LAPORAN MINGGUAN

MINGGU KE-56
Periode Tanggal (27 September s/d 03 October '20 )

PAKET : PENATAAN KAWASAN SAMUBAAH KABUPATEN MAYBRAT


NOMOR KONTRAK : HK.02.03/PBL/BPPW-PB/11
NOMOR ADDENDUM KE-1 : HK.02.03/ADD.I/PBL/BPPW-PB/11
NOMOR ADDENDUM KE-2 : HK.02.03/ADD.II/PBL/BPPW-PB/11
NOMOR ADDENDUM KE-3 : HK.02.03/ADD.III/PBL/BPPW-PB/11
NOMOR ADDENDUM KE-4 : HK.02.03/ADD.IV/PBL/BPPW-PB/12
TANGGAL KONTRAK : 07 SEPTEMBER 2020
TANGGAL ADDENDUM KE-1: 31 OKTOBER 2020
TANGGAL ADDENDUM KE-2: 08 FEBRUARI 2021
TANGGAL ADDENDUM KE-3: 26 FEBRUARI 2021
TANGGAL ADDENDUM KE-4: 01 SEPTEMBER 2021

KONTRAKTOR PELAKSANAN : -

TAHUN.2021
KONTRAKTOR KONSULTAN SUPERVISI

CV. ADYCITRA CONSULTAN

REKAPITULASI PROGRES MINGGUAN

NAMA PROYEK PENATAAN KAWASAN SAMUBAAH KABUPATEN MAYBRAT MASA KONTRAK 400 Hari Kalender
NOMOR KONTRAK HK.02.03/PBL/BPPW-PB/11 MASA REALISASI 392 Hari Kalender
NOMOR ADDENDUM KE-1 HK.02.03/ADD.I/PBL/BPPW-PB/11 SISA TERHADAP KONTRAK 8 Hari Kalender
NOMOR ADDENDUM KE-2 HK.02.03/ADD.II/PBL/BPPW-PB/11
NOMOR ADDENDUM KE-3 HK.02.03/ADD.III/PBL/BPPW-PB/11
NOMOR ADDENDUM KE-4 HK.02.03/ADD.IV/PBL/BPPW-PB/11
TANGGAL KONTRAK 07 September 2020
TANGGAL ADDENDUM KE-1 30 Oktober 2020
TANGGAL ADDENDUM KE-2 08 Februari 2021
TANGGAL ADDENDUM KE-3 26 Februari 2021
TANGGAL ADDENDUM KE-4 01 September 2021
LOKASI KABUPATEN MAYBRAT MASA ADD 4
PERIODE TANGGAL (27 September s/d 03 October '20 ) Minggu ke : 56 ( Lima Puluh Enam )

Bobot Bobot Bobot PROGRES ( % ) Nilai


No. Rencana Deviasi
Jenis Pekerjaan Kontrak Adendum I Adendum III s/d Minggu s/d Prestasi
RAB % %
(%) (%) (%) Minggu lalu ini Minggu ini %
1 2 3 4 5 6 7 8 9 10 11

I PEKERJAAN PERSIAPAN
- PERALATAN 0.176 0.176 0.176 0.176 0.000 0.176 100.000 0.176 0.000
- MOBILISASI FASILITAS KONTRAKTOR 0.216 0.216 0.216 0.216 0.000 0.216 100.000 0.216 0.000
- MOBILISASI LAINNYA 0.049 0.049 0.049 0.049 0.000 0.049 99.531 0.049 0.000
- DEMOBILISASI 0.083 0.083 0.083 0.069 0.002 0.071 85.109 0.075 -0.004
II PENYELENGGARAAN RK3K
- PENYELENGGARAAN RK3K 0.326 0.326 0.326 0.322 0.000 0.322 98.767 0.324 -0.002
III PEKERJAAN PEMBANGUNAN PANGGUNG BUDAYA
- PEKERJAAN PERSIAPAN 0.023 0.023 0.023 0.023 0.000 0.023 100.000 0.023 0.000
- PEKERJAAN TANAH 1.148 0.199 0.248 0.248 0.000 0.248 100.000 0.248 0.000
- PEKERJAAN PONDASI 7.832 0.924 1.028 1.028 0.000 1.028 100.000 1.028 0.000
- PEKERJAAN LANTAI 2.692 0.332 0.599 0.599 0.000 0.599 100.000 0.599 0.000
- PEKERJAAN DINDING 0.379 0.065 0.101 0.101 0.000 0.101 100.000 0.101 0.000
- PEKERJAAN PENGECATAN 0.078 0.016 0.016 0.016 0.000 0.016 100.000 0.016 0.000
- PEKERJAAN ATAP 0.000 3.235 3.235 3.235 0.000 3.235 100.000 3.235 0.000
- PEKERJAAN MECANIKAL ELEKTRICAL 0.000 0.000 0.127 0.026 0.000 0.026 20.145 0.127 -0.101
IV PEKERJAAN PEMBANGUNAN GAZEBO
- PEKERJAAN PERSIAPAN 0.187 0.087 0.087 0.087 0.000 0.087 100.000 0.087 0.000
- PEKERJAAN TANAH 0.010 0.119 0.149 0.149 0.000 0.149 100.000 0.149 0.000
- PEKERJAAN PONDASI PASANGAN BATU 0.499 0.409 0.409 0.409 0.000 0.409 100.000 0.409 0.000
- PEKERJAAN KAYU 1.696 0.027 0.027 0.027 0.000 0.027 100.000 0.027 0.000
- PEKERJAAN ATAP 1.630 0.555 0.591 0.591 0.000 0.591 100.000 0.591 0.000
- PEKERJAAN PENGECATAN 0.532 0.183 0.207 0.207 0.000 0.207 100.000 0.207 0.000
- PEKERJAAN BETON,PASANGAN DAN PLESTERAN 0.000 0.778 0.903 0.903 0.000 0.903 100.000 0.903 0.000
- PEKERJAAN LANTAI 0.000 0.340 0.380 0.380 0.000 0.380 100.000 0.380 0.000
- PEKERJAAN MECANIKAL ELEKTRICAL 0.000 0.034 0.056 0.008 0.000 0.008 13.387 0.056 -0.049
V PEKERJAAN PEMBANGUNAN RUANG TERBUKA HIJAU ( RTH ) 0.000
- JOGGING TRACK 16.389 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
- TAMAN BERMAIN 12.897 30.240 29.348 28.971 0.218 29.189 99.459 29.348 -0.159
TANGGA UTAMA 0.000
- PEKERJAAN PERSIAPAN 0.000 0.104 0.103 0.103 0.000 0.103 100.000 0.103 0.000
- PEKERJAAN PONDASI 0.000 1.937 1.488 1.488 0.000 1.488 100.000 1.488 0.000
- PEKERJAAN LANTAI 0.000 1.586 1.747 1.747 0.000 1.747 100.000 1.747 0.000
- PEKERJAAN PLESTERAN DAN PENGECATAN 0.000 0.229 0.265 0.265 0.000 0.265 100.000 0.265 0.000
TIFA UTAMA 0.000
- PEKERJAAN PERSIAPAN 0.000 0.000 0.012 0.012 0.000 0.012 100.000 0.012 0.000
- PEKERJAAN TANAH DAN PONDASI 0.000 0.000 0.183 0.183 0.000 0.183 100.000 0.183 0.000
- PEKERJAAN BETON,PASANGAN DAN PLESTERAN 0.000 0.000 0.323 0.323 0.000 0.323 100.000 0.323 0.000
- PEKERJAAN LANTAI 0.000 0.000 0.182 0.182 0.000 0.182 100.000 0.182 0.000
- PEKERJAAN PENGECATAN 0.000 0.000 0.013 0.013 0.000 0.013 100.000 0.013 0.000
PEKERJAAN TIFA UTAMA 0.000 3.784 1.816 1.816 0.000 1.816 100.000 1.816 0.000
VI PEKERJAAN PEMBANGUNAN PUJASERA
- PEKERJAAN PERSIAPAN 0.135 0.120 0.117 0.117 0.000 0.117 100.000 0.117 0.000
- PEKERJAAN TANAH DAN PONDASI 3.931 2.810 3.006 3.006 0.000 3.006 100.000 3.006 0.000
- PEKERJAAN STRUKTUR DAN PENULANGAN 3.664 3.513 3.641 3.641 0.000 3.641 100.000 3.641 0.000
- PEKERJAAN DINDING DAN LANTAI 4.806 3.658 3.657 3.657 0.000 3.657 100.000 3.657 0.000
- PEKERJAAN KUSEN, KACA, KUNCI, DAN ALAT PENGGANTUNG 1.176 0.521 0.560 0.560 0.000 0.560 100.000 0.560 0.000
- PEKERJAAN ATAP DAN PLAFOND 1.941 1.730 2.013 1.672 0.069 1.741 86.454 2.013 -0.273
- PEKERJAAN CAT DAN LABURAN 0.478 0.368 0.479 0.409 0.000 0.409 85.468 0.479 -0.070
- PEKERJAAN MECANIKAL ELEKTRICAL 0.669 0.333 0.333 0.333 0.000 0.333 100.000 0.333 0.000
- PEKERJAAN SANITAIR DAN SEPTICTANK 0.000 1.068 0.738 0.738 0.000 0.738 100.000 0.738 0.000
- PEKERJAAN BAK AIR 0.000 0.000 0.254 0.254 0.000 0.254 100.000 0.020 0.234
VII PEKERJAAN PEMBANGUNAN POS JAGA
- PEKERJAAN PERSIAPAN 0.015 0.009 0.009 0.009 0.000 0.009 100.000 0.009 0.000
- PEKERJAAN TANAH DAN PONDASI 0.251 0.078 0.080 0.080 0.000 0.080 100.000 0.080 0.000
- PEKERJAAN STRUKTUR DAN PENULANGAN 0.202 0.255 0.259 0.259 0.000 0.259 100.000 0.259 0.000
- PEKERJAAN DINDING DAN LANTAI 0.349 0.144 0.144 0.144 0.000 0.144 100.000 0.144 0.000
- PEKERJAAN KUSEN, KACA, KUNCI, & ALAT PENGGANTUNG 0.074 0.047 0.056 0.056 0.000 0.056 100.000 0.056 0.000
- PEKERJAAN ATAP DAN PLAFOND 0.122 0.135 0.105 0.105 0.000 0.105 100.000 0.105 0.000
- PEKERJAAN CAT DAN LABURAN 0.063 0.031 0.032 0.032 0.000 0.032 100.000 0.032 0.000
- PEKERJAAN MECANIKAL ELEKTRICAL 0.035 0.022 0.022 0.022 0.000 0.022 100.000 0.022 0.000
VIII PEKERJAAN PEMBANGUNAN KIOS SOUVENIR
- PEKERJAAN PERSIAPAN 0.013 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
- PEKERJAAN GALIAN DAN URUGAN 0.041 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
- PEKERJAAN BETON, PASANGAN DAN PLESTERAN 0.708 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
- PEKERJAAN KUDA-KUDA DAN ATAP 0.189 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
- PEKERJAAN PLAFOND 0.088 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
Bobot Bobot Bobot PROGRES ( % ) Nilai
No. Rencana Deviasi
Jenis Pekerjaan Kontrak Adendum I Adendum III s/d Minggu s/d Prestasi
RAB % %
(%) (%) (%) Minggu lalu ini Minggu ini %
1 2 3 4 5 6 7 8 9 10 11
- PEKERJAAN PENUTUP LANTAI DAN DINDING 0.057 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
- PEKERJAAN PENGECATAN 0.048 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
- PEKERJAAN INSTALASI LISTRIK 0.025 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
IX PEKERJAAN PEMBANGUNAN TOILET
- PEKERJAAN PERSIAPAN 0.041 0.031 0.036 0.036 0.000 0.036 100.000 0.036 0.000
- PEKERJAAN TANAH DAN PONDASI 0.662 0.604 0.855 0.855 0.000 0.855 100.000 0.855 0.000
- PEKERJAAN STRUKTUR DAN PENULANGAN 0.429 1.051 1.030 1.030 0.000 1.030 100.000 1.030 0.000
- PEKERJAAN DINDING DAN LANTAI 1.248 1.395 1.501 1.501 0.000 1.501 100.000 1.501 0.000
- PEKERJAAN KUSEN, KACA, KUNCI, & ALAT PENGGANTUNG 0.183 0.188 0.366 0.366 0.000 0.366 100.000 0.366 0.000
- PEKERJAAN ATAP DAN PLAFOND 0.271 0.554 0.556 0.556 0.000 0.556 100.000 0.556 0.000
- PEKERJAAN CAT DAN LABURAN 0.076 0.144 0.168 0.162 0.000 0.162 96.139 0.168 -0.006
- PEKERJAAN MECANIKAL ELEKTRICAL 0.057 0.109 0.109 0.109 0.000 0.109 100.000 0.109 0.000
- PEKERJAAN SANITAIR 0.538 0.932 0.867 0.867 0.000 0.867 100.000 0.867 0.000
X PEKERJAAN PEMBANGUNAN TALUD PENGAMAN
- PEKERJAAN PERSIAPAN 0.108 0.073 0.073 0.073 0.000 0.073 100.000 0.073 0.000
- PEKERJAAN GALIAN DAN URUGAN 0.088 1.067 1.067 1.067 0.000 1.067 100.000 1.067 0.000
- PEKERJAAN BETON, PASANGAN DAN PLESTERAN 2.553 7.331 7.334 7.334 0.000 7.334 100.000 7.334 0.000
- PEKERJAAN PENGECATAN 0.000 0.203 0.205 0.205 0.000 0.205 100.000 0.205 0.000
XI PEKERJAAN PEMBANGUNAN GEDUNG PENGELOLA
- PEKERJAAN PERSIAPAN 0.024 0.062 0.061 0.061 0.000 0.061 100.000 0.061 0.000
- PEKERJAAN GALIAN DAN URUGAN 0.146 0.178 0.295 0.295 0.000 0.295 100.000 0.295 0.000
- PEKERJAAN BETON, PASANGAN DAN PLESTERAN 2.801 3.418 4.029 4.029 0.000 4.029 100.000 4.029 0.000
- PEKERJAAN KUDA-KUDA DAN ATAP 0.423 0.673 0.836 0.652 0.038 0.690 82.498 0.836 -0.146
- PEKERJAAN KUSEN PINTU DAN JENDELA 0.391 0.161 0.161 0.161 0.000 0.161 100.000 0.161 0.000
- PEKERJAAN ALAT GANTUNGAN DAN ACCESORIS 0.092 0.051 0.064 0.064 0.000 0.064 100.000 0.064 0.000
- PEKERJAAN PLAFOND 0.243 0.300 0.298 0.298 0.000 0.298 100.000 0.298 0.000
- PEKERJAAN PENUTUP LANTAI DAN DINDING 0.399 0.664 0.662 0.662 0.000 0.662 100.000 0.662 0.000
- PEKERJAAN PENGECATAN 0.223 0.207 0.271 0.251 0.000 0.251 92.758 0.271 -0.020
- PEKERJAAN INSTALASI LISTRIK 0.131 0.157 0.157 0.157 0.000 0.157 100.000 0.157 0.000
- PEKERJAAN SANITAIR 0.139 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
- PEKERJAAN SANITAIR DAN SEPTICTANK 0.000 0.466 0.388 0.388 0.000 0.388 100.000 0.388 0.000
- PEKERJAAN PEMASANGAN LISTRIK DAN JARINGAN 0.000 0.885 0.884 0.884 0.000 0.884 100.000 0.884 0.000
- PEKERJAAN PERPIPAAN 0.000 1.050 0.820 0.820 0.000 0.820 100.000 0.820 0.000
XII PEKERJAAN PENANAMAN TANAMAN
- PEKERJAAN PERSIAPAN 0.056 0.056 0.056 0.056 0.000 0.056 100.000 0.056 0.000
- PENANAMAN DAN PEMELIHARAAN TANAMAN 7.822 5.230 3.749 3.648 0.008 3.655 97.497 3.749 -0.094
- POT TANAMAN 0.000 5.010 5.325 5.325 0.000 5.325 100.000 5.325 0.000
XIII PEKERJAAN PEMBANGUNAN GAPURA
- PEKERJAAN PERSIAPAN 0.049 0.035 0.035 0.035 0.000 0.035 100.000 0.035 0.000
- PEKERJAAN GALIAN DAN URUGAN 0.072 0.012 0.010 0.010 0.000 0.010 100.000 0.010 0.000
- PEKERJAAN BETON, PASANGAN DAN PLESTERAN 1.978 0.952 0.936 0.936 0.000 0.936 100.000 0.936 0.000
- PEKERJAAN ATAP 0.144 0.303 0.371 0.371 0.000 0.371 100.000 0.371 0.000
- PEKERJAAN PENUTUP LANTAI DAN DINDING 0.131 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
- PEKERJAAN PENGECATAN 0.045 0.010 0.049 0.049 0.000 0.049 100.000 0.049 0.000
XIV PEKERJAAN PEMBANGUNAN PAPAN INFORMASI
- PEKERJAAN PERSIAPAN 0.009 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
- PEKERJAAN TANAH 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
- PEKERJAAN BETON, PASANGAN DAN PLESTERAN 0.219 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
XV PEKERJAAN PEMBANGUNAN DRAINASE
- PEKERJAAN PERSIAPAN 0.105 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
- PEKERJAAN GALIAN DAN URUGAN 0.157 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
- PEKERJAAN BETON, PASANGAN DAN PLESTERAN 2.872 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
XVI PEKERJAAN PEMBANGUNAN VIEW SPOT
- PEKERJAAN PERSIAPAN 0.018 0.070 0.070 0.070 0.000 0.070 100.000 0.070 0.000
- PEKERJAAN GALIAN DAN URUGAN 0.005 0.009 0.011 0.011 0.000 0.011 100.000 0.011 0.000
- PEKERJAAN BETON, PASANGAN DAN PLESTERAN 0.554 3.410 3.996 3.996 0.000 3.996 100.000 3.996 0.000
- PEKERJAAN KAYU 0.068 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
XVII PEKERJAAN PEMBANGUNAN TAMAN
- PEKERJAAN PERSIAPAN 0.024 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
- PEKERJAAN TANAH 0.367 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
- PEKERJAAN STRUKTUR DAN PENULANGAN 0.503 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
- PEKERJAAN DINDING DAN LANTAI 0.989 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
XVIII PEKERJAAN PEMBANGUNAN RESERVOIR
- PEKERJAAN TANAH 0.042 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
- PEKERJAAN PONDASI 0.133 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
- PEKERJAAN BETON DAN PONDASI 1.497 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
- PEKERJAAN PLESTERAN 0.117 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
- PEKERJAAN LAIN-LAIN 0.163 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
- PEKERJAAN PERPIPAAN 0.211 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
- PEKERJAAN PENGECATAN DAN WATER STOP 0.118 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
- INSTALASI AIR BERSIH 0.815 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
XIX PEKERJAAN PEMBANGUNAN MENARA AIR
- PEKERJAAN PERSIAPAN 0.025 0.024 0.024 0.024 0.000 0.024 100.000 0.024 0.000
- PEKERJAAN TANAH DAN PONDASI 0.377 0.326 0.326 0.326 0.000 0.326 100.000 0.326 0.000
- PEKERJAAN KAYU 0.515 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
- PEKERJAAN BETON 0.000 0.928 0.928 0.928 0.000 0.928 100.000 0.928 0.000
- PEKERJAAN ATAP 0.117 0.175 0.175 0.175 0.000 0.175 100.000 0.175 0.000
- PROFIL TANK 2200 L 0.102 0.505 0.640 0.640 0.000 0.640 100.000 0.640 0.000
- PEKERJAAN PENGECATAN 0.000 0.032 0.118 0.118 0.000 0.118 100.000 0.118 0.000
Bobot Bobot Bobot PROGRES ( % ) Nilai
No. Rencana Deviasi
Jenis Pekerjaan Kontrak Adendum I Adendum III s/d Minggu s/d Prestasi
RAB % %
(%) (%) (%) Minggu lalu ini Minggu ini %
1 2 3 4 5 6 7 8 9 10 11
XX PEKERJAAN PEMBANGUNAN BOX CULVERT
- PEKERJAAN TANAH 0.066 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
- PEKERJAAN BETON 2.257 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
XXI PEMBERSIHAN AKHIR
- PEMBERSIHAN AKHIR 0.068 0.068 0.068 0.000 0.034 0.034 50.000 0.000 0.034

