Anda di halaman 1dari 9

RENCANA ANGGARAN PROYEK

PROYEK PERUMAHAN GRAHA SWA BHUANA


TYPE 36

HARGA TOTAL
NO. JENIS PEKERJAAN SAT. Vol JUMLAH
SATUAN JUMLAH
A PEKERJAAN PERSIAPAN
1 Pembersihan Lokasi ls 1.00 200,000.00 200,000.00
2 Pengukuran dan bouwplank ls 1.00 200,000.00 200,000.00
3 Direksi Keet dan Gudang ls 1.00 200,000.00 200,000.00
4 Air kerja + Listrik kerja ls 1.00 200,000.00 200,000.00
800,000.00
B PEKERJAAN STRUKTUR PONDASI
1 Galian tanah Pondasi dan Footplate m3 6.62 50,000.00 331,200.00
2 Urugan pasir bawah pondasi t=5cm m3 1.66 266,666.67 442,666.67
3 Pondasi batu kali 1:8 uk.20x40x40 m3 7.97 750,000.00 5,976,000.00
4 Urugan tanah kembali m3 3.19 20,000.00 63,744.00
5 Urugan tanah untuk ketinggian tanah m3 5.40 50,000.00 270,000.00
7,083,610.67
C PEKERJAAN BETON
1 Sloof 15x20 m3 1.78 2,053,333.33 3,646,720.00
2 Kolom struktur 15x15 m3 1.95 2,053,333.33 3,999,996.00
3 Kolom praktis 15x15 m3 0.24 2,053,333.33 485,100.00
4 Balok latei 15x15 m3 0.38 2,053,333.33 771,540.00
5 Balok kanopi 15x20 m3 0.35 2,053,333.33 714,560.00
6 Plat beton kanopi tebal 12cm m3 0.60 2,053,333.33 1,229,536.00
7 Ring balok +325 uk. 15x20 m3 1.78 2,053,333.33 3,646,720.00
8 Ring balok +5,75 uk. 15x20 m3 1.08 2,053,333.33 2,217,600.00
9 Meja beton dapur m3 0.12 2,053,333.33 246,400.00
16,958,172.00
D PEKERJAAN PASANGAN DINDING
2 Pasangan Bata Biasa 1:8 m2 122.00 110,000.00 13,420,000.00
4 Plesteran Biasa 1:8 m2 132.54 30,000.00 3,976,200.00
5 Acian dinding m2 132.54 15,000.00 1,988,100.00
6 Sekonengan sudut m' 80.00 11,500.00 920,000.00
20,304,300.00
E PEKERJAAN ATAP
Rangka atap baja ,Gordeng C 150 ,usuk 120,000.00
1 m2 60.00 7,200,000.00
baja ringan
2 Penutup atap genteng beton m2 60.00 50,000.00 3,000,000.00
3 Genteng Nok m' 15.25 50,000.00 762,500.00
4 Talang cor m' 7.00 55,000.00 385,000.00
5 Listplank Atap GRC m' 30.39 25,000.00 759,750.00

12,107,250.00
F PEKERJAAN PLAFOND
Plafond Gypsum 9mm, rangka hollow 2x4 130,000.00
1 m2 36.00 4,680,000.00
dan 4x4
2 Cat Plafond m2 36.00 15,000.00 540,000.00
3 List profil sudut m' 55.00 10,000.00 550,000.00

