A. UPAH
1 Mandor Lapangan Org/hari L 01 70,000.00
2 Kepala Tukang Org/hari L 02 85,500.00
3 Tukang Batu / Kayu / Gali / Besi / Cor / Semen / Cat / Listrik / Pancang Org/hari L 03 60,000.00
4 Pekerja / Buruh Lapangan Tak terlatih Org/hari L 04 45,000.00
BAHAN HARGA
NO SATUAN KODE
( Rp.)
B. BAHAN PENGISI
1 Batu Kong M³ M 01 156,500.00
2 Batu Sap Pinang M³ M 02 204,000.00
3 Batu pecah 15/20 cm M³ M 03 278,100.00
4 Batu pecah 10/15 cm M³ M 04 278,100.00
5 Batu pecah 5/7 cm M³ M 05 290,600.00
6 Batu pecah 3/5 cm M³ M 06 346,800.00
7 Batu pecah 2/3 cm M³ M 07 471,800.00
8 Batu pecah 1/2 cm M³ M 08 643,700.00
9 Batu pecah 0,5 - 1 cm M³ M 09 556,200.00
10 Stone dust M³ M 10 431,200.00
11 Aspal Kg M 11 11,605.00
12 Pasir M³ M 12 75,000.00
13 Pasir Beton/Pasang M3 M 13 185,600.00
14 Semen PC Zak M 14 94,100.00
15 Semen PC Kg M 15 1,882.00
16 Tanah Urug Pilihan M³ M 16 79,300.00
17 Tanah EX. Peladis/ Tanah Subur Pilihan M³ M 17 99,300.00
18 Paving Block Bh M 18 2,280.00
19 Paving Stone Bh M 19 3,300.00
20 Batu Bata 5 x 11 x 22cm Bh M 20 2,400.00
21 Batako 15 x 30 x 7 cm Bh M 21 2,500.00
22 Batako 20 x 40 x 7 cm press mesin Bh M 22 3,500.00
23 Keramik 20 x 20 cm Kotak M 23 62,500.00
24 Keramik 30 x 30 cm (biasa) Kotak M 24 62,500.00
25 Keramik 30 x 30 cm (anti gores) Kotak M 25 94,000.00
26 Keramik 40 x 40 cm (biasa) Kotak M 26 71,100.00
27 Keramik 40 x 40 cm (anti gores) Kotak M 27 98,000.00
28 Granito 40 x 40 cm Kotak M 28 158,125.00
29 Batu laman Corak Bergaris M2 M 29 325,000.00
30 Marmer M² M 30 491,400.00
31 Wood Flooring M² M 31 245,000.00
32 List Keramik WC. 8 x 20 cm Bh M 32 4,900.00
33 Plint Keramik 8 x 40 Bh M 33 4,900.00
34 Plint Kayu uk. 2 x 10 cm M1 M 34 12,000.00
35 Keramik dinding 20 x 20 cm M² M 35 62,500.00
36 Keramik dinding 20 x 25 cm M² M 36 62,500.00
37 Bahan Plastik Cor Beton M² M 37 3,500.00
C. BAHAN KAYU
1 Ky. Belian tdk ketam Uk. 6/6 - 4 M M³ M 38 10,394,000.00
2 Ky. Belian tdk ketam Uk. 7/7 - 4 M M³ M 39 12,453,000.00
3 Ky. Belian tdk ketam Uk. 8/8 - 4 M M³ M 40 12,653,000.00
4 Ky. Belian tdk ketam Uk. 9/9 - 4 M M³ M 41 11,532,000.00
5 Ky. Belian tdk ketam Uk. 10/10 - 4 M M³ M 42 10,270,000.00
6 Ky. Belian tdk ketam Uk. 12/12 - 4 M M³ M 43 10,454,000.00
7 Ky. Belian ketam Uk. 6/6 - 4 M M³ M 44 10,644,000.00
8 Ky. Belian ketam Uk. 7/7 - 4 M M³ M 45 12,703,000.00
9 Ky. Belian ketam Uk. 8/8 - 4 M M³ M 46 12,903,000.00
BAHAN HARGA
NO SATUAN KODE
( Rp.)
D. BAHAN CAT
1 Amplas Lbr M 77 2,300.00
2 Minyak cat Kg M 78 24,000.00
3 Cat dasar kayu Kg M 79 27,600.00
4 Cat dasar tembok Kg M 80 27,600.00
5 Cat kilat Kg M 81 49,000.00
6 Cat tembok Kg M 82 17,700.00
7 Cat tembok type weather shield Kg M 83 51,500.00
8 Dempul kayu Kg M 84 18,000.00
9 Dempul tembok Kg M 85 18,000.00
10 Plamur Kg M 86 16,100.00
11 Plitur Kg M 87 31,200.00
12 Thiner kg M 88 8,100.00
13 Thiner ND Ltr M 89 28,800.00
14 Melamic Ltr M 90 40,800.00
15 Vernis Ltr M 91 27,600.00
16 Meni Kayu Kg M 92 38,400.00
17 Meni Besi Kg M 93 47,160.00
18 Oker Kg M 94 63,000.00
19 Lem Kayu Kg M 95 18,000.00
20 Soda Api Kg M 96 18,000.00
21 Sabun / cream pembersih kotoran Kg M 97 17,400.00
22 Teak Oil Ltr M 98 28,800.00
23 Ter / Residu Ltr M 99 15,900.00
24 Kuas 4" Bh M 100 14,400.00
25 Road Line Paint ( Cat Marka ) Ltr M 101 54,000.00
26 Glass Bit Kg M 102 39,840.00
27 Weatherbond Emulsion ( cat kerb ) Kg M 103 39,960.00
28 Termoplast Kg M 104 18,960.00
F. BAHAN PENGANTUNG
1 Pintu Plastik untuk WC Bh M 136 320,000.00
2 Kait angin Bh M 137 9,800.00
3 Handle Bh M 138 6,900.00
4 Engsel jendela Bh M 139 12,500.00
5 Engsel pintu Bh M 140 15,500.00
6 Slot pintu Bh M 141 2,600.00
7 Slot jendela Bh M 142 2,000.00
8 Kunci tanam 2 slag besar (setaraf Belluci) Bh M 143 168,000.00
9 Kunci tanam 2 slag besar (biasa) Bh M 144 100,000.00
10 Kunci pintu kecil Bh M 145 50,000.00
11 Kunci tanam antik Bh M 146 150,000.00
12 Kunci tanam biasa Bh M 147 90,000.00
13 Kunci silinder Bh M 148 102,000.00
14 Door Closer Bh M 149 120,000.00
15 Door Stoper Bh M 150 18,000.00
16 Paku ulir aluminium Kg M 151 73,430.00
17 Paku campuran 1" - 5 " Kg M 152 20,000.00
18 Paku beton Kg M 153 29,790.00
19 Paku Seng RRT Kg M 154 26,000.00
20 Paku triplek Kg M 155 24,000.00
21 Paku GRC Kg M 156 22,200.00
22 Sekrup Gypsum Kg M 157 21,600.00
G. BAHAN ATAP
1 Sirap belian Lbr M 158 1,900.00
2 Asbes Lbr M 159 43,200.00
3 Eternit M² M 160 57,000.00
4 Genteng Metal 0,25 mm Lbr M 161 47,500.00
5 Genteng Metal 0,30 mm Lbr M 162 56,200.00
6 Genteng Metal 0,35 mm Lbr M 163 98,000.00
7 Genteng Metal Stone ( Type Classic 0.35 ) Lbr M 164 102,000.00
8 Genteng Metal Stone ( Type Prima 0.35 ) Lbr M 165 75,600.00
9 Nok bubungan genteng metal 1/2 lingkaran 0.35 (pj 40cm) Bh M 166 55,000.00
10 Nok bubungan genteng metal kotak 0.35 Meter M 167 78,000.00
11 Nok bubungan genteng metal stone kotak 0.35 Meter M 168 90,000.00
12 Seng Gelombang Bjls 30 Lbr M 169 85,500.00
13 Seng Gelombang Bjls 20 Lbr M 170 56,000.00
14 Seng Plat Bjls 20 Lbr M 171 69,100.00
15 Seng Plat Bjls 30 Lbr M 172 87,700.00
16 Plat Datar Color 0.35 Lbr M 173 66,000.00
17 Atap Zincalum Lbr M 174 143,000.00
18 Paku atap zincalum /btg M 175 1,400.00
19 Multi Sirap 0.4 mm ( type borneo, andalas, dwipa ) m2 M 176 270,900.00
20 Zincalume Plat 0.2 Lbr M 177 143,000.00
21 Aluminium Foil M² M 178 48,000.00
H. BAHAN KACA
1 Kaca Polos, t = 4,3 mm M² M 179 95,000.00
BAHAN HARGA
NO SATUAN KODE
( Rp.)
I. BAHAN LANGIT-LANGIT
1 Triplek t = 3 mm Lbr M 188 65,000.00
2 Triplek t = 4 mm Lbr M 189 80,000.00
3 Triplek t =9 mm Lbr M 190 145,000.00
4 Multiplek t = 12 mm Lbr M 191 195,000.00
5 Plywood 4' x 8' x 4mm Lbr M 192 110,000.00
6 Panel GRC 120 x 240 t 4 mm Lbr M 193 78,000.00
7 GypsumBoard t = 9mm Lbr M 194 75,600.00
8 Sungkai / Nyatoh Lbr M 195 276,000.00
J. BAHAN SANITASI
1 Kloset duduk monoblok Bh M 196 2,500,000.00
2 Kloset jongkok polos Bh M 197 150,000.00
3 Kloset jongkok warna Bh M 198 150,000.00
4 Tempat sabun warna Bh M 199 29,600.00
5 Kran air uk 1/2" (metal/stainless steel) Bh M 200 36,600.00
6 Kran air uk 3/4" (metal/stainless steel) Bh M 201 38,400.00
7 Floor drain Bh M 202 18,000.00
8 Besi/pipa penguras Bh M 203 26,790.00
9 Pipa paralon dia 1/2" Btg M 204 21,200.00
10 Pipa paralon dia 3/4" Btg M 205 32,500.00
11 Pipa paralon dia 1" Btg M 206 49,700.00
12 Pipa paralon dia 2" Btg M 207 85,000.00
13 Pipa paralon dia 3" Btg M 208 178,300.00
14 Pipa paralon dia 4" Btg M 209 259,500.00
K. BAHAN MINYAK
1 Minyak solar Ltr M 210 5,489.00
2 Bensin premium Ltr M 211 5,750.00
3 Minyak pelumas Ltr M 212 23,000.00
4 Minyak tanah Ltr M 213 4,450.00
5 Gas Elpiji Kg M 214 7,560.00
6 Alat-alat bantu Set M 215 120,000.00
1m1 Pembuatan Pagar Sementara dari Seng Gelombang Tinggi 2 meter (P.Ps. 01)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Tukang Kayu OH 60,000.00 0.200 12,000.00
2 Pekerja OH 45,000.00 0.400 18,000.00
3 Kepala Tukang OH 85,500.00 0.020 1,710.00
4 Mandor OH 70,000.00 0.020 1,400.00
Jumlah 33,110.00
B BAHAN
1 Kayu Pancang (Dolken) d = 10cm, p = 4m Btg 10,000.00 1.250 12,500.00
2 Seng Gelombang BJLS 0.20 Lbr 56,000.00 1.200 67,200.00
3 Kayu Kelas II uk. 4/6 M3 2,370,000.00 0.072 170,640.00
4 Paku Kg 20,000.00 0.060 1,200.00
Jumlah 251,540.00
C Jumlah A + B 284,650.00
D Harga Satuan 284,650.00
Acuan : ABK Bangunan Gedung dan Perumahan - 6.2
Jumlah 0.00
C Jumlah A + B 8,000.00
D Harga Satuan 8,000.00
Acuan : ABK Bangunan Gedung dan Perumahan - 6.8
1m2 Pembuatan Direksi Keet / Gudang Bahan Bangunan dan Alat / Bedeng Pekerja (P.Ps. 04)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Tukang Kayu OH 60,000.00 2.000 120,000.00
