Anda di halaman 1dari 6

RENCANA ANGGARAN BIAYA

PEKERJAAN : LISTRIK WAREHOUSE TRAKINDO


LOKASI : MUARA TEWEH

NO URAIAN PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH

PEKERJAAN LISTRIK
1 Tarikan Lampu ( NYM 2x1,5 mm², Eterna) Titik 12.00 144,000.00 1,728,000.00
2 Tarikan Stop Kontak ( NYM 3x2,5 mm², Eterna) Titik 4.00 229,200.00 916,800.00
3 Stop Kontak 1 Phase 16A Titik 4.00 72,000.00 288,000.00
4 Saklar Double (Seri) 10A Titik 6.00 74,400.00 446,400.00
5 MCB 1 Phase 6A - 40A bh 4.00 50,000.00 200,000.00
1 Box MCB bh 1.00 75,000.00 75,000.00
2 Lampu TL LED 16W 120cm bh 4.00 173,760.00 695,040.00
Lampu LED HIGHBAY 200 WATT PHILIPS LAMPU GANTUNG LED HIGH -
3 BY229P bh 8.00 4,333,440.00 34,667,520.00
39,016,760.00

727368478.xls / rab (2) Hal. 1 / 6


RENCANA ANGGARAN BIAYA
PEKERJAAN : LISTRIK WAREHOUSE TRAKINDO
LOKASI : MUARA TEWEH

NO URAIAN PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH

I PEKERJAAN PERSIAPAN
1 Mobilisasi / demob peralatan dan material Ls 4.00 7,000,000.00 28,000,000.00
2 Mobilisasi / demob tenaga kerja Ls 1.00 2,500,000.00 2,500,000.00
3 Penyediaan daya listrik dan air kerja Ls 1.00 5,000,000.00 5,000,000.00
4 Gudang sementara dan ruangan kerja Ls 1.00 1,000,000.00 1,000,000.00
5 Pembersihan dan Buang Puing Ls 1.00 3,000,000.00 3,000,000.00
39,500,000.00
PEKERJAAN LISTRIK
A PEKERJAAN TANAH dan PONDASI
1 Tarikan Lampu ( NYM 2x1,5 mm², Eterna) m' 62.00 47,500.00 2,945,000.00
2 Galian tanah biasa sedalam sampai 1 meter m 3
7.78 81,000.00 629,856.00
3 Pondasi plat 90x90x25, beton K300 Titik 8.00 935,000.00 7,480,000.00
4 Kolom pedestal 30/30, beton K-300 m' 15.60 665,625.00 10,383,750.00
5 Sloof beton struktur 15/25, beton K-300 m' 67.40 281,250.00 18,956,250.00
6 Pas. Angkur besi 3/4" x 800 mm bh 64.00 62,000.00 3,968,000.00
44,362,856.00
B PEKERJAAN PASANGAN DAN PLESTERAN
1 Kolom beton 15/15, beton K-300 m' 24.00 176,250.00 4,230,000.00
2 Ring balok beton 15/15, beton K-300 m' 69.40 243,750.00 16,916,250.00
3 Pasangan bata m² 54.90 133,000.00 7,301,700.00
4 Plesteran + Acian m² 109.80 68,000.00 7,466,400.00
5 Besi siku 40x40x4 U/rangka dinding Kg 1,857.93 63,114.00 117,261,604.40
6 Pasang Zincalumn tct 0,35 m² 459.90 135,000.00 62,086,500.00
7 CNP 125 u/ rangka pintu Kg 162.60 63,114.00 10,262,336.40
225,524,790.80
C PEKERJAAN LANTAI
1 Cor lantai tebal 25 cm, beton K-300 m3 48.00 1,375,000.00 66,000,000.00
2 Water Proofing Sika m² 192.00 102,500.00 19,680,000.00
3 Pasang Wiremesh Uk.M10 m² 384.00 198,000.00 76,032,000.00
161,712,000.00

