RENCANA ANGGARAN BIAYA (RAB) PROYEK RESTO MIE GACOAN

GWT,IPAL, RUMAH GENSET, DUMPSTER


CV. KARYA MAHESA KENCANAMECHANICAL & ELECTRICAL CONTRACTOR JL. KEDUNGTURI PERMAI II / U-16 TAMAN
NO URAIAN PEKERJAAN SPESIFIKASI VOLUME VOLUM

I PEKERJAAN DUMPSTER
1 Pasang dinding 1 bata camp.1 pc : 6 psr (rollagh bata) 1.32 m2 180,000 237,600.00
2 Pasang dinding bata ringan 60x20x10 cm ex. Citicon atau setara 6.12 m2 162,000 991,440.00
3 Kolom praktis 10x10
- Cor beton site mix mutu K175 0.05 m3 830,000 41,500.00
- Bekisting 1.44 m2 100,000 144,000.00
- Pembesian Polos 10.89 kg 15,000 163,350.00
4 Rabatan Beton lantai dumpster tebal 8 cm 0.43 m3 750,000 322,500.00
5 Pasang dinding keramik 30x30 cm warna putih (Detail GBR di SOP) 16.02 m2 156,000 2,499,120.00
6 Pasang lantai keramik 30x30 cm warna putih 2.60 m2 156,000 405,600.00
7 Pasang tutup plat besi bordes + Finish cat besi synthetic enamel warna hitam 1.00 unit 1,200,000 1,200,000.00
8 Pasang pintu plat besi bordes + Finish cat besi synthetic enamel warna hitam 1.00 unit 1,200,000 1,200,000.00
7,205,110.00
II. PEKERJAAN RUMAH GENSET
1 Pasang dinding 1 bata camp.1 pc : 6 psr (rollagh bata) 1.10 m2 162,000 178,200.00
2 Rabatan Beton pondasi lantai genset tebal 15 cm 0.56 m3 830,000 464,800.00
3 Acian beton lantai 4.30 m2 30,000 129,000.00
4 Benangan sudut 5.50 m2 30,000 165,000.00
5 Pasang atap rumah genset (Detail GBR di SOP) 6.00 m2 315,000 1,890,000.00
Spesifikasi : - Rangka Hollow 40.40 tebal 1.4 mm Finish cat besi syntetic enamel warna hitam
- Atap spandek galvalume tebal 0.3 mm
2,827,000.00
III. PEKERJAAN IPAL
1 Pembuatan IPAL kapasitas 9 m3 sejumlah 1 unit
a. Galian tanah 18.22 m3 90,000 1,639,800.00
b. Kolom Praktis 10/10
- Cor beton site mix mutu K225 0.05 m3 830,000 41,500.00
- Bekisting 4.20 m2 100,000 420,000.00
- Pembesian Polos 30.59 kg 15,000 458,850.00
c. Sloof Praktis 15/20
- Cor beton site mix mutu K225 0.49 m3 830,000 406,700.00
- Bekisting 6.56 m2 100,000 656,000.00
- Pembesian Polos 37.70 kg 15,000 565,500.00
d. Balok Praktis 10/12
- Cor beton site mix mutu K225 0.20 m3 830,000 166,000.00
- Bekisting 3.94 m2 100,000 394,000.00
- Pembesian Polos 33.65 kg 15,000 504,750.00
e. Plat penutup tebal 12 cm
- Cor beton site mix mutu K225 0.77 m3 830,000 639,100.00
- Bekisting 6.45 m2 100,000 645,000.00
- Pembesian Polos 82.63 kg 15,000 1,239,450.00
f. Rabatan lantai beton IPAL tebal 10 cm 0.65 m3 830,000 539,500.00
g. Pasang dinding bata ringan 60x20x10 cm ex. Citicon atau setara 21.90 m2 162,000 3,547,800.00
h. Plesteran dinding 26.40 m2 63,250 1,669,800.00
i. Acian 26.40 m2 30,000 792,000.00
j. Coating waterproofing ex. Sika Top 26.40 m2 95,000 2,508,000.00
k. Accesoris Pipa-pipa di dalam IPAL 1.00 Ls 1,500,000 1,500,000.00
l. Tutup Plat Bordes Finish Cat Besi 2.00 unit 1,200,000 2,400,000.00
m. Filter IPAL (Pasir, Koral, Ijuk, Batu Apung) 1.00 Ls 1,500,000 1,500,000.00
n. Pipa PVC D 6" (Dari Gutter Ke IPAL dipasang 2 baris) Ex. Wavin 2.00 m 172,500 345,000.00
20,938,950.00
2 Bak pengendap lemak uk.80x80 cm sejumlah 1 unit
a. Galian tanah 1.00 m3 90,000 90,000.00
b. Pasangan dinding bata 2.56 m2 162,000 414,720.00
c. Plesteran dinding 3.20 m2 63,250 202,400.00
d. Acian dinding 3.20 m2 30,000 96,000.00
e. Benangan Sudut 6.40 m1 30,000 192,000.00
f. Rabatan beton lantai 0.06 m3 830,000 49,800.00
g. Tutup Plat bordes finish cat 2.00 unit 1,200,000 2,400,000.00
h. Bak Strainer Stainless uk.60x60x60 cm (2 unit)
3,444,920.00
3 Bak kontrol untuk uk.60x60 cm sejumlah 1 unit
a. Galian tanah 0.51 m3 90,000 45,900.00
b. Pasangan dinding bata 1.44 m2 162,000 233,280.00
c. Plesteran dinding 1.92 m2 63,250 121,440.00
d. Acian dinding 1.92 m2 30,000 57,600.00
e. Benangan Sudut 4.80 m1 30,000 144,000.00
f. Rabatan beton lantai 0.04 m3 830,000 33,200.00
g. Tutup Plat bordes finish cat 1.00 unit 1,200,000 1,200,000.00
1,835,420.00
4 Pembuatan sumur peresapan (1 unit)
a. Galian sumur peresapan dia.1.0 m kedalaman 1.5 meter 1.70 m3 90,000 153,000.00
b. Beton Buis diameter 100 cm 3.00 bh 460,200 1,380,600.00
c. Lapisan Filter (Pasir, Koral, Ijuk, Batu Apung) 1.00 Ls 1,500,000 1,500,000.00
d. Tutup cor beton bertulang tebal 12 cm 0.14 m3 4,500,000 630,000.00
e. Pipa PVC D 4" Dari IPAL ke Resapan 2.00 m 75,000 150,000.00