2 Pekerja OH 45,000.00 1.000 45,000.00
3 Kepala Tukang OH 85,500.00 0.200 17,100.00
4 Mandor OH 70,000.00 0.050 3,500.00
Jumlah 185,600.00
B BAHAN
1 Kayu Pancang (Dolken) d = 10cm, p = 4m Btg 10,000.00 1.250 12,500.00
2 Kayu Kelas III M3 1,803,000.00 0.186 335,358.00
3 Paku Kg 20,000.00 0.300 6,000.00
4 Seng Gelombang BJLS 0.20 Lbr 56,000.00 1.500 84,000.00
5 Triplek 4mm Lbr 65,000.00 1.3500 87,750.00
Jumlah 525,608.00
C Jumlah A + B 711,208.00
D Harga Satuan 711,208.00
Acuan : ABK Bangunan Gedung dan Perumahan - 6.9
ANALISA 6
B. PEKERJAAN TANAH (P.T.)
Jumlah 0.00
C Jumlah A + B 20,800.00
D Harga Satuan 20,800.00
Acuan : ABK Bangunan Gedung dan Perumahan - 6.1
Jumlah 0.00
C Jumlah A + B 32,465.00
D Harga Satuan 32,465.00
Acuan : ABK Bangunan Gedung dan Perumahan - 6.4
Jumlah 0.00
C Jumlah A + B 42,845.00
D Harga Satuan 42,845.00
Acuan : ABK Bangunan Gedung dan Perumahan - 6.6
1m3 Pembuangan Tanah Galian sejauh 150 meter secara Manual (P.T. 04)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 45,000.00 0.516 23,220.00
2 Mandor OH 70,000.00 0.050 3,500.00
Jumlah 26,720.00
B BAHAN
Jumlah 0.00
C Jumlah A + B 26,720.00
D Harga Satuan 26,720.00
Acuan : ABK Bangunan Gedung dan Perumahan - 6.8
Jumlah 0.00
C Jumlah A + B 2,600.00
D Harga Satuan 2,600.00
Acuan : ABK Bangunan Gedung dan Perumahan - 6.7
ANALISA 7
1m3 Urugan Kembali (P.T. 06)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 45,000.00 0.192 8,640.00
2 Mandor OH 70,000.00 0.019 1,330.00
Jumlah 9,970.00
B BAHAN
Jumlah 0.00
C Jumlah A + B 9,970.00
D Harga Satuan 9,970.00
Acuan : ABK Bangunan Gedung dan Perumahan - 6.9
Jumlah 0.00
C Jumlah A + B 26,000.00
D Harga Satuan 26,000.00
Acuan : ABK Bangunan Gedung dan Perumahan - 6.10
ANALISA 8
1m3 Urugan Pasir Alas (P.T. 11)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 45,000.00 0.300 13,500.00
2 Mandor OH 70,000.00 0.010 700.00
Jumlah 14,200.00
B BAHAN
1 Pasir Urug M3 75,000.00 1.250 93,750.00
Jumlah 93,750.00
C Jumlah A + B 107,950.00
D Harga Satuan 107,950.00
Acuan : Harga Satuan Bahan, Upah dan Analisa Biaya Pekerjaan BOW - W. 1
ANALISA 9
D. PEKERJAAN BETON BERTULANG (P.BB.)
ANALISA 10
Acuan : ABK Bangunan Gedung dan Perumahan - 6.27
ANALISA 11
1m2 Pasang Bekesting untuk Pondasi (P.BB. 04)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 45,000.00 0.300 13,500.00
2 Tukang Kayu OH 60,000.00 0.260 15,600.00
3 Kepala Tukang OH 85,500.00 0.026 2,223.00
4 Mandor OH 70,000.00 0.005 350.00
Jumlah 31,673.00
B BAHAN
1 Papan Mal (Kayu Kelas III) M3 2,030,000.00 0.040 81,200.00
2 Paku 2" - 5" Kg 20,000.00 0.300 6,000.00
3 Minyak Bekesting Lt 5,489.00 0.100 548.90
Jumlah 87,748.90
C Jumlah A + B 119,421.90
D Harga Satuan 119,421.90
Acuan : ABK Bangunan Gedung dan Perumahan - 6.28
ANALISA 12
1m2 Pasang Bekesting untuk Balok (P.BB. 07)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 45,000.00 0.320 14,400.00
2 Tukang Kayu OH 60,000.00 0.330 19,800.00
3 Kepala Tukang OH 85,500.00 0.033 2,821.50
4 Mandor OH 70,000.00 0.006 420.00
Jumlah 37,441.50
B BAHAN
1 Kayu Kelas III uk. 4/6 M3 1,803,000.00 0.040 72,120.00
2 Paku 2" - 5" Kg 20,000.00 0.400 8,000.00
3 Minyak Bekesting Lt 5,489.00 0.200 1,097.80
4 Balok Kayu Kelas II uk. 4/6 M3 2,370,000.00 0.018 42,660.00
5 Triplek t = 9mm Lbr 145,000.00 0.350 50,750.00
6 Cerucuk Ǿ 8 - 10cm / 4m Btg 8,000.00 2.000 16,000.00
Jumlah 190,627.80
C Jumlah A + B 228,069.30
D Harga Satuan 228,069.30
Acuan : ABK Bangunan Gedung dan Perumahan - 6.31
ANALISA 13
E. PEKERJAAN DINDING (P.Dnd.)
1m2 Pasang Bata Merah Tebal 1/2 Bata Camp 1Pc : 2Ps (P.Dnd. 04)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 45,000.00 0.32 14,400.00
2 Tukang Batu OH 60,000.00 0.10 6,000.00
3 Kepala Tukang OH 85,500.00 0.01 855.00
4 Mandor OH 70,000.00 0.015 1,050.00
Jumlah 22,305.00
B BAHAN
1 Bata Merah 5 x 11 x 22cm Bh 2,400.00 70 168,000.00
2 Semen Portland Kg 1,882.00 18.950 35,663.90
3 Pasir Pasang M3 75,000.00 0.038 2,850.00
Jumlah 206,513.90
C Jumlah A + B 228,818.90
D Harga Satuan 228,818.90
Acuan : ABK Bangunan Gedung dan Perumahan - 6.9
1m2 Pasang Bata Merah Tebal 1/2 Bata Camp 1Pc : 3Ps (P.Dnd. 05)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 45,000.00 0.32 14,400.00
2 Tukang Batu OH 60,000.00 0.10 6,000.00
3 Kepala Tukang OH 85,500.00 0.01 855.00
4 Mandor OH 70,000.00 0.015 1,050.00
Jumlah 22,305.00
B BAHAN
1 Bata Merah 5 x 11 x 22cm Bh 2,400.00 70 168,000.00
2 Semen Portland Kg 1,882.00 14.370 27,044.34
3 Pasir Pasang M3 75,000.00 0.040 3,000.00
Jumlah 198,044.34
C Jumlah A + B 220,349.34
D Harga Satuan 220,349.34
Acuan : ABK Bangunan Gedung dan Perumahan - 6.10
1m2 Pasang Bata Merah Tebal 1/2 Bata Camp 1Pc : 4Ps (P.Dnd. 06)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 45,000.00 0.32 14,400.00
2 Tukang Batu OH 60,000.00 0.10 6,000.00
3 Kepala Tukang OH 85,500.00 0.01 855.00
4 Mandor OH 70,000.00 0.015 1,050.00
Jumlah 22,305.00
B BAHAN
1 Bata Merah 5 x 11 x 22cm Bh 2,400.00 70 168,000.00
2 Semen Portland Kg 1,882.00 11.500 21,643.00
3 Pasir Pasang M3 75,000.00 0.043 3,225.00
Jumlah 192,868.00
C Jumlah A + B 215,173.00
D Harga Satuan 215,173.00
Acuan : ABK Bangunan Gedung dan Perumahan - 6.10
ANALISA 14
F. PEKERJAAN PLASTERAN (P.Pls)
ANALISA 15
1m2 Plasteran 1Pc : 3Ps tebal 2cm (P.Pls. 05)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 45,000.00 0.250 11,250.00
2 Tukang Batu OH 60,000.00 0.200 12,000.00
3 Kepala Tukang OH 85,500.00 0.020 1,710.00
4 Mandor OH 70,000.00 0.0125 875.00
Jumlah 25,835.00
B BAHAN
1 Semen Portland Kg 1,882.00 10.800 20,325.60
2 Pasir M3 75,000.00 0.026 1,950.00
Jumlah 22,275.60
C Jumlah A + B 48,110.60
D Harga Satuan 48,110.60
Acuan : ABK Bangunan Gedung dan Perumahan - 6.14
ANALISA 16
1m2 Plasteran 1Pc : 4Ps tebal 3cm (P.Pls. 09)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 45,000.00 0.320 14,400.00
2 Tukang Batu OH 60,000.00 0.250 15,000.00
3 Kepala Tukang OH 85,500.00 0.025 2,137.50
4 Mandor OH 70,000.00 0.015 1,050.00
Jumlah 32,587.50
B BAHAN
1 Semen Portland Kg 1,882.00 11.380 21,417.16
2 Pasir M3 75,000.00 0.042 3,150.00
Jumlah 24,567.16
C Jumlah A + B 57,154.66
D Harga Satuan 57,154.66
Acuan : ABK Bangunan Gedung dan Perumahan - 6.25
1m2 Plasteran dan Acian 1Pc : 2Ps tebal 1,5cm (P.Pls. 11)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 45,000.00 0.330 14,850.00
2 Tukang Batu OH 60,000.00 0.165 9,900.00
3 Kepala Tukang OH 85,500.00 0.0165 1,410.75
4 Mandor OH 70,000.00 0.0165 1,155.00
Jumlah 27,315.75
B BAHAN
1 Semen Portland Zak 1,882.00 0.320 602.24
2 Pasir M3 75,000.00 0.018 1,350.00
Jumlah 1,952.24
C Jumlah A + B 29,267.99
D Harga Satuan 29,267.99
Acuan : Buku Menghitung Anggaran Biaya Bangunan Zainal A. Z. terbitan PT Gramedia Pustaka Utama Jakarta
1m2 Plasteran dan Acian 1Pc : 3Ps tebal 1,5cm (P.Pls. 12)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 45,000.00 0.330 14,850.00
2 Tukang Batu OH 60,000.00 0.165 9,900.00
3 Kepala Tukang OH 85,500.00 0.0165 1,410.75
4 Mandor OH 70,000.00 0.0165 1,155.00
Jumlah 27,315.75
B BAHAN
1 Semen Portland Zak 1,882.00 0.265 498.73
2 Pasir M3 75,000.00 0.021 1,575.00
Jumlah 2,073.73
C Jumlah A + B 29,389.48
D Harga Satuan 29,389.48
Acuan : Buku Menghitung Anggaran Biaya Bangunan Zainal A. Z. terbitan PT Gramedia Pustaka Utama Jakarta
ANALISA 17
1m2 Plasteran dan Acian 1Pc : 4Ps tebal 1,5cm (P.Pls. 13)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 45,000.00 0.330 14,850.00
2 Tukang Batu OH 60,000.00 0.165 9,900.00
3 Kepala Tukang OH 85,500.00 0.0165 1,410.75
4 Mandor OH 70,000.00 0.0165 1,155.00
Jumlah 27,315.75
B BAHAN
1 Semen Portland Zak 1,882.00 0.230 432.86
2 Pasir M3 75,000.00 0.023 1,725.00
Jumlah 2,157.86
C Jumlah A + B 29,473.61
D Harga Satuan 29,473.61
Acuan : Buku Menghitung Anggaran Biaya Bangunan Zainal A. Z. terbitan PT Gramedia Pustaka Utama Jakarta