JUMLAH 100.000 100.000 100.000 98.664 0.368 99.032 99.688 -0.656

Prestasi Pekerjaan 99.032 %

Sorong, 03 October 2021


Disetujui: Diperiksa : Dibuat oleh :
PPK PKP & BPB Satker Pelaksanaan Konsultan Supervisi Kontraktor Pelaksana
prasarana Permukiman Provinsi Papua CV. ADYCITRA CONSULTAN PT. SINAR ARENGKA SETIA MAJU – PT.
Barat YAVANA ABADI KONTRUKSI (KSO)

MARIO L.KAOTJIL, ST ANDDY SANTOSO, ST FAQIH USMAN, ST


19820829 201104 1 001 Supervisior Engineer Kuasa KSO
PENGGUNA ANGGARAN :

REKAPITULASI KEMAJUAN PEKERJAAN MINGGUAN

PENATAAN KAWASAN SAMUBAAH KABUPATEN MAYBRAT KONSULTAN SUPERVISI :

CV. ADYCITRA CONSULTAN


NO. SPK / KONTRAK : HK.02.03/PBL/BPPW-PB/11
NOMOR ADDENDUM KE-1 HK.02.03/ADD.I/PBL/BPPW-PB/11 KONTRAKTOR PELAKSANA :
NOMOR ADDENDUM KE-2 HK.02.03/ADD.II/PBL/BPPW-PB/11
NOMOR ADDENDUM KE-3 HK.02.03/ADD.III/PBL/BPPW-PB/11
NOMOR ADDENDUM KE-4 HK.02.03/ADD.IV/PBL/BPPW-PB/11
TANGGAL SPK / KONTRAK : 07 September 2020
TANGGAL ADDENDUM KE-1 : 30 Oktober 2020
TANGGAL ADDENDUM KE-2 : 08 Februari 2021
TANGGAL ADDENDUM KE-3 26 Februari 2021
TANGGAL ADDENDUM KE-4 01 September 2021
MINGGU KE : 56 ( Lima Puluh Enam )
PERIODE TANGGAL : (27 September s/d 03 October '20 )

Kontrak Awal Kontrak Adendum I Kontrak Adendum III S/d Minggu Lalu Minggu ini S/d Minggu ini Thdp
NO. URAIAN PEKERJAAN SATUAN VOLUME Bobot VOLUME Bobot VOLUME Bobot Volume Bobot Volume Bobot Volume Bobot Item Pek

(%) (%) (%) (%) (%) (%) (%)


a b c d g h k l o p q r s t u v
I. PEKERJAAN PESIAPAN
1 PERALATAN LS 1.00 0.18 1.00 0.18 1.00 0.18 1.00 0.18 - 1.00 0.18 100.00
2 Direksi Keet M2 30.00 0.22 30.00 0.22 30.00 0.22 30.00 0.22 - 30.00 0.22 100.00
3 Papan Nama Proyek LS 1.00 0.01 1.00 0.01 1.00 0.01 1.00 0.01 - 1.00 0.01 100.00
4 Pengurusan Dokumen Perizinan LS 1.00 0.02 1.00 0.02 1.00 0.02 1.00 0.02 - 1.00 0.02 100.00
5 Dokumentasi LS 1.00 0.02 1.00 0.02 1.00 0.02 0.99 0.02 - 0.99 0.02 98.90
6 Demobilisasi LS 1.00 0.08 1.00 0.08 1.00 0.08 0.83 0.07 0.02 0.00 0.85 0.07 85.11
-
-
II. PENYELENGGARAAN RK3K -
1 Penyelenggaraan rk3k LS 1.00 0.33 1.00 0.33 1.00 0.33 0.99 0.32 - 0.99 0.32 98.77
-
-
III. PEKERJAAN PEMBANGUNAN GEDUNG BUDAYA -
- PEKERJAAN PERSIAPAN -
1 Pengukuran kembali dan pemasangan bouwplank LS 1.00 0.02 1.00 0.02 1.00 0.02 1.00 0.02 - 1.00 0.02 100.00
- PEKERJAAN TANAH -
1 Pekerjaan Galian Tanah Penurunan Elevasi Panggung M3 348.82 0.29 -
2 Pekerjaan galian tanah pondasi telapak M3 46.83 0.04 8.45 0.01 8.45 0.01 8.45 0.01 - 8.45 0.01 100.00
3 Pekerjaan galian tanah pondasi pasangan batu tempat duduk M3 154.39 0.13 -
4 Pekerjaan galian tanah pondasi pasangan batu panggung M3 28.69 0.02 6.10 0.01 6.61 0.01 6.61 0.01 - 6.61 0.01 100.00
5 Pekerjaan galian tanah pondasi tangga M3 3.17 0.00 3.53 0.00 3.53 0.00 - 3.53 0.00 100.00
6 Pekerjaan galian tanah turap pasangan batu M3 10.99 0.01 -
7 Urugan tanah kembali pondasi telapak M3 18.75 0.01 2.11 0.00 2.11 0.00 2.11 0.00 - 2.11 0.00 100.00
8 Urugan tanah kembali pasangan batu tempat duduk M3 51.46 0.03 -
9 Urugan tanah kembali pondasi pasangan batu panggung M3 9.56 0.01 -
10 Pekerjaan urugan tanah kembali turap pasangan batu M3 3.66 0.00 -
11 Urugan pasir di bawah pondasi telapak M3 2.25 0.02 -
12 Urugan pasir di bawah pondasi pasangan batu tempat duduk M3 31.35 0.26 -
13 Urugan pasir di bawah pondasi pasangan batu panggung M3 3.45 0.03 -
14 Urugan pasair di bawah turap pasangan batu M3 2.19 0.02 -
15 Urugan pasir di bawah Lantai M3 33.11 0.27 2.54 0.02 4.81 0.04 4.81 0.04 - 4.81 0.04 100.00
16 Urugan Tanah M3 43.15 0.16 50.82 0.19 50.82 0.19 - 50.82 0.19 100.00
- PEKERJAAN PONDASI -
1 Pekerjaan pasangan batu pada panggung sp. 1:4 M3 34.32 0.67 36.81 0.72 37.23 0.73 37.23 0.73 - 37.23 0.73 100.00
2 Pekerjaan pasangan batu pada tempat duduk sp. 1:4 M3 186.60 3.64 -
3 Pekerjaan lantai kerja beton di bawah pondasi telapak tbl 10 cm K-100 M3 22.92 0.47 -
4 Lantai kerja beton K-100 di bawah lantai tebal 7 cm M3 29.34 0.60 3.55 0.07 6.84 0.14 6.84 0.14 - 6.84 0.14 100.00
5 Pekerjaan pondasi telapak -
Pondasi Telapak beton mutu 19.3 Mpa M3 5.61 0.13 3.94 0.09 3.94 0.09 3.94 0.09 - 3.94 0.09 100.00
Besi tulangan KG 1,620.00 0.29 154.17 0.03 315.44 0.06 315.44 0.06 - 315.44 0.06 100.00
Bekisting M3 18.00 0.02 16.72 0.02 16.72 0.02 16.72 0.02 - 16.72 0.02 100.00
6 Pekerjaan kolom Beton -
Kolom beton mutu 19.3 Mpa M3 5.93 0.14 -
Besi tulangan KG 3,058.44 0.55 -
Bekisting M3 43.20 0.12 -
7 Pekerjaan sloof beton -
Sloof beton mutu 19.3 Mpa M3 5.13 0.12 -
Besi tulangan KG 2,029.65 0.36 -
Bekisting M3 18.00 0.03 -
8 Pekerjaan ring balok -
Ring Balk beton mutu 19.3 Mpa M3 2.54 0.06 -
Besi tulangan KG 2,029.65 0.36 -
Bekisting M3 18.00 0.05 -
9 Pekerjaan Roster M2 34.50 0.24 -
- PEKERJAAN LANTAI -
1 Pasang batu Andesit Tempat duduk M2 486.27 1.98 -
2 Pasang batu Andesit jalan M2 67.20 0.27 -
3 Pasang batu Andesit panggung M2 108.89 0.44 81.69 0.33 147.48 0.60 147.48 0.60 - 147.48 0.60 100.00
- PEKERJAAN DINDING -
1 Pas dinding bata Tela sp. 1:4 (tebal 8cm) M2 22.12 0.05 13.28 0.03 13.28 0.03 - 13.28 0.03 100.00
2 Pek plesteran dinding tbl 2 cm sp. 1:4 M2 44.25 0.04 50.01 0.04 51.93 0.05 51.93 0.05 - 51.93 0.05 100.00
3 Pek plesteran kolom beton dan dinding tbl.1.5 cm sp. 1:4 M2 203.40 0.18 -
4 Pek acian M2 247.65 0.11 50.01 0.02 51.93 0.02 51.93 0.02 - 51.93 0.02 100.00
- PEKERJAAN PENGECATAN -
1 Pekerjaan pengecatan dinding M2 247.65 0.08 50.01 0.02 51.93 0.02 51.93 0.02 - 51.93 0.02 100.00
- PEKERJAAN ATAP -
1 Pekerjaan rangka dan atap membrane M2 142.50 3.23 142.50 3.23 142.50 3.23 - 142.50 3.23 100.00
- PEKERJAAN MECANIKAL ELEKTRICAL -
1 Pas. Titik Instalasi BH 8.00 0.02 8.00 0.02 - 8.00 0.02 100.00
2 Lampu Spot Light Panggung Budaya BH 8.00 0.10 - - - - - -
3 Stop Kontak BH 4.00 0.01 4.00 0.01 - 4.00 0.01 100.00
-
-
IV. PEKERJAAN PEMBANGUNAN GAZEBO -
- PEKERJAAN PERSIAPAN -
1 Pembersihan Lokasi M2 240.00 0.04 151.20 0.03 151.20 0.03 151.20 0.03 - 151.20 0.03 100.00
2 Pengukuran Dan pasang Bowplank M' 240.00 0.14 99.20 0.06 99.20 0.06 99.20 0.06 - 99.20 0.06 100.00
- PEKERJAAN TANAH -
1 Galian tanah pondasi Titik M3 11.40 0.01 -
2 Galian tanah pondasi menerus M3 26.52 0.02 26.52 0.02 26.52 0.02 - 26.52 0.02 100.00
3 Urugan Tanah M3 16.54 0.06 26.97 0.10 26.97 0.10 - 26.97 0.10 100.00
4 Urugan pasir di bawah lantai M3 4.14 0.03 3.10 0.03 3.10 0.03 - 3.10 0.03 100.00
- PEKERJAAN PONDASI PASANGAN BATU -
Kontrak Awal Kontrak Adendum I Kontrak Adendum III S/d Minggu Lalu Minggu ini S/d Minggu ini Thdp
NO. URAIAN PEKERJAAN SATUAN VOLUME Bobot VOLUME Bobot VOLUME Bobot Volume Bobot Volume Bobot Volume Bobot Item Pek

(%) (%) (%) (%) (%) (%) (%)


