KEGIATAN :
Pembangunan Rumah Kost Ibu Suraedah
di Samata
TAHUN 2021
REKAPITULASI
RENCANA ANGGARAN BIAYA
JUMLAH HARGA
NO. NAMA PEKERJAAN
(Rp)
1 2 3
JUMLAH 700,352,985.60
DIBULATKAN Rp 700,300,000.00
TERBILANG : TUJUH RATUS JUTA TIGA RATUS RIBU RUPIAH
Enrekang,………………….. 2020
RENCANA ANGGARAN BIAYA (RAB)
3 Pek. Sloof 15 x 20
3.1. Bekisting 2x pakai Plywood 9 mm m2 52.66 127,755.50 6,727,604.63
3.2. Pembesian Besi Ø 12 mm kg 753.97 18,551.80 13,987,426.79
3.3. Beton K225 m3 4.12 1,388,075.00 5,724,247.79
4 Pek. Kolom 15 x 15
4.1. Bekisting 2x pakai Plywood 9 mm m2 117.60 231,812.00 27,261,091.20
4.2. Pembesian Besi Ø 12 mm kg 1,069.12 18,551.80 19,834,115.61
4.3. Beton K225 m3 6.00 1,388,075.00 8,331,920.19
7 Pek. Atap
7.1. Rangka Atap Kuda-Kuda Baja Ringan m2 175.75 258,038.72 45,350,304.16
7.2. Atap Spandek m2 175.75 134,396.13 23,620,119.85
7.3. Listplank m' 24.90 42,209.00 1,051,004.10
2 Pek. Lantai
2.1. Timbunan Tanah Bawah Lantai m2 25.13 193,350.00 4,858,361.91
2.2. Pasir Urug Bawah Lantai m2 13.61 211,500.00 2,878,493.00
2.3. Rabat Beton m3 6.80 1,214,852.00 8,267,004.69
2.4. Homogenous Tile uk. 40 x 40 m2 82.42 331,677.00 27,338,131.78
2.5. Homogenous Tile uk. 20 x 20 m2 11.83 292,488.00 3,458,670.60
3 Pek. Plafond
3.1. Pek. Rangka Plafond Hollow 4/4 dan 2/4 m2 175.75 193,558.00 34,017,818.50
3.2. Pek. Plafond Gypsumboard m2 175.75 68,026.00 11,955,569.50
4 Pek. Pengecatan
4.1. Pek. Pengecatan Interior m2 402.92 47,379.00 19,089,946.68
4.2. Pek. Pengecatan Eksterior m2 402.92 59,333.00 23,906,452.36
4.3. Pek. Pengecatan Plafond m2 175.75 47,379.00 8,326,859.25
2 Pintu PVC
2.1. Pintu PVC bh 10.00 750,000.00 7,500,000.00
3 Jendela 1 (J1)
3.1. Kusen Kayu Kayu Klas II m3 0.63 9,914,657.00 6,246,233.91
3.2. Daun Jendela + Kaca Kayu Klas II m2 12.00 752,851.00 9,034,212.00
3.3. Engsel Jendela bh 40.00 34,866.00 1,394,640.00
3.4. Spring Knip Jendela bh 40.00 93,955.00 3,758,200.00
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.7500 138,700.000 104,025.00
Mandor L.04.01 OH 0.0250 216,300.000 5,407.50
JUMLAH TENAGA KERJA 109,432.50
B BAHAN 0.00 -
JUMLAH HARGA BAHAN
C PERALATAN 0.00 -
JUMLAH HARGA ALAT
D Jumlah (A+B+C) - 109,432.50
E Overhead & Profit 10% 10% 10,943.25
F Harga Satuan Pekerjaan (D+E) - 120,375.00
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.2500 138,700.00 34,675.00
Mandor L.04.01 OH 0.0250 216,300.00 5,407.50
JUMLAH TENAGA KERJA 40,082.50
B BAHAN 0.00 -
JUMLAH HARGA BAHAN
C PERALATAN 0.00 -
JUMLAH HARGA ALAT
D Jumlah (A+B+C) - 40,082.50
E Overhead & Profit 10% 10% 4,008.25
F Harga Satuan Pekerjaan (D+E) - 44,090.00
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.3000 138,700.00 41,610.00
Mandor L.04.01 OH 0.0100 216,300.00 2,163.00
JUMLAH TENAGA KERJA 43,773.00
B BAHAN
Pasir urug M3 1.2000 247,500.00 297,000.00
JUMLAH HARGA BAHAN
C PERALATAN 0.00 -
JUMLAH HARGA ALAT
D Jumlah (A+B+C) 0.00 192,273.00
E Overhead & Profit 10% 10% 19,227.30
F Harga Satuan Pekerjaan (D+E) 0.00 211,500.00
A.2.3.1.11. Pengurugan 1 m3 dengan tanah timbunan
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.3000 138,700.00 41,610.00
Mandor L.04.01 OH 0.0100 216,300.00 2,163.00
JUMLAH TENAGA KERJA 43,773.00
B BAHAN
Tanah Timbunan M3 1.2000 220,000.00 264,000.00
JUMLAH HARGA BAHAN
C PERALATAN 0.00 -
JUMLAH HARGA ALAT
D Jumlah (A+B+C) 0.00 175,773.00
E Overhead & Profit 10% 10% 17,577.30
F Harga Satuan Pekerjaan (D+E) 0.00 193,350.00
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 1.5000 138,700.00 208,050.00
Tukang Batu L.02.03 OH 0.7500 173,300.00 129,975.00
Kepala Tukang L.03.01 OH 0.0750 187,200.00 14,040.00
Mandor L.04.01 OH 0.0750 216,300.00 16,222.50
JUMLAH TENAGA KERJA 368,287.50
B BAHAN
Batu belah m3 1.2000 385,000.00 462,000.00
Semen portland Kg 163.0000 1,430.00 233,090.00
Pasir Pasang m3 0.5200 247,500.00 128,700.00
JUMLAH HARGA BAHAN 823,790.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 1,192,077.50
E Overhead & Profit 10% 10% 119,207.75
F Harga Satuan Pekerjaan (D+E) - 1,311,285.00
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.7800 138,700.00 108,186.00
Tukang Batu L.02.03 OH 0.3900 173,300.00 67,587.00
Kepala Tukang L.03.01 OH 0.0390 187,200.00 7,300.80
Mandor L.04.01 OH 0.0390 216,300.00 8,435.70
JUMLAH TENAGA KERJA 191,509.50
B BAHAN
Batu belah m3 1.2000 451,000.00 541,200.00
Pasir urug m3 0.4320 177,000.00 76,464.00
JUMLAH HARGA BAHAN 617,664.00
C PERALATAN 0.00 -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 809,173.50
E Overhead & Profit 10% 10% 80,917.35
F Harga Satuan Pekerjaan (D+E) - 890,090.00
HARGA SATUAN PEKERJAAN BETON
A.4.1.1.1 Membuat 1 m3 beton mutu f’c = 7,4 MPa (K 100)
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 1.6500 138,700.00 228,855.00
Tukang Batu L.02.03 OH 0.2750 173,300.00 47,657.50
Kepala Tukang L.03.01 OH 0.0280 187,200.00 5,241.60
Mandor L.04.01 OH 0.0830 216,300.00 17,952.90
JUMLAH TENAGA KERJA 299,707.00
B BAHAN
Semen portland kg 247.0000 1,430.00 353,210.00
Pasir Beton kg 869.0000 190.38 165,444.23
Kerikil (Maks 30 mm) kg 999.0000 264.81 264,550.00
Air Liter 215.0000 100.00 21,500.00
JUMLAH HARGA BAHAN 804,704.23
C PERALATAN 0.00 -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 1,104,411.23
E Overhead & Profit 10% 10% 110,441.12
F Harga Satuan Pekerjaan (D+E) - 1,214,852.00
A.4.1.1.7. Membuat 1 m3 beton mutu f’ = 19,3 MPa (K 225), slump (120 ± 20) mm, w/c = 0,58
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 1.6500 138,700.00 228,855.00
Tukang Batu L.02.03 OH 0.2750 173,300.00 47,657.50
Kepala Tukang L.03.01 OH 0.0280 187,200.00 5,241.60
Mandor L.04.01 OH 0.0830 216,300.00 17,952.90
JUMLAH TENAGA KERJA 299,707.00
B BAHAN
Semen portland kg 371.0000 1,430.00 530,530.00
Pasir Beton kg 698.0000 190.38 132,888.46
Kerikil (Maks 30 mm) kg 1047.0000 264.81 277,261.11
Air Liter 215.0000 100.00 21,500.00
JUMLAH HARGA BAHAN 962,179.57
C PERALATAN 0.00 -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 1,261,886.57
E Overhead & Profit 10% 10% 126,188.66
F Harga Satuan Pekerjaan (D+E) - 1,388,075.00
A.4.1.1.17 Pembesian 10 kg dengan besi polos atau besi ulir
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.0700 138,700.00 9,709.00
Tukang Besi L.02.05 OH 0.0700 173,300.00 12,131.00
Kepala Tukang L.03.01 OH 0.0070 187,200.00 1,310.40
Mandor L.04.01 OH 0.0040 216,300.00 865.20
JUMLAH TENAGA KERJA 24,015.60
B BAHAN
Besi beton (polos/ulir) kg 10.5000 13,500.00 141,750.00
Kawat beton kg 0.1500 19,250.00 2,887.50
JUMLAH HARGA BAHAN 144,637.50
C PERALATAN 0.00 -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 168,653.10