ANALISA 18
G. PEKERJAAN KAYU (P.K.)
1m3 Pek. Membuat Kayu Sandaran Jembatan, Balok Pemikul, Balok Air Pada Barau,
Topangan Angin dan Balok Tarahan Kayu-kayu Penahan Menggunakan Kayu Belian Uk. 9/9 (P.K. 01)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Tukang Kayu OH 60,000.00 24.000 1,440,000.00
2 Pekerja OH 45,000.00 8.000 360,000.00
3 Kepala Tukang OH 85,500.00 2.400 205,200.00
4 Mandor OH 70,000.00 0.400 28,000.00
Jumlah 2,033,200.00
B BAHAN
1 Kayu Belian (Tidak Ketam uk. 9/9) M3 11,532,000.00 1.100 12,685,200.00
2 Paku beton Kg 29,790.00 3.000 89,370.00
Jumlah 12,774,570.00
C Jumlah A + B 14,807,770.00
D Harga Satuan 14,807,770.00
Acuan : Harga Satuan Bahan, Upah dan Analisa Biaya Pekerjaan BOW - F.3
1m3 Pek. Membuat Kayu Sandaran Jembatan, Balok Pemikul, Balok Air Pada Barau,
Topangan Angin dan Balok Tarahan Kayu-kayu Penahan Menggunakan Kayu Belian Uk. 10/10(P.K. 02)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Tukang Kayu OH 60,000.00 24.000 1,440,000.00
2 Pekerja OH 45,000.00 8.000 360,000.00
3 Kepala Tukang OH 85,500.00 2.400 205,200.00
4 Mandor OH 70,000.00 0.400 28,000.00
Jumlah 2,033,200.00
B BAHAN
1 Kayu Belian (Tidak Ketam uk 10/10) M3 10,270,000.00 1.100 11,297,000.00
2 Paku beton Kg 29,790.00 3.000 89,370.00
Jumlah 11,386,370.00
C Jumlah A + B 13,419,570.00
D Harga Satuan 13,419,570.00
Acuan : Harga Satuan Bahan, Upah dan Analisa Biaya Pekerjaan BOW - F.3
1m3 Pek. Membuat Kayu Sandaran Jembatan, Balok Pemikul, Balok Air Pada Barau,
Topangan Angin dan Balok Tarahan Kayu-kayu Penahan Menggunakan Kayu Belian
Uk. 12/12 - 15/15 (P.K. 03)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Tukang Kayu OH 60,000.00 24.000 1,440,000.00
2 Pekerja OH 45,000.00 8.000 360,000.00
3 Kepala Tukang OH 85,500.00 2.400 205,200.00
4 Mandor OH 70,000.00 0.400 28,000.00
Jumlah 2,033,200.00
B BAHAN
1 Kayu Belian (Tidak Ketam uk. 12/12 - 15/15) M3 10,454,000.00 1.100 11,499,400.00
2 Paku beton Kg 29,790.00 3.000 89,370.00
Jumlah 11,588,770.00
C Jumlah A + B 13,621,970.00
D Harga Satuan 13,621,970.00
Acuan : Harga Satuan Bahan, Upah dan Analisa Biaya Pekerjaan BOW - F.3
1m3 Pekerjaan Rangka Badan Kayu Belian Uk. 7/7 (P.K. 05)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Tukang Kayu OH 60,000.00 36.000 2,160,000.00
2 Pekerja OH 45,000.00 12.000 540,000.00
3 Kepala Tukang OH 85,500.00 3.600 307,800.00
4 Mandor OH 70,000.00 0.600 42,000.00
Jumlah 3,049,800.00
B BAHAN
1 Kayu Belian (Ketam uk. 7/7) M3 12,703,000.00 1.100 13,973,300.00
2 Paku beton Kg 29,790.00 6.000 178,740.00
Jumlah 14,152,040.00
C Jumlah A + B 17,201,840.00
D Harga Satuan 17,201,840.00
Acuan : Harga Satuan Bahan, Upah dan Analisa Biaya Pekerjaan BOW - F.27
ANALISA 19
1m3 Pekerjaan Rangka Badan Kayu Belian Uk. 8/8 (P.K. 06)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Tukang Kayu OH 60,000.00 36.000 2,160,000.00
2 Pekerja OH 45,000.00 12.000 540,000.00
3 Kepala Tukang OH 85,500.00 3.600 307,800.00
4 Mandor OH 70,000.00 0.600 42,000.00
Jumlah 3,049,800.00
B BAHAN
1 Kayu Belian (Ketam uk. 8/8) M3 12,903,000.00 1.100 14,193,300.00
2 Paku belian Kg 29,790.00 6.000 178,740.00
Jumlah 14,372,040.00
C Jumlah A + B 17,421,840.00
D Harga Satuan 17,421,840.00
Acuan : Harga Satuan Bahan, Upah dan Analisa Biaya Pekerjaan BOW - F.27
1m3 Pekerjaan Rangka Badan Kayu Kelas I Uk. 7/7 (P.K. 07)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Tukang Kayu OH 60,000.00 24.000 1,440,000.00
2 Pekerja OH 45,000.00 8.000 360,000.00
3 Kepala Tukang OH 85,500.00 2.400 205,200.00
4 Mandor OH 70,000.00 0.400 28,000.00
Jumlah 2,033,200.00
B BAHAN
1 Kayu Kelas I (Ketam Uk. 7/7) M3 4,110,000.00 1.100 4,521,000.00
2 Paku Kg 20,000.00 6.000 120,000.00
Jumlah 4,641,000.00
C Jumlah A + B 6,674,200.00
D Harga Satuan 6,674,200.00
Acuan : Harga Satuan Bahan, Upah dan Analisa Biaya Pekerjaan BOW - F.27.a
1m3 Pekerjaan Rangka Badan Kayu Kelas I Uk. 8/8 (P.K. 08)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Tukang Kayu OH 60,000.00 24.000 1,440,000.00
2 Pekerja OH 45,000.00 8.000 360,000.00
3 Kepala Tukang OH 85,500.00 2.400 205,200.00
4 Mandor OH 70,000.00 0.400 28,000.00
Jumlah 2,033,200.00
B BAHAN
1 Kayu Kelas I (Ketam Uk. 8/8) M3 4,310,000.00 1.100 4,741,000.00
2 Paku Kg 20,000.00 6.000 120,000.00
Jumlah 4,861,000.00
C Jumlah A + B 6,894,200.00
D Harga Satuan 6,894,200.00
Acuan : Harga Satuan Bahan, Upah dan Analisa Biaya Pekerjaan BOW - F.27.a
Jumlah 0.00
C Jumlah A + B 21,987.50
D Harga Satuan 21,987.50
Acuan : Harga Satuan Bahan, Upah dan Analisa Biaya Pekerjaan BOW - E.1
ANALISA 20
Membuat Puting dan Lobang / Pasang (P.K. 10)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Tukang Kayu OH 60,000.00 0.600 36,000.00
2 Kepala Tukang OH 85,500.00 0.060 5,130.00
Jumlah 41,130.00
B BAHAN
Jumlah 0.00
C Jumlah A + B 41,130.00
D Harga Satuan 41,130.00
Acuan : Harga Satuan Bahan, Upah dan Analisa Biaya Pekerjaan BOW - E.4
Jumlah 0.00
C Jumlah A + B 86,752.00
D Harga Satuan 86,752.00
E Harga Upah 1/2 x Harga Satuan 43,376.00
Acuan : Harga Satuan Bahan, Upah dan Analisa Biaya Pekerjaan BOW - E.13
1m3 Pasang Kusen Pintu dan Jendela Kayu Belian (P.K. 12)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 45,000.00 6.000 270,000.00
2 Tukang Kayu OH 60,000.00 20.000 1,200,000.00
3 Kepala Tukang OH 85,500.00 2.000 171,000.00
4 Mandor OH 70,000.00 0.300 21,000.00
Jumlah 1,662,000.00
B BAHAN
1 Kayu Belian 5/10 - 4 m(Ketam) M3 10,270,000.00 1.200 12,324,000.00
Jumlah 12,324,000.00
C Jumlah A + B 13,986,000.00
D Harga Satuan 13,986,000.00
Acuan : ABK Bangunan Gedung dan Perumahan - 6.1
1 M3 Kayu 5 /10- 4 m Klas I 50.00 BTg
Total Panjang 200.00 M'
1 M' Kusen 5/10 Klas I 69,930.00
1m3 Pasang Kusen Pintu dan Jendela Kayu Kelas I (P.K. 13)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 45,000.00 6.000 270,000.00
2 Tukang Kayu OH 60,000.00 18.000 1,080,000.00
3 Kepala Tukang OH 85,500.00 2.000 171,000.00
4 Mandor OH 70,000.00 0.300 21,000.00
Jumlah 1,542,000.00
B BAHAN
1 Kayu Kelas 1 uk. 5/10 (Ketam - utk Kusen) M3 4,310,000.00 1.200 5,172,000.00
Jumlah 5,172,000.00
C Jumlah A + B 6,714,000.00
D Harga Satuan 6,714,000.00
Acuan : ABK Bangunan Gedung dan Perumahan - 6.1
1m' Pasang Kusen Pintu dan Jendela Kayu Kelas I (P.K. 13a)
ANALISA 21
1m2 Pasang Pintu Panel Kayu Belian (P.K. 14)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 45,000.00 1.000 45,000.00
2 Tukang Kayu OH 60,000.00 2.500 150,000.00
3 Kepala Tukang OH 85,500.00 0.250 21,375.00
4 Mandor OH 70,000.00 0.050 3,500.00
Jumlah 219,875.00
B BAHAN
1 Papan Kayu Belian (Ketam) M3 13,749,000.00 0.040 549,960.00
Jumlah 549,960.00
C Jumlah A + B 769,835.00
D Harga Satuan 769,835.00
Acuan : ABK Bangunan Gedung dan Perumahan - 6.7
1m2 Pasang Pintu dan Jendela Kaca Kayu Belian (P.K. 16)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 45,000.00 0.800 36,000.00
2 Tukang Kayu OH 60,000.00 2.000 120,000.00
3 Kepala Tukang OH 85,500.00 0.200 17,100.00
4 Mandor OH 70,000.00 0.040 2,800.00
Jumlah 175,900.00
B BAHAN
1 Papan Kayu Belian (Ketam) M3 13,749,000.00 0.035 481,215.00
2 Kaca t. 5 mm M2 120,000.00 1.000 120,000.00
Jumlah 601,215.00
C Jumlah A + B 777,115.00
D Harga Satuan 777,115.00
Acuan : ABK Bangunan Gedung dan Perumahan - 6.9
1m2 Pasang Pintu dan Jendela Kaca Kayu Kelas I (P.K. 17)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 45,000.00 0.800 36,000.00
2 Tukang Kayu OH 60,000.00 2.000 120,000.00
3 Kepala Tukang OH 85,500.00 0.200 17,100.00
4 Mandor OH 70,000.00 0.040 2,800.00
Jumlah 175,900.00
B BAHAN
1 Papan Kayu Kelas I (Ketam) M3 4,510,000.00 0.035 157,850.00
2 Kaca t. 5 mm M2 120,000.00 1.000 120,000.00
Jumlah 277,850.00
C Jumlah A + B 453,750.00
D Harga Satuan 453,750.00
Acuan : ABK Bangunan Gedung dan Perumahan - 6.9
ANALISA 22
1m2 Pasang Pintu dan Jendela Jalusi Kayu Belian (P.K. 18)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 45,000.00 1.000 45,000.00
2 Tukang Kayu OH 60,000.00 3.000 180,000.00
3 Kepala Tukang OH 85,500.00 0.300 25,650.00
4 Mandor OH 70,000.00 0.300 21,000.00
Jumlah 271,650.00
B BAHAN
1 Papan Kayu Belian (Ketam) M3 13,749,000.00 0.064 879,936.00
Jumlah 879,936.00
C Jumlah A + B 1,151,586.00
D Harga Satuan 1,151,586.00
Acuan : ABK Bangunan Gedung dan Perumahan - 6.12
1m2 Pasang Pintu dan Jendela Jalusi Kayu Kelas I (P.K. 19)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 45,000.00 1.000 45,000.00
2 Tukang Kayu OH 60,000.00 3.000 180,000.00
3 Kepala Tukang OH 85,500.00 0.300 25,650.00
4 Mandor OH 70,000.00 0.300 21,000.00
Jumlah 271,650.00
B BAHAN
1 Papan Kayu Kelas I (Ketam) M3 4,510,000.00 0.064 288,640.00
Jumlah 288,640.00
C Jumlah A + B 560,290.00
D Harga Satuan 560,290.00
Acuan : ABK Bangunan Gedung dan Perumahan - 6.12
1m2 Pasang Pintu Plywood Rangkap, Rangka Kayu Kelas I (P.K. 20)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 45,000.00 1.000 45,000.00
2 Tukang Kayu OH 60,000.00 3.000 180,000.00
3 Kepala Tukang OH 85,500.00 0.300 25,650.00
4 Mandor OH 70,000.00 0.300 21,000.00
Jumlah 271,650.00
B BAHAN
1 Papan Kayu Kelas I (Ketam) M3 4,510,000.00 0.0196 88,396.00
2 Paku 1/2" -1" Kg 20,000.00 0.030 600.00