727368478.xls / rab (3) Hal. 2 / 6


NO URAIAN PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH

D BANGUNAN UTAMA
1 Struktur WF 250.125.6.9 kg 1,430.40 63,114.00 90,278,265.60
2 Struktur Wf 200.100.5,5.8 kg 1,592.82 63,114.00 100,529,090.01
3 Rafter WF 200.100.5,5.8 kg 85.36 63,114.00 5,387,411.04
4 Gordeng CNP 125.50.2,3 kg 614.27 63,114.00 38,768,826.40
5 Base plat 15 mm kg 175.00 63,114.00 11,045,151.96
6 Plat joint 15 mm kg 291.67 63,114.00 18,408,586.61
7 Trekstank besi 12 mm kg 93.45 63,114.00 5,898,003.30
8 Brecing besi 16 mm bh 12.00 63,114.00 757,368.00
9 Baut M16 bh 256.00 75,000.00 19,200,000.00
10 Dudukan Talang plat setrip 50.4 kg 21.60 63,114.00 1,363,262.40
11 Pasang talang datar, Z/A tct 0,40 mm, lebar 30 cm m' 34.00 224,000.00 7,616,000.00
12 Talang vertikal PVC 4" m' 56.00 145,000.00 8,120,000.00
13 Pasang atap Zincalumn tct 0,35 m² 222.02 135,000.00 29,972,700.00
14 Pasang nok Z/A tct 0,40 mm m' 17.00 125,000.00 2,125,000.00
15 Pas. InsulasiThick 4mm m' 222.02 45,000.00 9,990,900.00
16 Pintu Rollingdoor m² 16.00 1,000,000.00 16,000,000.00
365,460,565.32
E PEK. CAT
1 Pek.Cat Dinding m² 118.80 24,500.00 2,910,600.00
2,910,600.00
TOTAL 839,470,812.12

727368478.xls / rab (3) Hal. 3 / 6


RENCANA ANGGARAN BIAYA
PEKERJAAN : RUANG PRODUKSI (A-1)
LOKASI : PT. CIPTA DWI BUSANA
SPESIFIKASI :
PANJANG : 108.00 M
LEBAR : 36.00 M
LUAS : 3,888.00 M2
JUMLAH : 1.00 UNIT

