PEMBANGUNAN RUMAH DUA LANTAI TYPE 50/96

RENCANA ANGGARAN BIAYA (RAB)


PERUMAHAN BUMI SANGKURIANG RESIDENCE
LOKASI : Blok Cicabe Desa. Pasiripis Kec. Kertajati Kab. Majalengka

NO URAIAN PEKERJAAN SPESIFIKASI VOL SAT BOBOT H. SATUAN JUMLAH


I PEKERJAAN PERSIAPAN
1 Persiapan Kerja 1.00 Ls 975,000 975,000
2 Pengukuran & Bowplank 48.00 m' 45,000 2,160,000
3 Persiapan air bersih 1.00 Ls 148,750 148,750
Sub Total I 3,283,750
II PEK. TANAH & PONDASI
1 Galian tanah pondasi 35.25 m3 86,700 3,056,175
2 Galian pondasi cakar ayam untuk (9 Titik Cakar ayam) 3.24 m3 86,700 280,908
3 pegurugan kembali (fill) 2.40 m3 63,963 153,511
4 urugan pasir 3cm 1.01 m3 153,170 154,702
5 pondasi batu kali 1 pc : 5 ps (tinggi 60 cm) 28.20 m3 541,875 15,280,875
6 septictank + rembesan P.2 cm L. 1cm T. 1.5 cm ( sumur) 1.00 unit 3,251,250 3,251,250
7 pipa air kotor PVC wavin D.4" + fitting 6.00 m' 137,275 823,650
8 pipa air bersih PCV wavin D. 3" + fitting 20.00 m' 119,213 2,384,260
Sub Total II 25,385,331
IIIPEK. PASANGAN & BETON
1 Sloof beton bertulang U.15/20 (besi full.10mm ring 8mm) 3.50 m3 1,986,875 6,954,063
2 dinding hebbel U.10 cm pas. 1:2:3 196.99 m2 54,188 10,674,494
3 kolom praktis beton bertulang U. 8/8 (besi Full 10mm ring 6mm) 0.99 m3 1,986,875 1,967,006
kolom praktis cakar ayam 9 titik ( 25/15) besi 12.. Ring 8mm) 1.35 m3 1,986,875 2,682,281
4 ringbalk beton bertulang U. 25/15 (besi Full 12mm ring 8mm) 0.78 m3 1,986,875 1,549,763
5 pondasi setempat U. 60x60x120 (besi 12 ring 8mm) 0.95 m3 1,986,875 1,887,531
6 Cor lantai beton (besi Full 10mm ring 8mm) 1.40 m3 2,080,000 2,912,000
7 beton kanopi teras T.0.08mm 1.72 m3 1,986,875 3,417,425
8 plesteran dinding dan dinding aci 1 pc : 5 ps 393.98 m2 46,963 18,502,483
9 pasangan pipa listrik 10.00 unit 9,754 97,540
10 groof tampak depan di profile 6.54 m2 86,700 567,018
11 pas. Batu alam dengan tali air t.7 cm 6.70 m2 108,375 726,113
Sub Total III 51,937,716
IV PEKERJAAN ATAP
1 rangka baja ringan U. 0.75 P.6m 62.37 m2 83,088 5,182,199
2 penutup atap genteng flat beton Ex. Mutiara 62.37 m2 80,325 5,009,870
3 nok genteng 8.02 m' 29,250 234,585
4 listplank GRC U. 8x 200mm 42.35 m' 18,424 780,256
5 ban flashing penutup genteng 45.84 m' 25,288 1,159,202
Sub Total IV 12,366,112
V PEKERJAAN PLAFOND
1 plafond gypsum rangka hollo hollo 4x4 galvanize. Gypsum elephant 50.94 m2 90,313 4,600,544
2 list tepi plafond profile gypsum list T. 8cm 235.25 m' 10,838 2,549,640
Sub Total V 7,150,184
VI PEKERJAAN LANTAI
1 stemper tanah 50.00 m2 25,288 1,264,400
2 urugan pasir 3cm 2.50 m3 153,170 382,925
3 keramik lantai U. 60 x 60 granit (setara) 56.00 m2 151,725 8,496,600
4 keramik tangga U. 60 x 60 granit (setara) 5.40 m2 151,725 819,315
5 keramik lantai KM/WC U.25 x25 merk. Roman (setara) 3.00 m2 126,438 379,314
