REKAPITULASI

PROGRAM : PEMBANGUNAN WISATA TNKS


KEGIATAN : PEMBANGUNAN WISATA TNKS
PEKERJAAN : PEMBANGUNAN SIGNAGE
LOKASI : PULAU KELAPA DUA

NO URAIAN PEKERJAAN BIAYA KETERANGAN

1 2 3 4

I PEKERJAAN PERSIAPAN Rp 6,448,135.04

II PEKERJAAN BETON Rp 16,209,436.45

III PEKERJAAN BACKDROP Rp 23,340,052.00

IV PEKERJAAN SIGNAGE Rp 5,775,000.00

VII PEKERJAAN MOBILISASI MATERIAL Rp 5,000,000.00

JUMLAH Rp 56,772,623.49
PPn 10 % Rp 5,677,262.35
TOTAL Rp 62,449,885.84
DIBULATKAN Rp 62,449,000.00

TERBILANG :

DIPERIKSA OLEH : DIHITUNG OLEH :

DISAHKAN OLEH : DISETUJUI OLEH :


RENCANA ANGGARAN BIAYA
( RAB )
PROGRAM : PEMBANGUNAN WISATA TNKS
KEGIATAN : PEMBANGUNAN WISATA TNKS
PEKERJAAN : PEMBANGUNAN SIGNAGE
LOKASI : PULAU KELAPA DUA

HARGA JUMLAH
SAT VOL
NO. URAIAN PEKERJAAN SATUAN HARGA
Rp. Rp.
1 2 4 5 6
I PEKERJAAN PERSIAPAN
1 Pek. Papan Nama Kegiatan Ls 1 Rp 343,000.00 Rp 343,000.00
2 Bedeng Pekerja & Gudang m² 9 Rp 300,000.00 Rp 2,700,000.00
3 Pek. Pengukuran / Pas. Bowplank m¹ 22.48 Rp 84,748.00 Rp 1,905,135.04
4 Pengadaan Air dan Listrik Kerja Bln 1 Rp 1,500,000.00 Rp 1,500,000.00

JUMLAH I Rp 6,448,135.04
II PEKERJAAN BETON
PONDASI UMPAK 60x60
1 Pek. Galian Tanah Pondasi m³ 5.58 118,930.00 Rp 663,272.61
2 Pek. Urugan tanah kembali m³ 4.46 50,765.00 Rp 226,386.52
3 Pek. Lantai kerja T=5cm m³ 0.25 Rp 403,975.00 Rp 102,407.66
4 Pek. Pondasi umpak 60x60 cm m³ 0.86 Rp 7,605,828.00 Rp 6,571,435.39
5 Pek. Balok beton 20/30 m³ 0.48 Rp 5,207,974.00 Rp 2,499,827.52
6 Pek. Pondasi Cerucuk dia. 10 cm - 2 m terpasang m¹ 6.00 Rp 21,219.13 Rp 127,314.75
PEMBUATAN BANGKU BETON
1 Pek. Bangku Beton T=10cm m³ 2.00 3,009,396.00 Rp 6,018,792.00
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -

JUMLAH II Rp 16,209,436.45
III PEKERJAAN BACKDROP
1 Artwork Perunggu (Cangkang) 23.34 Rp 1,000,000.00 Rp 23,340,052.00
2
3
4

JUMLAH III Rp 23,340,052.00


IV PEKERJAAN SIGNAGE
1 Backdrop Tulisan GRC (ombak) m² 9.60 385,000.00 Rp 3,696,000.00
2 Huruf Timbul Ls 231.00 9,000.00 Rp 2,079,000.00
HARGA JUMLAH
SAT VOL
NO. URAIAN PEKERJAAN SATUAN HARGA
Rp. Rp.
1 2 4 5 6
3
4

Rp 5,775,000.00
VII PEKERJAAN MOBILISASI MATERIAL
1 Angkutan Pasir m³ Rp 514,000.00 Rp -
2 Angkutan Split m³ Rp 514,000.00 Rp -
3 Angkutan Semen zak Rp 21,600.00 Rp -
4 Angkutan Besi beton ton Rp 432,000.00 Rp -
5 Angkutan Kayu (Balok, Kaso, Papan, Triplek dll) m³ Rp 504,000.00 Rp -
6 Angkutan Batu Bata m³ Rp 472,000.00 Rp -
7 Angkutan Bahan Bangunan Lainnya ls 1.00 Rp 5,000,000.00 Rp 5,000,000.00
JUMLAH VII Rp 5,000,000.00
BACK UP DATA PERHITUNGAN VOLUME
KEGIATAN : PEMBANGUNAN WISATA TNKS
PEKERJAAN : PEMBANGUNAN SIGNAGE

LOKASI : PULAU KELAPA DUA

Dimensi (m)
No Jenis Pekerjaan Quantity Volume Satuan Sket / Gambar
Panjang Lebar Tinggi
1 2 4 5 6 3 7 8 9

I PEKERJAAN PERSIAPAN
1 Pek. Papan Nama Kegiatan Ls
2 Bedeng Pekerja & Gudang Ls
3 Pek. Pengukuran / Pas. Bowplank Ls
4 Pengadaan Air dan Listrik Kerja bln

II PEKERJAAN BETON
PONDASI UMPAK 60x60
1 Pek. Galian Tanah Pondasi 0.65 0.65 1.10 12 5.58 m3
2 Pek. Urugan tanah kembali
3 Pek. Lantai kerja T=5cm 0.65 0.65 0.05 12 0.25 m3
4 Pek. Pondasi umpak 60x60 cm 0.60 0.60 0.20 12 0.86 m3
5 Pek. Balok beton 20/30 0.20 0.30 8.00 1 0.48 m3
6 Pek. Pondasi Cerucuk dia. 10 cm - 2 m terpasang 2.00 3 6.00

PEMBUATAN BANGKU BETON


1 Pek. Bangku Beton T=10cm 8.00 2.50 0.10 1 2.00 m3

III PEKERJAAN BACKDROP


1
2
3
4

IV PEKERJAAN SIGNAGE
1 Backdrop Tulisan GRC (ombak) 8.00 1.20 9.60
2 Huruf Timbul 3.00 77.00 231.00
3
4
Dimensi (m)
No Jenis Pekerjaan Quantity Volume Satuan Sket / Gambar
Panjang Lebar Tinggi
1 2 4 5 6 3 7 8 9
DAFTAR RINCIAN ANALISA HARGA SATUAN PEKERJAAN

Harga Sat. Jumlah Harga Jumlah Harga


No. Uraian Jenis Pekerjaan Sat. Koeff. Bahan / Upah Bahan Upah Bahan + Upah
Rp. Rp. Rp. Rp.
1 2 3 4 5 6 7 8