3 Lem Kayu Lt 18,000.00 0.300 5,400.00
4 Plywood 4' x 8' x 4mm Lbr 110,000.00 1.000 110,000.00
Jumlah 204,396.00
C Jumlah A + B 476,046.00
D Harga Satuan 476,046.00
Acuan : ABK Bangunan Gedung dan Perumahan - 6.14
1m2 Pasang Pintu Plywood Rangkap, Rangka Kayu Kelas II (P.K. 21)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 45,000.00 1.000 45,000.00
2 Tukang Kayu OH 60,000.00 3.000 180,000.00
3 Kepala Tukang OH 85,500.00 0.300 25,650.00
4 Mandor OH 70,000.00 0.300 21,000.00
Jumlah 271,650.00
B BAHAN
1 Papan Kayu Kelas II (Ketam) M3 3,250,000.00 0.0196 63,700.00
2 Paku 1/2" -1" Kg 20,000.00 0.030 600.00
3 Lem Kayu Lt 18,000.00 0.300 5,400.00
4 Plywood 4' x 8' x 4mm Lbr 110,000.00 1.000 110,000.00
Jumlah 179,700.00
C Jumlah A + B 451,350.00
D Harga Satuan 451,350.00
Acuan : ABK Bangunan Gedung dan Perumahan - 6.14
ANALISA 23
1m2 Pemasangan Ventilasi Jalusie/Reng Lat Kayu Kelas I (P.K. 22)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Tukang Kayu OH 60,000.00 0.800 48,000.00
2 Pekerja OH 45,000.00 0.500 22,500.00
3 Kepala Tukang OH 85,500.00 0.080 6,840.00
4 Mandor OH 70,000.00 0.014 980.00
Jumlah 78,320.00
B BAHAN
1 Papan Reng Lat Kayu Kelas I (Ketam) M3 8,114,300.00 0.013 105,485.90
2 Paku Kg 20,000.00 0.100 2,000.00
Jumlah 107,485.90
C Jumlah A + B 185,805.90
D Harga Satuan 185,805.90
Acuan : Harga Satuan Bahan, Upah dan Analisa Biaya Pekerjaan BOW - F.37.i
ANALISA 24
1m2 Pemasangan Kasau + Reng Atap Sirap (P.K. 26)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Tukang Kayu OH 60,000.00 0.100 6,000.00
2 Pekerja OH 45,000.00 0.100 4,500.00
3 Kepala Tukang OH 85,500.00 0.010 855.00
4 Mandor OH 70,000.00 0.005 350.00
Jumlah 11,705.00
B BAHAN
1 Kayu Kelas II (Tidak Ketam) M3 3,050,000.00 0.0200 61,000.00
2 Paku Kg 20,000.00 0.100 2,000.00
Jumlah 63,000.00
C Jumlah A + B 74,705.00
D Harga Satuan 74,705.00
Acuan : Harga Satuan Bahan, Upah dan Analisa Biaya Pekerjaan BOW - F.16
1m2 Pasang Kasau + Reng Atap Genteng Metal Kayu Kelas II (P.K. 28)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 45,000.00 0.100 4,500.00
2 Tukang Kayu OH 60,000.00 0.100 6,000.00
3 Kepala Tukang OH 85,500.00 0.010 855.00
4 Mandor OH 70,000.00 0.005 350.00
Jumlah 11,705.00
B BAHAN
1 Kayu Kelas II (Tidak Ketam) M3 3,050,000.00 0.014 42,700.00
2 Paku Kg 20,000.00 0.150 3,000.00
Jumlah 45,700.00
C Jumlah A + B 57,405.00
D Harga Satuan 57,405.00
Acuan : ABK Bangunan Gedung dan Perumahan - 6.35
1m2 Pasang Rangka Langit-langit (1.00 x 1.00) m Kayu Kelas II (P.K. 29)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 45,000.00 0.150 6,750.00
2 Tukang Kayu OH 60,000.00 0.250 15,000.00
3 Kepala Tukang OH 85,500.00 0.025 2,137.50
4 Mandor OH 70,000.00 0.075 5,250.00
Jumlah 29,137.50
B BAHAN
1 Kayu Kelas II (Tidak Ketam) M3 3,050,000.00 0.012 36,600.00
2 Paku Kg 20,000.00 0.100 2,000.00
Jumlah 38,600.00
C Jumlah A + B 67,737.50
D Harga Satuan 67,737.50
Acuan : ABK Bangunan Gedung dan Perumahan - 6.38
ANALISA 25
1m2 Pasang Rangka Langit-langit (30 x 60)cm Kayu Kelas II (P.K. 30)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 45,000.00 0.200 9,000.00
2 Tukang Kayu OH 60,000.00 0.300 18,000.00
3 Kepala Tukang OH 85,500.00 0.030 2,565.00
4 Mandor OH 70,000.00 0.010 700.00
Jumlah 30,265.00
B BAHAN
1 Kayu Kelas II (Tidak Ketam) M3 3,050,000.00 0.023 70,150.00
2 Paku Kg 20,000.00 0.150 3,000.00
Jumlah 73,150.00
C Jumlah A + B 103,415.00
D Harga Satuan 103,415.00
Acuan : ABK Bangunan Gedung dan Perumahan - 6.41
1m2 Pasang Rangka Langit-langit (30 x 30)cm Kayu Kelas II (P.K. 31)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 45,000.00 0.250 11,250.00
2 Tukang Kayu OH 60,000.00 0.350 21,000.00
3 Kepala Tukang OH 85,500.00 0.035 2,992.50
4 Mandor OH 70,000.00 0.0125 875.00
Jumlah 36,117.50
B BAHAN
1 Kayu Kelas II (Tidak Ketam) M3 3,050,000.00 0.027 82,350.00
2 Paku Kg 20,000.00 0.200 4,000.00
Jumlah 86,350.00
C Jumlah A + B 122,467.50
D Harga Satuan 122,467.50
Acuan : ABK Bangunan Gedung dan Perumahan - 6.44
ANALISA 26
1m1 Pasang Lisplank Ukuran 2 x (2 x 20cm) Kayu Belian (P.K. 34)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 45,000.00 0.100 4,500.00
2 Tukang Kayu OH 60,000.00 0.100 6,000.00
3 Kepala Tukang OH 85,500.00 0.010 855.00
4 Mandor OH 70,000.00 0.050 3,500.00
Jumlah 14,855.00
B BAHAN
1 Papan Kayu Belian (Ketam) M3 13,749,000.00 0.0088 120,991.20
2 Paku Beton Kg 29,790.00 0.060 1,787.40
Jumlah 122,778.60
C Jumlah A + B 137,633.60
D Harga Satuan 137,633.60
Acuan : ABK Bangunan Gedung dan Perumahan - 6.53
ANALISA 27
1m2 Pasang Rangka Dinding Pemisah Kayu Kelas II (P.K. 38)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 45,000.00 0.150 6,750.00
2 Tukang Kayu OH 60,000.00 0.450 27,000.00
3 Kepala Tukang OH 85,500.00 0.045 3,847.50
4 Mandor OH 70,000.00 0.075 5,250.00
Jumlah 42,847.50
B BAHAN
1 Balok Kayu Kelas II (Tidak Ketam) M3 2,900,000.00 0.0195 56,550.00
2 Papan Kayu Kelas II (Tidak Ketam) M3 3,250,000.00 0.007 22,750.00
3 Paku Kg 20,000.00 0.100 2,000.00
Jumlah 81,300.00
C Jumlah A + B 124,147.50
D Harga Satuan 124,147.50
Acuan : ABK Bangunan Gedung dan Perumahan - 6.54
1m2 Pasang Dinding Pemisah Teakwood Rangkap, Rangka Kayu Kelas I (P.K. 39)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 45,000.00 0.200 9,000.00
2 Tukang Kayu OH 60,000.00 0.600 36,000.00
3 Kepala Tukang OH 85,500.00 0.060 5,130.00
4 Mandor OH 70,000.00 0.010 700.00
Jumlah 50,830.00
B BAHAN
1 Balok Kayu Kelas I (Tidak Ketam) M3 3,860,000.00 0.0195 75,270.00
2 Papan Kayu Kelas I (Tidak Ketam) M3 4,510,000.00 0.007 31,570.00
3 Paku Kg 20,000.00 0.100 2,000.00
4 Lem Kayu Ltr 18,000.00 0.560 10,080.00
5 Plywood 4' x 8' x 4mm Kg 110,000.00 1.000 110,000.00
Jumlah 228,920.00
C Jumlah A + B 279,750.00
D Harga Satuan 279,750.00
Acuan : ABK Bangunan Gedung dan Perumahan - 6.56
1m2 Pasang Dinding Pemisah Teakwood Rangkap, Rangka Kayu Kelas II (P.K. 40)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 45,000.00 0.200 9,000.00
2 Tukang Kayu OH 60,000.00 0.600 36,000.00
3 Kepala Tukang OH 85,500.00 0.060 5,130.00
4 Mandor OH 70,000.00 0.010 700.00
Jumlah 50,830.00
B BAHAN
1 Balok Kayu Kelas II (Tidak Ketam) M3 2,900,000.00 0.0195 56,550.00
2 Papan Kayu Kelas II (Tidak Ketam) M3 3,250,000.00 0.007 22,750.00
3 Paku Kg 20,000.00 0.100 2,000.00
4 Lem Kayu Ltr 18,000.00 0.560 10,080.00
5 Plywood 4' x 8' x 4mm Kg 110,000.00 1.000 110,000.00
Jumlah 201,380.00
C Jumlah A + B 252,210.00
D Harga Satuan 252,210.00
Acuan : ABK Bangunan Gedung dan Perumahan - 6.56
ANALISA 28
1m2 Pasang Dinding Lambriziring dari Kayu Kelas I (P.K. 42)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 45,000.00 0.600 27,000.00
2 Tukang Kayu OH 60,000.00 1.800 108,000.00
3 Kepala Tukang OH 85,500.00 0.180 15,390.00
4 Mandor OH 70,000.00 0.030 2,100.00
Jumlah 152,490.00
B BAHAN
1 Papan Kayu Kelas I (Ketam) M3 4,510,000.00 0.007 31,570.00
2 Sekrup Kg 21,600.00 0.150 3,240.00
3 Paku Kg 20,000.00 0.100 2,000.00
Jumlah 36,810.00
C Jumlah A + B 189,300.00
D Harga Satuan 189,300.00
Acuan : ABK Bangunan Gedung dan Perumahan - 6.58
ANALISA 29
1m2 Pemasangan Lantai Papan Kayu Kelas I (P.K. 46)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Tukang Kayu OH 60,000.00 1.800 108,000.00
2 Pekerja OH 45,000.00 0.600 27,000.00
3 Kepala Tukang OH 85,500.00 0.180 15,390.00
4 Mandor OH 70,000.00 0.030 2,100.00
Jumlah 152,490.00
B BAHAN
1 Papan Kayu Kelas I (Ketam) M3 4,510,000.00 0.0240 108,240.00
2 Paku Kg 20,000.00 0.200 4,000.00
Jumlah 112,240.00
C Jumlah A + B 264,730.00
D Harga Satuan 264,730.00
Acuan : Harga Satuan Bahan, Upah dan Analisa Biaya Pekerjaan BOW - F.38
Jumlah 0.00
C Jumlah A + B 21,987.50
D Harga Satuan 7,321.84
Acuan : Harga Satuan Bahan, Upah dan Analisa Biaya Pekerjaan BOW - E.1
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Tukang Kayu OH 60,000.00 18.000 1,080,000.00
2 Kepala Tukang OH 85,500.00 1.800 153,900.00
3 Pekerja OH 45,000.00 6.000 270,000.00
4 Mandor OH 70,000.00 0.300 21,000.00
Jumlah 1,524,900.00
B BAHAN
1 Balok Kayu Kelas II (Tidak Ketam) M3 3,050,000.00 1.100 3,355,000.00
2 Paku Kg 20,000.00 3.000 60,000.00
Jumlah 3,415,000.00
C Jumlah A + B 4,939,900.00
D Harga Satuan 4,939,900.00
Acuan : Harga Satuan Bahan, Upah dan Analisa Biaya Pekerjaan BOW - F.2
ANALISA 30
1m2 Pasang Pintu Double Triplek Lapis Sungkai / Nyatoh, Rangka Kayu Kelas I + Kaca (P.K. 49)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 45,000.00 1.000 45,000.00
2 Tukang Kayu OH 60,000.00 3.000 180,000.00
3 Kepala Tukang OH 85,500.00 0.300 25,650.00
4 Mandor OH 70,000.00 0.300 21,000.00
Jumlah 271,650.00
B BAHAN
1 Balok Kayu Klas I ( Ketam ) M3 4,110,000.00 0.0196 80,556.00
2 Paku 1/2" -1" Kg 20,000.00 0.030 600.00
3 Lem Kayu Lt 18,000.00 0.300 5,400.00
4 Lapisan Sungkai/ Nyatoh Lbr 276,000.00 0.400 110,400.00
5 Kaca 5 mm M2 120,000.00 1.000 120,000.00
6 Triplek Lbr 65,000.00 0.400 26,000.00
Jumlah 342,956.00
C Jumlah A + B 614,606.00
D Harga Satuan 614,606.00
Acuan : ABK Bangunan Gedung dan Perumahan - 6.14
1m2 Pasang Dinding Partisi Double Triplek Lapis Sungkai / Nyatoh, Rangka Kayu Kelas II (P.K. 50)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 45,000.00 0.200 9,000.00