5,770,000.00
HARGA TOTAL
NO. JENIS PEKERJAAN SAT. Vol JUMLAH
SATUAN JUMLAH
G PEKERJAAN KUSEN PINTU DAN JENDELA DAN Accesories
1 Kusen + Pintu Utama , 0,9*2,2 unit 1.00 1,250,000.00 1,250,000.00
2 Kusen + Pintu Kamar , 0,9*2,2 unit 2.00 1,250,000.00 2,500,000.00
Kusen + Pintu samping , 0,9*2,2 unit 1.00 1,250,000.00 1,250,000.00
4 Kusen + Pintu KM , 0,7*1,7 unit 1.00 900,000.00 900,000.00
5 Kusen + Jendela Kamar1 , 1,25*1,4 unit 1.00 850,000.00 850,000.00
6 Kusen + Jendela Kamar2 , 0,65*1,4 unit 1.00 600,000.00 600,000.00
7 Kusen + Jendela Ruang Tamu , 3*2 unit 1.00 2,500,000.00 2,500,000.00
10 Boven , 1,35*0,5 unit 1.00 500,000.00 500,000.00
10,350,000.00
H PEKERJAAN INSTALASI AIR
a. Air Bersih
1 Pipa PVC AW 1/2" m' 15.00 6,250.00 93,750.00
2 Pipa PVC AW 3/4" m' 24.00 10,000.00 240,000.00
b. Air Kotor
1 Pipa PVC D 2,5" m' 15.00 11,250.00 168,750.00
2 Pipa PVC D 4" m' 9.00 22,500.00 202,500.00
705,000.00
I PEKERJAAN INSTALASI LISTRIK
1 Sambung daya listrik 1300 va ls 1.00 2,500,000.00 2,500,000.00
2 Instalasi titik lampu + Fitting (tanpa bolam titik 8.00 150,000.00 1,200,000.00
3 Instalasi Stopkontak titik 5.00 150,000.00 750,000.00
4 Saklar Engkel Broco bh 4.00 35,000.00 140,000.00
5 Saklar Dobel Broco bh 2.00 45,000.00 90,000.00
6 Stopkontak Broco bh 5.00 35,000.00 175,000.00
7 Fitting + lampu bh 8.00 50,000.00 400,000.00
8 Box MCB 8 group unit 1.00 250,000.00 250,000.00
9 MCB 10A bh 1.00 55,000.00 55,000.00
5,560,000.00
J PEKERJAAN FINISHING LANTAI DAN DINDING
1 Urugan pasir bawah Lantai keramik t=5cm m3 1.80 266,666.67 480,000.00
2 Lantai kerja keramik t=5cm m3 1.80 500,000.00 900,000.00
3 Lantai kramik 50x50 Asia/setara m2 33.75 120,000.00 4,050,000.00
9 Kamar mandi m2
- Lantai - keramik 20x20 Asia/setara m2 2.25 80,000.00 180,000.00
- Dinding - Keramik 20x25 Asia/setara m2 9.44 95,000.00 896,800.00
10 Dapur
- Meja dapur m2 1.40 120,000.00 168,000.00
- Dinding dapur m2 3.20 120,000.00 384,000.00
11 Plint lantai 10cm m' 43.00 25,000.00 1,075,000.00
m2
8,133,800.00
K PEKERJAAN SANITAIR
a. Kamar mandi dalam
1 Closet duduk (Setara Volk) bh 1.00 2,000,000.00 2,000,000.00
2 Shower + Kran bh 1.00 150,000.00 150,000.00
3 Tempat sabun kecil 10x20cm bh 1.00 35,000.00 35,000.00
4 Floor Drain ex. San Ei bh 1.00 35,000.00 35,000.00
b. Dapur
1 Kitchen Zink ex.Royal SB 57 bh 1.00 450,000.00 450,000.00
2 Kran angsa bh 1.00 175,000.00 175,000.00
c. Taman Luar / Carport
1 Kran Taman bh 1.00 35,000.00 35,000.00
HARGA TOTAL
NO. JENIS PEKERJAAN SAT. Vol JUMLAH
SATUAN JUMLAH
2 Floor Drain ex. San Ei bh 1.00 35,000.00 35,000.00
2,915,000.00
L PEKERJAAN FINISHING
1 Cat dinding m2 117.54 25,000.00 2,938,500.00
3 Cat Listplank atap m' 30.39 15,000.00 455,850.00
4 Cat kerpusan atap / Nok m' 15.25 25,000.00 381,250.00
5 Cat atap genteng m2 60.00 25,000.00 1,500,000.00
5,275,600.00
M PEKERJAAN HALAMAN
1 Septictank + Sumur resapan unit 1.00 2,500,000.00 2,500,000.00
2 Bak kontrol Pasangan Bata 30x30 + tutup unit 1.00 500,000.00 500,000.00
3 Carport 0.00
- Rabat beton t=10cm m3 1.67 1,066,666.67 1,776,000.00
- Pasir bawah rabat beton t=5cm m3 0.23 266,666.67 60,000.00

4,836,000.00
TOTAL 100,798,732.67
TYPE 36 36.00
Harga /m2 2,799,964.80
RENCANA ANGGARAN PROYEK
PROYEK PERUMAHAN GRAHA SWA BHUANA
TYPE 43

