PEMBANGUNAN RUMAH SATU LANTAI TYPE 45/84

RENCANA ANGGARAN BIAYA (RAB)


PERUMAHAN BUMI SANGKURIANG RESIDENCE
LOKASI : Blok Cicabe Desa. Pasiripis Kec. Kertajati Kab. Majalengka

NO URAIAN PEKERJAAN SPESIFIKASI VOL SAT BOBOT H. SATUAN JUMLAH


I PEKERJAAN PERSIAPAN
1 Persiapan Kerja 1.00 Ls 1,185,750 1,185,750
2 Pengukuran & Bowplank 48.00 m2 45,000 2,160,000
3 Persiapan air bersih 1.00 Ls 162,750 162,750
Sub Total I 3,508,500
II PEK. TANAH & PONDASI
1 Galian tanah pondasi 16.56 m3 94,860 1,570,882
2 urugan kembali (fill) 2.76 m3 69,983 193,152
3 urugan pasir 3cm 1.38 m3 167,586 231,269
4 pondasi batu kali 1 pc : 5 ps (tinggi 60 cm) 14.49 m3 592,875 8,590,759
5 septictank + rembesan P.2 cm L. 1cm T. 1.5 cm ( sumur) 1.00 unit 3,557,250 3,557,250
6 pipa air kotor PVC wavin D.4" + fitting 10.00 m' 150,195 1,501,950
7 pipa air bersih PCV wavin D. 3" + fitting 10.00 m' 130,433 1,304,325
Sub Total II 16,949,586
III PEK. PASANGAN & BETON
1 Sloof beton bertulang U.15/20 (besi full.10mm ring 8mm) 1.66 m3 2,173,875 3,608,633
2 dinding hebbel U.10 cm pas. 1:2:3 154.53 m2 59,288 9,161,697
3 kolom praktis beton bertulang U. 8/8 (besi Full 10mm ring 6mm) 1.48 m3 2,173,875 3,217,335
4 ringbalk beton bertulang U. 25/15 (besi Full 12mm ring 8mm) 4.45 m3 2,173,875 9,673,744
5 beton kanopi 0.62 m3 2,173,875 1,347,803
6 plesteran dinding dan dinding aci 1 pc : 5 ps 271.43 m2 51,383 13,946,752
7 pasangan pipa listrik 10.00 unit 10,672 106,718
8 groof tampak depan di profile 11.29 m2 94,860 1,070,969
9 ban-banan motif 17.60 m' 94,860 1,669,536
10 pas. Batu alam dengan tali air t.7 cm 0.56 m2 118,575 66,402
Sub Total III 43,869,588
IV PEKERJAAN ATAP
1 rangka baja ringan U. 0.75 P.6m 60.32 m2 90,908 5,483,540
2 penutup atap genteng beton flet mutiara 60.32 m2 87,885 5,301,223
3 nok genteng 7.45 m' 41,850 311,783
4 listplank GRC U. 8x 200mm 31.23 m' 20,158 629,527
5 ban flashing penutup genteng 15.44 m' 27,668 427,186
Sub Total IV 12,153,259
V PEKERJAAN PLAFOND
1 plafond gypsum rangka hollo hollo 4x4 galvanize. Gypsum elephant 53.60 m2 98,813 5,695,000
2 list tepi plafond profile gypsum list T. 8cm 93.55 m' 11,858 1,192,763
Sub Total V 6,887,763
VI PEKERJAAN LANTAI
1 stemper tanah 84.00 m2 27,668 2,499,000
2 urugan pasir 3cm 2.25 m3 167,586 405,450
3 keramik lantai U. 60 x 60 granit (setara) 43.78 m2 166,005 7,814,730
4 keramik lantai KM/WC U.25 x25 merk. Roman (setara) 3.00 m2 138,338 446,250
5 keramik dinding KM U. 25 x40 merk. Roman (setara) 10.89 m2 146,243 1,712,453
6 keramik lantai dapur U.25 x25 merk. Roman (setara) 60.00 m2 138,338 8,925,000
