Anda di halaman 1dari 4

BIL OF QUANTITY

Pekerjaan : Rumah Kos


Lokasi : Jl. Rela No.19, RT 006/09, Kelurahan Menteng Atas, Kec. Setiabudi, Jakarta Selatan
Lantai : 3 (tiga)

HARGA SATUAN JUMLAH HARGA


NO URAIAN PEKERJAAN SAT VOL
(RP) (RP)
I PEKERJAAN PERSIAPAN
1 Mobilisasi dan demobilisasi Alat dan Bahan ls 1.00 7,500,000 7,500,000
2 Pembersihan / pembuangan Ex. Galian dll Ls 1.00 19,000,000 19,000,000
26,500,000
LANTAI 1

II PEKERJAAN GALIAN DAN BETON


1 Bauw plang m1 84.40 75,000 6,330,000
2 Galian tanah m³ 94.50 85,000 8,032,500
3 Pondasi batu kali m³ 47.25 1,200,000 56,700,000
4 Galian boring pondasi strous Ø 20 cm 10 ttk m1 140.00 150,000 21,000,000
5 Urugan kembali padat m³ 32.40 65,000 2,106,000
6 Sloof besi 16 mm+ 8mm (40x15) m³ 6.90 4,263,000 29,414,700
7 Tapak besi 14 mm (100 x100x25) cm m³ 5.25 4,263,000 22,380,750
8 Kolom praktis besi 14 mm+8mm ( 40X15 cm) m³ 6.90 4,263,000 29,414,700
9 Ring Balk besi 13 mm + 8mm ( 15X20 cm) m³ 3.15 4,263,000 13,428,450
10 Beton lantai dan lisplang Warmes M10 (1 lapis/beton K250)) m³ 10.70 4,700,000 50,290,000
11 Floordec 0.75 m² 56.54 295,400 16,701,916
255,799,016
III PEKERJAAN DINDING DAN LANTAI
1 Pasang bata ringan (bata hebel 20X10X60 cm) m² 228.12 125,300 28,583,436
2 Pekerjaan plasteran + acian 2 sisi m² 417.56 141,600 59,126,496
3 Pasang keramik tangga 30 X 60 cm (Stara Roman Granit) m² 5.10 364,200 1,857,420
4 Pasang keramik lantai 60 X 60 cm (Stara Roman Granit) m² 50.40 331,100 16,687,440
106,254,792
IV PEKERJAAN SANITASI DAN KAMAR MANDI
1 Pasang keramik dinding 30 X 60 cm (Roman) m² 38.68 362,700 14,029,236
2 Pasang keramik lantai 30 X 30 cm ( Roman) m² 7.00 275,400 1,927,800
3 Floordrind m² 4.00 166,300 665,200
4 Intalasi air bersih ttk 8.00 385,000 3,080,000
5 Instalasi air kotor 3" m1 14.00 46,000 644,000
6 Instalasi air kotor 4" m1 16.00 75,000 1,200,000
7 Kloset duduk american standar bh 4.00 2,100,000 8,400,000
8 Jet Wazer bh 4.00 187,400 749,600
9 Kran cabang bh 4.00 294,200 1,176,800
10 Sower mandi bh 4.00 466,300 1,865,200
33,737,836
V PEK. KUSEN, PINTU DAN JENDELA
1 Kusen pintu + ovening (alumunium ex dacon 4' ) unit 11.00 2,300,000 25,300,000
2 Kusen jendela + ovening (alumunium ex dacon 4' ) unit 11.00 750,000 8,250,000
3 Kusen bovenly + ovening (alumunium ex dacon 4') unit 5.00 700,000 3,500,000
4 Daun pintu kaca (ram/frem alumunium ex dacon) unit 4.00 1,800,000 7,200,000
termasuk kunci dan engsel
5 Daun pintu multiplek 18 mm lapisan HPL unit 9.00 1,510,000 13,590,000
6 Kunci pintu stara Onasis bh 9.00 435,000 3,915,000
7 Engsel pintu bh 18.00 65,000 1,170,000
8 Daun jendela kaca (ram/frem alumunium ex dacon) unit 11.00 1,200,000 13,200,000
termasuk slot dan engsel
7 Daun bovenly (ram/frem alumunium ex dacon) unit 5.00 700,000 3,500,000
termasuk slot dan engsel
79,625,000
VI PEKERJAAN LISTRIK
1 Instalasi lampu ttk 14.00 356,200 4,986,800
2 Instalasi Stopkontak ttk 7.00 394,800 2,763,600
3 Pasang saklar seri ttk 2.00 93,000 186,000
4 Pasang saklar single ttk 11.00 93,000 1,023,000
5 Pasang stop kontak ttk 7.00 93,000 651,000
6 Pasang Viting + bohlam ttk 14.00 77,500 1,085,000
10,695,400
VII PEKERJAAN PLAFONN
1 Plafon gypsum + hollo m² 50.40 165,000 8,316,000
8,316,000
VIII PEKERJAAN PENGECATAN
1 Pengecatan (Duluk pentalic) m² 50.40 26,400 1,330,560
2 Pengecatan dinding bagian dalam (Duluk pentalic) m² 385.36 26,400 10,173,504
3 Pengecatan dinding bagian luar (Duluk Wattersile) m² 125.40 35,100 4,401,540
15,905,604
LANTAI 2