E Overhead & Profit 10% 10% 16,865.31
F Harga Satuan Pekerjaan (D+E) - 185,518.00
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.5200 138,700.00 72,124.00
Tukang Kayu L.02.04 OH 0.2600 173,300.00 45,058.00
Kepala Tukang L.03.01 OH 0.0260 187,200.00 4,867.20
Mandor L.04.01 OH 0.0260 216,300.00 5,623.80
JUMLAH TENAGA KERJA 127,673.00
B BAHAN
Kayu kelas III m3 0.0450 2,200,000.00 99,000.00
Paku 5 - 10 cm kg 0.3000 18,700.00 5,610.00
Minyak bekisting Liter 0.1000 0.00 -
JUMLAH HARGA BAHAN 104,610.00
C PERALATAN 0.00 -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 232,283.00
E Overhead & Profit 10% 10% 23,228.30
F Harga Satuan Pekerjaan (D+E) - 255,511.00
A.4.1.1.22 (K3) Pemasangan 1 m2 bekisting untuk kolom
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.6600 138,700.00 91,542.00
Tukang Kayu L.02.04 OH 0.3300 173,300.00 57,189.00
Kepala Tukang L.03.01 OH 0.0330 187,200.00 6,177.60
Mandor L.04.01 OH 0.0330 216,300.00 7,137.90
JUMLAH TENAGA KERJA 162,046.50
B BAHAN
Kayu kelas III m3 0.0400 2,200,000.00 88,000.00
Paku 5 - 12 cm kg 0.4000 18,700.00 7,480.00
Minyak bekisting Liter 0.2000 0.00 -
Balok kayu kelas II m3 0.0150 3,850,000.00 57,750.00
Tripleks 0.6 mm Lbr 0.3500 132,000.00 46,200.00
Dolken kayu Ø 8-10/400 cm Batang 2.0000 30,000.00 60,000.00
JUMLAH HARGA BAHAN 259,430.00
C PERALATAN 0.00 -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 421,476.50
E Overhead & Profit 10% 10% 42,147.65
F Harga Satuan Pekerjaan (D+E) - 463,624.00
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.6600 138,700.00 91,542.00
Tukang Kayu L.02.04 OH 0.3300 173,300.00 57,189.00
Kepala Tukang L.03.01 OH 0.0330 187,200.00 6,177.60
Mandor L.04.01 OH 0.0330 216,300.00 7,137.90
JUMLAH TENAGA KERJA 162,046.50
B BAHAN
Kayu kelas III m3 0.0400 2,200,000.00 88,000.00
Paku 5 - 12 cm kg 0.4000 18,700.00 7,480.00
Minyak bekisting Liter 0.2000 0.00 -
Balok kayu kelas II m3 0.0180 3,850,000.00 69,300.00
Tripleks 0.6 mm Lbr 0.3500 132,000.00 46,200.00
Dolken kayu Ø 8-10/400 cm Batang 2.0000 30,000.00 60,000.00
JUMLAH HARGA BAHAN 270,980.00
C PERALATAN 0.00 -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 433,026.50
E Overhead & Profit 10% 10% 43,302.65
F Harga Satuan Pekerjaan (D+E) - 476,329.00
A.4.4.1.9 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SP :4PP
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.3000 138,700.00 41,610.00
Tukang Batu L.02.03 OH 0.1000 173,300.00 17,330.00
Kepala Tukang L.03.01 OH 0.0100 187,200.00 1,872.00
Mandor L.04.01 OH 0.0150 216,300.00 3,244.50
JUMLAH TENAGA KERJA 64,056.50
B BAHAN
Bata merah m3 70.0000 1,100.00 77,000.00
Semen portland Kg 11.5000 1,430.00 16,445.00
Pasir Pasang m3 0.0430 247,500.00 10,642.50
JUMLAH HARGA BAHAN 104,087.50
C PERALATAN 0.00 -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 168,144.00
E Overhead & Profit 10% 10% 16,814.40
F Harga Satuan Pekerjaan (D+E) - 184,958.00
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.3000 138,700.00 41,610.00
Tukang Batu L.02.03 OH 0.1500 173,300.00 25,995.00
Kepala Tukang L.03.01 OH 0.0150 187,200.00 2,808.00
Mandor L.04.01 OH 0.0150 216,300.00 3,244.50
JUMLAH TENAGA KERJA 73,657.50
B BAHAN
Semen portland Kg 10.2240 1,430.00 14,620.32
Pasir Pasang m3 0.0200 247,500.00 4,950.00
JUMLAH HARGA BAHAN 19,570.32
C PERALATAN 0.00 -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 0.00 93,227.82
E Overhead & Profit 10% 10% 9,322.78
F Harga Satuan Pekerjaan (D+E) 0.00 102,550.00
A.4.4.2.27. Pemasangan 1 m2 acian.
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.2000 138,700.00 27,740.00
Tukang Batu L.02.03 OH 0.1000 173,300.00 17,330.00
Kepala Tukang L.03.01 OH 0.0100 187,200.00 1,872.00
Mandor L.04.01 OH 0.0100 216,300.00 2,163.00
JUMLAH TENAGA KERJA 49,105.00
B BAHAN
Semen portland Kg 3.2500 1,430.00 4,647.50
JUMLAH HARGA BAHAN 4,647.50
C PERALATAN 0.00 -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 53,752.50
E Overhead & Profit 10% 10% 5,375.25
F Harga Satuan Pekerjaan (D+E) - 59,127.00
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.7000 138,700.00 97,090.00
Tukang Batu L.02.03 OH 0.3500 173,300.00 60,655.00
Kepala tukang L.03.01 OH 0.0350 187,200.00 6,552.00
Mandor L.04.01 OH 0.0350 216,300.00 7,570.50
JUMLAH TENAGA KERJA 171,867.50
B BAHAN
keramik ukuran 40cm x 40cm Bh 11.8700 6,000.00 71,220.00
Semen portland Kg 10.0000 1,430.00 14,300.00
Pasir Pasang M3 0.0450 247,500.00 11,137.50
Semen Warna Kg 1.5000 22,000.00 33,000.00
JUMLAH HARGA BAHAN 129,657.50
C PERALATAN 0.00 -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 301,525.00
E Overhead & Profit 10% 10% 30,152.50
F Harga Satuan Pekerjaan (D+E) - 331,677.00
A.4.4.3.36. Pemasangan 1m2 lantai keramik ukuran 20cm x 20cm
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.7000 138,700.00 97,090.00
Tukang Batu L.02.03 OH 0.3500 173,300.00 60,655.00
Kepala tukang L.03.01 OH 0.0350 187,200.00 6,552.00
Mandor L.04.01 OH 0.0350 216,300.00 7,570.50
JUMLAH TENAGA KERJA 171,867.50
B BAHAN
Keramik ukuran 20cm x 20cm Bh 11.8700 2,728.00 32,381.36
Semen portland Kg 10.4000 1,430.00 14,872.00
Pasir Pasang M3 0.0450 247,500.00 11,137.50
Semen Warna Kg 1.6200 22,000.00 35,640.00
JUMLAH HARGA BAHAN 94,030.86
C PERALATAN 0.00 -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 265,898.36
E Overhead & Profit 10% 10% 26,589.84
F Harga Satuan Pekerjaan (D+E) - 292,488.00
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.1000 138,700.00 13,870.00
Tukang kayu L.02.04 OH 0.0500 173,300.00 8,665.00
Kepala tukang L.03.01 OH 0.0050 187,200.00 936.00
Mandor L.04.01 OH 0.0050 216,300.00 1,081.50
JUMLAH TENAGA KERJA 24,552.50
B BAHAN
Gypsum board 9 mm (1200 x 2400 mm) Lembar 0.3640 82,500.00 30,030.00
Paku skrup kg 0.1100 66,000.00 7,260.00
JUMLAH HARGA BAHAN 37,290.00
C PERALATAN 0.00 -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 0.00 61,842.50
E Overhead & Profit 10% 10% 6,184.25
F Harga Satuan Pekerjaan (D+E) 0.00 68,026.00
A.4.5.1.9. Pemasangan 1 m’ list langit-langit kayu profil
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.0500 138,700.00 6,935.00
Tukang Kayu L.02.04 OH 0.0500 173,300.00 8,665.00
Kepala tukang L.03.01 OH 0.0050 187,200.00 936.00
Mandor L.04.01 OH 0.0030 216,300.00 648.90
JUMLAH TENAGA KERJA 17,184.90
B BAHAN
List kayu profil m 1.0500 20,000.00 21,000.00
Paku Biasa kg 0.0100 18,700.00 187.00
JUMLAH HARGA BAHAN 21,187.00
C PERALATAN 0.00 -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 0.00 38,371.90
E Overhead & Profit 10% 10% 3,837.19
F Harga Satuan Pekerjaan (D+E) 0.00 42,209.00
