RENCANA ANGGARAN BIAYA

PEKERJAAN : PEMBANGUNAN RUANG PRAKTEK SISWA KENDARAAN RINGAN OTOMOTIF


LOKASI : SMKN 12 SAMARINDA
TAHUN : 2023

HARGA JUMLAH
NO. URAIAN PEKERJAAN VOL. SAT. SATUAN HARGA
( Rp. ) ( Rp. )
1 2 3 4 6 7
I PEK. PENDAHULUAN
1 Pekerjaan Bouplank 106,00 M1 108.900,00 11.543.400,00
2 Papan Nama Kegiatan 1,00 Bh 200.000,00 200.000,00
Total I 11.743.400,00
II PEK. TANAH
1 Galian Pondasi 51,30 M3 108.900,00 5.586.570,00
2 Timbunan kembali bekas galian 17,10 M3 75.000,00 1.282.500,00
3 Urugan pasir bawah lantai t=5cm 23,10 M3 221.000,00 5.105.100,00
4 Urugan tanah bawah lantai dipadatkan 231,00 M3 137.000,00 31.647.000,00
Total II 43.621.170,00
III PEK. PASANGAN
1 Pas. Batu Bata 1 : 4 293,00 M2 207.540,00 60.809.220,00
2 Plasteran dinding dan beton 454,00 M2 84.040,80 38.154.523,20
3 Acian dinding dan beton 454,00 M2 37.415,00 16.986.410,00
4 Pasangan Granit lantai Ruang 60x60 36,00 M2 374.486,00 13.481.496,00
5 Pasangan Granit lantai Teras 60x60 8,00 M2 374.486,00 2.995.888,00
6 Pasangan parit air hujan keliling gedung Pas. Batu bata (Acian) 112,00 M1 178.663,27 20.010.286,24
Total III 152.437.823,44
IV PEK. BETON
1 Foot Plate 1x1.5x0.3 33,00 M3 6.546.389,40 216.030.850,20
2 Cor Sloef Beton 20x40 9,60 M3 6.858.034,81 65.837.134,21
3 Cor Kolom beton 25x35 3,85 M3 8.207.692,78 31.599.617,20
4 Cor Beton K300 Lantai t=15cm 79,20 M3 1.509.991,27 119.591.308,57
5 Pembesian Lantai dengan Wiremash M6 462,00 M2 64.535,00 29.815.170,00
6 Cor Kolom praktis 0,29 M1 113.720,00 32.751,36
Total IV 462.906.831,54
IV PEK. KONSTRUKSI BAJA
1 WF - 200 x 100 x 5.5 x 8 2.346,30 Kg 39.030,00 91.576.089,00
2 WF - 150 x 75 x 5 x 7 2.156,00 Kg 39.030,00 84.148.680,00
3 WF - 100 x 50 x 5 x 7 1.567,44 Kg 39.030,00 61.177.183,20
4 Gording C-125x50x20x2.3 2.474,27 Kg 38.505,00 95.271.638,00
5 Base Plate 1.2mm 103,62 Kg 39.030,00 4.044.288,60
6 plat besi tebal 8 mm 343,54 Kg 39.030,00 13.408.491,10
7 Trakstank-besi Ø10 lengkap dengan ulir & pengait 105,24 Kg 38.505,00 4.052.266,20
8 Trakstank 24,00 Bh 87.500,00 2.100.000,00
9 besi siku 50 dudukan gording 67,47 Kg 38.505,00 2.597.804,00
10 baut HTB M16 1.232,00 Bh 7.500,00 9.240.000,00
11 baut HTB M12 448,00 Bh 5.835,00 2.614.080,00
12 Anchor Bolt HTB L - dia 19mm - 70cm 88,00 Bh 207.000,00 18.216.000,00
Total IV 388.446.520,10
V PEK. KUSEN, PINTU, JENDELA DAN PENGGANTUNG
1 Kusen Kayu Ulin 39,00 M1 84.274,75 3.286.715,25
2 Daun pintu Panel ulin 70 x 200 2,00 Bh 1.128.960,00 2.257.920,00
3 Daun Jendela rangka ulin 100 x 60, kaca 5mm 4,00 Bh 623.339,23 2.493.356,94
4 Jalusi Kayu ulin 28,00 Bh 40.000,00 1.120.000,00
5 Pas. Kaca mati polos 5mm termasuk les kayu 3x1 1,30 M2 268.810,00 349.453,00