a b c d g h k l o p q r s t u v
1 Pekerjaan pondasi pondasi batu belah campuran 1SP : 4PP M3 16.45 0.32 20.96 0.41 20.96 0.41 20.96 0.41 - 20.96 0.41 100.00
2 Pekerjaan pondasi pondasi batu belah campuran 1SP : 4PP M3 9.12 0.18 -
- PEKERJAAN KAYU -
1 Pekerjaan pasangan kolom 10x10 cm kayu kls I M3 1.89 0.14 -
2 Pekerjaan pasangan kolom 10x10 cm kayu kls I M3 0.35 0.03 0.35 0.03 0.35 0.03 - 0.35 0.03 100.00
3 Pekerjaan pasangan balok 10x10 cm kayu kls I M3 1.74 0.13 -
4 Pamasangan balok lantai 5x10 cm kayu kls I M3 1.62 0.12 -
5 Pekerjaan pasangan ring balok 10x10 cm kayu kls I M3 1.86 0.14 -
6 Pekerjaan pasangan balok 5x10 cm kayu kls I M3 0.93 0.07 -
7 Pekerjaan pasangan balok reling 5x10 cm kayu kls I M3 1.86 0.14 -
8 Pekerjaan pasangan balok reling 5x5 cm kayu kls I M3 1.41 0.11 -
9 Pemasangan lantai papan 3x 30 cm kayu kls I M2 139.50 0.47 -
10 Pemasangan papan penutup 3x 30 cm kayu kls I M2 113.40 0.38 -
- PEKERJAAN ATAP -
1 Pekerjaan rangka atap kuda-kuda ekspose M3 9.75 0.75 0.42 0.03 0.68 0.05 0.68 0.05 - 0.68 0.05 100.00
2 Pekerjaan penutup rangka atap M2 551.24 0.77 183.22 0.26 183.22 0.26 183.22 0.26 - 183.22 0.26 100.00
3 Pekerjaan Nok Atap M' 76.50 0.04 22.80 0.01 22.80 0.01 22.80 0.01 - 22.80 0.01 100.00
4 Pekerjaan pasangan lispang 30 cm M2 85.50 0.07 -
5 Pemasangan lisplank M' 168.96 0.13 190.56 0.15 190.56 0.15 - 190.56 0.15 100.00
6 Gording ky. Klas I M3 1.69 0.12 1.69 0.12 1.69 0.12 - 1.69 0.12 100.00
- PEKERJAAN PENGECATAN -
1 Pelaburan dengan vernis M2 956.64 0.53 256.34 0.14 154.97 0.09 154.97 0.09 - 154.97 0.09 100.00
2 Pekerjaan pengecatan dinding M2 128.06 0.04 164.74 0.05 164.74 0.05 - 164.74 0.05 100.00
3 Cat Lisplank M2 84.48 0.05 84.48 0.05 - 84.48 0.05 100.00
4 Cat Menie Besi M2 21.03 0.01 21.03 0.01 - 21.03 0.01 100.00
5 Cat Besi M2 21.03 0.01 21.03 0.01 - 21.03 0.01 100.00
- PEKERJAAN BETON, PASANGAN DAN PLESTERAN -
1 Beton mutu f’c = 7,4 MPa (K 100) ( Bawah Lantai ) M3 10.80 0.22 4.50 0.09 4.50 0.09 - 4.50 0.09 100.00
2 Beton Sloof beton mutu 19.3 Mpa M3 1.78 0.04 1.54 0.04 1.54 0.04 - 1.54 0.04 100.00
Bekisting M2 11.84 0.02 10.24 0.02 10.24 0.02 - 10.24 0.02 100.00
Pembesian KG 295.84 0.05 292.72 0.05 292.72 0.05 - 292.72 0.05 100.00
3 Kolom beton mutu 19.3 Mpa M3 4.76 0.11 4.85 0.11 4.85 0.11 - 4.85 0.11 100.00
Bekisting M2 19.24 0.05 42.07 0.11 42.07 0.11 - 42.07 0.11 100.00
Pembesian KG 356.65 0.06 388.54 0.07 388.54 0.07 - 388.54 0.07 100.00
4 Ring Balok beton mutu 19.3 Mpa M3 2.09 0.05 2.28 0.05 2.28 0.05 - 2.28 0.05 100.00
Bekisting M2 16.32 0.04 17.54 0.05 17.54 0.05 - 17.54 0.05 100.00
Pembesian KG 380.95 0.07 380.95 0.07 380.95 0.07 - 380.95 0.07 100.00
5 Plat Beton beton mutu 19.3 Mpa M3 0.49 0.01 0.49 0.01 0.49 0.01 - 0.49 0.01 100.00
Bekisting M2 4.80 0.01 4.80 0.01 4.80 0.01 - 4.80 0.01 100.00
Pembesian KG 55.04 0.01 55.04 0.01 55.04 0.01 - 55.04 0.01 100.00
6 Pek. Batu Bata Merah tebal 1/2 bata, 1SP : 4PP M2 4.72 0.01 4.72 0.01 4.72 0.01 - 4.72 0.01 100.00
7 Pas dinding Batu Tela Camp, 1 : 4 M2 41.69 0.10 41.69 0.10 - 41.69 0.10 100.00
8 Plesteran Dinding sp. 1 : 4 M2 9.44 0.01 15.64 0.01 15.64 0.01 - 15.64 0.01 100.00
9 Acian M2 9.44 0.00 15.64 0.01 15.64 0.01 - 15.64 0.01 100.00
10 Railing Pipa 2" Gazebo M 32.96 0.07 32.96 0.07 - 32.96 0.07 100.00
- PEKERJAAN LANTAI -
1 Lantai Keramik 40/40 M2 106.59 0.34 119.20 0.38 119.20 0.38 - 119.20 0.38 100.00
- PEKERJAAN MECANIKAL ELEKTRIKAL -
1 Pas. Titik Instalasi BH 8.00 0.02 4.00 0.01 4.00 0.01 - 4.00 0.01 100.00
2 Lampu SL 18 Watt BH 8.00 0.02 - - -
3 Lampu Gazebo BH 4.00 0.05 - - - - - -
-
-
V. PEKERJAAN RUANG TERBUKA HIJAU (RTH) -
- JOGING TRACK -
1 Galian Tanah M3 848.00 0.71 -
2 Pasang batu Tela M2 431.91 1.07 -
3 Cor Kansteen beton mutu M3 9.84 0.22 -
4 Cor Ramp Disabilitas beton M3 10.00 0.23 -
5 Plesteran M2 460.70 0.40 -
6 Acian M2 460.70 0.20 -
7 Cat M2 460.70 0.15 -
8 Urugan Tanah peninggian lantai M2 127.20 0.48 -
9 Pasang batu Andesit Teks ture Merah M2 1,098.40 4.46 -
10 Pasang batu Andesit Teks ture Abu abu M2 428.00 1.74 -
11 Pasang batu Andesit Teks ture Kuning M2 85.60 0.35 -
12 Pasang batu Andesit teks ture bergaris M2 288.00 1.17 -
13 Finishing batu Sikat M2 204.10 0.99 -
14 Pasang kursi taman UNIT 20.00 0.64 -
15 Pasang Lampu Taman UNIT 36.00 2.59 -
16 Pasang Bak Sampah 3 jenis UNIT 28.00 0.46 -
17 Urugan pasir di bawah Lantai M3 63.12 0.52 -
- TAMAN BERMAIN -
1 Galian Tanah M3 583.00 0.49 9.92 0.01 9.92 0.01 - 9.92 0.01 100.00
2 Pekerjaan Pas. Pondasi Batu Gunung 1:4 M3 27.02 0.53 27.02 0.53 - 27.02 0.53 100.00
3 Pasang batu tela 1:4 M2 188.79 0.47 37.51 0.09 37.51 0.09 - 37.51 0.09 100.00
4 Cor Kansteen beton M3 12.36 0.28 -
5 Plesteran M2 201.37 0.18 118.82 0.10 118.82 0.10 - 118.82 0.10 100.00
6 Acian M2 201.37 0.09 65.43 0.03 65.43 0.03 - 65.43 0.03 100.00
7 Cat M2 201.37 0.06 8.50 0.00 8.50 0.00 - 8.50 0.00 100.00
8 Pekerjaan Pengecatan Dudukan Tulisan Beton + GRC 26.72 0.02 26.72 0.02 - 26.72 0.02 100.00
9 Urugan Tanah peninggian lantai M2 87.45 0.33 224.30 0.84 202.51 0.76 202.51 0.76 - 202.51 0.76 100.00
10 Cor Lantai beton mutu f’c = 7,4 MPa tebal 7 cm, M3 314.02 6.42 285.02 5.83 285.02 5.83 - 285.02 5.83 100.00
11 Pasang batu Andesit Teks ture Merah M2 966.54 3.93 185.17 0.75 177.44 0.72 177.44 0.72 - 177.44 0.72 100.00
12 Pasang batu Andesit Teks ture Abu abu M2 515.50 2.10 4,214.58 17.13 3,787.34 15.39 3,787.3 15.39 - 3,787.3 15.39 100.00
13 Pasang batu Andesit Teks ture Kuning M2 81.60 0.33 -
14 Pekerjaan Coating batu andesit M2 885.59 0.35 885.59 0.35 - 885.59 0.35 100.00
15 Finishing batu Sikat M2 408.40 1.99 12.56 0.06 12.56 0.06 12.56 0.06 - 12.56 0.06 100.00
16 Pemasangan 1 m2 Keramik Disabilitas Spot Type 30 x 30 M2 2.97 0.02 4.59 0.03 4.59 0.03 - 4.59 0.03 100.00
17 Pemasangan 1 m2 Keramik Disabilitas Line Type 30 x 30 M2 70.74 0.40 68.28 0.39 68.28 0.39 - 68.28 0.39 100.00
18 Pasang kursi taman UNIT 16.00 0.51 27.00 0.87 27.00 0.87 26.00 0.84 1.00 0.03 27.00 0.87 100.00
19 Ayunan Anak UNIT 4.00 0.18 2.00 0.09 2.00 0.09 2.00 0.09 - 2.00 0.09 100.00
20 Perosotan Anak UNIT 2.00 0.08 2.00 0.08 2.00 0.08 - 2.00 0.08 100.00
21 Pasang Lampu Taman UNIT 15.00 1.08 9.00 0.65 9.00 0.65 8.00 0.58 1.00 0.07 9.00 0.65 100.00
22 Pasang Lampu Jalan UNIT 5.00 0.57 4.00 0.45 3.00 0.34 1.00 0.11 4.00 0.45 100.00
23 Pasang Lampu Spotlight + Casing Pelindung UNIT 10.00 0.11 14.00 0.16 - - - - - -
24 Pasang Tiang dan bendera UNIT 6.00 0.16 6.00 0.16 - 6.00 0.16 100.00
25 Pasang Bak Sampah 3 jenis UNIT 24.00 0.39 24.00 0.39 20.00 0.33 20.00 0.33 - 20.00 0.33 100.00
26 Urgan pasir di bawah Lantai M3 59.16 0.49 224.30 1.86 208.83 1.73 208.83 1.73 - 208.83 1.73 100.00
27 Tulisan Beton + GRC Taman Samubaah BH 13.00 0.49 13.00 0.49 - 13.00 0.49 100.00
28 Cor Beton beton mutu 19.3 Mpa M3 0.51 0.01 0.51 0.01 - 0.51 0.01 100.00
29 Bekisting M2 8.32 0.02 8.32 0.02 - 8.32 0.02 100.00
30 Pembesian KG 38.05 0.01 38.05 0.01 - 38.05 0.01 100.00
- TANGGA UTAMA -
- PEKERJAAN PERSIAPAN -
1 Pembersihan Lokasi M2 307.65 0.06 305.13 0.06 305.13 0.06 - 305.13 0.06 100.00
2 Pengukuran dan Pemasangan Bouwplank M' 79.60 0.05 79.12 0.05 79.12 0.05 - 79.12 0.05 100.00
- PEKERJAAN PONDASI -
1 Pekerjaan Galian Tanah Pondasi M3 68.61 0.06 66.41 0.06 66.41 0.06 - 66.41 0.06 100.00
2 Pekerjaan Galian Tanah Tangga M3 253.53 0.21 253.53 0.21 253.53 0.21 - 253.53 0.21 100.00
Kontrak Awal Kontrak Adendum I Kontrak Adendum III S/d Minggu Lalu Minggu ini S/d Minggu ini Thdp
NO. URAIAN PEKERJAAN SATUAN VOLUME Bobot VOLUME Bobot VOLUME Bobot Volume Bobot Volume Bobot Volume Bobot Item Pek

(%) (%) (%) (%) (%) (%) (%)


a b c d g h k l o p q r s t u v
3 Pekerjaan Pas. Pondasi Batu Gunung 1:4 M3 85.32 1.67 62.41 1.22 62.41 1.22 - 62.41 1.22 100.00
- PEKERJAAN LANTAI -
1 Urugan Tanah M3 58.20 0.22 58.20 0.22 - 58.20 0.22 100.00
2 Urugan Pasir Bawah Lantai M3 16.75 0.14 9.14 0.08 9.14 0.08 - 9.14 0.08 100.00
3 Cor Lantai beton mutu f’c = 7,4 Mpa M3 10.18 0.21 9.28 0.19 9.28 0.19 - 9.28 0.19 100.00
4 Pas dinding Batu Tela Camp, 1 : 4 M2 189.55 0.47 188.58 0.47 188.58 0.47 - 188.58 0.47 100.00
5 Pasang batu Andesit Teks ture Abu abu M2 189.55 0.77 196.03 0.80 196.03 0.80 - 196.03 0.80 100.00
- PEKERJAAN PLESTERAN DAN PENGECATAN -
1 Plesteran 1:4 tebal 15 mm M2 158.69 0.14 168.17 0.15 168.17 0.15 - 168.17 0.15 100.00
2 Acian M2 75.03 0.03 75.03 0.03 - 75.03 0.03 100.00
3 Pek Pengecatan Dinding Pembatas M2 158.69 0.09 148.99 0.09 148.99 0.09 - 148.99 0.09 100.00
- TIFA UTAMA -
- PEKERJAAN PERSIAPAN -
1 Pembersihan Lokasi M2 16.00 0.00 16.00 0.00 - 16.00 0.00 100.00
2 Pengukuran dan Pemasangan Bouwplank M2 16.00 0.01 16.00 0.01 - 16.00 0.01 100.00
- PEKERJAAN TANAH DAN PONDASI -
1 Pekerjaan Galian Tanah Pondasi M3 3.74 0.00 3.74 0.00 - 3.74 0.00 100.00
2 Urugan Tanah M3 9.83 0.04 9.83 0.04 - 9.83 0.04 100.00
3 Pekerjaan Pas. Pondasi Batu Gunung 1:4 M3 7.33 0.14 7.33 0.14 - 7.33 0.14 100.00
- PEKERJAAN BETON PASANGAN DAN PLESTERAN -
1 Pekerjaan Pondasi Beton Bertulang -
a. Beton M3 2.88 0.07 2.88 0.07 - 2.88 0.07 100.00
b. Pembesian KG 184.22 0.03 184.22 0.03 - 184.22 0.03 100.00
c. Bekisting M2 8.96 0.02 8.96 0.02 - 8.96 0.02 100.00
2 Plesteran M2 28.01 0.02 28.01 0.02 - 28.01 0.02 100.00
3 Acian M2 5.30 0.00 5.30 0.00 - 5.30 0.00 100.00
4 Relief Tifa UNIT 1.00 0.18 1.00 0.18 - 1.00 0.18 100.00
- PEKERJAAN LANTAI -
1 Cor Lantai beton mutu f’c = 7,4 Mpa M3 7.52 0.15 7.52 0.15 - 7.52 0.15 100.00
2 Pas Keramik 40x40 M2 8.72 0.03 8.72 0.03 - 8.72 0.03 100.00
- PEKERJAAN PENGECATAN -
1 Pekerjaan Pengecatan M2 22.71 0.01 22.71 0.01 - 22.71 0.01 100.00
- PEKERJAAN TIFA UTAMA -
1 Pekerjaan Tifa Utama LS 1.00 3.78 1.00 1.82 1.00 1.82 - 1.00 1.82 100.00
-
-
VI. PEKERJAAN PEMBANGUNAN PUJASERA -
- PEKERJAAN PERSIAPAN -
1 Pembersihan Lokasi M2 455.00 0.08 389.95 0.07 374.11 0.07 374.11 0.07 - 374.11 0.07 100.00
2 Pengukuran dan Pemasangan Bouwplank M' 87.00 0.05 82.17 0.05 81.78 0.05 81.78 0.05 - 81.78 0.05 100.00
- PEKERJAAN TANAH DAN PONDASI -
1 Pekerjaan Galian Tanah Pondasi Menerus M3 329.16 0.28 72.92 0.06 74.01 0.06 74.01 0.06 - 74.01 0.06 100.00
2 Urugan Kembali Galian Tanah Pondasi Menerus M3 213.11 0.13 24.67 0.02 24.67 0.02 - 24.67 0.02 100.00
3 Urugan Tanah Peninggi Lantai Bekas Galian M3 72.92 0.04 - - -
4 Urugan Tanah Peninggi Lantai Bekas Galian M3 85.46 0.32 -
5 Urugan Tanah M3 73.35 0.28 128.81 0.48 128.81 0.48 - 128.81 0.48 100.00
6 Urugan Pasir Bawah Pondasi Menerus M3 21.10 0.18 -
7 Urugan Pasir Bawah Lantai M3 22.55 0.19 14.63 0.12 14.06 0.12 14.06 0.12 - 14.06 0.12 100.00
8 Pasangan Batu Kosong M3 42.20 0.58 -
9 Pekerjaan Pas. Pondasi Batu Gunung 1:4 M3 116.05 2.26 114.40 2.23 115.49 2.25 115.49 2.25 - 115.49 2.25 100.00
10 Pondasi Telapak Beton Bertulang M3 0.88 0.07 0.88 0.07 0.88 0.07 - 0.88 0.07 100.00
11 Kolom Telapak Beton Bertulang M3 0.11 0.01 0.11 0.01 0.11 0.01 - 0.11 0.01 100.00
- PEKERJAAN STRUKTUR DAN PENULANGAN -
1 Pek. Sloof 15/20 , beton mutu 19.3 Mpa -
a. Pek. Sloof 15/20 , beton mutu 19.3 Mpa M3 10.55 0.24 5.81 0.133 5.81 0.13 5.81 0.13 - 5.81 0.13 100.00
b. Pembesian KG 1899 0.34 988.83 0.176 988.83 0.18 988.83 0.18 - 988.83 0.18 100.00
c. Bekisting M2 105.5 0.19 77.52 0.141 77.52 0.14 77.52 0.14 - 77.52 0.14 100.00
2 Pek. Kolom K1 (20/20) , beton mutu 19.3 Mpa -
a. Pek. Kolom K1 (20/20) , beton mutu 19.3 Mpa M3 4.80 0.11 -
b. Pembesian KG 864.00 0.15 -
c. Bekisting M2 96.00 0.26 -
3 Pek. Kolom K1 , beton mutu 19.3 Mpa -
a. Pek. Kolom K1 M3 2.57 0.06 2.57 0.06 2.57 0.06 - 2.57 0.06 100.00
b. Pek. Pembesian KG 333.89 0.06 333.89 0.06 333.89 0.06 - 333.89 0.06 100.00
c. Pek. Bekisting M2 28.31 0.08 28.31 0.08 28.31 0.08 - 28.31 0.08 100.00
4 Pek. Kolom K2 (15/15), beton mutu 19.3 Mpa -
a. Pek. Kolom K2 (15/15), beton mutu 19.3 Mpa M3 3.87 0.09 -
b. Pembesian KG 696.60 0.12 -
c. Bekisting M2 103.20 0.28 -
5 Pek. Kolom K2 (20/30) , beton mutu 19.3 Mpa -
a. Pek. Kolom K2 (20/30) M3 2.02 0.05 2.02 0.05 2.02 0.05 - 2.02 0.05 100.00
b. Pek. Pembesian KG 311.50 0.06 311.50 0.06 311.50 0.06 - 311.50 0.06 100.00
c. Pek. Bekisting M2 33.60 0.09 33.60 0.09 33.60 0.09 - 33.60 0.09 100.00
6 Pek. Kolom K2 (20/20) , beton mutu 19.3 Mpa -
a. Pek. Kolom K2 (20/20) M3 3.54 0.08 3.54 0.08 3.54 0.08 - 3.54 0.08 100.00
b. Pek. Pembesian KG 773.17 0.14 773.17 0.14 773.17 0.14 - 773.17 0.14 100.00
c. Pek. Bekisting M2 70.88 0.19 70.88 0.19 70.88 0.19 - 70.88 0.19 100.00
7 Pek. Kolom K4 (13/13) , beton mutu 19.3 Mpa -
a. Pek. Kolom K4 (13/13) M3 1.86 0.04 1.86 0.04 1.86 0.04 - 1.86 0.04 100.00
b. Pek. Pembesian KG 506.86 0.09 506.86 0.09 506.86 0.09 - 506.86 0.09 100.00
c. Pek. Bekisting M2 57.10 0.15 57.10 0.15 57.10 0.15 - 57.10 0.15 100.00
8 Pek. Ring Balok (15/20), beton mutu 19.3 Mpa -
a. Pek. Ring Balok (15/20), beton mutu 19.3 Mpa M3 6.33 0.14 -
b. Pembesian KG 1,139.40 0.20 -
c. Bekisting M2 84.40 0.23 -
9 Pek. Balok (13/20), beton mutu 19.3 Mpa -
a. Pek. Balok (13/20), beton mutu 19.3 Mpa M3 6.69 0.15 6.69 0.15 6.69 0.15 - 6.69 0.15 100.00
b. Pek. Pembesian KG 1,286.03 0.23 1,286.03 0.23 1,286.0 0.23 - 1,286.0 0.23 100.00
c. Pek. Bekisting M2 102.92 0.28 102.92 0.28 102.92 0.28 - 102.92 0.28 100.00
10 Pek. Balok (20/40), beton mutu 19.3 Mpa -
a. Pek. Balok (20/40), beton mutu 19.3 Mpa M3 4.48 0.10 4.48 0.10 4.48 0.10 - 4.48 0.10 100.00
b. Pek. Pembesian KG 646.13 0.12 646.13 0.12 646.13 0.12 - 646.13 0.12 100.00
c. Pek. Bekisting M2 44.80 0.12 44.80 0.12 44.80 0.12 - 44.80 0.12 100.00
11 Pek. Dak Atap Tebal 12cm, beton mutu 19.3 Mpa -
a . Pek. Dak Atap Tebal 12cm, beton mutu 19.3 Mpa M3 11.88 0.27 -
b. Pembesian KG 2,138.40 0.38 -
c. Bekisting M2 110.10 0.41 -
12 Plat Dak Beton mutu 19.3 Mpa -
a. Plat Dak Beton mutu 19.3 Mpa M3 12.21 0.28 13.35 0.31 13.35 0.31 - 13.35 0.31 100.00
b. Pek. Pembesian KG 1,812.08 0.32 1,990.17 0.35 1,990.2 0.35 - 1,990.2 0.35 100.00
c. Pek. Bekisting M2 101.71 0.38 120.54 0.45 120.54 0.45 - 120.54 0.45 100.00
13 Pek. Kolom 20/50, beton mutu 19.3 Mpa -
a. Pek. Kolom 20/50, beton mutu 19.3 Mpa M3 2.20 0.05 -
b. Pembesian KG 396.00 0.07 -
c. Bekisting
Pek. Bekisting M2 30.80 0.08 -
14 Pek. Balok 20/50, beton mutu 19.3 Mpa -
a. Pek. Balok 20/50, beton mutu 19.3 Mpa M3 0.24 0.01 -
b. Pembesian KG 43.20 0.01 -
c. Bekisting M2 9.60 0.03 -
- PEKERJAAN DINDING DAN LANTAI -
Kontrak Awal Kontrak Adendum I Kontrak Adendum III S/d Minggu Lalu Minggu ini S/d Minggu ini Thdp
NO. URAIAN PEKERJAAN SATUAN VOLUME Bobot VOLUME Bobot VOLUME Bobot Volume Bobot Volume Bobot Volume Bobot Item Pek