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A. TENAGA
Pekerja L.01 OH 0.200 138,700.00 27,740.00
Tukang kayu L.02 OH 0.100 173,300.00 17,330.00
Kepala tukang L.03 OH 0.010 187,200.00 1,872.00
Mandor L.04 OH 0.001 216,300.00 216.30
JUMLAH TENAGA KERJA 47,158.30
B. BAHAN
Atap Spandek T. 0.40 m2 1.200 60,500.00 72,600.00
Paku Skrup Kg 0.040 60,500.00 2,420.00
JUMLAH HARGA BAHAN 75,020.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah ( A + B + C ) 122,178.30
E Overhead & Profit 10% x D (maksimum) 12,217.83
F Harga Satuan Pekerjaan 134,396.13
A.4.6.1.2. Pembuatan dan pemasangan 1 m3 kusen pintu dan kusen jendela, kayu kelas II atau III
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 6.0000 138,700.00 832,200.00
Tukang kayu L.02.04 OH 18.0000 173,300.00 3,119,400.00
Kepala tukang L.03.01 OH 1.8000 187,200.00 336,960.00
Mandor L.04.01 OH 0.3000 216,300.00 64,890.00
JUMLAH TENAGA KERJA 4,353,450.00
B BAHAN
Balok kayu m3 1.2000 3,850,000.00 4,620,000.00
Paku Biasa Kg 1.2500 18,700.00 23,375.00
Lem Kayu/Karet Kg 1.0000 16,500.00 16,500.00
JUMLAH HARGA BAHAN 4,659,875.00
C PERALATAN 0.00 -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 9,013,325.00
E Overhead & Profit 10% 10% 901,332.50
F Harga Satuan Pekerjaan (D+E) - 9,914,657.00
A.4.6.1.5. Pembuatan dan pemasangan 1 m2 daun pintu panel, kayu kelas I atau II
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 1.0000 138,700.00 138,700.00
Tukang kayu L.02.04 OH 3.0000 173,300.00 519,900.00
Kepala tukang L.03.01 OH 0.3000 187,200.00 56,160.00
Mandor L.04.01 OH 0.0500 216,300.00 10,815.00
JUMLAH TENAGA KERJA 725,575.00
B BAHAN
kayu Papan m3 0.0400 4,125,000.00 165,000.00
Lem Kayu/Karet Kg 0.5000 16,500.00 8,250.00
JUMLAH HARGA BAHAN 173,250.00
C PERALATAN 0.00 -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 0.00 898,825.00
E Overhead & Profit 10% 10% 89,882.50
F Harga Satuan Pekerjaan (D+E) 0.00 988,707.00
A.4.6.1.6. Pembuatan dan pemasangan 1 m2 pintu dan jendela kaca, kayu kelas I atau II
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.8000 138,700.00 110,960.00
Tukang kayu L.02.04 OH 2.4000 173,300.00 415,920.00
Kepala tukang L.03.01 OH 0.2400 187,200.00 44,928.00
Mandor L.04.01 OH 0.0400 216,300.00 8,652.00
JUMLAH TENAGA KERJA 580,460.00
B BAHAN
kayu Papan m3 0.0240 4,125,000.00 99,000.00
Lem Kayu/Karet Kg 0.3000 16,500.00 4,950.00
JUMLAH HARGA BAHAN 103,950.00
C PERALATAN 0.00 -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 0.00 684,410.00
E Overhead & Profit 10% 10% 68,441.00
F Harga Satuan Pekerjaan (D+E) 0.00 752,851.00
A.4.6.2.2. Pemasangan 1 buah kunci tanam biasa
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.010 138,700.00 1,387.00
Tukang kayu L.02.04 OH 0.500 173,300.00 86,650.00
Kepala tukang L.03.01 OH 0.050 187,200.00 9,360.00
Mandor L.04.01 OH 0.005 216,300.00 1,081.50
JUMLAH TENAGA KERJA 98,478.50
B BAHAN
Kunci tanam biasa Bh 1.000 110,000.00 110,000.00
JUMLAH HARGA BAHAN 110,000.00
C PERALATAN 0.00 -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 0.00 208,478.50
E Overhead & Profit 10% 10% 20,847.85
F Harga Satuan Pekerjaan (D+E) 0.00 229,326.00
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.015 138,700.00 2,080.50
Tukang kayu L.02.04 OH 0.150 173,300.00 25,995.00
Kepala tukang L.03.01 OH 0.015 187,200.00 2,808.00
Mandor L.04.01 OH 0.001 216,300.00 173.04
JUMLAH TENAGA KERJA 31,056.54
B BAHAN
Engsel pintu Bh 1.000 27,500.00 27,500.00
JUMLAH HARGA BAHAN 27,500.00
C PERALATAN 0.00 -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 0.00 58,556.54
E Overhead & Profit 10% 10% 5,855.65
F Harga Satuan Pekerjaan (D+E) 0.00 64,412.00
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.010 138,700.00 1,387.00
Tukang kayu L.02.04 OH 0.100 173,300.00 17,330.00
Kepala tukang L.03.01 OH 0.010 187,200.00 1,872.00
Mandor L.04.01 OH 0.001 216,300.00 108.15
JUMLAH TENAGA KERJA 20,697.15
B BAHAN
Engsel kupu-kupu Bh 1.000 11,000.00 11,000.00
JUMLAH HARGA BAHAN 11,000.00
C PERALATAN 0.00 -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 0.00 31,697.15
E Overhead & Profit 10% 10% 3,169.72
F Harga Satuan Pekerjaan (D+E) 0.00 34,866.00
A.4.6.2.8. Pemasangan 1 buah spring knip
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.015 138,700.00 2,080.50
Tukang kayu L.02.04 OH 0.150 173,300.00 25,995.00
Kepala tukang L.03.01 OH 0.015 187,200.00 2,808.00
Mandor L.04.01 OH 0.008 216,300.00 1,730.40
JUMLAH TENAGA KERJA 32,613.90
B BAHAN
Spring knip Bh 1.000 52,800.00 52,800.00
JUMLAH HARGA BAHAN 52,800.00
C PERALATAN 0.00 -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 0.00 85,413.90
E Overhead & Profit 10% 10% 8,541.39
F Harga Satuan Pekerjaan (D+E) 0.00 93,955.00
A.4.7.1.10. Pengecatan 1 m2 tembok baru ( 1lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup) interior
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.020 138,700.00 2,774.00
Tukang cat L.02.08 OH 0.063 173,300.00 10,917.90
Kepala tukang L.03.01 OH 0.006 187,200.00 1,179.36
Mandor L.04.01 OH 0.003 216,300.00 648.90
JUMLAH TENAGA KERJA 15,520.16
B BAHAN
Plamuur Kg 0.100 49,500.00 4,950.00
Cat dasar Tembok Kg 0.100 37,257.14 3,725.71
Cat Penutup Tembok Kg 0.260 72,600.00 18,876.00
JUMLAH HARGA BAHAN 27,551.71
C PERALATAN 0.00 -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 0.00 43,071.87
E Overhead & Profit 10% 10% 4,307.19
F Harga Satuan Pekerjaan (D+E) 0.00 47,379.00
A.4.7.1.10. Pengecatan 1 m2 tembok baru ( 1lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup) eksterior
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.020 138,700.00 2,774.00
Tukang cat L.02.08 OH 0.063 173,300.00 10,917.90
Kepala tukang L.03.01 OH 0.006 187,200.00 1,179.36
Mandor L.04.01 OH 0.003 216,300.00 648.90
JUMLAH TENAGA KERJA 15,520.16
B BAHAN
Plamuur Kg 0.100 49,500.00 4,950.00
Cat dasar Tembok Kg 0.100 37,257.14 3,725.71
Cat Penutup Tembok Kg 0.260 114,400.00 29,744.00
JUMLAH HARGA BAHAN 38,419.71
C PERALATAN 0.00 -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 0.00 53,939.87
E Overhead & Profit 10% 10% 5,393.99
F Harga Satuan Pekerjaan (D+E) 0.00 59,333.00
A.5.1.1 2. Pemasangan 1 buah closet jongkok porslen
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 1.000 138,700.00 138,700.00
Tukang batu L.02.03 OH 1.500 173,300.00 259,950.00
Kepala tukang L.03.01 OH 0.150 187,200.00 28,080.00
Mandor L.04.01 OH 0.160 216,300.00 34,608.00
JUMLAH TENAGA KERJA 461,338.00
B BAHAN
Closet jongkok Unit 1.000 313,500.00 313,500.00
Semen portland Kg 6.000 1,430.00 8,580.00
Pasir pasang M3 0.010 247,500.00 2,475.00
JUMLAH HARGA BAHAN 324,555.00
