50,058,312.65
7. Pekerjaan Mekanikal Dan Elektrikal
5.1 Lampu LED 12 Watt 5 Titik 200,000.00 1,000,000.00
5.2 Pasang Kabel NYM 2 x 2,5 Sqmm 40 M' 18,315.00 732,600.00
5.3 Upah Pasang Box KWH Meter (1 Unit) 1 Unit 10,000,000.00 10,000,000.00
5.4 Upah Pasang Box Panel dan Panel Kontrol 1 Unit 1 Unit 300,000.00 300,000.00
5.5 Pemasangan Saklar Tunggal 2 Unit 69,300.00 138,600.00
5.6 Pemasangan Stop Kontak 2 Unit 69,301.00 138,602.00
5.7 Memasang Pipa PVC tipe AW Ø ¾" 70 M' 22,321.00 1,562,470.00
5.8 Memasang Pipa PVC tipe AW Ø 3" 62 M' 70,116.00 4,347,192.00
5.9 L bow Ø3/4'' 6 Unit 7,000.00 42,000.00
5.10 L bow Ø3'' 6 Unit 20,000.00 120,000.00
5.11 Memasang Kran Ø ¾" atau ½" 2 Unit 45,574.00 91,148.00
5.12 Memasang Floor Drain 1 Unit 83,985.00 83,985.00
18,556,597.00
TOTAL 207,844,846.82
BIL OF QUALITY PERTASHOP SIPIONGOT
2. Septick Tank
2.1 Galian Tanah 5 M3 116,325.00 523,462.50
2.2 Memasang dinding bata merah ukuran (5 x 11 x 22) cm tebal 1/2 bata, campuran spesi 1 PC : 4 PP 10 M2 117,048.00 1,170,480.00
2.3 Membuat beton mutu f’c = 14,5 MPa (K 175), slump (12 ± 2) cm, w/c = 0,66 1 M3 1,085,376.00 651,225.60
2.4 Besi Ø8 4 Kg 40,920.00 155,617.27
2,500,785.37
TOTAL 15,530,304.27
BIL OF QUALITY PERTASHOP SIPIONGOT