HARGA TOTAL
NO. JENIS PEKERJAAN SAT. Vol JUMLAH
SATUAN JUMLAH
A PEKERJAAN PERSIAPAN
1 Pembersihan Lokasi ls 1.00 200,000.00 200,000.00
2 Pengukuran dan bouwplank ls 1.00 200,000.00 200,000.00
3 Direksi Keet dan Gudang ls 1.00 200,000.00 200,000.00
4 Air kerja + Listrik kerja ls 1.00 200,000.00 200,000.00
800,000.00
B PEKERJAAN STRUKTUR PONDASI
1 Galian tanah Pondasi dan Footplate m3 10.00 50,000.00 500,000.00
2 Urugan pasir bawah pondasi t=5cm m3 1.72 266,666.67 458,666.67
3 Pondasi batu kali 1:8 uk.20x40x40 m3 7.80 750,000.00 5,850,000.00
4 Urugan tanah kembali m3 3.00 20,000.00 60,000.00
5 Urugan tanah untuk ketinggian tanah m3 5.40 50,000.00 270,000.00
7,138,666.67
C PEKERJAAN BETON
1 Sloof 15x20 m3 1.85 2,053,333.33 3,794,560.00
2 Kolom struktur 15x15 m3 1.95 2,053,333.33 3,999,996.00
3 Kolom praktis 15x15 m3 0.24 2,053,333.33 485,100.00
4 Balok latei 15x15 m3 0.33 2,053,333.33 679,140.00
5 Balok kanopi 15x20 m3 0.35 2,053,333.33 714,560.00
6 Plat beton kanopi tebal 12cm m3 0.60 2,053,333.33 1,229,536.00
7 Ring balok +325 uk. 15x20 m3 1.85 2,053,333.33 3,794,560.00
8 Ring balok +5,75 uk. 15x20 m3 1.08 2,053,333.33 2,217,600.00
9 Meja beton dapur m3 0.12 2,053,333.33 246,400.00
17,161,452.00
D PEKERJAAN PASANGAN DINDING
2 Pasangan Bata Biasa 1:8 m2 168.57 110,000.00 18,542,150.00
4 Plesteran Biasa 1:8 m2 225.67 30,000.00 6,770,100.00
5 Acian dinding m2 225.67 15,000.00 3,385,050.00
6 Sekonengan sudut m' 80.00 11,500.00 920,000.00
29,617,300.00
E PEKERJAAN ATAP
Rangka atap baja ,Gordeng C 150 ,usuk 120,000.00
1 m2 63.00 7,560,000.00
baja ringan
2 Penutup atap genteng beton m2 63.00 50,000.00 3,150,000.00
3 Genteng Nok m' 15.25 50,000.00 762,500.00
4 Talang cor m' 7.00 55,000.00 385,000.00
5 Listplank Atap GRC m' 30.39 25,000.00 759,750.00

12,617,250.00
F PEKERJAAN PLAFOND
Plafond Gypsum 9mm, rangka hollow 2x4 130,000.00
1 m2 43.00 5,590,000.00
dan 4x4
2 Cat Plafond m2 43.00 15,000.00 645,000.00
3 List profil sudut m' 55.00 10,000.00 550,000.00