2 Tukang Kayu OH 60,000.00 0.600 36,000.00
3 Kepala Tukang OH 85,500.00 0.060 5,130.00
4 Mandor OH 70,000.00 0.010 700.00
Jumlah 50,830.00
B BAHAN
1 Balok Kayu Kelas II ( Ketam) M3 2,900,000.00 0.0195 56,550.00
2 Triplek M3 65,000.00 0.700 45,500.00
3 Paku Kg 20,000.00 0.100 2,000.00
4 Lem Kayu Ltr 18,000.00 0.560 10,080.00
5 Sungkai / Nyatoh Lembar 276,000.00 0.700 193,200.00
Jumlah 307,330.00
C Jumlah A + B 358,160.00
D Harga Satuan 358,160.00
Acuan : ABK Bangunan Gedung dan Perumahan - 6.56
1m2 Pasang Atap Genteng Metal Type PRIMA 0.35 (P.PA. 01)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 45,000.00 0.200 9,000.00
2 Tukang kayu OH 60,000.00 0.100 6,000.00
3 Kepala Tukang OH 85,500.00 0.010 855.00
4 Mandor OH 70,000.00 0.001 70.00
Jumlah 15,925.00
B BAHAN
1 Genteng Metal Type PRIMA 0.35 Lbr 47,500.00 1.840 87,400.00
2 Paku Kg 26,000.00 0.200 5,200.00
Jumlah 92,600.00
C Jumlah A + B 108,525.00
D Harga Satuan 108,525.00
Acuan : ABK Bangunan Gedung dan Perumahan - 6.32
ANALISA 31
1m2 Pasang Atap Genteng Metal Type ROYAL 0.35 (P.PA. 02)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 45,000.00 0.200 9,000.00
2 Tukang kayu OH 60,000.00 0.100 6,000.00
3 Kepala Tukang OH 85,500.00 0.010 855.00
4 Mandor OH 70,000.00 0.001 70.00
Jumlah 15,925.00
B BAHAN
1 Genteng Metal Type ROYAL 0.35 Lbr 56,200.00 1.710 96,102.00
2 Paku Kg 26,000.00 0.200 5,200.00
Jumlah 101,302.00
C Jumlah A + B 117,227.00
D Harga Satuan 117,227.00
Acuan : ABK Bangunan Gedung dan Perumahan - 6.32
1m2 Pasang Atap Genteng Metal Type CLASSIC 0.35 (P.PA. 03)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 45,000.00 0.200 9,000.00
2 Tukang kayu OH 60,000.00 0.100 6,000.00
3 Kepala Tukang OH 85,500.00 0.010 855.00
4 Mandor OH 70,000.00 0.001 70.00
Jumlah 15,925.00
B BAHAN
1 Genteng Metal Type CLASSIC 0.35 Lbr 98,000.00 1.620 158,760.00
2 Paku Kg 26,000.00 0.200 5,200.00
Jumlah 163,960.00
C Jumlah A + B 179,885.00
D Harga Satuan 179,885.00
Acuan : ABK Bangunan Gedung dan Perumahan - 6.32
1m2 Pasang Atap Genteng Metal Stone Type CLASSIC 0.35 (P.PA. 04)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 45,000.00 0.200 9,000.00
2 Tukang kayu OH 60,000.00 0.100 6,000.00
3 Kepala Tukang OH 85,500.00 0.010 855.00
4 Mandor OH 70,000.00 0.001 70.00
Jumlah 15,925.00
B BAHAN
1 Genteng Metal Stone Type CLASSIC 0.35 Lbr 102,000.00 1.620 165,240.00
2 Paku Kg 26,000.00 0.200 5,200.00
Jumlah 170,440.00
C Jumlah A + B 186,365.00
D Harga Satuan 186,365.00
Acuan : ABK Bangunan Gedung dan Perumahan - 6.32
1m2 Pasang Atap Genteng Metal Stone Type PRIMA 0.35 (P.PA. 05)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 45,000.00 0.200 9,000.00
2 Tukang kayu OH 60,000.00 0.100 6,000.00
3 Kepala Tukang OH 85,500.00 0.010 855.00
4 Mandor OH 70,000.00 0.001 70.00
Jumlah 15,925.00
B BAHAN
1 Genteng Metal Stone Type PRIMA 0.35 Lbr 75,600.00 1.840 139,104.00
2 Paku Kg 26,000.00 0.200 5,200.00
Jumlah 144,304.00
C Jumlah A + B 160,229.00
D Harga Satuan 160,229.00
Acuan : ABK Bangunan Gedung dan Perumahan - 6.32
ANALISA 32
1m2 Pasang Atap Genteng Metal Sirap 0.40 (P.PA. 05.a)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 45,000.00 0.200 9,000.00
2 Tukang kayu OH 60,000.00 0.100 6,000.00
3 Kepala Tukang OH 85,500.00 0.010 855.00
4 Mandor OH 70,000.00 0.001 70.00
Jumlah 15,925.00
B BAHAN
1 Genteng Metal Sirap 0,40 mm type borneo m2 270,900.00 1.000 270,900.00
2 Paku Kg 26,000.00 0.200 5,200.00
Jumlah 276,100.00
C Jumlah A + B 292,025.00
D Harga Satuan 292,025.00
Acuan : ABK Bangunan Gedung dan Perumahan - 6.32
1m1 Pekerjaan Bubungan dengan Seng Datar Color 0.35 / 10 m 1 (P.PA. 07)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 45,000.00 0.250 11,250.00
2 Tukang kayu OH 60,000.00 0.250 15,000.00
3 Kepala Tukang OH 85,500.00 0.025 2,137.50
Jumlah 28,387.50
B BAHAN
1 Paku Kg 20,000.00 0.100 2,000.00
2 Seng Datar Color 0.35 Lbr 66,000.00 6.000 396,000.00
3 Papan Kayu Kelas II (tdk ketam) M3 4,510,000.00 0.072 324,720.00
Jumlah 722,720.00
C Jumlah A + B 751,107.50
D Harga Satuan 751,107.50
Jadi 1 M1 75,110.75
Acuan : Harga Satuan Bahan, Upah dan Analisa Biaya Pekerjaan BOW - H.10
1m1 Pasang Nok / Bumbungan Genteng Metal 1/2 Lingkaran 0.35 (P.PA. 08)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 45,000.00 0.250 11,250.00
2 Tukang kayu OH 60,000.00 0.150 9,000.00
3 Kepala Tukang OH 85,500.00 0.015 1,282.50
4 Mandor OH 70,000.00 0.013 910.00
Jumlah 22,442.50
B BAHAN
1 Nok / Bubungan Genteng Metal 1/2 lingk 0.35 Bh 55,000.00 2.500 137,500.00
2 Paku 1/2" - 1" Kg 20,000.00 0.050 1,000.00
Jumlah 138,500.00
C Jumlah A + B 160,942.50
D Harga Satuan 160,942.50
Acuan : ABK Bangunan Gedung dan Perumahan - 6.36
ANALISA 33
1m1 Pasang Nok / Bumbungan Genteng Metal Kotak 0.35 (P.PA. 09)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 45,000.00 0.250 11,250.00
2 Tukang kayu OH 60,000.00 0.150 9,000.00
3 Kepala Tukang OH 85,500.00 0.015 1,282.50
4 Mandor OH 70,000.00 0.013 910.00
Jumlah 22,442.50
B BAHAN
1 Nok / Bubungan Genteng Metal Kotak 0.35 Meter 78,000.00 1.000 78,000.00
2 Paku 1/2" - 1" Kg 20,000.00 0.050 1,000.00
Jumlah 79,000.00
C Jumlah A + B 101,442.50
D Harga Satuan 101,442.50
Acuan : ABK Bangunan Gedung dan Perumahan - 6.36
1m1 Pasang Nok / Bumbungan Genteng Metal Stone Kotak 0.35 (P.PA. 10)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 45,000.00 0.250 11,250.00
2 Tukang kayu OH 60,000.00 0.150 9,000.00
3 Kepala Tukang OH 85,500.00 0.015 1,282.50
4 Mandor OH 70,000.00 0.013 910.00
Jumlah 22,442.50
B BAHAN
1 Nok / Bubungan Genteng Metal Stone Kotak Meter 90,000.00 1.000 90,000.00
2 Paku 1/2" - 1" Kg 20,000.00 0.050 1,000.00
Jumlah 91,000.00
C Jumlah A + B 113,442.50
D Harga Satuan 113,442.50
Acuan : ABK Bangunan Gedung dan Perumahan - 6.36
ANALISA 34
1m1 Pekerjaan Bubungan Atap Seng BJLS 30 / 10m1 (P.PA. 13)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Tukang Kayu OH 60,000.00 0.250 15,000.00
2 Kepala Tukang Kayu OH 85,500.00 0.025 2,137.50
3 Pekerja OH 45,000.00 0.250 11,250.00
Jumlah 28,387.50
B BAHAN
1 Paku Kg 20,000.00 0.100 2,000.00
2 Seng Plat BJLS 0.30 Lbr 87,700.00 6.000 526,200.00
3 Papan Kayu Kelas II (Tidak Ketam) M3 3,250,000.00 0.072 234,000.00
Jumlah 762,200.00
C Jumlah A + B 790,587.50
D Harga Satuan 790,587.50
Jadi 1 M1 79,058.75
Acuan : Harga Satuan Bahan, Upah dan Analisa Biaya Pekerjaan BOW - H.10
ANALISA 35
1m2 Langit-langit Gypsum Board, Tebal 9mm (P.Pf. 03)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 45,000.00 0.100 4,500.00
2 Tukang Kayu OH 60,000.00 0.050 3,000.00
3 Kepala Tukang OH 85,500.00 0.005 427.50
4 Mandor OH 70,000.00 0.005 350.00
Jumlah 8,277.50
B BAHAN
1 Gypsum Board (120 x 240 x 9) Lbr 75,600.00 0.364 27,518.40
2 Paku Sekrup Gypsum Kg 21,600.00 0.110 2,376.00
Jumlah 29,894.40
C Jumlah A + B 38,171.90
D Harga Satuan 38,171.90
Acuan : ABK Bangunan Gedung dan Perumahan - 6.24
ANALISA 36
Memasang 1m1 Pipa Galvanis Ø 1/2" (P.Snt. 03)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 45,000.00 0.054 2,430.00
2 Tukang Batu OH 60,000.00 0.090 5,400.00
3 Kepala Tukang OH 85,500.00 0.009 769.50
4 Mandor OH 70,000.00 0.027 1,890.00
Jumlah 10,489.50
B BAHAN
1 Pipa Galvanis Ø 1/2 " M1 86,225.00 1.200 103,470.00
2 Perlengkapan Ls 86,225.00 35% Harga Pipa 30,178.75
Jumlah 133,648.75
C Jumlah A + B 144,138.25
D Harga Satuan 144,138.25
Acuan : ABK Bangunan Gedung dan Perumahan - 6.19
ANALISA 37
Memasang 1m1 Pipa Galvanis Ø 3" (P.Snt. 07)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 45,000.00 0.108 4,860.00
2 Tukang Batu OH 60,000.00 0.180 10,800.00
3 Kepala Tukang OH 85,500.00 0.018 1,539.00
4 Mandor OH 70,000.00 0.005 378.00
Jumlah 17,577.00
B BAHAN
1 Pipa Galvanis Ø 3" M1 120,600.00 1.200 144,720.00
2 Perlengkapan Ls 120,600.00 35% Harga Pipa 42,210.00
Jumlah 186,930.00
C Jumlah A + B 204,507.00
D Harga Satuan 204,507.00
Acuan : ABK Bangunan Gedung dan Perumahan - 6.23
ANALISA 38
Memasang 1m1 Pipa PVC Tipe AW Ø 1" (P.Snt. 11)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 45,000.00 0.036 1,620.00
2 Tukang Batu OH 60,000.00 0.060 3,600.00
3 Kepala Tukang OH 85,500.00 0.006 513.00
4 Mandor OH 70,000.00 0.0018 126.00
Jumlah 5,859.00
B BAHAN
1 Pipa PVC Ø 1" M1 12,425.00 1.200 14,910.00
2 Perlengkapan Ls 12,425.00 35% Harga Pipa 4,348.75
Jumlah 19,258.75
C Jumlah A + B 25,117.75
D Harga Satuan 25,117.75
Acuan : ABK Bangunan Gedung dan Perumahan - 6.27
ANALISA 39
Memasang 1 Buah Kran Air Ø 3/4" atau Ø 1/2" (P.Snt. 15)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 45,000.00 0.010 450.00
2 Tukang Batu OH 60,000.00 0.100 6,000.00
3 Kepala Tukang OH 85,500.00 0.010 855.00
4 Mandor OH 70,000.00 0.005 350.00
Jumlah 7,655.00
B BAHAN
1 Kran Air 3/4 " Bh 38,400.00 1.000 38,400.00
2 Seal Tape Set 2,000.00 0.025 50.00
Jumlah 38,450.00
C Jumlah A + B 46,105.00
D Harga Satuan 46,105.00
Acuan : ABK Bangunan Gedung dan Perumahan - 6.35
ANALISA 40
1m2 Pasang Kawat Kassa (P.BA. 04)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 45,000.00 0.100 4,500.00
2 Tukang Kayu OH 60,000.00 0.100 6,000.00
