(cxe) h 5495470000

H PEKERJAAN PENUTUP ATAP


H-01 1 m2 PASANG ATAP GENTENG PALENTONG KECIL
Genteng palentong 25.0000 Bh 1,200.00 30,000.00
Pekerja 0.1500 HOK 35,000.00 5,250.00
Tukang kayu 0.0750 HOK 45,000.00 3,375.00
Kepala tukang 0.0080 HOK 50,000.00 400.00
Mandor 0.0080 HOK 50,000.00 400.00
Total 9,425.00 30,000.00
Total Harga 39,425.00
Keuntungan 5,913.75
Jumlah Total 45,338.75

Dihitung 1 m2 PASANG ATAP GENTENG MORANDO NATURAL


Genteng Morando natural 18.0000 Bh 1,500.00 27,000.00
Pekerja 0.1500 HOK 35,000.00 5,250.00
Tukang kayu 0.0750 HOK 45,000.00 3,375.00
Kepala tukang 0.0080 HOK 50,000.00 400.00
Mandor 0.0080 HOK 50,000.00 400.00
Total 9,425.00 27,000.00
Total Harga 36,425.00
Keuntungan
Jumlah Total 36,425.00

H-02 1 m2 PASANG ATAP GENTENG KODOK / GLAZZUR


Genteng kodok 25.0000 Bh 1,500.00 37,500.00
Pekerja 0.1500 HOK 35,000.00 5,250.00
Tukang kayu 0.0750 HOK 45,000.00 3,375.00
Kepala tukang 0.0080 HOK 50,000.00 400.00
Mandor 0.0080 HOK 50,000.00 400.00
Total 9,425.00 37,500.00
Total Harga 46,925.00
Keuntungan 7,038.75
Jumlah Total 53,963.75

H-03 1 m2 PASANG ATAP GENTENG PALENTONG SUPER / BESAR


Genteng palentong super 12.0000 Bh 1,800.00 21,600.00
Pekerja 0.1500 HOK 35,000.00 5,250.00
Tukang kayu 0.0600 HOK 45,000.00 2,700.00
Kepala tukang 0.0060 HOK 50,000.00 300.00
Mandor 0.0080 HOK 50,000.00 400.00
Total 8,650.00 21,600.00
Total Harga 30,250.00
Keuntungan 4,537.50
Jumlah Total 34,787.50

H-04 1 m1 PASANG GENTENG BUBUNG PALENTONG


Genteng bubung palentong 5.0000 Bh 2,250.00 11,250.00
Semen portland 8.0000 Kg 1,090.00 8,720.00
Pasir pasang 0.0320 m3 85,000.00 2,720.00
Pekerja 0.4000 HOK 35,000.00 14,000.00
Tukang kayu 0.2000 HOK 45,000.00 9,000.00
Kepala tukang 0.0200 HOK 50,000.00 1,000.00
Mandor 0.0020 HOK 50,000.00 100.00
Total 24,100.00 22,690.00
Total Harga 46,790.00
Keuntungan 7,018.50
Jumlah Total 53,808.50
Dihitung 1 m1 PASANG GENTENG BUBUNG MORANDO
Genteng bubung Morando 4.0000 Bh 3,000.00 12,000.00
Semen portland 8.0000 Kg 1,090.00 8,720.00
Pasir pasang 0.0320 m3 85,000.00 2,720.00
Pekerja 0.4000 HOK 35,000.00 14,000.00
Tukang kayu 0.2000 HOK 45,000.00 9,000.00
Kepala tukang 0.0200 HOK 50,000.00 1,000.00
Mandor 0.0020 HOK 50,000.00 100.00
Total 24,100.00 23,440.00
a b c d e f=(cxe) g=(cxe) h 5495470000
Total Harga 47,540.00
Keuntungan
Jumlah Total 47,540.00

H-05 1 m' PASANG BUBUNG GENTENG KODOK GLAZZUR


Genteng bubung kodok 5.0000 Bh 2,250.00 11,250.00
Semen portland 8.0000 Zak 1,090.00 8,720.00
Pasir pasang 0.0320 m3 85,000.00 2,720.00
Pekerja 0.4000 HOK 35,000.00 14,000.00
Tukang kayu 0.2000 HOK 45,000.00 9,000.00
Kepala tukang 0.0200 HOK 50,000.00 1,000.00
Mandor 0.0020 HOK 50,000.00 100.00
Total 24,100.00 22,690.00
Total Harga 46,790.00
Keuntungan 7,018.50
Jumlah Total 53,808.50

H-06 1 m' PASANG BUBUNG GENTENG PALENTONG BESAR


Genteng bubung palentong 4.0000 Bh 2,250.00 9,000.00
Semen portland 8.0000 Kg 1,090.00 8,720.00
Pasir pasang 0.0320 m3 85,000.00 2,720.00
Pekerja 0.4000 HOK 35,000.00 14,000.00
Tukang kayu 0.2000 HOK 45,000.00 9,000.00
Kepala tukang 0.0200 HOK 50,000.00 1,000.00
Mandor 0.0020 HOK 50,000.00 100.00
Total 24,100.00 20,440.00
Total Harga 44,540.00
Keuntungan 6,681.00
Jumlah Total 51,221.00

H-07 1 m2 PASANG ROOF LIGHT FIBREGLASS ( 180X90 ) cm


Roof light fibreglass 0.6000 Lbr 49,700.00 29,820.00
Paku biasa 1/2"-1" 0.0500 Kg 11,000.00 550.00
Pekerja 0.1400 HOK 35,000.00 4,900.00
Tukang kayu 0.0670 HOK 45,000.00 3,015.00
Kepala tukang 0.0070 HOK 50,000.00 350.00
Mandor 0.0070 HOK 50,000.00 350.00
Total 8,615.00 30,370.00
Total Harga 38,985.00
Keuntungan 5,847.75
Jumlah Total 44,832.75

H-08 1 m2 PASANG ATAP ASBES GELOMBANG ( 2,50X0,920 m )X 5 mm


Asbes gelombang 0.5000 Lbr 146,100.00 73,050.00
Paku pancing 60x230 0.1200 Kg 11,000.00 1,320.00
Pekerja 0.1400 HOK 35,000.00 4,900.00
Tukang kayu 0.0750 HOK 45,000.00 3,375.00
Kepala tukang 0.0080 HOK 50,000.00 400.00
Mandor 0.0080 HOK 50,000.00 400.00
Total 9,075.00 74,370.00
Total Harga 83,445.00
Keuntungan 12,516.75
Jumlah Total 95,961.75

H-09 1 m2 PASANG ATAP ASBES GELOMBANG ( 2,25X0,920 m )X 5 mm


Asbes gelombang 0.6000 Lbr 146,100.00 87,660.00
Paku pancing 60x230 0.1200 Kg 11,000.00 1,320.00
Pekerja 0.1400 HOK 35,000.00 4,900.00
Tukang kayu 0.0750 HOK 45,000.00 3,375.00
Kepala tukang 0.0080 HOK 50,000.00 400.00
Mandor 0.0080 HOK 50,000.00 400.00
Total 9,075.00 88,980.00
Total Harga 98,055.00
Keuntungan 14,708.25
Jumlah Total 112,763.25

H-10 1 m2 PASANG ATAP ASBES GELOMBANG ( 2,00X0,920 m )X 5 mm


a b c d e f=(cxe) g=(cxe) h 5495470000
Asbes gelombang 0.0600 Lbr 146,100.00 8,766.00
Paku pancing 60x230 0.1200 Kg 11,000.00 1,320.00
Pekerja 0.1400 HOK 35,000.00 4,900.00
Tukang kayu 0.0700 HOK 45,000.00 3,150.00
Kepala tukang 0.0070 HOK 50,000.00 350.00
Mandor 0.0070 HOK 50,000.00 350.00
Total 8,750.00 10,086.00
Total Harga 18,836.00
Keuntungan 2,825.40
Jumlah Total 21,661.40

H-11 1 m2 PASANG ATAP ASBES GELOMBANG ( 1,80X0,920 m )X 5 mm


Asbes gelombang 0.7500 Lbr 146,100.00 109,575.00
Paku pancing 60x230 0.1200 Kg 11,000.00 1,320.00
Pekerja 0.1400 HOK 35,000.00 4,900.00
Tukang kayu 0.0700 HOK 45,000.00 3,150.00
Kepala tukang 0.0070 HOK 50,000.00 350.00
Mandor 0.0070 HOK 50,000.00 350.00
Total 8,750.00 110,895.00
Total Harga 119,645.00
Keuntungan 17,946.75
Jumlah Total 137,591.75

H-12 1 m2 PASANG ATAP ASBES GELOMBANG ( 3,00X1,50 m )X 4 mm


Asbes gelombang 0.3500 Lbr 27,600.00 9,660.00
Paku pancing 0.1200 Kg 11,000.00 1,320.00
Pekerja 0.1400 HOK 35,000.00 4,900.00
Tukang kayu 0.0700 HOK 45,000.00 3,150.00
Kepala tukang 0.0070 HOK 50,000.00 350.00
Mandor 0.0070 HOK 50,000.00 350.00
Total 8,750.00 10,980.00
Total Harga 19,730.00
Keuntungan 2,959.50
Jumlah Total 22,689.50

H-13 1 m2 PASANG ATAP ASBES GELOMBANG ( 2,70X1,50 m )X 4 mm


Asbes gelombang 0.4200 Lbr 27,600.00 11,592.00
Paku pancing 0.1200 Kg 11,000.00 1,320.00
Pekerja 0.1400 HOK 35,000.00 4,900.00
Tukang kayu 0.0700 HOK 45,000.00 3,150.00
Kepala tukang 0.0070 HOK 50,000.00 350.00
Mandor 0.0070 HOK 50,000.00 350.00
Total 8,750.00 12,912.00
Total Harga 21,662.00
Keuntungan 3,249.30
Jumlah Total 24,911.30

H-14 1 m2 PASANG ATAP ASBES GELOMBANG ( 2,40X1,50 m )X 4 mm


Asbes gelombang 0.4400 Lbr 27,600.00 12,144.00
Paku pancing 0.1200 Kg 11,000.00 1,320.00
Pekerja 0.1400 HOK 35,000.00 4,900.00
Tukang kayu 0.0670 HOK 45,000.00 3,015.00
Kepala tukang 0.0070 HOK 50,000.00 350.00
Mandor 0.0070 HOK 50,000.00 350.00
Total 8,615.00 13,464.00
Total Harga 22,079.00
Keuntungan 3,311.85
Jumlah Total 25,390.85

H-15 1 m2 PASANG ATAP ASBES GELOMBANG ( 2,10X1,50 m )X 4 mm


Asbes gelombang 0.5100 Lbr 27,600.00 14,076.00
Paku pancing 0.1200 Kg 11,000.00 1,320.00
Pekerja 0.1400 HOK 35,000.00 4,900.00
Tukang kayu 0.0670 HOK 45,000.00 3,015.00
Kepala tukang 0.0070 HOK 50,000.00 350.00
Mandor 0.0070 HOK 50,000.00 350.00
Total 8,615.00 15,396.00
a b c d e f=(cxe) g=(cxe) h 5495470000
Total Harga 24,011.00
Keuntungan 3,601.65
Jumlah Total 27,612.65

H-16 1 m2 PASANG ATAP ASBES GELOMBANG ( 5,50X1,50 m )X 4 mm


Asbes gelombang 0.8000 Lbr 27,600.00 22,080.00
Paku pancing 0.1200 Kg 11,000.00 1,320.00
Pekerja 0.1400 HOK 35,000.00 4,900.00
Tukang kayu 0.0670 HOK 45,000.00 3,015.00
Kepala tukang 0.0070 HOK 50,000.00 350.00
Mandor 0.0070 HOK 50,000.00 350.00
Total 8,615.00 23,400.00
Total Harga 32,015.00
Keuntungan 4,802.25
Jumlah Total 36,817.25

H-17 1 m2 PASANG ATAP ASBES GELOMBANG ( 3,00x1,80 m ) x 6 mm


Asbes gelombang 0.3700 Lbr
Paku pancing 0.1200 Kg
Pekerja 0.1400 HOK
Tukang kayu 0.0670 HOK
Kepala tukang 0.0070 HOK
Mandor 0.0070 HOK
Total
Total Harga -
Keuntungan -
Jumlah Total -

H-18 1 m2 PASANG ATAP ASBES GELOMBANG ( 2,70x1,80 m ) x 6 mm


Asbes gelombang 0.3800 Lbr
Paku pancing 0.1200 Kg
Pekerja 0.1400 HOK
Tukang kayu 0.0670 HOK
Kepala tukang 0.0070 HOK
Mandor 0.0070 HOK
Total
Total Harga

H-19 1 m2 PASANG ATAP ASBES GELOMBANG ( 2,40x1,80 m ) x 6 mm


Asbes gelombang 0.4600 Lbr
Paku pancing 0.1200 Kg
Pekerja 0.1400 HOK
Tukang kayu 0.0670 HOK
Kepala tukang 0.0070 HOK
Mandor 0.0070 HOK
Total
Total Harga

H-20 1 m2 PASANG ATAP ASBES GELOMBANG ( 2,10x1,80 m ) x 6 mm


Asbes gelombang 0.4900 Lbr
Paku pancing 0.1200 Kg
Pekerja 0.1400 HOK
Tukang kayu 0.0670 HOK
Kepala tukang 0.0070 HOK
Mandor 0.0070 HOK
Total
Total Harga

H-21 1 m2 PASANG ATAP ASBES GELOMBANG ( 1,80x1,80 m ) x 6 mm


Asbes gelombang 0.5700 Lbr
Paku pancing 0.1200 Kg
Pekerja 0.1400 HOK
Tukang kayu 0.0670 HOK
Kepala tukang 0.0070 HOK
Mandor 0.0070 HOK
Total
Total Harga
a b c d e f=(cxe) g=(cxe) h 5495470000
Keuntungan -
Jumlah Total -

H-22 1 m' PASANG BUBUNG STEL GELOMBANG 0.92 m


Bubung stel gelombang 2.4000 Lbr 26,200.00
Paku skrup 3.5" 6.0000 Bh 0.00
Pekerja 0.0840 HOK 35,000.00
Tukang kayu 0.1250 HOK 45,000.00
Kepala tukang 0.0130 HOK 50,000.00
Mandor 0.0040 HOK 50,000.00
Total 0.00 0.00
Total Harga -
Keuntungan -
Jumlah Total -

H-25 1 m' PASANG NOK PATEN 0.92 m


Nok paten 1.2000 Lbr 0.00 0.00
Paku skrup 3.5" 6.0000 Kg 0.00 0.00
Pekerja 0.0840 HOK 0.00 0.00
Tukang kayu 0.1250 HOK 0.00 0.00
Kepala tukang 0.0130 HOK 0.00 0.00
Mandor 0.0040 HOK 0.00 0.00
Total 0.00 0.00
Total Harga -
Keuntungan -
Jumlah Total -

H-28 1 m' PASANG NOK STEL RATA 0.92 m


Nok stel rata 1.1000 Lbr 0.00 0.00
Paku skrup 3.5" 6.0000 Kg 0.00 0.00
Pekerja 0.1000 HOK 0.00 0.00
Tukang kayu 0.1500 HOK 0.00 0.00
Kepala tukang 0.0130 HOK 0.00 0.00
Mandor 0.0040 HOK 0.00 0.00
Total 0.00 0.00
Total Harga -
Keuntungan -
Jumlah Total -

H-30 1 m2 PASANG ATAP GENTENG BETON


Genteng beton 11.0000 bh 6,800.00 74,800.00
Paku biasa 2"-5" 0.0300 Kg 11,000.00 330.00
Pekerja 0.2000 HOK 35,000.00 7,000.00
Tukang kayu 0.1000 HOK 45,000.00 4,500.00
Kepala tukang 0.0100 HOK 50,000.00 500.00
Mandor 0.0100 HOK 50,000.00 500.00
Total 12,500.00 75,130.00
Total Harga 87,630.00
Keuntungan 13,144.50
Jumlah Total 100,774.50

H-32 1 m2 PASANG ATAP GENTENG METAL


Genteng metal 1.0200 Lbr
Paku biasa 2"-5" 0.2000 Kg
Pekerja 0.2000 HOK
Tukang kayu 0.1000 HOK
Kepala tukang 0.0100 HOK
Mandor 0.0010 HOK
Total 0.00 0.00
Total Harga -
Keuntungan -
Jumlah Total -

H-33 1 m2 PASANG ATAP SIRAP


Genteng sirap 60.0000 bh
Paku biasa 1/2"-1" 0.2000 Kg
Pekerja 0.1660 HOK
a b c d e f=(cxe) g=(cxe) h 5495470000
Tukang kayu 0.2500 HOK
Kepala tukang 0.0250 HOK
Mandor 0.0080 HOK
Total 0.00 0.00
Total Harga -
Keuntungan -
Jumlah Total -

H-34 1 m' PASANG NOK GENTENG BETON


Nok genteng beton 3.5000 bh
Paku biasa 2"-5" 0.0500 Kg 0.00
Semen PC (50 kg) 0.2160 Zak 1,090.00
Pasir pasang 0.0320 m3 85,000.00
Semen warna 1.0000 Kg 7,000.00
Pekerja 0.4000 HOK 35,000.00
Tukang kayu 0.2000 HOK 45,000.00
Kepala tukang 0.0200 HOK 50,000.00
Mandor 0.0200 HOK 50,000.00
Total 0.00 0.00
Total Harga -

H-36 1 m' PASANG NOK GENTENG METAL


Nok genteng decra bond 1.1000 bh 0.00
Paku biasa 1/2"-1" 0.0500 Kg 11,000.00
Pekerja 0.2500 HOK 0.00
Tukang kayu 0.1500 HOK 0.00
Kepala tukang 0.0150 HOK 0.00
Mandor 0.0130 HOK 0.00
Total 0.00 0.00
Total Harga -
Keuntungan -
Jumlah Total -