6,785,000.00
G PEKERJAAN KUSEN PINTU DAN JENDELA DAN Accesories
1 Kusen + Pintu Utama , 0,9*2,2 unit 1.00 1,250,000.00 1,250,000.00
2 Kusen + Pintu Kamar , 0,9*2,2 unit 2.00 1,250,000.00 2,500,000.00
HARGA TOTAL
NO. JENIS PEKERJAAN SAT. Vol JUMLAH
SATUAN JUMLAH
Kusen + Pintu samping , 0,9*2,2 unit 1.00 1,250,000.00 1,250,000.00
3 Kusen + Pintu belakang , 0,9*2,2 unit 1.00 1,250,000.00 1,250,000.00
4 Kusen + Pintu KM , 0,7*1,7 unit 1.00 900,000.00 900,000.00
5 Kusen + Jendela Kamar1 , 1,25*1,4 unit 1.00 850,000.00 850,000.00
6 Kusen + Jendela Kamar2 , 0,65*1,4 unit 1.00 600,000.00 600,000.00
7 Kusen + Jendela Ruang Tamu , 3*2 unit 1.00 2,500,000.00 2,500,000.00
8 Kusen + Jendela Dapur , 0,65*1,75 unit 1.00 1,000,000.00 1,000,000.00
9 Kusen + Jendela belakang , 0,65*1,75 unit 2.00 1,000,000.00 2,000,000.00
10 Boven , 1,35*0,5 unit 1.00 500,000.00 500,000.00
14,600,000.00
H PEKERJAAN INSTALASI AIR
a. Air Bersih
1 Pipa PVC AW 1/2" m' 15.00 6,250.00 93,750.00
2 Pipa PVC AW 3/4" m' 24.00 10,000.00 240,000.00
b. Air Kotor
1 Pipa PVC D 2,5" m' 15.00 11,250.00 168,750.00
2 Pipa PVC D 4" m' 9.00 22,500.00 202,500.00
705,000.00
I PEKERJAAN INSTALASI LISTRIK
1 Sambung daya listrik 1300 va ls 1.00 2,500,000.00 2,500,000.00
2 Instalasi titik lampu + Fitting (tanpa bolam titik 8.00 150,000.00 1,200,000.00
3 Instalasi Stopkontak titik 5.00 150,000.00 750,000.00
4 Saklar Engkel Broco bh 4.00 35,000.00 140,000.00
5 Saklar Dobel Broco bh 2.00 45,000.00 90,000.00
6 Stopkontak Broco bh 5.00 35,000.00 175,000.00
7 Fitting + lampu bh 8.00 50,000.00 400,000.00
8 Box MCB 8 group unit 1.00 250,000.00 250,000.00
9 MCB 10A bh 1.00 55,000.00 55,000.00
5,560,000.00
J PEKERJAAN FINISHING LANTAI DAN DINDING
1 Urugan pasir bawah Lantai keramik t=5cm m3 2.15 266,666.67 573,333.33
2 Lantai kerja keramik t=5cm m3 2.15 500,000.00 1,075,000.00
3 Lantai kramik 50x50 Asia/setara m2 40.75 120,000.00 4,890,000.00
9 Kamar mandi m2
- Lantai - keramik 20x20 Asia/setara m2 2.25 80,000.00 180,000.00
- Dinding - Keramik 20x25 Asia/setara m2 9.44 95,000.00 896,800.00
10 Dapur
- Meja dapur m2 1.40 120,000.00 168,000.00
- Dinding dapur m2 3.20 120,000.00 384,000.00
11 Plint lantai 10cm m' 43.00 25,000.00 1,075,000.00
m2
9,242,133.33
K PEKERJAAN SANITAIR
a. Kamar mandi dalam
1 Closet duduk (Setara Volk) bh 1.00 2,000,000.00 2,000,000.00
2 Shower + Kran bh 1.00 150,000.00 150,000.00
3 Tempat sabun kecil 10x20cm bh 1.00 35,000.00 35,000.00
4 Floor Drain ex. San Ei bh 1.00 35,000.00 35,000.00
b. Dapur
1 Kitchen Zink ex.Royal SB 57 bh 1.00 450,000.00 450,000.00
2 Kran angsa bh 1.00 175,000.00 175,000.00
c. Taman Luar / Carport
1 Kran Taman bh 2.00 35,000.00 70,000.00
HARGA TOTAL
NO. JENIS PEKERJAAN SAT. Vol JUMLAH
SATUAN JUMLAH
2 Floor Drain ex. San Ei bh 1.00 35,000.00 35,000.00
2,950,000.00
L PEKERJAAN FINISHING
1 Cat dinding m2 225.67 25,000.00 5,641,750.00
3 Cat Listplank atap m' 30.39 15,000.00 455,850.00
4 Cat kerpusan atap / Nok m' 15.25 25,000.00 381,250.00
5 Cat atap genteng m2 63.00 25,000.00 1,575,000.00
8,053,850.00
M PEKERJAAN HALAMAN
1 Septictank + Sumur resapan unit 1.00 2,500,000.00 2,500,000.00
2 Bak kontrol Pasangan Bata 30x30 + tutup unit 1.00 500,000.00 500,000.00
3 Carport 0.00
- Rabat beton t=10cm m3 1.67 1,066,666.67 1,776,000.00
- Pasir bawah rabat beton t=5cm m3 0.23 266,666.67 60,000.00

4,836,000.00
TOTAL 120,066,652.00
TYPE 43.00
Harga /m2 2,792,247.72
RENCANA ANGGARAN PROYEK
PROYEK PERUMAHAN GRAHA SWA BHUANA
TYPE 50