3 Kepala Tukang OH 85,500.00 0.010 855.00
4 Mandor OH 70,000.00 0.0005 35.00
Jumlah 11,390.00
B BAHAN
1 Kawat Kassa M2 23,160.00 1.100 25,476.00
2 Paku 1/2" - 1" Kg 20,000.00 0.020 400.00
3 Papan Kayu Kelas 2 Ketam M3 3,250,000.00 0.0018 5,850.00
Jumlah 31,726.00
C Jumlah A + B 43,116.00
D Harga Satuan 43,116.00
Acuan : ABK Bangunan Gedung dan Perumahan - 6.15
1m2 Pasang Talang Datar Seng BJLS 30 / Talang Sembunyi (P.BA. 06)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 45,000.00 0.150 6,750.00
2 Tukang Kayu OH 60,000.00 0.400 24,000.00
3 Kepala Tukang OH 85,500.00 0.025 2,137.50
4 Mandor OH 70,000.00 0.00125 87.50
Jumlah 32,975.00
B BAHAN
1 Seng Plat 3' x 6' BJLS 30 Lbr 85,500.00 0.500 42,750.00
2 Paku 1/2" - 1" Kg 20,000.00 0.015 300.00
3 Papan Kayu Kelas 2 Tidak Ketam M3 3,250,000.00 0.0096 31,200.00
4 Meni Kg 47,160.00 0.250 11,790.00
Jumlah 86,040.00
C Jumlah A + B 119,015.00
D Harga Satuan 119,015.00
Acuan : ABK Bangunan Gedung dan Perumahan - 6.18
1m2 Pasang Talang Miring Seng BJLS 30 / Jurai Dalam (P.BA. 07)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1
Pekerja OH 45,000.00 0.040 1,800.00
2
Tukang Kayu OH 60,000.00 0.400 24,000.00
3
Kepala Tukang OH 85,500.00 0.025 2,137.50
4
Mandor OH 70,000.00 0.00125 87.50
Jumlah 28,025.00
B BAHAN
1 Seng Plat 3' x 6' BJLS 30 Lbr 85,500.00 0.50 42,750.00
2 Paku 1/2" - 1" Kg 20,000.00 0.015 300.00
3 Papan Kayu Kelas 2 Tidak Ketam M3 3,250,000.00 0.019 61,750.00
4 Meni Kg 47,160.00 0.300 14,148.00
Jumlah 118,948.00
C Jumlah A + B 146,973.00
D Harga Satuan 146,973.00
Acuan : ABK Bangunan Gedung dan Perumahan - 6.19
ANALISA 41
10m1 Talang Cucuran Atap 1/2 Lingkaran Ø 15cm BJLS 30 (P.BA. 08)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Tukang Kayu OH 60,000.00 5.000 300,000.00
2 Kepala Tukang Kayu OH 85,500.00 0.500 42,750.00
3 Pekerja OH 45,000.00 3.000 135,000.00
4 Mandor OH 70,000.00 0.150 10,500.00
Jumlah 488,250.00
B BAHAN
1 Seng Plat BJLS 30 Lbr 85,500.00 3.000 256,500.00
2 Besi Penahan Bh 12,600.00 9.000 113,400.00
Jumlah 369,900.00
C Jumlah A + B 858,150.00
D Harga Satuan 858,150.00
Jadi 1m1 85,815.00
Acuan : Harga Satuan Bahan, Upah dan Analisa Biaya Pekerjaan BOW - H.17
10m1 Pemasangan Pipa Pembuangan dari Talang Atap Ø 8cm BJLS 30 (P.BA. 09)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Tukang Kayu OH 60,000.00 3.750 225,000.00
2 Kepala Tukang Kayu OH 85,500.00 0.375 32,062.50
3 Pekerja OH 45,000.00 2.250 101,250.00
4 Mandor OH 70,000.00 0.110 7,700.00
Jumlah 366,012.50
B BAHAN
1 Seng Plat BJLS 30 Lbr 85,500.00 2.500 213,750.00
Jumlah 213,750.00
C Jumlah A + B 579,762.50
D Harga Satuan 579,762.50
Jadi 1m1 57,976.25
Acuan : Harga Satuan Bahan, Upah dan Analisa Biaya Pekerjaan BOW - H.18
ANALISA 42
1 Buah Pemasangan Kunci Silinder (P.KK. 03)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 45,000.00 0.005 225.00
2 Tukang Kayu OH 60,000.00 0.500 30,000.00
3 Kepala Tukang OH 85,500.00 0.005 427.50
4 Mandor OH 70,000.00 0.00025 17.50
Jumlah 30,670.00
B BAHAN
1 Kunci Tanam Silinder Bh 102,000.00 1.000 102,000.00
Jumlah 102,000.00
C Jumlah A + B 132,670.00
D Harga Satuan 132,670.00
Acuan : ABK Bangunan Gedung dan Perumahan - 6.4
ANALISA 43
1 Buah Pemasangan Door Stoper (P.KK. 08)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 45,000.00 0.010 450.00
2 Tukang Kayu OH 60,000.00 0.100 6,000.00
3 Kepala Tukang OH 85,500.00 0.010 855.00
4 Mandor OH 70,000.00 0.0005 35.00
Jumlah 7,340.00
B BAHAN
1 Door Stoper Bh 18,000.00 1.000 18,000.00
Jumlah 18,000.00
C Jumlah A + B 25,340.00
D Harga Satuan 25,340.00
Acuan : ABK Bangunan Gedung dan Perumahan - 6.13
ANALISA 44
1 Buah Pemasangan Engsel Jendela (P.KK. 13)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 45,000.00 0.015 675.00
2 Tukang Kayu OH 60,000.00 0.150 9,000.00
3 Kepala Tukang OH 85,500.00 0.015 1,282.50
4 Mandor OH 70,000.00 0.00075 52.50
Jumlah 11,010.00
B BAHAN
1 Engsel Jendela Bh 12,500.00 1.000 12,500.00
Jumlah 12,500.00
C Jumlah A + B 23,510.00
D Harga Satuan 23,510.00
Acuan : ABK Bangunan Gedung dan Perumahan - 6.5
ANALISA 45
1m2 Pasang Lantai Keramik 30 x 30cm Antigores (P.LD. 03)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 45,000.00 0.260 11,700.00
2 Tukang Batu OH 60,000.00 0.125 7,500.00
3 Kepala Tukang OH 85,500.00 0.0125 1,068.75
4 Mandor OH 70,000.00 0.013 910.00
Jumlah 21,178.75
B BAHAN
1 Ubin Keramik 30 x 30cm Unpolished Bh 8,460.00 11.870 100,420.20
2 Semen Portland Kg 1,882.00 10.000 18,820.00
3 Pasir Pasang M3 75,000.00 0.0215 1,612.50
120,852.70
C Jumlah A + B 142,031.45
D Harga Satuan 142,031.45
Acuan : ABK Bangunan Gedung dan Perumahan - 6.2
ANALISA 46
1m2 Pasang Lantai Marmer (P.LD. 07)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 45,000.00 0.620 27,900.00
2 Tukang Batu OH 60,000.00 0.350 21,000.00
3 Kepala Tukang OH 85,500.00 0.035 2,992.50
4 Mandor OH 70,000.00 0.030 2,100.00
Jumlah 53,992.50
B BAHAN
1 Marmer M2 491,400.00 1.0520 516,952.80
2 Semen Portland Kg 1,882.00 14.15 26,630.30
3 Pasir Pasang M3 75,000.00 0.039 2,925.00
4 Oker Pengisi Nat Marmer Kg 63,000.00 0.200 12,600.00
559,108.10
C Jumlah A + B 613,100.60
D Harga Satuan 613,100.60
Acuan : ABK Bangunan Gedung dan Perumahan - 6.51
ANALISA 47
1m2 Pasang Dinding Keramik 20 x 20cm (P.LD. 11)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 45,000.00 0.600 27,000.00
2 Tukang Batu OH 60,000.00 0.450 27,000.00
3 Kepala Tukang OH 85,500.00 0.045 3,847.50
4 Mandor OH 70,000.00 0.030 2,100.00
Jumlah 59,947.50
B BAHAN
1 Keramik 20 x 20 cm Bh 2,500.00 25.000 62,500.00
2 Semen Kg 1,882.00 9.300 17,502.60
3 Pasir Pasang M3 75,000.00 0.018 1,350.00
4 Semen Pengisi Nat Keramik Kg 1,882.00 0.200 376.40
81,729.00
C Jumlah A + B 141,676.50
D Harga Satuan 141,676.50
Acuan : ABK Bangunan Gedung dan Perumahan - 6.63
ANALISA 48
1m2 Mengerok Karat Cat Lama Permukaan Baja dengan Cara Manual (P.Ct. 02)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 45,000.00 0.150 6,750.00
2 Mandor OH 70,000.00 0.0025 175.00
Jumlah 6,925.00
B BAHAN
1 Sabun Kg 17,400.00 0.050 870.00
870.00
C Jumlah A + B 7,795.00
D Harga Satuan 7,795.00
Acuan : ABK Bangunan Gedung dan Perumahan - 6.3
1m2 Pengecatan Bidang Kayu Baru (1Lapis Plamir, 1Lapis Cat Dasar, 2Lapis Cat Penutup) (P.Ct. 04)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 45,000.00 0.070 3,150.00
2 Tukang Cat OH 60,000.00 0.009 540.00
3 Kepala Tukang OH 85,500.00 0.006 513.00
4 Mandor OH 70,000.00 0.0025 175.00
Jumlah 4,378.00
B BAHAN
1 Cat Meni Kayu Kg 38,400.00 0.200 7,680.00
2 Plamur (dempul kayu) Kg 18,000.00 0.150 2,700.00
3 Cat Dasar Kayu Kg 27,600.00 0.170 4,692.00
4 Cat Kilat Penutup 2 Kali Kg 49,000.00 0.260 12,740.00
27,812.00
C Jumlah A + B 32,190.00
D Harga Satuan 32,190.00
Acuan : ABK Bangunan Gedung dan Perumahan - 6.8
1m2 Pengecatan Bidang Kayu Baru (1Lapis Plamir, 1Lapis Cat Dasar, 3Lapis Cat Penutup) (P.Ct. 05)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 45,000.00 0.070 3,150.00
2 Tukang Cat OH 60,000.00 0.105 6,300.00
3 Kepala Tukang OH 85,500.00 0.004 342.00
4 Mandor OH 70,000.00 0.0025 175.00
Jumlah 9,967.00
B BAHAN
1 Cat Meni Kg 38,400.00 0.200 7,680.00
2 Plamur (dempul kayu) Kg 18,000.00 0.150 2,700.00
3 Cat Dasar Kayu Kg 27,600.00 0.170 4,692.00
4 Cat Kilat Penutup 3 Kali Kg 49,000.00 0.350 17,150.00
32,222.00
C Jumlah A + B 42,189.00
D Harga Satuan 42,189.00
Acuan : ABK Bangunan Gedung dan Perumahan - 6.9
ANALISA 49
1m2 Pelaburan Bidang Kayu dengan Teak Oil (P.Ct. 06)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 45,000.00 0.040 1,800.00
2 Tukang Cat OH 60,000.00 0.063 3,780.00
3 Kepala Tukang OH 85,500.00 0.063 5,386.50
4 Mandor OH 70,000.00 0.0025 175.00
Jumlah 11,141.50
B BAHAN
1 Teak Oil Ltr 28,800.00 0.360 10,368.00
10,368.00
C Jumlah A + B 21,509.50
D Harga Satuan 21,509.50
Acuan : ABK Bangunan Gedung dan Perumahan - 6.10
1m2 Pelaburan Bidang Kayu Dengan Cat Residu dan Ter (P.Ct. 09)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Tukang Cat OH 60,000.00 0.100 6,000.00
2 Kepala Tukang OH 85,500.00 0.006 513.00
Jumlah 6,513.00
B BAHAN
1 Residu dan Ter Ltr 15,900.00 0.350 5,565.00
5,565.00
C Jumlah A + B 12,078.00
D Harga Satuan 12,078.00
Acuan : ABK Bangunan Gedung dan Perumahan - 6.12
ANALISA 50
1m2 Pengecatan Tembok Baru (1 Lapis Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup)
Dengan Cat Mutu Baik. (P.Ct. 11)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 45,000.00 0.020 900.00
2 Tukang Cat OH 60,000.00 0.063 3,780.00
3 Kepala Tukang OH 85,500.00 0.0063 538.65
4 Mandor OH 70,000.00 0.0025 175.00
Jumlah 5,393.65
B BAHAN
1 Plamur (dempul tembok) Kg 16,100.00 0.100 1,610.00
2 Cat Dasar tembok Kg 27,600.00 0.120 3,312.00
3 Cat Tembok Penutup 2 x Kg 17,700.00 0.260 4,602.00
9,524.00
C Jumlah A + B 14,917.65
D Harga Satuan 14,917.65
Acuan : ABK Bangunan Gedung dan Perumahan - 6.14
1m2 Pengecatan Tembok Baru (1 Lapis Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup)
Dengan Cat Mutu Baik. (P.Ct. 11a)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 45,000.00 0.020 900.00
2 Tukang Cat OH 60,000.00 0.063 3,780.00
3 Kepala Tukang OH 85,500.00 0.0063 538.65