C PERALATAN 0.00 -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 0.00 785,893.00
E Overhead & Profit 10% 10% 78,589.30
F Harga Satuan Pekerjaan (D+E) 0.00 864,482.00
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.081 138,700.00 11,234.70
Tukang batu L.02.03 OH 0.135 173,300.00 23,395.50
Kepala tukang L.03.01 OH 0.014 187,200.00 2,527.20
Mandor L.04.01 OH 0.004 216,300.00 865.20
JUMLAH TENAGA KERJA 38,022.60
B BAHAN
Pipa PVC 3” M 1.200 30,250.00 36,300.00
Perlengkapan % 35.000 30,250.00 10,587.50
JUMLAH HARGA BAHAN 46,887.50
C PERALATAN 0.00 -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 0.00 84,910.10
E Overhead & Profit 10% 10% 8,491.01
F Harga Satuan Pekerjaan (D+E) 0.00 93,401.00
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.081 138,700.00 11,234.70
Tukang batu L.02.03 OH 0.135 173,300.00 23,395.50
Kepala tukang L.03.01 OH 0.014 187,200.00 2,527.20
Mandor L.04.01 OH 0.004 216,300.00 865.20
JUMLAH TENAGA KERJA 38,022.60
B BAHAN
Pipa PVC 4” M 1.200 110,916.67 133,100.00
Perlengkapan % 35.000 110,916.67 38,820.83
JUMLAH HARGA BAHAN 171,920.83
C PERALATAN 0.00 -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 0.00 209,943.43
E Overhead & Profit 10% 10% 20,994.34
F Harga Satuan Pekerjaan (D+E) 0.00 230,937.00
Pemasangan 1 buah saklar ganda
Kode Satuan Koefisien Harga Satuan Jumlah Harga
No Uraian
(Rp) (Rp)
1 2 3 4 5 6 7
A Tenaga Kerja
Upah % 0.10 138,700.00 13,870.00
Jumlah Harga Tenaga Kerja 13,870.00
B Bahan
Saklar ganda bh 1.00 19,500.00 19,500.00
Jumlah Harga Bahan 19,500.00
C Peralatan
Jumlah Harga Peralatan -
D Jumlah (A+B+C) 33,370.00
E Overhead + Profit 10% X D 3,337.00
F Harga Satuan Pekerjaan Per- m³ (D+E) 36,707.00
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 OH 0.2000 138,700.00 27,740.00
Tukang Kayu L.02 OH 0.3000 173,300.00 51,990.00
Kepala tukang L.03 OH 0.0300 187,200.00 5,616.00
Mandor L.04 OH 0.0100 216,300.00 2,163.00
JUMLAH TENAGA KERJA 87,509.00
B BAHAN
Rangka Hollow 2x4 Galvanis m' 2.0460 17,416.67 35,634.50
Rangka Hollow 4X4 Galvanis m' 1.5620 29,333.33 45,818.67
Paku Rumset bh 14.0000 500.00 7,000.00
JUMLAH HARGA BAHAN 88,453.17
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 175,962.17
E Overhead & Profit 10% 10% 17,596.22
F Harga Satuan Pekerjaan (D+E) - 193,558.00
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A. TENAGA
Pekerja L.01 OH 0.247 138,700.00 34,258.90
Tukang kayu L.02 OH 0.176 173,300.00 30,500.80
Kepala tukang L.03 OH 0.117 187,200.00 21,902.40
Mandor L.04 OH 0.059 216,300.00 12,653.55
JUMLAH TENAGA KERJA 99,315.65
B. BAHAN
Main Truss C.70 - 80 M 2.800 14,300.00 40,040.00
Roof Botton/ Reng (R.33-0.45) M 5.100 6,416.67 32,725.00
Self Drilling Screw Truss Bh 25.000 1,000.00 25,000.00
Self Drilling Screw Roof Botton Bh 35.000 1,000.00 35,000.00
Dinabolt Bh 1.000 2,500.00 2,500.00
JUMLAH HARGA BAHAN 135,265.00
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah ( A + B + C ) 234,580.65
E Overhead & Profit 10% 23,458.07
F Harga Satuan Pekerjaan (D+E) 258,038.72
HARGA SATUAN BAHAN & UPAH KERJA
TAHUN ANGGARAN 2020
HASIL SURVEY
NO BAHAN MATERIAL DAN UPAH KERJA SATUAN
TRIWULAN I
1 2 3 4
B. BAHAN DASAR
1 Batu Kali M3 Rp 385,000.00
2 Batu kali Belah M3 Rp 275,000.00
3 Batu Gunung M3 Rp 385,000.00
4 Batu gunung Belah 10 - 15 cm M3 Rp 275,000.00
5 Batu Pecah 7 - 10 cm M3 Rp 440,000.00
6 Batu Pecah 5 - 7 cm M3 Rp 385,000.00
7 Batu Pecah 3 - 5 cm M3 Rp 385,000.00
8 Batu Pecah 2 - 3 cm M3 Rp 385,000.00
9 Batu Pecah 1- 2 cm M3 Rp 385,000.00
10 Batu Pecah 0,5 - 1 cm M3 Rp 385,000.00
11 Batu Merah Standar Biji Rp 1,100.00
12 Bata Ringan M3 Rp 990,000.00
13 Batako 40x20x10 cm - 13 Bh/M2 @Rp.4950 M2 Rp 70,800.00
14 Roster Beton 20 x 20 cm Biji Rp 27,500.00
15 Roster Keramik 20 x 20 cm Biji Rp 57,200.00
16 Roster Keramik 30 x 30 cm Biji Rp 68,200.00
17 Roster Keramik 20 x 40 cm Biji Rp 68,200.00
18 Glass Block Biji Rp 33,000.00
19 Gravel M3 Rp 165,000.00
20 Pasir Kasar/Pasir Beton/Pasir Pasangan M3 Rp 247,500.00
21 Sirtu A M3 Rp 286,000.00
22 Sirtu B M3 Rp 286,000.00
23 Sirtu C M3 Rp 286,000.00
24 Pasir Timbunan M3 Rp 176,000.00
25 Tanah Timbunan M3 Rp 220,000.00
26 Kerikil Sungai M3 Rp 357,500.00
27 Semen 50 kg (Tonasa) PC Sak Rp 71,500.00
28 Semen 40 kg (Tonasa) PC Sak Rp 52,800.00
29 Semen (Bosowa 40 kg) PC Zak Rp 51,700.00
30 Semen Tiga Roda 40 Kg PC Zak Rp 51,700.00
31 Semen Holcim 40 Kg PC Zak Rp 49,500.00
32 Semen Putih 40 kg per sak Sak Rp 77,000.00
33 Pigmen Warna Sak Rp 275,000.00
34 Semen Nat Tegel Kg Rp 22,000.00
35 Semen Abu Tiga Roda 40 Kg Kg Rp 49,500.00
36 Semen Abu Tiga Roda 50 Kg Kg Rp 62,200.00
37 Semen Putih Tiga Roda 40 Kg Kg Rp 126,300.00
38 Semen Acian Mortar Putih 40 Kg Kg Rp 121,300.00
39 Water Proofing M2 Rp 54,500.00
40 Paku jembatan kg Rp 33,000.00
41 Plastik untuk beton M2 Rp 88,000.00
42 Batu Kecil Gravel Batu Pecah atau Batu Tumbuk (Batu Gunung) M3 Rp 385,000.00
D 'BAHAN BESI
1 Angker Mur Baut Kecil Bh Rp 9,600.00
2 Angker Baut Tinggi 70 cm Bh Rp 8,000.00
3 Baut Diameter 12 mm x 10 cm (stainless) wf 150 Batang/Biji Rp 14,300.00
4 Baut Diameter 12 mm x 12,50 cm (stainless) Batang Rp 23,100.00
5 Baut Diameter 12 mm x 18 cm Batang Rp 14,800.00
6 Baut Diameter 12 mm x 20 cm Batang Rp 15,500.00
7 Baut Diameter 12 mm x 25 cm Batang Rp 19,200.00
8 Baut Diameter 12 mm x 30 cm Batang Rp 22,000.00
9 Baut Skrup Bh Rp 6,100.00
10 Baut Baja Bh Rp 27,500.00
11 Besi Streep 30 x 3 mm M'/ Btg Rp 209,000.00
12 Besi Hollow 40.60.1,2 mm P = 6 m Btg Rp 201,300.00
13 Besi Hollow 40.60.1 mm P = 6 m Btg Rp 203,500.00
14 Besi Hollow 40.40. 2 mm P = 6 m /40.40. 1,8 P = 6 m Btg Rp 209,000.00
15 Besi Hollow 40.40.1,5 mm P = 6 m Btg Rp 176,000.00
16 Besi Hollow 40.20.2 mm P =6 m Btg Rp 148,500.00
17 Besi Hollow 40.20.1,5 mm P =6 m Btg Rp 126,500.00
18 Besi Hollow 40.20.1,2 mm P = 6 m Btg Rp 104,500.00
19 Besi Hollow 20.20.1,5 mm P = 6 m Btg Rp 93,500.00
20 Besi Hollow 2x4 (12x31), 0.25mm P = 4m Btg Rp 19,800.00
21 Besi Hollow 2x4 (15x35), 0.25mm P = 4m Btg Rp 20,900.00
22 Besi Hollow 2x4 (18x38), 0.25mm P = 4m Btg Rp 23,100.00
23 Besi Hollow 2x4 (18x38), 0.30mm P = 4m Btg Rp 26,400.00
24 Besi Hollow 2x4 (18x38), 0.35mm P = 4m Btg Rp 29,700.00
25 Besi Hollow 4x4 (34x37), 0.25mm P = 4m Btg Rp 27,500.00
26 Besi Hollow 4x4 (34x37), 0.30mm P = 4m Btg Rp 31,900.00
27 Besi Hollow 4x4 (34x37), 0.40mm P = 4m Btg Rp 40,700.00
28 Besi Kanal C 8 cm, 0.55mm P = 6m Btg Rp 71,500.00
29 Besi Kanal C 8 cm, 0.60mm P = 6m Btg Rp 78,100.00
30 Besi Kanal C 8 cm, 0.65mm P = 6m Btg Rp 82,500.00
31 Besi Kanal C 8 cm, 0.70mm P = 6m Btg Rp 88,000.00
32 Besi Kanal C 8 cm, 0.75mm P = 6m Btg Rp 93,500.00