(%) (%) (%) (%) (%) (%) (%)


a b c d g h k l o p q r s t u v
1 Pas dinding Batu Tela Camp, 1 : 4 M2 495.90 1.23 -
2 Pek. Batu Bata Merah tebal 1/2 bata, 1SP : 4PP M2 352.61 0.872 347.09 0.86 347.09 0.86 - 347.09 0.86 100.00
3 Plesteran 1:4 tebal 15 mm M2 991.80 0.86 602.75 0.52 650.46 0.57 650.46 0.57 - 650.46 0.57 100.00
4 Pekerjaan Acian M2 991.80 0.43 602.75 0.26 715.96 0.31 715.96 0.31 - 715.96 0.31 100.00
5 Pekerjaan Lantai Keramik 40/40 M2 356.25 1.14 333.88 1.06 334.72 1.07 334.72 1.07 - 334.72 1.07 100.00
6 Pekerjaan Keramik Lantai KM/WC 20/20 M2 15.75 0.05 -
7 Pekerjaan Keramik dinding KM/WC 20/25 M2 101.22 0.38 102.48 0.38 101.50 0.38 101.50 0.38 - 101.50 0.38 100.00
8 Cor Lantai beton mutu 7,4 MPa tebal 7 cm, M3 26.04 0.53 23.38 0.48 19.60 0.40 19.60 0.40 - 19.60 0.40 100.00
9 Cor Rabat beton mutu 7,4 Mpa tebal 5 cm, M3 3.95 0.08 -
10 Pekerjaan Roster M2 15.00 0.10 10.24 0.07 10.24 0.07 10.24 0.07 - 10.24 0.07 100.00
- PEKERJAAN KUSEN, KACA, KUNCI, DAN ALAT PENGGANTUNG -
1 Pek. Kusen Pintu, Jendela, Jalusi dan Boven Kayu Besi M3 0.50 0.04 0.64 0.05 0.64 0.05 0.64 0.05 - 0.64 0.05 100.00
2 Pek. Daun Pintu Panil Kayu Besi M2 27.72 0.19 20.93 0.14 20.93 0.14 20.93 0.14 - 20.93 0.14 100.00
3 Pas. Kunci Tanam 2 Slaag BH 18.00 0.07 13.00 0.05 13.00 0.05 13.00 0.05 - 13.00 0.05 100.00
4 Pas. Engsel Pintu Panil Kayu SET 27.00 0.02 39.00 0.02 39.00 0.02 39.00 0.02 - 39.00 0.02 100.00
5 Pek. Jalusi Kaca M2 3.80 0.02 3.80 0.02 3.80 0.02 - 3.80 0.02 100.00
6 Pas. Grendel Pintu BH 12.00 0.01 13.00 0.01 13.00 0.01 - 13.00 0.01 100.00
7 Pintu Rolling Door M2 79.80 0.69 -
8 Pintu Lipat Besi M2 31.00 0.24 31.00 0.24 31.00 0.24 - 31.00 0.24 100.00
9 Pas. Teralis Besi M2 26.73 0.17 -
10 Tulisan Sign Acrylic 3.00 0.01 3.00 0.01 - 3.00 0.01 100.00
11 Handrail Toilet Disabilitas 1.00 0.02 1.00 0.02 - 1.00 0.02 100.00
12 Tempat tisu Toilet 1.00 0.00 1.00 0.00 - 1.00 0.00 100.00
- PEKERJAAN ATAP DAN PLAFOND -
1 Pas. Kuda-kuda dan Skoor Kayu Besi 5/10 M3 4.24 0.33 3.20 0.25 3.20 0.25 3.20 0.25 - 3.20 0.25 100.00
2 Pekerjaan rangka atap kanopi hollow 4/4 KG 468.29 0.19 - - 140.49 0.06 140.49 0.06 30.00
3 Pekerjaan rangka atap kanopi hollow 2/4 KG 86.77 0.03 - - 26.03 0.01 26.03 0.01 30.00
4 Pas. Gording Kayu Besi 5/10 M3 3.38 0.25 2.19 0.16 2.19 0.16 2.19 0.16 - 2.19 0.16 100.00
5 Pas. Atap seng gelombang BJLS 0.30 mm M2 416.00 0.58 -
6 Pekerjaan penutup rangka atap M2 329.39 0.46 329.39 0.46 329.39 0.46 - 329.39 0.46 100.00
7 Pekerjaan penutup atap kanopi M2 49.40 0.11 - - - - - -
8 Pas. Lisplank Kayu besi 3/30 M' 80.00 0.07 -
9 Pemasangan Lisplank M' 71.34 0.05 110.99 0.08 110.99 0.08 - 110.99 0.08 100.00
10 Pas. Nok Atap M' 48.00 0.02 39.65 0.02 39.65 0.02 39.65 0.02 - 39.65 0.02 100.00
11 Pas. Rangka Plafond M2 364.00 0.35 312.43 0.30 299.76 0.29 299.76 0.29 - 299.76 0.29 100.00
12 Pas. Plafond tripleks 4 mm M2 364.00 0.23 312.43 0.20 299.76 0.19 299.76 0.19 - 299.76 0.19 100.00
13 Pas. List Plafond Kayu profil M' 416.00 0.11 457.93 0.12 457.93 0.12 457.93 0.12 - 457.93 0.12 100.00
14 Talang Air M' 71.34 0.16 48.00 0.10 48.00 0.10 - 48.00 0.10 100.00
- PEKERJAAN CAT DAN LABURAN -
1 Cat Kilap Kusen Pintu, Jendela, Jalusi Dan Daun Pintu M2 79.44 0.05 123.26 0.08 97.95 0.06 97.95 0.06 - 97.95 0.06 100.00
2 Cat/Laburan Tembok dan Plafond M2 1,355.80 0.43 915.18 0.29 1,097.93 0.35 1,097.9 0.35 - 1,097.9 0.35 100.00
3 Cat Menie Besi M2 98.08 0.03 - - - - - -
4 Cat Besi M2 98.08 0.04 - - - - - -
- PEKERJAAN MECANIKAL DAN ELEKTRIKAL -
1 Pas. Titik Instalasi BH 80.00 0.15 69.00 0.13 69.00 0.13 69.00 0.13 - 69.00 0.13 100.00
2 Stop Kontak BH 24.00 0.06 15.00 0.04 15.00 0.04 15.00 0.04 - 15.00 0.04 100.00
3 Saklar Tunggal BH 13.00 0.03 13.00 0.03 13.00 0.03 - 13.00 0.03 100.00
4 Saklar Ganda BH 24.00 0.06 6.00 0.02 6.00 0.02 6.00 0.02 - 6.00 0.02 100.00
5 Pas. MCB 6A BH 6.00 0.03 5.00 0.02 5.00 0.02 5.00 0.02 - 5.00 0.02 100.00
6 Lampu XL 18 Watt BH 56.00 0.13 11.00 0.03 11.00 0.03 11.00 0.03 - 11.00 0.03 100.00
7 Lampu SL 23 Watt BH 24.00 0.06 24.00 0.06 24.00 0.06 - 24.00 0.06 100.00
8 Pemasangan Listrik 1.300 watt UNIT 6.00 0.20 -
9 Box Panel lengkap UNIT 6.00 0.03 1.00 0.00 1.00 0.00 1.00 0.00 - 1.00 0.00 100.00
- PEKERJAAN SANITAIR DAN SEPTICTANK -
1 Galian Tanah M3 11.33 0.01 11.33 0.01 11.33 0.01 - 11.33 0.01 100.00
2 Pas dinding Batu Tela Camp, 1 : 4 M2 15.95 0.04 15.95 0.04 15.95 0.04 - 15.95 0.04 100.00
3 Urugan Pasir Resapan M3 0.49 0.00 0.49 0.00 0.49 0.00 - 0.49 0.00 100.00
4 Urugan Kerikil Resapan M3 0.81 0.01 0.81 0.01 0.81 0.01 - 0.81 0.01 100.00
5 Ijuk Resapan M2 0.33 0.00 0.33 0.00 0.33 0.00 - 0.33 0.00 100.00
6 Sloof Beton Bertulang M3 0.28 0.03 0.28 0.03 0.28 0.03 - 0.28 0.03 100.00
7 Kolom Beton Bertulang M3 0.23 0.02 0.23 0.02 0.23 0.02 - 0.23 0.02 100.00
8 Ring Balok Beton Bertulang M3 0.38 0.04 0.38 0.04 0.38 0.04 - 0.38 0.04 100.00
9 Plat Beton Bertulang M3 0.87 0.08 0.87 0.08 0.87 0.08 - 0.87 0.08 100.00
10 Plesteran 1 : 2, tebal 15 mm M2 20.25 0.02 20.25 0.02 20.25 0.02 - 20.25 0.02 100.00
11 Pas. Kloset Jongkok BH 4.00 0.03 4.00 0.03 4.00 0.03 - 4.00 0.03 100.00
12 Pas. Kloset Duduk BH 3.00 0.09 3.00 0.09 3.00 0.09 - 3.00 0.09 100.00
13 Pas. Urinoir BH 3.00 0.04 3.00 0.04 3.00 0.04 - 3.00 0.04 100.00
14 Meja Dapur beton+bak zink BH 3.00 0.11 3.00 0.11 3.00 0.11 - 3.00 0.11 100.00
15 Pekerjaan Pengecatan M2 0.74 0.00 0.95 0.00 0.95 0.00 - 0.95 0.00 100.00
16 Pekerjaan Lantai Keramik 40/40 M2 6.79 0.02 6.79 0.02 6.79 0.02 - 6.79 0.02 100.00
17 Pas. Pipa Air Kotor PVC 4" dari Wc ke Septictank dan Resapan M' 48.00 0.08 24.00 0.04 24.00 0.04 - 24.00 0.04 100.00
18 Pas. Pipa Air Kotor PVC 2" dari Km+Urinoir+Wastafel M' 40.00 0.03 48.00 0.03 48.00 0.03 - 48.00 0.03 100.00
19 Pas. Floor Drain BH 9.00 0.01 9.00 0.01 9.00 0.01 - 9.00 0.01 100.00
20 Pas. Kran Air 3/4 BH 12.00 0.01 7.00 0.01 7.00 0.01 - 7.00 0.01 100.00
21 Pas. Wastafel BH 5.00 0.07 5.00 0.07 5.00 0.07 - 5.00 0.07 100.00
22 Pas. Pipa Air Bersih PVC 1" M' 52.00 0.02 8.00 0.00 8.00 0.00 - 8.00 0.00 100.00
23 Pas. Pipa Air Bersih PVC 3/4" M' 40.00 0.01 64.00 0.02 64.00 0.02 - 64.00 0.02 100.00
24 Pas. Pipa Air Bersih PVC 2 1/2" M' 11.00 0.01 11.00 0.01 - 11.00 0.01 100.00
25 Tempat Sampah ` UNIT 4.00 0.00 5.00 0.00 5.00 0.00 - 5.00 0.00 100.00
26 Ember BH 4.00 0.00 4.00 0.00 - 4.00 0.00 100.00
27 Sumur Bor BH 1.00 0.26 - - -
28 Pompa Sumersible BH 1.00 0.03 - - -
- PEKERJAAN BAK AIR -
1 Galian Tanah M3 1.80 0.00 1.80 0.00 - 1.80 0.00 100.00
2 Pas dinding Batu Tela Camp, 1 : 4 M2 2.48 0.01 2.48 0.01 - 2.48 0.01 100.00
3 Cor Beton beton bak air M3 2.81 0.06 2.81 0.06 - 2.81 0.06 100.00
4 Pembesian KG 507.80 0.09 507.80 0.09 - 507.80 0.09 100.00
5 Bekisting M2 18.72 0.03 18.72 0.03 - 18.72 0.03 100.00
6 Plesteran M2 4.96 0.00 4.96 0.00 - 4.96 0.00 100.00
7 Acian M2 27.44 0.01 27.44 0.01 - 27.44 0.01 100.00
8 Pengecatan M2 23.20 0.01 23.20 0.01 - 23.20 0.01 100.00
9 Penutup Besi Manhole M2 0.72 0.01 0.72 0.01 - 0.72 0.01 100.00
10 Pompa Hisap BH 1.00 0.02 1.00 0.02 - 1.00 0.02 100.00
11 Pas. Pipa Air Bersih PVC 3/4" M 40.00 0.01 40.00 0.01 - 40.00 0.01 100.00
-
-
VII. PEKERJAAN PEMBANGUNAN POS JAGA -
- PEKERJAAN PERSIAPAN -
1 Pembersihan Lokasi M2 25.87 0.00 8.00 0.00 8.00 0.00 8.00 0.00 - 8.00 0.00 100.00
2 Pengukuran dan Pemasangan Bouwplank M' 17.00 0.01 12.00 0.01 12.00 0.01 12.00 0.01 - 12.00 0.01 100.00
- PEKERJAAN TANAH DAN PONDASI - - -
1 Pekerjaan Galian Tanah Pondasi Menerus M3 16.49 0.01 5.04 0.00 5.04 0.00 5.04 0.00 - 5.04 0.00 100.00
2 Urugan Kembali Galian Tanah Pondasi Menerus M3 4.15 0.00 1.68 0.00 1.68 0.00 1.68 0.00 - 1.68 0.00 100.00
3 Urugan Tanah Peninggi Lantai Bekas Galian M3 3.48 0.00 0.56 0.00 - - -
4 Urugan Tanah 0.56 0.00 0.56 0.00 - 0.56 0.00 100.00
5 Urugan Pasir Bawah Pondasi Menerus M3 0.85 0.01 -
6 Urugan Pasir Bawah Lantai M3 1.22 0.01 0.35 0.00 0.35 0.00 0.35 0.00 - 0.35 0.00 100.00
7 Pasangan Batu Kosong M3 5.10 0.07 -
8 Pekerjaan Pas. Pondasi Batu Gunung 1:4 M3 7.48 0.15 3.57 0.07 3.57 0.07 3.57 0.07 - 3.57 0.07 100.00
- PEKERJAAN STRUKTUR DAN PENULANGAN -
Kontrak Awal Kontrak Adendum I Kontrak Adendum III S/d Minggu Lalu Minggu ini S/d Minggu ini Thdp
NO. URAIAN PEKERJAAN SATUAN VOLUME Bobot VOLUME Bobot VOLUME Bobot Volume Bobot Volume Bobot Volume Bobot Item Pek

(%) (%) (%) (%) (%) (%) (%)


