Anda di halaman 1dari 3

RENCANA ANGGARAN BIAYA (RAB)

VOLUME HARGA SATUAN JUMLAH


NO. URAIAN PEKERJAAN
SATUAN ( Rp. ) ( Rp. )

A. PEKERJAAN GEDUNG
I. PEKERJAAN PERSIAPAN 52,000,000.00
-
1 Mobilisasi dan Demobilisasi 1.00 Ls 40,000,000.00 40,000,000.00
2 Pengadaan Listrik Kerja Dan Air Kerja 1.00 Ls 12,000,000.00 12,000,000.00

II. PEKERJAAN BONGKARAN & GALIAN 232,616,000.00


1 Pekerjaan galian pondasi 24.00 m3 756,000.00 18,144,000.00
2 pekerjaan galian septitank 6.00 m3 756,000.00 4,536,000.00
3 urugan 356.00 m3 556,000.00 197,936,000.00
4 Pekerjaan Sumur Air 1.00 unit 12,000,000.00 12,000,000.00

III. PEKERJAAN STRUKTUR BETON 2,879,047,727.76


a. Lantai Dasar
1 Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm site mix (kolom praktis) 266.00 m' 260,000.00 69,160,000.00
2 Membuat 1 m’ ring balok beton bertulang (10 x 15) cm (balok lintel di atas kusen) 476.00 m' 341,500.00 162,554,000.00
3 Balok 48.00 m3 6,219,800.00 298,550,400.00
4 kolom utama 46.60 m3 6,792,137.00 316,513,584.20
dak lt1 98.40 m3 7,485,000.00 736,524,000.00
b. Lantai Atas
1 Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm site mix (kolom praktis) 245.00 m' 88,871.20 21,773,444.00
2 Pekerjaan Plat Kanopi Beton t. 10 cm Site Mix K-175 5.08 m3 105,493.85 535,908.76
3 Membuat 1 m’ ring balok beton bertulang (10 x 15) cm (balok lintel di atas kusen) 209.30 m3 105,493.85 22,079,862.81
4 Pekerjaan Plat Meja Beton ( t = 8 cm ) Site Mix K-175 1.08 m3 6,680,600.00 7,215,048.00
Dak Lt 2 136.22 m3 7,485,000.00 1,019,606,700.00
balok 36.10 m3 6,219,800.00 224,534,780.00
IV. PEKERJAAN DINDING 598,320,218.60
a. Lantai Dasar
1 Pemasangan 1 m2 Dinding hebel (10x20x60) + Space PM 110 468.00 m2 189,383.91 88,631,668.13
2 Pemasangan plesteran 1PC : 5PP tebal 20 mm 847.25 m2 70,910.40 60,078,836.40
3 Pemasangan acian 847.25 m2 53,088.00 44,978,808.00
4 Pemasangan 1 m2 Dinding Keramik ukuran 20x25 88.75 m2 301,345.00 26,744,368.75
5 Pemasangan 1 m' List Border ukuran 8x20 161.00 m' 96,835.20 15,590,467.20
6 glass block 10.00 m 680,000.00 6,800,000.00
b. Lantai Atas
1 Pemasangan 1 m2 Dinding hebel (10x20x60) + Space PM 110 748.00 m2 189,383.91 141,659,161.88
2 Pemasangan plesteran 1PC : 5PP tebal 20 mm 772.25 m2 70,910.40 54,760,556.40
3 Pemasangan acian 772.25 m2 43,615.00 33,681,683.75
3 Pemasangan 1 m2 Dinding Keramik ukuran 20x25 Toilet + Meja Beton 723.75 m2 117,561.84 85,085,381.70
4 Pemasangan 1 m' List Border ukuran 8x20 332.00 m' 96,835.20 32,149,286.40
5 glass block 12.00 m2 680,000.00 8,160,000.00

V. PEKERJAAN LANGIT-LANGIT 240,004,802.30


b. Lantai Atas
1 Pemasangan 1 m2 Rangka Plafond Besi Hollow Galvanize, Modul 60x60 889.00 m2 139,562.50 124,071,062.50
2 Pemasangan 1 m2 Langit-langit Gypsum Board ukuran 120x240x8 mm, tebal 9 mm 889.00 m2 68,019.00 60,468,891.00
3 Pemasangan 1 m2 Langit-langit Gypsum Board Drop Ceilling ukuran 120x240x8 mm, tebal 9 mm 134.00 m2 53,913.20 7,224,368.80
4 Pemasangan 1 m' List Plafond Gypsum 920.00 m' 46,884.00 43,133,280.00
5 Pemasangan 1 m2 Langit-langit GRC Board ukuran 120x240x8 mm, tebal 4 mm 64.00 m2 79,800.00 5,107,200.00