33 Besi Kanal C 8 cm, 1mm P = 6m Btg Rp 127,600.00
34 Besi Kanal C 8 cm, 0.55mm P = 5,8m Btg Rp 69,300.00
35 Besi Kanal C 8 cm, 0.60mm P = 5,8m Btg Rp 75,900.00
36 Besi Kanal C 8 cm, 0.65mm P = 5,8m Btg Rp 80,300.00
37 Besi Kanal C 8 cm, 0.70mm P = 5,8m Btg Rp 85,300.00
38 Besi Kanal C 8 cm, 0.75mm P = 5,8m Btg Rp 90,800.00
39 Besi Reng 3 cm, 0,4mm P = 6m Btg Rp 38,500.00
40 Besi Reng 3 cm, 0,45mm P = 6m Btg Rp 40,700.00
41 Besi Reng 3 cm, 0,4mm P = 5,8m Btg Rp 37,400.00
42 Besi Reng 3 cm, 0,45mm P = 5,8m Btg Rp 39,600.00
43 Besi Reng 3,8 cm, 0,4mm P = 6m Btg Rp 51,700.00
44 Besi Reng 3,8 cm, 0,45mm P = 6m Btg Rp 57,200.00
45 Besi Reng 3,8 cm, 0,4mm P = 5,8m Btg Rp 50,600.00
46 Besi Reng 3,8 cm, 0,45mm P = 5,8m Btg Rp 55,600.00
47 Plat Besi Kembang 2,3 mm M2 Rp 869,000.00
48 Besi Metal Stud L. 76 mm Btg Rp 77,000.00
49 Besi Siku L. 30.30.3/ 2,8 mm banci Btg Rp 112,800.00
50 Besi siku L. 40.40.4/ 3,8 mm Btg Rp 187,000.00
51 Besi siku L. 50.50.5/ 4,8 mm Btg Rp 275,000.00
52 Besi Siku L. 60. 60. 6/ 5,8 mm Btg Rp 495,000.00
53 Besi Siku L. 70. 70. 7 / 6,8 mm Btg Rp 676,500.00
54 Besi Siku L. 70.70.6 / 5 mm Btg Rp 574,200.00
55 Besi Siku L.100.100.10 Btg Rp 1,177,000.00
56 Besi Beton Polos 6 mm ( 0, 22 kg / M' ) (5,7) Btg Rp 30,800.00
57 Besi Beton Polos 8 mm ( 0,39 kg / M' ) (7,8) Btg Rp 52,800.00
58 Besi Beton polos 10 mm ( 0, 62 kg / M' ) (9,8) Btg Rp 71,500.00
59 Besi Beton Polos 12 mm ( 0, 89 kg / M' ) (11,8) Btg Rp 93,500.00
60 Besi Beton 14 mm ( 1, 21 kg / M' ) (13,8) Btg Rp 159,500.00
61 Besi Beton 16 mm ( 1, 39 kg / M' ) (15,8) Btg Rp 204,600.00
62 Besi Beton 19 mm ( 2, 23 kg / M' ) Btg Rp 269,500.00
63 Besi Beton 20 mm ( 2, 46 kg / M' ) Btg Rp 407,000.00
64 Besi Beton Ulir Dia 8 mm ( 0, 39 kg / M' ) ulir 10 full Btg Rp 86,300.00
65 Besi Beton Ulir Dia. 16 mm SNI Btg Rp 211,700.00
66 Besi Plat 1,5mm 1,2 mm M2 Rp 500,500.00
67 Besi Plat 2 mm (1,8) M2 Rp 711,700.00
68 Besi Plat 2,5mm M2 Rp 803,000.00
69 Besi Plat 3 mm (2,8) M2 Rp 1,001,000.00
70 Besi Plat 3,5mm M2 Rp 1,430,000.00
71 Besi Plat 4 mm M2 Rp 1,540,000.00
72 Besi Plat 4,5mm M2 Rp 1,782,000.00
73 Besi Plat 5 mm (4,8) M2 Rp 1,903,000.00
74 Besi Plat 5,5mm M2 Rp 2,145,000.00
75 Besi Plat 6 mm (5,8) M2 Rp 2,255,000.00
76 Besi Plat 8 mm (7,8) M2 Rp 2,871,000.00
77 Besi Plat 9 mm 10 mm (9,8) M2 Rp 3,685,000.00
78 Besi Plat T = 12 mm Ukr. 120x240 Lembar Rp 4,139,600.00
79 Besi Plat T = 16 mm Ukr. 120x240 Lembar Rp 5,482,400.00
80 Besi Plat T = 18 mm Ukr. 120x240 Lembar Rp 6,283,200.00
81 Baja Tulangan ( Polos ) U24 ᶲ 6 Batang Rp 36,900.00
82 Baja Tulangan ( Polos ) U24 ᶲ 8 Batang Rp 48,400.00
83 Baja Tulangan ( Polos ) U24 ᶲ 10 Batang Rp 72,600.00
84 Baja Tulangan ( Polos ) U24 ᶲ 12 Batang Rp 110,000.00
85 Baja Tulangan ( Polos ) U24 ᶲ 16 Batang Rp 198,000.00
86 Baja Tulangan ( Polos ) U24 ᶲ 16 Batang Rp 172,700.00
87 Baja Tulang ( Ulir ) D32, D39 16 Batang Rp 181,500.00
88 Baja Tulang ( Ulir ) D32, D39 18 Batang Rp 297,000.00
89 Besi Profil H 200x200 P = 12 meter Batang Rp 11,642,400.00
90 Besi Profil H 100x100 P = 12 meter Batang Rp 4,090,300.00
91 Besi IWF 300 P = 12 meter Batang Rp 8,106,600.00
92 Besi IWF 200 P = 12 meter Batang Rp 4,638,500.00
93 Besi UNP 100 P = 6 meter Batang Rp 542,100.00
94 Beugel kap V Plat Besi kg Rp 15,200.00
95 Kawat Ikat Beton 1 roll 20 Kg kg Rp 385,000.00
96 Kawat Dul ( 1 Roll = M ') Roll Rp 192,500.00
97 Kawat Ram Lubang 3,0 cm ( Rang Armonika ) M' Rp 38,500.00
98 Kawat Nyamuk plastik Rang 1 cm L. 1,20 Rang 2 cm M Rp 11,000.00
99 Kawat Nyamuk Aluminium M Rp 27,500.00
100 Kawat Nyamuk Baja M Rp 38,500.00
101 Kawat Las 2,6 nikko Dos Rp 143,000.00
102 Kawat Saringan Pasir / Ayakan M Rp 19,800.00
103 Kawat Bronjong kg Rp 27,500.00
104 Karet Untuk Pintu dan Jendela Aluminium PVC M'/Roll Rp 71,500.00
105 Door Closer Set Unit Rp 203,500.00
106 Kanopi Polycarbonite + Rangka Besi Tempa Biasa 400 per roll M2 Rp 632,500.00
107 Kanopi Polycarbonite + Rangka Besi Tempa Biasa 500 M2 Rp 275,000.00
108 Lem Kayu Dan Karet ( Fox ) Besar ( 800 gr ) Tube Rp 16,500.00
109 Lem Karet ( Fox ) Besar 450 10 kg Tube Rp 203,500.00
110 Lem Seng M Rp 17,600.00
111 Lembaran Atap Ploycarbonite untuk Kanopi Tebal 6 mm Roll Rp 1,622,500.00
112 Lembaran Atap Ploycarbonite untuk Kanopi Tebal 5 mm Roll Rp 3,300,000.00
113 Paku Campuran ( 5-10 cm ) Kg Rp 18,700.00
114 Paku Asbes dan Karet Kg Rp 60,500.00
115 Paku 5 cm 7 cm 10 cm Kg Rp 18,700.00
116 Paku ( 1 1/2 - 2 1/2 cm ) ( setara Paku 2-3 cm ) Kg Rp 22,000.00
117 Paku 4 cm Kg Rp 19,800.00
118 Paku 2-3 cm Kg Rp 20,900.00
119 Paku Sirap ( Setara Paku 2-3 cm ) Kg Rp 24,200.00
120 Paku Seng ( 1 kg/ Dos ) Kg Rp 55,000.00
121 Paku Skrup 5 cm Biji Rp 275,000.00
122 Paku Skrup Besi Hollow - 1000 Biji Per dos ( bdrilling 450 b = 4,5 cm ) Dos/ Bgks Rp 192,500.00
123 Paku skrup Gyapsum - 500 biji per dos bungkus Dos/ Bgks Rp 66,000.00
124 Paku Jembatan Kg Rp 15,400.00
125 Paku Beton 5 cm Dos Rp 16,500.00
126 Paku Beton 6 cm Dos Rp 16,500.00
127 Paku Beton 7 cm - 10 cm Dos Rp 16,500.00
128 Paku Payung Berulir ( 1 kg/ Dos ) Kg Rp 38,500.00
129 Paku Asbes Berulir Dos Rp 52,300.00
130 Paku Asbes Biasa Dos Rp 55,000.00
131 Paku Tripl ( Setara Paku 2-3 cm) Kg Rp 27,500.00
132 Paku Eter ( Setara Paku 2-3 Cm ) Kg Rp 27,500.00
133 Paku Ripet Biji Rp 1,100.00
134 Skamp ( Paku Tembak Hollow alumunium ) Bh Rp 27,500.00
135 pagar Jadi Besi ( Tinggi 1 M ) M' Rp 440,000.00
136 Pagar Pracetak - 5 panel M' Rp 495,000.00
137 Pagar Pracetak - 6 panel M' Rp 550,000.00
138 Pagar Pracetak - 7 panel M' Rp 631,400.00
139 Tiang Beton untuk 5 Daun Buah Rp 264,000.00
140 Tiang Beton untuk 6 Daun Buah Rp 316,800.00
141 Tiang Beton untuk 7 Daun Buah Rp 369,600.00
142 Rangka Baja Ringan 0,75 M2/ 6 Rp 85,800.00
143 Spandek 0,25 silver M Rp 41,800.00
144 Spandek 0,35 silver M Rp 57,200.00
145 Spandek 0,4 silver M Rp 60,500.00
146 Spandek 0,45 0,35 M Rp 61,600.00
147 Nok Spandek M Rp 49,500.00
148 Hollow Aluminium Rangka Plafond 0,25 (2x4) Btg Rp 20,900.00
149 Hollow Aluminium Rangka Plafond 0,3 2x4/4x4 Btg Rp 33,000.00
150 Hollow Aluminium Rangka Plafond 40 X 20 X 2 mm Btg Rp 26,400.00
151 Hollow Aluminium Rangka Plafond 40 X 40 X 2 mm Btg Rp 23,100.00
152 Hollow Aluminium Rangka Plafond 40 X 20 X 8 mm Btg Rp 71,500.00
153 Kawat Penggantung Hollow Aluminium Kg Rp 33,000.00
154 Aluminium 4'' Brown - 6 Meter Btg Rp 231,000.00
155 Aluminium 3'' Brown - 6 Meter Btg Rp 137,500.00
156 Aluminium Slimar 4'' Brown Untuk Daun Jendela Btg Rp 175,500.00
157 Aluminium Slimar 3'' Brown Untuk Daun Jendela Btg Rp 99,900.00
158 Pas. Kusen Aluminium 4' M' Rp 132,000.00
