MASJID CICALENGKA
V PEKERJAAN LANTAI
1 Urugan pasir bawah lantai 112,8000 m3 225.000,00 25.380.000,00
2 Lantai kerja 5 cm 28,2000 m3 650.000,00 18.330.000,00
3 Keramik lantai Granit 484,0000 m2 420.000,00 203.280.000,00
4 Keramik lantai kolam / wc 80,0000 m2 175.000,00 14.000.000,00
5 Lantai Pavling Blok 42,0000 m2 175.000,00 7.350.000,00
6 Material bantu pasang keramik 684,0000 m2 20.000,00 13.680.000,00
JUMLAH PEKERJAAN LANTAI 282.020.000,00
IX PEKERJAAN LISTRIK
1 Titik lampu, kabel 2.5 x 2 mm 70,0000 ttk 175.000,00 12.250.000,00
2 Stop kontak, kabel 3 x 4.0 mm 25,0000 ttk 155.000,00 3.875.000,00
4 Pasang Saklar Tunggal, Ganda 20,0000 ttk 90.000,00 1.800.000,00
5 Pasang Lampu Downlight 64,0000 ttk 145.000,00 9.280.000,00
6 Pasang Lampu Spotlight 15,0000 ttk 325.000,00 4.875.000,00
7 Pasang Lampu LED Strip 16,0000 ttk 743.000,00 11.888.000,00
8 Pasang Lampu Gantung 1,0000 bh 13.500.000,00 13.500.000,00
9 Pasang Lampu Flood Light 12,0000 ttk 420.000,00 5.040.000,00
10 Panel Penerangan Daya Box sekering + mcb 1,0000 bh 10.772.000,00 10.772.000,00
11 Pentanahan / arde 1,0000 bh 1.250.000,00 1.250.000,00
JUMLAH PEKERJAAN LISTRIK 74.530.000,00