1
VOLUME HARGA SATUAN JUMLAH
NO. URAIAN PEKERJAAN
SATUAN ( Rp. ) ( Rp. )
VI. PEKERJAAN KUSEN PINTU & JENDELA 598,087,400.00
a. Lantai Dasar
1 Pekerjaan Kusen Pintu Alumunium Type PJ1 14.00 unit 7,731,300.00 108,238,200.00
2 Pekerjaan Kusen Pintu Alumunium Type PJ3 14.00 unit 3,944,300.00 55,220,200.00
3 Pekerjaan Kusen Pintu Alumunium Type P1 14.00 unit 3,780,900.00 52,932,600.00
4 Pekerjaan Kusen Pintu Alumunium Type PG 14.00 unit 3,359,900.00 47,038,600.00

b. Lantai Atas
1 Pekerjaan Kusen Pintu Alumunium Type PJ2 18.00 unit 4,640,500.00 83,529,000.00
2 Pekerjaan Kusen Pintu Alumunium Type P1 18.00 unit 3,944,300.00 70,997,400.00
3 Pekerjaan Kusen Pintu Alumunium Type P1.b 18.00 unit 3,780,900.00 68,056,200.00
4 Pekerjaan Kusen Pintu Alumunium Type P2 18.00 unit 6,226,400.00 112,075,200.00

VII. PEKERJAAN LANTAI 658,619,280.00


a. Lantai Dasar
1 Pemasangan m2 Granit 60x60 377.00 m2 429,000.00 161,733,000.00

b. Lantai Atas
1 Pemasangan m2 Granit 60x60 783.00 m2 429,000.00 335,907,000.00
2 Pemasangan 1 m2 Lantai Keramik ukuran 20x20 (Warna) 112.00 m2 265,760.00 29,765,120.00
3 1 m2 Water Proofing (untuk daerah basah) 833.00 m2 85,305.00 71,059,065.00
4 Pekerjaan Screed (di atas waterproof) 833.00 m2 72,215.00 60,155,095.00

VIII. PEKERJAAN PENGECATAN 124,987,775.83


a. Lantai Dasar
1 1 m2 Pengecatan Tembok Baru Interior ( 1 lapis Plamur, 1 Lapis Cat dasar. 2 Lapis cat penutup) (ex. VINILEX, Pas. Bata) 1,048.00 m2 43,340.00 45,420,320.00

a. Lantai Dasar
1 1 m2 Pengecatan Tembok Baru Interior ( 1 lapis Plamur, 1 Lapis Cat dasar. 2 Lapis cat penutup) (ex. VINILEX, Pas. Bata) 1,226.00 m2 43,340.00 53,134,840.00
2 1 m2 Pengecatan Plafond Vinilex (ex. VINILEX) 1,115.07 m2 23,705.00 26,432,615.83

IX. PEKERJAAN SANITAIR DAN PLUMBING 274,630,469.90


a. Lantai Dasar
1 Pemasangan 1 m’ pipa PVC tipe AW diameter 1/2” 89.00 m' 23,303.50 2,074,011.50
2 Pemasangan 1 m’ pipa PVC tipe AW diameter 3/4” 100.00 m' 26,422.00 2,642,200.00
3 Pemasangan 1 m’ pipa PVC tipe AW diameter 2” (wastafel) 76.00 m' 63,244.50 4,806,582.00
4 Memasang 1 Buah Wastafel 2.00 bh 2,727,049.60 5,454,099.20
pasangan septitank 2.00 bh 4,875,000.00 9,750,000.00
a. Lantai Dasar
1 Pemasangan 1 m’ pipa PVC tipe AW diameter 1/2” 377.00 m' 23,303.50 8,785,419.50
2 Pemasangan 1 m’ pipa PVC tipe AW diameter 3/4” 379.00 m' 26,422.00 10,013,938.00
3 Pemasangan 1 m’ pipa PVC tipe AW diameter 4” (air kotor) 166.00 m' 126,170.00 20,944,220.00
4 Pemasangan 1 m’ pipa PVC tipe AW diameter 3” (air kotor) 166.00 m' 111,468.50 18,503,771.00
5 Pemasangan 1 m’ pipa PVC tipe AW diameter 2” (wastafel) 89.00 m' 63,244.50 5,628,760.50
6 Memasang 1 Buah Closet Jongkok 4.00 bh 676,318.50 2,705,274.00
7 Memasang 1 Buah Closet Duduk 30.00 bh 4,398,750.00 131,962,500.00
8 Memasang 1 Buah Jet Washer 30.00 bh 155,000.00 4,650,000.00
9 Memasang 1 Buah Wastafel 2.00 bh 2,727,049.60 5,454,099.20
10 Memasang 1 Buah Kitchen Zink 3.00 bh 555,445.00 1,666,335.00
11 Memasang 1 Buah Kran 1/2" atau 3/4" 34.00 bh 158,895.00 5,402,430.00
12 Memasang 1 Buah Floor Drain 34.00 bh 77,495.00 2,634,830.00
Pemasangan Torn Air 8.00 bh 3,944,000.00 31,552,000.00

