VI Pekerjaan Plafond
Pasang rangka plafond hollow 40/40, 20/40 m2 12.00 120,000 1,440,000
Pasang Plafon gypsum board 9mm ruang dalam m2 12.00 135,000 1,620,000
Pasang Plafon GRC board 4 mm teras luar m2 8.25 130,000 1,072,500
Pasang List Palfond m' 246.00 35,000 8,610,000
Sub Total Pekerjaan Plafond 12,742,500
IX Instalasi Penerangan
1 Instalasi Titik Listrik / lampu ttk 20.00 300,000 6,000,000
2 Instalasi Titik Listrik/Stop Kontak ttk 10.00 330,000 3,300,000
3 Lampu Downlight bh 20.00 200,000 4,000,000
4 Stop Kontak bh 10.00 55,000 550,000
5 Saklar Seri bh 4.00 50,000 200,000
6 Saklar Tunggal bh 1.00 45,000 45,000
Sub Total Instalasi Penerangan 14,095,000
1 RENCANA PEKERJAAN FISI 1.36% 8.01% 13.30% 18.59% 27.77% 37.64% 47.51% 57.38% 68.48% 79.17% 96.07% 100.00%
Dibuat Oleh :
I Pekerjaan Persiapan
1 Pengukuran dan Pemasangan Bowplank m' 100.00 75,000 7,500,000
2 Pembersihan dan Buang puing selama proyek ls 1.00 10,000,000 10,000,000
3 Alat Bantu Steger ls 1.00 15,000,000 15,000,000
Sub Total Pekerjaan Persiapan 32,500,000
II Pekerjaan Pondasi & Struktur
1 Galian Tanah Pondasi m3 148.00 135,000 19,980,000
2 Urugan Pasir m3 4.60 450,000 2,070,000
3 Lantai Kerja tebal 5 cm di bawah pondasi m2 92.00 75,000 6,900,000
4 Cor Pondasi Tapak m3 7.50 6,000,000 45,000,000
5 Pondasi Batu Belah m3 46.80 1,500,000 70,200,000
6 Urugan Tanah kembali m3 49.33 65,000 3,206,667
7 Sloof uk. 15 x 20 cm m3 1.86 3,500,000 6,510,000
8 Pemadatan tanah ruang dalam m2 324.00 30,000 9,720,000
9 Pemadatan tanah lantai teras m2 177.50 30,000 5,325,000
10 Urugan Pasir dibawah lantai m3 22.68 350,000 7,938,000
11 Lantai Kerja tebal 5 cm bawah lantai m2 501.50 75,000 37,612,500
12 Kolom Beton 25/25 cm m3 5.00 4,500,000 22,500,000
13 Balok Beton 15/30 cm m3 3.51 4,700,000 16,497,000
Sub Total Pekerjaan Pondasi & Struktur 253,459,167
VI Pekerjaan Plafond
Pasang rangka plafond hollow 40/40, 20/40 m2 388.80 120,000 46,656,000
Pasang Plafon gypsum board 9mm ruang dalam m2 388.80 135,000 52,488,000
Pasang Plafon GRC board 4 mm teras luar m2 195.25 130,000 25,382,500
Pasang List Palfond m' 246.00 35,000 8,610,000
Harga Satuan Jumlah Harga
No Jenis Pekerjaan Satuan Volume
(Rp.) (Rp.)
Sub Total Pekerjaan Plafond 133,136,500
IX Instalasi Penerangan
1 Instalasi Titik Listrik / lampu ttk 20.00 300,000 6,000,000
2 Instalasi Titik Listrik/Stop Kontak ttk 10.00 330,000 3,300,000
3 Lampu Downlight bh 20.00 200,000 4,000,000
4 Stop Kontak bh 10.00 55,000 550,000
5 Saklar Seri bh 4.00 50,000 200,000
6 Saklar Tunggal bh 1.00 45,000 45,000
Sub Total Instalasi Penerangan 14,095,000
Total 1,197,429,417
Terbilang : Satu milyar seratus sembilan puluh tujuh juta empat ratus dua puluh sembilan ribu empat ratus tujuh belas
rupiah.