A ANALISA BIAYA PEKERJAAN BONGKARAN


1 1 M3 MEMBONGKAR DINDING BATA ( SNI. Edisi Rev. 2005)
(Jika Bongkaran dipakai lagi)
Tenaga Kerja :
Pekerja Org 2.0000 138,000.00 276,000.00
Mandor Org 0.0900 185,000.00 16,650.00
Jumlah - 292,650.00 292,650.00
Keuntungan maksimal 10% 29,265.00
Jumlah 321,915.00
Dibulatkan 321,915.00
2 1 M2 MEMBONGKAR PLESTERAN DINDING ( SNI. Edisi Rev. 2005)
Tenaga Kerja :
Pekerja Org 0.0500 138,000.00 6,900.00
Mandor Org 0.0250 185,000.00 4,625.00
Jumlah - 11,525.00 11,525.00
Keuntungan maksimal 10% 1,152.50
Jumlah 12,677.50
Dibulatkan 12,677.00
3 1 M2 MEMBONGKAR LANTAI KERAMIK ( SNI. Edisi Rev. 2005)
Tenaga Kerja :
Pekerja Org 0.0500 138,000.00 6,900.00
Mandor Org 0.0100 185,000.00 1,850.00
Jumlah 8,750.00 8,750.00
Keuntungan maksimal 10% 875.00
Jumlah 9,625.00
Dibulatkan 9,625.00
4 1 M2 MEMBONGKAR GENTENG / SIRAP ( SNI. Edisi Rev. 2005)
(Jika bongkaran tidak dipakai)
Tenaga Kerja :
Pekerja Org 0.0200 138,000.00 2,760.00
Mandor Org 0.0100 185,000.00 1,850.00
Jumlah - 4,610.00 4,610.00
Keuntungan maksimal 10% 461.00
Jumlah 5,071.00
Dibulatkan 5,071.00
5 1 M2 MEMBONGKAR GENTENG / SIRAP ( SNI. Edisi Rev. 2005)
(Jika bongkaran dipakai)
Tenaga Kerja :
Pekerja setengah terampil Org 0.0400 138,000.00 5,520.00
Mandor Org 0.0200 185,000.00 3,700.00
Jumlah - 9,220.00 9,220.00
Keuntungan maksimal 10% 922.00
Jumlah 10,142.00
Dibulatkan 10,142.00
6 1 M2 MEMBONGKAR RANGKA ATAP/RENG KASO ( SNI. Edisi Rev. 2005)
(Jika Bongkaran dipakai)
Tenaga Kerja :
Tukang Kayu Org 0.2000 158,000.00 31,600.00
Pekerja Org 0.0500 138,000.00 6,900.00
Kepala Tukang Kayu Org 0.0050 173,000.00 865.00
Mandor Org 0.0100 185,000.00 1,850.00
Jumlah - 41,215.00 41,215.00
Keuntungan maksimal 10% 4,121.50
Jumlah 45,336.50
Dibulatkan 45,336.00
7 1 M2 MEMBONGKAR RANGKA ATAP/RENG KASO ( SNI. Edisi Rev. 2005)
(Jika Bongkaran tidak dipakai)
Tenaga Kerja :
Tukang Kayu Org 0.1000 158,000.00 15,800.00
Pekerja Org 0.0250 138,000.00 3,450.00
Kepala Tukang Kayu Org 0.0025 173,000.00 432.50
Mandor Org 0.0050 185,000.00 925.00
Jumlah - 20,607.50 20,607.50
Keuntungan maksimal 10% 2,060.75
Jumlah 22,668.25
Dibulatkan 22,668.00
8 1 M3 MEMBONGKAR KUDA-KUDA, GORDING/BALOK-BALOK ( SNI. Edisi Rev. 2005)
(Jika Bongkaran dipakai)
Tenaga Kerja :
Tukang Kayu Org 4.0000 158,000.00 632,000.00
Pekerja Org 6.0000 138,000.00 828,000.00
Kepala Tukang Kayu Org 0.6000 173,000.00 103,800.00
Mandor Org 0.2000 185,000.00 37,000.00
Jumlah - 1,600,800.00 1,600,800.00
Keuntungan maksimal 10% 160,080.00
Jumlah 1,760,880.00
Dibulatkan 1,760,880.00
9 1 M3 MEMBONGKAR KUDA-KUDA, GORDING/BALOK-BALOK ( SNI. Edisi Rev. 2005)
(Jika bongkaran tidak dipakai)
Tenaga Kerja :
Pekerja Org 4.0000 138,000.00 552,000.00
Tukang Kayu Org 3.0000 158,000.00 474,000.00
Mandor Org 0.2000 185,000.00 37,000.00
Jumlah - 1,063,000.00 1,063,000.00
Keuntungan maksimal 10% 106,300.00
Jumlah 1,169,300.00
Dibulatkan 1,169,300.00
1 2 3 4 5 6 7 8
10 1 M2 MEMBONGKAR PLAFOND ( SNI. Edisi Rev. 2005)
(Jika bongkaran dipakai lagi)
Tenaga Kerja :
Pekerja Org 0.1000 138,000.00 13,800.00
Tukang Kayu Org 0.2500 158,000.00 39,500.00
Kepala Tukang Kayu Org 0.0150 173,000.00 2,595.00
Mandor Org 0.0050 185,000.00 925.00
Jumlah - 56,820.00 56,820.00
Keuntungan maksimal 10% 5,682.00
Jumlah 62,502.00
Dibulatkan 62,502.00
11 1M2 MEMBONGKAR PLAFOND ( SNI. Edisi Rev. 2005)
(Jika bongkaran tidak dipakai lagi)
Tenaga Kerja :
Pekerja Org 0.1250 138,000.00 17,250.00
Mandor Org 0.0050 185,000.00 925.00
Jumlah - 18,175.00 18,175.00
Keuntungan maksimal 10% 1,817.50
Jumlah 19,992.50
Dibulatkan 19,992.00
B ANALISA BIAYA PEKERJAAN PERSIAPAN
1 1 M' PAS. BOUWPLANK & PENGUKURAN ( SNI. Edisi Rev. 2005)
Bahan :
Kayu Borneo 5/7 M3 0.0070 4,000,000.00 28,000.00 -
Paku biasa 2" - 5" Kg 0.0200 22,800.00 456.00 -
Kayu papan Albasia M3 0.0070 2,354,760.00 16,483.32 -
Tenaga Kerja :
Pekerja Oh 0.1000 138,000.00 - 13,800.00
Tukang Kayu Oh 0.1000 158,000.00 - 15,800.00
Kepala Tukang Kayu Oh 0.0100 173,000.00 - 1,730.00
Mandor Oh 0.0050 185,000.00 - 925.00
Jumlah 44,939.32 32,255.00 77,194.32
Keuntungan maksimal 10% 7,719.43
Jumlah 84,913.75
Dibulatkan 84,913.00
2 1 M2 PEMB. DIREKSI KEET DENGAN LANTAI PLESTER ( SNI. Edisi Rev. 2005 )
Bahan :
Kayu dolken dia 8 - 10/400 cm Btg 1.2500 39,240.00 49,050.00 -
Kayu papan Albasia M3 0.1800 2,354,760.00 423,856.80 -
Paku biasa 2" - 5" Kg 0.8500 22,800.00 19,380.00 -
Besi strip kg 1.1000 3,987.50 4,386.25 -
Semen Portland Kg 35.0000 1,460.00 51,100.00 -
Pasir pasang M3 0.1500 135,278.00 20,291.70 -
Pasir beton M3 0.1000 210,540.00 21,054.00 -
Koral beton M3 0.1500 205,373.30 30,806.00 -
Bata merah Bh 30.0000 660.00 19,800.00 -
Seng plat, BJLS 25 Lbr 0.2500 66,550.00 16,637.50 -
Jendela nako Bh 2.0000 - - -
Kaca polos M2 0.0800 150,000.00 12,000.00 -
Kunci tanam Bh 0.1500 - - -
Plywood 4 mm Lbr 0.0600 58,300.00 3,498.00 -
Tenaga Kerja :
Pekerja Oh 1.0000 138,000.00 - 138,000.00
Tukang Kayu Oh 1.5000 158,000.00 - 237,000.00
Tukang Batu Oh 1.0000 158,000.00 - 158,000.00
Kepala Tukang Kayu Oh 0.3000 173,000.00 - 51,900.00
Mandor Oh 0.0500 185,000.00 - 9,250.00
Jumlah 671,860.25 594,150.00 1,266,010.25
Keuntungan maksimal 10% 126,601.02
Jumlah 1,392,611.27
Dibulatkan 1,392,610.00
C ANALISA BIAYA PEKERJAAN TANAH
1 1 M3 GALIAN TANAH BIASA KEDALAMAN 1 M' ( SNI. Edisi Rev. 2008 )
Tenaga Kerja :
Pekerja Oh 0.7500 138,000.00 - 103,500.00
Mandor Oh 0.0250 185,000.00 - 4,625.00
Jumlah 108,125.00 108,125.00
Keuntungan maksimal 10% 10,812.50
Jumlah 118,937.50
Dibulatkan 118,930.00
2 1 M3 GALIAN TANAH KERAS KEDALAMAN 1 M' ( SNI. Edisi Rev. 2008 )
Tenaga Kerja :
Pekerja Oh 1.0000 138,000.00 - 138,000.00
Mandor Oh 0.0320 185,000.00 - 5,920.00
Jumlah 143,920.00 143,920.00
Keuntungan maksimal 10% 14,392.00
Jumlah 158,312.00
Dibulatkan 158,310.00
3 1 M3 GALIAN TANAH BATUAN ( SNI. Edisi Rev. 2008 )
Tenaga Kerja :
Pekerja Oh 0.9500 138,000.00 - 131,100.00
Mandor Oh 0.0230 185,000.00 - 4,255.00
Compresor Jam 0.1167 85,580.00 9,987.19
Jak Hammer Jam 0.1667 8,900.00 1,483.63
Dump Truck Jam 0.2671 172,000.00 45,941.20
Alat Bantu ls 1.0000 4,000.00 4,000.00
Jumlah 61,412.02 135,355.00 196,767.02
Keuntungan maksimal 10% 19,676.70
Jumlah 216,443.72
Dibulatkan 216,440.00
4 1 M3 URUGAN TANAH
Bahan
Tanah Urug M3 1.0000 240,000.00 240,000.00
Tenaga Kerja :
Pekerja Oh 0.1920 138,000.00 - 26,496.00
Mandor Oh 0.0190 185,000.00 - 3,515.00
Jumlah 240,000.00 30,011.00 270,011.00
Keuntungan maksimal 10% 27,001.10
Jumlah 297,012.10
Dibulatkan 297,012.00
5 1 M3 URUGAN PASIR ( SNI. Edisi Rev. 2005 )
Bahan :
Pasir urug M3 1.2000 270,000.00 324,000.00 -
Tenaga Kerja :
Pekerja Oh 0.3000 138,000.00 - 41,400.00
Mandor Oh 0.0100 185,000.00 - 1,850.00
Jumlah 324,000.00 43,250.00 367,250.00
Keuntungan maksimal 10% 36,725.00
Jumlah 403,975.00
Dibulatkan 403,975.00
6 1 M3 URUGAN SIRTU PADAT UNTUK PENINGGIAN LANTAI BANGUNAN ( SNI. Edisi Rev. 2008 )
Bahan :
Sirtu M3 1.2000 210,000.00 252,000.00 -
Tenaga Kerja :
Pekerja Oh 0.2500 138,000.00 - 34,500.00
Mandor Oh 0.0250 185,000.00 - 4,625.00
Jumlah 252,000.00 39,125.00 291,125.00
Keuntungan maksimal 10% 29,112.50
Jumlah 320,237.50
Dibulatkan 320,237.00
7 1 M3 URUGAN TANAH LEMBANG
Bahan
Tanah Lembang M3 1.1000 280,000.00 308,000.00
Tenaga Kerja :
Pekerja Oh 0.1920 138,000.00 - 26,496.00
Mandor Oh 0.0190 185,000.00 - 3,515.00
Jumlah 308,000.00 30,011.00 338,011.00
Keuntungan maksimal 10% 33,801.10
Jumlah 371,812.10
Dibulatkan 371,812.00
8 1 M3 URUGAN TANAH KEMBALI ( SNI. Edisi Rev. 2008 )
Tenaga Kerja :
Pekerja Oh 0.2500 138,000.00 - 34,500.00
Mandor Oh 0.0083 185,000.00 - 1,541.67
Jumlah 36,041.67 36,041.67
Keuntungan maksimal 10% 3,604.17
Jumlah 39,645.83
Dibulatkan 39,645.00
D ANALISA BIAYA PEKERJAAN PONDASI
1 1 M3 PASANGAN BATU KOSONG / AANSTAMPING ( SNI. Edisi Rev. 2008 )
Bahan :
Batu Belah M3 1.2000 325,000.00 390,000.00 -
Pasir urug M3 0.4320 270,000.00 116,640.00 -
Tenaga Kerja :
Pekerja Oh 0.7800 138,000.00 - 107,640.00
Tukang Batu Oh 0.3900 158,000.00 - 61,620.00
Kepala Tukang Batu Oh 0.0390 173,000.00 - 6,747.00
Mandor Oh 0.0390 185,000.00 - 7,215.00
Jumlah 506,640.00 183,222.00 689,862.00
Keuntungan maksimal 10% 68,986.20
Jumlah 758,848.20
Dibulatkan 758,848.00
2 1 M3 PASANGAN PONDASI BATU KALI, 1 PC. : 3 PS. ( SNI. Edisi Rev. 2008 )
Bahan :
Batu Belah 15/20 cm M3 1.2000 264,000.00 316,800.00 -
Semen Portland Kg 202.0000 1,330.00 268,660.00 -
Pasir Pasang M3 0.4850 280,000.00 135,800.00 -
Tenaga Kerja :
Pekerja Oh 1.5000 138,000.00 - 207,000.00
Tukang Batu Oh 0.7500 158,000.00 - 118,500.00
Kepala Tukang Batu Oh 0.0750 173,000.00 - 12,975.00
Mandor Oh 0.0750 185,000.00 - 13,875.00
Jumlah 721,260.00 352,350.00 1,073,610.00
Keuntungan maksimal 10% 107,361.00
Jumlah 1,180,971.00
Dibulatkan 1,180,971.00
3 1 M3 PASANGAN PONDASI BATU KALI, 1 PC. : 5 PS. ( SNI. Edisi Rev. 2008 )
Bahan :
Batu Belah 15/20 cm M3 1.2000 325,000.00 390,000.00 -
Semen Portland Kg 136.0000 1,330.00 180,880.00 -
Pasir Pasang M3 0.5440 280,000.00 152,320.00 -
Tenaga Kerja :
Pekerja Oh 1.5000 138,000.00 - 207,000.00
Tukang Batu Oh 0.7500 158,000.00 - 118,500.00
Kepala Tukang Batu Oh 0.0750 173,000.00 - 12,975.00
Mandor Oh 0.0750 185,000.00 - 13,875.00
Jumlah 723,200.00 352,350.00 1,075,550.00
Keuntungan maksimal 10% 107,555.00
Jumlah 1,183,105.00
Dibulatkan 1,183,105.00
1 2 3 4 5 6 7 8
4 1 M3 PASANGAN PONDASI SUMURAN, DIAMETER 100 cm ( SNI. Edisi Rev. 2008 )
Bahan :
Batu Belah 15/20 cm M3 0.4500 325,000.00 146,250.00 -
Semen Portland Kg 194.0000 1,330.00 258,020.00 -
Pasir Beton M3 0.3120 290,000.00 90,480.00 -
Kerikil M3 0.4680 - -
Tenaga Kerja :
Pekerja Oh 2.4000 138,000.00 - 331,200.00
Tukang Batu Oh 0.8000 158,000.00 - 126,400.00
Kepala Tukang Batu Oh 0.0800 173,000.00 - 13,840.00
Mandor Oh 0.1190 185,000.00 - 22,015.00
Jumlah 494,750.00 493,455.00 988,205.00
Keuntungan maksimal 10% 98,820.50
Jumlah 1,087,025.50
Dibulatkan 1,087,025.00
1 1 M3 LANTAI KERJA 1 pc : 5 ps ( SNI. Edisi Rev. 2005 )
Bahan :
Semen Portland kg 218.0000 1,330.00 289,940.00 -
Pasir beton m3 0.5200 290,000.00 150,800.00 -
Koral beton m3 0.8700 264,000.00 229,680.00 -
Tenaga Kerja :
Pekerja Oh 1.6500 138,000.00 - 227,700.00
Tukang Batu Oh 0.2500 158,000.00 - 39,500.00
Kepala Tukang Batu Oh 0.0250 173,000.00 - 4,325.00
Mandor Oh 0.0800 185,000.00 - 14,800.00
Jumlah 670,420.00 286,325.00 956,745.00
Keuntungan maksimal 10% 95,674.50
Jumlah 1,052,419.50
Dibulatkan 1,052,419.00
E ANALISA STRUKTUR
E.1 ANALISA BIAYA KONSTRUKSI PEKERJAAN BETON
1 1 M3 ADUKAN BETON TUMBUK CAMP. 1 PC : 3 PS : 5 KR ( SNI. Edisi Rev. 2005 )
Bahan :
Semen Portland kg 218.0000 1,330.00 289,940.00 -
Pasir beton m3 0.5200 290,000.00 150,800.00 -
Koral beton m3 0.8700 264,000.00 229,680.00 -
Tenaga Kerja :
Pekerja Oh 1.6500 138,000.00 - 227,700.00
Tukang Batu Oh 0.2500 158,000.00 - 39,500.00
Kepala Tukang Batu Oh 0.0250 173,000.00 - 4,325.00
Mandor Oh 0.0800 185,000.00 - 14,800.00
Jumlah 670,420.00 286,325.00 956,745.00
Keuntungan maksimal 10% 95,674.50
Jumlah 1,052,419.50
Dibulatkan 1,052,419.00
2 1 M3 ADUKAN BETON TUMBUK CAMP. 1 PC : 2 PS : 3 KR ( SNI. Edisi Rev. 2005 )
Bahan :
Semen Portland kg 232.0000 1,330.00 308,560.00 -
Pasir beton m3 0.5200 290,000.00 150,800.00 -
Koral beton m3 0.7800 264,000.00 205,920.00 -
Tenaga Kerja :
Pekerja Oh 1.6500 138,000.00 - 227,700.00
Tukang Batu Oh 0.2500 158,000.00 - 39,500.00
Kepala Tukang Batu Oh 0.0250 173,000.00 - 4,325.00
Mandor Oh 0.0800 185,000.00 - 14,800.00
Jumlah 665,280.00 286,325.00 951,605.00
Keuntungan maksimal 10% 95,160.50
Jumlah 1,046,765.50
Dibulatkan 1,046,765.00
3 1 M3 ADUKAN BETON TUMBUK CAMP. 1 PC : 1,5 PS : 2,5 KR ( SNI. Edisi Rev. 2005 )
Bahan :
Semen Portland kg 386.0000 1,330.00 513,380.00 -
Pasir beton m3 0.4700 290,000.00 136,300.00 -
Koral beton m3 0.7800 264,000.00 205,920.00 -
Tenaga Kerja :
Pekerja Oh 1.6500 138,000.00 - 227,700.00
Tukang Batu Oh 0.2500 158,000.00 - 39,500.00
Kepala Tukang Batu Oh 0.0250 173,000.00 - 4,325.00
Mandor Oh 0.0800 185,000.00 - 14,800.00
Jumlah 855,600.00 286,325.00 1,141,925.00
Keuntungan maksimal 10% 114,192.50
Jumlah 1,256,117.50
Dibulatkan 1,256,117.00
4 1 M3 ADUKAN BETON K. 100 ( SNI. Edisi Rev. 2008 )
Bahan :
Semen Portland kg 247.00 1,330.00 328,510.00 -
Pasir beton kg 869.00 290.00 252,010.00 -
Koral beton kg 999.00 264.00 263,736.00 -
Air Ltr 215.00 50.00 10,750.00 -
Tenaga Kerja :
Pekerja Oh 1.6500 138,000.00 - 227,700.00
Tukang Batu Oh 0.2750 158,000.00 - 43,450.00
Kepala Tukang Batu Oh 0.0280 173,000.00 - 4,844.00
Mandor Oh 0.0830 185,000.00 - 15,355.00
Jumlah 855,006.00 291,349.00 1,146,355.00
Keuntungan maksimal 10% 114,635.50
Jumlah 1,260,990.50
Dibulatkan 1,260,990.00
5 1 M3 ADUKAN LANTAI BETON K. 100 ( SNI. Edisi Rev. 2008 )
Bahan :
Semen Portland kg 230.00 1,330.00 305,900.00 -
Pasir beton Kg 893.00 290.00 258,970.00 -
Koral beton Kg 1027.00 264.00 271,128.00 -
Air Ltr 200.00 50.00 10,000.00 -
Tenaga Kerja :
Pekerja Oh 1.2000 138,000.00 - 165,600.00
Tukang Batu Oh 0.2000 158,000.00 - 31,600.00
Kepala Tukang Batu Oh 0.0200 173,000.00 - 3,460.00
Mandor Oh 0.0600 185,000.00 - 11,100.00
Jumlah 845,998.00 211,760.00 1,057,758.00
Keuntungan maksimal 10% 105,775.80
Jumlah 1,163,533.80
Dibulatkan 1,163,533.00
1 2 3 4 5 6 7 8
6 1 M3 ADUKAN BETON K. 125 ( SNI. Edisi Rev. 2008 )
Bahan :
Semen Portland kg 276.00 1,330.00 367,080.00 -
Pasir beton Kg 828.00 290.00 240,120.00 -
Koral beton Kg 1012.00 264.00 267,168.00 -
Air Ltr 215.00 50.00 10,750.00 -
Tenaga Kerja :
Pekerja Oh 1.6500 138,000.00 - 227,700.00
Tukang Batu Oh 0.2750 158,000.00 - 43,450.00
Kepala Tukang Batu Oh 0.0280 173,000.00 - 4,844.00
Mandor Oh 0.0830 185,000.00 - 15,355.00
Jumlah 885,118.00 291,349.00 1,176,467.00
Keuntungan maksimal 10% 117,646.70
Jumlah 1,294,113.70
Dibulatkan 1,294,113.00
7 1 M3 ADUKAN BETON K. 150 ( SNI. Edisi Rev. 2008 )
Bahan :
Semen Portland kg 299.00 1,330.00 397,670.00 -
Pasir beton Kg 799.00 290.00 231,710.00 -
Koral beton Kg 1017.00 264.00 268,488.00 -
Air Ltr 215.00 50.00 10,750.00 -
Tenaga Kerja :
Pekerja Oh 1.6500 138,000.00 - 227,700.00
Tukang Batu Oh 0.2750 158,000.00 - 43,450.00
Kepala Tukang Batu Oh 0.0280 173,000.00 - 4,844.00
Mandor Oh 0.0830 185,000.00 - 15,355.00
Jumlah 908,618.00 291,349.00 1,199,967.00
Keuntungan maksimal 10% 119,996.70
Jumlah 1,319,963.70
Dibulatkan 1,319,963.00
8 1 M3 ADUKAN BETON K. 175 ( SNI. Edisi Rev. 2008 )
Bahan :
Semen Portland kg 326.00 1,330.00 433,580.00 -
Pasir beton Kg 760.00 290.00 220,400.00 -
Koral beton Kg 1029.00 264.00 271,656.00 -
Air Ltr 215.00 50.00 10,750.00 -
Tenaga Kerja :
Pekerja Oh 1.6500 138,000.00 - 227,700.00
Tukang Batu Oh 0.2750 158,000.00 - 43,450.00
Kepala Tukang Batu Oh 0.0280 173,000.00 - 4,844.00
Mandor Oh 0.0830 185,000.00 - 15,355.00
Jumlah 936,386.00 291,349.00 1,227,735.00
Keuntungan maksimal 10% 122,773.50
Jumlah 1,350,508.50
Dibulatkan 1,350,508.00
9 1 M3 ADUKAN BETON K. 200 ( SNI. Edisi Rev. 2008 )
Bahan :
Semen Portland kg 352.00 1,330.00 468,160.00 -
Pasir beton Kg 731.00 290.00 211,990.00 -
Koral beton Kg 1031.00 264.00 272,184.00 -
Air Ltr 215.00 50.00 10,750.00 -
Tenaga Kerja :
Pekerja Oh 1.6500 138,000.00 - 227,700.00
Tukang Batu Oh 0.2750 158,000.00 - 43,450.00
Kepala Tukang Batu Oh 0.0280 173,000.00 - 4,844.00
Mandor Oh 0.0830 185,000.00 - 15,355.00
Jumlah 963,084.00 291,349.00 1,254,433.00
Keuntungan maksimal 10% 125,443.30
Jumlah 1,379,876.30
Dibulatkan 1,379,876.00
10 1 M3 ADUKAN BETON K. 225 ( SNI. Edisi Rev. 2008 )
Bahan :
Semen Portland kg 371.00 1,330.00 493,430.00 -
Pasir beton Kg 698.00 290.00 202,420.00 -
Koral beton Kg 1047.00 264.00 276,408.00 -
Air Ltr 215.00 50.00 10,750.00 -
Tenaga Kerja :
Pekerja Oh 1.6500 138,000.00 - 227,700.00
Tukang Batu Oh 0.2750 158,000.00 - 43,450.00
Kepala Tukang Batu Oh 0.0280 173,000.00 - 4,844.00
Mandor Oh 0.0830 185,000.00 - 15,355.00
Jumlah 983,008.00 291,349.00 1,274,357.00
Keuntungan maksimal 10% 127,435.70
Jumlah 1,401,792.70
Dibulatkan 1,401,792.00
11 1 M3 ADUKAN BETON K. 250 ( SNI. Edisi Rev. 2008 )
Bahan :
Semen Portland kg 384.00 1,330.00 510,720.00 -
Pasir beton Kg 692.00 290.00 200,680.00 -
Koral beton Kg 1039.00 264.00 274,296.00 -
Air Ltr 215.00 50.00 10,750.00 -
Tenaga Kerja :
Pekerja Oh 1.6500 138,000.00 - 227,700.00
Tukang Batu Oh 0.2750 158,000.00 - 43,450.00
Kepala Tukang Batu Oh 0.0280 173,000.00 - 4,844.00
Mandor Oh 0.0830 185,000.00 - 15,355.00
Jumlah 996,446.00 291,349.00 1,287,795.00
Keuntungan maksimal 10% 128,779.50
Jumlah 1,416,574.50
Dibulatkan 1,416,574.00
1 2 3 4 5 6 7 8
12 1 M3 ADUKAN BETON K. 275 ( SNI. Edisi Rev. 2008 )
Bahan :
Semen Portland kg 406.00 1,330.00 539,980.00 -
Pasir beton Kg 684.00 290.00 198,360.00 -
Koral beton Kg 1026.00 264.00 270,864.00 -
Air Ltr 215.00 50.00 10,750.00 -
Tenaga Kerja :
Pekerja Oh 1.6500 138,000.00 - 227,700.00
Tukang Batu Oh 0.2750 158,000.00 - 43,450.00
Kepala Tukang Batu Oh 0.0280 173,000.00 - 4,844.00
Mandor Oh 0.0830 185,000.00 - 15,355.00
Jumlah 1,019,954.00 291,349.00 1,311,303.00
Keuntungan maksimal 10% 131,130.30
Jumlah 1,442,433.30
Dibulatkan 1,442,433.00
13 1 M3 ADUKAN BETON K. 300 ( SNI. Edisi Rev. 2008 )
Bahan :
Semen Portland kg 413.00 1,330.00 549,290.00 -
Pasir beton Kg 681.00 290.00 197,490.00 -
Koral beton Kg 1021.00 264.00 269,544.00 -
Air Ltr 215.00 50.00 10,750.00 -
Tenaga Kerja :
Pekerja Oh 1.6500 138,000.00 - 227,700.00
Tukang Batu Oh 0.2750 158,000.00 - 43,450.00
Kepala Tukang Batu Oh 0.0280 173,000.00 - 4,844.00
Mandor Oh 0.0830 185,000.00 - 15,355.00
Jumlah 1,027,074.00 291,349.00 1,318,423.00
Keuntungan maksimal 10% 131,842.30
Jumlah 1,450,265.30
Dibulatkan 1,450,265.00
14 1 M3 ADUKAN BETON K. 325 ( SNI. Edisi Rev. 2008 )
Bahan :
Semen Portland kg 439.00 1,330.00 583,870.00 -
Pasir beton Kg 670.00 290.00 194,300.00 -
Koral beton Kg 1006.00 264.00 265,584.00 -
Air Ltr 215.00 50.00 10,750.00 -
Tenaga Kerja :
Pekerja Oh 2.1000 138,000.00 - 289,800.00
Tukang Batu Oh 0.3500 158,000.00 - 55,300.00
Kepala Tukang Batu Oh 0.0350 173,000.00 - 6,055.00
Mandor Oh 0.1050 185,000.00 - 19,425.00
Jumlah 1,054,504.00 370,580.00 1,425,084.00
Keuntungan maksimal 10% 142,508.40
Jumlah 1,567,592.40
Dibulatkan 1,567,592.00
15 1 M3 ADUKAN BETON K. 350 ( SNI. Edisi Rev. 2008 )
Bahan :
Semen Portland kg 448.00 1,330.00 595,840.00 -
Pasir beton Kg 667.00 290.00 193,430.00 -
Koral beton Kg 1000.00 264.00 264,000.00 -
Air Ltr 215.00 50.00 10,750.00 -
Tenaga Kerja :
Pekerja Oh 2.1000 138,000.00 - 289,800.00
Tukang Batu Oh 0.3500 158,000.00 - 55,300.00
Kepala Tukang Batu Oh 0.0350 173,000.00 - 6,055.00
Mandor Oh 0.1050 185,000.00 - 19,425.00
Jumlah 1,064,020.00 370,580.00 1,434,600.00
Keuntungan maksimal 10% 143,460.00
Jumlah 1,578,060.00
Dibulatkan 1,578,060.00
16 10 KG TULANGAN BETON DENGAN BESI POLOS / ULIR ( SNI. Edisi Rev. 2008 )
Bahan :
Besi Beton Polos Kg 10.5000 - -
Kawat Beton kg 0.1500 18,571.00 2,785.65 -
Tenaga Kerja :
Pekerja Oh 0.0700 138,000.00 - 9,660.00
Tukang Besi Oh 0.0700 158,000.00 - 11,060.00
Kepala Tukang Besi Oh 0.0070 173,000.00 - 1,211.00
Mandor Oh 0.0040 185,000.00 - 740.00
Jumlah 2,785.65 22,671.00 25,456.65
Keuntungan maksimal 10% 2,545.67
Jumlah 28,002.32
Dibulatkan 28,002.00
1 KG TULANGAN BETON DENGAN BESI POLOS / ULIR 2,800.20
17 1 M2. PASANG BEKISTING UNTUK PONDASI ( SNI. Edisi Rev. 2008 )
Bahan :
Kayu Papan/balok Albasia M3 0.0400 2,354,760.00 94,190.40 -
Paku Biasa 2" - 5" Kg 0.3000 22,800.00 6,840.00 -
Minyak Bekisting Lt 0.1000 21,876.00 2,187.60 -
Tenaga Kerja :
Pekerja Oh 0.5200 138,000.00 - 71,760.00
Tukang Kayu Oh 0.2600 158,000.00 - 41,080.00
Kepala Tukang Kayu Oh 0.0260 173,000.00 - 4,498.00
Mandor Oh 0.0260 185,000.00 - 4,810.00
Jumlah 103,218.00 122,148.00 225,366.00
Keuntungan maksimal 10% 22,536.60
Jumlah 247,902.60
Dibulatkan 247,902.00
1 2 3 4 5 6 7 8
18 1 M2. PASANG BEKISTING UNTUK SLOOF ( SNI. Edisi Rev. 2008 )
Bahan :
Kayu Papan/balok Albasia M3 0.0450 2,354,760.00 105,964.20 -
Paku Biasa 2" - 5" Kg 0.3000 22,800.00 6,840.00 -
Minyak Bekisting Lt 0.1000 21,876.00 2,187.60 -
Tenaga Kerja :
Pekerja Oh 0.5200 138,000.00 - 71,760.00
Tukang Kayu Oh 0.2600 158,000.00 - 41,080.00
Kepala Tukang Kayu Oh 0.0260 173,000.00 - 4,498.00
Mandor Oh 0.0260 185,000.00 - 4,810.00
Jumlah 114,991.80 122,148.00 237,139.80
Keuntungan maksimal 10% 23,713.98
Jumlah 260,853.78
Dibulatkan 260,853.00
19 1 M2. PASANG BEKISTING UNTUK KOLOM ( SNI. Edisi Rev. 2008 )
Bahan :
Kayu Papan Albasia M3 0.0400 2,354,760.00 94,190.40 -
Paku Biasa 2" - 5" Kg 0.4000 22,800.00 9,120.00 -
Minyak Bekisting Lt 0.2000 21,876.00 4,375.20 -
Balok Kayu Borneo 5/7 M3 0.0150 4,000,000.00 60,000.00 -
Multipleks 12 mm Lbr 0.3500 182,316.00 63,810.60 -
Dolken dia 8 - 10/400 cm Btg 2.0000 39,240.00 78,480.00 -
Tenaga Kerja :
Pekerja Oh 0.6600 138,000.00 - 91,080.00
Tukang Kayu Oh 0.3300 158,000.00 - 52,140.00
Kepala Tukang Kayu Oh 0.0330 173,000.00 - 5,709.00
Mandor Oh 0.0330 185,000.00 - 6,105.00
Jumlah 309,976.20 155,034.00 465,010.20
Keuntungan maksimal 10% 46,501.02
Jumlah 511,511.22
Dibulatkan 511,511.00
20 1 M2. PASANG BEKISTING UNTUK BALOK ( SNI. Edisi Rev. 2008 )
Bahan :
Kayu papan Albasia M3 0.0400 2,354,760.00 94,190.40 -
Paku Biasa 2" - 5" Kg 0.4000 22,800.00 9,120.00 -
Minyak Bekisting Lt 0.2000 21,876.00 4,375.20 -
Balok Kayu Borneo 5/7 M3 0.0180 4,000,000.00 72,000.00 -
Multipleks 9 mm Lbr 0.3500 182,316.00 63,810.60 -
Dolken dia 8 - 10/400 cm Btg 2.0000 39,240.00 78,480.00 -
Tenaga Kerja :
Pekerja Oh 0.6600 138,000.00 - 91,080.00
Tukang Kayu Oh 0.3300 158,000.00 - 52,140.00
Kepala Tukang Kayu Oh 0.0330 173,000.00 - 5,709.00
Mandor Oh 0.0330 185,000.00 - 6,105.00
Jumlah 321,976.20 155,034.00 477,010.20
Keuntungan maksimal 10% 47,701.02
Jumlah 524,711.22
Dibulatkan 524,711.00
21 1 M2. PASANG BEKISTING UNTUK PLAT LANTAI ( SNI. Edisi Rev. 2008 )
Bahan :
Kayu papan Albasia M3 0.0400 2,354,760.00 94,190.40 -
Paku Biasa 2" - 5" Kg 0.4000 22,800.00 9,120.00 -
Minyak Bekisting Lt 0.2000 21,876.00 4,375.20 -
Balok Kayu Borneo 5/7 M3 0.0150 4,000,000.00 60,000.00 -
Multipleks 9 mm Lbr 0.3500 182,316.00 63,810.60 -
Dolken dia 8 - 10/400 cm Btg 6.0000 39,240.00 235,440.00 -
Tenaga Kerja :
Pekerja Oh 0.6600 138,000.00 - 91,080.00
Tukang Kayu Oh 0.3300 158,000.00 - 52,140.00
Kepala Tukang Kayu Oh 0.0330 173,000.00 - 5,709.00
Mandor Oh 0.0330 185,000.00 - 6,105.00
Jumlah 466,936.20 155,034.00 621,970.20
Keuntungan maksimal 10% 62,197.02
Jumlah 684,167.22
Dibulatkan 684,167.00
22 1 M2. PASANG BEKISTING UNTUK DINDING ( SNI. Edisi Rev. 2008 )
Bahan :
Kayu papan Albasia M3 0.0300 2,354,760.00 70,642.80 -
Paku Biasa 2" - 5" Kg 0.4000 22,800.00 9,120.00 -
Minyak Bekisting Lt 0.2000 21,876.00 4,375.20 -
Balok Kayu Borneo 5/7 M3 0.0200 4,000,000.00 80,000.00 -
Multipleks 9 mm Lbr 0.3500 182,316.00 63,810.60 -
Dolken dia 8 - 10/400 cm Btg 3.0000 39,240.00 117,720.00 -
Formite/ Penjaga Jarak Bekisting/Spacer bh 4.0000 2,000.00 8,000.00 -
Tenaga Kerja :
Pekerja Oh 0.6600 138,000.00 - 91,080.00
Tukang Kayu Oh 0.3300 158,000.00 - 52,140.00
Kepala Tukang Kayu Oh 0.0330 173,000.00 - 5,709.00
Mandor Oh 0.0330 185,000.00 - 6,105.00
Jumlah 353,668.60 155,034.00 508,702.60
Keuntungan maksimal 10% 50,870.26
Jumlah 559,572.86
Dibulatkan 559,572.00
1 2 3 4 5 6 7 8
23 1 M2. PASANG BEKISTING UNTUK TANGGA ( SNI. Edisi Rev. 2008 )
Bahan :
Kayu papan Albasia M3 0.0300 2,354,760.00 70,642.80 -
Paku Biasa 2" - 5" Kg 0.4000 22,800.00 9,120.00 -
Minyak Bekisting Lt 0.1500 21,876.00 3,281.40 -
Balok Kayu Borneo 5/7 M3 0.0150 4,000,000.00 60,000.00 -
Multipleks 9 mm Lbr 0.3500 182,316.00 63,810.60 -
Dolken dia 8 - 10/400 cm Btg 2.0000 39,240.00 78,480.00 -
Tenaga Kerja :
Pekerja Oh 0.6600 138,000.00 - 91,080.00
Tukang Kayu Oh 0.3300 158,000.00 - 52,140.00
Kepala Tukang Kayu Oh 0.0330 173,000.00 - 5,709.00
Mandor Oh 0.0330 185,000.00 - 6,105.00
Jumlah 285,334.80 155,034.00 440,368.80
Keuntungan maksimal 10% 44,036.88
Jumlah 484,405.68
Dibulatkan 484,405.00
24 1 M3. PONDASI BETON BERTULANG ( SNI. Edisi Rev. 2008 )
Bahan :
Kayu papan Albasia M3 0.2000 2,354,760.00 470,952.00 -
Paku Biasa 2" - 5" Kg 1.5000 22,800.00 34,200.00 -
Minyak Bekisting ltr 0.4000 21,876.00 8,750.40 -
Besi Beton Polos Kg 157.5000 - - -
Kawat Beton Kg 2.2500 18,571.00 41,784.75 -
Semen Portland Kg 336.0000 1,330.00 446,880.00 -
Pasir beton M3 0.5400 290,000.00 156,600.00 -
Kerikil M3 0.8100 264,000.00 213,840.00 -
Tenaga Kerja :
Pekerja Oh 5.3000 138,000.00 - 731,400.00
Tukang Batu Oh 0.2750 158,000.00 - 43,450.00
Tukang Kayu Oh 1.3000 158,000.00 - 205,400.00
Tukang Besi Oh 1.0500 158,000.00 - 165,900.00
Kepala Tukang Oh 0.2620 173,000.00 - 45,326.00
Mandor Oh 0.2650 185,000.00 - 49,025.00
Jumlah 1,373,007.15 1,240,501.00 2,613,508.15
Keuntungan maksimal 10% 261,350.82
Jumlah 2,874,858.97
Dibulatkan 2,874,858.00
25 1 M3. BETON BERTULANG RING BALK 15 x 20 cm ADUKAN BETON K.175 ( SNI. Edisi Rev. 2005 )
- Adukan beton K. 175 M3 1.0000 1,350,508.00 1,350,508.00
- Bekisting papan (untuk 2xpakai
diambil 50%) M2 13.3300 164,739.00 1,097,985.44
- Besi beton U.24 175 kg/m3 Kg 172.1870 2,800.20 482,158.04
Jumlah 2,930,651.47
Dibulatkan 2,930,651.00
26 1 M3. BETON BERTULANG SLOOF 20 x 25 cm ADUKAN BETON K.175 ( SNI. Edisi Rev. 2005 )
- Adukan beton K. 175 M3 1.0000 1,350,508.00 1,350,508.00
- Bekisting papan (untuk 2xpakai
diambil 50%) M2 5.0000 164,739.00 411,847.50
- Besi beton U.24 Kg 101.3600 2,800.20 283,828.27
Jumlah 2,046,183.77
Dibulatkan 2,046,183.00
26 1 M3. BETON BERTULANG SLOOF 15 x 20 cm ADUKAN BETON K.175 ( SNI. Edisi Rev. 2005 )
- Adukan beton K. 175 M3 1.0000 1,350,508.00 1,350,508.00
- Bekisting papan (untuk 2xpakai
diambil 50%) M2 6.6667 164,739.00 549,130.00
- Besi beton U.24 Kg 151.6000 2,800.20 424,510.32
Jumlah 2,324,148.32
Dibulatkan 2,324,148.00
27 1 M3. BETON BERTULANG SLOOF 20 x 30 cm ADUKAN BETON K.175 ( SNI. Edisi Rev. 2005 )
- Adukan beton K. 175 M3 1.0000 1,350,508.00 1,350,508.00
- Bekisting papan (untuk 2xpakai
diambil 50%) M2 10.0000 164,739.00 823,695.00
- Besi beton U.24 Kg 99.6583 2,800.20 279,063.17
Jumlah 2,453,266.17
Dibulatkan 2,453,266.00
28 1 M3. BETON BERTULANG KOLOM 30 x 30 cm ADUKAN BETON K.175 ( SNI. Edisi Rev. 2005 )
- Adukan beton K. 175 M3 1.0000 1,350,508.00 1,350,508.00
- Bekisting papan (untuk 2xpakai
diambil 50%) M2 13.3333 511,511.00 3,410,073.33
- Besi beton U.24 Kg 210.7833 2,800.20 590,235.49
Jumlah 5,350,816.82
Dibulatkan 5,350,816.00
29 1 M3. BETON BERTULANG KOLOM 12 x 40 cm ADUKAN BETON K.175 ( SNI. Edisi Rev. 2005 )
- Adukan beton K. 175 M3 1.0000 1,350,508.00 1,350,508.00
- Bekisting papan (untuk 2xpakai
diambil 50%) M2 21.6700 511,511.00 5,542,221.69
- Besi beton U.24 175 kg/m3 Kg 126.4300 2,800.20 354,029.29
Jumlah 7,246,758.97
Dibulatkan 7,246,758.00
29 1 M3. BETON BERTULANG KOLOM 15 x 15 cm ADUKAN BETON K.175 ( SNI. Edisi Rev. 2005 )
- Adukan beton K. 175 M3 1.0000 1,350,508.00 1,350,508.00
- Bekisting papan (untuk 2xpakai
diambil 50%) M2 13.3333 511,511.00 3,410,073.33
- Besi beton U.24 175 kg/m3 Kg 144.8889 2,800.20 405,717.87
Jumlah 5,166,299.20
Dibulatkan 5,166,299.00
1 2 3 4 5 6 7 8
30 1 M3. BETON BERTULANG BALOK 20 x 40 cm ADUKAN BETON K.225 ( SNI. Edisi Rev. 2005)
- Adukan beton K. 225 M3 1.0000 1,401,792.00 1,401,792.00
- Bekisting papan (untuk 2xpakai
diambil 50%) M2 9.5000 524,711.00 2,492,377.25
- Besi beton U.24 Kg 246.1500 2,800.20 689,269.23
Jumlah 4,583,438.48
Dibulatkan 4,583,438.00
31 1 M3. BETON BERTULANG BALOK 15 x 30 cm ADUKAN BETON K.225 ( SNI. Edisi Rev. 2005 )
- Adukan beton K. 225 M3 1.0000 1,401,792.00 1,401,792.00
- Bekisting papan (untuk 2xpakai)
diambil 50%) M2 9.5000 524,711.00 2,492,377.25
- Besi beton U.24 175 kg/m3 Kg 109.1200 2,800.20 305,557.82
Jumlah 4,199,727.07
Dibulatkan 4,199,727.00
32 1 M3. BETON POER PLAT ADUKAN BETON K.225 ( SNI. Edisi Rev. 2005 )
- Adukan beton K. 225 M3 1.0000 1,401,792.00 1,401,792.00
- Bekisting papan (untuk 2xpakai)
diambil 50%) M2 6.6667 247,902.00 826,340.00
- Besi beton U.24 Kg 124.9778 2,800.20 174,981.39
Jumlah 2,403,113.39
Dibulatkan 2,403,113.00
32 1 M3. BETON PONDASI TANGGA
- Adukan beton K. 175 M3 1.0000 1,401,792.00 1,401,792.00
- Bekisting papan (untuk 2xpakai)
diambil 50%) M2 4.5000 247,902.00 557,779.50
- Besi beton U.24 Kg 247.8625 2,800.20 347,032.29
Jumlah 2,306,603.79
Dibulatkan 2,306,603.00
33 1 M3. BETON PLAT LANTAI TEBAL 12 CM ADUKAN BETON K.175 ( SNI. Edisi Rev. 2005 )
- Adukan beton K. 175 M3 1.0000 1,401,792.00 1,401,792.00
- Bekisting papan (untuk 2xpakai)
diambil 50%) M2 8.3330 684,167.00 2,850,581.81
- Besi beton U.24 Kg 93.4770 2,800.20 261,754.30
Jumlah 4,514,128.10
Dibulatkan 4,514,128.00
34 1 M3. BETON BERTULANG KOLOM 15 x 20 cm ADUKAN BETON K.175 ( SNI. Edisi Rev. 2005 )
- Adukan beton K. 175 M3 1.0000 1,401,792.00 1,401,792.00
- Bekisting papan (untuk 2xpakai
diambil 50%) M2 13.3300 164,739.00 1,097,985.44
- Besi beton U.24 175 kg/m3 Kg 172.1870 2,800.20 482,158.04
Jumlah 2,981,935.47
Dibulatkan 2,981,935.00
35 1 M3. BETON KOLOM PRAKTIS 12 x 12cm ADUKAN BETON K.175 ( SNI. Edisi Rev. 2005 )
- Adukan beton K. 175 M3 1.0000 1,350,508.00 1,350,508.00
- Bekisting papan (untuk 2xpakai)
diambil 50%) M2 33.3000 164,739.00 2,742,904.35
- Besi beton U.24 175 kg/m3 Kg 242.6000 2,800.20 679,328.52
Jumlah 4,772,740.87
Dibulatkan 4,772,740.00
36 1 M3. BETON PLAT PENUTUP SEPTICTANK ADUKAN BETON K.175 ( SNI. Edisi Rev. 2005 )
- Adukan beton K. 175 M3 1.0000 1,401,792.00 1,401,792.00
- Bekisting papan (untuk 2xpakai)
diambil 50%) M2 4.0000 164,739.00 329,478.00
- Besi beton U.24 175 kg/m3 Kg 75.0000 2,800.20 210,015.00
Jumlah 1,941,285.00
Dibulatkan 1,941,285.00
E.2 ANALISA STRUKTUR ATAP
1 1 M3 PASANG KONSTRUKSI KUDA-KUDA, KAYU BORNEO ( SNI. Edisi Rev. 2008 )
Bahan :
Kayu Borneo, Balok M3 1.1000 5,907,324.00 6,498,056.40 -
Besi strip Kg 15.0000 66,300.00 994,500.00 -
Paku biasa 12 cm Kg 5.6000 22,800.00 127,680.00 -
Tenaga Kerja :
Pekerja Oh 4.0000 138,000.00 - 552,000.00
Tukang Kayu Oh 12.0000 158,000.00 - 1,896,000.00
Kepala Tukang Kayu Oh 1.2000 173,000.00 - 207,600.00
Mandor Oh 0.2000 185,000.00 - 37,000.00
Jumlah 7,620,236.40 2,692,600.00 10,312,836.40
Keuntungan maksimal 10% 1,031,283.64
Jumlah 11,344,120.04
Dibulatkan 11,344,120.00
2 1 M2 Pasang Konstruksi Baja Ringan
Bahan :
Baja ringan m2 1.1000 215,050.00 236,555.00
Tenaga Kerja :
Pekerja Oh 0.1000 138,000.00 13,800.00
Tukang Kayu Oh 0.1000 158,000.00 15,800.00
Kepala Tukang Kayu Oh 0.0100 173,000.00 1,730.00
Mandor Oh 0.0050 185,000.00 925.00
Jumlah 236,555.00 32,255.00 268,810.00
Keuntungan maksimal 10% 26,881.00
Jumlah 295,691.00
Dibulatkan 295,691.00
1 2 3 4 5 6 7 8
3 1 M3 PASANG KONSTRUKSI KUDA-KUDA EXPOSE, KAYU KELAS I ( SNI. Edisi Rev. 2008 )
Bahan :
Kayu Borneo, Balok M3 1.2000 5,907,324.00 7,088,788.80 -
Besi strip Kg 15.0000 66,300.00 994,500.00 -
Paku biasa 12 cm Kg 5.6000 22,800.00 127,680.00 -
Tenaga Kerja :
Pekerja Oh 6.7000 138,000.00 - 924,600.00
Tukang Kayu Oh 0.1000 158,000.00 - 15,800.00
Kepala Tukang Kayu Oh 2.0100 173,000.00 - 347,730.00
Mandor Oh 0.3350 185,000.00 - 61,975.00
Jumlah 8,210,968.80 1,350,105.00 9,561,073.80
Keuntungan maksimal 10% 956,107.38
Jumlah 10,517,181.18
Dibulatkan 10,517,181.00
3 1 M3 PASANG KONSTRUKSI GORDENG, KAYU KELAS II ( SNI. Edisi Rev. 2008 )
Bahan :
Kayu Balok M3 1.1000 5,907,324.00 6,498,056.40 -
Besi strip T. 5 mm Kg 15.0000 66,300.00 994,500.00 -
Paku biasa 12 cm Kg 3.0000 22,800.00 68,400.00 -
Tenaga Kerja :
Pekerja Oh 2.4000 138,000.00 - 331,200.00
Tukang Kayu Oh 7.2000 158,000.00 - 1,137,600.00
Kepala Tukang Kayu Oh 0.7200 173,000.00 - 124,560.00
Mandor Oh 0.1200 185,000.00 - 22,200.00
Jumlah 7,560,956.40 1,615,560.00 9,176,516.40
Keuntungan maksimal 10% 917,651.64
Jumlah 10,094,168.04
Dibulatkan 10,094,168.00
4 1 M2 PASANG PAPAN RUITER 2 x 20 CM, KAYU BORNEO ( SNI. Edisi Rev. 2005 )
Bahan :
Kayu Borneo, Papan M3 0.0043 4,000,000.00 17,200.00 -
Paku biasa 2" - 5" Kg 0.0500 22,800.00 1,140.00 -
Tenaga Kerja :
Pekerja Oh 0.1000 138,000.00 - 13,800.00
Tukang Kayu Oh 0.2000 158,000.00 - 31,600.00
Kepala Tukang Kayu Oh 0.0250 173,000.00 - 4,325.00
Mandor Oh 0.0050 185,000.00 - 925.00
Jumlah 18,340.00 50,650.00 68,990.00
Keuntungan maksimal 10% 6,899.00
Jumlah 75,889.00
Dibulatkan 75,889.00
5 1 M' PASANG LISTPLANK 3 x 20 CM, KAYU BORNEO ( SNI. Edisi Rev. 2008 )
Bahan :
Kayu Borneo, Papan M3 0.0108 4,000,000.00 43,200.00 -
Paku biasa 2" - 5" Kg 0.1000 22,800.00 2,280.00 -
Tenaga Kerja :
Pekerja Oh 0.1000 138,000.00 - 13,800.00
Tukang Kayu Oh 0.2000 158,000.00 - 31,600.00
Kepala Tukang Kayu Oh 0.0200 173,000.00 - 3,460.00
Mandor Oh 0.0050 185,000.00 - 925.00
Jumlah 45,480.00 49,785.00 95,265.00
Keuntungan maksimal 10% 9,526.50
Jumlah 104,791.50
Dibulatkan 104,791.00
6 1 M' PASANG LISTPLANK 3 x 30 CM, KAYU BORNEO ( SNI. Edisi Rev. 2008 )
Bahan :
Kayu Kamper, Papan M3 0.0110 4,000,000.00 44,000.00 -
Paku biasa 2" - 5" Kg 0.0500 22,800.00 1,140.00 -
Tenaga Kerja :
Pekerja Oh 0.1000 138,000.00 - 13,800.00
Tukang Kayu Oh 0.2000 158,000.00 - 31,600.00
Kepala Tukang Kayu Oh 0.0200 173,000.00 - 3,460.00
Mandor Oh 0.0050 185,000.00 - 925.00
Jumlah 45,140.00 49,785.00 94,925.00
Keuntungan maksimal 10% 9,492.50
Jumlah 104,417.50
Dibulatkan 104,410.00
7 1 M2 PEKERJAAN RANGKA RENG KY BORNEO
Bahan :
Balok Reng Ky Borneo M3 0.0042 4,455,000.00 18,711.00
Paku 2"- 3" Kg 0.2000 22,800.00 4,560.00
Tenaga Kerja :
Pekerja Oh 0.0900 138,000.00 12,420.00
Tukang Kayu Oh 0.0900 158,000.00 14,220.00
Kepala Tukang Oh 0.0090 173,000.00 1,557.00
Mandor Oh 0.0050 185,000.00 925.00
Jumlah 23,271.00 29,122.00 52,393.00
Keuntungan maksimal 10% 5,239.30
Jumlah 57,632.30
Dibulatkan 57,632.00
8 1 M2 PEKERJAAN RANGKA ATAP SIRAP, KAYU KELAS II ( SNI. Edisi Rev. 2008 )
Bahan :
Kayu Kelas II M3 0.1650 6,500,000.00 1,072,500.00
Paku 5"- 10" Kg 0.2000 22,800.00 4,560.00
Tenaga Kerja :
Pekerja Oh 0.1200 138,000.00 16,560.00
Tukang Kayu Oh 0.1200 158,000.00 18,960.00
Kepala Tukang Oh 0.0120 173,000.00 2,076.00
Mandor Oh 0.0060 185,000.00 1,110.00
Jumlah 1,077,060.00 38,706.00 1,115,766.00
Keuntungan maksimal 10% 111,576.60
Jumlah 1,227,342.60
Dibulatkan 1,227,342.00
1 2 3 4 5 6 7 8
9 1 M2 PASANG ATAP SIRAP ( SNI. Edisi Rev. 2005 )
Bahan :
Genteng Sirap Bh 70.0000 2,500.00 175,000.00
Paku 1/2"- 1" Kg 0.2000 22,800.00 4,560.00
Tenaga Kerja :
Pekerja Oh 0.1660 138,000.00 22,908.00
Tukang Kayu Oh 0.2500 158,000.00 39,500.00
Kep Tukang Kayu Oh 0.0250 173,000.00 4,325.00
Mandor Oh 0.0080 185,000.00 1,480.00
Jumlah 179,560.00 68,213.00 247,773.00
Keuntungan maksimal 10% 24,777.30
Jumlah 272,550.30
Dibulatkan 272,550.00
9 1 M2 Pasang atap Genteng Beton
Bahan
Genteng Beton m2 1.0000 13,700.00 13,700.00
Paku Genteng kg 0.0300 30,057.50
Tenaga
Pekerja Oh 0.2000 138,000.00 27,600.00
Tukang kayu Oh 0.1000 158,000.00 15,800.00
Kepala tukang kayu Oh 0.0100 173,000.00 1,730.00
Mandor Oh 0.0010 185,000.00 185.00
Jumlah 13,700.00 45,315.00 59,015.00
Keuntungan maksimal 10% 5,901.50
Jumlah 64,916.50
Dibulatkan 64,916.00
9 1 M1 Pasang nok Genteng Beton
Bahan
Nok Genteng Beton bh 3.5000 13,000.00 45,500.00
Paku Genteng kg 0.0500 30,057.50 1,502.88
Tenaga
Pekerja Oh 0.1500 138,000.00 20,700.00
Tukang kayu Oh 0.0700 158,000.00 11,060.00
Kepala tukang kayu Oh 0.0080 173,000.00 1,384.00
Mandor Oh 0.0060 185,000.00 1,110.00
Jumlah 47,002.88 34,254.00 81,256.88
Keuntungan maksimal 10% 8,125.69
Jumlah 89,382.56
Dibulatkan 89,382.00
10 1 M2 PAS ALLUMUNIUM FOIL/SISALATION ( SNI. Edisi Rev. 2005 )
Bahan :
Allumunium Foil M2 1.0500 3,500.00 3,675.00
Tenaga Kerja :
Pekerja Oh 0.1500 138,000.00 20,700.00
Tukang kayu Oh 0.0500 158,000.00 7,900.00
Kep. Tukang Kayu Oh 0.0050 173,000.00 865.00
Mandor Oh 0.0080 185,000.00 1,480.00
Jumlah 3,675.00 30,945.00 34,620.00
Keuntungan maksimal 10% 3,462.00
Jumlah 38,082.00
Dibulatkan 38,082.00
11 1 M2 PAS LAPISAN TRIPLEK 4 mm ( SNI. Edisi Rev. 2005 )
Bahan :
Triplek 4 mm Lb 0.3800 77,280.00 29,366.40
Paku Kg 0.0200 22,800.00 456.00
Tenaga Kerja :
Pekerja Oh 0.1500 138,000.00 20,700.00
Tukang kayu Oh 0.0500 158,000.00 7,900.00
Kep. Tukang Oh 0.0050 173,000.00 865.00
Mandor Oh 0.0080 185,000.00 1,480.00
Jumlah 29,822.40 30,945.00 60,767.40
Keuntungan maksimal 10% 6,076.74
Jumlah 66,844.14
Dibulatkan 66,844.00
12 1 M' PEK. RANGKA ATAP BESI HOLLOW 4/4
Bahan :
Besi Hollow 4/4 M' 1.1000 33,750.00 37,125.00
Peralatan Ls 1.0000 2,500.00 2,500.00
Tenaga Kerja :
Pekerja Oh 0.0600 138,000.00 8,280.00
Tukang Besi Oh 0.0040 158,000.00 632.00
Kep. Tukang Oh 0.0010 173,000.00 173.00
Mandor Oh 0.0002 185,000.00 37.00
Jumlah 39,625.00 9,122.00 48,747.00
Keuntungan maksimal 10% 4,874.70
Jumlah 53,621.70
Dibulatkan 53,621.00
13 1 M' PEK. RANGKA ATAP BESI HOLLOW 2/4
Bahan :
Besi Hollow 2/4 M' 1.1000 18,750.00 20,625.00
Peralatan Ls 1.0000 2,500.00 2,500.00
Tenaga Kerja :
Pekerja Oh 0.0600 138,000.00 8,280.00
Tukang Besi Oh 0.0040 158,000.00 632.00
Kep. Tukang Oh 0.0010 173,000.00 173.00
Mandor Oh 0.0002 185,000.00 37.00
Jumlah 23,125.00 9,122.00 32,247.00
Keuntungan maksimal 10% 3,224.70
Jumlah 35,471.70
Dibulatkan 35,471.00
1 2 3 4 5 6 7 8
14 1 M2 PAS ATAP TWIN LIGHT
Bahan :
Twin Light M2 1.1000 120,500.00 132,550.00 82,843.75
Alat Bantu Ls 1.0000 7,500.00 7,500.00 7,500.00
Tenaga Kerja :
Pekerja Oh 0.1400 61,050.00 8,547.00
Tukang Besi Oh 0.0670 75,700.00 5,071.90
Kep. Tukang Oh 0.0070 82,700.00 578.90
Mandor Oh 0.0070 80,100.00 560.70
Jumlah 140,050.00 14,758.50 154,808.50
Keuntungan maksimal 10% 15,480.85
Jumlah 170,289.35
Dibulatkan 170,289.00
15 1 M2 PAS. KASO + RENG, GENTENG KODOK/PALENTONG KAYU BORNEO ( SNI. Edisi Rev. 2005 )
Bahan :
Kayu Borneo, Balok 5/7 M3 0.0120 5,304,751.43 63,657.02 -
Paku biasa 2" - 5" Kg 0.1500 22,800.00 3,420.00 -
Tenaga Kerja :
Pekerja Oh 0.1000 138,000.00 - 13,800.00
Tukang Kayu Oh 0.1000 158,000.00 - 15,800.00
Kepala Tukang Kayu Oh 0.0100 173,000.00 - 1,730.00
Mandor Oh 0.0050 185,000.00 - 925.00
Jumlah 67,077.02 32,255.00 99,332.02
Keuntungan maksimal 10% 9,933.20
Jumlah 109,265.22
Dibulatkan 109,265.00
16 1 M2 PASANG ATAP GENTENG PALENTONG ( SNI. Edisi Rev. 2005 )
Bahan :
Genteng Palentong Bh 25.0000 1,600.00 40,000.00 -
Tenaga Kerja :
Pekerja Oh 0.1500 138,000.00 - 20,700.00
Tukang Kayu Oh 0.0750 158,000.00 - 11,850.00
Kepala Tukang Kayu Oh 0.0080 173,000.00 - 1,384.00
Mandor Oh 0.0080 185,000.00 - 1,480.00
Jumlah 40,000.00 35,414.00 75,414.00
Keuntungan maksimal 10% 7,541.40
Jumlah harga 82,955.40
Dibulatkan 82,955.00
17 1 M2 PASANG GENTENG BUBUNG PALENTONG ( SNI. Edisi Rev. 2005 )
Bahan :
Genteng Bubung Palentong Bh 5.0000 1,750.00 8,750.00 -
Semen Portland Kg 8.0000 1,379.40 11,035.20 -
Pasir Pasang M3 0.0320 135,278.00 4,328.90 -
Tenaga Kerja :
Pekerja Oh 0.4000 138,000.00 - 55,200.00
Tukang Batu Oh 0.2000 158,000.00 - 31,600.00
Kepala Tukang Batu Oh 0.0200 173,000.00 - 3,460.00
Mandor Oh 0.0020 185,000.00 - 370.00
Jumlah 24,114.10 90,630.00 114,744.10
Keuntungan maksimal 10% 11,474.41
Jumlah harga 126,218.51
Dibulatkan 126,218.00
18 1 M2 PASANG ATAP GENTENG METAL ( SNI. Edisi Rev. 2005 )
Bahan :
Genteng metal lb 1.0200 88,000.00 89,760.00 -
Paku Biasa 2" - 5" Kg 0.2000 19,250.00 3,850.00 -
Tenaga Kerja :
Pekerja Oh 0.2000 138,000.00 - 27,600.00
Tukang Kayu Oh 0.1000 158,000.00 - 15,800.00
Kepala Tukang Kayu Oh 0.0100 173,000.00 - 1,730.00
Mandor Oh 0.0010 185,000.00 - 185.00
Jumlah 93,610.00 45,315.00 138,925.00
Keuntungan maksimal 10% 13,892.50
Jumlah harga 152,817.50
Dibulatkan 152,800.00
19 1 M' PASANG NOK GENTENG METAL ( SNI. Edisi Rev. 2005 )
Bahan :
Bubungan Metal Bh 1.1000 62,000.00 68,200.00 -
Paku Biasa 1/2" - 1" Kg 0.0500 19,250.00 962.50 -
Tenaga Kerja :
Pekerja Oh 0.2500 138,000.00 - 34,500.00
Tukang Kayu Oh 0.1500 158,000.00 - 23,700.00
Kepala Tukang Kayu Oh 0.0150 173,000.00 - 2,595.00
Mandor Oh 0.0130 185,000.00 - 2,405.00
Jumlah 69,162.50 63,200.00 132,362.50
Keuntungan maksimal 10% 13,236.25
Jumlah harga 145,598.75
Dibulatkan 145,590.00
20 1 M2 LABURAN BIDANG KAYU DENGAN RESIDU DAN TER ( SNI. Edisi Rev. 2005 )
Bahan :
Residu atau Ter Ltr 0.3500 6,750.00 2,362.50
Kuas bh 0.0500 18,500.00 925.00
Tenaga Kerja :
Pekerja Oh 0.1000 61,050.00 - 6,105.00
Mandor Oh 0.0060 80,100.00 - 480.60
Jumlah 3,287.50 6,585.60 9,873.10
Keuntungan maksimal 10% 987.31
Jumlah 10,860.41
Dibulatkan 10,860.00
1 2 3 4 5 6 7 8
21 1 M2 PASANG ATAP ASBES GELOMBANG ( SNI. Edisi Rev. 2005 )
Bahan :
Asbes Gelombang lbr 0.9700 25,000.00 24,250.00 -
Tenaga Kerja :
Pekerja Oh 0.1500 61,050.00 - 9,157.50
Tukang Kayu Oh 0.0750 75,700.00 - 5,677.50
Kepala Tukang Kayu Oh 0.0080 82,700.00 - 661.60
Mandor Oh 0.0080 80,100.00 - 640.80
Jumlah 24,250.00 16,137.40 40,387.40
Keuntungan maksimal 10% 4,038.74
Jumlah harga 44,426.14
Dibulatkan 44,426.00
22 1 M' TALANG DATAR/RAMBU SENG BAJA BJLS 30 ( SNI. Edisi Rev. 2005 )
Bahan :
Seng Plat 3'x6' BJLS 30 Lbr 0.5000 66,550.00 33,275.00
Paku Kg 0.0150 17,210.00 258.15
Papan Kayu Borneo Super M3 0.0096 5,147,000.00 49,411.20
Tenaga Kerja :
Pekerja Setengah Terampil Oh 0.1500 61,050.00 9,157.50
Tukang Kayu Setengah Terampil Oh 0.4000 75,700.00 30,280.00
Kep Tukang Kayu Oh 0.0250 82,700.00 2,067.50
Mandor Oh 0.0070 80,100.00 560.70
Jumlah 82,944.35 42,065.70 125,010.05
Keuntungan maksimal 10% 12,501.01
Jumlah 137,511.06
Dibulatkan 137,511.00
23 1 M' TALANG DATAR/JURAI SENG BAJA BJLS 28 LEBAR 90 ( SNI. Edisi Rev. 2008 )
Bahan :
Seng Plat 3'x6' BJLS 30 M' 1.0500 66,550.00 69,877.50
Paku Kg 0.0150 17,210.00 258.15
Papan Kayu Borneo Super M3 0.0190 5,147,000.00 97,793.00
Tenaga Kerja :
Pekerja Setengah Terampil Oh 0.2000 61,050.00 12,210.00
Tukang Kayu Setengah Terampil Oh 0.4000 75,700.00 30,280.00
Kep Tukang Kayu Oh 0.0250 82,700.00 2,067.50
Mandor Oh 0.0100 80,100.00 801.00
Jumlah 167,928.65 45,358.50 213,287.15
Keuntungan maksimal 10% 21,328.72
Jumlah 234,615.87
Dibulatkan 234,615.00
24 1 M' PASANG TALANG METAL
Bahan :
Talang Metal m' 1.0000 102,120.00 102,120.00
Bracket bh 1.0000 30,820.00 30,820.00
Alat Bantu ls 1.0000 5,000.00 5,000.00
Upah Pasang ls 1.0000 30,150.00 30,150.00
Jumlah 137,940.00 30,150.00 168,090.00
Keuntungan maksimal 10% 16,809.00
Jumlah 184,899.00
Dibulatkan 184,899.00
25 1 BH PASANG CORONG TALANG
Bahan :
Corong Talang bh 1.0000 79,120.00 79,120.00
Alat Bantu ls 1.0000 10,000.00 10,000.00
Upah Pasang ls 1.0000 19,700.00 19700
Jumlah 89,120.00 19,700.00 108,820.00
Keuntungan maksimal 10% 10,882.00
Jumlah 119,702.00
Dibulatkan 119,702.00
26 1 BH PASANG TALANG SUDUT DALAM / LUAR
Bahan :
Talang Sudut Dalam bh 1.0000 125,120.00 125,120.00
Alat Bantu ls 1.0000 10,000.00 10,000.00
Upah Pasang ls 1.0000 29,700.00 29700
Jumlah 135,120.00 29,700.00 164,820.00
Keuntungan maksimal 10% 16,482.00
Jumlah 181,302.00
Dibulatkan 181,302.00
27 1 BH PASANG SAMBUNGAN / SOCKET
Bahan :
Socket bh 1.0000 37,720.00 37,720.00
Alat Bantu ls 1.0000 5,000.00 5,000.00
Upah Pasang ls 1.0000 9,450.00 9450
Jumlah 42,720.00 9,450.00 52,170.00
Keuntungan maksimal 10% 5,217.00
Jumlah 57,387.00
Dibulatkan 57,387.00
F ANALISA ARSITEKTUR
F.1 PEKERJAAN DINDING
1 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 PC. : 3 PS. ( SNI. Edisi Rev. 2008 )
Bahan :
Bata Merah Bh 70.0000 798.00 55,860.00 -
Semen Portland Kg 14.3700 1,379.40 19,821.98 -
Pasir Pasang M3 0.0400 135,278.00 5,411.12 -
Tenaga Kerja :
Pekerja Oh 0.3000 61,050.00 - 18,315.00
Tukang Batu Oh 0.1000 73,300.00 - 7,330.00
Kepala Tukang Batu Oh 0.0100 81,000.00 - 810.00
Mandor Oh 0.0150 80,100.00 - 1,201.50
Jumlah 81,093.10 27,656.50 108,749.60
Keuntungan maksimal 10% 10,874.96
Jumlah 119,624.56
Dibulatkan 119,624.00
1 2 3 4 5 6 7 8
2 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 PC. : 5 PS. ( SNI. Edisi Rev. 2008 )
Bahan :
Bata Merah Bh 70.0000 798.00 55,860.00 -
Semen Portland Kg 9.6800 1,379.40 13,352.59 -
Pasir Pasang M3 0.0450 135,278.00 6,087.51 -
Tenaga Kerja :
Pekerja Oh 0.3000 61,050.00 - 18,315.00
Tukang Batu Oh 0.1000 73,300.00 - 7,330.00
Kepala Tukang Batu Oh 0.0100 81,000.00 - 810.00
Mandor Oh 0.0150 80,100.00 - 1,201.50
Jumlah 75,300.10 27,656.50 102,956.60
Keuntungan maksimal 10% 10,295.66
Jumlah 113,252.26
Dibulatkan 113,252.00
3 1 M2 PLESTERAN DINDING 1 PC. : 3 PS; TEB. 15 MM ( SNI. Edisi Rev. 2008 )
Bahan :
Semen Portland Kg 6.4800 1,379.40 8,938.51 -
Pasir Pasang M3 0.0190 135,278.00 2,570.28 -
Tenaga Kerja :
Pekerja Oh 0.2000 61,050.00 - 12,210.00
Tukang Batu Oh 0.1500 73,300.00 - 10,995.00
Kepala Tukang Batu Oh 0.0150 81,000.00 - 1,215.00
Mandor Oh 0.0100 80,100.00 - 801.00
Jumlah 11,508.79 25,221.00 36,729.79
Keuntungan maksimal 10% 3,672.98
Jumlah 40,402.77
Dibulatkan 40,402.00
4 1 M2 PLESTERAN DINDING 1 PC. : 5 PS; TEB. 15 MM ( SNI. Edisi Rev. 2008 )
Bahan :
Semen Portland Kg 4.3200 1,379.40 5,959.01 -
Pasir Pasang M3 0.0220 135,278.00 2,976.12 -
Tenaga Kerja :
Pekerja Oh 0.2000 61,050.00 - 12,210.00
Tukang Batu Oh 0.1500 73,300.00 - 10,995.00
Kepala Tukang Batu Oh 0.0150 81,000.00 - 1,215.00
Mandor Oh 0.0100 80,100.00 - 801.00
Jumlah 8,935.12 25,221.00 34,156.12
Keuntungan maksimal 10% 3,415.61
Jumlah 37,571.74
Dibulatkan 37,571.00
5 1 M2 PEKERJAAN DINDING SKAT DOUBLE MDF 9MM, RANGKA STEELUM 0.7mm
Bahan : -
Rangka Steelum m1 4.5000 34,236.67 154,065.00
Skrup Kg 0.0800 - -
Lem Putih Fox Kg 0.5600 - -
MDF 9 mm Lbr 0.8700 210,000.00 182,700.00
Tenaga Kerja :
Pekerja Oh 0.2000 138,000.00 27,600.00
Tukang Kayu Oh 0.6000 158,000.00 94,800.00
Kep Tukang Kayu Oh 0.0600 173,000.00 10,380.00
Mandor Oh 0.0100 185,000.00 1,850.00
Jumlah 336,765.00 134,630.00 471,395.00
Keuntungan maksimal 10% 47,139.50
Jumlah 518,534.50
Dibulatkan 518,534.00
6 1 M2 PEKERJAAN PELAPIS DINDING Wallpaper
Bahan :
Lem Putih Fox Kg 0.5600 - -
Walpaper Lbr 0.5000 55,000.00 27,500.00
Tenaga Kerja :
Pekerja Oh 0.1500 138,000.00 20,700.00
Tukang Kayu Oh 0.4500 158,000.00 71,100.00
Kep Tukang Kayu Oh 0.0045 173,000.00 778.50
Mandor Oh 0.0080 185,000.00 1,480.00
Jumlah 27,500.00 94,058.50 121,558.50
Keuntungan maksimal 10% 12,155.85
Jumlah 133,714.35
Dibulatkan 133,714.00
7 1 M2 PEKERJAAN PELAPIS DINDING Glasswool
Bahan :
Lem Putih Fox Kg 0.5600 - -
Glasswool Kg 1.0000 275,000.00 275,000.00
Tenaga Kerja :
Pekerja Oh 0.1500 138,000.00 20,700.00
Tukang Kayu Oh 0.4500 158,000.00 71,100.00
Kep Tukang Kayu Oh 0.0045 173,000.00 778.50
Mandor Oh 0.0080 185,000.00 1,480.00
Jumlah 275,000.00 94,058.50 369,058.50
Keuntungan maksimal 10% 36,905.85
Jumlah 405,964.35
Dibulatkan 405,964.00
8 1 M2 PASANGAN ROOSTER BETON 20/20. ( SNI. Edisi Rev. 2005 )
Bahan :
Rooster Beton 20/20 Bh 25.0000 5,940.00 148,500.00 -
Semen Portland Kg 12.8000 1,379.40 17,656.32 -
Pasir Pasang M3 0.0350 135,278.00 4,734.73 -
Tenaga Kerja :
Pekerja Oh 0.3000 61,050.00 - 18,315.00
Tukang Batu Oh 0.1000 73,300.00 - 7,330.00
Kepala Tukang Batu Oh 0.0100 81,000.00 - 810.00
Mandor Oh 0.0150 80,100.00 - 1,201.50
Jumlah 170,891.05 27,656.50 198,547.55
Keuntungan maksimal 10% 19,854.76
Jumlah 218,402.31
Dibulatkan 218,402.00