I PEKERJAAN BETON
1 Kolom praktis besi 14 mm+8mm ( 25X10 cm) m³ 5.40 4,263,000 23,020,200
2 Balok lantai besi 16 mm + 8mm ( 15x40 cm) m³ 5.67 4,263,000 24,171,210
3 Beton lantai dan lisplang Warmes M10 (1 lapis/beton K250)) m³ 11.70 4,263,000 49,877,100
4 Floordec 0.75 m² 56.54 150,000 8,481,000
105,549,510
II PEKERJAAN DINDING DAN LANTAI
1 Pasang bata ringan (bata hebel 20X10X60 cm) m² 202.50 125,300 25,373,250
2 Pekerjaan plasteran + acian 2 sisi m² 357.08 141,600 50,562,528
3 Pasang keramik tangga 30 X 60 cm (Stara Roman Granit) m² 9.12 356,700 3,253,104
4 Pasang keramik lantai 60 X 60 cm (Stara Roman Granit) m² 48.65 331,100 16,108,015
95,296,897
III PEKERJAAN SANITASI DAN KAMAR MANDI
1 Pasang keramik dinding 30 X 60 cm (Stara Ruman Granit) m² 47.92 362,700 17,380,584
2 Pasang keramik lantai 30 X 30 cm (Stara Roman Granit) m² 8.75 275,400 2,409,750
3 Floordrind m² 4.00 166,300 665,200
4 Intalasi air bersih ttk 9.00 385,000 3,465,000
5 Instalasi air kotor 3" m1 22.00 46,000 1,012,000
6 Instalasi air kotor 4" m1 22.00 75,000 1,650,000
7 Kloset duduk american standar bh 5.00 2,100,000 10,500,000
8 Jet Wazer bh 5.00 187,400 937,000
9 Kran cabang bh 5.00 294,200 1,471,000
10 Sower mandi bh 5.00 466,300 2,331,500
41,822,034
IV PEK. KUSEN, PINTU DAN JENDELA
1 Kusen pintu + ovening (alumunium ex dacon 4' ) unit 11.00 2,300,000 25,300,000
2 Kusen jendela + ovening (alumunium ex dacon 4' ) unit 13.00 750,000 9,750,000
3 Kusen bovenly + ovening (alumunium ex dacon 4') unit 6.00 700,000 4,200,000
4 Daun pintu kaca (ram/frem alumunium ex dacon) unit 2.00 1,800,000 3,600,000
termasuk kunci dan engsel
5 Daun pintu multiplek 18 mm lapisan HPL unit 10.00 1,510,000 15,100,000
6 Kunci pintu stara Onasis bh 10.00 435,000 4,350,000
7 Engsel pintu bh 20.00 65,000 1,300,000
8 Daun jendela kaca (ram/frem alumunium ex dacon) unit 13.00 1,200,000 15,600,000
termasuk slot dan engsel
9 Daun bovenly (ram/frem alumunium ex dacon) unit 6.00 700,000 4,200,000
termasuk slot dan engsel
83,400,000
V PEKERJAAN LISTRIK
1 Instalasi lampu ttk 15.00 356,200 5,343,000
2 Instalasi Stopkontak ttk 7.00 394,800 2,763,600
3 Pasang saklar seri ttk 2.00 93,000 186,000
4 Pasang saklar single ttk 11.00 93,000 1,023,000
5 Pasang stop kontak ttk 7.00 93,000 651,000
6 Pasang Viting + bohlam ttk 15.00 77,500 1,162,500
11,129,100
VI PEKERJAAN LAFON DAN RALING
1 Pagar/reling balkon pipa holow 4 x 4 cm finishing cat (galvanis) m² 5.10 657,100 3,351,210
2 Plafon gypsum + hollo m² 48.65 165,000 8,027,250
11,378,460
VII PEKERJAAN PENGECATAN
1 Pengecatan dinding bagian dalam (Duluk pentalic) m² 324.88 26,400 8,576,832
2 Pengecatan dinding bagian luar (Duluk Wattersile) m² 125.40 35,100 4,401,540
12,978,372
LANTAI 3