4 Mandor OH 70,000.00 0.0025 175.00
Jumlah 5,393.65
B BAHAN
1 Plamur (dempul tembok) Kg 16,100.00 0.100 1,610.00
2 Cat Dasar tembok Kg 27,600.00 0.120 3,312.00
3 Cat tembok Wheather Sheild Kg 51,500.00 0.260 13,390.00
18,312.00
C Jumlah A + B 23,705.65
D Harga Satuan 23,705.65
Acuan : ABK Bangunan Gedung dan Perumahan - 6.14
1m2 Pengecatan Tembok Lama (1 Lapis Cat Dasar, 2 Lapis Cat Penutup)
Dengan Cat Mutu Baik. (P.Ct. 12)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 45,000.00 0.028 1,260.00
2 Tukang Cat OH 60,000.00 0.042 2,520.00
3 Kepala Tukang OH 85,500.00 0.0042 359.10
4 Mandor OH 70,000.00 0.0025 175.00
Jumlah 4,314.10
B BAHAN
1 Cat Dasar tembok Kg 27,600.00 0.120 3,312.00
2 Cat Tembok Penutup 2 x Kg 17,700.00 0.180 3,186.00
6,498.00
C Jumlah A + B 10,812.10
D Harga Satuan 10,812.10
Acuan : ABK Bangunan Gedung dan Perumahan - 6.15
ANALISA 51
1m2 Pengecatan Permukaan Baja dengan Meni Besi dan Perancah (P.Ct. 14)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Tukang Cat OH 45,000.00 0.250 11,250.00
2 Kepala Tukang OH 60,000.00 0.225 13,500.00
3 Pekerja OH 85,500.00 0.0225 1,923.75
4 Mandor OH 70,000.00 0.0075 525.00
Jumlah 27,198.75
B BAHAN
1 Meni Besi Kg 47,160.00 0.100 4,716.00
2 Kuas Bh 14,400.00 0.010 144.00
3 Perancah Kayu Kelas II M3 2,850,000.00 0.002 5,700.00
10,560.00
C Jumlah A + B 37,758.75
D Harga Satuan 37,758.75
Acuan : ABK Bangunan Gedung dan Perumahan - 6.21
Jumlah 0.00
C Jumlah A + B 323,325.00
D Harga Satuan 323,325.00
Acuan : ABK Bangunan Gedung dan Perumahan - 6.13
1m2 Pekerjaan Bongkaran Dinding Tembok Plesteran Simpai (P. Bkr. 02)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 45,000.00 1.000 45,000.00
2 Mandor OH 70,000.00 0.050 3,500.00
Jumlah 48,500.00
B BAHAN
Jumlah 0.00
C Jumlah A + B 48,500.00
D Harga Satuan 48,500.00
Acuan : Harga Satuan Bahan, Upah dan Analisa Biaya Pekerjaan BOW - L.4
Jumlah 0.00
C Jumlah A + B 2,425.00
D Harga Satuan 2,425.00
Acuan : Harga Satuan Bahan, Upah dan Analisa Biaya Pekerjaan BOW - L.5
ANALISA 52
1m2 Pekerjaan Bongkaran Atap Genteng / Sirap (P.Bkr. 04)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 45,000.00 0.010 450.00
2 Mandor OH 70,000.00 0.005 350.00
Jumlah 800.00
B BAHAN
Jumlah 0.00
C Jumlah A + B 800.00
D Harga Satuan 800.00
Acuan : Harga Satuan Bahan, Upah dan Analisa Biaya Pekerjaan BOW - L.7
Jumlah 0.00
C Jumlah A + B 8,000.00
D Harga Satuan 8,000.00
Acuan : Harga Satuan Bahan, Upah dan Analisa Biaya Pekerjaan BOW - L.8
Jumlah 0.00
C Jumlah A + B 48,500.00
D Harga Satuan 48,500.00
Acuan : Harga Satuan Bahan, Upah dan Analisa Biaya Pekerjaan BOW - L.9
Jumlah 0.00
C Jumlah A + B 403,533.33
D Harga Satuan 403,533.33
Acuan : Harga Satuan Bahan, Upah dan Analisa Biaya Pekerjaan BOW - L.13
ANALISA 53
REKAPITULASI ANALISA HARGA SATUAN
PROGRAM : PENINGKATAN SARANA DAN PRASARANA APARATUR
KEGIATAN : PEMBANGUNAN GEDUNG KANTOR PEMERINTAH I
PEKERJAAN : PEMBANGUNAN GEDUNG KANTOR DINAS PENDIDIKAN
LOKASI : JL. PEMBANGUNAN SAMBAS KAB. SAMBAS
TAHUN ANGGARAN : 2009
Rekapitulasi 54
KODE HARGA SATUAN
NO URAIAN PEKERJAAN
ANALISA (Rp)
1 2 3 4
G. PEKERJAAN KAYU……….(Sambungan)
22 P. K. 21 1m2 Pasang Pintu Plywood Rangkap, Rangka Kayu Kelas II (P.K. 21) 451,350.00
23 P. K. 22 1m2 Pemasangan Ventilasi Jalusie/Reng Lat Kayu Kelas I (P.K. 22) 185,805.90
1m2 Pemasangan Ventilasi Kaca
24 P. K. 23 186,620.00
Setiap luas 1 m2 bidang daun ventilasi, luas kacanya adalah 0.60 m2 (P.K. 23)
25 P. K. 24 1m3 Pasang Konstruksi Kuda-kuda Kayu Kelas I (P.K. 24) 5,878,600.00
26 P. K. 25 1m3 Pasang Konstruksi Kuda-kuda Kayu Kelas II (P.K. 25) 4,987,600.00
27 P. K. 26 1m2 Pemasangan Kasau + Reng Atap Sirap (P.K. 26) 74,705.00
28 P. K. 27 1m2 Pemasangan Rangka Atap Seng (P.K. 27) 49,553.89
29 P. K. 28 1m2 Pasang Kasau + Reng Atap Genteng Metal Kayu Kelas II (P.K. 28) 57,405.00
30 P. K. 29 1m2 Pasang Rangka Langit-langit (1.00 x 1.00) m Kayu Kelas II (P.K. 29) 67,737.50
31 P. K. 30 1m2 Pasang Rangka Langit-langit (30 x 60)cm Kayu Kelas II (P.K. 30) 103,415.00
32 P. K. 31 1m2 Pasang Rangka Langit-langit (30 x 30)cm Kayu Kelas II (P.K. 31) 122,467.50
33 P. K. 32 1m1 Pasang Lisplank Ukuran (3 x 20cm) Kayu Kelas I (P.K. 32) 52,032.00
34 P. K. 33 1m1 Pasang Lisplank Ukuran 2 x (3 x 20cm) Kayu Kelas I (P.K. 33) 95,732.50
35 P. K. 34 1m1 Pasang Lisplank Ukuran 2 x (2 x 20cm) Kayu Belian (P.K. 34) 137,633.60
36 P. K. 35 1m1 Pasang Lisplank Ukuran 2 x (2 x 20cm) Kayu Kelas I (P.K. 35) 55,743.00
37 P. K. 36 1m1 Pasang Lisplank Ukuran 2 x (2 x 20cm) Kayu Kelas II (P.K. 36) 44,655.00
38 P. K. 37 1m2 Pasang Rangka Dinding Pemisah Kayu Kelas I (P.K. 37) 151,687.50
39 P. K. 38 1m2 Pasang Rangka Dinding Pemisah Kayu Kelas II (P.K. 38) 124,147.50
40 P. K. 39 1m2 Pasang Dinding Pemisah Teakwood Rangkap, Rangka Kayu Kelas I (P.K. 39) 279,750.00
41 P. K. 40 1m2 Pasang Dinding Pemisah Teakwood Rangkap, Rangka Kayu Kelas II (P.K. 40) 252,210.00
42 P. K. 41 1m2 Pasang Dinding Lambriziring dari Kayu Belian (P.K. 41) 253,202.00
43 P. K. 42 1m2 Pasang Dinding Lambriziring dari Kayu Kelas I (P.K. 42) 189,300.00
44 P. K. 43 1m2 Pasang Plywood Tebal 4mm, Untuk Dinding (P.K. 43) 51,357.25
45 P. K. 44 1m1 Pasang List Plafond, Kayu Profil (P.K. 44) 10,321.00
46 P. K. 45 1m2 Pemasangan Lantai Papan Kayu Belian (P.K. 45) 488,424.00
47 P. K. 46 1m2 Pemasangan Lantai Papan Kayu Kelas I (P.K. 46) 264,730.00
48 P.K.47 1BTG Pemancangan Cerucuk / dolken dia. 12/15cm - 12 M (P.K. 47) 108,121.84
49 P.K.74a 1BTG Pemancangan Cerucuk / dolken dia. 8/10-4 m (P.K. 47a) 15,321.84
50 P.K.47b 1BTG Pemancangan Cerucuk / dolken dia. 8/10-2 m (P.K. 47b) 6,440.61
51 P.K.47c 1BTG Pemancangan Cerucuk / dolken dia. 8/10-1 m (P.K. 47c) 4,440.61
52 P.K.47d 1BTG Pemancangan Cerucuk / dolken dia. 12/15-6 m (P.K. 47d) 57,721.84
53 P.K.47e 1BTG Pemancangan Cerucuk / dolken dia. 12/15-10 m (P.K. 47e) 108,121.84
54 P.K.48 1m3 Pekerjaan Gording + Balok Angin Kayu Kelas II (P.K. 48) 4,939,900.00
55 P.K.49 1m2 Pasang Pintu Double Triplek Lapis Sungkai / Nyatoh, Rangka Kayu Kelas I + Kaca (P.K. 49) 614,606.00
56 P.K.50 1m2 Pasang Dinding Partisi Double Triplek Lapis Sungkai / Nyatoh, Rangka Kayu Kelas II (P.K. 50) 358,160.00
P. K. 51 1m3 Mengerjakan gelegar kayu Belian (P.K. 51) 14,015,950.00
Rekapitulasi 55
6 P. KK. 06 1 Buah Pemasangan Door Closer (P.KK. 06) 156,700.00
7 P. KK. 07 1 Buah Pemasangan Slot Pintu (P.KK. 07) 17,280.00
8 P. KK. 08 1 Buah Pemasangan Door Stoper (P.KK. 08) 25,340.00
9 P. KK. 09 1 m2 Pemasangan Kaca Tebal 5mm (P.KK. 09) 143,010.00
10 P. KK. 11 1 m2 Pemasangan Kaca Cermin, Tebal 3mm (P.KK. 11) 189,210.00
11 P. KK. 12 1 m2 Pemasangan Kaca Patri (P.KK. 12) 981,210.00
12 P.KK.13 1 Buah Pemasangan Engsel Jendela (P.KK. 13) 23,510.00
13 P.KK.14 1 Buah Pemasangan Slot Jendela (P.KK. 14) 16,680.00
Rekapitulasi 56
RENCANA ANGGARAN BIAYA
( ENGINEERING ESTIMATE / EE )
I PEK. PERSIAPAN
1 Pek. Pembersihan Lokasi P. Ps. 03 387.04 M2 8,000.00 3,096,320.00
2 Pek. Pemasangan Baouwplank P. Ps. 02 80.00 M' 34,315.00 2,745,200.00
3 Pek. Bangsal Kerja P. Ps. 04 20.00 M2 711,208.00 14,224,160.00
II PEK. PONDASI
1 Pek. Galian Tanah P. T. 01 301.57 M3 20,800.00 6,272,728.80
2 Pek. Urugan Kembali P. T. 06 211.10 M3 9,970.00 2,104,681.46
3 Pek. Urugan pasir t. 20 cm P. T. 10 35.38 M3 104,200.00 3,686,804.40
4 Pek. Cerucuk dia. 12/15- 12 m P.K.47e 1,050.00 Btg 108,121.84 113,527,929.38
5 Pek. Cerucuk dia. 8/10 - 4 m P.K.74a 99.00 Btg 15,321.84 1,516,861.91
6 Pek. Lantai Kerja t. 5 cm P. BB. 01 8.85 M3 1,030,157.50 9,112,258.17
7 Pek. Pondasi Plat Pondasi Beton Bertulang
Cor Beton Camp 1:2:3 P. BB. 02 42.00 M3 1,307,366.50 54,909,393.00
Besi P. BB. 03 3,855.60 Kg 14,079.15 54,283,570.74
Bekisting P. BB. 04 100.80 M2 119,421.90 12,037,727.52
8 Kolom Pondasi 40/40
Cor Beton Camp 1:2:3 P. BB. 02 9.41 M3 1,307,366.50 12,299,704.03
Besi P. BB. 03 851.61 Kg 14,079.15 11,989,975.34
Bekisting P. BB. 06.a 70.56 M2 138,839.30 9,796,501.01
9 Kolom Pondasi 20/20
Cor Beton Camp 1:2:3 P. BB. 02 0.09 M3 1,307,366.50 115,048.25
Besi P. BB. 03 12.20 Kg 14,079.15 171,766.42
Bekisting P. BB. 06.a 1.76 M2 138,839.30 244,357.17
10 Pek. Pondasi Cyclop
Cor Beton 1:3:5 P. BB. 01 6.44 M3 1,030,157.50 6,629,063.51
Bekisting P. BB. 04 15.06 M2 119,421.90 1,798,243.03
A LANTAI DASAR
B LANTAI SATU
1 Pek. Kolom 40/40
Cor Beton Camp 1:2:3 P. BB. 02 18.56 M3 1,307,366.50 24,264,722.24
Besi P. BB. 03 1,680.05 Kg 14,079.15 23,653,692.85
Bekisting P. BB. 06.a 139.20 M2 138,839.30 19,326,430.56
2 Pek. Balok 20/60
Cor Beton Camp 1:2:3 P. BB. 02 13.82 M3 1,307,366.50 18,073,034.50
Besi P. BB. 03 2,129.38 Kg 14,079.15 29,979,858.17
Bekisting P. BB. 07.a 161.28 M2 172,193.30 27,771,414.77
3 Pek. Balok 20/40
Cor Beton Camp 1:2:3 P. BB. 02 5.76 M3 1,307,366.50 7,530,431.04
Besi P. BB. 03 826.66 Kg 14,079.15 11,638,616.53
Bekisting P. BB. 07.a 72.00 M2 172,193.30 12,397,917.60
4 Pek Kolom Praktis 10/10
Cor Beton Camp 1:2:3 P. BB. 02 0.24 M3 1,307,366.50 313,767.96
Besi P. BB. 03 58.40 Kg 14,079.15 822,177.31
Bekisting P. BB. 06.a 9.60 M2 138,839.30 1,332,857.28
C LANTAI DUA
1 Pek. Kolom 40/40
Cor Beton Camp 1:2:3 P. BB. 02 21.60 M3 1,307,366.50 28,239,116.40