1 2 3 4 5 6 7 8
9 1 M2 PASANG GLASS BLOCK 20/20
Bahan :
Glass Block Bh 25.0000 27,700.00 692,500.00
Semen Portland Kg 12.8000 1,379.40 17,656.32
Pasir Pasang M3 0.0350 135,278.00 4,734.73
Tenaga Kerja :
Pekerja Oh 0.3000 61,050.00 18,315.00
Tukang Batu Oh 0.1000 73,300.00 7,330.00
Kep Tukang Batu Oh 0.0100 81,000.00 810.00
Mandor Oh 0.0150 80,100.00 1,201.50
Jumlah 714,891.05 27,656.50 742,547.55
Keuntungan maksimal 10% 74,254.76
Jumlah 816,802.31
Dibulatkan 816,802.00
10 1 M2 LAPISAN AM 100
Bahan :
AM 100 Kg 1.1000 55,250.00 60,775.00
Kwas Bh 0.2000 18,500.00 3,700.00
Upah Pasang = Upah Laburan Besi Ls 1.0000 #REF! #REF!
Jumlah 64,475.00 #REF! #REF!
Keuntungan maksimal 10% #REF!
Jumlah #REF!
Dibulatkan #REF!
11 1 M2 ACIAN SEMEN AM 86
Bahan :
Semen AM 86 Kg 2.2200 2,650.00 5,883.00
Tenaga Kerja :
Pekerja Oh 0.1500 61,050.00 9,157.50
Tukang Batu Oh 0.1000 73,300.00 7,330.00
Kepala Tukang Oh 0.0100 81,000.00 810.00
Mandor Oh 0.0075 80,100.00 600.75
Jumlah 5,883.00 17,898.25 23,781.25
Keuntungan maksimal 10% 2,378.13
Jumlah 26,159.38
Dibulatkan 26,159.00
9 1 M2 LAPISAN WATER PROFING, Sikatop 107 SEAL
Bahan :
Sika Top 107 Seal Kg 2.2000 17,850.00 39,270.00
Kwas Bh 0.2000 16,500.00 3,300.00
Upah Pasang = Upah Laburan Besi Ls 1.0000 #REF! #REF!
Jumlah 42,570.00 #REF! #REF!
Keuntungan maksimal 10% #REF!
Jumlah #REF!
Dibulatkan #REF!
10 1 M2 PLESTERAN ACI LAPIS KEEMSTONE
Bahan :
Semen Abu Kg 4.3200 1,379.40 5,959.01
Semen Warna Kg 0.1440 13,250.00 1,908.00
Pasir Pasang M3 0.0220 135,278.00 2,976.12
Serbuk Granit Kg 10.0000 6,930.00 69,300.00
Tenaga Kerja :
Pekerja Oh 0.2000 61,050.00 12,210.00
Tukang Batu Oh 0.0900 73,300.00 6,597.00
Kep Tukang Batu Oh 0.0090 81,000.00 729.00
Mandor Oh 0.0100 80,100.00 801.00
Jumlah 80,143.12 20,337.00 100,480.12
Keuntungan maksimal 10% 10,048.01
Jumlah 110,528.14
Dibulatkan 110,528.00
11 1 M2 Rangka Kayu Plafond 5/7 + Ram kawat
Bahan
Kayu Balok Borneo Super M3 0.0230 4,455,000.00 102,465.00
Ram Kawat Kg 6.0000 11,310.00 67,860.00
Paku Biasa 1/2" - 2" Kg 0.1500 5,000.00 750.00
Tenaga
Pekerja Oh 0.0210 138,000.00 2,898.00
Tukang Kayu Oh 0.0210 158,000.00 3,318.00
Kepala Tukang Kayu Oh 0.0020 173,000.00 346.00
Mandor Oh 0.0010 185,000.00 185.00
Jumlah 171,075.00 6,747.00 177,822.00
Keuntungan maksimal 10% 17,782.20
Jumlah 195,604.20
Dibulatkan 195,604.00
12 1 M2 PEKERJAAN RANGKA DINDING SKAT , KAYU KELAS II ( SNI. Edisi Rev. 2008 )
Bahan :
Balok kayu borneo m3 0.0280 5,304,751.43 148,533.04 -
Paku 2 - 5" kg 0.1500 17,210.00 2,581.50 -
Tenaga Kerja :
Pekerja org 0.1500 61,050.00 - 9,157.50
Tukang kayu org 0.4500 75,700.00 - 34,065.00
Kepala tukang kayu org 0.0450 82,700.00 - 3,721.50
Mandor org 0.0080 80,100.00 - 640.80
Jumlah 151,114.54 47,584.80 198,699.34
Keuntungan maksimal 10% 19,869.93
Jumlah 218,569.27
Dibulatkan 218,569.00
1 2 3 4 5 6 7 8
13 1 M2 PEKERJAAN DINDING SKAT DOUBLE TRIPLEK 4 MM, RANGKA KAYU BORNEO ( SNI. Edisi Rev. 2005 )
Bahan :
Balok kayu borneo m3 0.0195 5,304,751.43 103,442.65 -
Papan kayu borneo m3 0.0070 5,147,000.00 36,029.00 -
Paku 1/2 - 1" kg 0.1000 19,250.00 1,925.00 -
Paku 2 - 5" kg 0.1000 17,210.00 1,721.00 -
Lem putih Fox kg 0.5600 19,250.00 10,780.00 -
Triplek 4 mm lbr 1.0000 58,300.00 58,300.00 -
Tenaga Kerja :
Pekerja org 0.2000 61,050.00 - 12,210.00
Tukang kayu org 0.6000 75,700.00 - 45,420.00
Kepala tukang kayu org 0.0600 82,700.00 - 4,962.00
Mandor org 0.0100 80,100.00 - 801.00
Jumlah 212,197.65 63,393.00 275,590.65
Keuntungan maksimal 10% 27,559.07
Jumlah 303,149.72
Dibulatkan 303,149.00
14 1 M2 PEKERJAAN DINDING SKAT DOUBLE TRIPLEK 6 MM, RANGKA KAYU BORNEO ( SNI. Edisi Rev. 2005 )
Bahan :
Balok kayu borneo m3 0.0195 5,304,751.43 103,442.65 -
Papan kayu borneo m3 0.0070 5,147,000.00 36,029.00 -
Paku 1/2 - 1" kg 0.1000 19,250.00 1,925.00 -
Paku 2 - 5" kg 0.1000 17,210.00 1,721.00 -
Lem putih Fox kg 0.5600 19,250.00 10,780.00 -
Triplek 4 mm lbr 1.0000 80,300.00 80,300.00 -
Tenaga Kerja :
Pekerja org 0.2000 61,050.00 - 12,210.00
Tukang kayu org 0.6000 75,700.00 - 45,420.00
Kepala tukang kayu org 0.0600 82,700.00 - 4,962.00
Mandor org 0.0100 80,100.00 - 801.00
Jumlah 234,197.65 63,393.00 297,590.65
Keuntungan maksimal 10% 29,759.07
Jumlah 327,349.72
Dibulatkan 327,349.00
15 1 M2 PEKERJAAN DINDING SKAT DOUBLE MULTIPLEK RANGKA KAYU BORNEO ( SNI. Edisi Rev. 2005 )
Bahan :
Balok Kayu Borneo Super M3 0.0195 5,304,751.43 103,442.65
Papan Kayu Borneo Super M3 0.0070 5,147,000.00 36,029.00
Paku 1/2 - 1" Kg 0.1000 19,250.00 1,925.00
Paku 2 - 5" Kg 0.1000 17,210.00 1,721.00
Lem Putih Fox Kg 0.5600 19,250.00 10,780.00
Multiplek 9 mm Lbr 1.0000 137,500.00 137,500.00
Tenaga Kerja :
Pekerja Oh 0.2000 61,050.00 12,210.00
Tukang Kayu Oh 0.6000 75,700.00 45,420.00
Kep Tukang Kayu Oh 0.0600 82,700.00 4,962.00
Mandor Oh 0.0100 80,100.00 801.00
Jumlah 291,397.65 63,393.00 354,790.65
Keuntungan maksimal 10% 35,479.07
Jumlah 390,269.72
Dibulatkan 390,269.00
15 1 M2 PEKERJAAN DINDING SKAT 1 MUKA MULTIPLEK, RANGKA KAYU BORNEO
Bahan :
Balok Kayu Borneo Super M3 0.0195 5,304,751.43 103,442.65
Papan Kayu Borneo Super M3 0.0070 5,147,000.00 36,029.00
Paku 1/2 - 1" Kg 0.0500 19,250.00 962.50
Paku 2 - 5" Kg 0.1000 17,210.00 1,721.00
Lem Putih Fox Kg 0.2800 19,250.00 5,390.00
Multiplek 9 mm Lbr 0.5000 137,500.00 68,750.00
Tenaga Kerja :
Pekerja Oh 0.2000 61,050.00 12,210.00
Tukang Kayu Oh 0.6000 75,700.00 45,420.00
Kep Tukang Kayu Oh 0.0600 82,700.00 4,962.00
Mandor Oh 0.0100 80,100.00 801.00
Jumlah 216,295.15 63,393.00 279,688.15
Keuntungan maksimal 10% 27,968.82
Jumlah 307,656.97
Dibulatkan 307,656.00
16 1 M2 PEKERJAAN DINDING SKAT DOUBLE MULTIPLEK 9MM, RANGKA KAYU KAMPER ( SNI. Edisi Rev. 2005 )
Bahan :
Balok Kayu Kamper M3 0.0195 6,050,000.00 117,975.00
Papan Kayu Kamper M3 0.0070 6,352,000.00 44,464.00
Paku 1/2 - 1" Kg 0.1000 19,250.00 1,925.00
Paku 2 - 5" Kg 0.1000 17,210.00 1,721.00
Lem Putih Fox Kg 0.5600 19,250.00 10,780.00
Multiplek 9 mm Lbr 1.0000 137,500.00 137,500.00
Tenaga Kerja :
Pekerja Oh 0.2000 61,050.00 12,210.00
Tukang Kayu Oh 0.6000 75,700.00 45,420.00
Kep Tukang Kayu Oh 0.0600 82,700.00 4,962.00
Mandor Oh 0.0100 80,100.00 801.00
Jumlah 314,365.00 63,393.00 377,758.00
Keuntungan maksimal 10% 37,775.80
Jumlah 415,533.80
Dibulatkan 415,533.00
1 2 3 4 5 6 7 8
16 1 M2 PEKERJAAN DINDING SKAT DOUBLE MDF 9MM, RANGKA STEELUM 0.7mm
Bahan :
Rangka Steelum m1 4.5000 12,500.00 56,250.00
Skrup Kg 0.0800 - -
Lem Putih Fox Kg 0.5600 - -
MDF 9 mm Lbr 0.8700 210,000.00 182,700.00
Tenaga Kerja :
Pekerja Oh 0.2000 61,050.00 12,210.00
Tukang Kayu Oh 0.6000 75,700.00 45,420.00
Kep Tukang Kayu Oh 0.0600 82,700.00 4,962.00
Mandor Oh 0.0100 80,100.00 801.00
Jumlah 238,950.00 63,393.00 302,343.00
Keuntungan maksimal 10% 30,234.30
Jumlah 332,577.30
Dibulatkan 332,577.00
17 1 M2 PEKERJAAN PELAPIS DINDING HPL
Bahan :
Lem Putih Fox Kg 0.5600 - -
HPL Lbr 0.5000 185,000.00 92,500.00
Tenaga Kerja :
Pekerja Oh 0.1500 61,050.00 9,157.50
Tukang Kayu Oh 0.4500 75,700.00 34,065.00
Kep Tukang Kayu Oh 0.0045 82,700.00 372.15
Mandor Oh 0.0080 80,100.00 640.80
Jumlah 92,500.00 44,235.45 136,735.45
Keuntungan maksimal 10% 13,673.55
Jumlah 150,409.00
Dibulatkan 150,408.00
18 1 M2 PEKERJAAN DINDING SKAT DOUBLE TEAKWOOD 4 MM, RANGKA KAYU BORNEO ( SNI. Edisi Rev. 2005 )
Bahan :
Balok Kayu Borneo Super M3 0.0195 5,304,751.43 103,442.65
Papan Kayu Borneo Super M3 0.0070 5,147,000.00 36,029.00
Paku 1/2 - 1" Kg 0.1000 19,250.00 1,925.00
Paku Kg 0.1000 17,210.00 1,721.00
Lem Putih Fox Kg 0.5000 19,250.00 9,625.00
Teakwood 4 mm Lbr 1.0000 121,000.00 121,000.00
Tenaga Kerja :
Pekerja Oh 0.2000 61,050.00 12,210.00
Tukang Kayu Oh 0.6000 75,700.00 45,420.00
Kep Tukang Kayu Oh 0.0600 82,700.00 4,962.00
Mandor Oh 0.0100 80,100.00 801.00
Jumlah 273,742.65 63,393.00 337,135.65
Keuntungan maksimal 10% 33,713.57
Jumlah 370,849.22
Dibulatkan 370,849.00
19 PASANG 1 M' PLIN KAYU 2/10
Bahan :
Ky Kamper, Papan M3 0.0030 6,352,000.00 19,056.00
Paku Sekrup 5 cm kg 0.0500 -
Tenaga Kerja :
Pekerja Oh 0.1200 61,050.00 7,326.00
Tukang Kayu Oh 0.1200 75,700.00 9,084.00
Kep Tukang Kayu Oh 0.0120 82,700.00 992.40
Mandor Oh 0.0060 80,100.00 480.60
Jumlah 19,056.00 17,883.00 36,939.00
Keuntungan maksimal 10% 3,693.90
Jumlah 40,632.90
Dibulatkan 40,632.00
20 1 M2 PEKERJAAN PARTISI YUMEN KEDAP SUARA, T. 2 CM
Bahan :
Yumen Board, T. 2 cm Lbr 1.5000 148,000.00 222,000.00
Paku 1/2 - 1" Kg 0.1100 19,250.00 2,117.50
Lem Kg 0.5000 19,250.00 9,625.00
Alat Bantu ls 1.0000 3,000.00 3,000.00
Tenaga Kerja :
Pekerja Oh 0.1500 61,050.00 9,157.50
Tukang Kayu Oh 0.2500 75,700.00 18,925.00
Kep Tukang Kayu Oh 0.0250 82,700.00 2,067.50
Mandor Oh 0.0750 80,100.00 6,007.50
Jumlah 236,742.50 36,157.50 272,900.00
Keuntungan maksimal 10% 27,290.00
Jumlah 300,190.00
Dibulatkan 300,190.00
21 1 M2 PEKERJAAN PARTISI YUMEN KEDAP SUARA
Bahan :
Yumen Board, T. 1,5 cm Lbr 1.5000 116,000.00 174,000.00
Paku 1/2 - 1" Kg 0.1100 19,250.00 2,117.50
Lem Kg 0.5000 19,250.00 9,625.00
Alat Bantu ls 1.0000 3,000.00 3,000.00
Tenaga Kerja :
Pekerja Oh 0.1500 61,050.00 9,157.50
Tukang Kayu Oh 0.2500 75,700.00 18,925.00
Kep Tukang Kayu Oh 0.0250 82,700.00 2,067.50
Mandor Oh 0.0750 80,100.00 6,007.50
Jumlah 188,742.50 36,157.50 224,900.00
Keuntungan maksimal 10% 22,490.00
Jumlah 247,390.00
Dibulatkan 247,390.00
1 2 3 4 5 6 7 8
22 1 M2 PAS. GLASS WALL T. 10 CM
Bahan :
Glass Wall M2 1.1000 55,000.00 60,500.00
Alat Bantu ls 1.0000 5,000.00 5,000.00
Upah Pasang ( 30% ) Oh 1.0000 19,650.00 19,650.00
Jumlah 65,500.00 19,650.00 85,150.00
Keuntungan maksimal 10% 8,515.00
Jumlah 93,665.00
Dibulatkan 93,665.00
23 1 M2 PEK. WALL PAPER ( PER ROLL )
Bahan :
Wall paper biasa, uk. 0.50 x 10.00 m Roll 2.2000 102,850.00 226,270.00
Lem Vinyl Kg 0.2500 - -
Tenaga Kerja :
Pekerja Oh 0.3500 61,050.00 21,367.50
Tukang kayu Oh 0.1750 75,700.00 13,247.50
Kep. Tukang Kayu Oh 0.0170 82,700.00 1,405.90
Mandor Oh 0.0020 80,100.00 160.20
Jumlah 226,270.00 36,181.10 262,451.10
Keuntungan maksimal 10% 26,245.11
Jumlah 288,696.21
Dibulatkan 288,696.00
24 1 M2 PEK. WALL PAPER , LEBAR 50 CM ( SNI. Edisi Rev. 2008 )
Bahan :
Wall Paper m2 2.2000 -
Lem Vinyl Kg 0.2500 - -
Tenaga Kerja :
Pekerja Oh 0.3500 61,050.00 21,367.50
Tukang kayu Oh 0.1750 75,700.00 13,247.50
Kep. Tukang Kayu Oh 0.0170 82,700.00 1,405.90
Mandor Oh 0.0020 80,100.00 160.20
Jumlah - 36,181.10 36,181.10
Keuntungan maksimal 10% 3,618.11
Jumlah 39,799.21
Dibulatkan 39,799.00
25 1 M' PEKERJAAN PARAPET/TREATMENT
Bahan :
Multiplek 9 mm Lb 0.3800 137,500.00 52,250.00
Triplek Serat Sungkay Lb 0.3800 80,000.00 30,400.00
Profil Kayu M' 2.2000 7,000.00 15,400.00
Plin Kayu 10 cm M' 1.1000 27,466.00 30,212.60
Lem Putih Kg 0.2000 19,250.00 3,850.00
Lem Kuning Kg 0.1000 40,000.00 4,000.00
Wood Fller Kg 0.3000 42,000.00 12,600.00
Sending Seller Kg 0.3000 42,000.00 12,600.00
Melamik Kg 0.5000 42,350.00 21,175.00
Ampelas Lb 2.0000 4,436.00 8,872.00
Thinder Lt 1.0000 19,665.00 19,665.00
Alat Bantu Ls 1.0000 500.00 500.00
Tenaga Kerja :
Pekerja Oh 0.5000 61,050.00 30,525.00
Tukang Kayu Oh 1.0000 75,700.00 75,700.00
Kep Tukang Kayu Oh 0.1500 82,700.00 12,405.00
Tukang Cat Oh 0.8000 73,300.00 58,640.00
Kep Tukang Cat Oh 0.0800 81,000.00 6,480.00
Mandor Oh 0.0800 80,100.00 6,408.00
Jumlah 211,524.60 190,158.00 401,682.60
Keuntungan maksimal 10% 40,168.26
Jumlah 441,850.86
Dibulatkan 441,850.00
26 1 M' ARCHITRAP
Bahan :
Multiplek 12 cm Lbr 0.0500 176,000.00 8,800.00
Multiplek 9 cm Lbr 0.0500 137,500.00 6,875.00
Megateak Lbr 0.0400 80,000.00 3,200.00
Lem Kayu Kg 0.2000 40,000.00 8,000.00
Paku Biasa Kg 0.0300 19,250.00 577.50
Upah ( 30% X Bahan ) Ls 1.0000 8,235.75 8,235.75
Jumlah 27,452.50 8,235.75 35,688.25
Keuntungan maksimal 10% 3,568.83
Jumlah 39,257.08
Dibulatkan 39,257.00
27 PAS 1 M' END PROFIL
Bahan :
Multiplek 18 mm M2 0.1670 70,659.72 11,800.17
Balok Ky Kamper 3/3 M3 0.0040 6,050,000.00 24,200.00
Lem Kayu Kg 0.1000 19,250.00 1,925.00
Paku Kg 0.1000 19,250.00 1,925.00
Upah ( 30% X Jumlah Harga Bahan ) Ls 1.0000 11,955.05
Jumlah 39,850.17 11,955.05 51,805.23
Keuntungan maksimal 10% 5,180.52
Jumlah 56,985.75
Dibulatkan 56,985.00
28 1 M' PASANG LIST BAN PROFIL 2 CM
Bahan :
List Profil Kayu 2 cm M' 1.1000 4,510.00 4,961.00
Multiplek 12 cm Lbr 0.0760 176,000.00 13,376.00
Megateak Lbr 0.0760 80,000.00 6,080.00
Paku Kg 0.1000 19,250.00 1,925.00
Alat Bantu Ls 1.0000 500.00 500.00
Upah ( 15% X Bahan ) Ls 1.0000 4,026.30 4,026.30
Jumlah 26,842.00 4,026.30 30,868.30
Keuntungan maksimal 10% 3,086.83
Jumlah 33,955.13
Dibulatkan 33,955.00

