III ARSITEKTUR
A. Pekerjaan Lantai
1 Pek. Rabat Beton Lantai (K-100) 5 cm 1.42 m3 1,232,200.00 1,749,724.00 865,000.00 1,228,300.00
2 Pek. Urugan Pasir di Bawah Lantai 1.37 m3 409,200.00 560,604.00 310,000.00 424,700.00
3 Pek. Urugan Tanah Peninggian Lantai 5.10 m3 137,300.00 700,230.00 160,000.00 816,000.00
4 Pek. Lantai Keramik 30 x 30 cm 27.36 m2 254,700.00 6,968,592.00 145,000.00 3,967,200.00
5 Pek. Lantai Keramik KM / WC20 x 20 cm 1.63 m2 255,400.00 416,302.00 225,000.00 366,750.00
B. Pekerjaan Plafon dan Atap -
1 Memasang Rangka Hollow Galvalum 60x120cm Plafond 34.18 m2 161,800.00 5,530,324.00 95,500.00 3,264,190.00
2 Memasang penutup plafond kalsiboard 34.18 m2 69,800.00 2,385,764.00 44,672.00 1,526,888.96
3 Pekerjaan Penutup Atap Metal polos 49.82 m2 188,600.00 9,396,052.00 76,844.00 3,499,475.76
4 Pasangan bubungan atap metal 6.15 m 120,500.00 741,075.00 50,610.00 311,251.50
5 Pas.List plank Calsi plank 1x20 cm 24.28 m 66,700.00 1,619,476.00 32,688.00 793,664.64
C. Pekerjaan Kusen, Pintu dan Jendela -
1 Pek. Pembuatan dan Pemasangan Kusen Pintu dan Jendela Kayu 0.27 m3 26,907,600.00 7,265,052.00 6,991,952.00 1,887,827.04
3 Pek. Pembuatan Daun Pintu Tripleks rangkap tebal 4mm 5.69 m2 1,028,100.00 5,849,889.00 781,802.00 4,448,453.38
4 Pek. Pintu KM/WC Llapis fomika rangkap 1.00 unit 1,870,900.00 1,870,900.00 1,197,376.00 1,197,376.00
5 Pek. Daun Jendela Kayu Kelas II t=2cm 1.08 m2 911,600.00 984,528.00 583,424.00 630,097.92
6 Pek. Daun Jendela Kaca t = 3mm 2.51 m2 179,500.00 450,545.00 145,395.00 364,941.45
7 Pek. Pemasangan Kunci Tanam 5.00 unit 291,600.00 1,458,000.00 275,000.00 1,375,000.00
8 Pek. Pemasangan Engsel Pintu 5.00 unit 117,900.00 589,500.00 90,000.00 450,000.00
9 Pek. Pemasangan Engsel Jendela 6.00 unit 81,100.00 486,600.00 72,000.00 432,000.00
10 Pek. Rosster Beton 15 x 25 17.00 unit 89,900.00 1,528,300.00 60,000.00 1,020,000.00
11 Pek. Pemasangan Gerendel Jendela 6.00 unit 50,900.00 305,400.00 30,000.00 180,000.00
12 Pek. Pemasangan Hak Angin 6.00 unit 72,700.00 436,200.00 45,000.00 270,000.00
D. Pekerjaan Plesteran -
1 Pekerjaan Plesteran Dinding 202.74 m2 66,200.00 13,421,388.00 42,044.00 8,524,000.56
2 Pekerjaan Acian Dinding 192.41 m2 38,300.00 7,369,303.00 28,512.00 5,485,993.92
E. Pekerjaan Pengecatan -
1 Pek. Cat Tembok Luar dan Dalam (Plamir + Cat dasar + Cat Tembok) 192.41 m2 41,100.00 7,908,051.00 28,600.00 5,502,926.00
2 Pek. Cat Plafond 34.18 m2 41,100.00 1,404,798.00 24,000.00 820,320.00
3 Pek. Cat Kayu (Pintu + Lisplank + Jendela) 27.89 m2 51,500.00 1,436,335.00 65,000.00 1,812,850.00
4 Pembuatan dan Pemasangan Plat No Rumah 1.00 set 175,000.00 175,000.00 100,000.00 100,000.00
IV PEKERJAAN MEP
A. Pekerjaan Instalasi Listrik
1 Penyambungan Daya Listrik PLN SLO 1300 VA (include Panel & KWH meter) 1.00 Ls 1,825,000.00 1,825,000.00 1,850,000.00 1,850,000.00
2 Pek. Pasang Titik Lampu + instalasi 7.00 titik 365,700.00 2,559,900.00 165,000.00 1,155,000.00
3 Pek. Pasang Saklar Tunggal 3.00 buah 40,000.00 120,000.00 75,000.00 225,000.00
4 Pek Pasang Saklar Ganda 2.00 buah 53,800.00 107,600.00 90,000.00 180,000.00
5 Pek. Pasang Stop Kontak + Instalasi 3.00 buah 233,000.00 699,000.00 135,000.00 405,000.00
6 Pek. Pasang Lampu SL 20 Watt 7.00 buah 89,000.00 623,000.00 75,000.00 525,000.00