a b c d g h k l o p q r s t u v
1 Pek. Sloof 15/20, beton mutu 19.3 Mpa -
a. Pek. Sloof 15/20, beton mutu 19.3 Mpa M3 0.51 0.01 -
b. Pek. Sloof 13/20 M3 0.36 0.01 0.36 0.01 0.36 0.01 - 0.36 0.01 100.00
c Pek. Pembesian KG 91.80 0.02 68.81 0.01 68.81 0.01 68.81 0.01 - 68.81 0.01 100.00
d Pek. Bekisting M2 6.80 0.01 5.60 0.01 5.60 0.01 5.60 0.01 - 5.60 0.01 100.00
2 Pek. Kolom K2 (15/15), beton mutu 19.3 Mpa -
a. Pek. Kolom K2 (15/15), beton mutu 19.3 Mpa M3 0.55 0.01 -
b. Pek. Kolom 13/13 M3 0.28 0.01 0.09 0.00 0.09 0.00 - 0.09 0.00 100.00
c Pek. Pembesian KG 100.44 0.02 76.38 0.01 22.49 0.00 22.49 0.00 - 22.49 0.00 100.00
d Pek. Bekisting M2 14.88 0.04 8.58 0.02 2.86 0.01 2.86 0.01 - 2.86 0.01 100.00
3 a. Pek. Kolom K1 (13/20), beton mutu 19.3 Mpa -
b. Pek. Kolom 13/20 0.29 0.01 0.29 0.01 - 0.29 0.01 100.00
c Pek. Pembesian 43.04 0.01 43.04 0.01 - 43.04 0.01 100.00
d Pek. Bekisting 7.26 0.02 7.26 0.02 - 7.26 0.02 100.00
4 Pek. Ring Balok (15/20), beton mutu 19.3 Mpa -
a. Pek. Ring Balok (15/20), beton mutu 19.3 Mpa M3 0.51 0.01 -
b. Pek. Ring Balok 13/20 0.68 0.02 0.68 0.02 0.68 0.02 - 0.68 0.02 100.00
c Pek. Pembesian KG 91.80 0.02 130.07 0.02 130.07 0.02 130.07 0.02 - 130.07 0.02 100.00
d Pek. Bekisting M2 10.20 0.03 10.40 0.03 10.40 0.03 10.40 0.03 - 10.40 0.03 100.00
5 Pek. Ring Balok Gavel(15/20), beton mutu 19.3 Mpa -
a. Pek. Ring Balok Gavel(15/20), beton mutu 19.3 Mpa M3 0.14 0.00 -
b. Pek. Pembesian KG 25.70 0.00 -
c. Pek. Bekisting M2 1.90 0.01 -
6 Plat Dak Beton mutu 19.3 Mpa -
a. Plat Dak Beton M3 1.40 0.03 1.40 0.03 1.40 0.03 - 1.40 0.03 100.00
b. Bekisting KG 11.64 0.04 11.64 0.04 11.64 0.04 - 11.64 0.04 100.00
c. Pembesian M2 216.88 0.04 216.88 0.04 216.88 0.04 - 216.88 0.04 100.00
7 Pek. Kolom Gavel(15/15), beton mutu 19.3 Mpa -
a. Pek. Kolom Gavel(15/15), beton mutu 19.3 Mpa M3 0.05 0.00 -
b. Pek. Pembesian KG 10.61 0.00 -
c. Pek. Bekisting M2 1.57 0.00 -
8 Pek. Plat meja, beton mutu 19.3 Mpa -
a. Pek. Plat meja, beton mutu 19.3 Mpa M3 0.14 0.00 -
b. Pek. Pembesian KG 25.92 0.00 -
c. Pek. Bekisting M2 2.04 0.01 -
- PEKERJAAN DINDING DAN LANTAI -
1 Pas dinding batu Tela Camp, 1 : 4 M2 52.70 0.13 -
2 Pek. Batu Bata Merah tebal 1/2 bata, 1SP : 4PP M2 21.76 0.05 21.76 0.05 21.76 0.05 - 21.76 0.05 100.00
3 Plesteran 1:4 tebal 15 mm M2 105.40 0.09 43.51 0.04 43.51 0.04 43.51 0.04 - 43.51 0.04 100.00
4 Pekerjaan Acian M2 105.40 0.05 43.51 0.02 43.51 0.02 43.51 0.02 - 43.51 0.02 100.00
5 Pekerjaan Lantai Keramik 40/40 M2 12.00 0.04 7.24 0.02 7.24 0.02 7.24 0.02 - 7.24 0.02 100.00
6 Pekerjaan Dinding Keramik 20/20 M2 1.80 0.01 -
7 Cor Lantai beton mutu 7,4 Mpa tebal 3 cm, M3 0.36 0.01 -
8 Cor Rabat beton mutu7,4 Mpa tebal 5 cm, M3 0.62 0.01 -
9 Cor Lantai beton mutu 7,4 Mpa tebal 7 cm, M3 0.49 0.01 0.49 0.01 0.49 0.01 - 0.49 0.01 100.00
10 Pekerjaan Roster M2 2.28 0.02 -
- PEKERJAAN KUSEN, KACA, KUNCI, & ALAT PENGGANTUNG -
1 Pek. Kusen Pintu, Jendela, Jalusi dan Boven Kayu Besi M3 0.08 0.01 0.12 0.01 0.12 0.01 0.12 0.01 - 0.12 0.01 100.00
2 Pek. Daun Pintu Panil Kayu Besi M2 3.46 0.02 1.69 0.01 1.69 0.01 1.69 0.01 - 1.69 0.01 100.00
3 Pek. Kusen Pintu Aluminium M2 0.76 0.00 -
4 Pek. Jendela Kaca M2 0.24 0.00 3.12 0.02 3.12 0.02 3.12 0.02 - 3.12 0.02 100.00
5 Pek. Pintu Kaca M2 5.04 0.03 -
6 Pas. Jalusi Kayu Besi M2 0.78 0.01 -
7 Pas. Kunci Tanam 2 Slaag BH 2.00 0.01 1.00 0.00 1.00 0.00 1.00 0.00 - 1.00 0.00 100.00
8 Pas. Engsel Pintu Panil Kayu SET 3.00 0.00 3.00 0.00 3.00 0.00 3.00 0.00 - 3.00 0.00 100.00
9 Engsel Jendela BH 8.00 0.00 8.00 0.00 8.00 0.00 - 8.00 0.00 100.00
10 Pas. Grendel Jendela dan Pintu BH 2.00 0.00 4.00 0.00 5.00 0.00 5.00 0.00 - 5.00 0.00 100.00
11 Hak Angin BH 8.00 0.00 8.00 0.00 - 8.00 0.00 100.00
12 Tarikan Jendela BH 4.00 0.00 4.00 0.00 - 4.00 0.00 100.00
13 Tulisan Sign Acrylic BH 1.00 0.00 1.00 0.00 - 1.00 0.00 100.00
- PEKERJAAN ATAP DAN PLAFOND -
1 Pas. Kuda-kuda dan Skoor Kayu Besi 5/10 M3 0.18 0.01 0.20 0.02 0.20 0.02 0.20 0.02 - 0.20 0.02 100.00
2 Pas. Gording Kayu Besi 5/10 M3 0.22 0.02 0.15 0.01 0.15 0.01 0.15 0.01 - 0.15 0.01 100.00
3 Pas. Alumunium Spandek 6 feet tebal 3 mm M2 27.43 0.04 -
4 Pekerjaan penutup rangka atap M2 18.41 0.03 18.41 0.03 18.41 0.03 - 18.41 0.03 100.00
5 Pas. Lisplank Kayu besi 3/30 M' 19.58 0.02 -
6 Pemasangan lisplank M' 15.96 0.01 25.16 0.02 25.16 0.02 - 25.16 0.02 100.00
7 Pas. Nok Atap M' 5.40 0.00 9.20 0.00 9.20 0.00 9.20 0.00 - 9.20 0.00 100.00
8 Pas. Rangka Plafond M2 15.75 0.02 11.33 0.01 11.33 0.01 11.33 0.01 - 11.33 0.01 100.00
9 Pas. Plafond tripleks 4 mm M2 15.75 0.01 11.33 0.01 11.33 0.01 11.33 0.01 - 11.33 0.01 100.00
10 Pas. List Plafond Kayu profil M' 38.00 0.01 42.04 0.01 42.04 0.01 42.04 0.01 - 42.04 0.01 100.00
11 Talang Air M' 15.96 0.04 - - -
- PEKERJAAN CAT DAN LABURAN -
1 Cat Kilap Kusen Pintu, Jendela, Jalusi Dan Daun Pintu M2 10.34 0.01 20.60 0.01 17.32 0.01 17.32 0.01 - 17.32 0.01 100.00
2 Cat/Laburan Tembok dan Plafond M2 180.19 0.06 54.84 0.02 65.59 0.02 65.59 0.02 - 65.59 0.02 100.00
- PEKERJAAN MECANIKAL DAN ELEKTRIKAL -
1 Pas. Titik Instalasi BH 8.00 0.02 5.00 0.01 5.00 0.01 5.00 0.01 - 5.00 0.01 100.00
2 Stop Kontak BH 1.00 0.00 2.00 0.01 2.00 0.01 2.00 0.01 - 2.00 0.01 100.00
3 Saklar Ganda BH 2.00 0.01 1.00 0.00 1.00 0.00 1.00 0.00 - 1.00 0.00 100.00
4 Lampu SL 18 Watt BH 5.00 0.01 2.00 0.00 2.00 0.00 2.00 0.00 - 2.00 0.00 100.00
-
-
VIII. PEKERJAAN PEMBANGUNAN KIOS SOUVENIR -
- PEKERJAAN PERSIAPAN -
1 Pengukuran dan pemasangan bouwplank M' 22.00 0.01 -
- PEKERJAAN GALIAN DAN URUGAN -
1 Galian Tanah Pondasi M3 10.29 0.01 -
2 Timbunan Kembali Galian Tanah Pondasi M3 2.57 0.00 -
3 Urugan Tanah Dibawah Lantai M3 4.50 0.02 -
4 Urugan Pasir di Bawah Pondasi M3 0.73 0.01 -
5 Urugan Pasir di Bawah Lantai M3 0.90 0.01 -
- PEKERJAAN BETON, PASANGAN, DAN PLESTERAN -
1 Pondasi Batu Gunung sp 1:4 M3 7.35 0.14 -
2 Beton Tumbuk sp 1:3:5 M3 0.90 0.02 -
3 Beton Sloof 15/20, beton mutu 19.3 Mpa M3 0.63 0.01 -
Bekisting M2 8.40 0.02 -
Pembesian KG 75.60 0.01 -
4 Beton Kolom 15/15, beton mutu 19.3 Mpa M3 0.40 0.01 -
Bekisting M2 5.40 0.01 -
Pembesian KG 48.60 0.01 -
5 beton Ring Balok 15/20, beton mutu 19.3 Mpa M3 0.63 0.01 -
Bekisting M2 8.40 0.02 -
Pembesian KG 75.60 0.01 -
6 Beton Kolom Gavel(15/15), beton mutu 19.3 Mpa M3 0.24 0.01 -
Bekisting M2 5.23 0.01 -
Pembesian KG 24.81 0.00 -
7 Pasangan Batu Tela Dinding sp. 1 : 4 M2 61.20 0.15 -
8 Plesteran Dinding sp. 1 : 4 M2 122.40 0.11 -
9 Acian M2 122.40 0.05 -
Kontrak Awal Kontrak Adendum I Kontrak Adendum III S/d Minggu Lalu Minggu ini S/d Minggu ini Thdp
NO. URAIAN PEKERJAAN SATUAN VOLUME Bobot VOLUME Bobot VOLUME Bobot Volume Bobot Volume Bobot Volume Bobot Item Pek

(%) (%) (%) (%) (%) (%) (%)


a b c d g h k l o p q r s t u v
10 Beton Plat Meja, beton mutu 19.3 Mpa M3 0.35 0.01 -
Pek. Pembesian KG 63.03 0.01 -
Pek. Bekisting M2 2.88 0.01 -
11 Pekerjaan Roster M2 2.76 0.02 -
12 Cor Rabat Beton Mutu 7,4 Mpa tebal 5 cm M3 1.72 0.04 -
- PEKERJAAN KUDA-KUDA DAN ATAP -
1 Kuda-kuda ky. Klas I M3 0.39 0.03 -
2 Gording ky. Klas I M3 0.32 0.02 -
3 Pas. Atap seng gelombang BJLS 0.30 mm M2 56.00 0.08 -
4 Pas. Papan Nok M2 3.20 0.00 -
5 Nok Atap Seng Plat M' 8.00 0.00 -
6 Talang Air M' 16.00 0.03 -
7 Listplank Ky. Klas I 2x2/20 M' 30.00 0.02 -
- PEKERJAAN PLAFOND -
1 Pasang Rangka Plafond M2 48.00 0.05 -
2 Plafond Tripleks 4 mm M2 48.00 0.03 -
3 List propil SP 4 M' 42.00 0.01 -
- PEKERJAAN PENUTUP LANTAI DAN DINDING -
1 Lantai Keramik 40/40 M2 18.00 0.06 -
- PEKERJAAN PENGECATAN -
1 Cat Tembok M2 122.40 0.04 -
2 Cat Listplank M2 6.60 0.00 -
3 Cat Plafond M2 18.00 0.01 -
- PEKERJAAN INSTALASI LISTRIK -
1 Box Sekring SET 1.00 0.01 -
2 Lampu SL 18 Watt TITIK 4.00 0.01 -
3 Saklar Ganda TITIK 2.00 0.01 -
4 Stop Kontak TITIK 2.00 0.01 -
-
-
IX. PEKERJAAN PEMBANGUNAN TOILET -
- PEKERJAAN PERSIAPAN -
1 Pembersihan Lokasi M2 96.46 0.02 63.00 0.01 96.12 0.02 96.12 0.02 - 96.12 0.02 100.00
2 Pengukuran dan Pemasangan Bouwplank M' 39.00 0.02 32.00 0.02 31.32 0.02 31.32 0.02 - 31.32 0.02 100.00
- PEKERJAAN TANAH DAN PONDASI -
1 Pekerjaan Galian Tanah Pondasi Menerus M3 221.06 0.19 25.02 0.02 6.69 0.01 6.69 0.01 - 6.69 0.01 100.00
2 Urugan Kembali Galian Tanah Pondasi Menerus M3 4.85 0.00 2.23 0.00 2.23 0.00 - 2.23 0.00 100.00
3 Urugan Tanah Peninggi Lantai Bekas Galian M3 20.45 0.01 16.34 0.01 - - -
4 Urugan Tanah M3 72.37 0.27 72.37 0.27 - 72.37 0.27 100.00
5 Urugan Pasir Bawah Pondasi Menerus M3 1.96 0.02 -
6 Urugan Pasir Bawah Lantai M3 2.57 0.02 2.95 0.02 3.00 0.02 3.00 0.02 - 3.00 0.02 100.00
7 Pasangan Batu Kosong M3 6.66 0.09 -
8 Pekerjaan Pas. Pondasi Batu Gunung 1:4 M3 16.98 0.33 28.10 0.55 28.26 0.55 28.26 0.55 - 28.26 0.55 100.00
- PEKERJAAN STRUKTUR DAN PENULANGAN -
1 Pek. Sloof 15/20, mutu f’c = 24,0 Mpa -
a. Pek. Sloof 15/20, mutu fc = 24,0 Mpa M3 1.60 0.04 2.24 0.05 2.13 0.05 2.13 0.05 - 2.13 0.05 100.00
b. Pembesian KG 263.54 0.05 381.82 0.07 368.68 0.07 368.68 0.07 - 368.68 0.07 100.00
c. Bekisting M2 21.44 0.04 29.93 0.05 28.45 0.05 28.45 0.05 - 28.45 0.05 100.00
2 Pek. Kolom (15/15), beton mutu 19.3 Mpa -
a. Pek. Kolom 15/15,beton mutu fc = 19.3 Mpa M3 1.41 0.03 -
b. Pek. Kolom 13/13 M3 0.94 0.02 0.94 0.02 0.94 0.02 - 0.94 0.02 100.00
c. Pembesian KG 255.48 0.05 257.95 0.05 257.95 0.05 257.95 0.05 - 257.95 0.05 100.00
d. Bekisting M2 28.35 0.08 28.96 0.08 28.96 0.08 28.96 0.08 - 28.96 0.08 100.00
3 Pek. Kolom (20/20), beton mutu 19.3 Mpa -
a. Pek. Kolom 20/20 M3 1.50 0.03 1.50 0.03 1.50 0.03 - 1.50 0.03 100.00
b. Pek. Pembesian KG 325.76 0.06 325.76 0.06 325.76 0.06 - 325.76 0.06 100.00
c. Pek. Bekisting M2 29.92 0.08 29.92 0.08 29.92 0.08 - 29.92 0.08 100.00
3 Pek. Ring Balok (15/20), beton mutu 19.3 Mpa -
a. Pek. Ring Balok (15/20), beton mutu 19.3 Mpa M3 1.19 0.03 -
b. Pek. Ring Balok Latei 13/20 0.83 0.02 0.83 0.02 0.83 0.02 - 0.83 0.02 100.00
b. Pembesian KG 196.30 0.03 160.06 0.03 160.06 0.03 160.06 0.03 - 160.06 0.03 100.00
c. Bekisting M2 21.94 0.06 14.13 0.04 14.13 0.04 14.13 0.04 - 14.13 0.04 100.00
4 Pek. Ring Balok (15/15), beton mutu 19.3 Mpa -
a. Pek. Ring Balok (15/15), beton mutu 19.3 Mpa M3 0.26 0.01 -
b. Pek. Ring Balok 13/20 M3 1.95 0.04 1.85 0.04 1.85 0.04 - 1.85 0.04 100.00
c. Pembesian KG 55.93 0.01 373.94 0.07 360.80 0.06 360.80 0.06 - 360.80 0.06 100.00
d. Bekisting M2 5.37 0.01 30.77 0.08 29.29 0.08 29.29 0.08 - 29.29 0.08 100.00
5 Plat Dak Beton mutu 19.3 Mpa -
a. Plat Dak Beton M3 3.22 0.07 3.16 0.07 3.16 0.07 - 3.16 0.07 100.00
b. Pek. Pembesian KG 500.60 0.09 495.42 0.09 495.42 0.09 - 495.42 0.09 100.00
c. Pek. Bekisting M2 31.15 0.12 30.54 0.11 30.54 0.11 - 30.54 0.11 100.00
- PEKERJAAN DINDING DAN LANTAI -
1 Pas dinding Batu Tela Camp, 1 : 4 M2 122.78 0.30 24.46 0.06 24.46 0.06 - 24.46 0.06 100.00
2 Pek. Batu Bata Merah tebal 1/2 bata, 1SP : 4PP M2 146.38 0.36 145.79 0.36 145.79 0.36 - 145.79 0.36 100.00
3 Plesteran 1:4 tebal 15 mm M2 246.25 0.21 217.91 0.19 270.87 0.24 270.87 0.24 - 270.87 0.24 100.00
4 Pas.Roster M2 11.70 0.08 13.12 0.09 13.12 0.09 13.12 0.09 - 13.12 0.09 100.00
5 Pekerjaan Acian M2 128.51 0.06 217.91 0.10 242.16 0.11 242.16 0.11 - 242.16 0.11 100.00
6 Pekerjaan Lantai Keramik 20/20 M2 45.70 0.15 -
7 Pekerjaan Lantai Keramik 40/40 kasar M2 58.98 0.19 56.15 0.18 56.15 0.18 - 56.15 0.18 100.00
8 Pekerjaan Keramik Dinding WC 20/25 M2 117.73 0.44 102.48 0.38 101.50 0.38 101.50 0.38 - 101.50 0.38 100.00
9 Cor Lantai beton mutu f’c = 7,4 MPa tebal 5 cm, M3 0.31 0.01 -
10 Cor Lantai beton mutu f’c = 7,4 MPa tebal 7 cm, M3 4.14 0.08 4.27 0.09 4.27 0.09 - 4.27 0.09 100.00
- PEKERJAAN KUSEN, KACA, KUNCI, DAN ALAT PENGGANTUNG -
1 Pek. Kusen Pintu,dan Jalusi Kayu Besi M3 0.22 0.02 0.42 0.03 0.42 0.03 0.42 0.03 - 0.42 0.03 100.00
2 Pek. Daun Pintu Panil Kayu Besi M2 18.60 0.12 14.30 0.10 14.30 0.10 14.30 0.10 - 14.30 0.10 100.00
3 Pek. Daun Jalusi Kayu Besi M2 1.72 0.01 -
4 Pek. Jalusi Kaca M2 0.31 0.00 2.28 0.01 2.28 0.01 2.28 0.01 - 2.28 0.01 100.00
5 Pas. Kunci Tanam 2 Slaag BH 3.00 0.01 9.00 0.03 9.00 0.03 9.00 0.03 - 9.00 0.03 100.00
6 Pas. Engsel Pintu Panil Kayu SET 5.00 0.00 27.00 0.02 27.00 0.02 27.00 0.02 - 27.00 0.02 100.00
7 Pas. Engsel Jalusi SET 10.00 0.00 -
8 Pas. Grendel BH 3.00 0.00 9.00 0.01 9.00 0.01 - 9.00 0.01 100.00
9 Pas. Tarikan Jalusi BH 10.00 0.00 -
10 Pas. Kait Angin BH 10.00 0.00 -
11 Tulisan Sign Acrylic BH 3.00 0.01 3.00 0.01 - 3.00 0.01 100.00
12 Handrail Toilet Disabilitas BH 1.00 0.02 1.00 0.02 - 1.00 0.02 100.00
13 Tempat tisu Toilet BH 1.00 0.00 1.00 0.00 - 1.00 0.00 100.00
14 Railing Pipa GIP M 21.08 0.14 21.08 0.14 - 21.08 0.14 100.00
- PEKERJAAN ATAP DAN PLAFOND -
1 Pas. Kuda-kuda dan Skoor Kayu Besi 5/10 M3 0.30 0.02 1.17 0.09 1.17 0.09 1.17 0.09 - 1.17 0.09 100.00
2 Pas. Gording Kayu Besi 5/10 M3 0.32 0.02 0.68 0.05 0.68 0.05 0.68 0.05 - 0.68 0.05 100.00
3 Pas. Atap seng gelombang BJLS 0.30 mm M2 68.22 0.10 -
4 Pekerjaan penutup rangka atap M2 96.30 0.14 96.30 0.14 96.30 0.14 - 96.30 0.14 100.00
5 Pas. Lisplank Kayu besi 3/30 M' 16.80 0.01 -
6 Pemasangan Lisplank M' 36.36 0.03 57.28 0.04 57.28 0.04 - 57.28 0.04 100.00
7 Pas. Nok Atap M' 8.33 0.00 20.92 0.01 20.92 0.01 20.92 0.01 - 20.92 0.01 100.00
8 Pas. Rangka Plafond M2 53.74 0.05 70.41 0.07 67.58 0.07 67.58 0.07 - 67.58 0.07 100.00
9 Pas. Plafond tripleks 4 mm M2 53.74 0.03 70.41 0.05 67.58 0.04 67.58 0.04 - 67.58 0.04 100.00
10 Pas. List Plafond Kayu profil M' 95.80 0.02 169.12 0.04 169.12 0.04 169.12 0.04 - 169.12 0.04 100.00
11 Talang Air M' 36.36 0.08 36.80 0.07 36.80 0.07 - 36.80 0.07 100.00
- PEKERJAAN CAT DAN LABURAN -
Kontrak Awal Kontrak Adendum I Kontrak Adendum III S/d Minggu Lalu Minggu ini S/d Minggu ini Thdp
NO. URAIAN PEKERJAAN SATUAN VOLUME Bobot VOLUME Bobot VOLUME Bobot Volume Bobot Volume Bobot Volume Bobot Item Pek

