Anda di halaman 1dari 4

BILL OF QUANTITY

PEKERJAAN KOLAM RENANG, POOL DECK, RUANG POMPA (Uk. 25 x 50 x 1.75) m


LOKASI : Luwuk Binggai Sulawesi Tengah

HARGA SATUAN
NO. URAIAN PEKERJAAN SPESIFIKASI VOLUME JUMLAH (Rp.)
(Rp.)
I PEKERJAAN PERSIAPAN
1 Mobilisasi dan Akomodasi 1,00 LS 37.500.000,00 37.500.000,00
2 Pembersihan Lokasi 1.250,00 M1 37.500,00 46.875.000,00
3 Biaya K3L 1,00 Ls 15.000.000,00 15.000.000,00
4 Direksi Kit/Gudang Uk. 4 x 8 m 32,00 M2 1.275.000,00 40.800.000,00
5 Pengukuran, Alat Bantu Kerja dan marking 1,00 Ls 7.500.000,00 7.500.000,00
6 Pagar Sementara Seng gelombang dan Kayu Tinggi 1.8 m 170,00 M1 262.500,00 44.625.000,00
II AREA KOLAM RENANG
A PEKERJAAN RUANG POMPA, (3.5 m x 7 m, tinggi 3 m) 25 m
1 Dinding 1/2 Bata/Hebel 90,00 m2 262.500,00 23.625.000,00
2
2 Plester 180,00 m 112.500,00 20.250.000,00
2
3 Aci 180,00 m 97.500,00 17.550.000,00
2
4 Finishing Cat Dinding Interior ex Setara Jotun 148,75 m 48.000,00 7.140.000,00
2
5 Finishing Dinding Paras Yogya + Coating 31,25 m 367.500,00 11.484.375,00
6 Pintu Tipe P4, kusen, handle, engsel Pintu besi 1,00 unit 9.750.000,00 9.750.000,00

B PEKERJAAN STRUKTUR RUANG POMPA


1 Galian 9,60 M3 180.000,00 1.728.000,00
2 Pondasi Besi 10" dan 8" K 175 4,80 M3 4.500.000,00 21.600.000,00
3 Sloof Besi 10" dan 8" K 175 0,54 M3 4.500.000,00 2.430.000,00
4 Ring balok Besi 10" dan 8" K 175 0,54 M3 4.500.000,00 2.430.000,00
5 Kolom Besi 10" dan 8" K 175 0,86 M4 4.500.000,00 3.870.000,00
6 Beton atap Besi Wermes M 10 5,20 M3 4.500.000,00 23.400.000,00
C PEKERJAAN PLAFOND RUANG POMPA
2
1 Plafond Dak Ekspose Finish Cat Interior 24,30 m 232.500,00 5.649.750,00
2
2 Waterproofing Dak Atap Ruang Pompa 49,00 m 127.500,00 6.247.500,00

D PEKERJAAN LANTAI RUANG POMPA


1 Lantai R. Pompa, Plester + Aci Ekspose 25,00 m2 232.500,00 5.812.500,00

PEKERJAAN DINDING PEMBATAS POOL DECk dan TAMAN


PEKERJAAN POOL DECK
1 Batu Tabur 100,00 zak 262.500,00 26.250.000,00
Lantai Dek Kolam Renang, Batu Candi uk. 30x30 cm
2 300,00 m2 675.000,00 202.500.000,00
+ coating
Lantai Batu Andesit warna abu-abu muda +
3 300,00 m2 525.000,00 157.500.000,00
Coating
4 Rabat beton utk pooldeck 7 cm tanpa tulangan 700,00 m2 180.000,00 126.000.000,00
2
5 Paving block Abu-abu tua Tipe Lantai L4, Inlay Lantai Batu Andesit 300,00 m 180.000,00 54.000.000,00
6 Aksesoris kolam dan bermain anak 1,00 Ls 750.000.000,00 750.000.000,00
F PEKERJAAN KOLAM RENANG & Finishing
tebal beton 25cm, Tulang double d10-15,
1 Beton Bertulang Kolam Renang (lantai dan sloof) 361,50 m3 5.625.000,00 2.033.437.500,00
K350
2 Water proofing 1.300,00 m2 191.250,00 248.625.000,00
3 Keramik penutup lantai & dinding kolam renang 1.512,50 m2 675.000,00 1.020.937.500,00
4 Galian kolam dan tapak 2.340,00 m3 120.000,00 280.800.000,00
5 Pondasi tapak 55,20 m3 5.625.000,00 310.500.000,00
tebal beton 30 cm, Tulang double d10-15,
6 Beton dinding 91,44 m3 5.625.000,00 514.350.000,00
K300
10 Water Tahnk dan asesorisnya 4,00 Unit 75.000.000,00 300.000.000,00