2
VOLUME HARGA SATUAN JUMLAH
NO. URAIAN PEKERJAAN
SATUAN ( Rp. ) ( Rp. )
X. PEKERJAAN MEKANIKAL DAN ELEKTRIKAL 278,986,336.00
a. Lantai Dasar
1 Penambahan Daya Listrik instal kwh prabayar 33.00 Ls 1,850,000.00 61,050,000.00
2 Pengadaan Internet 1.00 10,000,000.00 10,000,000.00
pemasangan CCTV 24.00 ttk 3,860,000.00 92,640,000.00

a. Lantai Dasar
1 Instalasi Titik Listrik / Stop Kontak (ttk lampu) 65.00 ttk 298,000.00 19,370,000.00
2 Instalasi Titik Listrik / Stop Kontak (ttk stop kontak) 65.00 ttk 298,000.00 19,370,000.00
3 Instalasi Titik Listrik / Stop Kontak (ttk stopkontak AC + Exhaust Fan) 65.00 ttk 298,000.00 19,370,000.00
4 Pemasangan Saklar Engkel/Seri 36.00 bh 55,784.00 2,008,224.00
5 Pemasangan Stop Kontak 65.00 bh 55,784.00 3,625,960.00
6 Pemasangan Stop Kontak AC 28.00 bh 85,184.00 2,385,152.00
7 Pasangan Lampu Downlight + LED 9 watt 69.00 bh 115,000.00 7,935,000.00
8 Pasangan Lampu Downlight + LED 5 watt 65.00 bh 105,000.00 6,825,000.00
9 Pasangan Exhaust Fan Type Ceilling 12" 30.00 bh 780,000.00 23,400,000.00
10 Panel Pembantu Lengkap berikut Pasang + Instalasi (Penerangan dan AC) 3.00 unit 2,100,000.00 6,300,000.00
11 Pasangan Arde Panel 3.00 set 250,000.00 750,000.00
12 Kepala Penangkal Petir 2.00 bh 63,000.00 126,000.00
13 Kabel BCC lengkap klem 18.00 m' 110,000.00 1,980,000.00
14 Pipa GIP medium-B dia. 1" Sparing 3.00 btg 367,000.00 1,101,000.00
15 Pasangan Arde 3.00 set 250,000.00 750,000.00

XI. PEKERJAAN INTERIOR AULA 311,244,100.00


1 Pekerjaan Ornamen Backdrop 90.00 m2 1,600,000.00 144,000,000.00
2 Pekerjaan Frame Pintu Masuk 31.88 m2 950,000.00 30,284,100.00
3 pengadaan Kasur 32.00 unit 1,300,000.00 41,600,000.00
4 Pengadaan Lemari 32.00 unit 1,600,000.00 51,200,000.00
5 Pengadaan Hanger 32.00 unit 55,000.00 1,760,000.00
6 Pengadaan Kursi Meja 8.00 set 4,500,000.00 36,000,000.00
7 Pengadaan Jemuran 32.00 unit 200,000.00 6,400,000.00
8 Pemasangan AC 30.00 unit 6,200,000.00 186,000,000.00
9 Pekerjaan dapur umum 3.00 unit 22,000,000.00 66,000,000.00
XII. PEKERJAAN LAIN-LAIN 402,202,000.00
1 Perapihan Pekerjaan 1.00 Ls 25,000,000.00 25,000,000.00
2 Pemasangan Tangga Vertikal Stainless Steel (Lebar 50 cm) 77.00 m' 876,000.00 67,452,000.00
3 Pemasangan Pagar Railing 354.00 m' 875,000.00 309,750,000.00
4 paving bock 299.00 m2 380,000.00 113,620,000.00
B. PEKERJAAN KANOPI 370,939,159.71
a. Kanopi Depan
1 Pemasangan Rangka Kanopi Hollow Staenless Steel 104.50 m2 680,000.00 71,060,000.00
2 Pemasangan UPVC Rofftop Double Layer, Warna SEMI-TR 104.50 m2 330,000.00 34,485,000.00

Atap Atas
1 Rangka Atap Baja Ringan (Metal Zingkalum) 346.00 m2 361,000.00 124,906,000.00
2 Pemasangan 1 m2 Genteng Bitumen Onduvilla 346.00 m2 402,000.00 139,092,000.00
3 Pemasangan 1 m' Listplank GRC 1/20 20.90 m' 66,801.90 1,396,159.71

Jumlah 7,021,685,270.10