RENCANA ANGGARAN BIAYA (RAB)

PEMBANGUNAN ASRAMA SANTRI

HARGA JUMLAH HARGA SUB JUMLAH JUMLAH HARGA


NO URAIAN PEKERJAAN VOLUME SAT
SATUAN (Rp) (Rp) HARGA (Rp) TOTAL (Rp)

A LANTAI 01
I PEKERJAAN PERSIAPAN
1 Bongkaran Genteng Lama 1.000 Ls 300,000.00 300,000.00
2 Bongkaran Kuda-Kuda 1.000 Ls 1,200,000.00 1,200,000.00
3 Pek. Bongkaran Bangunan Lama 1.000 Ls 1,500,000.00 1,500,000.00
4 Pek. Buangan Bongkaran 1.000 Ls 2,000,000.00 2,000,000.00
Jumlah A.I 5,000,000.00
II PEKERJAAN TANAH
1 Galian Pondasi Footplat 77.295 m3 29,205.00 2,257,400.48
2 Urugan Tanah Kembali 25.765 m3 7,929.17 204,296.09
Jumlah A.II 2,461,696.56
III PEKERJAAN STRUKTUR
1 Beton Foot Plat K-250 16.891 m3 3,915,000.00 66,128,343.30
2 Beton Kolom K-250 16.748 m3 5,976,000.00 100,088,438.40
3 Beton Balok K-250 28.748 m3 5,976,000.00 171,795,060.00
4 Beton Plat Lantai K-225 45.144 m3 4,244,000.00 191,591,136.00
5 Beton Tangga 1.858 m3 4,700,000.00 8,732,600.00
Jumlah A.III 538,335,577.70
IV PEKERJAAN DINDING
1 Pek. Pasangan Batu Bata 1 Batu 75.200 m2 132,011.00 9,927,227.20
2 Pek. Pasangan Batu Bata 1/2 Batu 3.900 m2 63,750.50 248,626.95
3 Pek. Pasangan Roster Kotak 0.3x0.6 cm 42.000 bh 25,000.00 1,050,000.00
4 Pek. Plesteran Dinding 568.000 m2 24,875.40 14,129,227.20
5 Pek. Acian 568.000 m2 14,355.00 8,153,640.00
6 Pek. Sponengan 359.180 m' 4,707.45 1,690,821.89
Jumlah A.IV 35,199,543.24
V PEKERJAAN KUSEN
1 Pek. Pembuatan Kusen Aluminium 107.400 m' 117,813.00 12,653,116.20
2 Pek. Pembuatan DaunJendela Aluminium 45.000 bh 285,925.00 12,866,625.00
3 Pek. Pembuatan Daun Pintu Panil Jati 3.000 bh 342,830.00 1,028,490.00
4 Pek. Kaca bening 5 mm 10.238 m2 65,000.00 665,437.50
5 Pek. Pasang Selot Pintu 3.000 bh 150,550.00 451,650.00
6 Pek. Pasang Engsel Pintu 3.000 ps 35,000.00 105,000.00
7 Pek. Pasang engsel Jendela 45.000 ps 25,000.00 1,125,000.00
8 Pek. Pasang Hak Angin 45.000 ps 20,000.00 900,000.00
9 Pek. Pasang Grendel Tanam Jendela 45.000 bh 10,000.00 450,000.00
Jumlah A.V 30,245,318.70
VI PEKERJAAN LANTAI DAN PLAFOND
1 Pek. Pasangan Keramik Lantai 282.150 m2 118,817.00 33,524,216.55
2 Pek. Pasangan Keramik Dinding 111.419 m2 95,000.00 10,584,805.00
3 Pek. Pasangan Langit-langit Gypsum rangka hollow 0.4mm 376.200 m2 95,000.00 35,739,000.00
4 Pek. Pasang List Plafond t:12 cm gypsum 225.600 m' 14,750.00 3,327,600.00
Jumlah A.VI 83,175,621.55
VII PEKERJAAN ELEKTRIKAL
1 Pek. Instalasi Titik Lampu 47.000 ttk 130,000.00 6,110,000.00
2 Pek. Pasang Lampu Neon 1x20 W inbox 23.000 bh 175,000.00 4,025,000.00
3 Pek. Pasang Lampu XL 18 W Capp 6.000 bh 125,000.00 750,000.00
4 Pek. Pasang Saklar Single 3.000 bh 25,000.00 75,000.00
5 Pek. Pasang Saklar Double 9.000 bh 25,000.00 225,000.00
6 Pek. Stop Kontak 6.000 bh 25,000.00 150,000.00