1 2 3 4 5 6 7 8
29 1 M' PASANG LIST BAN PROFIL 7 CM
Bahan :
List Plafond Gifsum 7 cm M' 1.1000 12,100.00 13,310.00
Multiplek 12 cm Lbr 0.0760 176,000.00 13,376.00
Megateak Lbr 0.0760 80,000.00 6,080.00
Paku Kg 0.1000 19,250.00 1,925.00
Alat Bantu Ls 1.0000 500.00 500.00
Upah ( 15% X Bahan ) Ls 1.0000 5,278.65 5,278.65
Jumlah 35,191.00 5,278.65 40,469.65
Keuntungan maksimal 10% 4,046.97
Jumlah 44,516.62
Dibulatkan 44,516.00
30 1 M2 PASANG MULTIPLEK T. 9 MM LAPIS DINDING MELEKAT
Bahan :
Multiplek 9 mm Lbr 0.4000 137,500.00 55,000.00
Lem Kayu Kg 0.2500 19,250.00 4,812.50
Paku Kg 0.0500 19,250.00 962.50
Tenaga Kerja :
Pekerja Oh 0.0250 61,050.00 - 1,526.25
Tukang Kayu Oh 0.0750 75,700.00 - 5,677.50
Kepala Tukang Kayu Oh 0.0075 82,700.00 - 620.25
Mandor Oh 0.0013 80,100.00 - 104.13
Jumlah 60,775.00 7,928.13 68,703.13
Keuntungan maksimal 10% 6,870.31
Jumlah 75,573.44
Dibulatkan 75,573.00
31 1 M' PASANG LIST BAN PROFIL KAYU KAMPER 15/20
Bahan :
Kayu Kamper, Papan M3 0.0060 6,352,000.00 38,112.00
Profil 4 cm M' 2.2000 5,690.00 12,518.00
Paku Kg 0.0600 19,250.00 1,155.00
Tenaga Kerja :
Pekerja Oh 0.1000 61,050.00 - 6,105.00
Tukang Kayu Oh 0.1000 75,700.00 - 7,570.00
Kepala Tukang Kayu Oh 0.0100 82,700.00 - 827.00
Mandor Oh 0.0050 80,100.00 - 400.50
Jumlah 51,785.00 14,902.50 66,687.50
Keuntungan maksimal 10% 6,668.75
Jumlah 73,356.25
Dibulatkan 73,356.00
32 1 M2 PASANG VINYL
Bahan :
Vinyl kg 0.5500 45,000.00 24,750.00
Lem Kayu kg 0.5000 30,000.00 15,000.00
Upah 20% X Bahan oh 75,700.00 - 7,950.00
Jumlah 39,750.00 7,950.00 47,700.00
Keuntungan maksimal 10% 4,770.00
Jumlah 52,470.00
Dibulatkan 52,470.00
F.2 PEKERJAAN PLAFOND
1 1 M2 PASANG RANGKA LANGIT-LANGIT 0.30 x 0.60, KAYU BORNEO ( SNI. Edisi Rev. 2005 )
Bahan :
Kayu Borneo, Balok 5/7 M3 0.0230 4,455,000.00 102,465.00 -
Paku biasa 2" - 5" Kg 0.1500 17,210.00 2,581.50 -
Tenaga Kerja :
Pekerja Oh 0.2000 61,050.00 - 12,210.00
Tukang Kayu Oh 0.3000 75,700.00 - 22,710.00
Kepala Tukang Kayu Oh 0.0300 82,700.00 - 2,481.00
Mandor Oh 0.0100 80,100.00 - 801.00
Jumlah 105,046.50 38,202.00 143,248.50
Keuntungan maksimal 10% 14,324.85
Jumlah 157,573.35
Dibulatkan 157,573.00
2 1 M2 PASANG RANGKA LANGIT-LANGIT 1.00 x 1.00, KAYU BORNEO ( SNI. Edisi Rev. 2005 )
Bahan :
Kayu Borneo, Balok 5/7 M3 0.0175 4,455,000.00 77,962.50 -
Paku biasa 2" - 5" Kg 0.1000 17,210.00 1,721.00 -
Tenaga Kerja :
Pekerja Oh 0.1500 61,050.00 - 9,157.50
Tukang Kayu Oh 0.2500 75,700.00 - 18,925.00
Kepala Tukang Kayu Oh 0.0250 82,700.00 - 2,067.50
Mandor Oh 0.0750 80,100.00 - 6,007.50
Jumlah 79,683.50 36,157.50 115,841.00
Keuntungan maksimal 10% 11,584.10
Jumlah 127,425.10
Dibulatkan 127,425.00
3 1 M2 PASANG RANGKA LANGIT-LANGIT 0.5 x 1.00, KAYU BORNEO ( SNI. Edisi Rev. 2008 )
Bahan :
Kaso-Kaso 5/7 M3 0.0154 4,455,000.00 68,607.00 -
Paku biasa 7" - 10" Kg 0.2000 17,210.00 3,442.00 -
Tenaga Kerja :
Pekerja Oh 0.1500 61,050.00 - 9,157.50
Tukang Kayu Oh 0.3000 75,700.00 - 22,710.00
Kepala Tukang Kayu Oh 0.0300 82,700.00 - 2,481.00
Mandor Oh 0.0750 80,100.00 - 6,007.50
Jumlah 72,049.00 40,356.00 112,405.00
Keuntungan maksimal 10% 11,240.50
Jumlah 123,645.50
Dibulatkan 123,645.00
1 2 3 4 5 6 7 8
4 1 M2 PASANG RANGKA LANGIT-LANGIT 0.6 x 0.6, KAYU BORNEO ( SNI. Edisi Rev. 2008 )
Bahan :
Kaso-Kaso 5/7 M3 0.0163 4,455,000.00 72,616.50 -
Paku biasa 7" - 10" Kg 0.2500 17,210.00 4,302.50 -
Tenaga Kerja :
Pekerja Oh 0.2000 61,050.00 - 12,210.00
Tukang Kayu Oh 0.3000 75,700.00 - 22,710.00
Kepala Tukang Kayu Oh 0.0300 82,700.00 - 2,481.00
Mandor Oh 0.0100 80,100.00 - 801.00
Jumlah 76,919.00 38,202.00 115,121.00
Keuntungan maksimal 10% 11,512.10
Jumlah 126,633.10
Dibulatkan 126,633.00
5 1 M2 RANGKA PLAFOND BESI HOLLOW 4/4
Bahan :
Besi Hollow Bt 1.3000 135,000.00 175,500.00
Skrup/Paku Dus 0.0300 22,800.00 684.00
Alat Bantu Ls 1.0000 2,000.00 2,000.00
Tenaga Kerja :
Tukang Besi Oh 0.2500 158,000.00 39,500.00
Kep Tukang Besi Oh 0.0250 173,000.00 4,325.00
Mandor Oh 0.0050 185,000.00 925.00
Jumlah 178,184.00 44,750.00 222,934.00
Keuntungan maksimal 10% 22,293.40
Jumlah 245,227.40
Dibulatkan 245,227.00
6 1 M2 LANGIT-LANGIT GYPSUM ( SNI. Edisi Rev. 2008 )
Bahan :
Gypsum Lbr 0.3640 64,130.00 23,343.32
Paku 1/2 - 1" Kg 0.1100 22,800.00 2,508.00
Tenaga Kerja :
Pekerja Oh 0.1000 61,050.00 6,105.00
Tukang Kayu Oh 0.0500 75,700.00 3,785.00
Kep. Tukang kayu Oh 0.0050 82,700.00 413.50
Mandor Oh 0.0050 80,100.00 400.50
Jumlah 25,851.32 10,704.00 36,555.32
Keuntungan maksimal 10% 3,655.53
Jumlah 40,210.85
Dibulatkan 40,210.00
7 1 M2 PAS. PLAFOND GRC
Bahan :
GRC M2 1.1000 29,218.75 32,140.63
Paku 1/2" Kg 0.0100 22,800.00 228.00
Tenaga Kerja :
Pekerja Oh 0.0300 61,050.00 1,831.50
Tukang Kayu Oh 0.0700 75,700.00 5,299.00
Kep. Tukang Oh 0.0070 82,700.00 578.90
Mandor Oh 0.0015 80,100.00 120.15
Jumlah 32,368.63 7,829.55 40,198.18
Keuntungan maksimal 10% 4,019.82
Jumlah 44,217.99
Dibulatkan 44,217.00
8 1 M2 Langit-langit Gypsum akustik
Bahan
Akustik armstrong Lbr 0.3470 73,772.22 25,598.96
Plaster Board Ls 1.0000 3,688.61 3,688.61
Paku Skrup kg 0.0100 15,000.00 150.00
Tenaga
Pekerja Oh 0.0300 61,050.00 1,831.50
Tukang kayu Oh 0.0700 75,700.00 5,299.00
Kepala tukang kayu Oh 0.0070 82,700.00 578.90
Mandor Oh 0.0015 80,100.00 120.15
Jumlah 29,437.57 7,829.55 37,267.12
Keuntungan maksimal 10% 3,726.71
Jumlah 40,993.83
Dibulatkan 40,993.00
8 1 M2 LANGIT-LANGIT GYPSUM RANGKA BESI HOLLOW
Bahan :
Besi Hollow Bt 1.3000 135,000.00 175,500.00
Skrup/Paku Dus 0.0300 25,000.00 750.00
Alat Bantu Ls 1.0000 2,000.00 2,000.00
Gypsum M3 0.3640 64,130.00 23,343.32
Paku 1/2 - 1" Kg 0.1100 22,800.00 2,508.00
Tenaga Kerja :
Tukang Besi Oh 0.4000 158,000.00 63,200.00
Kep Tukang Besi Oh 0.0400 173,000.00 6,920.00
Pekerja Oh 0.1000 61,050.00 6,105.00
Tukang Kayu Oh 0.0500 75,700.00 3,785.00
Kep. Tukang kayu Oh 0.0050 82,700.00 413.50
Mandor Oh 0.0100 80,100.00 801.00
Jumlah 204,101.32 81,224.50 285,325.82
Keuntungan maksimal 10% 28,532.58
Jumlah 313,858.40
Dibulatkan 313,858.00
1 2 3 4 5 6 7 8
9 1 M2 LANGIT-LANGIT DOUBLE GYPSUM RANGKA BESI HOLLOW 4/4
Bahan :
Besi Hollow Bt 2.6000 135,000.00 351,000.00
Skrup/Paku Dus 0.0600 25,000.00 1,500.00
Alat Bantu Ls 1.0000 4,000.00 4,000.00
Gypsum M3 0.7280 64,130.00 46,686.64
Paku 1/2 - 1" Kg 0.2200 22,800.00 5,016.00
Tenaga Kerja :
Tukang Besi Oh 0.8000 158,000.00 126,400.00
Kep Tukang Besi Oh 0.0800 173,000.00 13,840.00
Pekerja Oh 0.1000 61,050.00 6,105.00
Tukang Kayu Oh 0.2000 75,700.00 15,140.00
Kep. Tukang kayu Oh 0.0100 82,700.00 827.00
Mandor Oh 0.0200 80,100.00 1,602.00
Jumlah 408,202.64 163,914.00 572,116.64
Keuntungan maksimal 10% 57,211.66
Jumlah 629,328.30
Dibulatkan 629,328.00
10 1 M2 PAS. LANGIT-LANGIT TRIPLEKS UKURAN ( 120 X 240 ), TEBAL 3 MM, 4 MM, 6 MM ( SNI. Edisi Rev. 2008 )
Bahan :
Tripleks Lbr 0.3750 47,300.00 17,737.50
Paku Tripleks Kg 0.0300 19,250.00 577.50
Tenaga Kerja :
Pekerja Oh 0.1000 61,050.00 6,105.00
Tukang Kayu Oh 0.1000 75,700.00 7,570.00
Kep. Tukang Oh 0.0100 82,700.00 827.00
Mandor Oh 0.0050 80,100.00 400.50
Jumlah 18,315.00 14,902.50 33,217.50
Keuntungan maksimal 10% 3,321.75
Jumlah 36,539.25
Dibulatkan 36,539.00
11 1 M2 LANGIT - LANGIT ASBES ( 1.00 x 1.00 ) M, T = 4 MM ( SNI Edisi Rev. 2005 )
Bahan :
Pelat Asbes Lbr 1.1000 13,500.00 14,850.00 -
Paku 1/2" - 1" Kg 0.0100 19,250.00 192.50 -
Tenaga Kerja :
Pekerja Oh 0.0300 61,050.00 - 1,831.50
Tukang Kayu Oh 0.0700 75,700.00 - 5,299.00
Kepala Tukang Kayu Oh 0.0070 82,700.00 - 578.90
Mandor Oh 0.0015 80,100.00 - 120.15
Jumlah 15,042.50 7,829.55 22,872.05
Keuntungan maksimal 10% 2,287.21
Jumlah 25,159.26
Dibulatkan 25,159.00
12 1 M2 LANGIT - LANGIT ASBES ( 1.00 x 1.00 ) M, T = 4 MM ( SNI. Edisi Rev. 2008 )
Bahan :
Asbes Semen m2 1.1000 13,500.00 14,850.00 -
Paku Tripleks Kg 0.0100 19,250.00 192.50 -
Tenaga Kerja :
Pekerja Oh 0.0300 61,050.00 - 1,831.50
Tukang Kayu Oh 0.0700 75,700.00 - 5,299.00
Kepala Tukang Kayu Oh 0.0070 82,700.00 - 578.90
Mandor Oh 0.0040 80,100.00 - 320.40
Jumlah 15,042.50 8,029.80 23,072.30
Keuntungan maksimal 10% 2,307.23
Jumlah 25,379.53
Dibulatkan 25,379.00
13 1 M' LIST LANGIT - LANGIT KAYU PROFIL ( SNI. Edisi Rev. 2008 )
Bahan :
List Kayu Profil 1/5 M' 1.0500 7,640.00 8,022.00 -
Paku 2" - 5" Kg 0.0100 19,250.00 192.50 -
Tenaga Kerja : -
Pekerja Oh 0.0500 61,050.00 - 3,052.50
Tukang Kayu Oh 0.0500 75,700.00 - 3,785.00
Kepala Tukang Kayu Oh 0.0050 82,700.00 - 413.50
Mandor Oh 0.0030 80,100.00 - 240.30
Jumlah 8,214.50 7,491.30 15,705.80
Keuntungan maksimal 10% 1,570.58
Jumlah 17,276.38
Dibulatkan 17,276.00
14 1 M' PASANG LIST GYPSUM DATAR
Bahan :
List Gypsum Datar M' 1.1000 12,100.00 13,310.00
Paku Kg 0.0100 4,000.00 40.00
Tenaga Kerja :
Pekerja Oh 0.0500 61,050.00 3,052.50
Tukang Kayu Oh 0.0500 75,700.00 3,785.00
Kep Tukang Kayu Oh 0.0050 82,700.00 413.50
Mandor Oh 0.0030 80,100.00 240.30
Jumlah 13,350.00 7,491.30 20,841.30
Keuntungan maksimal 10% 2,084.13
Jumlah 22,925.43
Dibulatkan 22,925.00
15 1 M' PASANG LIST PROFIL GIFSUM 5/7 CM ( SNI. Edisi Rev. 2008 )
Bahan :
List Gifsum 5 cm M' 1.0500 12,100.00 12,705.00
Paku Kg 0.1500 4,000.00 600.00
Tenaga Kerja :
Pekerja Oh 0.0600 61,050.00 3,663.00
Tukang Kayu Oh 0.0600 75,700.00 4,542.00
Kep Tukang Kayu Oh 0.0060 82,700.00 496.20
Mandor Oh 0.0030 80,100.00 240.30
Jumlah 13,305.00 8,941.50 22,246.50
Keuntungan maksimal 10% 2,224.65
Jumlah 24,471.15
Dibulatkan 24,471.00

