RENCANA ANGGARAN BIAYA


RUKO BANYUMAS

HARGA
NO JENIS PEKERJAAN VOLUME SATUAN JUMLAH
SATUAN

I PEKERJAAN PERSIAPAN
1 Pekerjaan Bouwplank 80 m2 23,500.00 1,880,000.00
2 Pengadaan Air Bersih & listrik Kerja 1 ls 1,500,000.00 1,500,000.00
Jumlah 3,380,000.00

II PEKERJAAN STRUKTUR

1 Galian Tanah Pondasi 11.16 m3 98,500.00 1,099,260.00


2 Galian Septick Tank 3.375 m3 98,500.00 332,437.50
3 Urugan Kembali Bekas Galian 7.56 m3 35,650.00 269,514.00
4 Urugan PasirPondasi 1.5 m3 135,750.00 203,625.00
5 Urugan Tanah Peninggian Lantai 7.2 m3 147,500.00 1,062,000.00
Jumlah 2,966,836.50

III PEKERJAAN PONDASI

1 Pek. Pas. Batu Belah 8.37 m3 967,000.00 8,093,790.00


Jumlah 8,093,790.00

IV PEKERJAAN BETON

1 Pek. Kolom 10/10 0.12 m3 4,164,920.00 499,790.40


2 Pek. Kolom 10/20 0.38 m3 3,665,140.00 1,392,753.20
2 Pek. Kolom 15/25 0.3 m3 4,164,920.00 1,249,476.00
3 Pek. Sloof 15/25 1.05 m3 3,665,140.00 3,848,397.00
4 Pek. Balok Lintel Beam 10/15 0.015 m3 3,896,870.00 58,453.05
6 Pek. Balok Gantung 15/25 0.27 m3 4,164,920.00 1,124,528.40
7 Pek. Ring balk 10/15 0.69 m3 4,153,370.00 2,865,825.30
Jumlah 11,039,223.35

V PEKERJAAN DINDING/PLESTERAN

1 Pek. Dinding Bata 125.98 m2 225,000.00 28,345,500.00


2 Pek. Plesteran + Acian 251.96 m2 52,250.00 13,164,910.00
3 Pek. Plesteran + Acian u/Beton Kolom 0.24 m2 52,250.00 12,540.00
Jumlah 41,522,950.00

VI PEKERJAAN KUSEN,PINTU DAN DAUN JENDELA

1 Pek. Kusen Kayu Meranti Bukit 0.38 m3 3,500,000.00 1,330,000.00


2 Pek. Daun Pintu Kayu Double Triplek 1.52 m2 441,900.00 671,688.00
3 Pek. Daun Pintu Fiber Kamar Mandi 1 Bh 235,000.00 235,000.00
4 Pek. Pintu Besi Polding Get 15 m2 967,000.00 14,505,000.00
5 Pek. Kusen Jendela 0.06 m2 3,500,000.00 210,000.00
6 Pek. Kaca Es Kamar Mandi 0.24 m2 53,000.00 12,720.00
7 Pas. Kunci Lkp Handle 1 bh 365,000.00 365,000.00
8 Pas. Engsel Pintu 3 bh 37,500.00 112,500.00
Jumlah 17,441,908.00

VII PEKERJAAN ATAP

1 Pemasangan setengahKuda kuda Baja Ringan 54 m2 275,000.00 14,850,000.00


2 Pemasangan Listpalnk Dari Woodplang 6 m1 32,500.00 195,000.00
3 Pemasangan Atap Genteng Metal 54 m2 78,500.00 4,239,000.00
4 Pemasangan Plafond Calsiboard + Rk Hollow 30 m2 136,500.00 4,095,000.00
Jumlah 23,379,000.00

VIII PEKERJAAN LANTAI

1 Urugan Pasir Bawah Lantai 2.85 m3 124,500.00 354,825.00


2 Lantai Keramik 30/30 Putih Polos 57.6 m2 134,500.00 7,747,200.00
3 Lantai Keramik 20/25 /KM/WC 6 m2 134,500.00 807,000.00
8,909,025.00

IX PEKERJAAN PENGECATAN

1 Pek. Cat Tembok 0.96 m2 24,250.00 23,280.00


2 Pek. Cat Plafond 48 m2 24,250.00 1,164,000.00
3 Pek. Cat Kayu 62.52 m2 32,830.00 2,052,531.60
Jumlah 3,239,811.60

X PEKERJAAN MEKANIKAL & ELEKTRIKAL

I PEKERJAAN PLUMBING
1 Instalasi Air Bersih
- PVC Dia 1/2 " 9 m1 17,500.00 157,500.00
- Accessories 1 ls 65,000.00 65,000.00
222,500.00

2 Instalasi Air Kotor


- PVC Dia 4" 10 m1 79,000.00 790,000.00
- Accessories 1 ls 124,500.00 124,500.00
- Bak Kontrol 1 unit 265,000.00 265,000.00
- Septicktank lkp Rembesan 1 unit 3,500,000.00 3,500,000.00
Jumlah 4,679,500.00
3 Alat Alat Sanitasi
- Kloset Jongkok 1 unit 265,000.00 265,000.00
- Kran Dindding 2 bh 29,500.00 59,000.00
- Jet Shower 1 bh 98,500.00 98,500.00
- Floor Drain Plastik 1 bh 35,000.00 35,000.00
- Tempat Sabun Keramik 1 bh 67,500.00 67,500.00
- Water Tank Stenless 1 bh 1,657,500.00 1,657,500.00
Jumlah 2,182,500.00

II PEKERJAAN ELEKTRIKAL

1 Pek. Titik Instalasi Penerangan 6 ttk 153,500.00 921,000.00


2 Pek. Titik Instalasi Stop Kontak 3 ttk 157,500.00 472,500.00
3 Lampu Tl 2 x 20 watt TKI 6 bh 253,000.00 1,518,000.00
4 Lampu PL 18 watt + fitting Plafond 1 bh 59,000.00 59,000.00
5 Saklar Tunggal 3 bh 21,500.00 64,500.00
6 Saklar Double 1 bh 23,000.00 23,000.00
7 Stop Kontak 3 bh 21,500.00 64,500.00
8 Panel lkp MCB 1 unit 1,750,000.00 1,750,000.00
Jumlah 4,872,500.00

JUMLAH 131,929,544.45

JUMLAH TOTAL 131,929,544.45