NO. URAIAN PEKERJAAN SPESIFIKASI VOLUME SAT. TOTAL (Rp.) KETERANGAN
SATUAN (Rp.)

A PEKERJAAN TANAH
termasuk urug kembali+buang di dalam
1 Galian tanah 10.58 m³ 100,000 1,058,400
lokasi+pemadatan
2 Urug pasir padat bawah pondasi dan lantai 4.18 m³ 205,000 857,515
3 Pekerjaan anti rayap Premise 200L ex.Bayer-5Ltr/m2 28.60 m² 20,350 582,010

B PEKERJAAN BETON, BEKISTING & PEMBESIAN


1 Rabat beton t: 10cm Beton Sitemix camp. 1:3:5 2.86 m³ 594,360 1,699,870
2 Pondasi batu kali 7.94 m³ 500,000 3,969,000
3 Sloof S1
- Beton Beton Sitemix camp. 1:3:5 0.88 m³ 594,360 524,226
- Bekisting 11.76 m² 96,769 1,138,006
- Pembesian <13mm BJTP 24, ≥ 13mm BJTD 40, SNI 132.30 kg 12,830 1,697,409
4 Kolom K1
- Beton Beton Sitemix camp. 1:3:5 1.02 m³ 594,360 608,476
- Bekisting 27.30 m² 96,769 2,641,800
- Pembesian <13mm BJTP 24, ≥ 13mm BJTD 40, SNI 153.56 kg 12,830 1,970,207
5 Balok B1
- Beton Beton Sitemix camp. 1:3:5 0.83 m³ 594,360 493,467
- Bekisting 16.61 m² 96,769 1,606,853
- Pembesian <13mm BJTP 24, ≥ 13mm BJTD 40, SNI 124.54 kg 12,830 1,597,816

C PEKERJAAN BAJA & ATAP


1 Penutup atap Spandek zincalume 0.45 mm TCT Lysaght - screw ex. Buildex 37.20 m² 201,420 7,492,824
2 Rangka atap baja ringan 37.20 m² 150,000 5,580,000

D PEKERJAAN DINDING
1 Pas. dinding 1/2 bata trasraam 1pc:3ps 20.18 m² 105,259 2,124,136
2 Pas. dinding 1/2 bata 1pc:5ps 77.24 m² 99,109 7,655,186
3 Plester + acian trasraam 1pc:3ps 40.36 m² 65,672 2,650,508
4 Plesteran + acian + benangan 1pc:5ps 154.48 m² 42,998 6,642,318
5 Cat Interior Mowilex AGE 600 WHITE 77.24 m² 41,438 3,200,697
6 Cat Exterior Mowilex weathercoat W-0959 Lakestone 107.64 m² 42,230 4,545,637

E PEKERJAAN LANTAI
1 Finish lantai teras 4.68 m² 130,000 608,400
2 Finish lantai kamar 18.75 m² 130,000 2,437,500
3 Finish lantai kamar mandi 3.75 m² 130,000 487,500
4 Finish meja dapur 1.50 m² 130,000 195,000
5 Finish dinding kamar mandi 12.75 m² 120,000 1,530,000

F PEKERJAAN PINTU
1 Pintu jendela 2.00 unit 2,000,000 4,000,000
2 Pintu kamar mandi 2.00 unit 500,000 1,000,000
3 Jendela 2.00 unit 750,000 1,500,000

G PEKERJAAN PLAFOND
1 Plafond gypsumboard+rangka 22.50 m² 150,000 3,375,000
2 shadowline 33.00 m' 25,000 825,000
3 Cat plafond 22.50 m² 30,000 675,000

H PEKERJAAN SANITARI
1 Closet 2.00 unit 750,000 1,500,000
2 Kran air 2.00 unit 270,000 540,000
3 Floor drain 2.00 unit 315,000 630,000
4 Pipa air bersih 20.00 m' 25,000 500,000
5 Pipa air kotor 20.00 m' 35,000 700,000
6 lain" 1.00 ls 387,000 387,000

I PEKERJAAN ELEKTRIKAL
1 Lampu 4.00 unit 150,000 600,000
2 Saklar 4.00 unit 150,000 600,000
3 Stop kontak 4.00 unit 150,000 600,000
4 Lain" 1.00 ls 180,000 180,000

J PEKERJAAN LAIN-LAIN
1 Bowplank 1.00 ls 720,000 720,000

JUMLAH TOTAL PEKERJAAN GARDU DISTRIBUSI 83,926,762