TIME SCHEDULE & CURVA S
PROYEK PEMBANGUNAN RUMAH KOST PAK TRIYANTO
BANDUNG - JAWA BARAT
BULAN KE-1 BULAN KE-2 BULAN KE-3 BULAN KE-4 BULAN KE-5 BULAN KE-6 BULAN KE-7 BULAN KE-8
DURASI
NO ITEM PEKERJAAN BOBOT %
MINGGU 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
LT 1.4 PEK.BETON BERTULANG / STRUKTUR 5.1240 6 0.854 0.854 0.854 0.854 0.854 0.854
80.00
LT 1.8 PEKERJAAN PLAFOND 1.0370 3 0.346 0.346 0.346
LT 1.10 PEK. SANITARY & INST. AIR 0.6510 5 0.130 0.130 0.130 0.130 0.130
LT 2.1 PEK.BETON BERTULANG / STRUKTUR 6.8410 7 0.977 0.977 0.977 0.977 0.977 0.977 0.977
LT 2.7 PEK. SANITARY & INST. AIR 1.1600 3 0.387 0.387 0.387
LT 3.1 PEK.BETON BERTULANG / STRUKTUR 6.9180 6 1.153 1.153 1.153 1.153 1.153 1.153
LT 3.7 PEK. SANITARY & INST. AIR 1.3980 3 0.466 0.466 0.466
TOTAL RENCANA % 1.70 0.36 0.36 1.81 1.45 1.45 2.30 0.85 1.83 1.83 1.83 2.98 4.15 4.15 7.61 6.78 7.00 4.89 5.47 5.86 3.48 0.98 3.62 3.62 3.51 2.55 2.51 2.50 2.12 4.14 3.80 2.50
RENCANA KOMULATIF % 1.70 2.06 2.43 4.23 5.68 7.13 9.43 10.29 12.12 13.95 15.78 18.76 22.91 27.07 34.67 41.46 48.45 53.35 58.82 64.67 68.16 69.14 72.76 76.38 79.88 82.44 84.95 87.44 89.56 93.71 97.50 100.00
NO JENIS KEUANGAN TOTAL
PENGELUARAN
PEMASUKAN
6 5% (retensi) Rp88,675,900
BULAN KE-1
1 2 3
Rp354,703,600