HARGA SATUAN
NO. URAIAN PEKERJAAN SPESIFIKASI VOLUME JUMLAH (Rp.)
(Rp.)
I PEKERJAAN PERSIAPAN
1 Mobilisasi dan Akomodasi 1,00 LS 37.500.000,00 37.500.000,00
2 Pembersihan Lokasi 1.250,00 M1 37.500,00 46.875.000,00
3 Biaya K3L 1,00 Ls 15.000.000,00 15.000.000,00
4 Direksi Kit/Gudang Uk. 4 x 8 m 32,00 M2 1.275.000,00 40.800.000,00
5 Pengukuran, Alat Bantu Kerja dan marking 1,00 Ls 7.500.000,00 7.500.000,00
6 Pagar Sementara Seng gelombang dan Kayu Tinggi 1.8 m 170,00 M1 262.500,00 44.625.000,00
II AREA KOLAM RENANG
A PEKERJAAN RUANG POMPA, (3.5 m x 7 m, tinggi 3 m) 25 m
1 Dinding 1/2 Bata/Hebel 90,00 m2 262.500,00 23.625.000,00
2
2 Plester 180,00 m 112.500,00 20.250.000,00
2
3 Aci 180,00 m 97.500,00 17.550.000,00
2
4 Finishing Cat Dinding Interior ex Setara Jotun 148,75 m 48.000,00 7.140.000,00
2
5 Finishing Dinding Paras Yogya + Coating 31,25 m 367.500,00 11.484.375,00
6 Pintu Tipe P4, kusen, handle, engsel Pintu besi 1,00 unit 9.750.000,00 9.750.000,00
TOTAL 8.063.632.125,00