I PEKERJAAN BETON
1 Kolom praktis besi 14 mm+8mm ( 40X10 cm) m³ 5.40 4,263,000 23,020,200
2 Talang beton 14 mm + 8mm (13x1x0,12 cm) m³ 1.60 4,263,000 6,820,800
3 Floordec 0.75 m² 16.48 165,000 2,719,200
4 Balok lantai besi 16 mm + 8mm ( 15X40 cm) m³ 5.62 4,263,000 23,958,060
5 Ring balok besi 12mm+8mm (15x30) m³ 4.30 4,263,000 18,330,900
6 dak torn m³ 2.40 4,263,000 10,231,200
85,080,360
II PEKERJAAN DINDING DAN LANTAI
1 Pasang bata ringan (bata hebel 20X10X60 cm) m² 208.04 125,300 26,067,412
2 Pekerjaan plasteran + acian 2 sisi m² 368.16 141,600 52,131,456
3 Pasang keramik tangga 30 X 60 cm (Stara Roman Granit) m² 9.12 356,700 3,253,104
4 Pasang keramik lantai 60 X 60 cm (Stara Roman Granit) m² 48.65 331,100 16,108,015
97,559,987
III PEKERJAAN SANITASI DAN KAMAR MANDI
1 Pasang keramik dinding 30 X 60 cm (Roman) m² 47.92 362,700 17,380,584
2 Pasang keramik lantai 30 X 30 cm (Roman) m² 8.75 275,400 2,409,750
3 Floordrind m² 4.00 166,300 665,200
4 Intalasi air bersih ttk 9.00 385,000 3,465,000
5 Instalasi air kotor 3" m1 22.00 46,000 1,012,000
6 Instalasi air kotor 4" m1 22.00 75,000 1,650,000
7 Kloset duduk american standar bh 5.00 2,100,000 10,500,000
8 Jet Wazer bh 5.00 187,400 937,000
9 Kran cabang bh 5.00 294,200 1,471,000
10 Sower mandi bh 5.00 466,300 2,331,500
41,822,034
IV PEK. KUSEN, PINTU DAN JENDELA
1 Kusen pintu + ovening (alumunium ex dacon 4' ) unit 11.00 2,300,000 25,300,000
2 Kusen jendela + ovening (alumunium ex dacon 4' ) unit 13.00 750,000 9,750,000
3 Kusen bovenly + ovening (alumunium ex dacon 4') unit 6.00 700,000 4,200,000
4 Daun pintu kaca (ram/frem alumunium ex dacon) unit 2.00 1,800,000 3,600,000
termasuk kunci dan engsel
5 Daun pintu multiplek 18 mm lapisan HPL unit 10.00 1,510,000 15,100,000
6 Kunci pintu stara Onasis bh 10.00 435,000 4,350,000
7 Engsel pintu bh 20.00 65,000 1,300,000
8 Daun jendela kaca (ram/frem alumunium ex dacon) unit 13.00 1,200,000 15,600,000
termasuk slot dan engsel
9 Daun bovenly (ram/frem alumunium ex dacon) unit 6.00 700,000 4,200,000
termasuk slot dan engsel
83,400,000
V PEKERJAAN LISTRIK
1 Instalasi lampu ttk 19.00 356,200 6,767,800
2 Instalasi Stopkontak ttk 14.00 394,800 5,527,200
3 Pasang saklar seri ttk 2.00 93,000 186,000
4 Pasang saklar single ttk 14.00 93,000 1,302,000
5 Pasang stop kontak ttk 14.00 93,000 1,302,000
6 Pasang Viting + bohlam ttk 19.00 77,500 1,472,500
7 Instalasi Stopkontak AC ttk 14.00 394,800 5,527,200
22,084,700
VI PEKERJAAN LAFON DAN RALING
1 Pagar/reling balkon pipa holow 4 x 4 cm finishing cat (galvanis) m² 5.10 657,100 3,351,210
2 Plafon PVC m² 50.40 291,600 14,696,640
3 Railing tangga m1 32.00 657,100 21,027,200
39,075,050
VII PEKERJAAN PENGECATAN
1 Pengecatan dinding bagian dalam (Duluk pentalic) m² 335.96 26,400 8,869,344
2 Pengecatan dinding bagian luar (Duluk Wattersile) m² 125.40 35,100 4,401,540
13,270,884
VIII PEKERJAAN ATAP
1 Rangka atap baja ringan m² 68.39 187,000 12,788,930
2 Penutup atap Zingkalum lapis pasir m² 72.79 132,600 9,651,954
22,440,884