Harga Jumlah Bobot


No Uraian pekerjaan Satuan Volume Satuan Harga Pekerjaan
(Rp) (Rp) (%)
I PEKERJAAN PERSIAPAN
1 Mobilisasi & demobilisasi ls 1 ### 10,000,000.00
2 Kantor dan gudang sementara untuk kontraktor m2 24 500,000.00 12,000,000.00
3 Penyediaan air dan listrik untuk pekerjaan ls disediakan owner
4 Penyiapan as built drawing laporan akhir ls 1 5,000,000.00 5,000,000.00
5 Keselamatan, kesehatan dan keamanan kerja
(safety dan peralatan kerja, Asuransi karyawan/pekerja,
penyimpanan dan pembuangan material hasil kerja ls 1 5,000,000.00 5,000,000.00
6 Pengukuran dan pemasangan bouwplank untuk gedu m' 310.00 42,000.00 13,020,000.00
SUB TOTAL 45,020,000.00
II PEKERJAAN BONGKARAN
1 Bongkar Kanopy ls 1 8,000,000.00 8,000,000.00
2 Bobok beton untuk lobang pondasi setempat ls 1 5,000,000.00 5,000,000.00
3 Bobok beton untuk sloof dan balok tarik ls 1 7,000,000.00 7,000,000.00
4 Bobok jalan beton ls 1 7,000,000.00 7,000,000.00
5 Angkut bekas bongkaran keluar area pekerjaan ls 1 5,000,000.00 5,000,000.00
SUB TOTAL 32,000,000.00
III PEKERJAAN SIPIL
A PEKERJAAN TANAH DAN PONDASI
1 Galian tanah biasa sedalam sampai 1 meter m3 #REF! 52,000.00 #REF!
2 Urugan tanah peninggian peil lantai m3 #REF! 9,000.00 #REF!
3 Pasangan batu kosong m3 11.25 158,000.00 1,777,500.00
4 Urugan pasir bawah pondasi dan bawah lantai m3 #REF!
5 Lantai kerja, 1 Pc : 3 Ps : 5 Kr m3 5.63 640,000.00 3,600,000.00
6 Pondasi setempat uk. 1,5x1,5m tebal 40 cm m3 #REF! #REF! #REF!
7 Sloof 20/40 mutu beton K-225 m' 252.50 #REF! #REF!
8 Angkur besi 1" x 800 mm bh 100.00 60,000.00 6,000,000.00
SUB TOTAL #REF!
B PEKERJAAN PASANGAN
1 Pasangan pondaTurap teras/selasar batu kali m3 80.00 430,000.00 34,400,000.00
2 Pasangan pondaTurap jalan batu kali m3 162.00 430,000.00 69,660,000.00
3 Pasangan pondaTurap loading area batu kali m3 47.00 430,000.00 20,210,000.00
4 Pasangan pondaTurap jalan batako press m' 24.00 430,000.00 10,320,000.00
SUB TOTAL 134,590,000.00
C PEKERJAAN DINDING
1 Pasangan dinding batako press (18X36) m2 ### 62,000.00 122,264,000.00
2 Pasangan roster 20x40 cm m' 48.00 78,000.00 3,744,000.00
3 Kolom praktis 15/20 m' 438.00 120,000.00 52,560,000.00
4 Balok latei 15/20 m' 324.00 120,000.00 38,880,000.00
5 Ring balok 15/20 m2 324.00 120,000.00 38,880,000.00
6 Plesteran batu kali 1pc:4ps m2 205.00 42,000.00 8,610,000.00
7 Plesteran 1 Pc : 4 Ps, tebal 15 mm m2 ### 29,000.00 125,802,000.00
8 Plesteran skoneng 1 Pc : 2 Ps ( untuk gedung ) m' ### 6,600.00 10,771,200.00
9 Acian dinding bata m2 ### 8,700.00 37,740,600.00
SUB TOTAL 439,251,800.00
D PEKERJAAN LANTAI
1 Urugan sirtu tebal 20 cm (dipadatkan) m2 ### 29,000.00 112,752,000.00
2 Cor lantai beton K-225 Lapis wire mesh M-8 m2 ### 154,000.00 598,752,000.00
3 Finishing lantai ploor hardiner (natural) m2 ### 20,000.00 77,760,000.00
4 Cutting lantai lebar 3x1 cm m' 684.00 15,000.00 10,260,000.00
5 Pek. Lantai panel beton HCS 15 CM m2 828.00 450,000.00 372,600,000.00
6 Finishing lantai HCS m2 648.00 22,000.00 14,256,000.00
7 Pasang lantai keramik 40/40 m2 300.00 83,000.00 24,900,000.00
8 Pasang plint keramik ukuran 10 x 40 cm m' 140.00 11,000.00 1,540,000.00
SUB TOTAL ###
E PEKERJAAN TOILET
1 Sloof 15/30 mutu beton K-225 m' 60.00 170,000.00 10,200,000.00
2 Kolom praktis 15/20 m' 86.00 124,000.00 10,664,000.00
3 Pasangan dinding batako press (18X36) m2 96.00 62,000.00 5,952,000.00
4 Plesteran 1 Pc : 4 Ps, tebal 15 mm m2 192.00 29,600.00 5,683,200.00
5 Acian dinding bata m2 134.00 8,700.00 1,165,800.00
6 Pasang keramik dinding 20/25 m2 72.00 110,000.00 7,920,000.00
7 Pasang lantai keramik 20/20 m2 120.00 80,000.00 9,600,000.00
8 Memasang kloset jongkok porselen unit 18.00 140,000.00 2,520,000.00
9 Memasang kran diameter 3/4" atau 1/2" bh 33.00 30,000.00 990,000.00
10 Memasang pintu PVC unit 18.00 414,000.00 7,452,000.00
11 Memasang floor drain bh 20.00 50,000.00 1,000,000.00
12 Septicktang dan sumur resapan unit 2.00 7,000,000.00 14,000,000.00
13 Instalasi air bersih ls 1.00 7,000,000.00 7,000,000.00