H-37 1 m' PASANG NOK SIRAP


Seng plat 3"x6" BJLS 28 0.4000 Lbr 0.00 0.00
Paku biasa 1/2"-1" 0.0600 Kg 0.00 0.00
Paku biasa 2"-5" 0.0500 Kg 0.00 0.00
Kayu papan 3 cm 0.0040 m3 0.00 0.00
Pekerja 0.1250 HOK 0.00 0.00
Tukang kayu 0.2500 HOK 0.00 0.00
Kepala tukang 0.0250 HOK 0.00 0.00
Mandor 0.0060 HOK 0.00 0.00
Total 0.00 0.00
Total Harga -
Keuntungan -
Jumlah Total -

H-38 1 m2 PASANG ATAP SENG GELOMBANG


Seng gelombang 3"x6" BJLS 28 0.7000 Lbr
Paku biasa 1/2"-1" 0.0200 Kg
Pekerja 0.1200 HOK
Tukang kayu 0.0600 HOK
Kepala tukang 0.0060 HOK
Mandor 0.0060 HOK
Total 0.00 0.00
Total Harga -
Keuntungan -
Jumlah Total -

H-39 1 m2 PASANG ATAP NOK SENG


Seng plat 3"x6" BJLS 28 0.3000 Lbr 0.00 0.00
Paku biasa 1/2"-1" 0.0400 Kg 0.00 0.00
Pekerja 0.1500 HOK 0.00 0.00
Tukang kayu 0.0700 HOK 0.00 0.00
Kepala tukang 0.0080 HOK 0.00 0.00
Mandor 0.0060 HOK 0.00 0.00
Total 0.00 0.00
a b c d e f=(cxe) g=(cxe) h 5495470000
Total Harga -
Keuntungan -
Jumlah Total -

H-40 1 m2 PASANG ATAP ALUMINIUM


Atap alluminium gelombang tebal 0.55 1.0500 m2 0.00 0.00
Paku hak panjang 15cm 0.0200 Kg 0.00 0.00
Pekerja 0.1500 HOK 0.00 0.00
Tukang kayu 0.7500 HOK 0.00 0.00
Kepala tukang 0.0080 HOK 0.00 0.00
Mandor 0.0060 HOK 0.00 0.00
Total 0.00 0.00
Total Harga -
Keuntungan -
Jumlah Total -

H-41 1 m2 PASANG NOK ALLUMINIUM


Nok standar 40 cm18, swg 22 1.2000 m2 0.00 0.00
Paku hak panjang 15cm 0.0400 Kg 0.00 0.00
Pekerja 0.1000 HOK 0.00 0.00
Tukang kayu 1.0000 HOK 0.00 0.00
Kepala tukang 0.0100 HOK 0.00 0.00
Mandor 0.0100 HOK 0.00 0.00
Total 0.00 0.00
Total Harga -
Keuntungan -
Jumlah Total -

H-42 1 m2 PASANG ALLUMINIUM FOIL /SISALATION


Alluminiumfoil /sisalation 1.0500 m2 0.00 0.00
Pekerja 0.1500 HOK 0.00 0.00
Tukang kayu 0.0500 HOK 0.00 0.00
Kepala tukang 0.0050 HOK 0.00 0.00
Mandor 0.0080 HOK 0.00 0.00
Total 0.00 0.00
Total Harga -
Keuntungan -
Jumlah Total -

I PEKERJAAN LANGIT-LANGIT
I-02 1 m2 LANGIT-LANGIT ASBES (1.00X1.00 ) m, TEBAL 5 mm
Plat asbes 5mm 1.1000 Lbr 8,000.00 8,800.00
Paku 0.0100 Kg 11,000.00 110.00
Pekerja 0.0300 HOK 35,000.00 1,050.00
Tukang kayu 0.0700 HOK 45,000.00 3,150.00
Kepala tukang 0.0070 HOK 50,000.00 350.00
Mandor 0.0015 HOK 50,000.00 75.00
Total 4,625.00 8,910.00
Total Harga 13,535.00
Keuntungan
Jumlah Total 13,535.00

I-11 1 m2 LANGIT-LANGIT PLYWOOD (60X120) cm, TEBAL 6 mm


Plywood 4x8x4 mm 0.3750 Lbr 63,800.00 23,925.00
Paku 0.0300 Kg 11,000.00 330.00
Pekerja 0.0700 HOK 35,000.00 2,450.00
Tukang kayu 0.1000 HOK 45,000.00 4,500.00
Kepala tukang 0.0100 HOK 50,000.00 500.00
Mandor 0.0035 HOK 50,000.00 175.00
Total 7,625.00 24,255.00
Total Harga 31,880.00
Keuntungan 4,782.00
Jumlah Total 36,662.00

I-13 1 m2 LANGIT-LANGIT TEAKWOOD (60X120) cm, TEBAL 4 mm


Teakwood 4x8x4 mm 0.3750 Lbr 148,500.00 55,687.50
Paku 0.0300 Kg 11,000.00 330.00
a b c d e f=(cxe) g=(cxe) h 5495470000
Pekerja 0.0700 HOK 35,000.00 2,450.00
Tukang kayu 0.1000 HOK 45,000.00 4,500.00
Kepala tukang 0.0100 HOK 50,000.00 500.00
Mandor 0.0035 HOK 50,000.00 175.00
Total 7,625.00 56,017.50
Total Harga 63,642.50
Keuntungan 9,546.38
Jumlah Total 73,188.88

I-14 1 m2 LANGIT-LANGIT LAT KAYU JATI


Kayu papan jati 0.0240 m3 5,692,500.00 136,620.00
Paku 0.0100 Kg 11,000.00 110.00
Paku skrup 0.0500 Kg 0.00 0.00
Pekerja 0.2000 HOK 35,000.00 7,000.00
Tukang kayu 0.6000 HOK 45,000.00 27,000.00
Kepala tukang 0.0600 HOK 50,000.00 3,000.00
Mandor 0.0100 HOK 50,000.00 500.00
Total 37,500.00 136,730.00
Total Harga 174,230.00
Keuntungan 26,134.50
Jumlah Total 200,364.50

I-19 1 m' LIST LANGIT-LANGIT KAYU PROFIL


List kayu profil 1.1000 m' 10,750.00 11,825.00
Paku 0.0100 Kg 11,000.00 110.00
Pekerja 0.0500 HOK 35,000.00 1,750.00
Tukang kayu 0.0500 HOK 45,000.00 2,250.00
Kepala tukang 0.0050 HOK 50,000.00 250.00
Mandor 0.0030 HOK 50,000.00 150.00
Total 4,400.00 11,935.00
Total Harga 16,335.00
Keuntungan 2,450.25
Jumlah Total 18,785.25

I-20 1 m2 LANGIT-LANGIT ASBES (1.00X1.00) m, Tebal 3,2 mm RANGKA KAYU BORNEO


Kayu borneo, balok 0.0120 m3 5,313,000.00 63,756.00
Paku biasa 0.0600 Kg 11,000.00 660.00
Asbes 1.00x1.00 m 1.1000 Lbr 8,000.00 8,800.00
Pekerja 0.1800 HOK 35,000.00 6,300.00
Tukang kayu 0.3200 HOK 45,000.00 14,400.00
Kepala tukang 0.0320 HOK 50,000.00 1,600.00
Mandor 0.0090 HOK 50,000.00 450.00
Total 22,750.00 73,216.00
Total Harga 95,966.00
Keuntungan 14,394.90
Jumlah Total 110,360.90

I-21 1 m2 LANGIT-LANGIT PLYWOOD 4 mm + RANGKA KAYU BORNEO


Kayu borneo, balok 0.0230 m3 5,313,000.00 122,199.00
Paku biasa 2" - 5" 0.0600 Kg 11,000.00 660.00
Plywood 4x8x4 mm 0.3900 Lbr 63,800.00 24,882.00
Pekerja 0.2700 HOK 35,000.00 9,450.00
Tukang kayu 0.4000 HOK 45,000.00 18,000.00
Kepala tukang 0.0400 HOK 50,000.00 2,000.00
Mandor 0.0135 HOK 50,000.00 675.00
Total 30,125.00 147,741.00
Total Harga 177,866.00
Keuntungan 26,679.90
Jumlah Total 204,545.90

I-24 1 m2 LANGIT-LANGIT GYPSUM BOARD TEBAL 9 mm


Gypsum board 120x240x9 mm 0.3640 Lbr 0.00 0.00
Paku biasa skrup 0.1100 Kg 0.00 0.00
Pekerja 0.1000 HOK 35,000.00 3,500.00
Tukang kayu 0.0500 HOK 45,000.00 2,250.00
Kepala tukang 0.0050 HOK 50,000.00 250.00
Mandor 0.0050 HOK 50,000.00 250.00
a b c d e f=(cxe) g=(cxe) h 5495470000
Total 6,250.00 0.00
Total Harga 6,250.00
Keuntungan 937.50
Jumlah Total 7,187.50

DIHITUNG 1 m2 LANGIT-LANGIT ASBES (1.00X1.00) m, RANGKA KAYU GUNUNG KELAS II


Kayu Gunung Kls II, balok 0.0120 m3 2,100,000.00 25,200.00
Paku biasa 0.0600 Kg 11,000.00 660.00
Asbes 1.00x1.00 m 1.1000 Lbr 8,000.00 8,800.00
Pekerja 0.1800 HOK 35,000.00 6,300.00
Tukang kayu 0.3200 HOK 45,000.00 14,400.00
Kepala tukang 0.0320 HOK 50,000.00 1,600.00
Mandor 0.0090 HOK 50,000.00 450.00
Total 22,750.00 34,660.00
Total Harga 57,410.00
Keuntungan 8,611.50
Jumlah Total 66,021.50

DIHITUNG 1 m2 LANGIT-LANGIT PLYWOOD, RANGKA KAYU GUNUNG KELAS II


Kayu Gunung Kls II, balok 0.0230 m3 2,100,000.00 48,300.00
Paku biasa 2" - 5" 0.0600 Kg 11,000.00 660.00
Plywood 4x8x4 mm 0.3900 Lbr 63,800.00 24,882.00
Pekerja 0.2700 HOK 35,000.00 9,450.00
Tukang kayu 0.4000 HOK 45,000.00 18,000.00
Kepala tukang 0.0400 HOK 50,000.00 2,000.00
Mandor 0.0135 HOK 50,000.00 675.00
Total 30,125.00 73,842.00
Total Harga 103,967.00
Keuntungan 15,595.05
Jumlah Total 119,562.05

J PEKERJAAN SANITASI
J-01 MEMASANG 1 BUAH KLOSET DUDUK /MONOBLOK
Kloset duduk /monoblok 1.0000 Unit *) 1,566,600.00 1,566,600.00
Perlengkapan 6.00% Harga Kloset 1,566,600.00 93,996.00
Pekerja 3.3000 HOK 35,000.00 115,500.00
Tukang batu 1.1000 HOK 45,000.00 49,500.00
Kepala tukang 0.0010 HOK 50,000.00 50.00
Mandor 0.1600 HOK 50,000.00 8,000.00
Total 173,050.00 1,660,596.00
Total Harga 1,833,646.00
Keuntungan 275,046.90
Jumlah Total 2,108,692.90

J-02 MEMASANG 1 BUAH KLOSET JONGKOK PORSELIN


Kloset jongkok porselin 1.0000 Bh 110,000.00 110,000.00
Semen Portland 6.0000 Kg 1,090.00 6,540.00
Pasir pasang 0.0100 m3 85,000.00 850.00
Pekerja 1.0000 HOK 35,000.00 35,000.00
Tukang batu 1.5000 HOK 45,000.00 67,500.00
Kepala tukang 1.5000 HOK 50,000.00 75,000.00
Mandor 0.1600 HOK 50,000.00 8,000.00
Total 185,500.00 117,390.00
Total Harga 302,890.00
Keuntungan 45,433.50
Jumlah Total 348,323.50

J-04 MEMASANG 1 BUAH URINOIR


Urinoir 1.0000 Bh 662,600.00 662,600.00
Perlengkapan 30.0% Urinoir 662,600.00 198,780.00
Semen Portland 6.0000 Kg 1,090.00 6,540.00
Pasir pasang 0.0100 m3 85,000.00 850.00
Pekerja 1.0000 HOK 35,000.00 35,000.00
Tukang batu 1.0000 HOK 45,000.00 45,000.00
Kepala tukang 0.1000 HOK 50,000.00 5,000.00
Mandor 0.1000 HOK 50,000.00 5,000.00
Total 90,000.00 868,770.00
a b c d e f=(cxe) g=(cxe) h 5495470000
Total Harga 958,770.00
Keuntungan 143,815.50
Jumlah Total 1,102,585.50

J-05 MEMASANG 1 BUAH WASTAFEL


Wastafel 1.0000 Bh 368,600.00 368,600.00
Perlengkapan 12.0% wastafel 368,600.00 44,232.00
Semen Abu-abu 6.0000 Kg 7,000.00 42,000.00
Pasir pasang 0.0100 m3 85,000.00 850.00
Pekerja 1.2000 HOK 35,000.00 42,000.00
Tukang batu 1.4500 HOK 45,000.00 65,250.00
Kepala tukang 0.1500 HOK 50,000.00 7,500.00
Mandor 0.1000 HOK 50,000.00 5,000.00
Total 119,750.00 455,682.00
Total Harga 575,432.00
Keuntungan 86,314.80
Jumlah Total 661,746.80

J-07 MEMASANG 1 BUAH BAK MANDI FIBREGLASS 0,30M3


Bak fibreglass 1.0000 Bh 120,000.00 120,000.00
Perlengkapan 18.0% Hrg Bak 120,000.00 21,600.00
Pembantu tukang 1.8000 HOK 35,000.00 63,000.00
Tukang batu 2.7000 HOK 45,000.00 121,500.00
Kepala tukang 0.5400 HOK 50,000.00 27,000.00
Mandor 0.1100 HOK 50,000.00 5,500.00
Total 217,000.00 141,600.00
Total Harga 358,600.00
Keuntungan 53,790.00
Jumlah Total 412,390.00

J-08 MEMASANG 1 BUAH BAK MANDI BATU BATA VOLUME 0,30 M3


Batu bata 0.4000 m3 550.00 220.00
Semen Portland 120.0000 Kg 1,090.00 130,800.00
Pasir pasang 0.3000 m3 85,000.00 25,500.00
Porselen (11x11) cm 360.0000 Bh 0.00
Semen nat 6.0000 Kg 7,000.00 42,000.00
Pekerja 6.0000 HOK 35,000.00 210,000.00
Tukang batu 3.0000 HOK 45,000.00 135,000.00
Kepala tukang 0.3000 HOK 50,000.00 15,000.00
Mandor 0.3000 HOK 50,000.00 15,000.00
Total 375,000.00 198,520.00
Total Harga 573,520.00
Keuntungan 86,028.00
Jumlah Total 659,548.00

J-09 MEMASANG 1 BUAH BADKIP PERSELEN


Badkip 1.0000 bh 0.00
Perlengkapan 20.0% Badkip 0.00
Pekerja - HOK
Tukang batu 0.0750 HOK
Kepala tukang 0.7500 HOK
Mandor 0.2500 HOK
Total 0.00 0.00
Total Harga -
Keuntungan -
Jumlah Total -

J-10 MEMBUAT 1 BUAH BAK BETON 1 M3 AIR


Beton 1 : 1.5 : 2.5 0.9000 m3 0.00
Besi beton 180.0000 Kg 0.00
Kayu cetakan 8.0000 m2 0.00
Ubin porselen 5.0000 m2 0.00
Perlengkapan 10.0% Tot bahan 0.00
Pekerja 3.5000 HOK 0.00
Tukang batu 4.5000 HOK 0.00
Kepala tukang 0.9000 HOK 0.00
Mandor 0.9000 HOK 0.00
a b c d e f=(cxe) g=(cxe) h 5495470000
Total 0.00 0.00
Total Harga -
Keuntungan -
Jumlah Total -

J-11 MEMASANG 1 BUAH BAK FIBREGLASS VOLUME 1M3 AIR


Bak fibreglass 1.0000 bh 0.00
Perlengkapan 12.0% Badkip 0.00
Pekerja 3.0000 HOK 0.00
Tukang batu 4.5000 HOK 0.00
Kepala tukang 0.9000 HOK 0.00
Mandor 0.9000 HOK 0.00
Total 0.00 0.00
Total Harga -
Keuntungan -
Jumlah Total -

J-14 MEMASANG 1 METER PIPA BETON, Ø 15-20 CM


Pipa beton 1.1000 bh 0.00
Batu bata 0.0270 m3 0.00
Semen Portland 3.9200 Kg 0.00
Pasir Pasang 0.0560 m3 0.00
Pasir Urug 0.2400 m3 0.00
Pekerja 0.1400 HOK 0.00
Tukang batu 0.0700 HOK 0.00
Kepala tukang 0.0070 HOK 0.00
Mandor 0.0070 HOK 0.00
Total 0.00 0.00
Total Harga -
Keuntungan -
Jumlah Total -

J-15 MEMASANG 1 METER PIPA BETON, Ø 30-100 CM


Pipa beton 1.1000 bh 0.00 0.00
Batu bata 0.0550 m3 0.00 0.00
Semen Portland 10.3000 Kg 0.00 0.00
Pasir Pasang 0.0610 m3 0.00 0.00
Pasir Urug 0.0690 m3 0.00 0.00
Pekerja 0.3800 HOK 0.00 0.00
Tukang batu 0.1900 HOK 0.00 0.00
Kepala tukang 0.0190 HOK 0.00 0.00
Mandor 0.0190 HOK 0.00 0.00
Total 0.00 0.00
Total Harga -
Keuntungan -
Jumlah Total -

J-16 MEMASANG 1 BUAH BAK KONTROL PASANGAN BATU BATA (30X30) CM TINGGI 35 CM
Batu bata 0.1450 m3 0.00
Semen Portland 44.0000 Kg 0.00
Pasir Pasang 0.0700 m3 0.00
Batu kerikil 0.0700 m3 0.00
Besi beton 1.6000 Kg 0.00
Pasir beton 0.0600 m3 0.00
Pekerja 3.2000 HOK 0.00
Tukang batu 1.0150 HOK 0.00
Kepala tukang 0.0015 HOK 0.00
Mandor 0.0160 HOK 0.00
Total 0.00 0.00
Total Harga -
Keuntungan -
Jumlah Total -