159 Pas. Daun Jendela Alumunium + Kaca Tabel 5 mm + Karet dan Sealent M2 Rp 1,403,200.00
160 Pas. Daun Pintu Aluminium panil Kaca Tebal 5 mm ( Lengkap Accessories ) Unit Rp 302,500.00
161 Pintu KM/WC Alumunium ( lengkap Accessories ) lebar 6 cm Unit Rp 275,000.00
162 Pintu KM/WC PVC kw.1( lengkap Accessories ) lebar 10 cm Unit Rp 253,000.00
163 Pintu fiberglass KM/WC Lembar Rp 242,000.00
164 Pintu KM/WC bahan PVC Lengkap Accessories ex MASPION star Unit Rp 231,000.00
E. BAHAN FINISHING :
1 Cat Minyak Afduner 1kg Liter/botol Rp 5,500.00
2 Cat Kayu Ex Avian (0,9 kg) Kaleng Rp 69,300.00
3 Cat Minyak Ex Emco Kg Rp 71,500.00
4 Cat kKayu Ex Mowilex 1kg Kaleng Rp 46,200.00
5 Cat Minyak Liter Rp 19,800.00
6 Cat Minyak Super klg liter Rp 39,600.00
7 Cat Kayu Dulux 1kg Kg Rp 58,300.00
8 Cat Dasar 3,5 kg Kaleng Rp 130,400.00
9 Cat Dasar Meni 3,5 Kg Kaleng Rp 150,700.00
10 Cat Meni Glatik 3,5 kg Kaleng Rp 105,600.00
11 Cat Tenner Kg Rp 31,000.00
12 Cat Genteng Cap Belmas 1kg Kg Rp 51,700.00
13 Cat Genteng yoko 4kg Kaleng Rp 110,000.00
14 Cat Genteng Biasa AGA (4 kg) Kaleng Rp 203,500.00
15 Cat Genteng Minyak Nippon 2,5 liter Kaleng Rp 220,000.00
16 Cat Residu/ cloter (10 kg) 30.000/ kg Kaleng Rp 330,000.00
17 Cat seng Nippon (2,5 kg) Kaleng Rp 77,000.00
18 Cat Tembok Sahara / Kembang / Postek Aries (25 Kg) Kg Rp 176,000.00
19 Cat Tembok Wintex / Maxilite (5kg) Kaleng Rp 19,800.00
20 Cat Tembok ICI (Dalam) Kaleng Rp 176,000.00
21 Cat Tembok Mowilex (Cat Dalam ) 2,5 Kg soff Kaleng Rp 181,500.00
22 Cat Tembok Mowilex (Cat Luar ) 2,5 Kg gelap & terang Kaleng Rp 286,000.00
23 Cat Tembok Aries 5kg Kaleng Rp 71,500.00
24 Cat Minyak Avian Liter Rp 181,500.00
25 Cat Tembok Kimex (5kg) Kaleng Rp 133,100.00
26 Cat Tembok Dulux (luar) 2,5 kg Kaleng Rp 143,000.00
27 Cat Tembok Warna Kuning , Hitam ,Merah (Belmax) kg Rp 88,000.00
28 Vernis/Plitur (24 Klg) kg Rp 62,700.00
29 Cat Altex Kg Rp 145,200.00
30 Cat Anti Lumut (Aquaseal) (Klg 20kg) Nodrop 20 kg Pail Rp 797,500.00
31 Cat Anti Lumut (No drop) (Klg 20 kg) Pail Rp 792,000.00
32 Cat Dasar Glatik kembang 1 kg Kg Rp 33,000.00
33 Plamur Tembok Boyo Dan Setara (5kg) Kaleng Rp 49,500.00
34 Minyak Cat (aff Dunner) Liter Rp 8,800.00
35 Dempul Kayu Cap Kuning / Merah (1 Kg) klg Kg Rp 44,000.00
36 Dempul Ex Impra Kg Rp 44,000.00
37 Dempul Ex Isamu Kg Rp 60,500.00
38 Tenner A ( Ex Avian) super Liter Rp 35,200.00
39 Minyak Te Botol Liter Rp 9,400.00
40 Kertas Gosok Lembar Rp 5,500.00
41 Pewarna Natural Kaleng Rp 104,500.00
42 pewarna brown Kaleng Rp 77,000.00
43 Pewarna Ex Impra Kaleng Rp 71,500.00
44 Wood Filler Ex Impra Kaleng Rp 71,500.00
45 Clear Kaleng Rp 79,500.00
46 Clear ex Impra Ltr Rp 66,000.00
47 Sending kg Rp 66,000.00
48 Sending ex Impra Ltr Rp 66,000.00
49 Cat Kayu Ex Dullux Mengkilap Kg Rp 93,500.00
50 Melamin Ex Impra kg Rp 148,500.00
51 Cat Air Untuk Genteng, Bataco, Paving Block (AGA) kg Rp 214,500.00
52 Cat Minyak Untuk Genteng, Bataco, Paving Block (AGA) kg Rp 111,700.00
53 Kuas 2" (Eterna) Buah Rp 8,800.00
54 Kuas 3" (Eterna) Buah Rp 13,200.00
55 Kuas 4" (Eterna) Buah Rp 19,800.00
56 Bahan Anti Karat Kg Rp 55,000.00
57 Comice - 20 kg (dingding eksterior ) kg Rp 82,500.00
58 Comice - 20 kg (dingding interior) kg Rp 62,700.00
59 Lem Fox Kaleng kg Rp 159,500.00
60 Lem Efoxi ltr Rp 203,500.00
61 Perban Conpon Roll/Bh Rp 13,200.00
62 Bubuk + air pelarut Ex Aqugart untuk Waterproofing kg Rp 29,700.00
63 Cat Waterproof eks aquaproo- kw.1 kg Rp 176,000.00
64 Cat waterproof- biasa Liter Rp 145,200.00
65 Cat Marka Jalan (aries gold 5kg) kg Rp 74,300.00
66 Aluminium Composite Panel (ACP) Seven Polyster 0,21 (Indoor) Lembar Rp 522,500.00
67 Aluminium Composite Panel (ACP) Seven PVDF 0,3 Doft Lembar Rp 763,400.00
68 Aluminium Composite Panel (ACP) Seven PVDF 0,3 Glossy Lembar Rp 781,000.00
69 Aluminium Composite Panel (ACP) Seven PVDF 0,3 Metalic Lembar Rp 799,700.00
70 Aluminium Composite Panel (ACP) Seven PVDF 0,3 Sparking, Safron, Olive Brown Lembar Rp 812,900.00
71 Aluminium Composite Panel (ACP) Seven Marble, Wood, Brush Lembar Rp 1,059,300.00
F BAHAN KAYU
1 Kayu Kls. I Bayam (balok) Chain Saw M3 Rp 14,300,000.00
2 Kayu Kls. I Bayam (balok) Sawmill M3 Rp 16,500,000.00
3 Kayu Kls. I Ulin (papan) M3 Rp 26,620,000.00
4 Kayu Kls. I Ulin (tiang) M3 Rp 27,500,000.00
5 Kayu Kls. I Bayam (papan) Shain Saw M3 Rp 22,000,000.00
6 Kayu Kls I Bayam(papan) sawmil M3 Rp 22,000,000.00
7 Kayu Klas. II Samarinda (papan)/ Lokal M3 Rp 4,125,000.00
8 Kayu Klas. II Samarinda (balok)/ Lokal M3 Rp 3,850,000.00
9 Kayu Kls. III Kapur (balok)/ Kemiri M3 Rp 2,200,000.00
10 Kayu Kls. III (papan) M3 Rp 2,200,000.00
11 Kayu Mangga/Kemiri (papan) M3 Rp 2,750,000.00
12 Kayu Kumea Balok M3 Rp 9,350,000.00
13 Kayu Kumea Papan M3 Rp 10,450,000.00
14 Kayu lapis Tripleks Lapis Kayu Lainnya Uk. (0,4 x 122 x 244)cm Lembar Rp 66,000.00
15 Kayu lapis Tripleks Lapis Kayu Lainnya Uk. (0,3 x 122 x 244)cm Lembar Rp 55,000.00
16 Kayu lapis Tripleks Lapis Kayu Lainnya Uk. (0,6 x 122 x 244)cm Lembar Rp 88,000.00
17 Kayu lapis Tripleks Lapis Kayu Lainnya (18 mm) Lembar Rp 308,000.00
18 Kayu lapis Tripleks Lapis Kayu Lainnya (12 mm) Lembar Rp 198,000.00
19 Kayu lapis Tripleks Lapis Kayu Lainnya ( 9 mm) Lembar Rp 132,000.00
20 Kayu lapis Tripleks Lapis Kayu Lainnya 2 mm Lembar Rp 55,000.00
21 Kayu lapis Tripleks Lapis Kayu Mewah jati Teakwood (0,3 x 122 x 244) cm Lembar Rp 220,000.00
22 Dolken Kayu Diameter 8-10/400 cm Btg Rp 30,000.00
G BAHAN PENGGANTUNG
1 Engsel Baja Biji Rp 27,500.00
Engsel Baja (Dumont) Biji Rp 181,500.00
2 Engsel Kuningan 4 Lubang Psg Rp 27,500.00
Engsel Kuningan 4 Lubang (Dumont) Psg Rp 84,700.00
3 Engsel Stainless Steel Psg Rp 49,500.00
4 Engsel H3 Lubang Psg Rp 16,500.00
5 Engsel Kupu-kupu Psg Rp 11,000.00
6 Engsel antik jendela Psg Rp 16,500.00
7 Engsel Pintu Biasa (Merk 777) Psg Rp 16,500.00
Engsel Pintu Biasa (Dumont) Psg Rp 84,700.00
8 Engsel Pintu Lemari Biasa Psg Rp 12,100.00
Engsel Pintu Lemari Biasa (Dakson) Psg Rp 66,000.00
9 Engsel Jendela Biasa (Merk 777) Psg Rp 13,800.00
Engsel Jendela Biasa (Dumont) Psg Rp 57,200.00
10 Engsel Jendela Kuningan (merk Kuningan) Psg Rp 22,000.00
Engsel Jendela Kuningan (Dakson) Psg Rp 63,800.00
11 Engsel Pintu 4" (SES) Bh Rp 38,500.00
Engsel Pintu 4" (Dumont) Bh Rp 58,100.00
12 Engsel Jendela 3"(SES) Bh Rp 27,500.00
Engsel Jendela 3"(Dumont) Bh Rp 57,200.00
13 Engsel Pintu Kuningan SES Psg Rp 84,700.00
Engsel Pintu Kuningan (Dumont) Psg Rp 84,700.00
14 Gagang Pintu Lemari Bh Rp 27,500.00
Gagang Pintu Lemari (Dakson) Bh Rp 37,400.00