7 keramik dinding dapur U. 25 x40 merk. Roman (setara) 1.20 m2 146,243 188,700
Sub Total VI 21,991,583
VII INSTALASI & SANITASI
1 titik lampu ex broco 9.00 Ttk 193,673 1,874,250
2 titik stop kontak ex broco 5.00 Ttk 83,003 446,250
3 saklar single ex broco 3.00 Ttk 83,003 267,750
4 saklar doble ex broco 3.00 Ttk 94,860 306,000
5 titik AC ex broco 2.00 Ttk 106,718 229,500
6 titik antena ex broco 3.00 Ttk 83,003 267,750
7 Box sekering presto + NCB 1.00 Ttk 197,625 212,500
8 floor drain steinlis 1.00 bh 94,860 102,000
9 closed duduk ex. American standar 1.00 bh 2,134,350 2,295,000
10 kran air dia.1/2" ex lokal 3.00 bh 134,385 433,500
11 kitchen sink Merek royal P.99xl.45 x T.15 1.00 bh 276,675 297,500
12 keran angsa Wasser TL2-040 leher angsa sink 1.00 bh 268,770 289,000
13 pipa air bersih PVC wavin d.3/4" AW+ fitting 10.00 m' 38,735 416,500
14 pipa air bersih PVC wavin d. 1/2" AW + fitting 15.00 m' 20,316 327,675
Sub Total VII 7,765,175
VIII PEK KUSEN & PENGGANTUNG
1 kusen pintu & jendela alumuniun U. 4" (Coklat) 60.00 m' 217,388 14,025,000
2 daun pintu utama & belakang Doble Triplex Finishing HPL kayu 2.00 bh 2,094,825 4,505,000
3 daun pintu kamar alumunium Finishing Spandrel 2.00 bh 1,462,425 3,145,000
4 daun pintu KM PVC platindo + kunci KM 1.00 bh 355,725 382,500
5 daun jendela U. 50 x 135 alumunium + kaca 8.00 bh 750,975 6,460,000
6 kaca polos T. 5mm (kaca mati) 0.77 m2 140,709 116,501
7 kunci pintu utama silinder merk Royal 1.00 bh 276,675 297,500
8 kunci pintu kamar silinder merk Royal 2.00 bh 252,960 544,000
9 kunci pintu belakang silinder merk Royal 1.00 bh 252,960 272,000
10 engsel pintu U. 4" 4.00 Set 158,100 680,000
Sub Total VIII 30,427,501
IX PEKERJAAN PENGECATAN
1 pengecatan dinding dalam ex. Catylax 229.00 m2 22,134 5,450,200
2 pengecatan dinding luar ex. Dulux 30.71 m2 25,296 835,312
3 pengecatan dinding luar groof ex. Dulux 11.29 m2 27,668 335,878
4 cat lisplank ex. Catylax 5.16 m2 26,877 149,124
5 pengecatan plafond ex. Catylax 53.60 m2 21,344 1,230,120
6 cat list plafon ex. Catylax 93.55 m1 11,067 1,113,245
Sub Total IX 9,113,879
X PEKERJAAN LAIN-LAIN
1 pembersihan hasil pekerjaan 1.00 ls 1,395,000 1,395,000
2 pas.hebbel pagar belakang 11.73 m2 69,750 818,168
3 pas.pelester+aci 23.47 m2 60,450 1,418,762
4 pas. Cat pagar belaang 23.47 m2 29,760 698,467
5 Carport depan 11.76 m2 111,600 1,312,416
Sub Total X 5,642,812
0.00
Jumlah biaya langsung 158,309,644
Dibulatkan 158,300,000
Terbilang : Seratus lima puluh delapan juta tiga ratus ribu rupiah

Total 17 Unit Rumah


Majalengka, 2 Februari 2021
PT. TRIBUN NACITRA ASRI

M.Ihwan Budiman ST. Yayuk Handayani


Konsultan Pengawas Direktur