J-17 MEMASANG 1 BUAH BAK KONTROL PASANGAN BATU BATA (45X45) CM TINGGI 50 CM
Batu bata 0.2500 m3 0.00 0.00
Semen Portland 77.0000 Kg 0.00 0.00
Pasir Pasang 0.1300 m3 0.00 0.00
a b c d e f=(cxe) g=(cxe) h 5495470000
Batu kerikil 0.0200 m3 0.00 0.00
Besi beton 2.6000 Kg 0.00 0.00
Pasir beton 0.0900 m3 0.00 0.00
Pekerja 1.4200 HOK 0.00 0.00
Tukang batu 0.4730 HOK 0.00 0.00
Kepala tukang 0.0470 HOK 0.00 0.00
Mandor 0.0710 HOK 0.00 0.00
Total 0.00 0.00
Total Harga -
Keuntungan -
Jumlah Total -

J-18 MEMASANG 1 BUAH BAK KONTROL PASANGAN BATU BATA (60x60) CM TINGGI 65 CM
Batu bata 0.3710 m3 0.00
Semen Portland 114.0000 Kg 0.00
Pasir Pasang 0.1840 m3 0.00
Batu koral 0.0330 m3 0.00
Besi beton 4.8500 Kg 0.00
Pasir beton 0.1200 m3 0.00
Pekerja 2.1600 HOK 0.00
Tukang batu 0.7200 HOK 0.00
Tukang gali 0.1000 HOK 0.00
Kepala tukang 0.0720 HOK 0.00
Mandor 0.1080 HOK 0.00
Total 0.00 0.00
Total Harga -
Keuntungan -
Jumlah Total -

J-19 MEMASANG 1 METER PIPA GALVANIS Ø 1/2"


Pipa galvanis 1.2000 m' 15,800.00 18,960.00
Perlengkapan 35.0% Hrg-pipa 5,530.00 1,935.50
Pekerja 0.0540 HOK 35,000.00 1,890.00
Tukang batu 0.0900 HOK 45,000.00 4,050.00
Kepala tukang 0.0090 HOK 50,000.00 450.00
Mandor 0.0270 HOK 50,000.00 1,350.00
Total 7,740.00 20,895.50
Total Harga 28,635.50
Keuntungan 4,295.33
Jumlah Total 32,930.83

J-20 MEMASANG 1 METER PIPA GALVANIS Ø 3/4"


Pipa galvanis 1.2000 m' 20,000.00 24,000.00
Perlengkapan 35.0% Hrg-pipa 7,000.00 2,450.00
Pekerja 0.0540 HOK 35,000.00 1,890.00
Tukang batu 0.0900 HOK 45,000.00 4,050.00
Kepala tukang 0.0090 HOK 50,000.00 450.00
Mandor 0.0270 HOK 50,000.00 1,350.00
Total 7,740.00 26,450.00
Total Harga 34,190.00
Keuntungan 5,128.50
Jumlah Total 39,318.50

J-21 MEMASANG 1 METER PIPA GALVANIS Ø 1"


Pipa galvanis 1.2000 m' 26,300.00 31,560.00
Perlengkapan 35.0% Hrg-pipa 9,205.00 3,221.75
Pekerja 0.0540 HOK 35,000.00 1,890.00
Tukang batu 0.0900 HOK 45,000.00 4,050.00
Kepala tukang 0.0090 HOK 50,000.00 450.00
Mandor 0.0270 HOK 50,000.00 1,350.00
Total 7,740.00 34,781.75
Total Harga 42,521.75
Keuntungan 6,378.26
Jumlah Total 48,900.01

J-22 MEMASANG 1 METER PIPA GALVANIS Ø 1 1/2"


Pipa galvanis 1.2000 m' 38,900.00 46,680.00
a b c d e f=(cxe) g=(cxe) h 5495470000
Perlengkapan 35.0% Hrg-pipa 38,900.00 13,615.00
Pekerja 0.1080 HOK 35,000.00 3,780.00
Tukang batu 0.1800 HOK 45,000.00 8,100.00
Kepala tukang 0.0180 HOK 50,000.00 900.00
Mandor 0.0054 HOK 50,000.00 270.00
Total 13,050.00 60,295.00
Total Harga 73,345.00
Keuntungan 11,001.75
Jumlah Total 84,346.75

J-23 MEMASANG 1 METER PIPA GALVANIS Ø 3"


Pipa galvanis 1.2000 m' 0.00
Perlengkapan 35.0% Hrg-pipa 0.00
Pekerja 0.1080 HOK 0.00
Tukang batu 0.1800 HOK 0.00
Kepala tukang 0.0180 HOK 0.00
Mandor 0.0054 HOK 0.00
Total 0.00 0.00
Total Harga -
Keuntungan -
Jumlah Total -

J-24 MEMASANG 1 METER PIPA GALVANIS Ø 4"


Pipa galvanis 1.2000 m' 0.00 0.00
Perlengkapan 35.0% Hrg-pipa 0.00 0.00
Pekerja 0.1350 HOK 35,000.00 4,725.00
Tukang batu 0.2250 HOK 45,000.00 10,125.00
Kepala tukang 0.0225 HOK 50,000.00 1,125.00
Mandor 0.0068 HOK 50,000.00 340.00
Total 16,315.00 0.00
Total Harga 16,315.00
Keuntungan 2,447.25
Jumlah Total 18,762.25

J-25 MEMASANG 1 METER PIPA PVC TIPE AW Ø 1/2"


Pipa PVC 1.2000 m' 2,250.00 2,700.00
Perlengkapan 35.0% Hrg-pipa 787.50 275.63
Pekerja 0.0360 HOK 35,000.00 1,260.00
Tukang batu 0.0600 HOK 45,000.00 2,700.00
Kepala tukang 0.0060 HOK 50,000.00 300.00
Mandor 0.0018 HOK 50,000.00 90.00
Total 4,350.00 2,975.63
Total Harga 7,325.63
Keuntungan 1,098.84
Jumlah Total 8,424.47

J-26 MEMASANG 1 METER PIPA PVC TIPE AW Ø 3/4"


Pipa PVC 1.2000 m' 3,125.00 3,750.00
Perlengkapan 35.0% Hrg-pipa 1,093.75 382.81
Pekerja 0.0360 HOK 35,000.00 1,260.00
Tukang batu 0.0600 HOK 45,000.00 2,700.00
Kepala tukang 0.0060 HOK 50,000.00 300.00
Mandor 0.0018 HOK 50,000.00 90.00
Total 4,350.00 4,132.81
Total Harga 8,482.81
Keuntungan 1,272.42
Jumlah Total 9,755.23

J-27 MEMASANG 1 METER PIPA PVC TIPE AW Ø 1"


Pipa PVC 1.2000 m' 3,750.00 4,500.00
Perlengkapan 35.0% Hrg-pipa 1,312.50 459.38
Pekerja 0.0360 HOK 35,000.00 1,260.00
Tukang batu 0.0600 HOK 45,000.00 2,700.00
Kepala tukang 0.0060 HOK 50,000.00 300.00
Mandor 0.0018 HOK 50,000.00 90.00
Total 4,350.00 4,959.38
Total Harga 9,309.38
a b c d e f=(cxe) g=(cxe) h 5495470000
Keuntungan 1,396.41
Jumlah Total 10,705.78

J-28 MEMASANG 1 METER PIPA PVC TIPE AW Ø 1 1/2"


Pipa PVC 1.2000 m' 1,562.50 1,875.00
Perlengkapan 35.0% Hrg-pipa 546.88 191.41
Pekerja 0.0360 HOK 35,000.00 1,260.00
Tukang batu 0.0600 HOK 45,000.00 2,700.00
Kepala tukang 0.0060 HOK 50,000.00 300.00
Mandor 0.0018 HOK 50,000.00 90.00
Total 4,350.00 2,066.41
Total Harga 6,416.41
Keuntungan 962.46
Jumlah Total 7,378.87

J-29 MEMASANG 1 METER PIPA PVC TIPE AW Ø 2"


Pipa PVC 1.2000 m' 1,781.25 2,137.50
Perlengkapan 35.0% Hrg-pipa 623.44 218.20
Pekerja 0.0540 HOK 35,000.00 1,890.00
Tukang batu 0.0900 HOK 45,000.00 4,050.00
Kepala tukang 0.0090 HOK 50,000.00 450.00
Mandor 0.0027 HOK 50,000.00 135.00
Total 6,525.00 2,355.70
Total Harga 8,880.70
Keuntungan 1,332.11
Jumlah Total 10,212.81

J-30 MEMASANG 1 METER PIPA PVC TIPE AW Ø 2 1/2"


Pipa PVC 1.2000 m' 9,000.00 10,800.00
Perlengkapan 35.0% Hrg-pipa 3,150.00 1,102.50
Pekerja 0.0360 HOK 35,000.00 1,260.00
Tukang batu 0.0600 HOK 45,000.00 2,700.00
Kepala tukang 0.0060 HOK 50,000.00 300.00
Mandor 0.0018 HOK 50,000.00 90.00
Total 4,350.00 11,902.50
Total Harga 16,252.50
Keuntungan 2,437.88
Jumlah Total 18,690.38

J-31 MEMASANG 1 METER PIPA PVC TIPE AW Ø 3"


Pipa PVC 1.2000 m' 10,500.00 12,600.00
Perlengkapan 35.0% Hrg-pipa 3,675.00 1,286.25
Pekerja 0.0810 HOK 35,000.00 2,835.00
Tukang batu 0.1350 HOK 45,000.00 6,075.00
Kepala tukang 0.0135 HOK 50,000.00 675.00
Mandor 0.0041 HOK 50,000.00 205.00
Total 9,790.00 13,886.25
Total Harga 23,676.25
Keuntungan 3,551.44
Jumlah Total 27,227.69

J-32 MEMASANG 1 METER PIPA PVC TIPE AW Ø 4"


Pipa PVC 1.2000 m' 13,250.00 15,900.00
Perlengkapan 35.0% Hrg-pipa 4,637.50 1,623.13
Pekerja 0.0810 HOK 35,000.00 2,835.00
Tukang batu 0.1350 HOK 45,000.00 6,075.00
Kepala tukang 0.0135 HOK 50,000.00 675.00
Mandor 0.0041 HOK 50,000.00 205.00
Total 9,790.00 17,523.13
Total Harga 27,313.13
Keuntungan 4,096.97
Jumlah Total 31,410.09

J-33 MEMASANG 1 BUAH BAK CUCI PIRING STAINLESS-STEEL


Bak cuci stainles steel 1.0000 Bh 0.00
Water drain + asesories 1.0000 Set 0.00
Pekerja 0.0300 HOK 0.00
a b c d e f=(cxe) g=(cxe) h 5495470000
Tukang batu 0.3000 HOK 0.00
Kepala tukang 0.0300 HOK 0.00
Mandor 0.0015 HOK 0.00
Total 0.00 0.00
Total Harga -
Keuntungan -
Jumlah Total -

J-35 MEMASANG 1 BUAH KRAN Ø 1/2" ATAU Ø 3/4"


Kran air 1.0000 Bh 13,500.00 13,500.00
Seal tape 0.0250 Set 1,800.00 45.00
Pekerja 0.0100 HOK 35,000.00 350.00
Tukang batu 0.1000 HOK 45,000.00 4,500.00
Kepala tukang 0.0100 HOK 50,000.00 500.00
Mandor 0.0050 HOK 50,000.00 250.00
Total 5,600.00 13,545.00
Total Harga 19,145.00
Keuntungan 2,871.75
Jumlah Total 22,016.75

J-36 MEMASANG 1 BUAH FLOOR DRAIN


Floor drain 1.0000 Bh 18,000.00 18,000.00
Pekerja 0.0100 HOK 35,000.00 350.00
Tukang batu 0.1000 HOK 45,000.00 4,500.00
Kepala tukang 0.0100 HOK 50,000.00 500.00
Mandor 0.0050 HOK 50,000.00 250.00
Total 5,600.00 18,000.00
Total Harga 23,600.00
Keuntungan 3,540.00
Jumlah Total 27,140.00
DIHITUNG 1 M' SALURAN GRAFEL BETON 1/2 Ø 20 cm + PASANGAN (A137)
Galian Tanah 0.1500 m3 16,000.00 2,400.00
Grafel beton Ø 20 cm 1.0000 Bh 15,000.00 15,000.00
Pasangan bata + Plesteran 1 : 5 1.0000 m 72,834.93 72,834.93
Upah kerja 0.3500 Ls 500.00 175.00
Total 175.00 90,234.93
Total Harga 90,409.93
Keuntungan 13,561.49
Jumlah Total 103,971.42
DIHITUNG 1 M' SALURAN GRAFEL BETON 1/2 Ø 20 cm + PASANGAN Pas. Bata Sebelah
Galian Tanah 0.1500 m3 16,000.00 2,400.00
Grafel beton Ø 20 cm 1.0000 Bh 15,000.00 15,000.00
Pasangan bata + Plesteran 1 : 5 1.0000 m 36,417.47 36,417.47
Upah kerja 0.3500 Ls 500.00 175.00
Total 175.00 53,817.47
Total Harga 53,992.47
Keuntungan 8,098.87
Jumlah Total 62,091.34

DIHITUNG 1 M' SALURAN GRAFEL BETON 1/2 Ø 30 cm + PASANGAN (A138)


Galian Tanah 0.2000 m3 0.00
Grafel beton Ø 30 cm 1.0000 Bh 0.00
Pasangan bata + Plesteran 1 : 3 1.0000 m 0.00
Upah kerja 0.3500 Ls 0.00
Total 0.00 0.00
Total Harga -
Keuntungan -
Jumlah Total -

DIHITUNG 1 UNIT SEPTICTANK 2.5 x 1.5 X 2 m (TYPE BESAR) + REMBESAN (A080)


Galian Tanah 7.5000 m3 0.00
Pasir urug 0.3570 m3 0.00
Lantai kerja 1 : 3 : 5 3.7500 m3 0.00
Pasangan bata + Plesteran 1 : 3 25.0000 m2 0.00
Plat beton penutup + balok 0.5000 m3 0.00
Pipa PVC 4" AW + sambungan 9.0000 m' 0.00
Pipa GIF 1 1/2" 2.0000 m' 0.00
a b c d e f=(cxe) g=(cxe) h 5495470000
Galian tanah untuk rembesan 5.6250 m3 0.00
Pasangan ijuk 9.0000 kg 0.00
Urugan kerikil 3.5 cm 1.7500 m3 0.00
Pipa PVC 4" AW berlobang 6.0000 m' 0.00
Urugan kembali perataan tanah 1.8750 m3 0.00
Tambahan upah kerja 0.0850 Ls 0.00
Total 0.00 0.00
Total Harga -
Keuntungan -
Jumlah Total -

DIHITUNG 1 UNIT SEPTICTANK 1.5 x 1.0 X 1.5 m (TYPE KECIL) + REMBESAN (A082)
Galian Tanah 2.2500 m3 0.00
Pasir urug 0.1071 m3 0.00
Lantai kerja 1 : 3 : 5 1.1250 m3 0.00
Pasangan bata + Plesteran 1 : 3 7.5000 m2 0.00
Plat beton penutup + balok 0.1500 m3 0.00
Pipa PVC 4" AW + sambungan 9.0000 m' 0.00
Pipa GIF 1 1/2" 0.6000 m' 0.00
Galian tanah untuk rembesan 1.6875 m3 0.00
Pasangan ijuk 2.7000 kg 0.00
Urugan kerikil 3.5 cm 0.5250 m3 0.00
Pipa PVC 4" AW berlobang 9.0000 m' 0.00
Urugan kembali perataan tanah 0.5625 m3 0.00
Tambahan upah kerja 0.0850 Ls 0.00
Total 0.00 0.00
Total Harga -
Keuntungan -
Jumlah Total -

K PEKERJAAN BESI DAN ALUMINIUM


K-01 1 Kg PASANG RANGKA ATAP BAJA
Besi profil WF 1.1000 Kg 0.00 0.00
Meni besi 0.0800 Kg 15,000.00 1,200.00
Pekerja 0.0600 HOK 35,000.00 2,100.00
Tukang besi 0.0060 HOK 43,500.00 261.00
Kepala tukang 0.0060 HOK 44,500.00 267.00
Mandor 0.0003 HOK 50,000.00 15.00
Total 2,643.00 1,200.00
Total Harga 3,843.00
Keuntungan 576.45
Jumlah Total 4,419.45

K-02 PASANG PINTU BESI BAJA


Pintu besi baja 1.0000 m2 0.00 0.00
Pekerja 0.6500 HOK 35,000.00 22,750.00
Tukang besi konstruksi 0.6500 HOK 43,500.00 28,275.00
Kepala tukang 0.0650 HOK 44,500.00 2,892.50
Mandor 0.0320 HOK 50,000.00 1,600.00
Total 55,517.50 0.00
Total Harga 55,517.50
Keuntungan 8,327.63
Jumlah Total 63,845.13

K-03 1 m2 PASANG JENDELA BESI


Jendela besi 1.0000 m2 0.00
Pekerja 1.0500 HOK 0.00
Tukang besi konstruksi 1.0500 HOK 0.00
Kepala tukang 0.1050 HOK 0.00
Mandor 0.00525 HOK 0.00
Total 0.00 0.00
Total Harga -
Keuntungan -
Jumlah Total -

K-05 1 m2 PASANG PINTU GULUNG BESI


a b c d e f=(cxe) g=(cxe) h 5495470000
Pintu gulung besi 1.0000 m2 0.00
Pekerja 1.2000 HOK 0.00
Tukang besi konstruksi 1.2000 HOK 0.00
Kepala tukang 0.1200 HOK 0.00
Mandor 0.0060 HOK 0.00
Total 0.00 0.00
Total Harga -

K-06 1 m2 PASANG PINTU LIPAT


Pintu lipat 1.0000 m2 0.00
Pekerja 1.0500 HOK 0.00
Tukang besi konstruksi 1.0500 HOK 0.00
Kepala tukang 0.1050 HOK 0.00
Mandor 0.0052 HOK 0.00
Total 0.00 0.00
Total Harga -