1 2 3 4 5 6 7 8
16 1 M' PASANG LIST PROFIL GIFSUM 10 cm ( SNI. Edisi Rev. 2005 )
Bahan :
List Gifsum 10 cm M' 1.1000 13,310.00 14,641.00
Paku Kg 0.0100 4,000.00 40.00
Tenaga Kerja :
Pekerja Oh 0.0500 61,050.00 3,052.50
Tukang Kayu Oh 0.0500 75,700.00 3,785.00
Kep Tukang Kayu Oh 0.0050 82,700.00 413.50
Mandor Oh 0.0030 80,100.00 240.30
Jumlah 14,681.00 7,491.30 22,172.30
Keuntungan maksimal 10% 2,217.23
Jumlah 24,389.53
Dibulatkan 24,389.00
17 1 M' PASANG LIST PLAFOND KAYU PROFIL 2/10 ( SNI. Edisi Rev. 2005 )
Bahan :
Kayu Profil 2 cm Lbr 1.0500 4,510.00 4,735.50
Paku 1/2 - 1" Kg 0.0500 4,000.00 200.00
Tenaga Kerja :
Pekerja Oh 0.0210 61,050.00 1,282.05
Tukang Kayu Oh 0.0210 75,700.00 1,589.70
Kep Tukang Kayu Oh 0.0020 82,700.00 165.40
Mandor Oh 0.0010 80,100.00 80.10
Jumlah 4,935.50 3,117.25 8,052.75
Keuntungan maksimal 10% 805.28
Jumlah 8,858.03
Dibulatkan 8,858.00
18 1 M' PASANG LIST LANGIT-LANGIT KY KAMPER 3 CM ( SNI. Edisi Rev. 2005 )
Bahan :
List Profil Ky Kamper 3 cm M' 1.1000 4,510.00 4,961.00
Paku 2 - 5" Kg 0.0100 4,000.00 40.00
Tenaga Kerja :
Pekerja Oh 0.0500 61,050.00 3,052.50
Tukang Kayu Oh 0.0500 75,700.00 3,785.00
Kep Tukang Kayu Oh 0.0050 82,700.00 413.50
Mandor Oh 0.0030 80,100.00 162.00
Jumlah 5,001.00 7,413.00 12,414.00
Keuntungan maksimal 10% 1,241.40
Jumlah 13,655.40
Dibulatkan 13,655.00
19 1 M' PASANG LIST PROFIL KAYU 5 cm ( SNI. Edisi Rev. 2005 )
Bahan :
List Profil Kayu 5 cm M' 1.0500 7,640.00 8,022.00
Paku Kg 0.0500 4,000.00 200.00
Tenaga Kerja :
Pekerja Oh 0.0210 61,050.00 1,282.05
Tukang Kayu Oh 0.0210 75,700.00 1,589.70
Kep Tukang Kayu Oh 0.0020 82,700.00 165.40
Mandor Oh 0.0010 80,100.00 80.10
Jumlah 8,222.00 3,117.25 11,339.25
Keuntungan maksimal 10% 1,133.93
Jumlah 12,473.18
Dibulatkan 12,473.00
ANALISA PINTU KUSEN
1 1 M3 PASANGAN KUSEN PINTU & JENDELA, KAYU BORNEO SUPER ( SNI. Edisi Rev. 2008 )
Bahan :
Kayu Borneo Super, Balok M3 1.2000 4,455,000.00 5,346,000.00 -
Paku kg 1.2500 17,210.00 21,512.50 -
Lem kayu Fox kg 1.0000 19,250.00 19,250.00 -
Tenaga Kerja :
Pekerja Oh 6.0000 61,050.00 - 366,300.00
Tukang Kayu Oh 18.0000 75,700.00 - 1,362,600.00
Kepala Tukang Kayu Oh 1.8000 82,700.00 - 148,860.00
Mandor Oh 0.3000 80,100.00 - 24,030.00
Jumlah 5,386,762.50 1,901,790.00 7,288,552.50
Keuntungan maksimal 10% 728,855.25
Jumlah 8,017,407.75
Dibulatkan 8,017,407.00
2 1M2 PASANG PINTU PANIL MULTI + TEAKWOOD
Bahan :
Kayu Borneo Super, Balok M3 1.2000 5,147,000.00 6,176,400.00 -
Teakwood, t = 4 mm
Paku kg 1.2500 17,210.00 21,512.50 -
Lem kayu Fox kg 1.0000 19,250.00 19,250.00 -
Tenaga Kerja :
Pekerja Oh 6.0000 75,700.00 - 454,200.00
Tukang Kayu Oh 18.0000 82,700.00 - 1,488,600.00
Kepala Tukang Kayu Oh 1.8000 80,100.00 - 144,180.00
Mandor Oh 0.3000 - - -
Jumlah 6,217,162.50 2,086,980.00 8,304,142.50
Keuntungan maksimal 10% 830,414.25
Jumlah 9,134,556.75
Dibulatkan 9,134,556.00
3 1 M3 PASANGAN KUSEN PINTU & JENDELA, KAYU JATI ( SNI. Edisi Rev. 2008 )
Bahan :
Kayu Jati, Balok M3 1.1000 8,728,000.00 9,600,800.00
Paku Kg 1.2500 17,210.00 21,512.50
Lem Kayu Fox Kg 1.0000 19,250.00 19,250.00
Tenaga Kerja :
Pekerja Oh 7.0000 61,050.00 427,350.00
Tukang Kayu Oh 21.0000 75,700.00 1,589,700.00
Kep Tukang Kayu Oh 2.1000 82,700.00 173,670.00
Mandor Oh 0.3500 80,100.00 28,035.00
Jumlah 9,641,562.50 2,218,755.00 11,860,317.50
Keuntungan maksimal 10% 1,186,031.75
Jumlah 13,046,349.25
Dibulatkan 13,046,349.00
1 2 3 4 5 6 7 8
4 1 M3 PASANGAN KUSEN PINTU & JENDELA, KAYU KAMPER BANJAR ( SNI. Edisi Rev. 2008 )
Bahan :
Kayu Kamper Banjar, Balok M3 1.2000 6,050,000.00 7,260,000.00
Paku Kg 1.2500 17,210.00 21,512.50
Lem Kayu Fox Kg 1.0000 19,250.00 19,250.00
Tenaga Kerja :
Pekerja Oh 6.0000 61,050.00 366,300.00
Tukang Kayu Oh 18.0000 75,700.00 1,362,600.00
Kep Tukang Kayu Oh 1.8000 82,700.00 148,860.00
Mandor Oh 0.3000 80,100.00 24,030.00
Jumlah 7,300,762.50 1,901,790.00 9,202,552.50
Keuntungan maksimal 10% 920,255.25
Jumlah 10,122,807.75
Dibulatkan 10,122,807.00
5 1 M2 PASANGAN KACA, T = 8 MM ( SNI. Edisi Rev. 2005 )
Bahan :
Kaca 8 mm M2 1.1000 - -
Tenaga Kerja :
Pekerja Oh 0.0150 #REF! - #REF!
Tukang Kayu Oh 0.1500 #REF! - #REF!
Kepala Tukang Kayu Oh 0.0150 #REF! - #REF!
Mandor Oh 0.0008 #REF! - #REF!
Jumlah - #REF! #REF!
Keuntungan maksimal 10% #REF!
Jumlah #REF!
Dibulatkan #REF!
ANALISA BIAYA PEKERJAAN BONGKARAN
1 1 M3 MEMBONGKAR DINDING BATA
(Jika Bongkaran dipakai lagi)
Tenaga Kerja :
Pekerja Org 2.0000 138,000.00 276,000.00
Mandor Org 0.0900 185,000.00 16,650.00
Jumlah - 292,650.00 292,650.00
Keuntungan maksimal 10% 29,265.00
Jumlah 321,915.00
Dibulatkan 321,915.00
2 1 M2 MEMBONGKAR LANTAI KERAMIK
Tenaga Kerja :
Pekerja Org 0.0500 138,000.00 6,900.00
Mandor Org 0.0100 185,000.00 1,850.00
Jumlah 8,750.00 8,750.00
Keuntungan maksimal 10% 875.00
Jumlah 9,625.00
Dibulatkan 9,625.00
3 1 M2 MEMBONGKAR RANGKA ATAP/RENG KASO
(Jika Bongkaran tidak dipakai)
Tenaga Kerja :
Tukang Kayu Org 0.1000 158,000.00 15,800.00
Pekerja Org 0.0250 138,000.00 3,450.00
Kepala Tukang Kayu Org 0.0025 173,000.00 432.50
Mandor Org 0.0050 185,000.00 925.00
Jumlah - 20,607.50 20,607.50
Keuntungan maksimal 10% 2,060.75
Jumlah 22,668.25
Dibulatkan 22,668.00
4 1 M2 MEMBONGKAR GENTENG / SIRAP
(Jika bongkaran dipakai kembali)
Tenaga Kerja :
Pekerja setengah terampil Org 0.0400 173,000.00 6,920.00
Mandor Org 0.0200 185,000.00 3,700.00
Jumlah - 10,620.00 10,620.00
Keuntungan maksimal 10% 1,062.00
Jumlah 11,682.00
Dibulatkan 11,682.00
5 1M2 MEMBONGKAR PLAFOND
(Jika bongkaran tidak dipakai lagi)
Tenaga Kerja :
Pekerja Org 0.1250 138,000.00 17,250.00
Mandor Org 0.0050 185,000.00 925.00
Jumlah - 18,175.00 18,175.00
Keuntungan maksimal 10% 1,817.50
Jumlah 19,992.50
Dibulatkan 19,992.00
B ANALISA BIAYA PEKERJAAN PERSIAPAN
1 1 M' PAS. BOUWPLANK & PENGUKURAN
Bahan :
Kayu Borneo 5/7 M3 0.0070 4,000,000.00 28,000.00 -
Paku biasa 2" - 5" Kg 0.0200 22,800.00 456.00 -
Kayu papan Albasia M3 0.0070 2,354,760.00 16,483.32 -
Tenaga Kerja :
Pekerja Oh 0.1000 138,000.00 - 13,800.00
Tukang Kayu Oh 0.1000 158,000.00 - 15,800.00
Kepala Tukang Kayu Oh 0.0100 158,000.00 - 1,580.00
Mandor Oh 0.0050 185,000.00 - 925.00
Jumlah 44,939.32 32,105.00 77,044.32
Keuntungan maksimal 10% 7,704.43
Jumlah 84,748.75
Dibulatkan 84,748.00
2 1 M2 PEMB. DIREKSI KEET DENGAN LANTAI PLESTER ( SNI. Edisi Rev. 2005 )
Bahan :
Kayu dolken dia 8 - 10/400 cm Btg 1.2500 39,240.00 49,050.00 -
Kayu papan Albasia M3 0.1800 2,354,760.00 423,856.80 -
Paku biasa 2" - 5" Kg 0.8500 22,800.00 19,380.00 -
Besi strip kg 1.1000 50,000.00 55,000.00 -
Semen Portland Kg 35.0000 1,330.00 46,550.00 -
Pasir pasang M3 0.1500 280,000.00 42,000.00 -
Pasir beton M3 0.1000 290,000.00 29,000.00 -
Koral beton M3 0.1500 264,000.00 39,600.00 -
Bata merah Bh 30.0000 650.00 19,500.00 -
Seng plat, BJLS 25 Lbr 0.2500 70,000.00 17,500.00 -
Jendela nako Bh 2.0000 92,400.00 184,800.00 -
Kaca polos M2 0.0800 52,000.00 4,160.00 -
Kunci tanam Bh 0.1500 45,000.00 6,750.00 -
Plywood 4 mm Lbr 0.0600 160,440.00 9,626.40 -
Tenaga Kerja :
Pekerja Oh 1.0000 138,000.00 - 138,000.00
Tukang Kayu Oh 1.5000 158,000.00 - 237,000.00
Tukang Batu Oh 1.0000 158,000.00 - 158,000.00
Kepala Tukang Kayu Oh 0.3000 158,000.00 - 47,400.00
Mandor Oh 0.0500 185,000.00 - 9,250.00
Jumlah 946,773.20 589,650.00 1,536,423.20
Keuntungan maksimal 10% 153,642.32
Jumlah 1,690,065.52
Dibulatkan 1,690,060.00
3 PENGADAAN ALAT PELINDING DIRI ( APD )
Bahan :
Sepatu Boot bh 20.0000 95,000.00 1,900,000.00
Helm Safety bh 20.0000 50,000.00 1,000,000.00
Rompi Jaring Proyek bh 20.0000 12,000.00 240,000.00
Sarung Tangan Proyek bh 20.0000 5,000.00 100,000.00
Safety Belt bh 5.0000 60,000.00 300,000.00
Jumlah 3,540,000.00 3,540,000.00
Keuntungan maksimal 10% 354,000.00
Jumlah 3,894,000.00
Dibulatkan 3,894,000.00
4 1 M' PEMBUATAN PAGAR SEMENTARA DARI SENG GELOMBANG T=2 M
Bahan :
Dolken Kayu ø 8-10/400 cm kg 1.2500 39,240.00 49,050.00 -
Semen Portland kg 2.5000 1,330.00 3,325.00 -
Seng gelombang lbr 1.2000 48,000.00 57,600.00 -
Pasir beton m3 0.0050 290,000.00 1,450.00
Koral beton m3 0.0090 264,000.00 2,376.00
Kayu 5/7 m3 0.0720 1,000,000.00 72,000.00
Paku biasa 2" - 5" kg 0.0600 22,800.00 1,368.00
Meni besi liter 0.4500 21,876.00 9,844.20
Tenaga Kerja :
Pekerja Oh 0.2000 138,000.00 - 27,600.00
Tukang Kayu Oh 0.4000 158,000.00 - 63,200.00
Kepala Tukang Kayu Oh 0.0200 173,000.00 - 3,460.00
Mandor Oh 0.0200 185,000.00 - 3,700.00
Jumlah 197,013.20 97,960.00 294,973.20
Keuntungan maksimal 10% 29,497.32
Jumlah 324,470.52
Dibulatkan 324,470.00
C ANALISA BIAYA PEKERJAAN TANAH
1 1 M3 GALIAN TANAH BIASA KEDALAMAN 1 M' s.d. 2 M
Tenaga Kerja :
Pekerja Oh 0.7500 138,000.00 - 103,500.00
Mandor Oh 0.0250 185,000.00 - 4,625.00
Jumlah 108,125.00 108,125.00
Keuntungan maksimal 10% 10,812.50
Jumlah 118,937.50
Dibulatkan 118,930.00
2 1 M3 URUGAN TANAH KEMBALI
Tenaga Kerja :
Pekerja Oh 0.3300 138,000.00 - 45,540.00
Mandor Oh 0.0033 185,000.00 - 610.50
Jumlah 46,150.50 46,150.50
Keuntungan maksimal 10% 4,615.05
Jumlah 50,765.55
Dibulatkan 50,765.00
3 1 M3 URUGAN PASIR
Bahan :
Pasir urug M3 1.2000 270,000.00 324,000.00 -
Tenaga Kerja :
Pekerja Oh 0.3000 138,000.00 - 41,400.00
Mandor Oh 0.0100 185,000.00 - 1,850.00
Jumlah 324,000.00 43,250.00 367,250.00
Keuntungan maksimal 10% 36,725.00
Jumlah 403,975.00
Dibulatkan 403,975.00
4 1 M3 LANTAI KERJA BETON
Bahan :
Semen Portland kg 230.0000 1,330.00 305,900.00 -
Pasir Beton kg 893.0000 290.00 258,970.00
Kerikil kg 1027.0000 264.00 271,128.00
Air Liter 200.0000 50.00 10,000.00
Tenaga Kerja :
Pekerja Oh 1.2000 138,000.00 - 165,600.00
Tukang Batu Oh 0.2000 158,000.00 31,600.00
Kepala Tukang Batu Oh 0.0200 173,000.00 3,460.00
Mandor Oh 0.0600 185,000.00 - 11,100.00
Jumlah 845,998.00 211,760.00 1,057,758.00
Keuntungan maksimal 10% 105,775.80
Jumlah 1,163,533.80
Dibulatkan 1,163,533.00
D ANALISA BIAYA PEKERJAAN PONDASI
1 1 M3 PASANGAN PONDASI BATU KALI, 1 PC. : 6 PS.
Bahan :
Batu Belah 15/20 cm M3 1.2000 325,000.00 390,000.00 -
Semen Portland Kg 91.0000 1,330.00 121,030.00 -
Pasir Pasang M3 0.5840 280,000.00 163,520.00 -
Tenaga Kerja :
Pekerja Oh 1.5000 138,000.00 - 207,000.00
Tukang Batu Oh 0.7500 158,000.00 - 118,500.00
Kepala Tukang Batu Oh 0.0750 173,000.00 - 12,975.00
Mandor Oh 0.0750 185,000.00 - 13,875.00
Jumlah 674,550.00 352,350.00 1,026,900.00
Keuntungan maksimal 10% 102,690.00
Jumlah 1,129,590.00
Dibulatkan 1,129,590.00
ANALISA BIAYA PEKERJAAN BETON
1 1 M3 ADUKAN BETON TUMBUK CAMP. 1 PC : 3 PS : 5 KR
Bahan :
Semen Portland kg 218.0000 1,330.00 289,940.00 -
Pasir beton m3 0.5200 290,000.00 150,800.00 -
Koral beton m3 0.8700 264,000.00 229,680.00 -
Tenaga Kerja :
Pekerja Oh 1.6500 138,000.00 - 227,700.00
Tukang Batu Oh 0.2500 158,000.00 - 39,500.00
Kepala Tukang Batu Oh 0.0250 173,000.00 - 4,325.00
Mandor Oh 0.0800 185,000.00 - 14,800.00
Jumlah 670,420.00 286,325.00 956,745.00
Keuntungan maksimal 10% 95,674.50
Jumlah 1,052,419.50
Dibulatkan 1,052,419.00
2 1 M3 ADUKAN BETON K. 175 ( Site Mix )
Bahan :
Semen Portland kg 326.00 1,330.00 433,580.00 -
Pasir beton Kg 760.00 290.00 220,400.00 -
Koral beton Kg 1029.00 264.00 271,656.00 -
Air Ltr 215.00 50.00 10,750.00 -
Tenaga Kerja :
Pekerja Oh 1.6500 138,000.00 - 227,700.00
Tukang Batu Oh 0.2750 158,000.00 - 43,450.00
Kepala Tukang Batu Oh 0.0280 173,000.00 - 4,844.00
Mandor Oh 0.0830 185,000.00 - 15,355.00
Jumlah 936,386.00 291,349.00 1,227,735.00
Keuntungan maksimal 10% 122,773.50
Jumlah 1,350,508.50
Dibulatkan 1,350,508.00
3 1 M3 ADUKAN BETON K. 250 ( Site Mix )
Bahan :
Semen Portland kg 384.00 1,330.00 510,720.00 -
Pasir beton Kg 692.00 290.00 200,680.00 -
Koral beton Kg 1039.00 264.00 274,296.00 -
Air Ltr 215.00 50.00 10,750.00 -
Peralatan sewa/hari 0.25 100,000.00 25,000.00
Tenaga Kerja :
Pekerja Oh 1.3230 138,000.00 - 182,574.00
Tukang Batu Oh 0.1890 158,000.00 - 29,862.00
Kepala Tukang Batu Oh 0.0190 173,000.00 - 3,287.00
Mandor Oh 0.1320 185,000.00 - 24,420.00
Jumlah 1,021,446.00 240,143.00 1,261,589.00
Keuntungan maksimal 10% 126,158.90
Jumlah 1,387,747.90
Dibulatkan 1,387,747.00
4 10 KG TULANGAN BETON DENGAN BESI POLOS / ULIR
Bahan :
Besi Beton Polos Kg 10.5000 12,000.00 126,000.00 -
Kawat Beton kg 0.1500 24,624.00 3,693.60 -
Tenaga Kerja :
Pekerja Oh 0.0700 138,000.00 - 9,660.00
Tukang Besi Oh 0.0700 158,000.00 - 11,060.00
Kepala Tukang Besi Oh 0.0070 173,000.00 - 1,211.00
Mandor Oh 0.0040 185,000.00 - 740.00
Jumlah 129,693.60 22,671.00 152,364.60
Keuntungan maksimal 10% 15,236.46
Jumlah 167,601.06
Dibulatkan 167,601.00
5 1 M2 PEKERJAAN WIREMESH M8
Bahan :
Wiremesh M8 lbr 0.0882 610,000.00 53,791.89 -
Kawat Las kg 0.1000 24,624.00 2,462.40 -
Tenaga Kerja :
Pekerja Oh 0.1000 138,000.00 - 13,800.00
Tukang Besi Oh 0.0750 158,000.00 - 11,850.00
Kepala Tukang Besi Oh 0.0070 173,000.00 - 1,211.00
Mandor Oh 0.0010 185,000.00 - 185.00
Jumlah 56,254.29 27,046.00 83,300.29
Keuntungan maksimal 10% 8,330.03
Jumlah 91,630.32
Dibulatkan 91,630.00
6 1 M2 PEMASANGAN METALDECK
Bahan :
Metal Deck m2 1.0100 120,000.00 121,200.00 -
Kawat Las m3 0.1000 38,000.00 3,800.00
Shear Connector set 1.0000 25,000.00 25,000.00
Tenaga Kerja :
Pekerja Oh 0.0400 138,000.00 - 5,520.00
Tukang Besi Oh 0.0400 158,000.00 - 6,320.00
Kepala Tukang Besi Oh 0.0040 173,000.00 - 692.00
Mandor Oh 0.0016 185,000.00 - 296.00
Jumlah 150,000.00 12,828.00 162,828.00
Keuntungan maksimal 10% 16,282.80
Jumlah 179,110.80
Dibulatkan 179,110.00
7 1 M2. PASANG BEKISTING UNTUK PONDASI
Bahan :
Kayu Papan/balok Albasia M3 0.0400 2,354,760.00 94,190.40 -
Paku Biasa 2" - 5" Kg 0.3000 22,800.00 6,840.00 -
Minyak Bekisting Lt 0.1000 21,876.00 2,187.60 -
Tenaga Kerja :
Pekerja Oh 0.5200 138,000.00 - 71,760.00
Tukang Kayu Oh 0.2600 158,000.00 - 41,080.00
Kepala Tukang Kayu Oh 0.0260 173,000.00 - 4,498.00
Mandor Oh 0.0260 185,000.00 - 4,810.00
Jumlah 103,218.00 122,148.00 225,366.00
Keuntungan maksimal 10% 22,536.60
Jumlah 247,902.60
Dibulatkan 247,902.00
8 1 M2. PASANG BEKISTING UNTUK SLOOF
Bahan :
Paku Biasa 2" - 5" Kg 0.2500 22,800.00 5,700.00 -
Minyak Bekisting Lt 0.2000 21,876.00 4,375.20 -
Balok Kayu 5/7 M3 0.0090 1,500,000.00 13,500.00 -
Multipleks 9 mm Lbr 0.1280 182,316.00 23,336.45 -
Tenaga Kerja :
Pekerja Oh 0.2000 138,000.00 - 27,600.00
Tukang Kayu Oh 0.1000 158,000.00 - 15,800.00
Kepala Tukang Kayu Oh 0.0100 173,000.00 - 1,730.00
Mandor Oh 0.0200 185,000.00 - 3,700.00
Jumlah - 48,830.00 48,830.00
Keuntungan maksimal 10% 4,883.00
Jumlah 53,713.00
Dibulatkan 53,713.00
9 1 M2. PASANG BEKISTING UNTUK KOLOM
Bahan :
Paku Biasa 2" - 5" Kg 0.2500 22,800.00 5,700.00 -
Minyak Bekisting Lt 0.2000 21,876.00 4,375.20 -
Balok Kayu 5/7 M3 0.0060 1,500,000.00 9,000.00 -
Multipleks 9 mm Lbr 0.1280 182,316.00 23,336.45 -
Dolkenkayu kls . III btg 0.7480 39,240.00 29,351.52
Paku Biasa 2" - 5" Kg 0.2400 22,800.00 5,472.00
Tenaga Kerja :
Pekerja Oh 0.3800 138,000.00 - 52,440.00
Tukang Kayu Oh 0.1900 158,000.00 - 30,020.00
Kepala Tukang Kayu Oh 0.0190 173,000.00 - 3,287.00
Mandor Oh 0.0380 185,000.00 - 7,030.00
Jumlah 77,235.17 92,777.00 170,012.17
Keuntungan maksimal 10% 17,001.22
Jumlah 187,013.38
Dibulatkan 187,013.00
10 1 M2. PASANG BEKISTING UNTUK BALOK
Bahan :
Paku Biasa 2" - 5" Kg 0.2500 22,800.00 5,700.00 -
Minyak Bekisting Lt 0.2000 21,876.00 4,375.20 -
Balok Kayu 5/7 M3 0.0110 1,500,000.00 16,500.00 -
Multipleks 12 mm Lbr 0.1280 182,316.00 23,336.45 -
Dolkenkayu kls . III btg 0.8130 39,240.00 31,902.12
Paku Biasa 2" - 5" Kg 0.2800 22,800.00 6,384.00
Tenaga Kerja :
Pekerja Oh 0.4000 138,000.00 - 55,200.00
Tukang Kayu Oh 0.2000 158,000.00 - 31,600.00
Kepala Tukang Kayu Oh 0.0200 173,000.00 - 3,460.00
Mandor Oh 0.0400 185,000.00 - 7,400.00
Jumlah 88,197.77 97,660.00 185,857.77
Keuntungan maksimal 10% 18,585.78
Jumlah 204,443.54
Dibulatkan 204,443.00
11 1 M2. PASANG BEKISTING UNTUK PLAT LANTAI
Bahan :
Paku Biasa 2" - 5" Kg 0.2500 22,800.00 5,700.00 -
Minyak Bekisting Lt 0.2000 21,876.00 4,375.20 -
Balok Kayu 5/7 M3 0.0110 1,500,000.00 16,500.00 -
Multipleks 12 mm Lbr 0.1280 182,316.00 23,336.45 -
Dolkenkayu kls . III btg 1.4630 39,240.00 57,408.12
Paku Biasa 2" - 5" Kg 0.3000 22,800.00 6,840.00
Tenaga Kerja :
Pekerja Oh 0.3400 138,000.00 - 46,920.00
Tukang Kayu Oh 0.1700 158,000.00 - 26,860.00
Kepala Tukang Kayu Oh 0.0170 173,000.00 - 2,941.00
Mandor Oh 0.0340 185,000.00 - 6,290.00
Jumlah 114,159.77 83,011.00 197,170.77
Keuntungan maksimal 10% 19,717.08
Jumlah 216,887.84
Dibulatkan 216,887.00
12 1 M3. PONDASI BETON BERTULANG 40.40.20
Bahan :
Kayu papan Albasia M3 0.2000 2,354,760.00 470,952.00
Paku Biasa 2" - 5" Kg 1.5000 22,800.00 34,200.00
Minyak Bekisting ltr 0.4000 21,876.00 8,750.40
OK PONDASI 40
Besi Beton Polos Kg 150.3938 16,760.10 2,520,614.29
Kawat Beton Kg 2.2500 18,571.00 41,784.75
Semen Portland Kg 336.0000 1,330.00 446,880.00
Pasir beton M3 0.5400 290,000.00 156,600.00
Kerikil M3 0.8100 264,000.00 213,840.00
Tenaga Kerja :
Pekerja Oh 5.3000 138,000.00 731,400.00
Tukang Batu Oh 0.2750 158,000.00 43,450.00
Tukang Kayu Oh 1.3000 158,000.00 205,400.00
Tukang Besi Oh 1.0500 158,000.00 165,900.00
Kepala Tukang Oh 0.2620 173,000.00 45,326.00
Mandor Oh 0.2650 185,000.00 49,025.00
Jumlah 3,893,621.44 1,240,501.00 5134122.439375
Keuntungan maksimal 10% 513412.2439375
Jumlah 5,647,534.68
Dibulatkan 5,647,534.00