7 Pek. Pasang Box MCB Group 1.00 buah 863,900.00 863,900.00 550,000.00 550,000.00
B. Pekerjaan Plumbing -
1 Penyambungan Air Bersih (pompa air + pagar pengaman pompa) 0.50 Ls 1,350,000.00 675,000.00 1,150,000.00 3,450,000.00
1 Instalasi Air Bersih Pipa PVC dia 1/2" AW + Assesories 6.10 m 25,200.00 153,720.00 39,000.00 237,900.00
2 Kran Air 1.00 buah 75,900.00 75,900.00 85,000.00 85,000.00
3 Floor Drain 1.00 buah 40,600.00 40,600.00 45,000.00 45,000.00
4 Pasangan Closet Jongkok 1.00 buah 438,500.00 438,500.00 300,000.00 300,000.00
5 Instalasi Air Kotor Pipa PVC dia 3" D + Assesories 5.70 m 122,900.00 700,530.00 100,000.00 570,000.00
6 Instalasi Air Kotor Pipa PVC dia 4" D + Assesories 4.10 m 241,800.00 991,380.00 130,000.00 533,000.00
7 Pek. Pembuatan Septik Tank & Resapan Buis Beton 7.00 buah 572,000.00 4,004,000.00 650,000.00 4,550,000.00
Total 2 162,051,861.00 115,633,661.97
TOTAL 1 120,650,000.00 111,600,000.00
TOTAL 2 (76 Unit) 12,315,941,436.00 8,788,158,309.72
GRAND TOTAL 12,436,591,436.00 8,899,758,309.72
PPN 10 % 1,243,659,143.60 889,975,830.97
TOTAL 13,680,250,579.60 9,789,734,140.69
PEMBULATAN 13,680,000,000.00 9,780,000,000.00
PERHITUNGAN HARGA PER UNIT 180,000,000.00 128,684,210.53
Data Pendukung
- Jenis Pekerjaan : Pembangunan Rumah Khusus Nelayan Bilelando
- Spesifikasi : Pekerjaan Konstruksi Rumah Khusus
Harga RAB Harga RAP
- Harga RAB per Unit + PPN : Rp 180,000,000 per unit - Harga RAB per Unit + PPN : Rp 128,684,211 per unit
- Jumlah : 76 unit - Jumlah : 76 unit
Total : Rp 13,680,000,000 Total : Rp 9,780,000,000
Sistem Pembayaran
- Metode Pembayaran : DP 30%
Termin ke 2, senilai 30%, setelah pekerjaan selesai 80%
Termin ke 3, senilai 40%, setelah pekerjaan selesai 100%
Nilai Kontrak
- Nilai Kontrak : Rp 13,680,000,000
- Jaminan Pelaksanaan (5%) : Rp 684,000,000
A. Planing Cost Bulan Ke 1 Bulan Ke 2 Bulan Ke 3 Bulan Ke 4 Bulan Ke 5 Bulan Ke 6 Bulan Ke 7 Bulan Ke 8 Bulan Ke 9
1 Pembayaran Jaminan Pelaksanaan Rp 684,000,000 684,000,000
2 Pekerjaan Persiapan Rp 122,760,000 122,760,000
3 Pembelian Material Ke 1 Rp 4,394,079,155 4,394,079,155
4 Pembayaran Jasa Ke 1 Rp 274,629,947 274,629,947
5 Pembelian Material Ke 2 Rp 1,098,519,789 1,098,519,789
6 Pembayaran Jasa Ke 2 Rp 274,629,947 274,629,947
7 Pembelian Material Ke 3 Rp 1,098,519,789 1,098,519,789
8 Pembayaran Jasa Ke 3 Rp 274,629,947 274,629,947
9 Pembelian Material Ke 4 Rp 2,197,039,577 2,197,039,577
10 Pembayaran Jasa Ke 4 Rp 274,629,947 274,629,947
11 Pembayaran Jasa Ke 5 Rp 274,629,947 274,629,947
12 Pembayaran Jasa Ke 6 Rp 274,629,947 274,629,947
13 Pembayaran Jasa Ke 7 Rp 274,629,947 274,629,947
14 Pembayaran Jasa Ke 8 Rp 274,629,947 274,629,947
Total A 5,506,569,102 1,404,249,736 1,404,249,736 2,502,769,525 305,729,947 305,729,947 305,729,947 305,729,947 31,100,000 12,040,757,887
B. Income Cash From Invoice Rp
1 DP 30% Rp 4,104,000,000 4,104,000,000
2 Investasi Rp 5,000,000,000 5,000,000,000
3 Termin Ke 1 (30% pekerjaan), 30% Rp 4,104,000,000 4,104,000,000
4 Termin Ke 2 (100% pekerjaan), 40% Rp - 5,472,000,000 5,472,000,000
Total B Rp 9,104,000,000 - - 4,104,000,000 - - - - 5,472,000,000 14,576,000,000
C. Balance Rp 3,597,430,898 2,193,181,162 788,931,426 2,390,161,902 2,084,431,954 1,778,702,007 1,472,972,060 1,167,242,113 6,608,142,113 2,535,242,113