K-07 1 m2 PASANG PINTU SUNSCREEN ALLUMINIUM


Sunscreen alluminium 1.0000 m2 0.00
Pekerja 0.0800 HOK 0.00
Tukang besi konstruksi 0.8000 HOK 0.00
Kepala tukang 0.0800 HOK 0.00
Mandor 0.0040 HOK 0.00
Total 0.00 0.00
Total Harga -

K-08 1 m2 PASANG ROLLING DOOR


Roll door 1.0000 m2 0.00 0.00
Pekerja 1.0500 HOK 0.00 0.00
Tukang besi konstruksi 1.5000 HOK 0.00 0.00
Kepala tukang 0.1050 HOK 0.00 0.00
Mandor 0.0052 HOK 0.00 0.00
Total 0.00 0.00
Total Harga -
Keuntungan -
Jumlah Total -

K-09 1 m2 PASANG PINTU ALUMUNIUM


Pintu Allumunium 1.0000 m2 0.00 0.00
Pekerja 1.0500 HOK 0.00 0.00
Tukang besi konstruksi 1.0500 HOK 0.00 0.00
Kepala tukang 0.1050 HOK 0.00 0.00
Mandor 0.0052 HOK 0.00 0.00
Total 0.00 0.00
Total Harga -
Keuntungan -
Jumlah Total -

K-12 1 m2 PASANG TERALI BESI


Besi strip 2x3 11.0000 m' 0.00 0.00
Pekerja 1.2000 HOK 0.00 0.00
Tukang las 1.2000 HOK 0.00 0.00
Kepala tukang 0.0120 HOK 0.00 0.00
Mandor 0.0006 HOK 0.00 0.00
Total 0.00 0.00
Total Harga -
Keuntungan -
Jumlah Total -

K-18 1 m' PASANG TALANG DATAR, SENG BJLS 28


Seng plat 3' x 6' BJLS 28 0.5000 Lbr 0.00 0.00
Paku biasa 1/2" - 1" 0.0150 Kg 11,000.00 165.00
Kayu borneo, papan 0.0096 m3 5,217,300.00 50,086.08
Flincote /meni besi 0.2500 Kg 15,000.00 3,750.00
Pekerja 0.1500 HOK 35,000.00 5,250.00
Tukang kayu 0.4000 HOK 45,000.00 18,000.00
Kepala tukang 0.0250 HOK 50,000.00 1,250.00
a b c d e f=(cxe) g=(cxe) h 5495470000
Mandor 0.00125 HOK 50,000.00 62.50
Total 24,562.50 54,001.08
Total Harga 78,563.58
Keuntungan 11,784.54
Jumlah Total 90,348.12

K-19 1 m' PASANG TALANG MIRING, SENG BJLS 28


Seng plat 3' x 6' BJLS 28 0.5000 Lbr 0.00 0.00
Paku biasa 1/2" - 1" 0.0150 Kg 11,000.00 165.00
Kayu borneo, papan 0.0190 m3 2,200,000.00 41,800.00
Flincote /meni besi 0.3000 Kg 15,000.00 4,500.00
Pekerja 0.0400 HOK 35,000.00 1,400.00
Tukang kayu 0.4000 HOK 45,000.00 18,000.00
Kepala tukang 0.0250 HOK 50,000.00 1,250.00
Mandor 0.00125 HOK 50,000.00 62.50
Total 20,712.50 46,465.00
Total Harga 67,177.50
Keuntungan 10,076.63
Jumlah Total 77,254.13

K-20 1 m' PASANG TALANG 1/2 LINGKARAN Ø10 cm, SENG BJLS 28
Seng plat 3' x 6' BJLS 28 0.3000 Lbr 0.00 0.00
Paku biasa 1/2" - 1" 0.1000 Kg 11,000.00 1,100.00
Kayu borneo, papan 0.0190 m3 2,200,000.00 41,800.00
Besi strip 0.5000 Kg 11,000.00 5,500.00
Pekerja 0.1500 HOK 35,000.00 5,250.00
Tukang kayu 0.2500 HOK 45,000.00 11,250.00
Kepala tukang 0.0250 HOK 50,000.00 1,250.00
Mandor 0.00125 HOK 50,000.00 62.50
Total 17,812.50 48,400.00
Total Harga 66,212.50
Keuntungan 9,931.88
Jumlah Total 76,144.38
Dihitung 1 Kg BESI
Besi Profil 1.0500 Kg 12,500.00 13,125.00
Pekerja 0.0600 Kg 35,000.00 2,100.00
Tukang Besi Profil Terampil 0.0040 HOK 43,500.00 174.00
Kepala Tukang Besi Profil 0.0010 HOK 44,500.00 44.50
Mandor 0.0002 HOK 50,000.00 10.00
Peralatan (O2,Solar, Elpiji, kawat las dll) 0.1250 HOK 23,187.50 2,898.44

Total 3,126.94 15,225.00


Total Harga 18,351.94
Keuntungan 2,752.79
Jumlah Total 21,104.73
L PEKERJAAN KUNCI DAN KACA
L-01 1 BUAH PASANG KUNCI TANAM ANTIK
Kunci tanam antik 1.0000 bh 35,000.00 35,000.00
Pekerja 0.0600 HOK 35,000.00 2,100.00
Tukang kayu 0.6000 HOK 45,000.00 27,000.00
Kepala tukang 0.0600 HOK 50,000.00 3,000.00
Mandor 0.0030 HOK 50,000.00 150.00
Total 32,250.00 35,000.00
Total Harga 67,250.00
Keuntungan 10,087.50
Jumlah Total 77,337.50

L-02 1 BUAH PASANG KUNCI TANAM BIASA


Kunci tanam biasa 1.0000 bh 78,000.00 78,000.00
Pekerja 0.0100 HOK 35,000.00 350.00
Tukang kayu 0.5000 HOK 45,000.00 22,500.00
Kepala tukang 0.0100 HOK 50,000.00 500.00
Mandor 0.0050 HOK 50,000.00 250.00
Total 23,600.00 78,000.00
Total Harga 101,600.00
Keuntungan
Jumlah Total 101,600.00
a b c d e f=(cxe) g=(cxe) h 5495470000

L-03 1 BUAH PASANG KUNCI TANAM KAMAR MANDI


Kunci tanam kamar mandi 1.0000 bh 78,000.00 78,000.00
Pekerja 0.0050 HOK 35,000.00 175.00
Tukang kayu 0.5000 HOK 45,000.00 22,500.00
Kepala tukang 0.0050 HOK 50,000.00 250.00
Mandor 0.0025 HOK 50,000.00 125.00
Total 23,050.00 78,000.00
Total Harga 101,050.00
Keuntungan 15,157.50
Jumlah Total 116,207.50

L-04 1 BUAH PASANG KUNCI SILINDER


Kunci silinder 1.0000 bh 35,000.00 35,000.00
Pekerja 0.0050 HOK 35,000.00 175.00
Tukang kayu 0.5000 HOK 45,000.00 22,500.00
Kepala tukang 0.0050 HOK 50,000.00 250.00
Mandor 0.00025 HOK 50,000.00 12.50
Total 22,937.50 35,000.00
Total Harga 57,937.50
Keuntungan 8,690.63
Jumlah Total 66,628.13

L-05 1 BUAH PASANG ENGSEL PINTU


Engsel pintu 1.0000 bh 12,500.00 12,500.00
Pekerja 0.0150 HOK 35,000.00 525.00
Tukang kayu 0.1500 HOK 45,000.00 6,750.00
Kepala tukang 0.0150 HOK 50,000.00 750.00
Mandor 0.00075 HOK 50,000.00 37.50
Total 8,062.50 12,500.00
Total Harga 20,562.50
Keuntungan
Jumlah Total 20,562.50
a b c d e f=(cxe) g=(cxe) h 5495470000

L-06 1 BUAH PASANG ENGSEL JENDELA KUPU-KUPU


Engsel jendela 1.0000 bh 7,200.00 7,200.00
Pekerja 0.0100 HOK 35,000.00 350.00
Tukang kayu 0.1000 HOK 45,000.00 4,500.00
Kepala tukang 0.0100 HOK 50,000.00 500.00
Mandor 0.0005 HOK 50,000.00 25.00
Total 5,375.00 7,200.00
Total Harga 12,575.00
Keuntungan
Jumlah Total 12,575.00

L-07 1 BUAH PASANG ENGSEL ANGIN


Engsel angin 1.0000 bh 7,200.00 7,200.00
Pekerja 0.0200 HOK 35,000.00 700.00
Tukang kayu 0.2000 HOK 45,000.00 9,000.00
Kepala tukang 0.0200 HOK 50,000.00 1,000.00
Mandor 0.01000 HOK 50,000.00 500.00
Total 11,200.00 7,200.00
Total Harga 18,400.00
Keuntungan 2,760.00
Jumlah Total 21,160.00

L-09 1 BUAH PASANG KAIT ANGIN


Kait angin 1.0000 bh 8,500.00 8,500.00
Pekerja 0.0150 HOK 35,000.00 525.00
Tukang kayu 0.1500 HOK 45,000.00 6,750.00
Kepala tukang 0.0150 HOK 50,000.00 750.00
Mandor 0.00075 HOK 50,000.00 37.50
Total 8,062.50 8,500.00
Total Harga 16,562.50
Keuntungan
Jumlah Total 16,562.50

L-11 1 BUAH PASANG KUNCI SELOT


Kunci selot 1.0000 bh 3,500.00 3,500.00
Pekerja 0.0200 HOK 35,000.00 700.00
Tukang kayu 0.2000 HOK 45,000.00 9,000.00
Kepala tukang 0.0200 HOK 50,000.00 1,000.00
Mandor 0.0010 HOK 50,000.00 50.00
Total 10,750.00 3,500.00
Total Harga 14,250.00
Keuntungan
Jumlah Total 14,250.00

L-12 1 BUAH PASANG PEGANGAN PINTU / DOOR HOLDER


Door holder 1.0000 bh 52,500.00 52,500.00
Pekerja 0.0500 HOK 35,000.00 1,750.00
Tukang kayu 0.5000 HOK 45,000.00 22,500.00
Kepala tukang 0.0500 HOK 50,000.00 2,500.00
Mandor 0.0025 HOK 50,000.00 125.00
Total 26,875.00 52,500.00
Total Harga 79,375.00
Keuntungan 11,906.25
Jumlah Total 91,281.25

L-14 1 BUAH PASANG REL PINTU DORONG


Rel pintu dorong 1.0000 bh 441,300.00 441,300.00
Pekerja 0.0600 HOK 35,000.00 2,100.00
Tukang kayu 0.6000 HOK 45,000.00 27,000.00
Kepala tukang 0.0600 HOK 50,000.00 3,000.00
Mandor 0.0030 HOK 50,000.00 150.00
Total 32,250.00 441,300.00
Total Harga 473,550.00
Keuntungan 71,032.50
Jumlah Total 544,582.50
a b c d e f=(cxe) g=(cxe) h 5495470000
L-15 1 BUAH PASANG KUNCI LEMARI
Kunci lemari 1.0000 Bh 13,100.00 13,100.00
Pekerja 0.0250 HOK 35,000.00 875.00
Tukang kayu 0.2500 HOK 45,000.00 11,250.00
Kepala tukang 0.0250 HOK 50,000.00 1,250.00
Mandor 0.00125 HOK 50,000.00 62.50
Total 13,437.50 13,100.00
Total Harga 26,537.50
Keuntungan 3,980.63
Jumlah Total 30,518.13

L-16 1 m2 PASANG KACA TEBAL 3 mm


Kaca 1.1000 M2 48,000.00 52,800.00
Pekerja 0.0150 HOK 35,000.00 525.00
Tukang kayu 0.1500 HOK 45,000.00 6,750.00
Kepala tukang 0.0150 HOK 50,000.00 750.00
Mandor 0.00075 HOK 50,000.00 37.50
Total 8,062.50 52,800.00
Total Harga 60,862.50
Keuntungan
Jumlah Total 60,862.50

L-17 1 m2 BUAH PASANG KACA TEBAL 5 mm


Kaca 1.1000 bh 65,000.00 71,500.00
Pekerja 0.0150 HOK 35,000.00 525.00
Tukang kayu 0.1500 HOK 45,000.00 6,750.00
Kepala tukang 0.0150 HOK 50,000.00 750.00
Mandor 0.00075 HOK 50,000.00 37.50
Total 8,062.50 71,500.00
Total Harga 79,562.50
Keuntungan 11,934.38
Jumlah Total 91,496.88

L-18 1 m2 BUAH PASANG KACA TEBAL 8 mm


Kaca polos 1.1000 bh 0.00
Pekerja 0.0165 HOK 0.00
Tukang kayu 0.1650 HOK 0.00
Kepala tukang 0.0165 HOK 0.00
Mandor 0.00080 HOK 0.00
Total 0.00 0.00
Total Harga -

L-20 1 m2 BUAH PASANG KACA CERMIN TEBAL 3 mm


Kaca cermin 1.1000 bh 0.00
Pekerja 0.0150 HOK 0.00
Tukang kayu 0.1500 HOK 0.00
Kepala tukang 0.0150 HOK 0.00
Mandor 0.00075 HOK 0.00
Total 0.00 0.00
Total Harga -

L-23 1 m2 BUAH PASANG KACA WIREGLASS TEBAL 5 mm


Kaca wireglass 1.1000 bh 0.00
Pekerja 0.0150 HOK 0.00
Tukang kayu 0.1500 HOK 0.00
Kepala tukang 0.0150 HOK 0.00
Mandor 0.00075 HOK 0.00
Total 0.00 0.00
Total Harga -

L-24 1 m2 BUAH PASANG KACA PATRI TEBAL 5 mm


Kaca wireglass 1.1000 bh 0.00
Pekerja 0.0150 HOK 0.00
Tukang kayu 0.1500 HOK 0.00
Kepala tukang 0.0150 HOK 0.00
Mandor 0.00075 HOK 0.00
Total 0.00 0.00
a b c d e f=(cxe) g=(cxe) h 5495470000
Total Harga -

M PEKERJAAN PENUTUP LANTAI DAN DINDING

M-02 1 m2 PASANG LANTAI UBIN PC ABU-ABU UKURAN 30X30 cm


Ubin abu-abu 30x30 cm 11.8700 bh 1,600.00 18,992.00
Semen Portland 10.0000 Kg 1,090.00 10,900.00
Pasir pasang 0.0215 m3 85,000.00 1,827.50
Pekerja 0.2600 HOK 35,000.00 9,100.00
Tukang batu 0.1250 HOK 45,000.00 5,625.00
Kepala tukang 0.0125 HOK 50,000.00 625.00
Mandor 0.0130 HOK 50,000.00 650.00
Total 16,000.00 31,719.50
Total Harga 47,719.50
Keuntungan 7,157.93
Jumlah Total 54,877.43

M-03 1 m2 PASANG LANTAI UBIN PC ABU-ABU UKURAN 20X20 cm


Ubin abu-abu 20x20 cm 26.5000 bh 0.00
Semen Portland 10.4000 Kg 0.00
Pasir pasang 0.0135 m3 0.00
Pekerja 0.2700 HOK 0.00
Tukang batu 0.1300 HOK 0.00
Kepala tukang 0.0130 HOK 0.00
Mandor 0.0135 HOK 0.00
Total 0.00 0.00
Total Harga -
Keuntungan -
Jumlah Total -

M-05 1 m2 PASANG LANTAI UBIN PC WARNA UKURAN 30X30 cm


Ubin warna 30x30 cm 11.8700 bh 0.00
Semen Portland 8.3600 Kg 0.00
Pasir pasang 0.0230 m3 0.00
Semen warna 0.9000 Kg 0.00
Pekerja 0.2500 HOK 0.00
Tukang batu 0.1200 HOK 0.00
Kepala tukang 0.0120 HOK 0.00
Mandor 0.0125 HOK 0.00
Total 0.00 0.00
Total Harga -
Keuntungan -
Jumlah Total -

M-06 1 m2 PASANG LANTAI UBIN PC WARNA UKURAN 20X20 cm


Ubin warna 20x20 cm 26.5000 bh 0.00
Semen Portland 8.7600 Kg 0.00
Pasir pasang 0.0230 m3 0.00
Semen warna 0.9000 Kg 0.00
Pekerja 0.2700 HOK 0.00
Tukang batu 0.1300 HOK 0.00
Kepala tukang 0.0130 HOK 0.00
Mandor 0.0135 HOK 0.00
Total 0.00 0.00
Total Harga -
Keuntungan -
Jumlah Total -

M-09 1 m2 PASANG LANTAI UBIN GRANITO UKURAN 40X40 cm


Ubin granito 40x40 cm 6.9300 bh 0.00
Semen Portland 9.8000 Kg 0.00
Pasir pasang 0.0215 m3 0.00
Semen warna 1.3000 Kg 0.00
Pekerja 0.2500 HOK 0.00
Tukang batu 0.1200 HOK 0.00
a b c d e f=(cxe) g=(cxe) h 5495470000
Kepala tukang 0.0120 HOK 0.00
Mandor 0.0125 HOK 0.00
Total 0.00 0.00
Total Harga -
Keuntungan -
Jumlah Total -

M-10 1 m2 PASANG LANTAI UBIN GRANITO UKURAN 30X30 cm


Ubin granito 30x30 cm 11.8700 bh 0.00
Semen Portland 10.0000 Kg 0.00
Pasir pasang 0.0215 m3 0.00
Semen warna 1.5000 Kg 0.00
Pekerja 0.2600 HOK 0.00
Tukang batu 0.1250 HOK 0.00
Kepala tukang 0.0125 HOK 0.00
Mandor 0.0130 HOK 0.00
Total 0.00 0.00
Total Harga -
Keuntungan -
Jumlah Total -