14 Instalasi air kotor ls 1.00 4,500,000.00 4,500,000.00
SUB TOTAL 88,647,000.00
IV PEKERJAAN KONSTRUKSI BESI
A PEKERJAAN KONSTRUKSI BESI RUANGPRODUKSI uk. 36x108 m, luas 3.888 m2
1 Kolom WF 400x200 kg ### 13,500.00 203,148,000.00 100.00
2 Rafter HoneyComb 400x150 kg ### 13,500.00 395,369,100.00 100.00
3 Kolom gebel Wf 200x100 kg ### 13,500.00 41,472,000.00 100.00
4 Konsol WF 150x75 kg 798.00 13,500.00 10,773,000.00 100.00
5 Balok gelagar 2xCNP 100x50x2,3 m' 150.00 213,000.00 31,950,000.00 100.00
6 Tie beam 2xCNP 125x50x2,3 m' 77.00 104,000.00 8,008,000.00 100.00
7 Rafter monitor UNP 100x50 unit 16.00 860,000.00 13,760,000.00 100.00
8 Gordeng CNP 125X50X2,3 m' ### 56,000.00 273,840,000.00 100.00
9 Rangka kawat monitor besi hollo 40x40 m' 168.00 222,000.00 37,296,000.00 100.00
10 Trekstank besi 10 mm bh ### 19,000.00 24,016,000.00 100.00
11 Brecing besi 16 mm bh 152.00 182,000.00 27,664,000.00 100.00
12 Listplank Z/A tct 0,35 Rangka besi hollo 40x40 m' 437.00 193,000.00 84,341,000.00 100.00
13 Pasang talang datar, Z/A tct 0,40 mm, lebar 50 cm m' 69.00 150,000.00 10,350,000.00 100.00
14 Pasang talang datar, Z/A tct 0,70 mm, lebar 70 cm m' 158.00 220,000.00 34,760,000.00 100.00
15 Talang vertikal PVC 6" m' 104.00 79,000.00 8,216,000.00 100.00
16 Talang vertikal PVC 8" m' 56.00 126,000.00 7,056,000.00 100.00
17 Pasang atap Zincalumn + Pe foam m2 ### 110,000.00 547,800,000.00 100.00
18 Pasang nok Z/A tct 0,4 mm m' 117.00 72,000.00 8,424,000.00 100.00
SUB TOTAL ###
B PEKERJAAN KONSTRUKSI BESI RUANG PRODUKSI 9x66 m, luas 1188 m2 (2lt)
1 Kolom WF 300x150 kg ### 13,500.00 23,787,000.00 100.00
2 Balok WF 300x150 kg ### 13,500.00 152,604,000.00 100.00
3 Rafter WF 200x100 kg ### 13,500.00 31,104,000.00 100.00
4 Tie beam 2xCNP 125x50x2,3 m' 66.00 104,000.00 6,864,000.00 100.00
5 Gordeng CNP 125X50X2,3 m' 552.00 56,000.00 30,912,000.00 100.00
6 Trekstank besi 10 mm bh 168.00 19,000.00 3,192,000.00 100.00
7 Brecing besi 16 mm bh 16.00 182,000.00 2,912,000.00 100.00
8 Pasang atap Zincalumn + Pe foam m2 621.00 110,000.00 68,310,000.00 100.00
SUB TOTAL 319,685,000.00
C PEKERJAAN KONSTRUKSI BESI OFFICE 5x36 m, 180 m2 (2lt)
1 Kolom WF 300x150 kg ### 13,500.00 23,787,000.00 100.00
2 Balok WF 300x150 kg ### 13,500.00 71,847,000.00 100.00
3 Rafter WF 200x100 kg 896.00 13,500.00 12,096,000.00 100.00
4 Tie beam 2xCNP 125x50x2,3 m' 36.00 104,000.00 3,744,000.00 100.00
5 Gordeng CNP 125X50X2,3 m' 195.00 56,000.00 10,920,000.00 100.00
6 Trekstank besi 10 mm bh 48.00 19,000.00 912,000.00 100.00
7 Brecing besi 16 mm bh 6.00 182,000.00 1,092,000.00 100.00
8 Listplank Z/A tct 0,35 Rangka besi hollo 40x40 m' 50.00 193,000.00 9,650,000.00 100.00
9 Pasang talang datar, Z/A tct 0,40 mm, lebar 50 cm m' 38.00 150,000.00 5,700,000.00 100.00
10 Talang vertikal PVC 4" m' 32.00 44,000.00 1,408,000.00 100.00
11 Pasang atap Zincalumn + Pe foam m2 234.00 110,000.00 25,740,000.00 100.00
12 Balok tangga wf 150x75 kg 504.00 13,500.00 6,804,000.00 100.00
13 Anak tangga besi siku 40x40, plat bordes 4mm kg 142.00 13,500.00 1,917,000.00 100.00
14 Ralling tangga besi Ø 1-1/2" kg 130.00 13,500.00 1,755,000.00 100.00
SUB TOTAL 177,372,000.00
V PEKERJAAN PENGECATTAN
1 Pengecatan besi dengan cat besi FTALIT m2 ### 26,000.00 167,518,000.00 100.00
2 Pengecatan tembok baru (1 lapis plamir, 2 lapis ca m2 ### 11,500.00 51,428,000.00
SUB TOTAL 218,946,000.00
VI PEKERJAAN LAIN-LAIN
1 Jendela nako & kawat loket 50x50 m2 170.00 300,000.00 51,000,000.00 100.00
2 Pintu gudang besi plat 1,2 mm, rangka hollo 50x50 m2 112.00 760,000.00 85,120,000.00 100.00
3 Pintu gudang wire mesh rangka hollo m3 112.00 500,000.00 56,000,000.00 100.00
4 Memasang buis beton, Ø 30 cm - 100 cm m' 144.00 200,000.00 28,800,000.00 100.00
5 Bak kontrol pas. bata (60 x 60) cm, tingg 65 cm bh 10.00 490,000.00 4,900,000.00 100.00
6 Membersihkan lapangan dan perataan ls 1.00 5,000,000.00 5,000,000.00
SUB TOTAL 230,820,000.00

TOTAL #REF!
DIBULATKAN #REF!

Cicurug, 10 Januari 2012


Dibuat oleh :
PT. BATU ALAM ABADI

DENI GUNAWAN

Anda mungkin juga menyukai