12 1 M3. PONDASI BETON BERTULANG 75.75.20


Bahan :
Kayu papan Albasia M3 0.2000 1,000,000.00 200,000.00 -
Paku Biasa 2" - 5" Kg 1.5000 22,800.00 34,200.00 -
Minyak Bekisting ltr 0.4000 21,876.00 8,750.40 -
Besi Beton Polos Kg 266.8444 16,760.10 4,472,339.57 -
Kawat Beton Kg 2.2500 18,571.00 41,784.75 -
Semen Portland Kg 336.0000 1,330.00 446,880.00 -
Pasir beton M3 0.5400 290,000.00 156,600.00 -
Kerikil M3 0.8100 264,000.00 213,840.00 -
Tenaga Kerja :
Pekerja Oh 5.3000 158,000.00 - 837,400.00
Tukang Batu Oh 0.2750 173,000.00 - 47,575.00
Tukang Kayu Oh 1.3000 173,000.00 - 224,900.00
Tukang Besi Oh 1.0500 173,000.00 - 181,650.00
Kepala Tukang Oh 0.2620 185,000.00 - 48,470.00
Mandor Oh 0.2650 - - -
Jumlah 5,574,394.72 1,339,995.00 6914389.72333333
Keuntungan maksimal 10% 691438.972333333
Jumlah 7,605,828.70
Dibulatkan 7,605,828.00
12 1 M3. PONDASI BETON BERTULANG 60.60.20
Bahan :
Kayu papan Albasia M3 0.2000 2,354,760.00 470,952.00
Paku Biasa 2" - 5" Kg 1.5000 22,800.00 34,200.00
Minyak Bekisting ltr 0.4000 21,876.00 8,750.40
Besi Beton Polos Kg 167.7333 16,760.10 2,811,227.44
OK PONDASI 60
Kawat Beton Kg 2.2500 18,571.00 41,784.75
Semen Portland Kg 336.0000 1,330.00 446,880.00
Pasir beton M3 0.5400 290,000.00 156,600.00
Kerikil M3 0.8100 264,000.00 213,840.00
Tenaga Kerja :
Pekerja Oh 5.3000 138,000.00 731,400.00
Tukang Batu Oh 0.2750 158,000.00 43,450.00
Tukang Kayu Oh 1.3000 158,000.00 205,400.00
Tukang Besi Oh 1.0500 158,000.00 165,900.00
Kepala Tukang Oh 0.2620 173,000.00 45,326.00
Mandor Oh 0.2650 185,000.00 49,025.00
Jumlah 4,184,234.59 1,240,501.00 5424735.59
Keuntungan maksimal 10% 542473.559
Jumlah 5,967,209.15
Dibulatkan 5,967,209.00
13 1 M3. PONDASI BETON BERTULANG 100.100.20
Bahan :
Kayu papan Albasia M3 0.2000 2,354,760.00 470,952.00 -
Paku Biasa 2" - 5" Kg 1.5000 22,800.00 34,200.00 -
Minyak Bekisting ltr 0.4000 21,876.00 8,750.40 -
Besi Beton Polos Kg 208.9111 16,760.10 3,501,371.11 -
Kawat Beton Kg 2.2500 18,571.00 41,784.75 -
Semen Portland Kg 336.0000 1,330.00 446,880.00 -
Pasir beton M3 0.5400 290,000.00 156,600.00 -
Kerikil M3 0.8100 264,000.00 213,840.00 -
Tenaga Kerja :
Pekerja Oh 5.3000 158,000.00 - 837,400.00
Tukang Batu Oh 0.2750 158,000.00 - 43,450.00
Tukang Kayu Oh 1.3000 158,000.00 - 205,400.00
Tukang Besi Oh 1.0500 158,000.00 - 165,900.00
Kepala Tukang Oh 0.2620 173,000.00 - 45,326.00
Mandor Oh 0.2650 185,000.00 - 49,025.00
Jumlah 4,874,378.26 1,346,501.00 6,220,879.26
Keuntungan maksimal 10% 622,087.93
Jumlah 6,842,967.19
Dibulatkan 6,842,967.00
14 1 M3. BETON BERTULANG SLOOF 20 x 25 cm ADUKAN BETON K.250
- Adukan beton K. 250 M3 1.0000 1,387,747.00 1,387,747.00
- Bekisting papan (untuk 2xpakai
diambil 50%) M2 5.0000 53,713.00 134,282.50
- Besi beton U.39 Kg 207.5200 16,760.10 3,478,055.95
Jumlah 5,000,085.45
Dibulatkan 5,000,085.00
15 1 M3. BETON BERTULANG SLOOF 15 x 20 cm ADUKAN BETON K.175
- Adukan beton K. 175 M3 1.0000 1,350,508.00 1,350,508.00
- Bekisting papan (untuk 2xpakai
diambil 50%) M2 3.3333 53,713.00 89,521.67
- Besi beton U.39 Kg 188.0000 16,760.10 3,150,898.80
Jumlah 4,590,928.47
Dibulatkan 4,590,928.00
16 1 M3. BETON BERTULANG KOLOM 15 x 15 cm ADUKAN BETON K.175
- Adukan beton K. 175 M3 1.0000 1,350,508.00 1,350,508.00
- Bekisting papan (untuk 2xpakai
diambil 50%) M2 6.6667 187,013.00 623,376.67
- Besi beton U.39 Kg 144.8889 16,760.10 2,428,352.27
Jumlah 4,402,236.93
Dibulatkan 4,402,236.00
17 1 M3. BETON BERTULANG KOLOM 30 x 30 cm ADUKAN BETON K.250
- Adukan beton K. 250 M3 1.0000 1,387,747.00 1,387,747.00
- Bekisting papan (untuk 2xpakai kolom 3
diambil 50%) M2 6.6667 187,013.00 623,376.67
- Besi beton U.39 Kg 196.9250 16,760.10 3,300,482.69
Jumlah 5,311,606.36
Dibulatkan 5,311,606.00
18 1 M3. BETON BERTULANG KOLOM 15 x 30 cm ADUKAN BETON K.250
- Adukan beton K. 250 M3 1.0000 1,387,747.00 1,387,747.00
- Bekisting papan (untuk 2xpakai
diambil 50%) M2 10.0000 187,013.00 935,065.00
- Besi beton U.39 Kg 373.2667 16,760.10 6,255,986.66
Jumlah 8,578,798.66
Dibulatkan 8,578,798.00
19 1 M3. BETON BERTULANG RING BALK 15 x 20 cm ADUKAN BETON K.175
Balok 1
- Adukan beton K. 175 M3 1.0000 1,350,508.00 1,350,508.00
- Bekisting papan (untuk 2xpakai
diambil 50%) M2 6.6650 204,443.00 681,306.30
- Besi beton U.39 Kg 188.0000 16,760.10 3,150,898.80
Jumlah 5,182,713.10
Dibulatkan 5,182,713.00
20 1 M3. BETON BERTULANG BALOK 20 x 30 cm ADUKAN BETON K.250
- Adukan beton K. 250 M3 1.0000 1,387,747.00 1,387,747.00
- Bekisting papan (untuk 2xpakai
diambil 50%) M2 4.6667 187,013.00 436,363.67
- Besi beton U.39 Kg 201.9000 16,760.10 3,383,864.19
Jumlah 5,207,974.86
Dibulatkan 5,207,974.00
21 1 M3. BETON BERTULANG BALOK 20 x 40 cm ADUKAN BETON K.250
- Adukan beton K. 250 M3 1.0000 1,387,747.00 1,387,747.00
- Bekisting papan (untuk 2xpakai
diambil 50%) M2 4.7500 187,013.00 444,155.88
- Besi beton U.39 Kg 172.7750 16,760.10 2,895,726.28
Jumlah 4,727,629.15
Dibulatkan 4,727,629.00
22 1 M3. BETON BERTULANG BALOK 20 x 50 cm ADUKAN BETON K.250
- Adukan beton K. 225 M3 1.0000 1,387,747.00 1,387,747.00
- Bekisting papan (untuk 2xpakai
diambil 50%) M2 4.8000 204,443.00 490,663.20
- Besi beton U.39 Kg 151.6750 16,760.10 2,542,088.17
Jumlah 4,420,498.37
Dibulatkan 4,420,498.00
23 1 M3. BETON PLAT LANTAI TEBAL 10 CM ADUKAN BETON K.250 ( SNI. Edisi Rev. 2005 )
- Adukan beton K. 250 M3 1.0000 1,387,747.00 1,387,747.00
- Bekisting papan (untuk 2xpakai)
diambil 50%) M2 5.0000 53,713.00 134,282.50
- Besi beton U.24 Kg 88.7445 16,760.10 1,487,366.69
Jumlah 3,009,396.19
Dibulatkan 3,009,396.00
ANALISA BIAYA PEKERJAAN DINDING
1 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 PC. : 6 PS.
Bahan :
Bata Merah Bh 70.0000 650.00 45,500.00 -
Semen Portland Kg 8.3200 1,330.00 11,065.60 -
Pasir Pasang M3 0.0490 280,000.00 13,720.00 -
Tenaga Kerja :
Pekerja Oh 0.3000 138,000.00 - 41,400.00
Tukang Batu Oh 0.1000 158,000.00 - 15,800.00
Kepala Tukang Batu Oh 0.0100 173,000.00 - 1,730.00
Mandor Oh 0.0150 185,000.00 - 2,775.00
Jumlah 70,285.60 61,705.00 131,990.60
Keuntungan maksimal 10% 13,199.06
Jumlah 145,189.66
Dibulatkan 145,189.00
2 1 M2 PLESTERAN DINDING 1 PC. : 6 PS; TEB. 15 MM
Bahan :
Semen Portland Kg 4.4160 1,330.00 5,873.28 -
Pasir Pasang M3 0.0270 280,000.00 7,560.00 -
Tenaga Kerja :
Pekerja Oh 0.2000 138,000.00 - 27,600.00
Tukang Batu Oh 0.1500 158,000.00 - 23,700.00
Kepala Tukang Batu Oh 0.0150 173,000.00 - 2,595.00
Mandor Oh 0.0100 185,000.00 - 1,850.00
Jumlah 13,433.28 55,745.00 69,178.28
Keuntungan maksimal 10% 6,917.83
Jumlah 76,096.11
Dibulatkan 76,096.00
3 1 M2 ACIAN SEMEN
Bahan :
Semen Portland Kg 3.2500 1,330.00 4,322.50
Tenaga Kerja :
Pekerja Oh 0.2000 138,000.00 27,600.00
Tukang Batu Oh 0.1000 158,000.00 15,800.00
Kepala Tukang Oh 0.0100 173,000.00 1,730.00
Mandor Oh 0.0100 185,000.00 1,850.00
Jumlah 4,322.50 46,980.00 51,302.50
Keuntungan maksimal 10% 5,130.25
Jumlah 56,432.75
Dibulatkan 56,432.00
4 1 M2 LAPISAN WATER PROFING COUTING
Bahan :
Waterprofing Emulsion Kg 2.2000 37,500.00 82,500.00
Kwas Bh 0.2000 8,000.00 1,600.00
Upah Pasang = Upah Laburan Besi Ls 1.0000 13,650.00 13,650.00 13,650.00
Jumlah 97,750.00 13,650.00 111,400.00
Keuntungan maksimal 10% 11,140.00
Jumlah 122,540.00
Dibulatkan 122,540.00
5 1 M2 SCREEDING TEBAL 3 CM
Bahan :
Semen Portland zak 0.2880 66,500.00 19,152.00
Pasir Beton m3 0.0239 290,000.00 6,931.00
Tenaga Kerja :
Pekerja Oh 0.1000 138,000.00 13,800.00
Tukang Batu Oh 0.0100 158,000.00 1,580.00
Kepala Tukang Oh 0.2000 173,000.00 34,600.00
Mandor Oh 0.0100 185,000.00 1,850.00
Jumlah 26,083.00 51,830.00 77,913.00
Keuntungan maksimal 10% 7,791.30
Jumlah 85,704.30
Dibulatkan 85,704.00
6 1 M2 PASANGAN DINDING BATU TEMPLEK
Bahan :
Batu Templek m2 0.2880 78,000.00 22,464.00
Semen Portland zak 0.2350 66,500.00 15,627.50
Pasir Pasang m3 0.0350 280,000.00 9,800.00
Tenaga Kerja :
Pekerja Oh 0.6200 138,000.00 85,560.00
Tukang Batu Oh 0.3500 158,000.00 55,300.00
Kepala Tukang Oh 0.0350 173,000.00 6,055.00
Mandor Oh 0.0300 185,000.00 5,550.00
Jumlah 47,891.50 152,465.00 200,356.50
Keuntungan maksimal 10% 20,035.65
Jumlah 220,392.15
Dibulatkan 220,392.00
7 1 M2 PASANGAN DINDING BATU ALAM
Bahan :
Batu Alam m2 0.2880 75,300.00 21,686.40
Semen Portland zak 0.2350 66,500.00 15,627.50
Pasir Pasang m3 0.0350 280,000.00 9,800.00
Tenaga Kerja :
Pekerja Oh 0.6200 138,000.00 85,560.00
Tukang Batu Oh 0.3500 158,000.00 55,300.00
Kepala Tukang Oh 0.0350 173,000.00 6,055.00
Mandor Oh 0.0300 185,000.00 5,550.00
Jumlah 47,113.90 152,465.00 199,578.90
Keuntungan maksimal 10% 19,957.89
Jumlah 219,536.79
Dibulatkan 219,536.00

8 1 UNIT HANDRAILLING TANGGA


Bahan :
Besi Pipa Stainless 2" m1 25.9900 46,000.00 1,195,540.00
Besi Pipa Stainless 1" m1 2.4000 22,000.00 52,800.00
Besi Pipa Stainless 1/2" m1 25.4100 13,500.00 343,035.00
Assesoris + Pengelasan ls 1.0000 556,981.25 556,981.25
Tenaga Kerja :
Upah Pasang ls 1.0000 556,981.25 556,981.25
Jumlah 2,148,356.25 556,981.25 2,705,337.50
Keuntungan maksimal 10% 270,533.75
Jumlah 2,975,871.25
Dibulatkan 2,975,871.00
9 1 UNIT HANDRAILLING RUMP ENTRANCE
Bahan :
Besi Pipa Stainless 2" m1 5.3200 1,150.00 6,118.00
Besi Pipa Stainless 1" m1 0.4000 33,144.00 13,257.60
Besi Pipa Stainless 1/2" m1 7.2000 33,144.00 238,636.80
Assesoris + Pengelasan ls 1.0000 90,304.34 90,304.34
Tenaga Kerja :
Upah Pasang ls 1.0000 90,304.34 90,304.34
Jumlah 348,316.74 90,304.34 438,621.08
Keuntungan maksimal 10% 43,862.11
Jumlah 482,483.19
Dibulatkan 482,483.00
ANALISA BIAYA PEKERJAAN ATAP
1 1 M3 PASANGAN KONSTRUKSI KUDA - KUDA KAYU KONVENSIONAL
Bahan :
Kayu Meranti, Balok M3 1.1000 6,500,000.00 7,150,000.00 -
Besi strip tebal 5mm kg 15.0000 66,300.00 994,500.00 -
Paku 12 cm kg 1.0000 22,800.00 22,800.00 -
Tenaga Kerja :
Pekerja Oh 4.0000 138,000.00 - 552,000.00
Tukang Kayu Oh 12.0000 158,000.00 - 1,896,000.00
Kepala Tukang Kayu Oh 1.2000 173,000.00 - 207,600.00
Mandor Oh 0.2000 185,000.00 - 37,000.00
Jumlah 8,167,300.00 2,692,600.00 10,859,900.00
Keuntungan maksimal 10% 1,085,990.00
Jumlah 11,945,890.00
Dibulatkan 11,945,890.00
2 1 M3 PASANGAN KONSTRUKSI GORDENG KAYU KLS. II ( SNI 3434:2008 )
Bahan :
Kayu Meranti, Balok M3 1.1000 6,500,000.00 7,150,000.00 -
Besi strip tebal 5mm kg 15.0000 66,300.00 994,500.00 -
Paku 12 cm kg 3.0000 22,800.00 68,400.00 -
Tenaga Kerja :
Pekerja Oh 2.4000 138,000.00 - 331,200.00
Tukang Kayu Oh 7.2000 158,000.00 - 1,137,600.00
Kepala Tukang Kayu Oh 0.7200 173,000.00 - 124,560.00
Mandor Oh 0.1200 185,000.00 - 22,200.00
Jumlah 8,212,900.00 1,615,560.00 9,828,460.00
Keuntungan maksimal 10% 982,846.00
Jumlah 10,811,306.00
Dibulatkan 10,811,306.00
3 1 M2 RANGKA ATAP GENTENG PALENTONG
Bahan :
Kayu Kaso 5/7 cm M3 0.0140 4,000,000.00 56,000.00 -
Reng 2/3 M3 0.0360 4,000,000.00 144,000.00 -
Paku 5 dan 10 kg 0.2500 22,800.00 5,700.00 -
Tenaga Kerja :
Pekerja Oh 0.1000 138,000.00 - 13,800.00
Tukang Kayu Oh 0.1000 158,000.00 - 15,800.00
Kepala Tukang Kayu Oh 0.0100 173,000.00 - 1,730.00
Mandor Oh 0.0050 185,000.00 - 925.00
Jumlah 205,700.00 32,255.00 237,955.00
Keuntungan maksimal 10% 23,795.50
Jumlah 261,750.50
Dibulatkan 261,750.00
4 1 M2 Atap Pelana Rangka Atap Baja Ringan profil C75
Bahan :
Baja ringan m2 1.0000 85,000.00 85,000.00
Tenaga Kerja :
Pekerja Oh 0.1000 138,000.00 13,800.00
Tukang Kayu Oh 0.1000 158,000.00 15,800.00
Kepala Tukang Kayu Oh 0.0100 173,000.00 1,730.00
Mandor Oh 0.0050 185,000.00 925.00
Jumlah 85,000.00 32,255.00 117,255.00
Keuntungan maksimal 10% 11,725.50
Jumlah 128,980.50
Dibulatkan 128,980.00
5 1 M2 PASANG ATAP GENTENG PALENTONG
Bahan :
Genteng Palentong Bh 25.0000 1,150.00 28,750.00 -
Tenaga Kerja :
Pekerja Oh 0.1500 138,000.00 - 20,700.00
Tukang Kayu Oh 0.0750 158,000.00 - 11,850.00
Kepala Tukang Kayu Oh 0.0080 173,000.00 - 1,384.00
Mandor Oh 0.0080 185,000.00 - 1,480.00
Jumlah 28,750.00 35,414.00 64,164.00
Keuntungan maksimal 10% 6,416.40
Jumlah harga 70,580.40
Dibulatkan 70,580.00
6 1 M2 PASANG GENTENG BUBUNG PALENTONG
Bahan :
Genteng Bubung Palentong Bh 5.0000 1,150.00 5,750.00 -
Semen Portland Kg 8.0000 1,330.00 10,640.00 -
Pasir Pasang M3 0.0320 280,000.00 8,960.00 -
Tenaga Kerja :
Pekerja Oh 0.4000 138,000.00 - 55,200.00
Tukang Batu Oh 0.2000 158,000.00 - 31,600.00
Kepala Tukang Batu Oh 0.0200 173,000.00 - 3,460.00
Mandor Oh 0.0020 185,000.00 - 370.00
Jumlah 25,350.00 90,630.00 115,980.00
Keuntungan maksimal 10% 11,598.00
Jumlah harga 127,578.00
Dibulatkan 127,578.00
7 1 M' PASANG LISTPLANK 2 x 20 CM, KAYU PAPAN KLS. II
Bahan :
Kayu Kls. II , Papan M3 0.0108 5,000,000.00 54,000.00 -
Paku biasa 2" - 5" Kg 0.1000 280,000.00 28,000.00 -
Tenaga Kerja :
Pekerja Oh 0.1000 138,000.00 - 13,800.00
Tukang Kayu Oh 0.2000 158,000.00 - 31,600.00
Kepala Tukang Kayu Oh 0.0200 173,000.00 - 3,460.00
Mandor Oh 0.0050 185,000.00 - 925.00
Jumlah 82,000.00 49,785.00 131,785.00
Keuntungan maksimal 10% 13,178.50
Jumlah 144,963.50
Dibulatkan 144,960.00
8 1m3 Pasang Nok kayu bengkirai
Bahan :
Kayu bengkirai M3 1.1000 9,750,000.00 10,725,000.00 -
Besi strip Kg 15.0000 66,300.00 994,500.00 -
Paku biasa 2" - 5" Kg 0.8000 22,800.00 18,240.00
Tenaga Kerja :
Pekerja Oh 0.1000 138,000.00 - 13,800.00
Tukang Kayu Oh 0.2000 158,000.00 - 31,600.00
Kepala Tukang Kayu Oh 0.0200 173,000.00 - 3,460.00
Mandor Oh 0.0050 185,000.00 - 925.00
Jumlah 11,737,740.00 49,785.00 11,787,525.00
Keuntungan maksimal 10% 1,178,752.50
Jumlah 12,966,277.50
Dibulatkan 12,966,270.00

PEKERJAAN PLAFOND
1 1 M2 RANGKA PLAFOND BESI HOLLOW 1x20,40,2mm, modul 60x60 cm
Bahan :
Besi Hollow 20.40.2mm m1 4.0000 13,500.00 54,000.00
Assesoris ls 1.0000 13,500.00 13,500.00
Tenaga Kerja :
Tukang Besi Oh 0.2500 158,000.00 39,500.00
Kep Tukang Besi Oh 0.0250 173,000.00 4,325.00
Mandor Oh 0.0050 185,000.00 925.00
Jumlah 67,500.00 44,750.00 112,250.00
Keuntungan maksimal 10% 11,225.00
Jumlah 123,475.00
Dibulatkan 123,475.00
2 1 M2 LANGIT-LANGIT GYPSUM
Bahan :
Gypsum Lbr 0.3640 65,000.00 23,660.00
Paku 1/2 - 1" Kg 0.1100 22,800.00 2,508.00
Tenaga Kerja :
Pekerja Oh 0.1000 138,000.00 13,800.00
Tukang Kayu Oh 0.0500 158,000.00 7,900.00
Kep. Tukang kayu Oh 0.0050 173,000.00 865.00
Mandor Oh 0.0050 185,000.00 925.00
Jumlah 26,168.00 23,490.00 49,658.00
Keuntungan maksimal 10% 4,965.80
Jumlah 54,623.80
Dibulatkan 54,623.00
3 1 M2 PAS. PLAFOND GRC
Bahan :
GRC M2 1.1000 17,361.11 19,097.22
Paku 1/2" Kg 0.0100 22,800.00 228.00
Tenaga Kerja :
Pekerja Oh 0.0300 138,000.00 4,140.00
Tukang Kayu Oh 0.0700 158,000.00 11,060.00
Kep. Tukang Oh 0.0070 173,000.00 1,211.00
Mandor Oh 0.0015 185,000.00 277.50
Jumlah 19,325.22 16,688.50 36,013.72
Keuntungan maksimal 10% 3,601.37
Jumlah 39,615.09
Dibulatkan 39,615.00
4 1 M' PASANG LIST PROFIL GIFSUM 5/7 CM
Bahan :
List Gifsum 5 cm M' 1.0000 13,000.00 13,000.00
Paku Kg 0.1500 19,000.00 2,850.00
Tenaga Kerja :
Upah Pasang ls 1.0000 5,547.50 5,547.50
Jumlah 15,850.00 5,547.50 21,397.50
Keuntungan maksimal 10% 2,139.75
Jumlah 23,537.25
Dibulatkan 23,537.00
PEKERJAAN LANTAI
1 1 M2 PASANGAN LANTAI KERAMIK , UK. 30x 30 CM,
Bahan :
Ubin Keramik, uk. 30 x 30 cm dus 1.0500 50,000.00 52,500.00 -
Semen Portland Kg 10.0000 1,330.00 13,300.00 -
Pasir Pasang M3 0.0450 280,000.00 12,600.00 -
Semen Warna Kg 0.5000 14,052.00 7,026.00 -
Tenaga Kerja :
Pekerja Oh 0.7000 138,000.00 - 96,600.00
Tukang Batu Oh 0.3500 158,000.00 - 55,300.00
Kepala Tukang Batu Oh 0.0350 173,000.00 - 6,055.00
Mandor Oh 0.0350 185,000.00 - 6,475.00
Jumlah 85,426.00 164,430.00 249,856.00
Keuntungan maksimal 10% 24,985.60
Jumlah 274,841.60
Dibulatkan 274,841.00
2 1 M2 PASANGAN LANTAI KERAMIK ANTI SLIP, UK. 25 x 25 CM
Bahan :
Ubin Keramik, uk. 25 x 25 cm dus 1.0500 60,000.00 63,000.00 -
Semen Portland Kg 10.4000 1,330.00 13,832.00 -
Pasir Pasang M3 0.0450 280,000.00 12,600.00 -
Semen Warna Kg 0.5000 14,052.00 7,026.00 -
Tenaga Kerja :
Pekerja Oh 0.7000 138,000.00 - 96,600.00
Tukang Batu Oh 0.3500 158,000.00 - 55,300.00
Kepala Tukang Batu Oh 0.0350 173,000.00 - 6,055.00
Mandor Oh 0.0350 185,000.00 - 6,475.00
Jumlah 96,458.00 164,430.00 260,888.00
Keuntungan maksimal 10% 26,088.80
Jumlah 286,976.80
Dibulatkan 286,976.00
3 1 M2 PASANGAN LANTAI KERAMIK , UK. 25 x 25 CM
Bahan :
Keramik, uk. 25 x 50 cm dus 1.0000 73,000.00 73,000.00 -
Semen Portland Kg 9.3000 1,330.00 12,369.00 -
Pasir Pasang M3 0.0180 280,000.00 5,040.00 -
Semen Warna Kg 1.9400 14,052.00 27,260.88 -
Tenaga Kerja :
Pekerja Oh 0.9000 138,000.00 - 124,200.00
Tukang Batu Oh 0.4500 158,000.00 - 71,100.00
Kepala Tukang Batu Oh 0.0450 173,000.00 - 7,785.00
Mandor Oh 0.0450 185,000.00 - 8,325.00
Jumlah 117,669.88 211,410.00 329,079.88
Keuntungan maksimal 10% 32,907.99
Jumlah 361,987.87
Dibulatkan 361,987.00
PEKERJAAN KUSEN DAN ALAT PENGGANTUNG
1 1 M3 PASANGAN KUSEN PINTU & JENDELA, KAYU KELAS II
Bahan :
Kayu Meranti, Balok M3 1.2000 6,500,000.00 7,800,000.00 -
Paku kg 1.2500 22,800.00 28,500.00 -
Lem kayu Fox kg 1.0000 25,000.00 25,000.00 -
Tenaga Kerja :
Pekerja Oh 6.0000 138,000.00 - 828,000.00
Tukang Kayu Oh 18.0000 158,000.00 - 2,844,000.00
Kepala Tukang Kayu Oh 1.8000 173,000.00 - 311,400.00
Mandor Oh 0.3000 185,000.00 - 55,500.00
Jumlah 7,853,500.00 4,038,900.00 11,892,400.00
Keuntungan maksimal 10% 1,189,240.00
Jumlah 13,081,640.00
Dibulatkan 13,081,640.00
2 1 M2 PASANGAN PINTU PANIL, KAYU MERANTI
Bahan :
Kayu Meranti, Papan M3 0.0400 5,000,000.00 200,000.00 -
Lem Fox Kayu Kg 0.5000 25,000.00 12,500.00
Tenaga Kerja :
Pekerja Oh 0.5000 138,000.00 - 69,000.00
Tukang Kayu Oh 2.0000 158,000.00 - 316,000.00
Kepala Tukang Kayu Oh 0.3000 173,000.00 - 51,900.00
Mandor Oh 0.0500 185,000.00 - 9,250.00
Jumlah 212,500.00 446,150.00 658,650.00
Keuntungan maksimal 10% 65,865.00
Jumlah 724,515.00
Dibulatkan 724,515.00
3 1 M2 PASANGAN DAUN JENDELA KACA, KAYU KELAS II
Bahan :
Papan Kayu M3 0.0240 5,000,000.00 120,000.00 -
Lem Fox Kayu Kg 0.5000 25,000.00 12,500.00
Tenaga Kerja :
Pekerja Oh 0.8000 138,000.00 - 110,400.00
Tukang Kayu Oh 2.4000 158,000.00 - 379,200.00
Kepala Tukang Kayu Oh 0.2400 173,000.00 - 41,520.00
Mandor Oh 0.0400 185,000.00 - 7,400.00
Jumlah 132,500.00 538,520.00 671,020.00
Keuntungan maksimal 10% 67,102.00
Jumlah 738,122.00
Dibulatkan 738,122.00
4 1 BUAH PASANG ENGSEL PINTU 4"
Bahan :
Engsel Pintu 4" Bh 1.0000 33,000.00 33,000.00
Tenaga Kerja :
Pekerja Oh 0.0150 138,000.00 2,070.00
Tukang Kayu Oh 0.1500 158,000.00 23,700.00
Kep Tukang Kayu Oh 0.0150 173,000.00 2,595.00
Mandor Oh 0.0008 185,000.00 138.75
Jumlah 33,000.00 28,503.75 61,503.75
Keuntungan maksimal 10% 6,150.38
Jumlah 67,654.13
Dibulatkan 67,654.00
5 1 BUAH PASANG ENGSEL KUPU - KUPU
Bahan :
Engsel Kupu - Kupu Bh 1.0000 17,000.00 17,000.00
Tenaga Kerja :
Pekerja Oh 0.0100 138,000.00 - 1,380.00
Tukang Kayu Oh 0.1000 158,000.00 - 15,800.00
Kepala Tukang Kayu Oh 0.0100 173,000.00 - 1,730.00
Mandor Oh 0.0005 185,000.00 - 92.50
Jumlah 17,000.00 19,002.50 36,002.50
Keuntungan maksimal 10% 3,600.25
Jumlah 39,602.75
Dibulatkan 39,602.00
6 1 BUAH PASANG KAIT ANGIN
Bahan :
Kait Angin Bh 1.0000 18,000.00 18,000.00
Tenaga Kerja :
Pekerja Oh 0.0150 138,000.00 - 2,070.00
Tukang Kayu Oh 0.1500 158,000.00 - 23,700.00
Kepala Tukang Kayu Oh 0.0150 173,000.00 - 2,595.00
Mandor Oh 0.0080 185,000.00 - 1,480.00
Jumlah 18,000.00 29,845.00 47,845.00
Keuntungan maksimal 10% 4,784.50
Jumlah 52,629.50
Dibulatkan 52,629.00
7 1 BUAH PASANG KUNCI SILINDER + HANDLE PINTU
Bahan :
Kunci Silinder Lengkap Bh 1.0000 160,000.00 160,000.00
Tenaga Kerja :
Pekerja Oh 0.0050 138,000.00 - 690.00
Tukang Kayu Oh 0.5000 158,000.00 - 79,000.00
Kepala Tukang Kayu Oh 0.0500 173,000.00 - 8,650.00
Mandor Oh 0.0030 185,000.00 - 555.00
Jumlah 160,000.00 88,895.00 248,895.00
Keuntungan maksimal 10% 24,889.50
Jumlah 273,784.50
Dibulatkan 273,784.00
8 1 M2 PASANGAN KACA RYBEN , T = 5 MM
Bahan :
Kaca tebal 5 mm M2 1.1000 150,000.00 165,000.00 -
Tenaga Kerja :
Pekerja Oh 0.0150 138,000.00 - 2,070.00
Tukang Kayu Oh 0.1500 158,000.00 - 23,700.00
Kepala Tukang Kayu Oh 0.0150 173,000.00 - 2,595.00
Mandor Oh 0.0008 185,000.00 - 138.75
Jumlah 165,000.00 28,503.75 193,503.75
Keuntungan maksimal 10% 19,350.38
Jumlah 212,854.13
Dibulatkan 212,854.00
9 1 M2 PASANGAN KACA ES , T = 3 MM
Bahan :
Kaca Es 3 mm M2 1.1000 140,000.00 154,000.00 -
Tenaga Kerja :
Pekerja Oh 0.0150 138,000.00 - 2,070.00
Tukang Kayu Oh 0.1500 158,000.00 - 23,700.00
Kepala Tukang Kayu Oh 0.0150 173,000.00 - 2,595.00
Mandor Oh 0.0008 185,000.00 - 138.75
Jumlah 154,000.00 28,503.75 182,503.75
Keuntungan maksimal 10% 18,250.38
Jumlah 200,754.13
Dibulatkan 200,754.00
PEKERJAAN ELEKTRIKAL
1 1 TTK PAS.TITIK LAMPU / CAHAYA
Bahan :
NYM 3 x 2,5 m' 8.9310 12,000.00 107,172.00
Solatif kabel roll 0.3330 8,000.00 2,664.00
Pipa Kabel btg 1.5000 21,910.00 32,865.00
T-Dus bh 1.0000 3,500.00 3,500.00
Inbow-dus bh 1.0000 4,500.00 4,500.00
Tenaga Kerja :
Upah Kerja pasang ls 1.0000 4,991.00 4,991.00
Jumlah 150,701.00 4,991.00 155,692.00
Keuntungan maksimal 10% 15,569.20
Jumlah 171,261.20
Dibulatkan 171,261.00
2 1 TTK PAS.TITIK DAYA / STOP KONTAK
Bahan :
NYM 3 x 2,5 m' 10.3500 12,000.00 124,200.00
Solatif kabel roll 0.3330 8,000.00 2,664.00
Pipa Kabel btg 1.5000 21,910.00 32,865.00
T-Dus bh 1.0000 3,500.00 3,500.00
Inbow-dus bh 1.0000 4,500.00 4,500.00
Tenaga Kerja :
Upah Kerja pasang ls 1.0000 4,991.00 4,991.00
Jumlah 167,729.00 4,991.00 172,720.00
Keuntungan maksimal 10% 17,272.00
Jumlah 189,992.00
Dibulatkan 189,992.00
3 1 BH PAS. LAMPU TL 1 X 18 WATT
Bahan :
Lampu TL 18 watt + assesoris bh 1.0000 120,000.00 120,000.00
Trapo Philip+ TKI " bh 1.0000 110,000.00 110,000.00
Alat Bantu lot 0.0250 10,000.00 250.00
Tenaga Kerja :
Upah Kerja pasang lot 1.0000 24,000.00 24,000.00
Jumlah 230,250.00 24,000.00 254,250.00
Keuntungan maksimal 10% 25,425.00
Jumlah 279,675.00
Dibulatkan 279,675.00
4 1 BH PAS. LAMPU DOWNLIGHT 15 WATT
Bahan :
Lampu SL 15 watt bh 1.0000 110,000.00 110,000.00
Fiting Lampu DL sek. Panasonic bh 1.0000 17,500.00 17,500.00
Alat Bantu lot 0.0250 10,000.00 250.00
Tenaga Kerja :
Upah Kerja pasang lot 1.0000 12,775.00 12,775.00
Jumlah 127,750.00 12,775.00 140,525.00
Keuntungan maksimal 10% 14,052.50
Jumlah 154,577.50
Dibulatkan 154,577.00
5 1 BH PAS. LAMPU SL 15 WATT
Bahan :
Lampu SL LED 15 watt bh 1.0000 110,000.00 110,000.00
Alat Bantu lot 0.0250 10,000.00 250.00
Tenaga Kerja :
Upah Kerja pasang lot 1.0000 11,025.00 11,025.00
Jumlah 110,250.00 11,025.00 121,275.00
Keuntungan maksimal 10% 12,127.50
Jumlah 133,402.50
Dibulatkan 133,402.00
6 1 BH PAS. STOP KONTAK
Bahan :
Stop Kontak sek. Panasonic bh 1.0000 33,000.00 33,000.00
Alat Bantu lot 1.0000 1,000.00 1,000.00
Tenaga Kerja :
Upah Kerja pasang lot 1.0000 3,400.00 3,400.00
Jumlah 34,000.00 3,400.00 37,400.00
Keuntungan maksimal 10% 3,740.00
Jumlah 41,140.00
Dibulatkan 41,140.00
7 1 BH PAS. SAKLAR TUNGGAL, sek. Panasonic
Bahan :
Saklar Tunggal sek. Panasonic bh 1.0000 22,500.00 22,500.00
Alat Bantu lot 1.0000 1,000.00 1,000.00
Tenaga Kerja :
Upah Kerja pasang lot 1.0000 2,350.00 2,350.00
Jumlah 23,500.00 2,350.00 25,850.00
Keuntungan maksimal 10% 2,585.00
Jumlah 28,435.00
Dibulatkan 28,435.00
8 1 BH PAS. SAKLAR GANDA, sek. Panasonic
Bahan :
Saklar Ganda sek. Panasonic bh 1.0000 27,500.00 27,500.00
Alat Bantu lot 1.0000 1,000.00 1,000.00
Tenaga Kerja :
Upah Kerja pasang lot 1.0000 2,850.00 2,850.00
Jumlah 28,500.00 2,850.00 31,350.00
Keuntungan maksimal 10% 3,135.00
Jumlah 34,485.00
Dibulatkan 34,485.00
PEKERJAAN MEKANIKAL
1 MEMASANG 1 M' PIPA PVC. TYPE AW, DIA 1/2"
Bahan :
Pipa PVC M' 1.2000 6,573.00 7,887.60 2,850.00
Perlengkapan ( 35% x Harga Pipa ) Ls 1.0000 2,300.55 2,300.55
Tenaga Kerja :
Pekerja Oh 0.0360 5,547.50 - 199.71
Tukang Pipa Oh 0.0600 158,000.00 - 9,480.00
Kepala Tukang Pipa Oh 0.0060 173,000.00 - 1,038.00
Mandor Oh 0.0018 185,000.00 - 333.00
Jumlah 10,188.15 11,050.71 21,238.86
Keuntungan maksimal 10% 2,123.89
Jumlah 23,362.75
Dibulatkan 23,362.00
2 MEMASANG 1 M' PIPA PVC. TYPE AW, DIA 3"
Bahan :
Pipa PVC M' 1.2000 49,614.00 59,536.80 -
Perlengkapan ( 35% x Harga Pipa ) Ls 1.0000 17,364.90 17,364.90 -
Tenaga Kerja :
Pekerja Oh 0.0810 5,547.50 - 449.35
Tukang Pipa Oh 0.1350 158,000.00 - 21,330.00
Kepala Tukang Pipa Oh 0.0135 173,000.00 - 2,335.50
Mandor Oh 0.0041 185,000.00 - 758.50
Jumlah 76,901.70 24,873.35 101,775.05
Keuntungan maksimal 10% 10,177.50
Jumlah 111,952.55
Dibulatkan 111,952.00
3 MEMASANG 1 M' PIPA PVC. TYPE AW, DIA 4"
Bahan :
Pipa PVC M' 1.2000 70,830.00 84,996.00 -
Perlengkapan ( 35% x Harga Pipa ) Ls 1.0000 24,790.50 24,790.50 -
Tenaga Kerja :
Pekerja Oh 0.0810 5,547.50 - 449.35
Tukang Pipa Oh 0.1350 158,000.00 - 21,330.00
Kepala Tukang Pipa Oh 0.0135 173,000.00 - 2,335.50
Mandor Oh 0.0041 185,000.00 - 758.50
Jumlah 109,786.50 24,873.35 134,659.85
Keuntungan maksimal 10% 13,465.98
Jumlah 148,125.83
Dibulatkan 148,125.00
4 MEMASANG 1 BUAH CLOSET JONGKOK PORSELEN
Bahan :
Closet Jongkok, American Standart unit 1.0000 350,000.00 350,000.00 -
Semen Portland kg 6.0000 1,330.00 7,980.00 -
Pasir Pasang m3 0.0100 280,000.00
Tenaga Kerja :
Pekerja Oh 1.0000 5,547.50 - 5,547.50
Tukang Batu Oh 1.5000 158,000.00 - 237,000.00
Kepala Tukang Batu Oh 0.1500 173,000.00 - 25,950.00
Mandor Oh 0.1600 185,000.00 - 29,600.00
Jumlah 357,980.00 298,097.50 656,077.50
Keuntungan maksimal 10% 65,607.75
Jumlah 721,685.25
Dibulatkan 721,685.00
5 MEMASANG 1 BUAH CLOSET DUDUK
Bahan :
Closet Jongkok, American Standart unit 1.0000 1,400,000.00 1,400,000.00 -
Perlengkapan ls 0.0600 1,400,000.00 84,000.00 -
Tenaga Kerja :
Pekerja Oh 3.3000 5,547.50 - 18,306.75
Tukang Batu Oh 1.1000 158,000.00 - 173,800.00
Kepala Tukang Batu Oh 0.0100 173,000.00 - 1,730.00
Mandor Oh 0.1600 185,000.00 - 29,600.00
Jumlah 1,484,000.00 223,436.75 1,707,436.75
Keuntungan maksimal 10% 170,743.68
Jumlah 1,878,180.43
Dibulatkan 1,878,180.00
PEKERJAAN PENGECATAN
1 1 M2 MENGEROK PERMUKAAN CAT TEMBOK LAMA
Bahan :
Soda Api Kg 0.0500 30,000.00 1,500.00
Tenaga Kerja :
Pekerja Oh 0.1500 5,547.50 - 832.13
Mandor Oh 0.0025 185,000.00 - 462.50
Jumlah 1,500.00 1,294.63 2,794.63
Keuntungan maksimal 10% 279.46
Jumlah 3,074.09
Dibulatkan 3,074.00
2 1 M2 PENGECATAN BIDANG TEMBOK BARU DENGAN PROPAN, 2X LAPIS CAT PENUTUP
Bahan :
Plamur Kg 0.1200 19,884.00 2,386.08
Cat Dasar Kg 0.1000 5,880.00 588.00
Cat Penutup Kg 0.2600 22,000.00 5,720.00
Tenaga Kerja :
Pekerja Oh 0.0200 5,547.50 110.95
Tukang Cat Oh 0.0630 158,000.00 9,954.00
Kep Tukang Cat Oh 0.0063 173,000.00 1,089.90
Mandor Oh 0.0030 185,000.00 555.00
Jumlah 8,694.08 11,709.85 20,403.93
Keuntungan maksimal 10% 2,040.39
Jumlah 22,444.32
Dibulatkan 22,444.00
3 1 M2 PENGECATAN PLAFOND BARU DENGAN PROPAN, 2X LAPIS CAT PENUTUP
Bahan :
Plamir Kg 0.1000 19,884.00 1,988.40
Cat Dasar Kg 0.1000 19,884.00 1,988.40
Cat Penutup, 2x Kg 0.2800 22,000.00 6,160.00
Tenaga Kerja :
Pekerja Oh 0.0300 5,547.50 166.43
Tukang Cat Oh 0.0750 158,000.00 11,850.00
Kep Tukang Cat Oh 0.0075 173,000.00 1,297.50
Mandor Oh 0.0030 185,000.00 555.00
Jumlah 10,136.80 13,868.93 24,005.73
Keuntungan maksimal 10% 2,400.57
Jumlah 26,406.30
Dibulatkan 26,406.00
4 1 M2 PENGECATAN KAYU BIDANG BARU DENGAN CAT ANTI RAYAP, 2X
Bahan :
Cat Kayu Kg 0.3500 30,000.00 10,500.00
Tenaga Kerja :
Pekerja Oh 0.0525 5,547.50 291.24
Tukang Cat Oh 0.0780 158,000.00 12,324.00
Kep Tukang Cat Oh 0.0030 173,000.00 519.00
Mandor Oh 0.0012 185,000.00 222.00
Jumlah 10,500.00 13,356.24 23,856.24
Keuntungan maksimal 10% 2,385.62
Jumlah 26,241.87
Dibulatkan 26,241.00
5 1 M2 LABURAN BIDANG KAYU DENGAN POLITUR
Bahan :