M-16 1 m2 PASANG PLINT UBIN PC ABU-ABU UKURAN 15X20 cm


Plin ubint 15x20 cm 5.3000 bh 0.00
Semen Portland 1.5600 Kg 0.00
Pasir pasang 0.0040 m3 0.00
Pekerja 0.0600 HOK 0.00
Tukang batu 0.0300 HOK 0.00
Kepala tukang 0.0030 HOK 0.00
Mandor 0.0030 HOK 0.00
Total 0.00 0.00
Total Harga -
Keuntungan -
Jumlah Total -

M-17 1 m' PASANG PLINT UBIN PC ABU-ABU UKURAN 10X30 cm


Plint ubin 10x30 cm 3.5300 bh 0.00
Semen Portland 1.5600 Kg 0.00
Pasir pasang 0.0030 m3 0.00
Pekerja 0.0600 HOK 0.00
Tukang batu 0.0300 HOK 0.00
Kepala tukang 0.0030 HOK 0.00
Mandor 0.0030 HOK 0.00
Total 0.00 0.00
Total Harga -
Keuntungan -
Jumlah Total -

M-19 1 m2 PASANG PLINT UBIN PC WARNA UKURAN 10X20 cm


Plin ubin pc warna 10x20 cm 5.3000 bh 0.00
Semen Portland 1.2000 Kg 0.00
Pasir pasang 0.0030 m3 0.00
Semen warna 0.1900 Kg
Pekerja 0.0600 HOK 0.00
Tukang batu 0.0300 HOK 0.00
Kepala tukang 0.0030 HOK 0.00
Mandor 0.0030 HOK 0.00
Total 0.00 0.00
Total Harga -
Keuntungan -
Jumlah Total -

M-25 1 m2 PASANG PLINT UBIN GRANITO UKURAN 10X30 cm


Plin ubin granito 10x30 cm 3.3300 bh 0.00
Semen Portland 1.6500 Kg 0.00
Pasir pasang 0.0032 m3 0.00
Semen warna 0.1000 Kg
a b c d e f=(cxe) g=(cxe) h 5495470000
Pekerja 0.9000 HOK 0.00
Tukang batu 0.0900 HOK 0.00
Kepala tukang 0.0090 HOK 0.00
Mandor 0.0045 HOK 0.00
Total 0.00 0.00
Total Harga -
Keuntungan -
Jumlah Total -

M-37 1 m' PASANG PLINT KERAMIK ARTISTIK UKURAN 10X20 cm


Plint keramik artistik 10x20 cm 5.0000 bh 0.00
Semen Portland 1.6500 Kg 0.00
Pasir pasang 0.0032 m3 0.00
Semen warna 0.1000 Kg 0.00
Pekerja 0.0900 HOK 0.00
Tukang batu 0.0900 HOK 0.00
Kepala tukang 0.0090 HOK 0.00
Mandor 0.0045 HOK 0.00
Total 0.00 0.00
Total Harga -
Keuntungan -
Jumlah Total -

M-42 1 m2 PASANG LANTAI KERAMIK 10X20 cm, WARNA ( Anti Selip )


Ubin keramik artistik 10x20 cm, anti selip 50.0000 bh 750.00 37,500.00
Semen Portland 0.2276 Kg 1,090.00 248.08
Pasir pasang 0.0420 m3 85,000.00 3,570.00
Semen warna 1.5000 Kg 7,000.00 10,500.00
Pekerja 0.6200 HOK 35,000.00 21,700.00
Tukang batu 0.3500 HOK 45,000.00 15,750.00
Kepala tukang 0.0350 HOK 50,000.00 1,750.00
Mandor 0.0300 HOK 50,000.00 1,500.00
Total 40,700.00 51,818.08
Total Harga 92,518.08
Keuntungan 13,877.71
Jumlah Total 106,395.80

M-43 1 m2 PASANG LANTAI KERAMIK 15X15 cm


Ubin keramik15x15 cm 44.0000 bh 852.27 37,500.00
Semen Portland 11.3800 Kg 1,090.00 12,404.20
Pasir pasang 0.0420 m3 85,000.00 3,570.00
Semen warna 1.5000 Kg 7,000.00 10,500.00
Pekerja 0.6200 HOK 35,000.00 21,700.00
Tukang batu 0.3500 HOK 45,000.00 15,750.00
Kepala tukang 0.0350 HOK 50,000.00 1,750.00
Mandor 0.0300 HOK 50,000.00 1,500.00
Total 40,700.00 63,974.20
Total Harga 104,674.20
Keuntungan 15,701.13
Jumlah Total 120,375.33

M-44 1 m2 PASANG LANTAI KERAMIK 20X20 cm


Ubin keramik 20x20 cm 25.0000 bh 1,600.00 40,000.00
Semen Portland 11.3800 Kg 1,090.00 12,404.20
Pasir pasang 0.0420 m3 85,000.00 3,570.00
Semen warna 1.5000 Kg 7,000.00 10,500.00
Pekerja 0.6200 HOK 35,000.00 21,700.00
Tukang batu 0.3500 HOK 45,000.00 15,750.00
Kepala tukang 0.0350 HOK 50,000.00 1,750.00
Mandor 0.0300 HOK 50,000.00 1,500.00
Total 40,700.00 66,474.20
Total Harga 107,174.20
Keuntungan 16,076.13
Jumlah Total 123,250.33
DIHITUNG 1 m2 PASANG LANTAI KERAMIK 20X25 cm
Ubin keramik 20x20 cm 20.0000 bh 1,500.00 30,000.00
Semen Portland 11.3800 Kg 1,090.00 12,404.20
a b c d e f=(cxe) g=(cxe) h 5495470000
Pasir pasang 0.0420 m3 85,000.00 3,570.00
Semen warna 1.5000 Kg 7,000.00 10,500.00
Pekerja 0.6200 HOK 35,000.00 21,700.00
Tukang batu 0.3500 HOK 45,000.00 15,750.00
Kepala tukang 0.0350 HOK 50,000.00 1,750.00
Mandor 0.0300 HOK 50,000.00 1,500.00
Total 40,700.00 56,474.20
Total Harga 97,174.20
Keuntungan 14,576.13
Jumlah Total 111,750.33

M-47 1 m2 PASANG LANTAI KERAMIK 33X33 cm


Ubin keramik 33x33 cm 10.0000 bh 2,850.00 28,500.00
Semen Portland 11.3800 Kg 1,090.00 12,404.20
Pasir pasang 0.0420 m3 85,000.00 3,570.00
Semen warna 1.5000 Kg 7,000.00 10,500.00
Pekerja 0.6200 HOK 35,000.00 21,700.00
Tukang batu 0.3500 HOK 45,000.00 15,750.00
Kepala tukang 0.0350 HOK 50,000.00 1,750.00
Mandor 0.0300 HOK 50,000.00 1,500.00
Total 40,700.00 54,974.20
Total Harga 95,674.20
Keuntungan 14,351.13
Jumlah Total 110,025.33

M-59 1 m2 PASANG DINDING PORSELIN 11X11 cm, WARNA


Porselin 11x11 cm, warna 83.0000 bh 481.93 40,000.00
Semen Abu-abu 9.3000 Kg 1,090.00 10,137.00
Pasir pasang 0.0180 m3 85,000.00 1,530.00
Semen warna 1.5000 Kg 7,000.00 10,500.00
Pekerja 0.6200 HOK 35,000.00 21,700.00
Tukang batu 0.5000 HOK 45,000.00 22,500.00
Kepala tukang 0.0500 HOK 50,000.00 2,500.00
Mandor 0.0300 HOK 50,000.00 1,500.00
Total 48,200.00 62,167.00
Total Harga 110,367.00
Keuntungan 16,555.05
Jumlah Total 126,922.05

M-62 1 m2 PASANG DINDING PORSELIN 10X20 cm, WARNA


Keramik 10x20 cm warna 50.0000 bh 750.00 37,500.00
Semen Abu-abu 9.3000 Kg 1,090.00 10,137.00
Pasir pasang 0.0180 m3 85,000.00 1,530.00
Semen warna 1.5000 Kg 7,000.00 10,500.00
Pekerja 0.6000 HOK 35,000.00 21,000.00
Tukang batu 0.4500 HOK 45,000.00 20,250.00
Kepala tukang 0.0450 HOK 50,000.00 2,250.00
Mandor 0.0300 HOK 50,000.00 1,500.00
Total 45,000.00 59,667.00
Total Harga 104,667.00
Keuntungan 15,700.05
Jumlah Total 120,367.05

M-64 1 m2 PASANG DINDING KERAMIK 10X20 cm


Keramik 10x20 cm 50.0000 bh 750.00 37,500.00
Semen Abu-abu 9.3000 Kg 1,090.00 10,137.00 ###
Pasir pasang 0.0180 m3 85,000.00 1,530.00
Semen warna 1.5000 Kg 7,000.00 10,500.00
Pekerja 0.6000 HOK 35,000.00 21,000.00
Tukang batu 0.4500 HOK 45,000.00 20,250.00
Kepala tukang 0.0450 HOK 50,000.00 2,250.00
Mandor 0.0300 HOK 50,000.00 1,500.00
Total 45,000.00 59,667.00
Total Harga 104,667.00
Keuntungan 15,700.05
Jumlah Total 120,367.05
a b c d e f=(cxe) g=(cxe) h 5495470000
M-67 1 m2 PASANG DINDING KERAMIK 15X15 cm
Keramik 15x15 cm 45.0000 bh 0.00
Semen Abu-abu 9.3000 Kg 0.00
Pasir pasang 0.0180 m3 0.00
Semen warna 1.5000 Kg 0.00
Pekerja 0.6000 HOK 0.00
Tukang batu 0.0450 HOK 0.00
Kepala tukang 0.0450 HOK 0.00
Mandor 0.0300 HOK 0.00
Total 0.00 0.00
Total Harga -
Keuntungan -
Jumlah Total -

M-68 1 m2 PASANG DINDING KERAMIK 20X20 cm


Keramik 20x20 cm 25.0000 bh 0.00
Semen Abu-abu 9.3000 Kg 0.00
Pasir pasang 0.0180 m3 0.00
Semen warna 1.5000 Kg 0.00
Pekerja 0.6000 HOK 0.00
Tukang batu 0.1000 HOK 0.00
Kepala tukang 0.0450 HOK 0.00
Mandor 0.0300 HOK 0.00
Total 0.00 0.00
Total Harga -
Keuntungan -
Jumlah Total -
DIHITUNG 1 m2 PASANG DINDING KERAMIK 20X25 cm
Keramik 20x20 cm 20.0000 bh 1,500.00 30,000.00
Semen Abu-abu 9.3000 Kg 1,090.00 10,137.00
Pasir pasang 0.0180 m3 85,000.00 1,530.00
Semen warna 1.5000 Kg 7,000.00 10,500.00
Pekerja 0.6000 HOK 35,000.00 21,000.00
Tukang batu 0.1000 HOK 45,000.00 4,500.00
Kepala tukang 0.0450 HOK 50,000.00 2,250.00
Mandor 0.0300 HOK 50,000.00 1,500.00
Total 29,250.00 52,167.00
Total Harga 81,417.00
Keuntungan 12,212.55
Jumlah Total 93,629.55

M-70 1 m2 PASANG DINDING MARMER


Marmer 1.0200 bh 0.00 0.00
Pacu Pancing 60 x 230 2.0000 bh 0.00 0.00
Semen Abu-abu 12.4400 Kg 0.00 0.00
Pasir pasang 0.0250 m3 0.00 0.00
Semen warna 1.5000 Kg 0.00 0.00
Pekerja 0.7200 HOK 0.00 0.00
Tukang batu 0.6500 HOK 0.00 0.00
Kepala tukang 0.0650 HOK 0.00 0.00
Mandor 0.0350 HOK 0.00 0.00
Total 0.00 0.00
Total Harga -
Keuntungan -
Jumlah Total -

M-74 1 m2 PASANG DINDING BATU TEMPEL HITAM


Batu tempel hitam 1.0500 m2 0.00
Semen Abu-abu 11.7500 Kg 0.00
Pasir pasang 0.0350 m3 0.00
Pekerja 0.6200 HOK 0.00
Tukang batu 0.3500 HOK 0.00
Kepala tukang 0.0350 HOK 0.00
Mandor 0.0300 HOK 0.00
Total 0.00 0.00
Total Harga -
Keuntungan -
a b c d e f=(cxe) g=(cxe) h 5495470000
Jumlah Total -

M-79 1 m2 PASANG WALL COVERING, LEBAR 50 cm


Vinyil wal covering, lebar 50 cm 1.1000 m2 0.00
Lem 0.2500 Kg 0.00
Pekerja 0.7500 HOK 0.00
Tukang batu 0.1700 HOK 0.00
Kepala tukang 0.0170 HOK 0.00
Mandor 0.0085 HOK 0.00
Total 0.00 0.00
Total Harga -
Keuntungan -
Jumlah Total -

M-82 1 m2 PLINT KAYU 2X10 cm


Kayu jati, papan 0.0024 m2 0.00
Paku skrup 3.5" 0.0500 Kg 0.00
Pekerja 0.1200 HOK 0.00
Tukang kayu 0.1200 HOK 0.00
Kepala tukang 0.0120 HOK 0.00
Mandor 0.0060 HOK 0.00
Total 0.00 0.00
Total Harga -
Keuntungan -
Jumlah Total -

DIHITUNG 1 m2 PASANG LANTAI KERAMIK 30X30 cm putih (polos)


Ubin keramik 30x30 cm 11.0000 bh 2,565.00 28,215.00
Semen Portland 11.3800 Kg 1,090.00 12,404.20
Pasir pasang 0.0420 m3 85,000.00 3,570.00
Semen warna 1.5000 Kg 7,000.00 10,500.00
Pekerja 0.6200 HOK 35,000.00 21,700.00
Tukang batu 0.3500 HOK 45,000.00 15,750.00
Kepala tukang 0.0350 HOK 50,000.00 1,750.00
Mandor 0.0300 HOK 50,000.00 1,500.00
Total 40,700.00 54,689.20
Total Harga 95,389.20
Keuntungan
Jumlah Total 95,389.20
a b c d e f=(cxe) g=(cxe) h 5495470000
DIHITUNG 1 m2 PASANG LANTAI KERAMIK 30X30 cm warna
Ubin keramik 30x30 cm 11.0000 bh 3,330.00 36,630.00
Semen Portland 11.3800 Kg 1,090.00 12,404.20
Pasir pasang 0.0420 m3 85,000.00 3,570.00
Semen warna 1.5000 Kg 7,000.00 10,500.00
Pekerja 0.6200 HOK 35,000.00 21,700.00
Tukang batu 0.3500 HOK 45,000.00 15,750.00
Kepala tukang 0.0350 HOK 50,000.00 1,750.00
Mandor 0.0300 HOK 50,000.00 1,500.00
Total 40,700.00 63,104.20
Total Harga 103,804.20
Keuntungan 15,570.63
Jumlah Total 119,374.83

DIHITUNG 1 m2 PASANG LANTAI KERAMIK 40X40 cm putih (polos)


Ubin keramik 40x40 cm 6.9300 bh 8,400.00 58,212.00
Semen Portland 11.3800 Kg 1,090.00 12,404.20
Pasir pasang 0.0420 m3 85,000.00 3,570.00
Semen warna 1.5000 Kg 7,000.00 10,500.00
Pekerja 0.6200 HOK 35,000.00 21,700.00
Tukang batu 0.3500 HOK 45,000.00 15,750.00
Kepala tukang 0.0350 HOK 50,000.00 1,750.00
Mandor 0.0300 HOK 50,000.00 1,500.00
Total 40,700.00 84,686.20
Total Harga 125,386.20
Keuntungan 18,807.93
Jumlah Total 144,194.13

DIHITUNG 1 m2 PASANG LANTAI KERAMIK 40X40 cm warna


Ubin keramik 40x40 cm 6.9300 bh 9,072.00 62,868.96
Semen Portland 11.3800 Kg 1,090.00 12,404.20
Pasir pasang 0.0420 m3 85,000.00 3,570.00
Semen warna 1.5000 Kg 7,000.00 10,500.00
Pekerja 0.6200 HOK 35,000.00 21,700.00
Tukang batu 0.3500 HOK 45,000.00 15,750.00
Kepala tukang 0.0350 HOK 50,000.00 1,750.00
Mandor 0.0300 HOK 50,000.00 1,500.00
Total 40,700.00 89,343.16
Total Harga 130,043.16
Keuntungan 19,506.47
Jumlah Total 149,549.63

DIHITUNG 1 m2 PASANG LANTAI KERAMIK 30X30 cm ANTI SELIP


Ubin keramik 30x30 cm anti selip 11.0000 bh 3,363.64 37,000.00
Semen Portland 11.3800 Kg 1,090.00 12,404.20
Pasir pasang 0.0420 m3 85,000.00 3,570.00
Semen warna 1.5000 Kg 7,000.00 10,500.00
Pekerja 0.6200 HOK 35,000.00 21,700.00
Tukang batu 0.3500 HOK 45,000.00 15,750.00
Kepala tukang 0.0350 HOK 50,000.00 1,750.00
Mandor 0.0300 HOK 50,000.00 1,500.00
Total 40,700.00 63,474.20
Total Harga 104,174.20
Keuntungan 15,626.13
Jumlah Total 119,800.33

DIHITUNG 1 m2 PASANG LANTAI KERAMIK 40X40 cm ANTI SELIP


Ubin keramik 40x40 cm anti selip 7.0000 bh 8,100.00 56,700.00
Semen Portland 11.3800 Kg 1,090.00 12,404.20
Pasir pasang 0.0420 m3 85,000.00 3,570.00
Semen warna 1.5000 Kg 7,000.00 10,500.00
Pekerja 0.6200 HOK 35,000.00 21,700.00
Tukang batu 0.3500 HOK 45,000.00 15,750.00
Kepala tukang 0.0350 HOK 50,000.00 1,750.00
Mandor 0.0300 HOK 50,000.00 1,500.00
Total 40,700.00 83,174.20
Total Harga 123,874.20
a b c d e f=(cxe) g=(cxe) h 5495470000
Keuntungan 18,581.13
Jumlah Total 142,455.33

DIHITUNG 1 m2 PASANG PAVING BLOCK 6 cm, WARNA (A139)


