RAB RUMAH TIPE 45

PEKERJAAN : RUMAH MINIMALIS TIPE 45
LOKASI : 
REVISI : 00  (13 Juni 2019)

 HARGA SAT.  (Rp) 
NO ITEM PEKERJAAN SAT VOLUME JUMLAH HARGA (Rp)
 BAHAN   UPAH   TOTAL 

A PEK. PERSIAPAN                 1,000,000.00

1 Pembersihan awal, pengukuran dan pas. Bouwplank Ls                   1.00        1,000,000.00        1,000,000.00                 1,000,000.00

B PEK. TANAH                                   ‐
1 Galian tanah manual M3                          ‐                                   ‐
2 Timbunan kembali Unit                          ‐                                   ‐

C PEK. PONDASI                 2,657,446.86
1 Pas. Batu pondasi sp.1:4 M3                   5.09           397,600.00           125,000.00           522,605.09                 2,657,446.86

C PEK. BETON BERTULANG                 6,521,633.71
1 Beton Pondasi Telapak 60x60 M3                   0.79        1,070,493.02           110,000.00        1,180,493.02                    934,950.47
2 Beton Sloof 15x20 M3                   1.47        1,070,493.02           110,000.00        1,180,493.02                 1,735,324.75
3 Beton Kolom 20x20 M3                   1.32        1,070,493.02           110,000.00        1,180,493.02                 1,558,250.79
4 Beton Kolom praktis 15x15 M3                   0.47        1,070,493.02           110,000.00        1,180,493.02                    557,782.95
5 Beton ring balok 15x20 M3                   1.47        1,070,493.02           110,000.00        1,180,493.02                 1,735,324.75

D PEK. DINDING              21,006,530.72
1 Pas. Dinding bata sp.1:4 M2                 96.28             70,600.00             30,000.00           100,600.00                 9,686,019.50
2 Plesteran dinding sp.1:4 M2              192.57                9,888.00             30,000.00             39,888.00                 7,681,032.72
3 Acian dinding M2              192.57                3,900.00             15,000.00             18,900.00                 3,639,478.50

E PEK. PINTU & JENDELA                                   ‐
1 Pintu Panel (Tipe P1) Unit                   2.00                          ‐                                   ‐
2 Pintu Panel (Tipe P2) Unit                   1.00                          ‐                                   ‐
3 Pintu WC Unit                   1.00                          ‐                                   ‐
4 Jendela (Tipe J1) Unit                   2.00                          ‐                                   ‐
5 Jendela (Tipe J2) Unit                   2.00                          ‐                                   ‐
6 Ventilasi Unit                 10.00                          ‐                                   ‐

F PEK. PLAFOND                 7,504,830.00
1 Pek. Rangka Plafond besi metal hollow M2                 45.00             84,500.00             30,000.00           114,500.00                 5,152,500.00
2 pemasangan plafond GRC M2                 45.00             42,274.00             10,000.00             52,274.00                 2,352,330.00

G PEK. ATAP                 9,072,640.00
Pek. Rangka atap baja ringan, pas. aluminium foil & 
1 M2                 51.58           150,000.00           150,000.00                 7,737,000.00
penutup atap spandek (termasuk bubungan)

2 Lisplank M'                 10.00             75,000.00             75,000.00                    750,000.00


3 Talang Air M'                   8.00             73,205.00             73,205.00                    585,640.00

H PEK. INSTALASI LISTRIK                 3,019,838.00
1 Pek. Instalasi Titik Lampu & Stop Kontak Titik                   8.00           250,000.00           250,000.00                 2,000,000.00
2 Pas. Lampu LED 15W+Fitting Bh                   8.00             75,289.50             75,289.50                    602,316.00
3 Pas. Saklar Tunggal Bh                   4.00             25,239.50             25,239.50                    100,958.00
4 Pas. Saklar Double Bh                   2.00             30,739.50             30,739.50                       61,479.00
5 Pas. Stop Kontak Bh                   5.00             28,017.00             28,017.00                    140,085.00
6 Pas. MCB Bh                   1.00           115,000.00           115,000.00                    115,000.00

I PEK. PENGECATAN              10,256,945.57
1 Pengecatan Plafond M2                 45.00             32,991.20             10,000.00             42,991.20                 1,934,604.00
2 Pengecatan Dinding Interior M2                 96.28             29,609.80             10,000.00             39,609.80                 3,813,730.57
3 Pengecatan Dinding Exterior M2                 96.28             36,826.90             10,000.00             46,826.90                 4,508,611.00

J PEKERJAAN PAS KERAMIK                 8,789,616.00
1 Pekerjaan Pas Keramik 40x40 polos M2                 72.00             72,078.00             50,000.00           122,078.00                 8,789,616.00
2 Pekerjaan Pas Keramik WC 25x25 M2                   3.00                          ‐             55,000.00             55,000.00
K PEK. INSTALASI AIR & SANITASI                    318,601.00
1 Instalasi air bersih Titik                     ‐             25,239.50             25,239.50                                   ‐
2 Instalasi air kotor Bh                     ‐           443,575.00           443,575.00                                   ‐
3 Pas. Keran air Bh                   1.00             30,739.50             30,739.50                       30,739.50
4 Pas. Kloset duduk Bh                   1.00             28,017.00             28,017.00                       28,017.00
5 Pas. Floor Drain Bh                   1.00                6,844.50                6,844.50                         6,844.50
6 Pek. Bak Mandi LS                   1.00           126,500.00           126,500.00                    126,500.00
7 Pek. Septic Tank Ls                   1.00           126,500.00           126,500.00                    126,500.00

L PEK. AKHIR                 1,000,000.00
1 Pembersihan akhir Ls                   1.00        1,000,000.00        1,000,000.00                 1,000,000.00

T O T A L    H A R G A             71,148,081.86