Politur L 0.150 70,000.00 10,500.00 -

Politur Jadi L 0.372 70,000.00 26,040.00 -

Ampelas Lbr 2.000 5,880.00 11,760.00 -


Tenaga Kerja :
Pekerja Oh 0.0400 5,547.50 - 221.90
Tukang Cat / Pelitur Oh 0.0600 158,000.00 - 9,480.00
Kepalla Tukang Cat / Pelitur Oh 0.0160 173,000.00 - 2,768.00
Mandor Oh 0.0030 185,000.00 - 555.00
Jumlah 48,300.00 13,024.90 61,324.90
Keuntungan maksimal 10% 6,132.49
Jumlah 67,457.39
Dibulatkan 67,457.00
6 1 M2 PAS. PAVING BLOK NATURAL TEBAL 8 cm
Bahan :
Paving Blok natural tebal 8 cm M2 1.0000 175,000.00 175,000.00
Pasir Beton M3 0.1000 290,000.00 29,000.00 PAV
Tenaga Kerja :
Pekerja Org 0.2500 138,000.00 - 34,500.00
Tukang Batu Org 0.5000 158,000.00 - 79,000.00
Kepala Tukang Batu Org 0.0250 173,000.00 - 4,325.00
Mandor Org 0.0030 185,000.00 - 555.00
Jumlah 204,000.00 118,380.00 322,380.00
Keuntungan maksimal 10% 32,238.00
Jumlah 354,618.00
Dibulatkan 354,618.00
7 1 M3 URUGAN PASIR ( SNI. Edisi Rev. 2005 )
Bahan :
Pasir urug M3 1.2000 270,000.00 324,000.00 -
Tenaga Kerja :
Pekerja Oh 0.3000 138,000.00 - 41,400.00
Mandor Oh 0.0100 185,000.00 - 1,850.00
Jumlah 324,000.00 43,250.00 367,250.00
Keuntungan maksimal 10% 36,725.00
Jumlah 403,975.00
Dibulatkan 403,975.00
8 1 M3 URUGAN SIRTU PADAT UNTUK PENINGGIAN LANTAI BANGUNAN ( SNI. Edisi Rev. 2008 )
Bahan :
Sirtu M3 1.0000 210,000.00 210,000.00 -
Tenaga Kerja :
Pekerja Oh 0.2500 138,000.00 - 34,500.00
Mandor Oh 0.0250 185,000.00 - 4,625.00
Jumlah 210,000.00 39,125.00 249,125.00
Keuntungan maksimal 10% 24,912.50
Jumlah 274,037.50
Dibulatkan 274,037.00
9 PEMBUATAN SUMUR RESAPAN
Galian Tanah m3 5.087 118,930.00 604,973.12
Pasangan Buis Beton dia 150 berlubang bh 4.000 500,000.00 2,000,000.00
Pasang Ijuk m2 0.610 35,000.00 21,364.56
Batukali m3 1.526 264,000.00 402,874.56
Jumlah 3,029,212.24 3,029,212.24
Keuntungan maksimal 10% 302,921.22
Jumlah 3,332,133.47
Dibulatkan 3,332,133.00
10 1 M' PEMBUATAN PAGAR BETAWI t= 90cm
Bahan :
Pagar Kayu Betawi t=60mm Btg 1.2500 55,000.00 68,750.00
Kayu 5/7 m3 0.0720 4,000,000.00 288,000.00
Paku biasa 2" - 5" kg 0.0600 22,800.00 1,368.00
Residu liter 0.4500 8,910.00 4,009.50
Tenaga Kerja :
Pekerja Oh 0.2000 138,000.00 27,600.00
Tukang Kayu Oh 0.4000 158,000.00 63,200.00
Kepala Tukang Kayu Oh 0.0200 173,000.00 3,460.00
Mandor Oh 0.0200 185,000.00 3,700.00
Jumlah 362,127.50 97,960.00 460,087.50
Keuntungan maksimal 10% 46,008.75
Jumlah 506,096.25
Dibulatkan 506,096.00
DAFTAR HARGA SATUAN BAHAN BANGUNAN

NO. JENIS BAHAN BANGUNAN SAT HARGA SATUAN


Rp.
1 2 3 4
A. AGREGAT KASAR, BAHAN PEREKAT & BAHAN JADINYA
1 Pasir Urug m³ 270,000.00
2 Tanah Urug m³ 240,000.00
3 Pasir Pasang m³ 280,000.00
4 Pasir Beton m³ 290,000.00
5 Batu Belah Pondasi m³ 325,000.00
6 Batu Koral Beton Kali m³ 264,000.00
7 Bata Merah Bakar Kelas - I bh 650.00
8 Semen Portland zak 66,500.00
9 Semen Warna kg 14,052.00
10 Sirtu m2 210,000.00
11 Batu Templek m2 78,000.00
12 Batu Andesit Susun Sirih 5×40 m2 75,300.00

Paving Blok natural tebal 8 cm m2 175,000.00


Air ltr 50.00
B. BAHAN FINISHING :
LABURAN, PENGISI DAN ALATNYA
1 Plamir Tembok kg 19,884.00
2 Cat Dasar Tembok kg 30,000.00
3 Cat Tembok Propan kg 22,000.00
4 Waterprofing Emulsion kg 37,500.00
5 Rool Cat bh 51,048.00
6 Ampelas lbr 5,880.00
7 Minyak Bekisting ltr 21,876.00
8 Cat kayu Anti rayap kg 30,000.00
9 Cat Politure Liter 70,000.00

C. BAHAN KAYU BERIKUT BAHAN JADINYA


1 Kayu balok Borneo super M³ 5,907,324.00
2 Papan Bekisting Kayu papan Albasia M³ 2,354,760.00
3 Dolken dia 8 s/d 10 cm btg 39,240.00
4 Kayu kaso Borneo , uk. 5/7 M³ 4,000,000.00
5 Balok Kayu Meranti M3 6,500,000.00
6 Papan Kayu Meranti M3 5,000,000.00
7 Balok Kayu Kls. II M3 1,500,000.00
8 Kayu bengkirai M3 9,750,000.00

D. BAHAN PENUTUP RANGKA PLAFOND


1 Gipsum 120 x 240 cm tebal 9mm lbr 65,000.00
2 List Gipsump C - 7 Profil M¹ 13,000.00
3 Lambersering ( kayu solid ) m2 240,000.00
4 GRC Lbr 50,000.00
-
E. BAHAN KAYU LAPIS -
1 Teakwood 4 mm 120 x 240 lbr 160,440.00
2 Triplek 4 mm 120 x 240 lbr 77,280.00
3 Multiplek 12 mm 120 x 240 lbr 182,316.00
4 Plywood uk. 1,22 x 2,44 (m), tebal 9 mm lbr 170,000.00
5 HPL lbr 216,000.00
-
F. BAHAN LANTAI DAN PELAPIS DINDING -
1 Keramik dinding 25/25, corak warna, M² 73,000.00
2 Keramik lantai 25 x 25 warna /corak, anti slip M² 60,000.00
3 keramik 30x30 polos M² 50,000.00
4 Step Noshing Granito 10 X 60 bh 38,400.00
5 Saluran air beton ( U-DITCH ) 20 x 50 tebal 4 cm bh 42,000.00
-
G. BAHAN SALURAN AIR BERSIH DAN KOTOR -
1 Pipa pralon PVC. ( AW ) dia 1/2 ", sekulaitas Maspion btg 26,292.00
2 Pipa pralon PVC. ( AW ) dia 3/4 ", sekulaitas Maspion btg 31,152.00
3 Pipa pralon PVC. ( AW ) dia 1 1/2 ", sekulaitas Maspion btg 73,560.00
4 Pipa pralon PVC. ( AW ) dia 2 ", sekulaitas Maspion btg 108,060.00
5 Pipa pralon PVC. ( AW ) dia 2 1/2 ", sekulaitas Maspion btg 140,760.00
6 Pipa pralon PVC. ( AW ) dia 3 ", sekulaitas Maspion btg 198,456.00
7 Pipa pralon PVC. ( AW ) dia 4 ", sekulaitas Maspion btg 283,320.00
-
H. BAHAN LOGAM -
1 Baja Tulangan U-24, polos kg 12,000.00
2 Besi Hollow 2 x 4 tebal 0,2 mm btg 54,000.00
3 Besi Strip, uk. 3 x 30 mm x 6 m ( 4,21 Kg ) btg 66,300.00
4 Kawat beton kg 24,624.00
5 Pipa Besi Stainlees Dia. 1/2" tebal 0.8mm m1 13,500.00
6 Pipa Besi Stainlees Dia. 1" tebal 0.8mm m1 22,000.00
7 Pipa Besi Stainlees Dia. 2" tebal 0.8mm m1 46,000.00
10 Seng plat BJLS 25 uk. 90 x 180 cm lbr 68,184.00
11 Almunium plat 0,50 mm ( 1.00 x 2.00 ) lbr 84,000.00
12 Almunium profil uk.3 " - 4.00 m ( bahan kusen ) ex. EDICO Warna btg 336,000.00
13 Alumunium daun pintu/Jendela M¹ 66,000.00
14 Floor Hinge Set 840,000.00
15 Skruf Fixer bh 10,932.00
16 Karet m1 4,200.00
17 Sealent Alumunium ke Kaca Tube 33,144.00
18 Sealent Alumunium ke dinding Tube 33,144.00
19 Bubungan genteng palentong bh 1,150.00
20 Kaca Ryben 5 mm m2 150,000.00
21 Kaca Es 3mm m2 140,000.00
22 Lem Fox Kayu Kg 25,000.00
23 Besi Wiremesh M8 uk. 2,1 x 5,4 m Lbr 610,000.00
24 Metal Deck tebal 0,7 mm m2 120,000.00
25 Seng gelombang t=0.2 mm lbr 48,000.00

I. BAHAN PAKU DAN MUR BAUD


1 Paku 1 s/d 2½ cm kg 22,800.00

J. BAHAN ELEKTRIKAL
1 Lampu pijar 25 watt s/d 100 watt bh 35,000.00
2 Lampu TL LED 18 watt bh 120,000.00
3 Down Light + SL LED 15 watt bh 110,000.00
4 Kabel NYM 3x2,5 qmm "Prime / Eterna" M¹ 12,000.00
5 Isolasi besar rol 8,000.00
6 Pipa Kabel Listrik btg 21,910.00
7 T-Dus bh 3,500.00
8 Inbow Dus bh 4,500.00
9 Fitting Lampu DL bh 17,500.00
10 Saklar Tunggal bh 22,500.00
11 Saklar Ganda bh 27,500.00
12 Stop Kontak bh 33,000.00
13 Trapo Philip+ TKI " bh 110,000.00

K. BAHAN ALAT PENGGANTUNG / KUNCI


1 Lever Hendle sek. Dekson + kunci psg 216,000.00
2 Sloot Jendela Tunggal bh 13,260.00
3 Engsel Casment sek. Dekson psg 113,400.00
4 Engsel Kupu - Kupu bh 17,000.00
5 Kait Angin bh 18,000.00
6 Espagnolet bh 65,000.00
7 Kunci Silinder + Handle bh 160,000.00
4 Engsel pintu Almunium ( Floor Hinge ), ex DORMA, uk. Pintu Standar bh 33,000.00
Kaca Ryben T=5mm m2 75,000.00

L. ALAT SANITASI
1 Closet Jongkok , Amerikan Standar unit 350,000.00
2 Washtafel Gantung Studio 45, American Standar unit 600,000.00
3 Kran Dual Flow PALOMA FCSZ 6141 bh 700,000.00
4 Closet Duduk, American Standart bh 1,400,000.00
5 Safety Belt bh 60,000.00
M. ALAT PELINDUNG DIRI
1 Sepatu Boot bh 114,000.00
2 Helm Safety bh 60,000.00
3 Rompi Jaring Proyek bh 14,400.00
4 Sarung Tangan Proyek bh 6,000.00
5 Safety Belt bh 72,000.00
-
1 Angkutan Barang dari dermaga ke pulau ton/m3/mil 9,600.00
2 Tarif muat dari dermaga ke kapal, kapal ke lokasi ton/m3 72,000.00
3 Tarif Bongkar dari kapal ke lokasi ton/m3 72,000.00
4 Tarif Pengemasan dan pengisian ton/m3 42,000.00
DAFTAR HARGA SATUAN BAHAN, UPAH DAN SEWA ALAT

KETERANGAN
NO. JENIS UPAH/BAHAN/SEWA ALAT SATUAN HARGA SATUAN

1 2 3 4 5
UPAH
1 PEKERJA Orang/Hari 138,000.00
2 TUKANG GALI Orang/Hari 158,000.00
3 TUKANG BATU Orang/Hari 158,000.00
4 KEPALA TUKANG BATU Orang/Hari 173,000.00
5 TUKANG KAYU Orang/Hari 158,000.00
6 KEPALA TUKANG KAYU Orang/Hari 173,000.00
7 TUKANG CAT / PELITUR Orang/Hari 158,000.00
8 KEPALA TUKANG CAT / PELITUR Orang/Hari 173,000.00
9 TUKANG BESI BETON Orang/Hari 158,000.00
10 KEPALA TUKANG BESI BETON Orang/Hari 173,000.00
11 TUKANG BESI PROFIL Orang/Hari 158,000.00
12 KEPALA TUKANG BESI PROFIL Orang/Hari 173,000.00
13 MANDOR Orang/Hari 185,000.00
14 SUPIR Orang/Hari 173,000.00
15 OPERATOR Orang/Hari 173,000.00

MATERIAL ALAM
1 Tanah Timbun (Lokal) M3 Rp 27,500.00
2 Tanah Timbun (Didatangkan) M3 Rp 61,050.00 Rp 40,000.00
3 Pasir Urug M3 Rp 116,050.00 Rp 81,250.00
4 Pasir Beton M3 Rp 290,000.00 Rp 125,000.00
5 Batu Kerikil M3 Rp 264,000.00 Rp 325,000.00
6 Batu Pecah / Split (Agregat Kasar) M3 Rp 659,175.00 Rp 562,500.00
8 Asphalt Emulsi (Dingin) Kilogram Rp 8,500.25
9 Filler (Agregat Halus) M3 Rp 671,000.00 Rp 562,500.00
10 Batu Kali M3 Rp 444,950.00 Rp 350,000.00
11 Sirtu / Urugan Pilihan M3 Rp 233,200.00 Rp 175,000.00
12 Base-A M3 Rp 547,800.00 Rp 435,000.00
13 Base-B M3 Rp 523,600.00 Rp 415,000.00
14 Base-C M3 Rp 354,200.00 Rp 275,000.00
MATERIAL BESI
1 Kawat Pengikat Kilogram Rp 19,807.15 Rp 20,000.00
2 Kawat Berduri Kilogram Rp 16,507.15 Rp 3,500.00
3 Besi Beton Polos Kilogram Rp 9,790.00 Rp 7,500.00

1 Paku Biasa 2" - 5" Kilogram Rp 22,800.00 Rp 18,000.00


2 Paku Putih Kilogram Rp 19,848.40 Rp 20,000.00
3 Paku Tripleks Kilogram Rp 26,448.40 Rp 15,000.00
4 Paku Beton Kilogram Rp 33,121.00 Rp 36,000.00
5 Paku Seng Kilogram Rp 33,143.00 Rp 28,000.00
6 Paku Asbes Kilogram Rp 30,057.50 Rp 25,000.00
7 Paku Sekrup Kilogram Rp 291.50 Rp 100.00
8 Baut 3/4" Panjang 4" Kilogram Rp 4,471.50 Rp 4,000.00
9 Baut 1/2" Panjang 4" Kilogram Rp 2,271.50 Rp 2,000.00
10 Teralis Besi Plat / Siku Kilogram Rp 254,650.00 Rp 225,000.00
11 Kawat Las Kilogram Rp 24,557.50 Rp 20,000.00
12 Besi Plat Strip Kilogram Rp 3,987.50 Rp 3,000.00
13 Geotextile Soilmat 15 Kilogram Rp 13,365.00 Rp 10,750.00
14 Geotextile Soilmat 20 Kilogram Rp 16,995.00 Rp 13,750.00
15 Geotextile Soilmat 25 Kilogram Rp 19,415.00 Rp 15,750.00
16 Kawat Beton Kilogram Rp 18,571.00
17 besi beton polos Kilogram Rp 16,660.20
18 Allumunium Foil M2 Rp 3,500.00

MATERIAL CAMPURAN
1 Semen Portland (50 KG) Kilogram Rp 1,330.00 Rp 1,160.00
2 Semen Putih/Warna Kilogram Rp 2,684.00 Rp 2,500.00
3 Lem Fox Putih Kilogram Rp 27,535.75 Rp 29,000.00
4 Lem Fox Kuning Kilogram Rp 38,786.00 Rp 25,000.00
5 Batu Bata Pres (5 x 11 x 22) Buah Rp 1,078.00 Rp 850.00
6 Batu Bata Biasa (5 x 11 x 22) Buah Rp 951.50 Rp 750.00
7 Batako Buah Rp 1,642.30 Rp 1,200.00
8 Paving Block Buah Rp 1,685.75 Rp 1,500.00
9 Kawat Harmonika Gaas M2 Rp 9,086.00 Rp 10,000.00
10 Kawat Nyamuk / Kasa Besi M2 Rp 16,786.00 Rp 17,000.00
11 Kawat Nyamuk / Kasa Plastik M2 Rp 20,086.00 Rp 20,000.00
12 Glass Block Buah Rp 22,035.75 Rp 20,000.00
13 Tiang Pancang Beton Pra Tekan Ø 35 cm p. 6 m (klas M' Rp 342,127.50 Rp 282,750.00
14 Tiang Pancang Beton Pra Tekan Ø 35 cm p. 9 m (klas M' Rp 313,027.00 Rp 258,700.00
15 Tiang Pancang Beton Pra Tekan Ø 35 cm p. 10 m (kla M' Rp 307,521.50 Rp 254,150.00
16 Tiang Pancang Beton Pra Tekan Ø 35 cm p. 12 m (kla M' Rp 298,870.00 Rp 247,000.00
17 Tiang Pancang Beton Pra Tekan Ø 40 cm p. 6 m (klas M' Rp 426,283.00 Rp 352,300.00
18 Tiang Pancang Beton Pra Tekan Ø 40 cm p. 9 m (klas M' Rp 390,104.00 Rp 322,400.00
19 Tiang Pancang Beton Pra Tekan Ø 40 cm p. 10 m (kla M' Rp 382,239.00 Rp 315,900.00
20 Tiang Pancang Beton Pra Tekan Ø 40 cm p. 12 m (kla M' Rp 372,014.50 Rp 307,450.00
21 Sheet Pile Type W.325.A.1000 Pjg 9 m - 14 m M' Rp 1,374,923.00 Rp 1,136,300.00
22 Sheet Pile Type W.325.B.1000 Pjg 9 m - 14 m M' Rp 1,438,448.00 Rp 1,188,800.00
23 Tiang Pancang Baja Ø 8" Tebal 5.16 mm Panjang 6 m M' Rp 790,468.80 Rp 653,280.00
24 Tiang Pancang Baja Ø 8" Tebal 6.35 mm Panjang 6 m M' Rp 967,032.00 Rp 799,200.00
25 Tiang Pancang Baja Ø 8" Tebal 8.18 mm Panjang 6 m M' Rp 1,234,200.00 Rp 1,020,000.00
26 Tiang Pancang Baja Ø 10" Tebal 5.16 mm Panjang 6 M' Rp 990,264.00 Rp 818,400.00
27 Tiang Pancang Baja Ø 10" Tebal 6.35 mm Panjang 6 M' Rp 1,210,968.00 Rp 1,000,800.00
28 Tiang Pancang Baja Ø 10" Tebal 8.18 mm Panjang 6 M' Rp 1,751,112.00 Rp 1,447,200.00