15 Grendel jendela Kuningan Bh Rp 52,800.00
Grendel jendela Kuningan (Dakson) Bh Rp 52,800.00
16 Grendel Pintu Biasa Bh Rp 38,500.00
Grendel Pintu Biasa (Dumont) Bh Rp 49,700.00
17 Grendel Pintu Kuningan/ Vertikal Bh Rp 22,000.00
18 Grendel Pintu Besar Bh Rp 72,600.00
19 Grendel Pintu Tanam (Expanyolet) Bh Rp 165,000.00
20 Kunci Tanam Yale 1 x Putar Bh Rp 729,700.00
21 Kunci Tanam Yale 2 x Putar Bh Rp 275,000.00
22 Kunci Tanam Pintu 2 x Putar Besar Biasa Bh Rp 165,000.00
23 Kunci Tanam Pintu 2 x Putar kecil Biasa Bh Rp 110,000.00
24 Kunci Tanam Pintu 2 x Putar SES Bh Rp 321,900.00
25 Hak Angin Kecil Antik Bh Rp 55,000.00
26 Hak Angin Besar Bh Rp 44,000.00
Hak Angin Besar (Dumont) Bh Rp 74,800.00
27 Hak Angin Kecil Bh Rp 27,500.00
Hak Angin Kecil (Dumont) Bh Rp 122,300.00
28 Kait angin Jendela Alumunium Kualias 1 Bh Rp 17,300.00
Kait angin Jendela Alumunium (Dumont) Bh Rp 188,800.00
29 Kait angin Jendela Alumunium biasa Bh Rp 8,300.00
Kait angin Jendela Alumunium (Dumont) Bh Rp 101,800.00
H BAHAN KACA
1 Kaca Bening 3 mm M2 Rp 121,000.00
2 Kaca Bening 5 mm M2 Rp 148,500.00
3 Kaca Bening 6 mm M2 Rp 275,000.00
4 Kaca Bening 8 mm M2 Rp 363,000.00
5 Kaca Bening 10 mm M2 Rp 484,000.00
6 Kaca Ryben Tebal 5 mm M2 Rp 154,000.00
7 Kaca Ryben Tebal 6 mm M2 Rp 462,000.00
8 Kaca Ryben Tebal 3 mm M2 Rp 121,000.00
9 Kaca Ryben Tebal 8 mm M2 Rp 632,500.00
10 Kaca Ryben Tebal 10 mm M2 Rp 660,000.00
11 Jendela Nako (Rangka+ Kaca Tebal 5mm) 0,8 m x 0,2 m 4 lbr terpasang + Stand M2 Rp 59,400.00
12 Kaca Es Buram 5 mm/ 10 mm M2 Rp 264,000.00
13 Kaca Lembaran Bening Tidak Berwarna FL Tebal 2 MM M2 Rp 71,500.00
14 Kaca Lembaran Bening Tidak Berwarna FL Tebal 3 MM M2 Rp 170,500.00
15 Kaca Lembaran Bening Tidak Berwarna FL Tebal 5 MM M2 Rp 187,000.00
Ukuran (1221 x 153) Lembar Rp 203,500.00
Ukuran (200 x 90) Lembar Rp 203,500.00
Ukuran (200 x 100) Lembar Rp 236,500.00
Ukuran (213 x 122) Lembar Rp 297,000.00
Ukuran (183 x 122) Lembar Rp 236,500.00
Ukuran (244 x 183) Lembar Rp 533,500.00
Kaca Lembaran Bening Tidak Berwarna FL Tebal 10 MM M2 Rp 2,491,500.00
16 Kaca Bening 12 mm M2 Rp 522,500.00
I BAHAN SANITER / SALURAN AIR
1 Kloset Duduk Lengkap(putih) Tangki Batu American standart Unit Rp 1,650,000.00
2 Kloset Duduk Ex KIA Lengkap (warna) Tanhki Batu Unit Rp 2,530,000.00
3 Kloset Duduk ex TOTO Lengkap Accessories warna Putih Unit Rp 3,284,600.00
4 Kloset Duduk ex TOTO Lengkap Accessories warna gelap Unit Rp 2,970,000.00
5 Kloset Jongkok KIA Bh Rp 385,000.00
6 Kloset Jongkok Biasa (American Standar) Bh Rp 313,500.00
7 Wastafel polos / putih lengkap Bh Rp 715,000.00
8 Wastafel warna lengkap Bh Rp 726,000.00
9 Slypon Wastafel Biasa Bh Rp 385,000.00
10 Urinoir Polos /Putih American Standart Unit Rp 550,000.00
11 Urinoir ex TOTO (lengkap) Unit Rp 1,540,000.00
12 Bak Tube Fiber Biasa Bh Rp 247,500.00
13 Bak Tube Fiber ex TOTO Bh Rp 3,300,000.00
14 Tangki Air Fiberglass Kap 0,25 M3 Bh Rp 550,000.00
15 Tangki Air Fiberglass Kap 0,50 M3 Bh Rp 825,000.00
16 Tangki Air Fiberglass Kap 1 M3 Bh Rp 1,320,000.00
17 Tangki Air Alumunium Kap 1 M3 Bh Rp 3,685,000.00
18 Kran Air Kuningan DIA 3/4 Biasa Bh Rp 59,400.00
19 Kran Air Kuningan DIA 1/2 Biasa Bh Rp 44,000.00
20 Kran Air Vernrkel DIA 3/4 Biasa Bh Rp 44,000.00
21 Kran Air Antik DIA 1/2 Bh Rp 253,000.00
22 Bak Cuci Piring Stain -Kosong Tanpa Saluran Pembuangan & Kran Air Bh Rp 247,500.00
23 Kran air 2 / Biasa / bisa Bh Rp 121,000.00
24 Seal Tape Bh Rp 5,500.00
25 Bak Mandi Unit Rp 330,000.00
26 Kloset Jongkok Biasa Bh Rp 121,000.00
27 Wallpaper & Penutup Dinding Rol Rp 330,000.00
28 Foil (Kertas Alumunium Foil) M Rp 176,000.00
29 Kloset Duduk (Data) Bh Rp 495,000.00
30 Kloset Jongkok TOTO (Putih) Bh Rp 379,500.00
31 Toilet Portable Fiberglass 400 Liter Unit Rp 23,100,000.00
32 Toilet Portable Fiberglass 400 Liter Unit Rp 29,260,000.00
J BAHAN LANGIT-LANGIT
1 Teakwood 120 x 240 cm t.3mm Lembar Rp 220,000.00
2 Triplex 3 mm 120 x 240 cm Lembar Rp 55,000.00
3 Triplex 4 mm 120 x 240 cm Lembar Rp 66,000.00
4 Triplex 5 ml Lembar Rp 93,500.00
5 Triplex 6 mm 120 x 240 cm Lembar Rp 99,000.00
6 Triplex 7 ml Lembar Rp 148,500.00
7 Triplex 10 ml Lembar Rp 209,000.00
8 Triplex 15 ml Lembar Rp 242,000.00
9 Triplex 20 ml Lembar Rp 291,500.00
10 Triplex Ukuran Pintu Lembar Rp 137,500.00
11 Triplex Melamin 120 x 240 cm 3 mm Lembar Rp 121,000.00
12 Teakwood 120 x 240 cm t.4mm Lembar Rp 165,000.00
13 Multiplex 120 x 240 cm t. 6 mm Lembar Rp 77,000.00
14 Multiplex 120 x 240 cm t. 9 mm Lembar Rp 110,000.00
15 Multiplex 120 x 240 cm t. 12 mm Lembar Rp 181,500.00
16 Multiplex 120 x 240 cm t. 18 mm Lembar Rp 291,500.00
17 Gypsum Board 122x244x tebal 9 mm ex Jayaboard untuk Plafond Gpyro Lembar Rp 82,500.00
18 Kalsiboard tebal 3,5 mm Lembar Rp 74,800.00
19 Kalsiboard tebal 4,5 mm Lembar Rp 100,100.00
20 Kalsiboard tebal 6 mm Lembar Rp 139,700.00
21 Kalsiboard tebal 8 mm Lembar Rp 192,500.00
22 Kalsiboard tebal 10 mm Lembar Rp 245,300.00
23 Kalsiboard tebal 20 mm Lembar Rp 653,400.00
24 Kalsiplank 8mm (10cm x 3m) Lembar Rp 29,200.00
25 Kalsiplank 8mm (10cm x 3m) Polos Lembar Rp 49,000.00
26 Kalsiplank 8mm (20cm x 3m) Jati Lembar Rp 51,700.00
27 Kalsiplank 8mm (30cm x 3m) Polos Lembar Rp 72,600.00
28 Kalsiplank 8mm (30cm x 4m) Jati Lembar Rp 74,800.00
29 Kalsiplank 9mm (20cm x 4m) Polos Lembar Rp 70,400.00
30 Kalsiplank 9mm (20cm x 4m) Cedar Lembar Rp 73,700.00
31 Lambriziring t:4mm, (4m') Lembar Rp 49,500.00
32 HPL Lembar Rp 242,000.00
33 Les Kayu Profil Lebar 5 cm ( 4 M' ) Batang Rp 22,000.00
34 Les Kayu Profil Lebar 3 cm ( 4 M' ) Batang Rp 40,300.00
35 Les Kayu Profil Lebar 11/2 cm ( 4 M' ) Batang Rp 22,000.00
36 Les Kayu 1 x 10 x 400 cm Btg Rp 63,300.00
37 Les Kayu Profil 4 x 4 x 400 cm Btg Rp 35,000.00
38 Les Kayu Biasa 0,5 x 3 cm Btg Rp 78,300.00
39 Les Gypsum Polos Batang Rp 22,000.00
40 Les Gypsum Polos - Kecil M' Rp 11,000.00
41 Les Gypsum Motif - Kecil - lebar 7 cm/10 cm M' Rp 13,800.00
42 Les Gypsum - Sedang M' Rp 19,300.00
43 Les Gypsum - lebar 10 cm M' Rp 22,000.00
44 Les Gypsum - Besar - lebar 15 cm M' Rp 27,500.00
45 Les Gypsum Profil Batang Rp 27,800.00
46 Beding Gypsum - Kecil M' Rp 11,000.00
47 Beding Gypsum - Sedang M' Rp 16,500.00
48 Beding Gypsum - Besar M' Rp 27,500.00
K BAHAN LANTAI
1 Tegel PC 30 x30 cm Dos Rp 93,500.00
2 Tegel Motif 30 x30 cm Platinum Diego grey / brown 2 Dos Rp 101,200.00
3 Tegel Keramik Putih 10 x 20 cm Dos Rp 63,000.00
4 Tegel Keramik Putih 20 x 20 cm Dos Rp 63,800.00
5 Tegel Keramik Putih 20 x 25 cm Dos Rp 65,600.00
6 Tegel Keramik Putih 30 x 30 cm Dos Rp 54,700.00
7 Tegel Keramik Putih 40 x 40 cm (accura) Dos Rp 117,700.00