G INSTALASI ME SISTEM KOLAM RENANG


KUBIKASI KOLAM : VOL AIR 2.187 M3
EQUIPMENT DAN ASSESORIES KOLAM RENANG
1 Pompa Sirkulasi : SWIMMING POOL Hayward 4 unit 52.500.000,00 210.000.000,00
Capasitas 26 m3 / Jam
Head 18 Mtr
Power 2 HP
2 Sand Filter : 24" Hayward 4 unit 33.000.000,00 132.000.000,00
Type S244T
3 Pasir Silicasend @ 50 kg Standart 18 ls 1.200.000,00 21.600.000,00
4 Chemical Fedeer: Type CL 200 Hayward 10 unit 3.750.000,00 37.500.000,00

PEKERJAAN ACCESSORIES KOLAM


1 Maindrain Frame 12" Hayward 4 bh 3.600.000,00 14.400.000,00
2 Inlet Fitting 1,5 Hayward 48 bh 375.000,00 18.000.000,00
4 Faccum Fitting Hayward 8 bh 225.000,00 1.800.000,00
5 Vacuum Set Perawatan : Hayward 4 ls 22.500.000,00 90.000.000,00
. Telescopic Hendle
. Vaccum House
. Vaccum Head
. Pool Brush
. Test Kit

PEKERJAAN ELECTRICAL DAN KABEL POWER


1 Panel Control Pompa Sirkulasi MCB-Scheider 2 unit 2.700.000,00 5.400.000,00
2 Panel Box Trafo UWL Pool Bok - Lokal 4 unit 3.750.000,00 15.000.000,00
3 Kabel Power Pompa NYY 4 x 4 mm2 Supreme 4 ttk 7.500.000,00 30.000.000,00
4 Kabel UWL 100 Watt NYMHY 3 x 2,5 mm2 Supreme 12 ttk 4.500.000,00 54.000.000,00
5 UWL 100 Watt C/W Trafo Emouk 12 bh 4.500.000,00 54.000.000,00

PEKERJAAN INSTALASI PEMIPAAN PVC AW


1 Pemipaan Overflow Pvc Aw dia 6" Wavin Aw 620 mtr 285.000,00 176.700.000,00
2 Pemipaan Cabang Overflow Pvc Aw dia 4" 160 mtr 135.000,00 21.600.000,00
3 Pemipaan Main Drain Pvc Aw dia 4" 320 mtr 135.000,00 43.200.000,00
4 Pemipaan Cabang Main Drain Pvc Aw dia 3" 320 mtr 135.000,00 43.200.000,00
5 Pemipaan Main Inlet Fitting Pvc Aw dia 3" 820 mtr 135.000,00 110.700.000,00
6 Pemipaan Cabang Inlet Fitting Pvc Aw dia 2 " 220 mtr 90.000,00 19.800.000,00
7 Pemipaan Vaccum Fitting Pvc Aw dia 2" 640 mtr 90.000,00 57.600.000,00
8 Header Pvc Diameter 150 mm2 6 ls 3.000.000,00 18.000.000,00
9 Pemipaan Ruang Pompa System Pvc Aw Wavin Aw 2 ls 7.500.000,00 15.000.000,00

PEKERJAAN VALVE - VALVE


1 Butterflay Valve diameter 100 mm2 Kitz 4 bh 3.300.000,00 13.200.000,00
2 Butterflay Valve diameter 80 mm2 Kitz 14 bh 2.625.000,00 36.750.000,00
3 Ball Valve diameter 2" Kdj - CM 14 bh 1.800.000,00 25.200.000,00
5 Ball Valve diameter 1" Kdj - CM 9 bh 1.800.000,00 16.200.000,00
6 Ceck Valve dia 65mm2 Kitz 6 bh 4.500.000,00 27.000.000,00
7 Fod Valve Pvc diameter 80 mm2 Kdj - CM 3 bh 3.450.000,00 10.350.000,00
8 Pressure Gauge Std 16 Kg/cm2 Standart 8 bh 2.700.000,00 21.600.000,00
9 Ploting Valve Balancing Tank dia 1.5" Standart 4 bh 3.750.000,00 15.000.000,00
10 Tangga Kolam Stainless 1" 3 Traf Stainless 6 bh 15.000.000,00 90.000.000,00
11 Exhausfent Ruang Pompa Sirkulasi Lokal 9 bh 2.250.000,00 20.250.000,00
12 Flexible Joint diameter 3" Tozen 12 bh 2.250.000,00 27.000.000,00
13 Floor Drain Cover Overflow diameter 4" Standart 24 bh 600.000,00 14.400.000,00

PEKERJAAN FITTING2 SAMBUNGAN PVC


1 Fitting-Fitting dan Material Bantu ( Support ) CM - Rucika/Aw 1 ls 15.000.000,00 15.000.000,00
2 Test and Commisioning ( Treadment Awal ) Chemical dan Air Olahan 2.178 m3 67.500,00 147.015.000,00
3 Training dan Manual Book 1 ls 15.000.000,00 15.000.000,00

TOTAL 8.063.632.125,00