Jumlah A.VII 11,335,000.00
VIII PEKERJAAN PENGECATAN
1 Pek. Cat Dinding dan plafond 944.200 m2 13,778.00 13,009,187.60
2 Pek. Pelitur Kayu 268.000 m2 18,293.00 4,902,524.00
Jumlah A.VIII 17,911,711.60
JUMLAH LANTAI 01 723,664,469.35
B LANTAI 02
I PEKERJAAN STUKTUR
1 Beton Kolom K-250 10.824 m3 5,976,000.00 64,681,714.08
2 Beton Ring Balok K-250 6.330 m3 5,976,000.00 37,828,080.00
Jumlah B.I 102,509,794.08
II PEKERJAAN PASANGAN
1 Pek. Pasangan Batu Bata 1/2 Batu 533.511 m2 63,750.50 34,011,561.13
2 Pek. Plesteran 1067.021 m2 24,875.40 26,542,574.18
3 Pek. Acian 1067.021 m2 14,355.00 15,317,086.46
4 Pek. Sponengan 718.360 m' 4,707.45 3,381,643.78
Jumlah B.II 79,252,865.55
III PEKERJAAN KUSEN DAN KACA
1 Pek. Pembuatan Kusen Aluminium 2.244 m3 117,813.00 264,315.82
2 Pek. Daun Jendela Kaca 5 mm Rangka Aluminium 50.074 m2 323,925.00 16,220,090.88
3 Pek. Pembuatan Daun Pintu Panil Jati 12.600 m2 342,830.00 4,319,658.00
4 Pek. Pasang Selot Pintu 8.000 bh 150,550.00 1,204,400.00
5 Pek. Pasang Engsel Pintu 8.000 psg 35,000.00 280,000.00
6 Pek. Pasang engsel Jendela 132.000 psg 25,000.00 3,300,000.00
7 Pek. Pasang Hak Angin 132.000 psg 20,000.00 2,640,000.00
8 Pek. Pasang Grendel Tanam Jendela 132.000 bh 10,000.00 1,320,000.00
Jumlah B.III 29,548,464.70
IV PEKERJAAN LANTAI DAN PLAFOND
1 Pek. Pasangan Keramik Lantai 402.900 m2 118,817.00 47,871,369.30
2 Pek. Pasangan Keramik Dinding 118.100 m2 95,000.00 11,219,500.00
3 Pek. Pasangan Langit-langit Gypsum rangka hollow 0.4mm 438.900 m2 95,000.00 41,695,500.00
4 Pek. Pasang List Plafond t:12 cm gypsum 305.200 m' 14,750.00 4,501,700.00
Jumlah B.IV 105,288,069.30
V PEKERJAAN ATAP
1 Pek. Rangka Atap Baja Ringan t:0.75 lapis alumunium foil 651.200 m2 400,000.00 260,480,000.00
2 Pek. Pasangan Genteng Vlampress Sokka 651.200 m2 46,500.00 30,280,800.00
3 Pek. Pasangan Bubungan Genteng Sejenis 43.000 m' 58,014.00 2,494,602.00
4 Pek. Pasangan Talang BJLS 0.2 12.600 m2 35,514.60 447,483.96
Jumlah B.V 293,702,885.96
VI PEKERJAAN ELEKTRIKAL
1 Pek. Instalasi Titik Lampu 51.000 ttk 130,000.00 6,630,000.00
2 Pek. Pasang Lampu Neon 1x20 W inbox 43.000 bh 175,000.00 7,525,000.00
3 Pek. Pasang Saklar Single 4.000 bh 25,000.00 100,000.00
4 Pek. Pasang Saklar Double 15.000 bh 25,000.00 375,000.00
5 Pek. Stop Kontak 8.000 bh 25,000.00 200,000.00
Jumlah B.VI 14,830,000.00
VII PEKERJAAN PENGECATAN
1 Pek. Cat Dinding dan plafond 1067.021 m2 13,778.00 14,701,415.34
2 Pek. Pelitur Kayu 335.000 m2 18,293.00 6,128,155.00
Jumlah B.VII 20,829,570.34
JUMLAH LANTAI 02 645,961,649.93
JUMLAH TOTAL 1,369,626,119.28
DIBULATKAN 1,370,000,000.00
Terbilang : Satu milyar Tiga Ratus Tujuh Puluh Juta Rupiah

Kayee Kunyet, 15 Oktober 2021


Pimpinan
 
  
( TGK. H. MARWAN ABDULLAH)