(%) (%) (%) (%) (%) (%) (%)


a b c d g h k l o p q r s t u v
1 Cat Kilap Kusen Pintu, Jendela, Daun Pintu M2 28.64 0.02 75.88 0.05 63.16 0.04 63.16 0.04 - 63.16 0.04 100.00
2 Cat/Laburan Tembok dan Plafond M2 182.26 0.06 303.17 0.10 383.52 0.12 383.52 0.12 - 383.52 0.12 100.00
3 Cat Menie Besi 9.15 0.00 - - - - - -
4 Cat Besi 9.15 0.00 - - - - - -
- PEKERJAAN MECANIKAL DAN ELEKTRIKAL -
1 Pas. Titik Instalasi BH 11.00 0.02 22.00 0.04 22.00 0.04 22.00 0.04 - 22.00 0.04 100.00
2 Pas. Saklar Tunggal BH 1.00 0.00 6.00 0.02 6.00 0.02 6.00 0.02 - 6.00 0.02 100.00
3 Pas. Saklar Ganda BH 2.00 0.01 3.00 0.01 3.00 0.01 3.00 0.01 - 3.00 0.01 100.00
4 Pas. MCB BH 1.00 0.00 2.00 0.01 2.00 0.01 2.00 0.01 - 2.00 0.01 100.00
5 Lampu XL 18 Watt BH 8.00 0.02 13.00 0.03 13.00 0.03 13.00 0.03 - 13.00 0.03 100.00
6 Box Panel lengkap UNIT 1.00 0.00 1.00 0.00 1.00 0.00 1.00 0.00 - 1.00 0.00 100.00
- PEKERJAAN SANITAIR -
Septictank dan Peresapan -
1 Galian Tanah M3 13.50 0.01 11.33 0.01 11.33 0.01 11.33 0.01 - 11.33 0.01 100.00
2 Pasangan 1/2 Batu tela Camp 1 : 4 M2 27.48 0.07 -
3 Pas dinding Batu Tela Camp, 1 : 4 M2 15.95 0.04 15.95 0.04 15.95 0.04 - 15.95 0.04 100.00
4 Urugan Pasir Resapan M3 0.55 0.00 0.49 0.00 0.49 0.00 0.49 0.00 - 0.49 0.00 100.00
5 Urugan Kerikil Resapan M3 0.36 0.00 0.81 0.01 0.81 0.01 0.81 0.01 - 0.81 0.01 100.00
6 Ijuk Resapan M2 0.36 0.00 0.33 0.00 0.33 0.00 0.33 0.00 - 0.33 0.00 100.00
7 Urugan Sirtu Resapan M3 0.36 0.00 -
8 Sloof Beton Bertulang M3 0.28 0.03 0.28 0.03 0.28 0.03 - 0.28 0.03 100.00
9 Kolom Beton Bertulang M3 0.23 0.02 0.23 0.02 0.23 0.02 - 0.23 0.02 100.00
10 Ring Balok Beton Bertulang M3 0.38 0.04 0.38 0.04 0.38 0.04 - 0.38 0.04 100.00
11 Plat Beton Bertulang M3 0.87 0.08 0.87 0.08 0.87 0.08 - 0.87 0.08 100.00
12 Cor Beton Plat Penutup tebal 10 cm M3 0.90 0.07 -
13 Plesteran 1 : 2, tebal 15 mm M2 48.00 0.04 20.25 0.02 20.25 0.02 20.25 0.02 - 20.25 0.02 100.00
14 Pas. Kloset Jongkok BH 4.00 0.03 4.00 0.03 4.00 0.03 4.00 0.03 - 4.00 0.03 100.00
15 Pas. Kloset Duduk BH 2.00 0.06 3.00 0.09 3.00 0.09 3.00 0.09 - 3.00 0.09 100.00
16 Pas. Urinoir BH 3.00 0.04 3.00 0.04 3.00 0.04 3.00 0.04 - 3.00 0.04 100.00
17 Pas. Pipa Air Kotor PVC 4" dari Wc ke Septictank dan Resapan M' 36.00 0.06 48.00 0.08 24.00 0.04 24.00 0.04 - 24.00 0.04 100.00
18 Pas. Pipa Air Kotor PVC 2" dari Km+Urinoir+Wastafel M' 38.00 0.03 40.00 0.03 28.00 0.02 28.00 0.02 - 28.00 0.02 100.00
19 Pas. Floor Drain BH 6.00 0.00 9.00 0.01 9.00 0.01 9.00 0.01 - 9.00 0.01 100.00
20 Pas. Kran Air 3/4 BH 5.00 0.01 12.00 0.01 4.00 0.00 4.00 0.00 - 4.00 0.00 100.00
21 Pas. Wastafel BH 4.00 0.06 5.00 0.07 5.00 0.07 5.00 0.07 - 5.00 0.07 100.00
22 Pas. Pipa Air Bersih PVC 1" M' 49.50 0.02 52.00 0.02 8.00 0.00 8.00 0.00 - 8.00 0.00 100.00
23 Pas. Pipa Air Bersih PVC 3/4" M' 4.05 0.00 40.00 0.01 40.00 0.01 40.00 0.01 - 40.00 0.01 100.00
24 Pas. Pipa Air Bersih PVC 2 1/2" M' 3.50 0.00 3.50 0.00 - 3.50 0.00 100.00
25 Tempat Sampah UNIT 5.00 0.00 4.00 0.00 5.00 0.00 5.00 0.00 - 5.00 0.00 100.00
26 Ember BH 4.00 0.00 4.00 0.00 - 4.00 0.00 100.00
27 Sumur Bor BH 1.00 0.26 1.00 0.26 1.00 0.26 - 1.00 0.26 100.00
28 Pompa Sumersible BH 1.00 0.03 1.00 0.03 1.00 0.03 - 1.00 0.03 100.00
29 Talang M' 13.98 0.03 -
-
-
X. PEKERJAAN TALUD PENGAMAN -
- PEKERJAAN PERSIAPAN -
1 Pembersihan Lokasi LS 1.00 0.01 1.00 0.01 1.00 0.01 1.00 0.01 - 1.00 0.01 100.00
2 Pengukuran dan Pemasangan Bouwplank M' 169.08 0.10 110.65 0.07 110.65 0.07 110.65 0.07 - 110.65 0.07 100.00
- PEKERJAAN GALIAN DAN URUGAN -
1 Galian Tanah Pondasi M3 88.77 0.07 1,266.01 1.07 1,266.01 1.07 1,266.0 1.07 - 1,266.0 1.07 100.00
2 Timbunan Kembali Galian Tanah Pondasi M3 22.19 0.01 -
- PEKERJAAN BETON,PASANGAN, DAN PLESTERAN -
1 Pondasi Batu Gunung sp 1:4 M3 120.99 2.36 359.85 7.02 359.85 7.02 359.85 7.02 - 359.85 7.02 100.00
2 Plesteran M2 219.81 0.19 353.43 0.31 357.08 0.31 357.08 0.31 - 357.08 0.31 100.00
- PEKERJAAN PENGECATAN -
1 Pekerjaan Dengecatan Dinding Talud M2 353.43 0.20 357.08 0.21 357.08 0.21 - 357.08 0.21 100.00
-
-
XI. PEKERJAAN PEMBANGUNAN GEDUNG PENGELOLA -
- PEKERJAAN PERSIAPAN -
1 Pembersihan Lokasi M2 144.12 0.03 142.16 0.03 142.16 0.03 - 142.16 0.03 100.00
2 Pengukuran dan Pasang Bouwplank M 40.00 0.02 59.14 0.04 58.67 0.04 58.67 0.04 - 58.67 0.04 100.00
- PEKERJAAN GALIAN DAN URUGAN -
1 Galian Tanah Pondasi M3 33.05 0.03 37.19 0.03 36.59 0.03 36.59 0.03 - 36.59 0.03 100.00
2 Timbunan Kembali Galian Tanah Pondasi M3 8.26 0.01 12.20 0.01 12.20 0.01 - 12.20 0.01 100.00
3 Urugan Tanah Peninggi Lantai Bekas Galian M3 37.19 0.02 -
4 Urugan Tanah Dibawah Lantai M3 24.00 0.09 20.38 0.08 54.79 0.21 54.79 0.21 - 54.79 0.21 100.00
5 Urugan Pasir Bawah Lantai M3 5.76 0.05 6.16 0.05 6.16 0.05 - 6.16 0.05 100.00
6 Urugan Pasir Bawah Pondasi Menerus M3 2.75 0.02 -
- PEKERJAAN BETON, PASANGAN, PLESTERAN -
1 Pondasi Batu Gunung sp 1:4 M3 20.06 0.39 23.06 0.45 52.97 1.03 52.97 1.03 - 52.97 1.03 100.00
2 Pasangan Batu Kosong M3 11.01 0.15 -
3 Pondasi Telapak Beton Bertulang M3 0.88 0.07 0.73 0.06 0.73 0.06 - 0.73 0.06 100.00
4 Kolom Telapak Beton Bertulang M3 0.11 0.01 0.09 0.01 0.09 0.01 - 0.09 0.01 100.00
5 beton mutu f’c = 7,4 MPa (K 100) M3 5.76 0.12 8.06 0.16 8.63 0.18 8.63 0.18 - 8.63 0.18 100.00
6 beton Sloof 15/20, beton mutu 19.3 Mpa M3 2.36 0.05 3.08 0.07 3.08 0.07 3.08 0.07 - 3.08 0.07 100.00
Bekisting M2 31.48 0.06 41.06 0.07 41.06 0.07 41.06 0.07 - 41.06 0.07 100.00
Pembesian KG 283.32 0.05 523.93 0.09 523.93 0.09 523.93 0.09 - 523.93 0.09 100.00
7 Kolom 1 (50/20), beton mutu 19.3 Mpa M3 0.70 0.02 -
Bekisting M2 6.30 0.02 -
Pembesian KG 84.00 0.01 -
8 Kolom 2 (20/20), beton mutu 19.3 Mpa M3 1.96 0.04 -
Bekisting M2 39.20 0.11 -
Pembesian KG 235.20 0.04 -
9 Kolom 3 (20/15), beton mutu 19.3 Mpa M3 0.63 0.01 -
Bekisting M2 8.70 0.02 -
Pembesian KG 75.60 0.01 -
10 Kolom 4 (15/15), beton mutu 19.3 Mpa M3 0.31 0.01 -
Bekisting M2 8.10 0.02 -
Pembesian KG 37.80 0.01 -
11 Kolom 20/30 M3 1.38 0.03 1.38 0.03 1.38 0.03 - 1.38 0.03 100.00
Bekisting M2 23.00 0.06 23.00 0.06 23.00 0.06 - 23.00 0.06 100.00
Pembesian KG 206.49 0.04 206.49 0.04 206.49 0.04 - 206.49 0.04 100.00
12 Kolom 20/20 M3 2.21 0.05 2.21 0.05 2.21 0.05 - 2.21 0.05 100.00
Bekisting M2 44.16 0.12 44.16 0.12 44.16 0.12 - 44.16 0.12 100.00
Pembesian KG 483.73 0.09 483.73 0.09 483.73 0.09 - 483.73 0.09 100.00
13 Kolom 13/20 M3 0.20 0.00 0.20 0.00 0.20 0.00 - 0.20 0.00 100.00
Bekisting M2 5.18 0.01 5.18 0.01 5.18 0.01 - 5.18 0.01 100.00
Pembesian KG 38.94 0.01 38.94 0.01 38.94 0.01 - 38.94 0.01 100.00
14 Kolom 13/13 M3 1.20 0.03 1.20 0.03 1.20 0.03 - 1.20 0.03 100.00
Bekisting M2 37.02 0.10 37.02 0.10 37.02 0.10 - 37.02 0.10 100.00
Pembesian KG 331.94 0.06 331.94 0.06 331.94 0.06 - 331.94 0.06 100.00
15 Ring Balok 1 (15/20), beton mutu 19.3 Mpa M3 2.07 0.05 -
Bekisting M2 37.95 0.10 -
Pembesian KG 248.40 0.04 -
16 Ring Balok 2 ( 20/15 ), beton mutu 19.3 Mpa M3 0.29 0.01 -
Bekisting M2 5.33 0.01 -
Pembesian KG 34.92 0.01 -
17 Ring Balok 2 ( 20/15 ), beton mutu 19.3 Mpa M3 1.66 0.04 -
Kontrak Awal Kontrak Adendum I Kontrak Adendum III S/d Minggu Lalu Minggu ini S/d Minggu ini Thdp
NO. URAIAN PEKERJAAN SATUAN VOLUME Bobot VOLUME Bobot VOLUME Bobot Volume Bobot Volume Bobot Volume Bobot Item Pek

(%) (%) (%) (%) (%) (%) (%)