6 Engsel pintu 5" (ring steel plate ) 9,00 Bh 53.810,00 484.290,00
7 Engsel Jendela 3" (ring steel plate ) 8,00 Bh 39.200,00 313.600,00
8 Kunci Pintu 2 slaag type Besar merk Belucci 2,00 pas 361.300,00 722.600,00
9 Grandel Pintu 4,00 Bh 69.400,00 277.600,00
10 Grandel jendela 8,00 Bh 55.400,00 443.200,00
11 Tarikan Jendela 4,00 Bh 56.400,00 225.600,00
12 Hak angin Jendela 8,00 Bh 49.250,00 394.000,00
Total V 12.368.335,19
VII PEK. ATAP
1 Atap Metal Spandek 0.35mm 638,00 M2 111.344,44 71.037.755,56
2 Bubungan metal roof 44,00 M1 73.300,00 3.225.200,00
Total VII 74.262.955,56
VIII PEK. PLAPON
1 Pasang Rangka Plapon dengan besi kotak/ hollow 36,00 M2 105.050,00 3.781.800,00
2 Pasang Plafon Gypsum Board 9mm 36,00 M2 81.412,43 2.930.847,43
3 Pasang List Gypsum board 10cm 42,00 M1 30.050,00 1.262.100,00
Total VIII 7.974.747,43
IX PEK. INSTALASI LISTRIK
Pasang Inst. Listrik ( Kabel NYM 2x1.5mm utk lampu dan NYM 2x2.5mm utk stop
1 49,00 ttk 303.150,00 14.854.350,00
kontak)
2 Pas. Lampu termasuk bola lampu tanam LED 12watt (Philips) 8,00 Bh 131.125,00 1.049.000,00
3 Pas. Lampu termasuk bola lampu tanam LED 6watt (Philips) 2,00 Bh 103.125,00 206.250,00
4 Pas. Stop kontak merk Masko 24,00 Bh 47.710,00 1.145.040,00
5 Pas. Saklar lampu merk Masko 7,00 Bh 47.710,00 333.970,00
6 Penggantian MCB MG 6A 3,00 Bh 65.000,00 195.000,00
7 Penggantian Box PVC Isi 2 Bh MCB 1,00 Bh 55.000,00 55.000,00
Total IX 17.838.610,00
X PEK. PENGECATAN
1 Cat Air untuk dinding dalam (interior) No. Cat W3000 329,00 M2 38.164,00 12.555.956,00
2 Cat Air untuk dinding luar (exterior) Code Cat : Sky blue , True Blue 293,00 M2 44.774,00 13.118.782,00
3 Cat Minyak untuk listplank, kusen, pintu, jendela 47,82 M2 45.620,00 2.181.639,64
Total X 27.856.377,64
TOTAL 1.199.456.770,89
REKAPITULASI RENCANA ANGGARAN BIAYA
PEKERJAAN : PEMBANGUNAN RUANG PRAKTEK SISWA KENDARAAN RINGAN OTOMOTIF
LOKASI : SMKN 12 SAMARINDA
TAHUN : 2023

JUMLAH
NO. JENIS PEKERJAAN HARGA
( Rp. )

I PEK. PENDAHULUAN 11.743.400,00


III PEK. TANAH 43.621.170,00
IV PEK. PASANGAN 152.437.823,44
V PEK. BETON 462.906.831,54
PEK. KONSTRUKSI BAJA 388.446.520,10
VI PEK. KUSEN, PINTU, JENDELA DAN PENGGANTUNG 12.368.335,19
VIII PEK. ATAP 74.262.955,56
IX PEK. PLAPON 7.974.747,43
X PEK. INSTALASI LISTRIK 17.838.610,00
XI PEK. PENGECATAN 27.856.377,64

JUMLAH 1.199.456.770,89
DIBULATKAN 1.199.456.000,00

TERBILANG : SATU MILYAR SERATUS SEMBILAN PULUH SEMBILAN JUTA EMPAT RATUS LIMA PULUH ENAM RIBU RUPIAH

Samarinda, 1 Februari 2023


DISETUJUI OLEH, KONSULTAN PERENCANA
KEPALA SMKN 12 SAMARINDA CV. DUTA PONTANA

DRS. PRIYANTO, M.Pd HAMZAH SAID