Anda di halaman 1dari 3

RENCANA ANGARAN BIAYA

Pekerjaan : Pembangunan Rumah 2 Lantai


Lokasi :
Th : 2022

HARGA JUMLAH HARGA


NO JENIS PEKERJAAN SAT VOLUME TOTAL HARGA Rp.
SATUAN (Rp.) (Rp.)

I PEKERJAAN PERSIAPAN
1 Pengukuran m2 144.00 17,034.90 2,453,025.60
2 Air Kerja ls 1.00 500,000.00 500,000.00
3 Listrik ls 1.00 500,000.00 500,000.00
4 Pembersihan lokasi m2 144.00 5,000.00 720,000.00
4,173,025.60

II PEKERJAAN TANAH DAN URUGAN


1 Galian tanah pondasi m3 33.00 44,800.00 1,478,400.00
2 Urugan tanah kembali m3 11.00 21,480.00 236,280.00
3 Urugan pasir bawah pondasi m3 1.65 340,080.00 561,132.00
4 Tanah Timbun T= 20 cm m3 72.80 156,000.00 11,356,800.00
13,632,612.00
III PEKERJAAN PASANGAN DAN PLESTERAN
1 Pas. Bata Merah 1:4 m2 525.08 148,449.00 77,948,194.72
2 Plesteran 1 : 4 m2 1,050.17 53,813.94 56,513,677.74
3 Acian Plesteran m2 525.08 18,475.00 9,700,926.90
144,162,799.36
IV PEKERJAAN BETON BERTULANG
1 Sloof 20/40 camp. 1pc:2ps:3split m3 12.00 4,737,718.00 56,861,712.42
2 Kolom utama 15/40 camp. 1pc:2ps:3split K1 m3 12.29 4,737,718.00 58,217,078.78
3 Balok 15/25 camp. 1pc:2ps:3split m3 3.38 4,737,718.00 15,992,356.62
4 Foot plat 100x100 cm tbl 20 cm camp. 1pc:2ps:3split m3 5.20 4,737,718.00 24,636,133.60
5 Foot plat 50x50 cm tbl 20 cm camp. 1pc:2ps:3split m3 0.85 4,737,718.00 4,027,060.30
6 Plat Lantai T= 10 cm camp. 1pc:2ps:3split m3 22.46 4,737,718.00 106,428,097.15
7 Tangga camp. 1pc:2ps:3split m3 9.80 4,737,718.00 46,429,636.40
312,592,075.27
V PEKERJAAN PINTU DAN JENDELA
1 Kusen dan pintu Aluminium set 20.00 900,000.00 18,000,000.00
2 Jendela dan Daun Aluminium set 24.00 450,000.00 10,800,000.00
3 Pintu Garasi set 4.00 4,500,000.00 18,000,000.00
4 Pintu Piber set 4.00 500,000.00 2,000,000.00
48,800,000.00
VI PEKERJAAN SANITAIR
1 Saluran air kotor Ø 4" m 80.00 80,000.00 6,400,000.00
2 Kran air Ø1/2" bh 8.00 75,000.00 600,000.00
3 Saluran air bersih m 60.00 25,000.00 1,500,000.00
4 Klosen duduk bh 8.00 3,500,000.00 28,000,000.00
5 Floor drain bh 8.00 55,000.00 440,000.00
6 Bak cuci piring stainless steel bh 4.00 900,000.00 3,600,000.00
7 Water Tank bh 4.00 1,200,000.00 4,800,000.00
8 Septick tank ls 4.00 3,250,000.00 13,000,000.00
58,340,000.00
VII PEKERJAAN PENGECATAN
1 Cat tembok m2 1,050.17 39,549.00 41,533,094.23
41,533,094.23
VIII INSTALASI LISTRIK
1 Titik lampu (siap nyala lampu SL) ttk 35.00 350,000.00 12,250,000.00
2 Stop kontak ttk 14.00 80,000.00 1,120,000.00
3 Kotak MCB bh 1.00 650,000.00 650,000.00
4 Pasang Baru PLN ttk 1.00 4,500,000.00 4,500,000.00
18,520,000.00
IX PEKERJAAN ATAP
1 Kuda-kuda Rangka baja m3 142.21 250,000.00 35,553,600.00
2 Atap genteng Metal m3 142.21 200,000.00 28,442,880.00
3 Lisplank m' 136.00 85,000.00 11,560,000.00
4 Bubungan m' 42.00 70,000.00 2,940,000.00
78,496,480.00
X PEKERJAAN PLAFON
1 Pekerjaan Plafon m2 158.40 230,000.00 36,432,000.00
36,432,000.00
XI PEKERJAAN LANTAI
1 Pasang Rabat Beton Lantai 1 T= 5 cm m3 7.20 1,419,630.00 10,221,336.00
2 Pasang keramik 50/50 cm m2 288.00 220,000.00 63,360,000.00
3 Pasang keramik KM/WC 20/20 cm m2 30.00 140,000.00 4,200,000.00
4 Pasang keramik Dinding KM/WC 20/40 cm m2 98.00 150,000.00 14,700,000.00
92,481,336.00
XIII PEKERJAAN LAIN LAIN
1 Biaya Lain Lain LS 1.00 5,000,000.00 5,000,000.00
5,000,000.00
TOTAL 854,163,422.46
REKAPITULASI ANGGARAN BIAYA

Pekerjaan : Pembangunan Rumah 2 Lantai


Lokasi :
Th : 2022

JUMLAH HARGA
NO JENIS PEKERJAAN
(RP.)

I PEKERJAAN PERSIAPAN 4,173,025.60


II PEKERJAAN TANAH DAN URUGAN 13,632,612.00
III PEKERJAAN PASANGAN DAN PLESTERAN 144,162,799.36
IV PEKERJAAN BETON BERTULANG 312,592,075.27
V PEKERJAAN PINTU DAN JENDELA 48,800,000.00
VI PEKERJAAN SANITAIR 58,340,000.00
VII PEKERJAAN PENGECATAN 41,533,094.23
VIII INSTALASI LISTRIK 18,520,000.00
IX PEKERJAAN ATAP 78,496,480.00
X PEKERJAAN PLAFON 36,432,000.00
XI PEKERJAAN LANTAI 92,481,336.00
XIII PEKERJAAN LAIN LAIN 5,000,000.00

JUMLAH BIAYA 854,163,422.46


ONGKOS TUKANG 213,540,855.62
JUMLAH 1,067,704,278.08
DIBULATKAN 1,067,704,000.00
TERBILANG ; SATU MILYAR ENAM PULUH TUJUH JUTA TUJUH RATUS EMPAT RIBU RUPIAH

Anda mungkin juga menyukai