Anda di halaman 1dari 2

RENCANA ANGGARAN BIAYA

Proyek : RUMAH TINGGAL


Owner : Orang Tua Ibu Ria
Alamat : Bintara
Pemborong : Lokal Desain

CCO
No Uraian Pekerjaan
Sat Volume Harga Satuan (Rp) Jumlah Harga (Rp)

A PEKERJAAN PERSIAPAN
1 Survey lokasi ls free -
2 Design 2D, 3D & RAB ls free -
3 Mobilisasi, demobilisasi ls 1.00 500,000.00 500,000.00
4 Pasang proteksi terpal + rangka m2 105.00 55,000.00 5,775,000.00
Total 6,275,000.00
B PEKERJAAN BONGKARAN
1 Bongkar Penutup Atap + rangka m2 50.95 65,000.00 3,311,750.00
2 Bongkar bubungan ls 1.00 500,000.00 500,000.00
3 Bongkar listplank ls 1.00 350,000.00 350,000.00
4 Bongkar plafond dan rangka m2 90.00 35,000.00 3,150,000.00
5 Bongkar pintu besi eksisting ls 1.00 150,000.00 150,000.00
6 Bongkar atap spandek + rangka ls 1.00 250,000.00 250,000.00
7 Bongkar keramik area laundry room ls 1.00 350,000.00 350,000.00
8 Bongkar meja beton dan kitchen set ls 1.00 500,000.00 500,000.00
Total 8,561,750.00
C PEKERJAAN PERBAIKAN
I Pekerjaan Struktur
1 Galian tanah untuk pondasi setempat ttk - 150,000.00 -
2 Urugan tanah kembali ttk - 95,000.00 -
3 Pondasi setempat 80x80 ttk - 875,000.00 -
4 Pondasi setempat 120x120 ttk - - -
5 Pedestal beton 25x25 m3 - 4,300,000.00 -
6 Sloof beton 40x20 m3 1.38 4,700,000.00 6,486,000.00
7 Lantai kerja m2 - 145,000.00 -
8 Kolom beton 15x20 m3 0.12 5,100,000.00 612,000.00
9 Kolom praktis 15x15 m3 - 5,100,000.00 -
10 Balok beton 40x20 m3 1.38 5,300,000.00 7,314,000.00
11 Balok beton 25x15 m3 0.56 5,300,000.00 2,981,250.00
12 Balok gantung ambang atas kusen m3 - 5,100,000.00 -
13 Pekerjaan Tangga besi fin.cat minyak m' 5.00 800,000.00 4,000,000.00
14 Talang beton samping dan belakang m3 2.90 5,300,000.00 15,370,000.00
15 waterproofing coating lantai beton m2 29.00 64,950.00 1,883,550.00
Sub Total 38,646,800.00
II Pekerjaan pasangan Dinding
1 Pasangan dinding hebel m2 7.94 115,800.00 919,452.00
2 Plesteran Dinding m2 123.88 65,180.00 8,074,498.40
3 Acian m2 123.88 36,150.00 4,478,262.00
4 Openingan m' - 35,000.00 -
Sub Total 13,472,212.40
III Pekerjaan Pelapis Lantai,Dinding Dan Tangga
1 Rangka Atap Baja Ringan m2 25.48 130,000.00 3,311,750.00
2 Genteng metal + alumunium foil double sided m2 25.48 155,500.00 3,961,362.50
3 Nok genteng metal m' 9.63 82,400.00 793,100.00
4 Listplank GRC m' 15.00 47,600.00 714,000.00
5 Screed lantai m2 2.04 106,499.00 217,257.96
5 Keramik Dinding meja beton (roman) m2 1.70 315,000.00 535,500.00
6 Granit meja beton m2 2.04 650,000.00 1,326,000.00
7 Keramik laundry room m2 9.63 245,800.00 2,365,825.00
Sub Total 13,224,795.46
CCO
No Uraian Pekerjaan
Sat Volume Harga Satuan (Rp) Jumlah Harga (Rp)

IV Pekerjaan Plafond
1 Plafond gypsum + rangka hollow m2 90.00 123,200.00 11,088,000.00

2 List Plafond m' 42.00 26,000.00 1,092,000.00


Sub Total 12,180,000.00
V Pekerjaan Pengecatan
1 Pembersihan cat eksisting m2 168.00 8,000.00 1,344,000.00
1 Cat dasar interior m2 168.00 23,000.00 3,864,000.00
2 Cat dasar exterior m2 - 28,000.00 -
3 Cat Interior Dinding dulux m2 168.00 42,500.00 7,140,000.00
4 Cat Plafond vinilex m2 90.00 32,500.00 2,925,000.00
5 Cat Eksterior Dinding dulux weatershield m2 - 47,000.00 -
Sub Total 15,273,000.00
VI Pekerjaan Kusen, Pintu dan Jendela
1 Pasang pintu besi unit 2.00 2,800,000.00 5,600,000.00
2 Pasang Jendela uk 2x0.4m unit 1.00 2,800,000.00 2,800,000.00
3 Partisi Kaca unit 1.00 14,300,000.00 14,300,000.00
Sub Total 22,700,000.00
F PEKERJAAN LAIN LAIN'
1 Kanopy kaca tempred roof top m2 - 1,500,000.00 -
2 Pasang tangga besi m' - 1,500,000.00 -
3 Instalasi air kotor ls 1.00 300,000.00 300,000.00
4 Floor drain lokal unit 1.00 150,000.00 150,000.00
5 Meja beton ls 1.00 1,200,000.00 1,200,000.00
6 Buang puing bekas bongkaran rit 7.00 250,000.00 1,750,000.00
Total 3,400,000.00
Jumlah Total 133,733,557.86
PROFIT 10% 13,373,355.79
TOTAL HARGA 147,106,913.65
DIBULATKAN 147,000,000.00

Anda mungkin juga menyukai