NO. JENIS PEKERJAAN SAT. Vol HARGA SATUAN JUMLAH TOTAL JUMLAH
A PEKERJAAN PERSIAPAN
1 Pembersihan Lokasi ls 1.00 200,000.00 200,000.00
2 Pengukuran dan bouwplank ls 1.00 200,000.00 200,000.00
3 Direksi Keet dan Gudang ls 1.00 200,000.00 200,000.00
4 Air kerja + Listrik kerja ls 1.00 200,000.00 200,000.00
800,000.00
B PEKERJAAN STRUKTUR PONDASI
1 Galian tanah Pondasi dan Footplate m3 11.01 50,000.00 550,400.00
2 Urugan pasir bawah pondasi t=5cm m3 1.72 266,666.67 458,666.67
3 Pondasi batu kali 1:8 uk.20x40x40 m3 8.71 750,000.00 6,532,500.00
4 Urugan tanah kembali m3 5.50 20,000.00 110,080.00
5 Urugan tanah untuk ketinggian tanah m3 25.20 50,000.00 1,260,000.00
8,911,646.67
C PEKERJAAN BETON
1 Sloof 15x20 m3 2.30 2,053,333.33 4,722,666.67
2 Kolom struktur 15x15 m3 1.95 2,053,333.33 3,999,996.00
3 Balok latei 15x15 m3 0.56 2,053,333.33 1,155,000.00
4 Balok kanopi 15x20 m3 0.44 2,053,333.33 905,520.00
5 Plat beton kanopi tebal 12cm m3 0.95 2,053,333.33 1,958,880.00
6 Ring balok +325 uk. 15x20 m3 2.30 2,053,333.33 4,722,666.67
7 Ring balok +5,75 uk. 15x20 m3 1.08 2,053,333.33 2,217,600.00
8 Meja beton dapur m3 0.12 2,053,333.33 246,400.00
19,928,729.33
D PEKERJAAN PASANGAN DINDING
1 Pasangan Bata Trasram 1:4 m2 186.79 110,000.00 20,546,900.00
2 Plesteran Biasa 1:8 m2 262.12 30,000.00 7,863,600.00
3 Acian dinding m2 262.12 15,000.00 3,931,800.00
4 Sekonengan sudut m' 80.00 11,500.00 920,000.00
33,262,300.00
E PEKERJAAN ATAP
1 Rangka atap baja ,Gordeng C 150 ,usuk baja ringan m2 69.14 120,000.00 8,296,800.00

2 Penutup atap genteng beton m2 69.14 50,000.00 3,457,000.00


3 Genteng Nok m' 15.90 50,000.00 795,000.00
4 Talang m' 3.35 55,000.00 184,250.00
5 Listplank Atap GRC m' 27.22 25,000.00 680,500.00

13,413,550.00
F PEKERJAAN PLAFOND
1 Plafond Gypsum 9mm, rangka hollow 2x4 dan 4x4 m2 48.25 130,000.00 6,272,500.00
2 Cat Plafond m2 48.25 15,000.00 723,750.00
3 List profil sudut m' 61.00 10,000.00 610,000.00