a b c d g h k l o p q r s t u v
Bekisting M2 22.22 0.06 -
Pembesian KG 199.46 0.04 -
18 Ring Balok 13/20 M3 4.18 0.10 4.14 0.09 4.14 0.09 - 4.14 0.09 100.00
Bekisting M2 64.35 0.18 63.64 0.17 63.64 0.17 - 63.64 0.17 100.00
Pembesian KG 804.11 0.14 794.96 0.14 794.96 0.14 - 794.96 0.14 100.00
19 Plat Dak Beton M3 4.49 0.10 4.09 0.09 4.09 0.09 - 4.09 0.09 100.00
Bekisting M2 37.43 0.14 34.10 0.13 34.10 0.13 - 34.10 0.13 100.00
Pembesian KG 697.63 0.12 635.26 0.11 635.26 0.11 - 635.26 0.11 100.00
20 Pasangan Roster M2 15.84 0.11 28.48 0.20 28.48 0.20 28.48 0.20 - 28.48 0.20 100.00
21 Pasangan Batu Tela Dinding sp. 1 : 4 M2 232.94 0.58 -
22 Pek. Batu Bata Merah tebal 1/2 bata, 1SP : 4PP M2 193.40 0.48 197.44 0.49 197.44 0.49 - 197.44 0.49 100.00
23 Plesteran Dinding sp. 1 : 4 M2 465.89 0.41 332.94 0.29 375.74 0.33 375.74 0.33 - 375.74 0.33 100.00
24 Acian M2 465.89 0.20 332.94 0.15 375.74 0.16 375.74 0.16 - 375.74 0.16 100.00
- PEKERJAAN KUDA-KUDA DAN ATAP -
1 Kuda-kuda ky. Klas I M3 0.87 0.07 2.00 0.15 2.00 0.15 2.00 0.15 - 2.00 0.15 100.00
2 Pekerjaan rangka atap kanopi hollow 4/4 262.65 0.11 - - 78.80 0.03 78.80 0.03 30.00
3 Pekerjaan rangka atap kanopi hollow 2/4 44.57 0.02 - - 13.37 0.01 13.37 0.01 30.00
4 Gording ky. Klas I M3 0.86 0.06 1.21 0.09 1.21 0.09 1.21 0.09 - 1.21 0.09 100.00
5 Pas.Atap Alumunium Spandek M2 121.72 0.17 185.91 0.26 185.91 0.26 185.91 0.26 - 185.91 0.26 100.00
6 Pekerjaan penutup atap kanopi 25.32 0.06 - - - - - -
7 Pas. Papan Nok M2 11.63 0.01 -
8 Pas. Nok Atap M' 29.08 0.01 29.07 0.01 29.07 0.01 29.07 0.01 - 29.07 0.01 100.00
9 Talang Air M' 30.48 0.07 50.34 0.12 36.10 0.07 36.10 0.07 - 36.10 0.07 100.00
10 Pas. Lisplank Kayu besi 3/30 M' 38.00 0.03 -
11 Pemasangan lisplank M' 50.34 0.04 79.41 0.06 79.41 0.06 - 79.41 0.06 100.00
- PEKERJAAN KUSEN PINTU DAN JENDELA -
1 Kusen Ky. Klas I M3 0.46 0.03 0.52 0.04 0.52 0.04 0.52 0.04 - 0.52 0.04 100.00
2 Bingkai Jendela Ky. Klas I M2 22.19 0.15 2.08 0.01 2.08 0.01 2.08 0.01 - 2.08 0.01 100.00
3 Daun Pintu Panil Papan Kayu Besi M2 4.62 0.03 12.44 0.08 12.44 0.08 12.44 0.08 - 12.44 0.08 100.00
4 Kaca polos 20 mm M2 3.64 0.08 -
5 Kaca polos 5 mm M2 27.35 0.09 7.12 0.02 7.12 0.02 7.12 0.02 - 7.12 0.02 100.00
- PEKERJAAN ALAT GANTUNGAN DAN ACCESORIS -
1 Grendel Jendela BH 22.00 0.01 8.00 0.00 8.00 0.00 8.00 0.00 - 8.00 0.00 100.00
2 Engsel Jendela BH 36.00 0.01 16.00 0.01 16.00 0.01 16.00 0.01 - 16.00 0.01 100.00
3 Engsel Pintu BH 15.00 0.01 21.00 0.01 21.00 0.01 21.00 0.01 - 21.00 0.01 100.00
4 Hak Angin BH 36.00 0.02 16.00 0.01 16.00 0.01 16.00 0.01 - 16.00 0.01 100.00
5 Tarikan Jendela BH 18.00 0.01 8.00 0.01 8.00 0.01 8.00 0.01 - 8.00 0.01 100.00
6 Kunci Pintu BH 2.00 0.00 7.00 0.02 7.00 0.02 7.00 0.02 - 7.00 0.02 100.00
7 Kunci Pintu Km/Wc BH 2.00 0.00 -
8 Pas.Grendel BH 7.00 0.00 7.00 0.00 - 7.00 0.00 100.00
9 Pembuatan Papan Nama dari Stainless LS 1.00 0.02 -
10 Tulisan Sign Acrylic LS 3.00 0.01 3.00 0.01 - 3.00 0.01 100.00
- PEKERJAAN PLAFOND -
1 Pasang Rangka Plafond M2 126.00 0.12 146.43 0.14 145.29 0.14 145.29 0.14 - 145.29 0.14 100.00
2 Plafond Tripleks 4 mm M2 126.00 0.08 146.43 0.09 145.29 0.09 145.29 0.09 - 145.29 0.09 100.00
3 List propil SP 4 M' 157.40 0.04 248.21 0.06 248.21 0.06 248.21 0.06 - 248.21 0.06 100.00
- PEKERJAAN PENUTUP LANTAI DAN DINDING -
1 Lantai Keramik 40/40 M2 74.00 0.24 146.45 0.47 145.92 0.47 145.92 0.47 - 145.92 0.47 100.00
2 Lantai keramik km/wc 20/20 M2 6.00 0.02 -
3 Dinding Keramik Km/Wc 20/25 M2 8.75 0.03 52.68 0.20 52.68 0.20 52.68 0.20 - 52.68 0.20 100.00
4 Pekerjaan Roster M2 15.84 0.11 -
- PEKERJAAN PENGECATAN -
1 Cat Tembok M2 465.89 0.15 332.94 0.10 497.05 0.16 497.05 0.16 - 497.05 0.16 100.00
2 Cat Kusen Kayu M2 18.47 0.01 24.07 0.02 24.07 0.02 24.07 0.02 - 24.07 0.02 100.00
3 Cat Listplank M2 12.00 0.01 30.20 0.02 19.85 0.01 19.85 0.01 - 19.85 0.01 100.00
4 Cat Plafond M2 126.00 0.04 146.43 0.05 145.29 0.05 145.29 0.05 - 145.29 0.05 100.00
5 Cat Pintu Panel dan Bingkai Jendela M2 26.82 0.02 31.89 0.02 31.89 0.02 31.89 0.02 - 31.89 0.02 100.00
6 Cat Menie Besi M2 27.66 0.01 - - - - - -
7 Cat Besi M2 27.66 0.01 - - - - - -
- PEKERJAAN INSTALASI LISTRIK -
1 Box Sekring SET 1.00 0.01 2.00 0.01 2.00 0.01 2.00 0.01 - 2.00 0.01 100.00
2 Pas. MCB 6A BH 2.00 0.01 2.00 0.01 2.00 0.01 - 2.00 0.01 100.00
3 Lampu PHILIPS 20 Watt TITIK 10.00 0.01 -
4 Lampu PHILIPS 10 Watt TITIK 7.00 0.02 -
5 Lampu SL 18 Watt BH 7.00 0.02 7.00 0.02 7.00 0.02 - 7.00 0.02 100.00
6 Lampu SL 23 Watt BH 7.00 0.02 7.00 0.02 7.00 0.02 - 7.00 0.02 100.00
7 Stop Kontak TITIK 9.00 0.02 8.00 0.02 8.00 0.02 8.00 0.02 - 8.00 0.02 100.00
8 Saklar Tunggal TITIK 3.00 0.01 5.00 0.01 5.00 0.01 5.00 0.01 - 5.00 0.01 100.00
9 Saklar Ganda TITIK 4.00 0.01 4.00 0.01 4.00 0.01 4.00 0.01 - 4.00 0.01 100.00
10 Instalasi Penerangan TITIK 33.00 0.06 31.00 0.06 31.00 0.06 31.00 0.06 - 31.00 0.06 100.00
- PEKERJAAN SANITAIR -
1 Kran Air BH 2.00 0.00 -
2 Closed Duduk BH 1.00 0.03 -
3 Closed Jongkok BH 1.00 0.01 -
4 Pipa Air Bersih PVC. Ø 1/2" M' 40.00 0.01 -
5 Pipa Air Kotor PVC. Ø 2" M' 16.00 0.01 -
6 Pipa Air Kotor PVC. Ø 4" M' 2.00 0.00 -
7 Floor Drain BH 1.00 0.00 -
8 Septictank Lengkap UNIT 1.00 0.08 -
- PEKERJAAN SANITAIR DAN SEPTICTANK -
1 Galian Tanah M3 11.33 0.01 11.33 0.01 11.33 0.01 - 11.33 0.01 100.00
2 Pas dinding Batu Tela Camp, 1 : 4 M2 15.95 0.04 15.95 0.04 15.95 0.04 - 15.95 0.04 100.00
3 Urugan Pasir Resapan M3 0.49 0.00 0.49 0.00 0.49 0.00 - 0.49 0.00 100.00
4 Urugan Kerikil Resapan M3 0.81 0.01 0.81 0.01 0.81 0.01 - 0.81 0.01 100.00
5 Ijuk Resapan M2 0.33 0.00 0.33 0.00 0.33 0.00 - 0.33 0.00 100.00
6 Sloof Beton Bertulang M3 0.28 0.03 0.28 0.03 0.28 0.03 - 0.28 0.03 100.00
7 Kolom Beton Bertulang M3 0.23 0.02 0.23 0.02 0.23 0.02 - 0.23 0.02 100.00
8 Ring Balok Beton Bertulang M3 0.38 0.04 0.38 0.04 0.38 0.04 - 0.38 0.04 100.00
9 Plat Beton Bertulang M3 0.87 0.08 0.87 0.08 0.87 0.08 - 0.87 0.08 100.00
10 Plesteran 1 : 2, tebal 15 mm M2 20.25 0.02 20.25 0.02 20.25 0.02 - 20.25 0.02 100.00
11 Pas. Kloset Jongkok BH 3.00 0.02 3.00 0.02 3.00 0.02 - 3.00 0.02 100.00
12 Pas. Pipa Air Kotor PVC 4" dari Wc ke Septictank dan Resapan M' 48.00 0.08 16.00 0.03 16.00 0.03 - 16.00 0.03 100.00
13 Pas. Pipa Air Kotor PVC 2" dari Km+Urinoir+Wastafel M' 40.00 0.03 16.00 0.01 16.00 0.01 - 16.00 0.01 100.00
14 Pas. Floor Drain BH 5.00 0.00 7.00 0.00 7.00 0.00 - 7.00 0.00 100.00
15 Pas. Kran Air 3/4 BH 11.00 0.01 11.00 0.01 11.00 0.01 - 11.00 0.01 100.00
16 Pas. Wastafel BH 3.00 0.04 3.00 0.04 3.00 0.04 - 3.00 0.04 100.00
17 Pas. Pipa Air Bersih PVC 1" M' 52.00 0.02 8.00 0.00 8.00 0.00 - 8.00 0.00 100.00
18 Pas. Pipa Air Bersih PVC 3/4" M' 40.00 0.01 32.00 0.01 32.00 0.01 - 32.00 0.01 100.00
19 Pas. Pipa Air Bersih PVC 2 1/2" M' 3.50 0.00 3.50 0.00 - 3.50 0.00 100.00
20 Ember BH 3.00 0.00 3.00 0.00 - 3.00 0.00 100.00
21 Tempat Sampah BH 3.00 0.00 3.00 0.00 - 3.00 0.00 100.00
- PEKERJAAN PEMASANGAN LISTRIK DAN JARINGAN -
1 Pemasangan Listrik 3.500 watt + Kabel dan Tiang UNIT 1.00 0.45 1.00 0.45 1.00 0.45 - 1.00 0.45 100.00
Pekerjaan Jaringan Listrik Bawah Tanah -
2 Gedung Pengelola Ke Pujasera 0.00 0.00 -
a. Pipa Listrik 20 mm M 30.00 0.00 30.00 0.00 30.00 0.00 - 30.00 0.00 100.00
b. Kabel NYY 2 x 2,5 mm M 30.00 0.01 30.00 0.01 30.00 0.01 - 30.00 0.01 100.00
c. Pas. MCB 16 A BH 1.00 0.00 1.00 0.00 1.00 0.00 - 1.00 0.00 100.00
3 Gedung Pengelola Ke Pos Jaga -
Kontrak Awal Kontrak Adendum I Kontrak Adendum III S/d Minggu Lalu Minggu ini S/d Minggu ini Thdp
NO. URAIAN PEKERJAAN SATUAN VOLUME Bobot VOLUME Bobot VOLUME Bobot Volume Bobot Volume Bobot Volume Bobot Item Pek

(%) (%) (%) (%) (%) (%) (%)


a b c d g h k l o p q r s t u v
a. Pipa Listrik 20 mm M 175.00 0.01 175.00 0.01 175.00 0.01 - 175.00 0.01 100.00
b. Kabel NYY 2 x 2,5 mm M 175.00 0.03 175.00 0.03 175.00 0.03 - 175.00 0.03 100.00
c. Pas. MCB 6 A BH 1.00 0.00 1.00 0.00 1.00 0.00 - 1.00 0.00 100.00
4 Gedung Pengelola Ke Gazebo A -
a. Pipa Listrik 20 mm M 100.00 0.00 100.00 0.00 100.00 0.00 - 100.00 0.00 100.00
b. Kabel NYY 2 x 2,5 mm M 100.00 0.02 100.00 0.02 100.00 0.02 - 100.00 0.02 100.00
c. Pas. MCB 6 A BH 1.00 0.00 1.00 0.00 1.00 0.00 - 1.00 0.00 100.00
5 Gedung Pengelola Ke Gazebo B dan C -
a. Pipa Listrik 20 mm M 125.00 0.01 125.00 0.01 125.00 0.01 - 125.00 0.01 100.00
b. Kabel NYY 2 x 2,5 mm M 125.00 0.02 125.00 0.02 125.00 0.02 - 125.00 0.02 100.00
c. Pas. MCB 6 A BH 1.00 0.00 1.00 0.00 1.00 0.00 - 1.00 0.00 100.00
6 Gedung Pengelola Ke Lampu Taman -
a. Pipa Listrik 20 mm M 135.00 0.01 135.00 0.01 135.00 0.01 - 135.00 0.01 100.00
b. Kabel NYY 2 x 2,5 mm M 135.00 0.03 135.00 0.03 135.00 0.03 - 135.00 0.03 100.00
c. Pas. MCB 6 A BH 2.00 0.01 2.00 0.01 2.00 0.01 - 2.00 0.01 100.00
7 Gedung Pengelola Ke Lampu Jalan -
a. Pipa Listrik 20 mm M 90.00 0.00 90.00 0.00 90.00 0.00 - 90.00 0.00 100.00
b. Kabel NYY 2 x 2,5 mm M 90.00 0.02 90.00 0.02 90.00 0.02 - 90.00 0.02 100.00
c. Pas. MCB 6 A BH 1.00 0.00 1.00 0.00 1.00 0.00 - 1.00 0.00 100.00
8 Gedung Pengelola Ke Toilet -
a. Pipa Listrik 20 mm M 140.00 0.01 140.00 0.01 140.00 0.01 - 140.00 0.01 100.00
b. Kabel NYY 2 x 2,5 mm M 140.00 0.03 140.00 0.03 140.00 0.03 - 140.00 0.03 100.00
c. Pas. MCB 16 A BH 1.00 0.00 1.00 0.00 1.00 0.00 - 1.00 0.00 100.00
9 Toilet Ke Panggung Budaya -
a. Pipa Listrik 20 mm M 60.00 0.00 60.00 0.00 60.00 0.00 - 60.00 0.00 100.00
b. Kabel NYY 2 x 2,5 mm M 65.00 0.01 60.00 0.01 60.00 0.01 - 60.00 0.01 100.00
c. Pas. MCB 6 A BH 1.00 0.00 1.00 0.00 1.00 0.00 - 1.00 0.00 100.00
10 Toilet Ke Lampu Jalan -
a. Pipa Listrik 20 mm M 120.00 0.00 120.00 0.00 120.00 0.00 - 120.00 0.00 100.00
b. Kabel NYY 2 x 2,5 mm M 120.00 0.02 120.00 0.02 120.00 0.02 - 120.00 0.02 100.00
c. Pas. MCB 6 A BH 2.00 0.01 2.00 0.01 2.00 0.01 - 2.00 0.01 100.00
11 Toilet Ke Lampu Taman -
a. Pipa Listrik 20 mm M 190.00 0.01 190.00 0.01 190.00 0.01 - 190.00 0.01 100.00
b. Kabel NYY 2 x 2,5 mm M 190.00 0.04 190.00 0.04 190.00 0.04 - 190.00 0.04 100.00
c. Pas. MCB 6 A BH 2.00 0.01 2.00 0.01 2.00 0.01 - 2.00 0.01 100.00
12 Toilet Ke Lampu Spotlight -
a. Pipa Listrik 20 mm M 297.00 0.01 297.00 0.01 297.00 0.01 - 297.00 0.01 100.00
b. Kabel NYY 2 x 2,5 mm M 297.00 0.06 297.00 0.06 297.00 0.06 - 297.00 0.06 100.00
c. Pas. MCB 6 A BH 4.00 0.02 4.00 0.02 4.00 0.02 - 4.00 0.02 100.00
13 Pos Jaga ke Lampu Jalan -
a. Pipa Listrik 20 mm M 56.00 0.00 56.00 0.00 56.00 0.00 - 56.00 0.00 100.00
b. Kabel NYY 2 x 2,5 mm M 56.00 0.01 56.00 0.01 56.00 0.01 - 56.00 0.01 100.00
c. Pas. MCB 6 A BH 1.00 0.00 1.00 0.00 1.00 0.00 - 1.00 0.00 100.00
- PEKERJAAN PERPIPAAN -
1 Pek.Galian Tanah Jaringan Pipa M3 67.28 0.25 61.65 0.05 61.65 0.05 - 61.65 0.05 100.00
2 Urugan Pasir Bawah Pipa m3 32.85 0.27 32.69 0.27 32.69 0.27 - 32.69 0.27 100.00
3 Timbunan Tanah kembali M3 22.43 0.01 20.55 0.01 20.55 0.01 - 20.55 0.01 100.00
4 Double Nipple Lengkap dia. 1" BH 4.00 0.00 - - -
5 Pas. Pipa PVC 1" ( Outlet ) M 24.00 0.01 - - -
6 Pas. Elbow PVC 1 " BH 8.00 0.00 - - -
7 Stop Kran PVC 1" BH 4.00 0.01 - - -
8 Pipa HDPE 1" M 4.00 0.00 -
9 Reducer HDPE 1" - 2" BH 4.00 0.00 - - -
10 Pipa HDPE 2" M 427.00 0.23 427.00 0.23 427.00 0.23 - 427.00 0.23 100.00
11 Clamp Sadle 2"-3/4" BH 23.00 0.02 23.00 0.02 23.00 0.02 - 23.00 0.02 100.00
12 Pas. Pipa GIP 3/4" M 230.00 0.21 230.00 0.21 230.00 0.21 - 230.00 0.21 100.00
13 Pas. Elbow GIP 3/4" BH 46.00 0.02 46.00 0.02 46.00 0.02 - 46.00 0.02 100.00
14 Dop HDPE 2" BH 4.00 0.00 4.00 0.00 4.00 0.00 - 4.00 0.00 100.00
15 Pasang Kran air, 3/4" BH 23.00 0.01 23.00 0.01 23.00 0.01 - 23.00 0.01 100.00
--
XII. PEKERJAAN PENANAMAN TANAMAN -
- PEKERJAAAN PERSIAPAN -
1 Pembersihan Lokasi LS 1.00 0.06 1.00 0.06 1.00 0.06 1.00 0.06 - 1.00 0.06 100.00
- PENANAMAN DAN PEMELIHARAAN TANAMAN -
1 Timbunan Tanah Humus tebal 20 cm M3 354.10 0.76 327.89 0.71 89.14 0.19 85.55 0.18 3.60 0.01 89.14 0.19 100.00
2 Palm Raja PHN 60.00 0.79 40.00 0.53 43.00 0.57 43.00 0.57 - 43.00 0.57 100.00
3 Palm Phoenix PHN 15.00 0.20 4.00 0.05 4.00 0.05 4.00 0.05 - 4.00 0.05 100.00
4 Palm Botol PHN 40.00 0.59 2.00 0.03 2.00 0.03 2.00 0.03 - 2.00 0.03 100.00
5 Palm Ekor Tupai PHN 100.00 1.45 83.00 1.21 70.00 1.02 70.00 1.02 - 70.00 1.02 100.00
6 Palm Costarica PHN 20.00 0.26 -
7 Palm Putri PHN 20.00 0.29 20.00 0.29 14.00 0.20 14.00 0.20 - 14.00 0.20 100.00
8 Pohon Tanjung PHN 50.00 0.42 2.00 0.02 - - -
9 Pohon Ketapang Kencana PHN 3.00 0.03 3.00 0.03 3.00 0.03 - 3.00 0.03 100.00
10 Pohon Tebebuya Kuning PHN 5.00 0.04 5.00 0.04 5.00 0.04 - 5.00 0.04 100.00
11 Pohon Tebebuya Ungu PHN 2.00 0.02 2.00 0.02 2.00 0.02 - 2.00 0.02 100.00
12 Diefenbachia PHN 40.00 0.13 40.00 0.13 39.00 0.12 39.00 0.12 - 39.00 0.12 100.00
13 Cemara Lilin PHN 20.00 0.21 -
14 Cemara Bangkok PHN 15.00 0.15 -
15 Cemara Kipas PHN 15.00 0.16 17.00 0.18 17.00 0.18 17.00 0.18 - 17.00 0.18 100.00
16 Nusa Indah PHN 10.00 0.06 6.00 0.04 6.00 0.04 6.00 0.04 - 6.00 0.04 100.00
17 Draisena PHN 30.00 0.11 30.00 0.11 29.00 0.11 29.00 0.11 - 29.00 0.11 100.00
18 Soka Daun Kecil PHN 450.00 0.62 395.00 0.54 260.00 0.36 260.00 0.36 - 260.00 0.36 100.00
19 Puring PHN 15.00 0.08 15.00 0.08 17.00 0.09 17.00 0.09 - 17.00 0.09 100.00
20 Pangkas Kuning PHN 500.00 0.30 493.00 0.30 155.00 0.09 - - - - - -
21 Pangkas Merah PHN 270.00 0.16 272.00 0.16 190.00 0.12 190.00 0.12 - 190.00 0.12 100.00
22 Kacangan PHN 500.00 0.30 391.00 0.24 360.00 0.22 360.00 0.22 - 360.00 0.22 100.00
23 Rumput Gajah M2 876.90 0.76 619.66 0.54 322.70 0.28 322.70 0.28 - 322.70 0.28 100.00
- POT TANAMAN -
1 Pek. Galian Pot Tanaman M3 53.84 0.05 17.81 0.02 17.81 0.02 - 17.81 0.02 100.00
2 Pek. Galian Tanaman M3 32.01 0.03 25.31 0.02 25.31 0.02 - 25.31 0.02 100.00
3 Urugan Tanah Peninggi Pot Bekas Galian M3 85.84 0.05 10.78 0.01 10.78 0.01 - 10.78 0.01 100.00
4 Urugan Tanah M3 78.81 0.30 385.53 1.45 385.53 1.45 - 385.53 1.45 100.00
5 Pas. Dinding Pot Batu Tela M2 480.60 1.19 522.17 1.29 522.17 1.29 - 522.17 1.29 100.00
6 Kolom 15/15 Pot M3 5.44 0.12 4.80 0.11 4.80 0.11 - 4.80 0.11 100.00
Bekisting M2 18.14 0.05 15.35 0.03 15.35 0.03 - 15.35 0.03 100.00
Pembesian KG 882.49 0.16 778.48 0.14 778.48 0.14 - 778.48 0.14 100.00
7 Pas. Dinding Pot Beton Bertulang M3 63.80 1.46 44.37 1.01 44.37 1.01 - 44.37 1.01 100.00
Bekisting M2 121.52 0.33 128.13 0.23 128.13 0.23 - 128.13 0.23 100.00
Pembesian KG 2,237.61 0.40 1,826.09 0.33 1,826.1 0.33 - 1,826.1 0.33 100.00
8 Pek. Plesteran M2 614.78 0.53 417.92 0.36 417.92 0.36 - 417.92 0.36 100.00
9 Acian M2 18.67 0.01 18.67 0.01 - 18.67 0.01 100.00
10 Pek Pengecatan Dinding Pot M2 614.78 0.35 562.67 0.32 562.67 0.32 - 562.67 0.32 100.00
-
-
XIII. PEKERJAAN PEMBANGUNAN GAPURA -
- PEKERJAAN PERSIAPAN -
1 Penyiapan Lokasi dan Bongkaran LS 1.00 0.03 1.00 0.03 1.00 0.03 1.00 0.03 - 1.00 0.03 100.00
2 Pengukuran dan Pasang Bouwplank M' 32.00 0.02 8.00 0.00 8.00 0.00 8.00 0.00 - 8.00 0.00 100.00
- PEKERJAAN GALIAN DAN URUGAN -
1 Galian Tanah Pondasi M3 41.40 0.03 5.78 0.00 5.78 0.00 5.78 0.00 - 5.78 0.00 100.00
Kontrak Awal Kontrak Adendum I Kontrak Adendum III S/d Minggu Lalu Minggu ini S/d Minggu ini Thdp
NO. URAIAN PEKERJAAN SATUAN VOLUME Bobot VOLUME Bobot VOLUME Bobot Volume Bobot Volume Bobot Volume Bobot Item Pek