6 keramik dinding KM U. 25 x40 merk. Roman (setara) 20.41 m2 133,663 2,728,062
7 keramik lantai dapur U. 25 x25 merk. Roman (setara) 1.11 m2 126,438 140,346
8 keramik dinding dapur U. 25 x 40 merk. Roman (setara) 1.48 m2 133,663 197,821
Sub Total VI 14,408,783
VII INSTALASI & SANITASI
1 titik lampu ex broco 17.00 Ttk 177,013 3,009,221
2 titik stop kontak ex broco 5.00 Ttk 75,863 379,315
3 saklar single ex broco 5.00 Ttk 75,863 379,315
4 saklar doble ex broco 2.00 Ttk 86,700 173,400
5 titik AC ex broco 3.00 Ttk 97,538 292,614
6 titik antena ex broco 3.00 Ttk 75,863 227,589
7 Box sekering presto + NCB 1.00 Ttk 180,625 180,625
8 floor drain steinlis 1.00 bh 86,700 86,700
9 closed duduk ex. American standar 1.00 bh 1,950,750 1,950,750
10 kran air dia.1/2" ex lokal 4.00 bh 122,825 491,300
kitchen sink merek royal P.99 x L.45 x T.15 1.00 bh 122,875 122,875
keran angsa wasser TL2-040 leher angsa sink 1.00 bh 245,650 245,650
11 pipa air bersih PVC wavin d.3/4" AW+ fitting 18.00 m' 35,403 637,254
12 pipa air bersih PVC wavin d. 1/2" AW + fitting 20.00 m' 18,568 371,360
Sub Total VII 8,547,968
VIII PEK KUSEN & PENGGANTUNG
1 kusen pintu & jendela alumuniun U. 3" (Coklat) 81.73 m' 198,688 16,238,770
2 daun pintu utama kaca alumunium 1.00 bh 1,914,625 1,914,625
3 daun pintu kamar dan dapur 4.00 bh 1,336,625 5,346,500
4 daun pintu KM PVC platindo + kunci KM 1.00 bh 325,125 325,125
5 daun jendela U. 60 x 180 alumunium + kaca 13.00 bh 686,375 8,922,875
6 kaca polos T. 5mm 34.81 m2 128,605 4,476,740
7 kunci pintu utama silinder merk Royal 1.00 bh 252,875 252,875
8 kunci pintu kamar silinder merk Royal 3.00 bh 231,200 693,600
9 kunci pintu belakang silinder merk Royal 1.00 bh 231,200 231,200
10 engsel pintu U. 4" 5.00 Set 144,500 722,500
Sub Total VIII 39,124,810
IX PEKERJAAN PENGECATAN
1 pengecatan dinding dalam ex. Vinilex 128.43 m2 20,230 2,598,139
2 pengecatan dinding luar ex. Vinilex 68.56 m2 23,120 1,585,107
3 pengecatan dinding luar groof ex. Vinilex 6.54 m2 25,288 165,384
4 cat lisplank ex. Vinilex 8.47 m2 24,565 208,066
5 cat pintu panil finishing semprot pelistur 8.96 m2 78,000 698,880
6 pengecatan plafond ex. Vinilex 50.94 m2 19,508 993,738
7 cat list plafon ex. Vinilex 235.25 m1 10,115 2,379,554
Sub Total IX 8,628,866
X PEKERJAAN LAIN-LAIN
1 pembersihan hasil pekerjaan 1.00 ls 975,000 975,000
2 pas.hebbel pagar belakang belakang dan samping 30.60 m2 63,750 1,950,750
3 pas.pelester+aci 30.60 m2 55,250 1,690,650
4 pas. Cat pagar belakang 30.60 m2 27,200 832,320
5 Carport depan 34.94 m2 102,000 3,563,880
Sub Total X 9,012,600
0.00
Jumlah biaya langsung 179,846,121
Dibulatkan 179,800,000
Terbilang : Seratus tujuh puluh sembilan juta delapan ratus ribu rupiah

Total 20 Unit Rumah


Majalengka, 2 Februari 2021
PT. TRIBUN NACITRA ASRI

M.Ihwan Budiman ST. Yayuk Handayani


Konsultan Pengawas Direktur