I Pekerjaan Persiapan
1 Pengukuran dan Pemasangan Bowplank m' 100.00 75,000 7,500,000
2 Pembersihan dan Buang puing selama proyek ls 1.00 10,000,000 10,000,000
3 Alat Bantu Steger ls 1.00 15,000,000 15,000,000
Sub Total Pekerjaan Persiapan 32,500,000
II Pekerjaan Pondasi & Struktur
1 Galian Tanah Pondasi m3 148.00 135,000 19,980,000
2 Urugan Pasir m3 4.60 450,000 2,070,000
3 Lantai Kerja tebal 5 cm di bawah pondasi m2 92.00 75,000 6,900,000
4 Cor Pondasi Tapak m3 7.50 6,000,000 45,000,000
5 Pondasi Batu Belah m3 46.80 1,500,000 70,200,000
6 Urugan Tanah kembali m3 49.33 65,000 3,206,667
7 Sloof uk. 15 x 20 cm m3 1.86 3,500,000 6,510,000
8 Pemadatan tanah ruang dalam m2 324.00 30,000 9,720,000
9 Pemadatan tanah lantai teras m2 177.50 30,000 5,325,000
10 Urugan Pasir dibawah lantai m3 22.68 350,000 7,938,000
11 Lantai Kerja tebal 5 cm bawah lantai m2 501.50 75,000 37,612,500
12 Kolom Beton 25/25 cm m3 5.00 4,500,000 22,500,000
13 Balok Beton 15/30 cm m3 3.51 4,700,000 16,497,000
Sub Total Pekerjaan Pondasi & Struktur 253,459,167
VI Pekerjaan Plafond
Pasang rangka plafond hollow 40/40, 20/40 m2 388.80 120,000 46,656,000
Pasang Plafon gypsum board 9mm ruang dalam m2 388.80 135,000 52,488,000
Pasang Plafon GRC board 4 mm teras luar m2 195.25 130,000 25,382,500
Pasang List Palfond m' 246.00 35,000 8,610,000
Harga Satuan Jumlah Harga
No Jenis Pekerjaan Satuan Volume
(Rp.) (Rp.)
Sub Total Pekerjaan Plafond 133,136,500
IX Instalasi Penerangan
1 Instalasi Titik Listrik / lampu ttk 20.00 300,000 6,000,000
2 Instalasi Titik Listrik/Stop Kontak ttk 10.00 330,000 3,300,000
3 Lampu Downlight bh 20.00 200,000 4,000,000
4 Stop Kontak bh 10.00 55,000 550,000
5 Saklar Seri bh 4.00 50,000 200,000
6 Saklar Tunggal bh 1.00 45,000 45,000
Sub Total Instalasi Penerangan 14,095,000
Total 1,197,429,417
Terbilang : Satu milyar seratus sembilan puluh tujuh juta empat ratus dua puluh sembilan ribu empat ratus tujuh belas
rupiah.
Sloof Beton 17 x 30
Jendela 1*1 36 bh
JADWAL WAKTU PELAKSANAAN
Pekerjaan : PEMBANGUNAN AULA SERBAGUNA PONDOK PESANTREN NUR RAUDHATUL JANNAH
Lokasi : CARINGIN, BOGOR
SERAH TERIMA
IV Pekerjaan Finishing Lantai 9.08 4.54 4.54
Dibuat Oleh :
I Pekerjaan Persiapan
1 Pengukuran dan Pemasangan Bowplank m' 100.00 75,000 7,500,000
2 Pembersihan dan Buang puing selama proyek ls 1.00 10,000,000 10,000,000
3 Alat Bantu Steger ls 1.00 15,000,000 15,000,000
Sub Total Pekerjaan Persiapan 32,500,000
II Pekerjaan Pondasi & Struktur
1 Galian Tanah Pondasi m3 148.00 135,000 19,980,000
2 Urugan Pasir m3 4.60 450,000 2,070,000
3 Lantai Kerja tebal 5 cm di bawah pondasi m2 92.00 75,000 6,900,000
4 Cor Pondasi Tapak m3 7.50 6,000,000 45,000,000
5 Pondasi Batu Belah m3 46.80 1,500,000 70,200,000
6 Urugan Tanah kembali m3 49.33 65,000 3,206,667
7 Sloof uk. 15 x 20 cm m3 1.86 3,500,000 6,510,000
8 Pemadatan tanah ruang dalam m2 324.00 30,000 9,720,000
9 Pemadatan tanah lantai teras m2 177.50 30,000 5,325,000
10 Urugan Pasir dibawah lantai m3 22.68 350,000 7,938,000
11 Lantai Kerja tebal 5 cm bawah lantai m2 501.50 75,000 37,612,500
12 Kolom Beton 25/25 cm m3 5.00 4,500,000 22,500,000
13 Balok Beton 15/30 cm m3 3.51 4,700,000 16,497,000
Sub Total Pekerjaan Pondasi & Struktur 253,459,167
VI Pekerjaan Plafond
Pasang rangka plafond hollow 40/40, 20/40 m2 388.80 120,000 46,656,000
Pasang Plafon gypsum board 9mm ruang dalam m2 388.80 135,000 52,488,000
Pasang Plafon GRC board 4 mm teras luar m2 195.25 130,000 25,382,500
Pasang List Palfond m' 246.00 35,000 8,610,000
Harga Satuan Jumlah Harga
No Jenis Pekerjaan Satuan Volume
(Rp.) (Rp.)
Sub Total Pekerjaan Plafond 133,136,500
IX Instalasi Penerangan
1 Instalasi Titik Listrik / lampu ttk 20.00 300,000 6,000,000
2 Instalasi Titik Listrik/Stop Kontak ttk 10.00 330,000 3,300,000
3 Lampu Downlight bh 20.00 200,000 4,000,000
4 Stop Kontak bh 10.00 55,000 550,000
5 Saklar Seri bh 4.00 50,000 200,000
6 Saklar Tunggal bh 1.00 45,000 45,000
Sub Total Instalasi Penerangan 14,095,000
Total
Terbilang : Satu milyar seratus sembilan puluh tujuh juta empat ratus dua puluh sembilan ribu empat ratus tujuh belas
rupiah.