Paving block 6 cm, warna 1.0100 m2 0.00 0.00
Pasir pasang kali 0.1000 m3 65,000.00 6,500.00
Pekerja 0.2500 HOK 35,000.00 8,750.00
Tukang batu 0.5000 HOK 45,000.00 22,500.00
Kepala tukang 0.0250 HOK 50,000.00 1,250.00
Mandor 0.0030 HOK 50,000.00 150.00
Peralatan 0.0000 Ls 3,000.00 0.00
Total 32,650.00 6,500.00
Total Harga 39,150.00
Keuntungan 5,872.50
Jumlah Total 45,022.50

DIHITUNG 1 m2 PASANG PAVING BLOCK 6 cm, NATURAL (A141)


Paving block 6 cm, Natural 1.0100 m2 0.00 0.00
Pasir pasang kali 0.1000 m3 65,000.00 6,500.00
Pekerja 0.2500 HOK 35,000.00 8,750.00
Tukang batu 0.5000 HOK 45,000.00 22,500.00
Kepala tukang 0.0250 HOK 50,000.00 1,250.00
Mandor 0.0030 HOK 50,000.00 150.00
Peralatan 0.0000 Ls 3,000.00 0.00
Total 32,650.00 6,500.00
Total Harga 39,150.00
Keuntungan 5,872.50
Jumlah Total 45,022.50

DIHITUNG 1 m2 PASANG PAVING BLOCK 8 cm, WARNA (A140)


Paving block 8 cm, warna 1.0100 m2 0.00 0.00
Pasir pasang kali 0.1000 m3 65,000.00 6,500.00
Pekerja 0.2500 HOK 35,000.00 8,750.00
Tukang batu 0.5000 HOK 45,000.00 22,500.00
Kepala tukang 0.0250 HOK 50,000.00 1,250.00
Mandor 0.0030 HOK 50,000.00 150.00
Peralatan 0.0000 Ls 3,000.00 0.00
Total 32,650.00 6,500.00
Total Harga 39,150.00
Keuntungan 5,872.50
Jumlah Total 45,022.50

DIHITUNG 1 m2 PASANG PAVING BLOCK 8 cm, NATURAL (A142)


Paving block 8 cm, NATURAL 1.0100 m2 0.00 0.00
Pasir pasang kali 0.1000 m3 65,000.00 6,500.00
Pekerja 0.2500 HOK 35,000.00 8,750.00
Tukang batu 0.5000 HOK 45,000.00 22,500.00
Kepala tukang 0.0250 HOK 50,000.00 1,250.00
Mandor 0.0030 HOK 50,000.00 150.00
Peralatan 0.0000 Ls 3,000.00 0.00
Total 32,650.00 6,500.00
Total Harga 39,150.00
Keuntungan 5,872.50
Jumlah Total 45,022.50

N PEKERJAAN PENGECATAN
N-01 1 m2 MENGIKIS / MENGEROK PERMUKAAN CAT TEMBOK LAMA
Soda api 0.0500 Kg 0.00 0.00
Pekerja 0.1500 HOK 35,000.00 5,250.00
Mandor 0.0025 HOK 50,000.00 125.00
Total 5,375.00 0.00
Total Harga 5,375.00
Keuntungan 806.25
Jumlah Total 6,181.25

N-02 1 m2 MENCUCI BIDANG PERMUKAAN TEMBOK YANG PERNAH DI CAT


Sabun 0.0500 Kg 1,500.00 75.00
a b c d e f=(cxe) g=(cxe) h 5495470000
Pekerja 0.1500 HOK 35,000.00 5,250.00
Mandor 0.0025 HOK 50,000.00 125.00
Total 5,375.00 75.00
Total Harga 5,450.00
Keuntungan 817.50
Jumlah Total 6,267.50

N-03 1 m2 MENGEROK KARAT CAT LAMA PERMUKAAN BAJA DENGAN CARA MANUAL
Sabun 0.0500 Kg 1,500.00 75.00
Pekerja 0.1500 HOK 35,000.00 5,250.00
Mandor 0.0025 HOK 50,000.00 125.00
Total 5,375.00 75.00
Total Harga 5,450.00
Keuntungan 817.50
Jumlah Total 6,267.50

N-04 1 m2 MENYABUN PERMUKAAN TEMBOK LAMA


Sabun 0.0500 Kg 1,500.00 75.00
Pekerja 0.1500 HOK 35,000.00 5,250.00
Mandor 0.0025 HOK 50,000.00 125.00
Total 5,375.00 75.00
Total Harga 5,450.00
Keuntungan 817.50
Jumlah Total 6,267.50

N-06 1 m2 MENDEMPUL DAN MENGGOSOK KAYU


Dempul jadi 0.0800 Kg 16,500.00 1,320.00
Minyak cat 0.0200 Kg 3,190.00 63.80
Batu apung 0.0100 Kg 1,500.00 15.00
Pekerja 0.0400 HOK 35,000.00 1,400.00
Tukang cat 0.0400 HOK 40,000.00 1,600.00
Kepala tukang 0.0040 HOK 50,000.00 200.00
Mandor 0.0025 HOK 50,000.00 125.00
Total 3,325.00 1,398.80
Total Harga 4,723.80
Keuntungan 708.57
Jumlah Total 5,432.37

N-07 1 m2 PENGECATAN BIDANG KAYU LAMA


Plamir 0.1500 Kg 12,000.00 1,800.00
Cat dasar 0.1700 Kg 35,000.00 5,950.00
Cat Penutup 0.1700 Kg 35,000.00 5,950.00
Pekerja 0.0700 HOK 35,000.00 2,450.00
Tukang cat 0.0750 HOK 40,000.00 3,000.00
Kepala tukang 0.0075 HOK 50,000.00 375.00
Mandor 0.0025 HOK 50,000.00 125.00
Total 5,950.00 13,700.00
Total Harga 19,650.00
Keuntungan 2,947.50
Jumlah Total 22,597.50

N-08 1 m2 PENGECATAN BIDANG KAYU BARU (1 Lapis Plamir; 1 Lapis Cat dasar; 2 Lapis Cat Penutup)
Cat meni 0.2000 Kg 15,000.00 3,000.00
Plamir 0.1500 Kg 12,000.00 1,800.00
Cat dasar 0.1700 Kg 35,000.00 5,950.00
Cat Penutup ( 2 kali ) 0.2600 Kg 35,000.00 9,100.00
Pekerja 0.0700 HOK 35,000.00 2,450.00
Tukang cat 0.0090 HOK 40,000.00 360.00
Kepala tukang 0.0060 HOK 50,000.00 300.00
Mandor 0.0025 HOK 50,000.00 125.00
Total 3,235.00 19,850.00
Total Harga 23,085.00
Keuntungan
Jumlah Total 23,085.00

N-09 1 m2 PENGECATAN BIDANG KAYU BARU (1 Lapis Plamir; 1 Lapis Cat dasar; 3 Lapis Cat Penutup)
a b c d e f=(cxe) g=(cxe) h 5495470000
Cat meni 0.2000 Kg 15,000.00 3,000.00
Plamir 0.1500 Kg 12,000.00 1,800.00
Cat dasar 0.1700 Kg 35,000.00 5,950.00
Cat Penutup ( 3 kali ) 0.3500 Kg 35,000.00 12,250.00
Pekerja 0.0700 HOK 35,000.00 2,450.00
Tukang cat 0.1050 HOK 40,000.00 4,200.00
Kepala tukang 0.0040 HOK 50,000.00 200.00
Mandor 0.0025 HOK 50,000.00 125.00
Total 6,975.00 23,000.00
Total Harga 29,975.00
Keuntungan 4,496.25
Jumlah Total 34,471.25

N-11 1 m2 PELABURAN BIDANG KAYU DENGAN POLITUR


Politur 0.1500 Ltr 12,600.00 1,890.00
Politur jadi 0.3720 Ltr 27,000.00 10,044.00
Ampelas 2.0000 Lbr 1,900.00 3,800.00
Tukang cat 0.0600 HOK 40,000.00 2,400.00
Kepala tukang 0.0160 HOK 50,000.00 800.00
Mandor 0.0025 HOK 50,000.00 125.00
Total 3,325.00 15,734.00
Total Harga 19,059.00
Keuntungan 2,858.85
Jumlah Total 21,917.85

N-12 1 m2 PELABURAN BIDANG KAYU DENGAN CAT RESIDU DAN TER


Residu atau ter 0.3500 Ltr 1,200.00 420.00
Pekerja 0.1000 HOK 35,000.00 3,500.00
Mandor 0.0060 HOK 50,000.00 300.00
Total 3,800.00 420.00
Total Harga 4,220.00
Keuntungan 633.00
Jumlah Total 4,853.00

N-13 1 m2 PELABURAN BIDANG KAYU DENGAN VERNIS


Vernis 0.1500 Ltr 18,260.00 2,739.00
Dempul 0.0500 Kg 16,500.00 825.00
Ampelas 0.1000 Lbr 1,900.00 190.00
Kuas 0.0100 Bh 13,310.00 133.10
Pekerja 0.1600 HOK 35,000.00 5,600.00
Tukang cat 0.1600 HOK 40,000.00 6,400.00
Kepala tukang 0.0160 HOK 50,000.00 800.00
Mandor 0.0025 HOK 50,000.00 125.00
Total 12,925.00 3,887.10
Total Harga 16,812.10
Keuntungan 2,521.82
Jumlah Total 19,333.92

N-14 1 m2 PENGECATAN BIDANG TEMBOK BARU (1 Lapis Plamir; 1 Lapis Cat dasar; 2 Lapis Cat Penutup)
Plamir 0.1000 Kg 12,000.00 1,200.00
Cat dasar 0.1000 Kg 12,000.00 1,200.00
Cat Penutup ( 2 kali ) 0.2600 Kg 12,000.00 3,120.00
Pekerja 0.0200 HOK 35,000.00 700.00
Tukang cat 0.0630 HOK 40,000.00 2,520.00
Kepala tukang 0.0063 HOK 50,000.00 315.00
Mandor 0.0025 HOK 50,000.00 125.00
Total 3,660.00 5,520.00
Total Harga 9,180.00
Keuntungan
Jumlah Total 9,180.00

N-15 1 m2 PENGECATAN BIDANG TEMBOK LAMA ( 1 Lapis Cat dasar; 2 Lapis Cat Penutup )
Cat dasar 0.1200 Kg 12,000.00 1,440.00
Cat Penutup ( 2 kali ) 0.1800 Kg 12,000.00 2,160.00
Pekerja 0.0280 HOK 35,000.00 980.00
Tukang cat 0.0420 HOK 40,000.00 1,680.00
Kepala tukang 0.0042 HOK 50,000.00 210.00
Mandor 0.0025 HOK 50,000.00 125.00
a b c d e f=(cxe) g=(cxe) h 5495470000
Total 2,995.00 3,600.00
Total Harga 6,595.00
Keuntungan 989.25
Jumlah Total 7,584.25

N-19 1 m2 PEMASANGAN WALL PAPER


Wall paper 1.2000 m3 0.00
Perekat 0.2000 Kg 0.00
Pekerja 0.0200 HOK 0.00
Tukang cat 0.2000 HOK 0.00
Kepala tukang 0.0020 HOK 0.00
Mandor 0.0025 HOK 0.00
a b c d e f=(cxe) g=(cxe) h 5495470000
Total 0.00 0.00
Total Harga -
Keuntungan -
Jumlah Total -

N-20 1 m2 PENGECATAN PERMUKAAN BAJA DENGAN MENI BESI


Meni besi 0.1000 Kg 15,000.00 1,500.00
Kuas 0.0100 Bh 13,310.00 133.10
Pekerja 0.0200 HOK 35,000.00 700.00
Tukang cat 0.2000 HOK 40,000.00 8,000.00
Kepala tukang 0.0200 HOK 50,000.00 1,000.00
Mandor 0.0100 HOK 50,000.00 500.00
Total 10,200.00 1,633.10
Total Harga 11,833.10
Keuntungan 1,774.97
Jumlah Total 13,608.07

N-21 1 m2 PENGECATAN PERMUKAAN BAJA DENGAN MENI BESI DAN PERANCAH


Meni besi 0.1000 Kg 15,000.00 1,500.00
Kuas 0.0100 Bh 13,310.00 133.10
Perancah kayu 0.0020 m3 1,300,000.00 2,600.00
Pekerja 0.2500 HOK 35,000.00 8,750.00
Tukang cat 0.2250 HOK 40,000.00 9,000.00
Kepala tukang 0.0225 HOK 50,000.00 1,125.00
Mandor 0.0075 HOK 50,000.00 375.00
Total 19,250.00 4,233.10
Total Harga 23,483.10
Keuntungan 3,522.47
Jumlah Total 27,005.57

N-22 1 m2 PENGECATAN PERMUKAAN BAJA LAPIS SENG GALBANI SECARA MANUAL (4 lapis cat konvensional, tebal 200 um)
Cat dasar 0.1100 Kg 0.00
Cat antara 0.1700 Kg 0.00
Cat penutup 0.0800 Kg 0.00
Pekerja 0.5000 HOK 0.00
Tukang cat 0.8000 HOK 0.00
Kepala tukang 0.3000 HOK 0.00
Mandor 0.2000 HOK 0.00
Total 0.00 0.00
Total Harga -

N-23 1 m2 PENGECATAN PERMUKAAN BAJA LAPIS GALBANI SECARA MANUAL (1 lapis cat mutakhir, tebal 200 um)
Cat 0.3000 Kg 45,000.00 13,500.00
Pekerja 0.0060 HOK 85,000.00 510.00
Tukang cat 0.0600 HOK 105,000.00 6,300.00
Kepala tukang 0.0120 HOK 110,000.00 1,320.00
Mandor 0.0060 HOK 120,000.00 720.00
Total 8,850.00 13,500.00
Total Harga 22,350.00
Keuntungan 3,352.50
Jumlah Total 25,702.50

Dihitung 1 KG. PEKERJAAN BESI


Besi Profil 1.0500 KG 12,500.00 13,125.00
Pekerja 0.0600 HOK 35,000.00 2,100.00
Tukang Besi Profil Terampil 0.0040 HOK 43,500.00 174.00
Kepala Tukang Besi Profil 0.0010 HOK 44,500.00 44.50
Mandor 0.0002 HOK 50,000.00 10.00
Peralatan (O2,Solar, Elpiji, kawat las dll) 0.1250 LOT 15,453.50 1,931.69
Total 4,260.19 13,125.00
Total Harga 17,385.19
Keuntungan 2,607.78
Jumlah Total 19,992.97

O-01 1 M2 HOTMIX TANGAN T=3 CM (JADI) UNTUK HALAMAN & JALAN KLS 6 TON KE BAWAH
Abu Batu 0.0360 M3 115,000.00 4,140.00
Aspal Penetrasi 5.0000 M3 8,064.52 40,322.58
a b c d e f=(cxe) g=(cxe) h 5495470000
Kayu Bakar 0.0080 Kg 90,000.00 720.00
Pekerja setengah terampil 0.0800 M3 85,000.00 6,800.00
Pekerja Terampil 0.0300 Ls 105,000.00 3,150.00
Mandor 0.0100 HOK 120,000.00 1,200.00
Peralatan 0.0980 Lot 56,332.58 5,520.59
Total 16,670.59 45,182.58 61,853.17
Keuntungan 9,277.98
Total Harga 71,131.15
isi pada cell berwarna biru saja, pami teu ngartos, tataros nyak..