8 Tegel Keramik Putih 50 x 50 cm # Platinum (accura motif) Dos Rp 117,700.00
9 Tegel Keramik Putih 60 x 60 cm Ex Granito (granit sandimas mega white) Dos Rp 261,800.00
10 Tegel Keramik Putih 60 x 60 cm Ex Garuda Dos Rp 176,000.00
11 Tegel Keramik Putih 30 x 60 cm Ex Granito (granit eleganza new vorio) Dos Rp 290,300.00
12 Tegel Keramik Warna 60 x 60 cm Ex Granito Top Gress Top Gress Dos Rp 390,500.00
13 Tegel Keramik Warna 60 x 60 cm EX Garuda/Pangress Double wodding (sandimas) Dos Rp 192,500.00
14 Tegel Keramik warna 30 x 60 cm Ex Garuda /Roman (kwalitas LebihBagus) Dos Rp 324,500.00
15 Tegel Keramik Putih 30 x 60 cm Dos Rp 118,700.00
16 Tegel Keramik Warna 20 x 20 cm Dos Rp 96,800.00
17 Tegel Keramik Warna 30 x 30 cm Dos Rp 66,000.00
18 Tegel Keramik Warna 20 x 25 cm M2 Rp 63,800.00
19 Tegel Keramik Warna 40 x 40 cm M2 Rp 71,500.00
20 Tegel Keramik Warna 50 x 50 cm Dos Rp 125,400.00
21 Tegel Keramik Warna 60 x 60 cm Dos Rp 151,800.00
22 Tegel Keramik Warna 30 x 60 cm Dos Rp 220,000.00
23 Tegel Keramik Indogress - Homogeneus Tile Ukur. 60x60 cm (GNS Ruffian) Dos Rp 462,000.00
24 Tegel Keramik Indogress - Homogeneus Tile Ukur. 60x60 cm (Topaz) Dos Rp 350,900.00
25 Tegel Keramik Indogress - Homogeneus Tile Ukur. 60x60 cm (Cottonwood) Dos Rp 379,500.00
26 Granit Uku 60 x 185
60 cm
x 185Dasar
cm Putih Dasar Putih M2 Rp 1,333,500.00
27 Granit Uku 60 x 185 cm Dasar Hitam / 63 X 198 cm (sandimas 60x60) M2 Rp 880,000.00
28 Granit ukuran 30 x 30 cm Asia Tile Dos Rp 55,200.00
29 Granit ukuran 40 x 40 cm Granito Asia Tile Dos Rp 74,800.00
30 Granit ukuran 60 x 60 cm (sandimas) Dos Rp 198,000.00
31 Keramik WC 20 x 20 cm Dos Rp 68,200.00
32 Keramik WC 20 x 25 cm Dos Rp 66,000.00
33 Keramik WC 30 x 30 cm Asia Tile Dos Rp 63,800.00
34 Keramik uku 30 x 30 cm Dos Rp 51,100.00
35 Keramik uku 40 x 40 cm Dos Rp 66,000.00
36 Keramik Warna uk. 25 x 40 cm (accura) Dos Rp 84,700.00
37 Batu Alam 10 x 20 cm Polos M2 Rp 176,000.00
38 Batu Alam 20 x 20 cm Polos 10x30 cm M2 Rp 212,800.00
39 Batu Alam Motif Sirip/Garis-garis di pahat 10x30 cm20x40
/ 15 Xcm
30 M2 Rp 264,700.00
40 Batu Alam Motif Sirip/Garis-garis di pahat 20x40 cm Bj Rp 115,500.00
41 Batu Alam ukuran 10 x 20 cm Polos / 30 X 60 CM Polos M2 Rp 192,500.00
42 Marmer Ukuran Slabs(type Burito/acaro/Great I) / 100 x 100 cm Dos Rp 881,700.00
43 Marmer Ukuran Slabs(type Burito/acaro/Great II) Dos Rp 692,800.00
44 Marmer Ukuran Slabs(type Burito/acaro/Great III) Dos Rp 691,900.00
45 Marmer Ukuran 60 x 60 cm (Type Burito/Acaro/Great I) / cream urat kayu Dos Rp 660,000.00
46 Marmer Ukuran 60 x 60 cm (Type Burito/Acaro/Great II) Dos Rp 495,000.00
47 Marmer Ukuran 60 x 60 cm (Type Burito/Acaro/Great III) Dos Rp 377,900.00
48 Marmer Ukuran 30 x 30 cm (Type Burito/Acaro/Great I) Dos Rp 315,000.00
49 Marmer Ukuran 30 x 30 cm (Type Burito/Acaro/Great II) Dos Rp 264,600.00
50 Marmer Ukuran 30 x 30 cm (Type Burito/Acaro/Great III) Dos Rp 189,000.00
51 Ubin Lantai dari Tanah Liat diglazur Accura 40 x 40 cm M2 Rp 74,800.00
52 Ubin Lantai dari Tanah Liat diglazur KIA Polos 40 x 40 cm Dos Rp 80,600.00
53 Ubin Lantai dari Tanah Liat diglazur Keramik Merk Arwana M2 Rp 74,800.00
54 Ubin Lantai dari Tanah Liat diglazur Asiatile Kw 40 x40 cm M2 Rp 80,600.00
55 Ubin Lantai dari Tanah Liat diglazur Impresso uku. 40 x40 cm M2 Rp 74,800.00
56 Ubin Lantai dari Tanah Liat diglazur Masterina Polos uku. 30 x 30 cm M2 Rp 49,500.00
57 Ubin Lantai dari Tanah Liat diglazur Mulia KW 1 uku. 30 x 30 cm M2 Rp 49,500.00
58 Ubin Lantai dari Tanah Liat diglazur Kia Polos uku. 30 x 30 cm M2 Rp 51,900.00
59 Ubin Lantai dari Tanah Liat diglazur Asia Tile Kw 1 uku. 30 x 30 cm M2 Rp 57,600.00
60 Ubin Lantai dari Tanah Liat diglazur Impresso Kw 1 uku. 30 x 30 cm M2 Rp 55,300.00
61 Ubin Lantai dari Tanah Liat diglazur Accura Kw 1 uku. 30 x 30 cm M2 Rp 51,900.00
62 Ubin Lantai dari Tanah Liat diglazur Masterina Kw 1 uku. 30 x 30 cm M2 Rp 48,300.00
63 Ubin Lantai dari Tanah Liat diglazur Mulia Kw 1 uku. 30 x 30 cm M2 Rp 55,300.00
L BAHAN LAIN-LAIN
1 Cover Dome Gazebo include Installment Unit Rp 47,250,000.00
1 E Pipa Wavin SNI Wavinsafe 1/2" -4M S - 10 / 10 Bar (1,0 Mpa ) Batang Rp 27,000.00
3/4" -4M S - 10 / 10 Bar (1,0 Mpa ) Batang Rp 38,000.00
1" -4M S - 10 / 10 Bar (1,0 Mpa ) Batang Rp 49,500.00
11/4" -4M S - 10 / 10 Bar (1,0 Mpa ) Batang Rp 71,800.00
11/2" -6M S - 10 / 10 Bar (1,0 Mpa ) Batang Rp 123,200.00
1F Pipa Wavin SNI Wavinlok 2" -6M S - 10 / 12,5 Bar (12,5 Mpa ) Batang Rp 194,200.00
3" -6M S - 10 / 12,5 Bar (12,5 Mpa ) Batang Rp 414,200.00
4" -6M S - 10 / 12,5 Bar (12,5 Mpa ) Batang Rp 623,200.00
6" -6M S - 10 / 12,5 Bar (12,5 Mpa ) Batang Rp 1,294,200.00
8" -6M S - 10 / 12,5 Bar (12,5 Mpa ) Batang Rp 1,998,200.00
10" -6M S - 10 / 12,5 Bar (12,5 Mpa ) Batang Rp 3,099,800.00
12" -6M S - 10 / 12,5 Bar (12,5 Mpa ) Batang Rp 4,936,800.00
16" -6M S - 10 / 12,5 Bar (12,5 Mpa ) Batang Rp 8,126,800.00
20" -6M S - 10 / 12,5 Bar (12,5 Mpa ) Batang Rp 12,669,800.00
24" -6M S - 10 / 12,5 Bar (12,5 Mpa ) Batang Rp 20,955,000.00
P MATERIAL POMPA
1 Pompa Air Shimiznu130 ( 125 Watt ) Buah Rp 577,500
2 Pompa Air Shimizu 230 ( 200 Watt ) Buah Rp 990,000
3 Pompa Air Panasonik 130 Jak ( 125 Watt ) Buah Rp 616,000
4 Pompa Air Panasonik 200 Jak Buah Rp 676,500
5 Pompa Air Sanyo 137 AC Buah Rp 621,500
6 Pompa Air Sanyo PH 130 AC Buah Rp 1,336,500
7 Pompa Air Wasser 139 EA Buah Rp 2,876,500
8 Pompa Air Lakoni 129 A Buah Rp 572,000
9 Pompa Air Inoto I Hp + Kabel 50 Meter Buah Rp 2,942,500
10 Pompa Air Evak I Hp Buah Rp 5,692,500
11 Pompa Air Franklin I Hp Buah Rp 11,220,000
12 Pompa Wasser 60 Ea Buah Rp 704,000
13 Pompa Wasser 169 EA Buah Rp 1,056,000
14 Pompa Air Tsutumi 3 Buah Rp 3,850,000
15 Mesin Las Hambatan dari Logam Otomatis (Las Listrik Yanmar TS 155 C 13 H Unit Rp 28,665,200.00
16 Generator SET ABB Mesin Diesel 8,5 PK Yanmar Unit Rp 21,265,800.00
17 Generator SET ABB Mesin Diesel 8,5 PK Kubota Unit Rp 20,576,100.00
S UPAH KERJA
1 Mandor Lapangan O/H Rp 216,300.00
2 Kepala tukang O/H Rp 187,200.00
3 Kepala Tukang Listrik O/H Rp 187,200.00
4 Tukang Batu /Cat O/H Rp 173,300.00
5 Tukang Kayu / besi O/H Rp 173,300.00
6 Tukang pasang paving O/H Rp 173,300.00
7 Pembantu Sopir O/H Rp 144,200.00
8 Pembantu Mekanik O/H Rp 184,400.00
9 Pembantu Tukang Listrik O/H Rp 144,200.00
10 Pembantu Operator O/H Rp 201,100.00
11 Mekanik O/H Rp 173,300.00
12 Operator Terlatih O/H Rp 219,100.00
13 Pekerja O/H Rp 138,700.00
14 Sopir Terampil O/H Rp 187,200.00
15 Biaya Pasang Canstein /M' Rp 144,200.00
16 Biaya Pasang Paving /M2 Rp 187,200.00