MINYAK
1 Minyak Solar Liter Rp 6,910.29 Rp 6,282.08
2 Minyak Pelumas / Oli Liter Rp 27,500.00 Rp 25,000.00
3 Minyak Bekisting Liter Rp 21,876.00 Rp 5,000.00
5 Minyak Tanah / Kerosene Liter Rp 7,150.00 Rp 6,500.00
MATEIAL LANTAI
1 Keramik 10 x 20 Kualitas Standar (Garuda) Buah Rp 1,465.75 Rp 940.00
2 Keramik 20 x 20 Kualitas Standar (Garuda) Buah Rp 2,601.50 Rp 2,000.00
3 Keramik 20 x 25 Kualitas Standar (Garuda) Buah Rp 3,269.75 Rp 2,500.00
4 Keramik 30 x 30 Kualitas Standar (Garuda) Buah Rp 6,193.00 Rp 5,000.00
5 Keramik 40 x 40 Kualitas Standar (Garuda) Buah Rp 12,498.75 Rp 10,600.00
6 Keramik 60 x 60 Kualitas Standar (Garuda) Buah Rp 40,089.50 Rp 40,000.00
7 Keramik 10 x 20 Kualitas Sedang (KIA/IKAD) Buah Rp 1,905.75 Rp 1,700.00
8 Keramik 20 x 20 Kualitas Sedang (KIA/IKAD) Buah Rp 2,849.00 Rp 2,520.00
9 Keramik 20 x 25 Kualitas Sedang (KIA/IKAD) Buah Rp 3,737.25 Rp 3,000.00
10 Keramik 30 x 30 Kualitas Sedang (KIA/IKAD) Buah Rp 7,183.00 Rp 6,000.00
11 Keramik 40 x 40 Kualitas Sedang (KIA/IKAD) Buah Rp 15,578.75 Rp 12,000.00
12 Keramik 60 x 60 Kualitas Sedang (KIA/IKAD) Buah Rp 55,357.50 Rp 43,000.00
13 Keramik 10 x 20 Kualitas Baik (ROMAN) Buah Rp 2,161.50 Rp 1,500.00
14 Keramik 20 x 20 Kualitas Baik (ROMAN) Buah Rp 8,871.50 Rp 8,000.00
15 Keramik 20 x 25 Kualitas Baik (ROMAN) Buah Rp 11,107.25 Rp 10,000.00
16 Keramik 30 x 30 Kualitas Baik (ROMAN) Buah Rp 22,143.00 Rp 20,000.00
17 Keramik 40 x 40 Kualitas Baik (ROMAN) Buah Rp 33,178.75 Rp 43,000.00
18 Keramik 60 x 60 Kualitas Baik (ROMAN) Buah Rp 62,089.50 Rp 45,000.00
19 Granit 30 x 30 (NIRO GRANIT) Buah Rp 28,072.00 Rp 25,000.00
20 Granit 40 x 40 (NIRO GRANIT) Buah Rp 44,572.00 Rp 34,000.00
21 Granit 60 x 60 (NIRO GRANIT) Buah Rp 68,821.50 Rp 55,000.00
22 Batu Tempel (ex : Candi 20 x 20) M2 Rp 177,787.50 Rp 120,000.00

MATEIAL KAYU
1 Dolken dia 8 s/d 10 cm btg Rp 39,240.00
2 Kayu kaso Borneo , uk. 5/7 M³ Rp 4,000,000.00
3 Balok Kayu Meranti M³ Rp 6,500,000.00
4 Papan Kayu Meranti M³ Rp 5,000,000.00
5 Balok Kayu Kls. II M³ Rp 1,500,000.00
6 Papan Kayu Kls. II M³ Rp 1,000,000.00
7 Kayu Balok 6/12 Bengkirai kelas I M³ Rp 9,750,000.00
8 Papan 3/20 Bengkirai kelas I M³ Rp 9,750,000.00
9 Papan Bekisting Kayu papan Albasia M³ Rp 2,354,760.00 Rp 1,400,000.00
10 Kayu Bakar M3 Rp 252,780.00 Rp 210,000.00
11 Bantalan Melting (Batang Kelapa) M' Rp 44,000.00 Rp 20,000.00
12 Kayu Pandal Penyirih Ø 12-15 CM M' Rp 3,663.00 Rp 2,500.00
13 Cerocok Bakau Panjang 5 M M' Rp 2,123.00 Rp 1,500.00
14 Cerocok Bakau Panjang 6 M M' Rp 2,233.00 Rp 2,000.00
15 Cerocok Bakau Panjang 7 M M' Rp 2,893.00 Rp 2,250.00
16 Perancah / Dolken Ø 8-10 Panjang 4 M' Batang Rp 6,468.00
17 Kayu Motif khas Betawi M² Rp 715,000.00
18 Atap sirap / m2 Rp 175,000.00
19 Atap sirap / buah Rp 2,500.00
20 Genteng Beton buah Rp 13,700.00
21 Wuwung Genteng Beton Badan Flat buah Rp 13,000.00
BAHAN PELAPIS / PENUTUP PLAFOND
1 Gypsum Lembar Rp 69,575.00
2 List Gypsum M' Rp 25,575.00
1 Plywood 3 mm Lembar Rp 54,862.50
2 Plywood 4 mm Lembar Rp 67,512.50
1 Plywood 6 mm Lembar Rp 84,315.00
2 Plywood 9 mm Lembar Rp 123,420.00

CAT DAN PENGAWET


1 Cat Air Kualitas Standar Kilogram Rp 11,385.00
2 Cat Air Kualitas Sedang Kilogram Rp 14,685.00
3 Cat Air Kualitas Baik Kilogram Rp 50,710.00
4 Cat Minyak Kualitas Standar Kilogram Rp 36,410.00
5 Cat Minyak Kualitas Sedang Kilogram Rp 46,310.00
6 Cat Minyak Kualitas Baik Kilogram Rp 49,610.00
7 Cat Dasar Kayu Kilogram Rp 42,460.00
8 Plamir / Dempul Kilogram Rp 15,510.00
9 Cat Menie Kilogram Rp 18,260.00
10 Teer / Residu Kilogram Rp 8,910.00
11 Minyak Cat / Thinner Liter Rp 18,535.00 Rp 20,000.00
12 Cat Marka Jalan (Thermo Plastic) Kilogram Rp 57,860.00 Rp 48,000.00
13 Blass Bit Kilogram Rp 28,710.00 Rp 25,000.00
14 Safety Net tali nilon 6mm lubang 10 cm M² Rp 55,000.00
HARGA SEWA ALAT
1 Concrete Mixer 0,3 - 0,6 M3 Jam Rp 36,769.12
ALAT PEMBERSIH
1 Parang Buah Rp 100,210.00
2 Cangkul Buah Rp 93,610.00
3 Sapu Lidi Buah Rp 14,960.00
4 Skop Besi Buah Rp 83,710.00
5 Godam/Palu Besar Buah Rp 146,960.00
6 Sarung Tangan Pasang Rp 15,510.00

M. ALAT PELINDUNG DIRI


1 Sepatu Boot bh Rp 95,000.00
2 Helm Safety bh Rp 50,000.00
3 Rompi Jaring Proyek bh Rp 12,000.00
4 Sarung Tangan Proyek bh Rp 5,000.00
5 Safety Belt bh Rp 60,000.00

1 Angkutan Barang dari dermaga ke pulau ton/m3/mil Rp 8,000.00


2 Tarif muat dari dermaga ke kapal, kapal ke lokasi ton/m3 Rp 60,000.00
3 Tarif Bongkar dari kapal ke lokasi ton/m3 Rp 60,000.00
4 Tarif Pengemasan dan pengisian ton/m3 Rp 35,000.00

OUTDOOR EQUIPMENTS
1 Booth Open Counter kayu pinus + rangka Ls Rp 2,500,000.00
2 Kain Membran Agtex 750 gsm + rangka pipa M² Rp 1,300,000.00
3 Booth Open Counter tiket full kayu pinus + rangka Rp 2,000,000.00
besi, leveling lantai+100mm
DAFTAR ANALISA HARGA SATUAN

ANALISA 1 M3 BALOK LANTAI KAYU KELAS II


U RAIAN HARGA BAHAN J U M LA H HARGA UPAH J U M LA H
a. Bahan
1.1000 M3 Kayu Kelas II Rp 1,500,000.00 Rp 1,650,000.00
2.0000 Kg Paku 1 s/d 2½ cm Rp 19,848.40 Rp 39,696.80

b. Upah
6.0000 OH Pekerja Rp 138,000.00 Rp 828,000.00
18.0000 OH Tukang Kayu Rp 158,000.00 Rp 2,844,000.00
2.0000 OH Kepala Tukang Rp 173,000.00 Rp 346,000.00
0.3000 OH Mandor Rp 185,000.00 Rp 55,500.00
JUMLAH Rp 1,689,696.80 Rp 4,073,500.00
JUMLAH TOTAL Rp 5,763,196.80

ANALISA 1 M2 PAGAR KAYU KLAS II


U RAIAN HARGA BAHAN J U M LA H HARGA UPAH J U M LA H
a. Bahan
0.0325 M3 Kayu kaso Borneo Rp 4,000,000.00 Rp 130,000.00
0.0100 Kg Paku 1 s/d 2½ cm Rp 19,848.40 Rp 198.48
b. Upah
0.0800 OH Pekerja Rp 138,000.00 Rp 11,040.00
0.2400 OH Tukang Kayu Rp 158,000.00 Rp 37,920.00
0.0240 OH Kepala Tukang Rp 173,000.00 Rp 4,152.00
0.0040 OH Mandor Rp 185,000.00 Rp 740.00
JUMLAH Rp 130,198.48 Rp 53,852.00
JUMLAH TOTAL Rp 184,050.48

ANALISA 1 M2 LANTAI PAPAN KAYU KLAS II


U RAIAN HARGA BAHAN J U M LA H HARGA UPAH J U M LA H
a. Bahan
0.0325 M3 Papan Kayu Kelas II Rp 1,000,000.00 Rp 32,500.00
0.0100 Kg Paku 1 s/d 2½ cm Rp 19,848.40 Rp 198.48
b. Upah
0.0800 OH Pekerja Rp 138,000.00 Rp 11,040.00
0.2400 OH Tukang Kayu Rp 158,000.00 Rp 37,920.00
0.0240 OH Kepala Tukang Rp 173,000.00 Rp 4,152.00
0.0040 OH Mandor Rp 185,000.00 Rp 740.00
JUMLAH Rp 32,698.48 Rp 53,852.00
JUMLAH TOTAL Rp 86,550.48

ANALISA 1 M2 CAT RESIDU ATAU TEER


U RAIAN HARGA BAHAN J U M LA H HARGA UPAH J U M LA H
a. Bahan
0.3500 Ltr Residu / Teer Rp 8,910.00 Rp 3,118.50

b. Upah
0.1000 OH Pekerja Rp 138,000.00 Rp 13,800.00
0.0060 OH Mandor Rp 185,000.00 Rp 1,110.00
JUMLAH Rp 3,118.50 Rp 14,910.00
JUMLAH TOTAL Rp 18,028.50

ANALISA 1 M' PEMANCANGAN CEROCOK KAYU (BOW) PANJANG 6 M


U RAIAN HARGA BAHAN J U M LA H HARGA UPAH J U M LA H
a. Bahan
1.0000 m' Cerocok dolken Rp 2,233.00 Rp 2,233.00

b. Upah
1.8000 OH Pekerja Rp 138,000.00 Rp 248,400.00
0.0400 OH Tukang Rp 158,000.00 Rp 6,320.00
1.8000 OH Kepala Tukang Rp 173,000.00 Rp 311,400.00
1.0450 OH Mandor Rp 185,000.00 Rp 193,325.00
JUMLAH Rp 2,233.00 Rp 759,445.00
Upah x 0,025 Rp 2,233.00 Rp 18,986.13
JUMLAH TOTAL Rp 21,219.13
PENGADAAN ALAT PELINDING DIRI ( APD )
U RAIAN HARGA BAHAN J U M LA H
Alat
20.0000 bh Sepatu Boot Rp 95,000.00 Rp 1,900,000.00
20.0000 bh Helm Safety Rp 50,000.00 Rp 1,000,000.00
20.0000 bh Rompi Jaring Proyek Rp 12,000.00 Rp 240,000.00
20.0000 bh Sarung Tangan Proyek Rp 5,000.00 Rp 100,000.00
5.0000 bh Safety Belt Rp 60,000.00 Rp 300,000.00
JUMLAH Rp 3,540,000.00 Rp -
JUMLAH TOTAL Rp 3,540,000.00
PERHITUNGAN KOEFISIEN TULANGAN BETO

Pondasi Strauszfaal 0 3 cm
No. Uraian dan Tulangan (kg)
Ukuran beton Banyak Diameter Panjang Berat/m1
(a) (b) (c) (d) (e) (f) (g)
0.3 0.3
Tul. Pokok 5.00 16.00 16.67 1.58
Sengkang 74.07 8.00 3.84 0.39
Berat / m3
Berat / m3

Poer 100 x 100 x 20 cm


No. Uraian dan Tulangan (kg)
Ukuran beton Banyak Diameter Panjang Berat/m1
(a) (b) (c) (d) (e) (f) (g)
1.5 1.5 0.2
Tul. Pokok 18.89 16.00 3.50 1.58
Tul. Pokok 18.89 16.00 3.50 1.58
Berat / m3 U-24

Poer 75 x 75 x 20 cm
No. Uraian dan Tulangan (kg)
Ukuran beton Banyak Diameter Panjang Berat/m1
(a) (b) (c) (d) (e) (f) (g)
0.75 0.75 0.2
Tul. Pokok 42.22 16.00 2.00 1.58
Tul. Pokok 42.22 16.00 2.00 1.58
Berat / m3 U-24

Pondasi 40 x 40 x 20 cm
No. Uraian dan Tulangan (kg)
Ukuran beton Banyak Diameter Panjang Berat/m1
(a) (b) (c) (d) (e) (f) (g)
0.4 0.4 0.2
Tul. Pokok 93.75 0.00 1.30 0.62
Tul. Pokok 93.75 0.00 1.30 0.62
Berat / m3 U-24

Pondasi 60 x 60 x 20 cm
No. Uraian dan Tulangan (kg)
Ukuran beton Banyak Diameter Panjang Berat/m1
(a) (b) (c) (d) (e) (f) (g)
0.6 0.6 0.2
Tul. Pokok 55.56 16.00 1.70 0.89
Tul. Pokok 55.56 16.00 1.70 0.89
Berat / m3 U-24

Poer 100 x 100 x 20 cm


No. Uraian dan Tulangan (kg)
Ukuran beton Banyak Diameter Panjang Berat/m1
(a) (b) (c) (d) (e) (f) (g)
1 1 0.2
Tul. Pokok 30.00 16.00 2.50 1.58
Tul. Pokok 30.00 16.00 2.50 1.58
Berat / m3 U-24

Sloof 20/25 cm
No. Uraian dan Tulangan (kg)
Ukuran beton Banyak Diameter Panjang Berat/m1
(a) (b) (c) (d) (e) (f) (g)
0.2 0.25
Tul. Pokok 4.00 16.00 20.00 1.58
Tul. Pokok 2.00 13.00 24.00 1.04
Sengkang 80.00 8.00 1.00 0.39
Berat / m3 U-24
Berat / m3

Sloof 15/20 cm
No. Uraian dan Tulangan (kg)
Ukuran beton Banyak Diameter Panjang Berat/m1
(a) (b) (c) (d) (e) (f) (g)
0.15 0.2
Tul. Pokok 4.00 12.00 33.33 0.89
Sengkang 222.22 8.00 0.80 0.39
Berat / m3 U-24

Kolom 30/30 cm
No. Uraian dan Tulangan (kg)
Ukuran beton Banyak Diameter Panjang Berat/m1
(a) (b) (c) (d) (e) (f) (g)
0.3 0.3
Tul. Pokok 6.00 16.00 13.33 1.58
Tul. Pokok 2.00 13.00 13.33 1.04
Sengkang 83.33 8.00 1.30 0.40
Berat / m3 U-39
Berat / m3

Kolom 15/30 cm
No. Uraian dan Tulangan (kg)
Ukuran beton Banyak Diameter Panjang Berat/m1
(a) (b) (c) (d) (e) (f) (g)
0.15 0.3
Tul. Pokok 6.00 16.00 26.67 1.58
Tul. Pokok 2.00 13.00 26.67 1.04
Sengkang 166.67 8.00 1.00 0.39
Berat / m3 U-39
Berat / m3
Kolom praktis 15/15 cm
No. Uraian dan Tulangan (kg)
Ukuran beton Banyak Diameter Panjang Berat/m1
(a) (b) (c) (d) (e) (f) (g)
0.15 0.15
Tul. Pokok 4.00 12.00 44.44 0.89
Sengkang 222.22 8.00 0.40 0.39
Berat / m3 U-24

Balok Anak 20/30 cm


No. Uraian dan Tulangan (kg)
Ukuran beton Banyak Diameter Panjang Berat/m1
(a) (b) (c) (d) (e) (f) (g)
0.2 0.3
Tul. Pokok 6.00 16.00 16.67 1.59
Sengkang 100.00 8.00 1.10 0.39

Berat / m3 U-39
Berat / m3

Balok 20/50 cm
No. Uraian dan Tulangan (kg)
Ukuran beton Banyak Diameter Panjang Berat/m1
(a) (b) (c) (d) (e) (f) (g)
0.2 0.5
Tul. Pokok 6.00 16.00 10.00 1.59
Ekstra 2.00 10.00 10.00 0.62
Sengkang 75.00 8.00 1.50 0.39

Berat / m3 U-39
Berat / m3

Balok Induk 20/40 cm


No. Uraian dan Tulangan (kg)
Ukuran beton Banyak Diameter Panjang Berat/m1
(a) (b) (c) (d) (e) (f) (g)
0.2 0.4
Tul. Pokok 6.00 16.00 12.50 1.59
Ekstra 2.00 10.00 12.50 0.62
Sengkang 75.00 8.00 1.30 0.39

Berat / m3 U-39
Berat / m3

Plat Lantai Tebal 12 cm


No. Uraian dan Tulangan (kg)
Ukuran beton Banyak Diameter Panjang Berat/m1
(a) (b) (c) (d) (e) (f) (g)
0.12
Tul. Pokok 10.25 8.00 8.33 0.39
Tul. Pokok 84.05 8.00 1.00 0.39
Berat / m3 U-24

Beton Tangga Tebal 15 cm


No. Uraian dan Tulangan (kg)
Ukuran beton Banyak Diameter Panjang Berat/m1
(a) (b) (c) (d) (e) (f) (g)
0.15
Tul. Pokok 12.30 12.00 6.67 0.89
Tul. Pokok 104.55 12.00 1.00 0.89
Berat / m3 U-24

Plat Dak Tebal 10 cm


No. Uraian dan Tulangan (kg)
Ukuran beton Banyak Diameter Panjang Berat/m1
(a) (b) (c) (d) (e) (f) (g)
0.1
Tul. Pokok 12.30 8.00 10.00 0.39
Tul. Pokok 104.55 8.00 1.00 0.39
Berat / m3 U-24

Plat Dak Tebal 10 cm


No. Uraian dan Tulangan (kg)
Ukuran beton Banyak Diameter Panjang Berat/m1
(a) (b) (c) (d) (e) (f) (g)
0.08
Tul. Pokok 12.30 8.00 12.50 0.39
Tul. Pokok 104.55 8.00 1.00 0.39
Berat / m3 U-24

List Plank Beton


No. Uraian dan Tulangan (kg)
Ukuran beton Banyak Diameter Panjang Berat/m1
(a) (b) (c) (d) (e) (f) (g)
0.1 0.5
Tul. Pokok 6 10.00 20.00 0.62
Tul. Pokok 8 10.00 1.30 0.62
Berat / m3 U-24
GAN KOEFISIEN TULANGAN BETON

Jumlah Bekisting (m2) Luas / Stootwerk (m2) Luas


(dxfxg) Luas 1 Luas 2 Pj. 1m3 1m3 beton Panjang Lebar 1m3 beton
(h) (i) (j) (k) (l) (m) (n) (o)

131.667
110.933
242.600
Luas Stootwerk

Jumlah Bekisting (m2) Luas / Stootwerk (m2) Luas


(dxfxg) Luas 1 Luas 2 Pj. 1m3 1m3 beton Panjang Lebar 1m3 beton
(h) (i) (j) (k) (l) (m) (n) (o)
0.60 0.60 2.22 2.67
104.456
104.456
208.911 Luas Pemasangan Bekisting 2.667 Luas Stootwerk

Jumlah Bekisting (m2) Luas / Stootwerk (m2) Luas


(dxfxg) Luas 1 Luas 2 Pj. 1m3 1m3 beton Panjang Lebar 1m3 beton
(h) (i) (j) (k) (l) (m) (n) (o)
0.30 0.30 8.89 5.33
133.422
133.422
266.844 Luas Pemasangan Bekisting 5.333 Luas Stootwerk

Jumlah Bekisting (m2) Luas / Stootwerk (m2) Luas


(dxfxg) Luas 1 Luas 2 Pj. 1m3 1m3 beton Panjang Lebar 1m3 beton
(h) (i) (j) (k) (l) (m) (n) (o)
0.16 0.16 31.25 10.00
75.197
75.197
150.394 Luas Pemasangan Bekisting 10.000 Luas Stootwerk

Jumlah Bekisting (m2) Luas / Stootwerk (m2) Luas


(dxfxg) Luas 1 Luas 2 Pj. 1m3 1m3 beton Panjang Lebar 1m3 beton
(h) (i) (j) (k) (l) (m) (n) (o)
0.24 0.24 13.89 6.67
83.867
83.867
167.733 Luas Pemasangan Bekisting 6.667 Luas Stootwerk

Jumlah Bekisting (m2) Luas / Stootwerk (m2) Luas


(dxfxg) Luas 1 Luas 2 Pj. 1m3 1m3 beton Panjang Lebar 1m3 beton
(h) (i) (j) (k) (l) (m) (n) (o)
0.40 0.40 5.00 4.00
118.500
118.500
237.000 Luas Pemasangan Bekisting 4.000 Luas Stootwerk

Jumlah Bekisting (m2) Luas / Stootwerk (m2) Luas


(dxfxg) Luas 1 Luas 2 Pj. 1m3 1m3 beton Panjang Lebar 1m3 beton
(h) (i) (j) (k) (l) (m) (n) (o)
- 0.50 20.00 10.00
126.400
49.920
31.200
207.520
Luas Pemasangan Bekisting 10.000 Luas Stootwerk

Jumlah Bekisting (m2) Luas / Stootwerk (m2) Luas


(dxfxg) Luas 1 Luas 2 Pj. 1m3 1m3 beton Panjang Lebar 1m3 beton
(h) (i) (j) (k) (l) (m) (n) (o)
- 0.20 33.33 6.67
118.667
69.333
188.000 Luas Pemasangan Bekisting 6.667 Luas Stootwerk

Jumlah Bekisting (m2) Luas / Stootwerk (m2) Luas


(dxfxg) Luas 1 Luas 2 Pj. 1m3 1m3 beton Panjang Lebar 1m3 beton
(h) (i) (j) (k) (l) (m) (n) (o)
0.60 0.60 11.11 13.33 0.25 8.33 2.08
126.400
27.733
42.792
196.925
Luas Pemasangan Bekisting 13.333 Luas Stootwerk 2.083

Jumlah Bekisting (m2) Luas / Stootwerk (m2) Luas


(dxfxg) Luas 1 Luas 2 Pj. 1m3 1m3 beton Panjang Lebar 1m3 beton
(h) (i) (j) (k) (l) (m) (n) (o)
0.30 0.60 22.22 20.00 0.25 8.33 2.08
252.800
55.467
65.000
373.267
Luas Pemasangan Bekisting 20.000 Luas Stootwerk 2.083

Jumlah Bekisting (m2) Luas / Stootwerk (m2) Luas


(dxfxg) Luas 1 Luas 2 Pj. 1m3 1m3 beton Panjang Lebar 1m3 beton
(h) (i) (j) (k) (l) (m) (n) (o)
- 0.30 44.44 13.33
158.222
34.667
192.889 Luas Pemasangan Bekisting 13.333 Luas Stootwerk -

Jumlah Bekisting (m2) Luas / Stootwerk (m2) Luas


(dxfxg) Luas 1 Luas 2 Pj. 1m3 1m3 beton Panjang Lebar 1m3 beton
(h) (i) (j) (k) (l) (m) (n) (o)
0.20 0.36 16.67 9.33 16.67 0.20 3.33
159.000
42.900

201.900
Luas Pemasangan Bekisting 9.333 Luas Stootwerk 3.33

Jumlah Bekisting (m2) Luas / Stootwerk (m2) Luas


(dxfxg) Luas 1 Luas 2 Pj. 1m3 1m3 beton Panjang Lebar 1m3 beton
(h) (i) (j) (k) (l) (m) (n) (o)
0.20 0.76 10.00 9.60 10.00 0.20 2.00
95.400
12.400
43.875

151.675
Luas Pemasangan Bekisting 9.600 Luas Stootwerk 2.000

Jumlah Bekisting (m2) Luas / Stootwerk (m2) Luas


(dxfxg) Luas 1 Luas 2 Pj. 1m3 1m3 beton Panjang Lebar 1m3 beton
(h) (i) (j) (k) (l) (m) (n) (o)
0.20 0.56 12.50 9.50 12.50 0.20 2.50
119.250
15.500
38.025

172.775
Luas Pemasangan Bekisting 9.500 Luas Stootwerk 2.500

Jumlah Bekisting (m2) Luas / Stootwerk (m2) Luas


(dxfxg) Luas 1 Luas 2 Pj. 1m3 1m3 beton Panjang Lebar 1m3 beton
(h) (i) (j) (k) (l) (m) (n) (o)
- 1.00 8.33 8.33 8.33 1.00 8.33
33.313
32.780
66.092 Luas Pemasangan Bekisting 8.333 Luas Stootwerk 8.333

Jumlah Bekisting (m2) Luas / Stootwerk (m2) Luas


(dxfxg) Luas 1 Luas 2 Pj. 1m3 1m3 beton Panjang Lebar 1m3 beton
(h) (i) (j) (k) (l) (m) (n) (o)
- 1.00 6.67 6.67 6.67 1.00 6.67
72.980
93.050
166.030 Luas Pemasangan Bekisting 6.667 Luas Stootwerk 6.667

Jumlah Bekisting (m2) Luas / Stootwerk (m2) Luas


(dxfxg) Luas 1 Luas 2 Pj. 1m3 1m3 beton Panjang Lebar 1m3 beton
(h) (i) (j) (k) (l) (m) (n) (o)
- 1.00 10.00 10.00 10.00 1.00 10.00
47.970
40.775
88.745 Luas Pemasangan Bekisting 10.000 Luas Stootwerk 10.000

Jumlah Bekisting (m2) Luas / Stootwerk (m2) Luas


(dxfxg) Luas 1 Luas 2 Pj. 1m3 1m3 beton Panjang Lebar 1m3 beton
(h) (i) (j) (k) (l) (m) (n) (o)
- 1.00 12.50 12.50 12.50 1.00 12.50
59.963
40.775
100.737 Luas Pemasangan Bekisting 12.500 Luas Stootwerk 12.500

Jumlah Bekisting (m2) Luas / Stootwerk (m2) Luas


(dxfxg) Luas 1 Luas 2 Pj. 1m3 1m3 beton Panjang Lebar 1m3 beton
(h) (i) (j) (k) (l) (m) (n) (o)
0.10 0.76 20.00 17.20 20.00 0.10 2.00
74.400
6.179
80.579 Luas Pemasangan Bekisting 17.200 Luas Stootwerk 2.000
berat besi kg/m1
dia 6 0.222
dia 8 0.395
dia 10 0.617
dia 12 0.888
dia 16 1.580
dia 19 2.230
DAFTAR ANALISA HARGA SATUAN PEKERJAAN MOBILISASI DARI JAKARTA - KEPULAUAN SERIBU (PULAU KELAPA DUA)

VOLUME HARGA SAT BIAYA (Rp) JML HARGA


NO URAIAN
SAT JUMLAH (Rp) UPAH BAHAN (Rp)
1 2 3 4 5 6 7 8
1 Biaya Mobilisasi Bahan Per/Ton Pasir ke P Harapan m3
Tarif angkutan barang dari dermaga ke pulau T/mil 30.000 9,600.00 288,000.00
Tarif bongkar muat dari dermaga ke kapal m3 1.000 72,000.00 72,000.00
Tarif bongkar muat dari kapal ke lokasi m3 1.000 72,000.00 72,000.00
Tarif pengemasan dan pengisian Unt/mil 1.000 42,000.00 42,000.00
Biaya pengemasan + Karung krg 25.000 1,600.00 40,000.00
Total 514,000.00 -
Total Harga 514,000.00 - 514,000.00
2 Biaya Mobilisasi Bahan Per/Ton Besi Beton ke P Harapan Ton
Tarif angkutan barang dari dermaga ke pulau T/mil 30.000 9,600.00 288,000.00
Tarif bongkar muat dari dermaga ke kapal Ton 1.000 72,000.00 72,000.00
Tarif bongkar muat dari kapal ke lokasi Ton 1.000 72,000.00 72,000.00

Total 432,000.00 -
Total Harga 432,000.00 - 432,000.00
3 Biaya Mobilisasi Bahan Per/Ton Split ke P Harapan Ton
Tarif angkutan barang dari dermaga ke pulau T/mil 30.000 9,600.00 288,000.00
Tarif bongkar muat dari dermaga ke kapal Ton 1.000 72,000.00 72,000.00
Tarif bongkar muat dari kapal ke lokasi Ton 1.000 72,000.00 72,000.00
Tarif pengemasan dan pengisian Unt/mil 1.000 42,000.00 42,000.00
Biaya pengemasan + Karung krg 25.000 1,600.00 40,000.00
Total 514,000.00 -
Total Harga 514,000.00 - 514,000.00
4 Biaya Mobilisasi Bahan Per/Ton Batu Bata ke P Harapan Ton
Tarif angkutan barang dari dermaga ke pulau T/mil 30.000 9,600.00 288,000.00
Tarif bongkar muat dari dermaga ke kapal Ton 1.000 72,000.00 72,000.00
Tarif bongkar muat dari kapal ke lokasi Ton 1.000 72,000.00 72,000.00
Biaya pengemasan + Karung krg 25.000 1,600.00 40,000.00
Total 472,000.00 -
Total Harga 472,000.00 - 472,000.00
5 Biaya Mobilisasi Bahan Per/Zak Semen ke P Harapan Zak
Tarif angkutan barang dari dermaga ke pulau T/mil 30.000 9,600.00 288,000.00
Tarif bongkar muat dari dermaga ke kapal Ton 1.000 72,000.00 72,000.00
Tarif bongkar muat dari kapal ke lokasi Ton 1.000 72,000.00 72,000.00

Total 432,000.00 -
Biaya Mobilisasi Bahan Per/Zak Semen @ 50 Kg 20.000 21,600.00
Total Harga 21,600.00 - 21,600.00
6 Biaya Mobilisasi Bahan Per/Ton/M³ Kayu ke P Harapan M3
Tarif angkutan barang dari dermaga ke pulau T/mil 30.000 9,600.00 288,000.00
Tarif Bongkar Muat di dermaga Ton 1.000 72,000.00 72,000.00
Tarif bongkar muat dari dermaga ke kapal Ton 1.000 72,000.00 72,000.00
Tarif bongkar muat dari kapal ke lokasi Ton 1.000 72,000.00 72,000.00

Total 504,000.00 -
Total Harga 504,000.00 - 504,000.00