DIMENSI VOLUME lihat gambar,


pekerjaan galian
PEKERJAAN Tinggi Lebar Pondasi Lebar Topi Panjang Galian Pasangan Suling2 Siaran Plesteran Urugan
termasuk tipe 1
H (m) B=0.47H (m) T (m) L (m) (m3) (m3) (m') (m2) (m2) (m3) atau 2

Pot. A-A 1.00 0.50 0.30 129.50 97.13 84.18 0.00 129.50 51.80 25.90 Galian Tipe 2
Pot. B-B 0.00 0.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Galian Tipe 2
Pot. C-C 0.40 0.00 0.00 0.00 0.00 0.00 0.00 Galian Tipe 2
Pot. D-D 0.40 0.00 0.00 0.00 0.00 0.00 0.00 Galian Tipe 2
Pot. E-E 0.40 0.00 0.00 0.00 0.00 0.00 0.00 Galian Tipe 2
Lantai 1.00 0.30 0.00 0.00 0.00 0.00
Jumlah 129.50 97.13 84.18 0.00 129.50 51.80 25.90
4,000,000,000
Rehabilitasi Irigasi Desa Citapen, Kecamatan Sadananya

PAS Bro!!
no Uraian
I. Pekerjaan Persiapan
1 Pengukuran Kembali/Uitzet
2 Informasi Kegiatan
3 Direksikeet

II. Pekerjaan Pelaksanaan


A. PEKERJAAN PASANGAN
Galian tanah biasa sedalam ≤ 1m' (manual)
Galian Tanah Pondasi
Galian Tanah Kirmir

Pasangan batu dengan mortar tipe N


Pas. Pondasi
Pas. Kirmir

Plesteran tebal 1,5 cm dengan mortar tipe S

Siaran dengan mortar tipe M

Timbunan/Urugan tanah termasuk perataan dan perapihan

Pasangan pipa suling-suling


Profil / Esteger 342.8
P L T qty jmh input rb keterangan

1 1 1 ls
1 1 1 ls
1 1 1 Sewa

2764.43 m3
2056.90 0.8 0.6 1 987.3125
2056.90 0.6 1.8 0.79998 1777.118

3208.77 m3
2056.90 0.8 0.6 1 987.3125
2056.90 0.6 1.8 1 2221.453

2056.90 0.4 1 822.7604 822.76 m2

2056.90 0.7 0.8 1151.865 1151.86 m2

2764.43 0.4 1105.772 1105.77 m3

575.93 0.8 460.7 460.74 m'


2031.50

10 0.83
1
0
0
0

0
0
0

0
0
0

0
LUSSAN PAVING
LEBAR
2.7 2.9 2.59 1.42 1.31 0.41
1.888333
36
67.98
PERHITUNGAN VOLUME PERENCANAAN

KEGIATAN : Rehabilitasi Irigasi di Kecamatan Sadananya


PEKERJAAN : Rehabilitasi Irigasi Desa Citapen, Kecamatan Sadananya
LOKASI : Desan Citapen

1. Galian Tanah Biasa = 36.26 M3 96.00 37.8% tanah biasa 100.94


2. Galian Tanah Berbatu = 64.68 M3 64.68 100.0% berbatu
3. Pasangan Batu Kali 1PC : 4Ps = 160.68 M3
4. Plesteran 1PC : 3Ps = 92.4 M2 0.00
5. Siaran 1PC : 2Ps = 228.5 M2 23.00
6. Suling-suling Pipa PVC 1,5" = 20.7 M1
7. Urugan tanah = 24.00 M3
8. - Pembersihan dan pengupasan permukaan tanah = 115.50 m2 L 0.5 P 231.00

No. SKETSA GAMBAR URAIAN

A. PEKERJAAN PASANGAN
1. PEK. PAS. SAL. Tinggi 1 m POT. A-A
PASANGAN SALURAN 1. Perhitungan Volume Galian Tanah Bi Perhitungan Volume Galian Tanah
Ba
a = 0.3 m A galian = ((a+0,5)/2) x b x p A galian = cxdxp
b = 1.0 m 4,000,000,000.00 = ( (0.3 + 0,5)/ 2) x 1 x 186 = ( 0.4 + 0.7 ) x 186
c = 0.4 m = 74.40 m3 = 52.08 m3
d = 0.7 m 93
e = d - a - 0,20 = 0.2 m 2. Perhitungan Urugan Tanah
p = 186.00 m A urugan = e/2 x b x p
a e = 0.2/2 x 1 x 186
= 18.60 m3
3. Perhitungan Volume Pas. Batu Kali 1PC : 4Ps
Pen I
AI = (a+0,5)/2 x b
= (0.3 + 0,5)/2 x 1 = 0.4 m2
Pen II
A II = c x d = 0.4 x 0.7 = 0.28 m2 +
b

Luas Total Pen (A I + A II) 0.7 m2


I
0.68 x 186.00 = 126.48 m3

4. Perhitungan Volume Pas. Plesteran 1PC : 3Ps


V plesteran = (a + 0,1) x p
= ( 0.3 + 0,1 ) x 186
= 74.40 m2
II
c

5. Perhitungan Volume Pas. Siaran 1PC : 2Ps


V siaran = (b-0,05) x p
= (1 - 0,05)x 186
d
= 176.70 m2

2. PEK. PAS. SAL. Tinggi 1.2 m POT. B-B


PASANGAN SALURAN 1. Perhitungan Volume Galian Tanah Bi Perhitungan Volume Galian Tanah
Ba

a = 0.3 m A galian = ((a+0,5)/2) x b x p A galian = cxdxp


b = 1.2 m = ( (0.3 + 0,5)/ 2) x 1.2 x 45 = ( 0.4 + 0.7 ) x 45
c = 0.4 m = 21.60 m3 = 12.60 m3
d = 0.7 m
e = d - a - 0,20 = 0.2 m 2. Perhitungan Urugan Tanah
p = 45.00 m A urugan = e/2 x b x p

a = 0.2/2 x 1.2 x 45
e
= 5.40 m3
3. Perhitungan Volume Pas. Batu Kali 1PC : 4Ps
Pen I
AI = (a+0,5)/2 x b
= (0.3 + 0,5)/2 x 1.2 = 0.48 m2
b

Pen II
I
A II = c x d = 0.4 x 0.7 = 0.28 m2 +
Luas Total Pen (A I + A II) 0.8 m2
0.76 x 45.00 = 34.2 m3

II 4. Perhitungan Volume Pas. Plesteran 1PC : 3Ps


c

V plesteran = (a + 0,1) x p
= ( 0.3 + 0,1 ) x 45
d
= 18.00 m2
5. Perhitungan Volume Pas. Siaran 1PC : 2Ps
V siaran = (b-0,05) x p
= (1.2 - 0,05)x 45
= 51.75 m2
ANALISA HARGA SATUAN JARAK ANGKUT 200 M'
HARGA PERKIRAAN PERENCANA
TAHUN ANGGARAN 2021

Kegiatan : Rehabilitasi Irigasi di Kecamatan Sadananya

Pekerjaan : Rehabilitasi Irigasi Desa Citapen, Kecamatan Sadananya


Lokasi : Desan Citapen
Jarak Angkut : 100 m'

HARGA JUMLAH
KODE BIAYA
URAIAN PEKERJAAN VOLUME SATUAN SATUAN BIAYA
ANALISIS
( Rp ) ( Rp ) ( Rp )
I. Pekerjaan Persiapan

1 Pengukuran Kembali/Uitzet - 1.00 ls 750,000.00 750,000.00

2 Informasi Kegiatan - 1.00 ls 300,000.00 300,000.00

3 Direksikeet - 1.00 Sewa 500,000.00 500,000.00

4 Pembayaran Iuran BPJS Ketenaga Kerjaan - 1.00 ls 4,913,700.00 4,913,700.00

Sub Total 6,463,700.00


II. Pekerjaan Pelaksanaan
A. PEKERJAAN PASANGAN
1 Galian tanah biasa sedalam ≤ 1m' (manual) T.06a.1) 2,764.43 m3 62,802.65 173,613,529.74
2 Pasangan batu dengan mortar tipe N P.01c 3,208.77 m3 1,012,362.64 3,248,438,871.56
3 Plesteran tebal 1,5 cm dengan mortar tipe S P.04e 822.76 m2 83,295.63 68,532,314.91
4 Siaran dengan mortar tipe M P.03a 1,151.86 m2 64,839.07 74,685,529.58
5 Timbunan/Urugan tanah termasuk perataan dan T.14a 1,105.77 m3 36,811.50 40,705,052.36
perapihan
6 Pasangan pipa suling-suling P.16 460.74 m' 28,037.85 12,918,158.41

Sub Total 3,618,893,456.56


III. Pekerjaan Pembantu
1 Profil / Esteger T.05.a 342.82 m' 32,108.00 11,007,162.88

Sub Total 11,007,162.88


Jumlah Sub. 3,636,364,319.45
PPN 10% 363,636,431.94
Jumlah Total 4,000,000,751.39
Dibulatkan 4,000,000,000.00

Terbilang : EMPAT MILYAR RUPIAH


JADWAL PELAKSANAAN PEKERJAAN

KEGIATAN : Rehabilitasi Irigasi di Kecamatan Sadananya


PEKERJAAN : Rehabilitasi Irigasi Desa Citapen, Kecamatan Sadananya
LOKASI : Desan Citapen
Jarak Angkut : 100 m'

JUMLAH BOBOT I II
No. URAIAN PEKERJAAN Keterangan
BIAYA (%) 1 2 3 4 5 6 7 8
I. PEKERJAAN PERSIAPAN
100%
1 Pengukuran Kembali/Uitzet 750,000.00 #REF! #REF! #REF!
2 Informasi Kegiatan 300,000.00 #REF! #REF!
3 Direksikeet 500,000.00 #REF! #REF!
II PEKERJAAN PELAKSANAAN
1 #REF! #REF! #REF! #REF!
2 PEKERJAAN PASANGAN 0.00 #REF! #REF!
3 #REF! #REF! #REF! #REF! #REF! #REF! #REF!
4 Pasangan batu dengan mortar tipe N 3,248,438,871.56 #REF! #REF! #REF! 50%
5 Plesteran tebal 1,5 cm dengan mortar tipe S 68,532,314.91 #REF! #REF! #REF!
6 #REF! #REF! #REF! #REF!
III PEKERJAAN PEMBANTU
1 Profil / Esteger 11,007,162.88 #REF! #REF! #REF! #REF! #REF! #REF! #REF!
2 Kistdam pasir/tanah 0.00 #REF! #REF! #REF! #REF! #REF! #REF! #REF!
3 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!

JUMLAH BOBOT PEKERJAAN #REF! #REF! 0%


RENCANA PRESTASI PERMINGGU #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
AKUMULASI RENCANA PRESTASI PERMINGGU #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
REALISASI PRESTASI PERMINGGU
AKUMULASI REALISASI PRESTASI PERMINGGU
DAFTAR HARGA SATUAN PEKERJAAN

Kegiatan : Rehabilitasi Irigasi di Kecamatan Sadananya


Pekerjaan : Rehabilitasi Irigasi Desa Citapen, Kecamatan Sadananya
Lokasi : Desan Citapen
Jarak Angkut : 100 m'

KODE HARGA SATUAN


NO. URAIAN PEKERJAAN ANALISIS SATUAN PEKERJAAN (HSP) KETERANGAN
(AHSP) (Rp.)
1 2 3 4 5 6
1 Profil melintang untuk galian tanah saluran T.05.a m' 32,108.00
2 Galian tanah biasa sedalam ≤ 1m' (manual) T.06a.1) m³ 62,802.65
3 Pasangan batu dengan mortar tipe N (1PC:4PP) P.01c m³ 1,012,362.64
4 Pasangan pipa suling-suling P.16 m' 28,037.85
5 Siaran dengan mortar tipe M (1PC:2PP) P.03a m² 64,839.07
6 Plesteran tebal 1,5 cm dengan mortar tipe S (1PC:3PP) P.04e m² 83,295.63
7 Timbunan/Urugan tanah termasuk perataan dan perapihan T.14a m³ 36,811.50
DAFTAR HARGA SATUAN DASAR
TENAGA KERJA, BAHAN DAN ALAT

Kegiatan : Rehabilitasi Irigasi di Kecamatan Sadananya


Pekerjaan : Rehabilitasi Irigasi Desa Citapen, Kecamatan Sadananya
Lokasi : Desan Citapen
Jarak Angkut : 100 m'

Harga Satuan HSD Lokasi


Biaya Angkutan Material ke Lokasi Pekerjaan
NO. URAIAN SATUAN KODE Dasar Pekerjaan KET.
( Rp ) Kode Deskripsi (Rp.) (Rp.)
1 2 3 4 5 6 7
I UPAH TENAGA KERJA
1 Pekerja OH L.01 85,000.00 85,000.00
2 Tukang
Tukang Gali
Tukang Batu/Tembok
Tukang Kayu
Tukang Besi/Besi Beton
OH L.02 105,000.00 105,000.00
Tukang Cat/Pelitur
Tukang Pipa/Operator Pompa
Tukang Penganyam Bronjong
Tukang Tebas
Tukang Las
3 Kepala Tukang OH L.03 110,000.00 110,000.00
4 Mandor OH L.04 120,000.00 120,000.00
5 Juru Ukur OH L.05 100,000.00 100,000.00
6 Pembantu Juru Ukur OH L.06 50,000.00 50,000.00
7 Ahli Alat Berat (Mekanik) OH L.07 90,000.00 90,000.00
8 Operator Alat Berat OH L.08 90,000.00 90,000.00
9 Pembantu Operator OH L.09 65,000.00 65,000.00
10 Supir Truk OH L.10 80,000.00 80,000.00
11 Kenek Truk OH L.11 65,000.00 65,000.00
12 Penjaga Malam/Satpam OH L.12 65,000.00 65,000.00
13 Drafter CAD/Manual OH L.13 100,000.00 100,000.00
14 Operator Komputer/Printer/Plotter OH L.15 50,000.00 50,000.00

II BAHAN/MATERIAL
1 Semen Portland/PC (50 kg) zak M.01 56,000.00 T.15a.6) Mengangkut 1 m³ material dengan jarak angkut 100 m 2,481.00 58,481.00
2 Batu Belah m³ M.02 142,000.00 T.15a.6) Mengangkut 1 m³ material dengan jarak angkut 100 m 46,658.00 188,658.00
3 Pasir Pasang m³ M.03 142,000.00 T.15a.6) Mengangkut 1 m³ material dengan jarak angkut 100 m 63,534.00 205,534.00
4 Pasir Beton m³ M.04 200,000.00 T.15a.6) Mengangkut 1 m³ material dengan jarak angkut 100 m 59,563.00 259,563.00
5 Batu Pecah 2/3 m³ M.05 190,000.00 T.15a.6) Mengangkut 1 m³ material dengan jarak angkut 100 m 62,541.00 252,541.00
6 Kerikil m³ M.06 160,000.00 T.15a.6) Mengangkut 1 m³ material dengan jarak angkut 100 m 62,541.00 222,541.00
7 Tanah Urug m³ M.07 50,000.00 T.21a Mengangkut 1 m³ material dengan jarak angkut 100 m 62,541.00 112,541.00
8 Pipa PVC AW Ø 1,5" m' M.08 9,500.00 9,500.00
9 Ijuk kg M.09 7,000.00 7,000.00
10 Paku Ukuran 10cm, 7cm dan 5cm kg M.10 14,000.00 14,000.00
11 Paku Beton Ukuran 7cm kg M.11 14,000.00 14,000.00
12 Besi Beton kg M.12 11,000.00 11,000.00
13 Kawat Beton kg M.13 14,000.00 14,000.00
14 Kayu Gunung Kls II m³ M.14 2,500,000.00 2,500,000.00
15 Papan Albasiah m³ M.15 2,000,000.00 2,000,000.00
16 Kaso Albasiah m³ M.16 2,000,000.00 2,000,000.00
17 Kayu Dolken m' M.17 6,000.00 6,000.00
18 Bambu m' M.18 1,400.00 1,400.00
19 Multiflex 18 mm lbr M.19 249,600.00 249,600.00
20 Karung Plastik (Bagor) buah M.20 2,000.00 2,000.00
21 Tali Plastik (Rapia) m' M.21 500.00 500.00
Harga Satuan HSD Lokasi
Biaya Angkutan Material ke Lokasi Pekerjaan
NO. URAIAN SATUAN KODE Dasar Pekerjaan KET.
( Rp ) Kode Deskripsi (Rp.) (Rp.)
1 2 3 4 5 6 7
22 Minyak Pelumas L M.22 6,000.00 6,000.00
23 Solar L M.23 6,900.00 6,900.00
24 Minyak Tanah L M.24 8,000.00 8,000.00
25 Air L M.25 200.00 200.00
26 Bronjong Kawat Ø3mm buah M.26 300,000.00 300,000.00
27 Bronjong Kawat Ø4mm buah M.27 350,000.00 350,000.00
28 Bronjong Kawat Ø5mm buah M.28 500,000.00 500,000.00
29 Buis Beton Ø=20cm; L=100cm buah M.29 25,000.00 25,000.00
30 Buis Beton Ø=30cm; L=100cm buah M.30 35,000.00 35,000.00
31 Buis Beton Ø=40cm; L=100cm buah M.31 60,000.00 60,000.00
32 Buis Beton Ø=60cm; L=50cm buah M.32 60,000.00 60,000.00
33 Buis Beton Ø=80cm; L=50cm buah M.33 80,000.00 80,000.00

III PERALATAN/ALAT BANTU


1 Chainsaw sewa/hari E.01 160,000 160,000
2 Waterpass sewa/hari E.02 200,000 200,000
3 Theodolith sewa/hari E.03 250,000 250,000
4 Pemadat Timbunan (Stamper) sewa/hari E.04 150,000 150,000
5 Linggis (Baja keras) buah E.05 70,000 70,000
6 Pahat Beton (baja keras) buah E.06 25,000 25,000
7 Palu/godam pemecah batu buah E.07 130,000 130,000
8 Molen (kapasitas 0,3 m³) sewa/hari E.08 350,000 350,000
9 Jack Hammer sewa/hari E.09 175,000 175,000
10 Tripod (tinggi 5 m) sewa/hari E.10 250,000 250,000
11 Alat Pancang Hammer (0.5 ton) sewa/hari E.11 120,000 120,000
12 Alat penyambung tiang pancang sewa/hari E.12 25,000 25,000
13 Pompa air diesel 5 KW sewa/hari E.13 80,000 80,000
14 Pompa air diesel 10 KW sewa/hari E.14 150,000 150,000
15 Dump Truck jam E.15 101,400 101,400
A. Koefisien AHSP Bidang Sumber Daya Air

Lampiran A.1
Pekerjaan Tanah

Pekerjaan tanah ini meliputi pekerjaan galian dan timbunan tanah serta houling yang dapat dilaksanakan baik secara manual dengan tenaga
manusia dan juga secara mekanisasi.