Besi P. BB. 03 1,955.23 Kg 14,079.15 27,528,004.61
Bekisting P. BB. 06.a 162.00 M2 138,839.30 22,491,966.60
2 Pek. Kolom 20/20
Cor Beton Camp 1:2:3 P. BB. 02 0.72 M3 1,307,366.50 941,303.88
Besi P. BB. 03 99.82 Kg 14,079.15 1,405,361.61
Bekisting P. BB. 06.a 14.40 M2 138,839.30 1,999,285.92
3 Pek. Balok 20/40
Cor Beton Camp 1:2:3 P. BB. 02 16.13 M3 1,307,366.50 21,085,206.91
Besi P. BB. 03 2,314.64 Kg 14,079.15 32,588,126.27
Bekisting P. BB. 07.a 201.60 M2 172,193.30 34,714,169.28
4 Pek. Balok 20/30
Cor Beton Camp 1:2:3 P. BB. 02 5.18 M3 1,307,366.50 6,777,387.94
Besi P. BB. 03 991.96 Kg 14,079.15 13,965,931.11
Bekisting P. BB. 07.a 69.10 M2 172,193.30 11,899,025.40
5 Pek. Ring Balok 15/40
Cor Beton Camp 1:2:3 P. BB. 02 13.82 M3 1,307,366.50 18,073,034.50
Besi P. BB. 03 2,645.30 Kg 14,079.15 37,243,572.88
Bekisting P. BB. 07.a 218.88 M2 172,193.30 37,689,590.16
6 Pek. Ring Balok 15/30
Cor Beton Camp 1:2:3 P. BB. 02 1.30 M3 1,307,366.50 1,694,346.98
Besi P. BB. 03 330.66 Kg 14,079.15 4,655,444.79
Bekisting P. BB. 07.a 21.60 M2 172,193.30 3,719,382.72
7 Pek Kolom Praktis 10/10
Cor Beton Camp 1:2:3 P. BB. 02 0.63 M3 1,307,366.50 823,640.90
Besi P. BB. 03 153.29 Kg 14,079.15 2,158,215.43
Bekisting P. BB. 06.a 25.20 M2 138,839.30 3,498,750.36
V PEKERJAAN PLAFOND
1 Pek. Plafond GRC Ruang Dalam dan Kaki Atap P. Pf. 04 467.04 M2 39,111.50 18,266,634.96
2 Pek. Rangka Plafond P. K. 29 467.04 M2 67,737.50 31,636,122.00
3 List Profil Gipsum - 528.80 M' 58,400.00 30,881,920.00
Sub Total V 80,784,676.96
VI PEK. ATAP
1 Konsul Kayu Klas Satu + Baut - 52.00 Unit 150,000.00 7,800,000.00
2 Rangka atap baja ringan (multi truss) - 510.00 M2 270,000.00 137,700,000.00
3 Atap Genteng Metal Stone Type Pryma 0,35 mm P. PA. 05 510.00 M2 160,229.00 81,716,790.00
4 Perabung Atap Genteng Metal P. PA. 09 39.00 M' 101,442.50 3,956,257.50
5 List Plank Kayu Klas I P. K. 35 160.00 M' 55,743.00 8,918,880.00
6 Tebing Layar kayu belian - 2.00 Unit 3,500,000.00 7,000,000.00
7 Ornamen atap "Tunjuk Langit" Kayu Belian - 2.00 Unit 250,000.00 500,000.00
X PEK. SANITASI
1 Instalasi Air Kotor - 1.00 Lsm 2,000,000.00 2,000,000.00
2 Instalasi Air Bersih - 1.00 Lsm 1,000,000.00 1,000,000.00
3 Kloset Jongkok P. Snt. 02 12.00 Buah 436,492.00 5,237,904.00
4 Berput dari Beton + Resapan+ Bak Pembuang - 3.00 Unit 5,500,000.00 16,500,000.00
5 Kran Air P. Snt. 15 10.00 Buah 46,105.00 461,050.00
6 Floor drain - 10.00 Buah 35,000.00 350,000.00
7 Bak Air Keramik - 10.00 Unit 550,000.00 5,500,000.00
8 Wasatafel Keramik + Kaca Cermin+ Meja Beton Keramik 20/20 Anti Gores - 1.00 Unit 2,000,000.00 2,000,000.00
9 Talang Air Vertikal P. Snt. 13 69.00 M' 82,277.50 5,677,147.50
10 Talang Air Horizontal - 60.40 M' 50,000.00 3,020,000.00
Sub Total X 41,746,101.50
XI PEK. PENGECATAN
1 Pek. Cat Tembok Ruang dalam ( Dinding, Kolom, Balok , Plafond ) P. Ct. 11 1,712.40 M2 14,917.65 25,544,983.86
2 Pek. Cat tembok Dinding Luar ( Wheather Shield ) P. Ct. 11a 1,245.36 M2 23,705.65 29,522,068.28
3 Pek. Cat Kilat (pintu, lisplank, jendela, kusen, konsul, list band, dll) P. Ct. 04 311.34 M2 32,190.00 10,022,034.60
Sub Total XI 65,089,086.74
Jumlah : 2,838,211,986.05
Dibulatkan : 2,838,210,000.00
Terbilang : Dua Milyar Delapan Ratus Tiga Puluh Delapan Juta Dua Ratus Sepuluh Ribu Rupiah
Mengetahui :
Kepala Dinas Pekerjaan Umum Cipta Karya,
Tata Ruang dan Perumahan
Kabupaten Sambas
Jumlah : 3,158,700,000.00
Dibulatkan : 3,158,700,000.00
Terbilang : Tiga Milyar Seratus Lima Puluh Delapan Juta Tujuh Ratus Ribu Rupiah
Mengetahui :
Kepala Dinas Pekerjaan Umum Cipta Karya,
Tata Ruang dan Perumahan
Kabupaten Sambas
Jumlah : 6,431,060,000.00
Dibulatkan : 6,431,060,000.00
Terbilang : Tujuh Milyar Empat Puluh Satu Juta Tiga Ratus Sepuluh Ribu Rupiah
Diperiksa Oleh :
Pejabat Pelaksana Teknis Kegiatan Sambas, Maret 2009
(PPTK) Dibuat Oleh :
Konsultan Perencana
CV. DINAMIKA
MULYANI MUAYAT
NIP. 195805101979031003
RINALDI, ST
Wakil Direktur
Mengetahui : Disetujui :
Kepala Dinas Pekerjaan Umum Cipta Karya, Kepala Bidang Penataan Ruang, Bangunan dan
Tata Ruang dan Perumahan Lingkungan
Selaku Pengguna Anggaran Selaku Kuasa Pengguna Anggaran
A BEBAN MATI
1 Beton bertulang #REF! m3 2.400 kg/m3 #REF! #REF!
2 Pasangan Dinding Batako #REF! m2 125 kg/m2 #REF! #REF!
3 Besi Beton #REF! kg - #REF! #REF!
4 Plafond GRC + Rangka #REF! m2 12 kg/m2 #REF! #REF!
5 Atap genteng metal #REF! m2 3 Kg/m2 #REF! #REF!
6 Rangka atap (TRUSS) #REF! m2 12 kg/m2 #REF! #REF!
7 Pintu #REF! M2 30 kg/m2 #REF! #REF!
8 Jendela + Ventilasi #REF! M2 25 kg/m2 #REF! #REF!
9 Keramik #REF! m2 24 kg/m2 #REF! #REF!
10 Plesteran #REF! m2 21 kg/m2 #REF! #REF!
Sub Jumlah #REF! #REF!
11 Beban mati lain lain 5% #REF! #REF!
Jumlah Beban Mati #REF! #REF!
B BEBAN HIDUP
1 Ruang kantor 933.12 m2 200 kg/m2 186,624.00 186.62
Jumlah Beban Hidup 186,624.00 186.62
C BEBAN ANGIN
1 Tekanan tiupan angin 270.00 m2 25 kg/m2 6,750.00 6.75
Jumlah Beban Angin 6,750.00 6.75
JUMLAH TOTAL BEBAN = TON #REF!
INPUT
1 Daya dukung 1 tiang diameter 15 cm, panjang 12 meter = 2.1245 ton/btg
2 Efisiensi daya dukung group tiang sesuai desain = 0.6350
Rumus : Converse - Labarre
E=1-0(n-1)m+(m-1)n
90 . m .n
3 Daya dukung total tiang
a Jumlah pondasi 42 bh
b Jumlah tiang/ pondasi 25 btg
c Daya dukung tiang 2.1245 ton/btg
d Efisiensi group 0.6350
E= 0.7033 E= 0.6049
0 = arc tg 0.38
0 = 0.3584
= 20.53 0
E= 0.6350
0.0177777778 0.37
0.6350
Besi Dia. 12
1 14 Btg 46.662 M' 41.44985
44 Btg 44 M' 39.0852
58 Btg 12.76 M' 11.33471
91.86976 Kg
Bekisting 8.66 M2
3,333
5.71428571
Sloof Balok 25/70 0.175
Bekisting 8
12.5
Balok Sloof 20/40 0.08
Besi dia. 16
Bekisting 12.5 M2
16.6666667
Kolom 20/30 0.06
Besi dia. 19
Bekisting 16.66667 M2
22.2222222
Kolom 15/30 0.045
Besi dia. 19
Bekisting 16.66667 M2
Lantai Tumbuk
10
0.1
67 Btg 67 14.874
1 7 Btg 70 15.54
30.414
10
Lantai gantung
8.333333
0.12
8.333
16.6666667
Balok dak 15/40 0.06
Besi dia. 16
Bekisting 15.83333 M2
25
Balok dak 20/20 0.04
Besi dia. 16
Bekisting 20 M2
11.11111
Sloof Balok 15/60 0.09
Bekisting 14.9985
16.6666667 1 5.26
bALOK 20/30 0.06 3 15.79
5 26.32
Besi dia. 16 2 10.53
1 5.26
dia. 16 100 M' 158 1 5.26
dia. 8 0.76 111.1111 84.44444 33.35556 1 5.26
191.3556 Kg 5 26.32
19 100
Bekisting 13.33333 M2
19
10
Balok Sloof 20/50 0.1
Besi dia. 16
Bekisting 12 M2
5.55555556
Balok Sloof 30/60 0.18
Besi dia. 16
Bekisting 8.333333 M2
14.8148148
Balok dak 15/45 0.0675
Besi dia. 16
Bekisting 14.07407 M2
10
Kolom 20/50 0.1
Besi dia. 16
Bekisting 14 M2
44.4444444
Kolom15/15 0.0225
Besi dia. 16
Bekisting 26.66667 M2
6.25
Kolom 40/40 0.16
Besi dia. 16
Bekisting 7.5 M2
25
Kolom20/20 0.04
Besi dia. 12
Bekisting 20 M2
5
Sloof Balok20/100 0.2
Bekisting 11
8.333333
Sloof Balok20/60 0.12
Bekisting 11.66667
16.6666667
bALOK 20/30 0.06
Besi dia. 16
Bekisting 13.33333 M2
12.5
bALOK 20/40 0.08
Besi dia. 16
Bekisting 12.5 M2
16.6666667
bALOK 15/40 0.06
Besi dia. 16
Bekisting 15.83333 M2
22.2222222
bALOK 15/30 0.045
Besi dia. 16
Bekisting 16.66667 M2
100
KolomPRAKTIS 10/10 0.01
Besi dia 8
dia. 8 400 M' 173.8
dia. 8 0.24 666.6667 160 69.52
243.32 Kg
Bekisting 40 M2
EHAB POLITEKNIK NEGERI PONTIANAK
1,080,450,000.00
638888577.47536
277733711.52464
UKURAN HARGA
NO JENIS BAHAN PERTAMANAN TINGGI DIAMETER UNIT BAHAN + PAJAK
(cm) (cm) UPAH
1 2 3 4 5 6 7
XVII PEKERJAAN PERBAIKAN TAMAN
AKIBAT GALIAN JARINGAN UTILITAS
1 Pengamanan pohon pelindung
a. Diameter batang 5 s/d 10 cm 1 Btg 15,717
b. Diameter batang 11 s/d 20 cm 1 Btg 16,433
c. Diameter batang 21 s/d 30 cm 1 Btg 25,041
d. Diameter batang 31 s/d 40 cm 1 Btg 26,254
e. Diameter batang 41 s/d 50 cm 1 Btg 29,233
f. Diameter batang 51 s/d 60 cm 1 Btg 35,249
g. Diameter batang 61 s/d 100 cm 1 Btg 56,143
2 Pemindahan pohon (termasuk pemeliharaan selama 3 bulan)
a. Diameter batang 5 s/d 10 cm 1 Btg 78,177
b. Diameter batang 11 s/d 20 cm 1 Btg 88,447
3 Penanaman pohon baru (termasuk pemeliharaan selama 3 bln)
a. Penanaman pohon kelas I
- Tinggi 1 s/d 2 m 1 Btg 90,320
- Tinggi 2,1 s/d 3 m 1 Btg 120,820
b. Penanaman pohon kelas II
- Tinggi 1 s/d 2 m 1 Btg 78,492
- Tinggi 2 s/d 3 m 1 Btg 94,465
c. Penanaman pohon kelas III
- Tinggi 1 s/d 2 m 1 Btg 65,992
- Tinggi 2 s/d 3 m 1 Btg 84,465
4 Border (termasuk pemeliharaan selama 3 bulan)
a. Kelas I 1 M2 355,750
b. Kelas II 1 M2 216,841
c. Kelas III 1 M2 148,681
5 Rumput gajah (termasuk pemeliharaan selama 3 bulan) 1 M2 19,243
WALIKOTA PONTIANAK
15,717
16,433
25,041
26,254
29,233
35,249
56,143
78,177
88,447
90,320
120,820
78,492
94,465
65,992
84,465
355,750
216,841
148,681
19,243
OTA PONTIANAK
ARY ABDURRACHMAN
RAB PERBAIKAN administrasi
Pekerjaan Struktur
LANTAI DASAR
Balok Sloof 15/100 32 12 25.2 25.2 15 10 6 125.4 M' 18.81 M3
Balok Sloof 20/40 50 5 21 76 6.08 M3
Balok 20/50 64 6.4 M3
Balok Sloof 20/30 18.5 1.11 M3
Kolom 20/50 144 14.4 M3
Kolom 15/15 104.4 2.349 M3
LANTAI SATU
Balok 20/50 137 32 36.4 62 18 267.4 249.4 24.94 M3
Balok 20/40 55 4.4 M3
Balok 20/30 18 19.9 37.9 2.274 M3
Balok 15/30 6.5 3.825 10.325 0.464625 M3
Kolom 20/50 112 11.2 M3
Kolom 15/15 91.2 2.052 M3
Ring Balok 15/30 183 8.235 M3
Ring Balok 15/40 64 3.84 M3