TOTAL A 1,303,121,920
I PEKERJAAN LAIN - LAIN
1 Instalasi air bersih 2" m1 25.30 65,000 1,644,500
2 Instalasi airAC pipa 1/2' ttk 14.00 76,300 1,068,200
3 Instalasi air kotor 4" (pipa talang) m² 66.00 85,000 5,610,000
4 Sumur resapan unit 1.00 5,000,000 5,000,000
5 Pekerjaan Ground watertank 12m termasuk galian ls 1.00 45,000,000 45,000,000
6 Torn air pinguin kap 5100 ltr unit 2.00 9,250,000 18,500,000
7 Sumur bor titik 1.00 6,500,000 6,500,000
8 Pintu besi lipat pipa holow 4 x 4 cm finishing cat (galvanis) m² 10.50 765,300 8,035,650
9 Ofis /gudang material m² 15.00 375,000 5,625,000
10 Pagar pengaman proyek pekerjaan (bajaringan dan spandek) m² 41.80 285,000 11,913,000
11 Pasang KWH meter 10 A (2200 Watt) untuk ruang pengelola dan ttk 1.00 5,500,000 5,500,000
untuk sarana
12 Pasang KWH meter 6 A (1.300 Watt) untuk ruang kamar ttk 13.00 2,500,000 32,500,000
TOTAL B 146,896,350

Sub-Total A+ B (Rp) SUB TOTAL 1,450,018,270

Grand Total (Rp) 1,450,018,270

Draf istimasi sementara


Catatan :
Pekerjaan hydrant belum dihitung