3,813,600.00
TOTAL 30,032,890.00
KETERANGAN
RENCANA ANGGARAN BIAYA (RAB) PROYEK RESTO MIE GACOAN GWT,IPAL, RUMAH GENSET, DUMPSTER
CV. KARYA MAHESA KENCANAMECHANICAL & ELECTRICAL CONTRACTORJL. KEDUNGTURI PERMAI II / U-16 TAMAN
NO URAIAN PEKERJAAN SPESIFIKASI VOLUME HARGA JUMLAH
IV PEKERJAAN GROUND WATER TANK (GWT)
Pembuatan GWT kapasitas 4400 liter (4.4 m3 )
1 Galian tanah 7.50 m3 90,000 675,000.00
2 Cor Lantai kerja tebal 3 cm 0.19 m3 750,000 142,500.00
3 Cor Lantai Bawah Beton bertulang
- Cor Beton tebal 12 cm mutu K250 0.60 m3 1,023,000 613,800.00
- Pembesian tulangan besi Ø12-150 (Rangkap) 160.56 kg 15,000 2,408,400.00
4 Cor Dinding beton bertulang
- Cor Beton tebal 12 cm mutu K250 1.18 m3 1,023,000 1,207,140.00
- Pembesian tulangan besi Ø12-150 (Rangkap) 325.76 kg 15,000 4,886,400.00
- Bekisting 19.71 m2 200,000 3,942,000.00
5 Cor Tutup beton bertulang
- Cor Beton tebal 12 cm mutu K250 0.56 m3 1,023,000 572,880.00
- Pembesian tulangan besi Ø12-150 (Rangkap) 160.56 kg 15,000 2,408,400.00
- Bekisting 4.66 m2 200,000 932,000.00
6 Lapis waterproofing membran ex. SIKA 12.80 m2 126,500 1,619,200.00
7 Pasang keramik lantai & dinding uk.30x30 warna putih ex. Asia Tile 12.80 m2 150,410 1,925,248.00
8 Tutup bak kontrol - plat besi bordes finish cat 1.00 unit 1,200,000 1,200,000.00
22,532,968.00
Pembuatan sumur bor debit kisaran 1.5 - 2 liter/det
1 Sumur bor dia.4" 30.00 m 240,000 7,200,000.00
2 Pompa Hisap Tipe Submersible 3" Merk Grundfos SQ3-80 2PK 1.00 unit 17,700,000 17,700,000.00
3 Instalasi perpipaan 1.00 Ls 2,250,000 2,250,000.00
27,150,000.00
Pembuatan Rumah pompa distribus i
1 Pasangan dinding bata 1.44 m2 162,000 233,280.00
2 Plesteran dinding 2.88 m2 55,000 158,400.00
3 Acian 2.88 m2 30,000 86,400.00
4 Benangan sudut 4.80 m1 30,000 144,000.00
5 Tutup plat besi bordes finish cat 1.00 unit 1,200,000 1,200,000.00
6 Pompa distribusi Jet Pump merk Wasser PC-255EA 250 watt 1.00 unit 1,537,500 1,537,500.00
7 Instalasi perpipaan 1.00 Ls 2,250,000 2,250,000.00
5,609,580.00
TOTAL 55,292,548.00
VOLUME KETERANGAN