7,606,250.00
G PEKERJAAN KUSEN PINTU DAN JENDELA DAN Accesories
1 Kusen + Pintu Utama , 0,9*2,2 unit 1.00 1,250,000.00 1,250,000.00
2 Kusen + Pintu Kamar , 0,9*2,2 unit 4.00 1,250,000.00 5,000,000.00
4 Kusen + Pintu belakang , 0,9*2,2 unit 1.00 1,250,000.00 1,250,000.00
3 Kusen + Pintu KM , 0,7*1,7 unit 1.00 900,000.00 900,000.00
5 Kusen + Jendela Kamar1 , 1,25*1,4 unit 1.00 850,000.00 850,000.00
6 Kusen + Jendela Kamar2 , 0,65*1,4 unit 2.00 600,000.00 1,200,000.00
7 Kusen + Jendela Ruang Tamu , 3*2 unit 1.00 2,500,000.00 2,500,000.00
8 Kusen + Jendela Dapur , 0,65*1,75 unit 1.00 1,000,000.00 1,000,000.00
Kusen + Jendela belakang , 0,65*1,75 unit 1.00 1,000,000.00 1,000,000.00
9 Boven , 1,35*0,5 unit 1.00 500,000.00 500,000.00
15,450,000.00
H PEKERJAAN INSTALASI AIR
a. Air Bersih
1 Pipa PVC AW 1/2" m' 15.00 6,250.00 93,750.00
2 Pipa PVC AW 3/4" m' 24.00 10,000.00 240,000.00
b. Air Kotor
1 Pipa PVC D 2,5" m' 15.00 11,250.00 168,750.00
2 Pipa PVC D 4" m' 9.00 22,500.00 202,500.00
705,000.00
I PEKERJAAN INSTALASI LISTRIK
1 Sambung daya listrik 1300 va ls 1.00 2,500,000.00 2,500,000.00
2 Instalasi titik lampu + Fitting (tanpa bolam lampu) titik 12.00 150,000.00 1,800,000.00
3 Instalasi Stopkontak titik 8.00 150,000.00 1,200,000.00
4 Saklar Engkel Broco bh 5.00 35,000.00 175,000.00
5 Saklar Dobel Broco bh 3.00 45,000.00 135,000.00
6 Stopkontak Broco bh 7.00 35,000.00 245,000.00
7 Fitting + lampu bh 12.00 50,000.00 600,000.00
8 Box MCB 8 group unit 1.00 250,000.00 250,000.00
9 MCB 10A bh 1.00 55,000.00 55,000.00
6,960,000.00
J PEKERJAAN FINISHING LANTAI DAN DINDING
1 Urugan pasir bawah Lantai keramik t=5cm m3 2.50 266,666.67 666,666.67
2 Lantai kerja keramik t=5cm m3 2.50 500,000.00 1,250,000.00
3 Lantai kramik 50x50 Asia/setara m2 45.55 120,000.00 5,466,000.00
9 Kamar mandi m2
- Lantai - keramik 20x20 Asia/setara m2 2.70 80,000.00 216,000.00
- Dinding - Keramik 20x25 Asia/setara m2 9.44 95,000.00 896,800.00
10 Dapur
- Meja dapur m2 1.40 120,000.00 168,000.00
- Dinding dapur m2 3.20 120,000.00 384,000.00
11 Plint lantai 10cm m' 54.00 25,000.00 1,350,000.00

10,397,466.67
K PEKERJAAN SANITAIR
a. Kamar mandi dalam
1 Closet duduk (Setara Volk) bh 1.00 2,000,000.00 2,000,000.00
2 Shower + Kran bh 1.00 150,000.00 150,000.00
3 Tempat sabun kecil 10x20cm bh 1.00 35,000.00 35,000.00
4 Floor Drain ex. San Ei bh 1.00 35,000.00 35,000.00
b. Dapur
1 Kitchen Zink ex.Royal SB 57 bh 1.00 450,000.00 450,000.00
2 Kran angsa bh 1.00 175,000.00 175,000.00
c. Taman Luar / Carport
1 Kran Taman bh 2.00 35,000.00 70,000.00
2 Floor Drain ex. San Ei bh 1.00 35,000.00 35,000.00
2,950,000.00
L PEKERJAAN FINISHING
1 Cat dinding Dalam m2 262.12 25,000.00 6,553,000.00
3 Cat Listplank atap m' 27.22 15,000.00 408,300.00
4 Cat kerpusan atap / Nok m' 15.90 25,000.00 397,500.00
5 Cat atap genteng m2 69.14 25,000.00 1,728,500.00
9,087,300.00
M PEKERJAAN HALAMAN
1 Septictank + Sumur resapan unit 1.00 2,500,000.00 2,500,000.00
2 Bak kontrol Pasangan Bata 30x30 + tutup unit 1.00 500,000.00 500,000.00
3 Carport
- Rabat beton t=10cm m3 1.73 1,066,666.67 1,845,333.33
- Pasir bawah rabat beton t=5cm m3 0.87 266,666.67 230,666.67
4 Torn dan Mesin Pompa Air unit 1.00 5,400,000.00 5,400,000.00

10,476,000.00
TOTAL 139,948,242.67
TYPE 50.00
Harga /m2 2,798,964.85
PROYEK PERUMAHAN GRAHA SWA BHUANA

KEBUTUHAN PEMBIAYAAN LAPANGAN BANGUNAN RUMAH UNTUK 30 UNIT RUMAH

jml harga jual Total Harga Jual / Total Harga RAP / Total Harga
No Uraian Kerja Luas Harga RAP / m2
unit /unit 30 unit unit RAP / 30 unit

1 Type 36 / 72 36 10 255,000,000 2,550,000,000 2,799,964.80 100,798,733 1,007,987,327


2 Type 43 / 72 43 10 312,000,000 3,120,000,000 2,792,247.72 120,066,652 1,200,666,520
3 Type 50 / 84 50 10 400,000,000 4,000,000,000 2,798,964.85 139,948,243 1,399,482,427

30 9,670,000,000 3,608,136,273