T.05.a Pasang 1 m' profil melintang untuk galian tanah saluran

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien
(Rp) (Rp)
1 2 3 4 5 6 7

A Tenaga Kerja
1 Pekerja L.01 OH 0.0600 85,000.00 5,100.00
2 Tukang kayu L.02 OH 0.0200 105,000.00 2,100.00
3 Mandor L.04 OH 0.0060 120,000.00 720.00
4 Juru Ukur L.05 OH 0.0200 100,000.00 2,000.00
5 Pembantu Juru Ukur L.06 OH 0.0200 50,000.00 1,000.00
Jumlah Harga Tenaga Kerja 10,920.00
B Bahan
1 Kaso 4/6 cm M.16 m3 0.0025 2,000,000.00 5,000.00
2 Papan 2/20 M.15 m 3
0.0042 2,000,000.00 8,400.00
3 Paku M.10 kg 0.2000 14,000.00 2,800.00
Jumlah Harga Bahan 16,200.00
C Peralatan
1 Waterpass E.02 Sewa-hari 0.0040 200,000.00 800.00
Jumlah Harga Peralatan 800.00
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 27,920.00
E Overhead + Profit 15% x D 4,188.00
F Harga Satuan Pekerjaan per - m1 (D+E) 32,108.00

c. AHSP pekerjaan tanah cara manual


Pelaksanaan galian tanah T.06 s.d T.11 secara umum sudah termasuk pembuangan hasil galian dengan jarak angkut L < 5 m serta perataan dan
perapihan, jika diperlukan angkutan dengan jarak lainnya lihat T.15: angkutan material dan/atau hasil galian. Jika pada pelaksanaan penggalian
tanah diperlukan perkuatan dinding galian tanah, perlu ditambah dengan analisa pada T.12.
T.06 Pekerjaan Galian Tanah Biasa
T.06a Cara Manual
T.06a.1) 1 m3 Galian tanah biasa sedalam < 1 m
Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
1 2 3 4 5 6 7

A Tenaga Kerja
1 Pekerja L.01 OH 0.5630 85,000.00 47,855.00
2 Mandor L.04 OH 0.0563 120,000.00 6,756.00
Jumlah Harga Tenaga Kerja 54,611.00
B Bahan
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 54,611.00
E Overhead + Profit 15% x D 8,191.65
F Harga Satuan Pekerjaan per - m3 (D+E) 62,802.65
T.14 Timbunan dan Pemadatan
T.14a 1 m3 Timbunan tanah atau urugan tanah kembali termasuk perataan dan perapihan
Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
1 2 3 4 5 6 7

A Tenaga Kerja
1 Pekerja L.01 OH 0.3300 85,000.00 28,050.00
2 Mandor L.04 OH 0.0330 120,000.00 3,960.00
Jumlah Harga Tenaga Kerja 32,010.00
B Bahan
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 32,010.00
E Overhead + Profit 15% x D 4,801.50
F Harga Satuan Pekerjaan per - m3 (D+E) 36,811.50
T.15 BIAYA ANGKUTAN SECARA MANUAL (BIAYA ANGKUTAN DIMASUKKAN DALAM HSD - BAHAN)
Perhitungan konversi berbagai jenis material dengan jarak angkut, naik dan turun; seperti pada tabel di bawah. Kode pekerjaan T.15a.5) s.d T.15a.10)
untuk mengangkut 1 m³ berbagai jenis material dengan jarak horizontal termasuk juga pelandaian turun < 20° serta pelandaian naik < 15° yang dihitung
sebagai panjang lintasannya. Material dengan tingkat kemudahan seperti besi beton dan pasir/koral/tanah/plastik, maka angkutan jarak horizontal datar,
vertikal turun dan naik, dikalikan lagi koefisien AHSP-nya besi beton x 0,7 dan pasir/koral/tanah/plastik x 1,0.

Asumsi Berat Isi 1.1 0.05 0.94 1.28 1.2 1.26


Tingkat kemudahan 1 1 1 1 1 1
Kode Deskripsi
Material Tanah Lepas Semen Batu Belah Pasir Pasang Pasir Beton Batu Pecah
Satuan m³ zak m³ m³ m³ m³
T.15a.5) Mengangkut 1 m³ material dengan jarak angkut 50 m 38,402.00 1,745.00 32,816.00 44,685.00 41,893.00 43,987.00
T.15a.6) Mengangkut 1 m³ material dengan jarak angkut 100 m 54,600.00 2,481.00 46,658.00 63,534.00 59,563.00 62,541.00
T.15a.7) Mengangkut 1 m³ material dengan jarak angkut 200 m 86,450.00 3,929.00 73,875.00 100,596.00 94,309.00 99,024.00
T.15a.8) Mengangkut 1 m³ material dengan jarak angkut 300 m 118,300.00 5,377.00 101,092.00 137,658.00 129,054.00 135,507.00
T.15a.9) Mengangkut 1 m³ material dengan jarak angkut 400 m 150,150.00 6,825.00 128,310.00 174,720.00 163,800.00 171,990.00
T.15a.10) Mengangkut 1 m³ material dengan jarak angkut 500 m 177,450.00 8,065.00 151,639.00 206,487.00 193,581.00 203,260.00

T.15a.5) Mengangkut 1 m³ material dengan jarak angkut 50 m


Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 0.4220 85,000.00 35,870.00
2 Mandor L.04 OH 0.0211 120,000.00 2,532.00
Jumlah Harga Tenaga Kerja 38,402.00
B Bahan
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 38,402.00

T.15a.6) Mengangkut 1 m³ material dengan jarak angkut 100 m


Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 0.6000 85,000.00 51,000.00
2 Mandor L.04 OH 0.0300 120,000.00 3,600.00
Jumlah Harga Tenaga Kerja 54,600.00
B Bahan
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 54,600.00

T.15a.7) Mengangkut 1 m³ material dengan jarak angkut 200 m


Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 0.9500 85,000.00 80,750.00
2 Mandor L.04 OH 0.0475 120,000.00 5,700.00
Jumlah Harga Tenaga Kerja 86,450.00
B Bahan
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 86,450.00
T.15a.8) Mengangkut 1 m³ material dengan jarak angkut 300 m
Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 1.3000 85,000.00 110,500.00
2 Mandor L.04 OH 0.0650 120,000.00 7,800.00
Jumlah Harga Tenaga Kerja 118,300.00
B Bahan
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 118,300.00

T.15a.9) Mengangkut 1 m³ material dengan jarak angkut 400 m


Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 1.6500 85,000.00 140,250.00
2 Mandor L.04 OH 0.0825 120,000.00 9,900.00
Jumlah Harga Tenaga Kerja 150,150.00
B Bahan
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 150,150.00

T.15a.10) Mengangkut 1 m³ material dengan jarak angkut 500 m


Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 1.9500 85,000.00 165,750.00
2 Mandor L.04 OH 0.0975 120,000.00 11,700.00
Jumlah Harga Tenaga Kerja 177,450.00
B Bahan
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 177,450.00

T.21a DT angkut material dari BA ke lokasi pekerjaan, jarak 1 km


Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
1 2 3 4 5 6 7

A Tenaga Kerja
1 Pekerja L.01 OH 1.9500 85,000.00 165,750.00
2 Mandor L.04 OH 0.0975 120,000.00 11,700.00
Jumlah Harga Tenaga Kerja 177,450.00
B Bahan
1 Tanah Urug M.06 m3 1.00 112,541.00 112,541.00

Jumlah Harga Bahan 112,541.00


C Peralatan
-

Jumlah Harga Peralatan -


D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 289,991.00
Lampiran A.2
Pekerjaan Pasangan

Berbagai jenis pekerjaan pasangan batu yang termasuk lapisan penutup batu muka dan lainnya. Pasangan batu dapat berupa pasangan batu
dengan mortar ataupun tanpa mortar. Sesuai dengan SNI 03-6882-2002, "Spesifikasi Mortar untuk Pekerjaan Pasangan" diklasifikasikan
berdasarkan kekuatan tekan mortarnya PC-PP. Untuk kedua jenis tersebut terbagi pula menjadi empat tipe mortar yaitu mortar tipe M (17,2 MPa);
tipe S (12,5 MPa); tipe N (5,2 MpPa) dan tipe O (2,4 MPa). Sehubungan dengan hal tersebut, maka AHSP untuk berbagai jenis pasangan tersebut
adalah sebagai berikut:

P.01 Pasangan batu dengan mortar jenis PC-PP (1 m 3)


P.01c Mortar tipe N (mutu PP tertentu setara dengan campuran 1 PC:4 PP)

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien
(Rp) (Rp)
1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 2.7000 85,000.00 229,500.00
2 Tukang batu L.02 OH 0.9000 105,000.00 94,500.00
3 Mandor L.04 OH 0.2700 120,000.00 32,400.00
Jumlah Harga Tenaga Kerja 356,400.00
B Bahan
1 Batu belah M.02 m3 1.2000 188,658.00 226,389.60
2 Pasir Pasang M.03 m3 0.5200 205,534.00 106,877.68
3 Portland Cement M.01 kg 163.00 1,169.62 190,648.06
Jumlah Harga Bahan 523,915.34
C Peralatan
Jumlah Harga Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 880,315.34
E Overhead + Profit 15% x D 132,047.30
F Harga Satuan Pekerjaan per - m3 (D+E) 1,012,362.64
P.03a Siaran dengan mortar jenis PC-PP tipe M (mutu PP tertentu setara dengan campuran 1 PC:2 PP)

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien
(Rp) (Rp)
1 2 3 4 5 6 7

A Tenaga Kerja
1 Pekerja L.01 OH 0.3000 85,000.00 25,500.00
2 Tukang batu L.02 OH 0.1500 105,000.00 15,750.00
3 Kepala Tukang L.03 OH 0.0150 110,000.00 1,650.00
4 Mandor L.04 OH 0.0300 120,000.00 3,600.00
Jumlah Harga Tenaga Kerja 46,500.00
B Bahan
1 Pasir Pasang M.03 m3 0.0120 205,534.00 2,466.41
2 Portland Cement M.01 kg 6.3400 1,169.62 7,415.39
Jumlah Harga Bahan 9,881.80
C Peralatan
Jumlah Harga Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 56,381.80
E Overhead + Profit 15% x D 8,457.27
F Harga Satuan Pekerjaan per - m2 (D+E) 64,839.07
P.04e Plesteran tebal 1,5 cm, dengan mortar jenis PC-PP tipe S (mutu PP tertentu setara dengan campuran 1 PC:3 PP)
Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 0.3840 85,000.00 32,640.00
2 Tukang batu L.02 OH 0.1920 105,000.00 20,160.00
3 Kepala Tukang L.03 OH 0.0190 110,000.00 2,090.00
4 Mandor L.04 OH 0.0190 120,000.00 2,280.00
Jumlah Harga Tenaga Kerja 57,170.00
B Bahan
1 Pasir Pasang M.03 m3 0.0300 205,534.00 6,166.02
2 Portland Cement M.01 kg 7.7760 1,169.62 9,094.97
Jumlah Harga Bahan 15,260.99
C Peralatan
Jumlah Harga Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 72,430.99
E Overhead + Profit 15% x D 10,864.65
F Harga Satuan Pekerjaan per - m2 (D+E) 83,295.63

P.16 Pasangan Pipa Suling-suling (1 m')

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien
(Rp) (Rp)
1 2 3 4 5 6 7
A Tenaga Kerja
1. Pekerja L.01 OH 0.1000 85,000.00 8,500.00
2. Mandor L.04 OH 0.0100 120,000.00 1,200.00
Jumlah Harga Tenaga Kerja 9,700.00
B Bahan
1. Pipa PVC AW Ø 1,5" M.08 m 1.0500 9,500.00 9,975.00
2. Ijuk M.09 kg 0.1000 7,000.00 700.00
3. Kerikil M.06 m3 0.0180 222,541.00 4,005.74
Jumlah Harga Bahan 14,680.74
C Peralatan
Jumlah Harga Peralatan -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 24,380.74
E Overhead + Profit 15% x D 3,657.11
F Harga Satuan Pekerjaan per - m1 (D+E) 28,037.85
Lampiran A.5
Pekerjaan Dewatering

Berbagai jenis pekerjaan yang dikelompokkan dalam pekerjaan dewatering meliputi pembuatan dan pemasangan kistdam dan pemompaan air pada
daerah kerja yang analisanya sebagai berikut:

D.01 Kistdam pasir/tanah


D.01a 1 bh Kistdam pasir/tanah dibungkus karung plastik bagor (sebesar karung beras 25 kg) uk. 43 x 65 cm
Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
1 2 3 4 5 6 7

A Tenaga Kerja
1 Pekerja L.01 OH 0.0400 85,000.00 3,400.00
2 Mandor L.04 OH 0.0040 120,000.00 480.00
Jumlah Harga Tenaga Kerja 3,880.00
B Bahan
1 Karung plastik / bagor M.20 bh 1.0000 2,000.00 2,000.00
2 Tali rapia / plastik M.21 m 2.0000 500.00 1,000.00
3 Sewa pasir * M.03 m3 0.0600 205,534.00 12,332.04
Jumlah Harga Bahan 15,332.04
C Peralatan
Jumlah Harga Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 19,212.04
E Overhead + Profit 15% x D 2,881.81
F Harga Satuan Pekerjaan per - buah (D+E) 22,093.85
* Koef. dihitung 50%, jika penggunaan kistdam selesai, pasir dimanfaatkan kembali, gunakan HS pasir 100%

D.02 Kerangka kayu untuk 1 m 3 kistdam pasir/tanah uk. 43 cm x 65 cm


Diasumsikan karung plastik setelah diisi menjadi berukuran 16,5 cm x 30 cm x 50 cm atau untuk 36 buah karung setiap m 3.AHSP ini
dihitung berdasarkan tinggi tumpukan kistdam 3 m dengan dalam pancangan kayu kaso sedalam 1 m ke dalam tanah.

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien
(Rp) (Rp)
1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 0.0500 85,000.00 4,250.00
2 Tukang kayu L.02 OH 0.1000 105,000.00 10,500.00
3 Mandor L.04 OH 0.0050 120,000.00 600.00
Jumlah Harga Tenaga Kerja 15,350.00
B Bahan
1 Kayu kaso ukuran 5/7 kelas II *) M.16 m3 0.1120 2,000,000.00 224,000.00
2 Paku campuran 5 cm & 7 cm M.10 kg 0.3250 14,000.00 4,550.00
Jumlah Harga Bahan 228,550.00
C Peralatan
Jumlah Harga Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 243,900.00
E Overhead + Profit 15% x D 36,585.00
F Harga Satuan Pekerjaan per - 1 m 3 (D+E) 280,485.00
*) Kayu kaso 8 batang, koefisien untuk pemakaian ke-1 (0,112), untuk ke-2 (0,0756) dan untuk ke-3 (0,0635)
Catatan:
- Asumsi untuk kistdam setinggi 30cm digunakan 4 buah karung per meter Rp. 88,375.38
- Kebutuhan kerangka kistdam setinggi 30cm per meter panjang Rp. 31,165.00
Jadi biaya pemasangan kistdam menggunakan kerangka kayu dengan tinggi 30cm adalah Rp. 119,540.38 per meter.
D.04 Pengoperasian per hari selama 24 jam 1 buah pompa air diesel daya 5 kW dengan suction head max. 3m dan discharge head max. 20m
(kapasitas 0,5 m3/s pada suction head 1m dan discharge head 10m)
Pengoperasian pompa diasumsikan akan beroperasi 24 jam dan disediakan 20% pompa cadangan (misalkan untuk 5 buah pompa
dioperasikan dan 1 cadangan), maka biaya operasi per 1 bh pompa:

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien
(Rp) (Rp)
1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja (memantau mengalirnya air) L.01 OH 1.0000 85,000.00 85,000.00
2 Operator pompa L.02 OH 3.0000 105,000.00 315,000.00
3 Mandor L.04 OH 0.1000 120,000.00 12,000.00
Jumlah Harga Tenaga Kerja 412,000.00
B Bahan
1 Solar M.23 L 42.4000 6,900.00 292,560.00
Jumlah Harga Bahan 292,560.00
C Peralatan
1 Pompa air diesel 5 KW E.13 Sewa-hari 1.2000 80,000.00 96,000.00
Jumlah Harga Peralatan 96,000.00
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 800,560.00
E Overhead + Profit 15% x D 120,084.00
F Harga Satuan Pekerjaan per - 1 hari (D+E) 920,644.00

D.05 Pengoperasian per hari selama 24 jam 1 buah pompa air diesel daya 10 kW dengan suction head max. 3m dan discharge head max. 20m
(kapasitas 1 m3/s pada suction head 1m dan discharge head 10m)
Pengoperasian pompa diasumsikan akan beroperasi 24 jam dan disediakan 20% pompa cadangan (misalkan untuk 5 buah pompa
dioperasikan dan 1 cadangan), maka biaya operasi per 1 bh pompa:

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien
(Rp) (Rp)
1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja (memantau mengalirnya air) L.01 OH 1.0000 85,000.00 85,000.00
2 Operator pompa L.02 OH 3.0000 105,000.00 315,000.00
3 Mandor L.04 OH 0.1000 120,000.00 12,000.00
Jumlah Harga Tenaga Kerja 412,000.00
B Bahan
1 Solar M.23 L 72.6000 6,900.00 500,940.00
2 Oli M.22 L 0.3000 6,000.00 1,800.00
Jumlah Harga Bahan 502,740.00
C Peralatan
1 Pompa air diesel 10 KW E.14 bh 1.2000 150,000.00 180,000.00
Jumlah Harga Peralatan 180,000.00
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 1,094,740.00
E Overhead + Profit 15% x D 164,211.00
F Harga Satuan Pekerjaan per - 1 hari (D+E) 1,258,951.00
HARGA PERKIRAAN PERENCANA
TAHUN ANGGARAN 2019

Kegiatan : Perkuatan Dinding Saluran Irigasi di Kecamatan Indihiang Kota Tasikmalaya


Pekerjaan : Rehabilitasi Saluran Irigasi Cibungkul Blok BLK
Lokasi : Kecamatan Indihiang Kota Tasikmalaya
Jarak Angkut : 100 m'

HARGA JUMLAH
KODE BIAYA
URAIAN PEKERJAAN VOLUME SATUAN SATUAN BIAYA
ANALISIS
( Rp ) ( Rp ) ( Rp )
I. Pekerjaan Persiapan

1 Pengukuran Kembali/Uitzet - 1.00 ls

2 Informasi Kegiatan - 1.00 ls

3 Direksikeet - 1.00 Sewa

Sub Total
II. Pekerjaan Pelaksanaan

1 Galian tanah biasa sedalam ≤ 1m' (manual) T.06a.1) 67.89 m3


2 Pasangan batu dengan mortar tipe N P.01c 163.44 m3
3 Plesteran tebal 1,5 cm dengan mortar tipe S P.04e 54.00 m2
4 Siaran dengan mortar tipe M P.03a 165.60 m2
5 Timbunan/Urugan tanah termasuk perataan dan T.14a 4.32 m3
perapihan
6 Pasangan pipa suling-suling P.16 82.80 m'

Sub Total
III. Pekerjaan Pembantu
1 Profil / Esteger T.05.a 27.00 m'
2 Kistdam pasir/tanah D.01a 12.00 bh

Sub Total
Jumlah Sub.
PPN 10%
Jumlah Total
Dibulatkan

Terbilang :

Tasikmalaya, 2019
Mengetahui, Penawar
Kepala Bidang SDA PT/CV

Drs. NANANG GUNAWAN, M.Si

NIP. 19641121 199203 1 006 Nama Lengkap


Jabatan
Menyetujui,
Kepala Dinas Pekerjaan Umum dan Penataan Ruang
Kota Tasikmalaya

Drs. IVAN DICKSAN HASANNUDIN, M.Si


NIP. 19660703 199603 1 002