(%) (%) (%) (%) (%) (%) (%)


a b c d g h k l o p q r s t u v
2 Timbunan Kembali Galian Tanah Pondasi M3 10.35 0.01 1.93 0.00 1.93 0.00 1.93 0.00 - 1.93 0.00 100.00
3 Urugan Tanah Dibawah Lantai M3 2.25 0.01 0.87 0.00 0.83 0.00 0.83 0.00 - 0.83 0.00 100.00
4 Urugan Pasir di Bawah Lantai M3 2.70 0.02 0.36 0.00 0.12 0.00 0.12 0.00 - 0.12 0.00 100.00
- PEKERJAAN BETON, PASANGAN, DAN PLESTERAN -
1 Pondasi Telapak 300/300 beton bertulang M3 7.20 0.55 -
2 Pondasi Telapak Beton Bertulang M3 0.64 0.05 0.64 0.05 0.64 0.05 - 0.64 0.05 100.00
3 Kolom Telapak 30/30 Beton bertulang M3 1.15 0.08 -
4 Kolom Telapak Beton bertulang M3 0.29 0.02 0.29 0.02 0.29 0.02 - 0.29 0.02 100.00
5 Pondasi Batu Gunung sp 1:4 M3 0.99 0.02 5.04 0.10 5.04 0.10 5.04 0.10 - 5.04 0.10 100.00
6 Beton mutu f’c = 7,4 MPa (K 100) M3 0.51 0.01 0.17 0.00 0.17 0.00 - 0.17 0.00 100.00
7 Beton Tumbuk sp 1:3:5 M3 3.02 0.06 -
8 Beton Sloof 25/40, beton mutu 19.3 Mpa M3 1.60 0.04 -
Bekisting M2 0.80 0.00 -
Pembesian KG 192.00 0.03 -
11 Kolom 35/35 (beton bertulang) M3 0.86 0.09 0.86 0.09 0.86 0.09 - 0.86 0.09 100.00
12 Beton Kolom 30/30, beton mutu 19.3 Mpa M3 2.52 0.06 -
Bekisting M2 6.04 0.02 -
Pembesian KG 302.40 0.05 -
13 Beton Kolom Praktis 10/10, beton mutu 19.3 Mpa M3 0.92 0.02 -
Bekisting M2 18.40 0.05 -
Pembesian KG 184.00 0.03 -
14 Beton Balok 25/40, beton mutu 19.3 Mpa M3 1.60 0.04 -
Bekisting M2 0.08 0.00 -
Pembesian KG 240.00 0.04 -
15 Beton Balok 10/15, beton mutu 19.3 Mpa M3 0.16 0.00 -
Bekisting M2 0.80 0.00 -
Pembesian KG 20.16 0.00 -
16 Beton Plat Lantai, beton mutu 19.3 Mpa M3 2.86 0.07 -
Bekisting M2 9.00 0.03 -
Pembesian KG 286.60 0.05 -
17 Beton Gapura, beton mutu 19.3 Mpa M3 7.21 0.16 7.21 0.16 7.21 0.16 - 7.21 0.16 100.00
Bekisting M2 31.11 0.08 31.36 0.08 31.36 0.08 - 31.36 0.08 100.00
Pembesian KG 403.69 0.07 276.93 0.05 276.93 0.05 - 276.93 0.05 100.00
18 Pasangan Batu Tela Dinding sp. 1 : 4 M2 71.52 0.18 -
19 Plesteran Dinding sp. 1 : 4 M2 143.04 0.12 9.52 0.01 9.52 0.01 - 9.52 0.01 100.00
20 Acian M2 143.04 0.06 9.52 0.00 9.52 0.00 - 9.52 0.00 100.00
21 Relief Tifa UNIT 2.00 0.36 2.00 0.36 2.00 0.36 2.00 0.36 - 2.00 0.36 100.00
- PEKERJAAN ATAP -
1 Pasang Ornamen Burung Cendrawasih UNIT 2.00 0.14 -
2 Rangka besi pipa di atas gapura BH 1.00 0.30 1.00 0.30 1.00 0.30 - 1.00 0.30 100.00
3 Pembuatan Papan Nama Selamat Datang dari Stainless LS 1.00 0.02 1.00 0.02 - 1.00 0.02 100.00
4 Pembuatan Papan Nama Indonesia Maju Stainless LS 1.00 0.02 1.00 0.02 - 1.00 0.02 100.00
5 Pembuatan Papan Nama PU Stainless LS 1.00 0.02 1.00 0.02 - 1.00 0.02 100.00
- PEKERJAAN PENUTUP LANTAI DAN DINDING LS -
1 Dinding Batu Alam M2 32.32 0.13 -
- PEKERJAAN PENGECATAN -
1 Cat Tembok M2 143.04 0.05 31.11 0.01 44.41 0.01 44.41 0.01 - 44.41 0.01 100.00
2 Cat Menie Besi M2 49.33 0.02 49.33 0.02 - 49.33 0.02 100.00
3 Cat Besi M2 49.33 0.02 49.33 0.02 - 49.33 0.02 100.00
-
-
XIV. PEKERJAAN PEMBANGUNAN PAPAN INFORMASI -
- PEKERJAAN PERSIAPAN -
1 Penyiapan Lokasi dan Bongkaran LS 1.00 0.01 -
2 Pengukuran dan Pemasangan Bouwplank M' 4.10 0.00 -
- PEKERJAAN TANAH -
1 Galian Tanah Pondasi M3 0.10 0.00 -
- PEKERJAAN BETON, PASANGAN DAN PLESTERAN -
1 Cor beton mutu 19.3 Mpa M3 0.32 0.01 -
2 Pasangan Batu Tela 1 : 4 M2 3.04 0.01 -
3 Plesteran Dinding sp. 1 : 4 M2 3.07 0.00 -
4 Pasangan Dinding Batu Andesit M2 3.07 0.01 -
5 Pembuatan Papan Nama Peta LS 1.00 0.19 -
-
-
XV. PEKERJAAN PEMBANGUNAN DRAINASE -
- PEKERJAAN PERSIAPAN -
1 Pembersihan Lokasi LS 1.00 0.00 -
2 Pengukuran dan Pemasangan Bouwplank M' 169.08 0.10 -
- PEKERJAAN GALIAN DAN URUGAN -
1 Galian Tanah Saluran M3 169.08 0.14 -
2 Timbunan Kembali Galian Tanah Pondasi M3 24.00 0.01 -
- PEKERJAAN BETON, PASANGAN DAN PLESTERAN -
1 Cor Drainase beton mutu f’c = 19,3 Mpa M3 76.95 1.76 -
2 Acian M2 351.19 0.15 -
3 Besi tulangan KG 537.51 0.10 -
4 Bekisting Dinding M2 333.63 0.86 -
-
-
XVI. PEKERJAAN VIEW SPOT -
- PEKERJAAN PERSIAPAN -
1 Penyiapan Lokasi LS 1.00 0.01 1.00 0.01 1.00 0.01 1.00 0.01 - 1.00 0.01 100.00
2 Pengukuran dan Pemasangan Bouwplank M' 18.00 0.01 106.49 0.06 106.49 0.06 106.49 0.06 - 106.49 0.06 100.00
- PEKERJAAN GALIAN DAN URUGAN -
1 Galian Tanah Pondasi M3 0.89 0.00 10.42 0.01 10.42 0.01 10.42 0.01 - 10.42 0.01 100.00
2 Timbunan Kembali Galian Tanah Pondasi M3 2.92 0.00 3.47 0.00 3.47 0.00 - 3.47 0.00 100.00
3 Urugan Pasir di Bawah Lantai M3 0.24 0.00 -
- PEKERJAAN BETON, PASANGAN, DAN PLESTERAN -
1 Pondasi Telapak 90/90 (BETON BERTULANG) M3 1.21 0.09 -
2 Pondasi Telapak Beton Bertulang M3 0.88 0.07 0.88 0.07 0.88 0.07 - 0.88 0.07 100.00
3 Kolom Telapak Beton Bertulang M3 0.21 0.01 0.21 0.01 0.21 0.01 - 0.21 0.01 100.00
4 Beton Tumbuk M3 0.36 0.01 -
5 Pondasi Batu Gunung sp 1:4 M3 7.35 0.14 6.13 0.12 6.13 0.12 - 6.13 0.12 100.00
6 Sloof 20/25 (Beton bertulang) M3 1.05 0.11 -
7 Kolom 20/20 (beton bertulang) M3 3.91 0.42 3.84 0.41 3.84 0.41 - 3.84 0.41 100.00
8 Kolom 30/30 (beton bertulang) M3 1.11 0.12 1.11 0.12 - 1.11 0.12 100.00
9 Kolom 25/25 (beton bertulang) M3 0.34 0.04 1.07 0.11 - - -
10 Plat Lantai Tebal 12 cm (beton Bertulang) M3 2.16 0.21 11.70 1.12 12.40 1.19 12.40 1.19 - 12.40 1.19 100.00
11 Balok 20/20 (beton bertulang) M3 1.67 0.17 1.76 0.18 1.76 0.18 - 1.76 0.18 100.00
12 Balok 25/40 (beton bertulang) M3 2.18 0.22 2.82 0.29 2.82 0.29 - 2.82 0.29 100.00
13 Ring Balok 20/25 (beton Bertulang) M3 1.05 0.11 -
14 Keramik 40/40 M2 113.50 0.36 113.75 0.36 113.75 0.36 - 113.75 0.36 100.00
15 Railing Pipa View Spot M 106.49 0.71 106.49 0.71 106.49 0.71 - 106.49 0.71 100.00
16 Cat View Spot M2 247.76 0.08 169.98 0.05 169.98 0.05 - 169.98 0.05 100.00
17 Relief View Spot BH 4.00 0.45 4.00 0.45 - 4.00 0.45 100.00
18 Cat Menie Besi Railing Pipa View Spot M2 57.42 0.02 57.42 0.02 - 57.42 0.02 100.00
19 Cat Besi Railing View Spot M2 57.42 0.02 57.42 0.02 - 57.42 0.02 100.00
- PEKERJAAN KAYU -
1 Pekerjaan pasangan kolom 5x10 cm kayu kls I M3 0.03 0.00 -
Kontrak Awal Kontrak Adendum I Kontrak Adendum III S/d Minggu Lalu Minggu ini S/d Minggu ini Thdp
NO. URAIAN PEKERJAAN SATUAN VOLUME Bobot VOLUME Bobot VOLUME Bobot Volume Bobot Volume Bobot Volume Bobot Item Pek

(%) (%) (%) (%) (%) (%) (%)


a b c d g h k l o p q r s t u v
2 Pekerjaan pasangan Balok 5x10 cm kayu kls I M3 0.18 0.01 -
3 Pekerjaan pasangan Sokong 5x10 cm kayu kls I M3 0.09 0.01 -
4 Tangga M3 0.06 0.00 -
5 Kayu Pancang Diameter 8 - 10 Cm M' 90.00 0.04 -
-
-
XVII. PEKERJAAN PEMBANGUNAN TAMAN -
- PEKERJAAN PERSIAPAN -
1 Penyiapan Lokasi dan Bongkaran LS 1.00 0.01 -
2 Pengukuran dan Pemasangan Bouwplank M' 28.80 0.02 -
- PEKRJAAN TANAH -
1 Galian Tanah M3 18.50 0.02 -
2 Urugan Kembali Galian Tanah Pondasi Menerus M3 5.80 0.00 -
3 Urugan Pasir Bawah Pondasi Menerus M3 1.11 0.01 -
4 Pasangan Batu Kosong M3 3.24 0.04 -
5 Pekerjaan Pas. Pondasi Batu Gunung 1:4 M3 15.09 0.29 -
- PEKERJAAN STRUKTUR DAN PENULANGAN -
1 Pek. Sloof 1 20/30, mutu k=250 -
a. Pek. Beton (Pek. Sloof 1 20/30, beton mutu K = 250 ) M3 0.65 0.01 -
b. Pek. Pembesian (Pek. Sloof 1 20/30, beton mutu K=250 ) KG 169.56 0.03 -
c. Pek. Bekisting (Pek. Sloof 1 20/30, beton mutu K = 250 ) M2 7.27 0.01 -
2 Pek. Sloof 2 15/20, mutu k=250 -
a. Pek. Beton (Pek. Sloof 2 15/20, beton mutu K = 250 ) M3 1.27 0.03 -
b. Pek. Pembesian (Pek. Sloof 2 15/20, beton mutu K=250 ) KG 274.87 0.05 -
c. Pek. Bekisting (Pek. Sloof 2 20/30, beton mutu K = 250 ) M2 17.04 0.03 -
3 Pek. Kolom K1 20/20, mutu k=250 -
a. Pek. Beton (Pek. Kolom K1 (20/20), mutu k=250) M3 0.97 0.02 -
b. Pek. Pembesian (Pek. Kolom K1 (20/20), mutu k=250) KG 186.10 0.03 -
c. Pek. Bekisting (Pek. Kolom K1 (20/20), mutu k=250) M2 19.48 0.05 -
4 Pek. Kolom K2 15/15, mutu k=250 -
a. Pek. Beton (Pek. Kolom K2 (15/15), mutu k=250) M3 0.91 0.02 -
b. Pek. Pembesian (Pek. Kolom K2 (15/15), mutu k=250) KG 135.10 0.02 -
c. Pek. Bekisting (Pek. Kolom K2 (15/15), mutu k=250) M2 18.28 0.05 -
5 Pek. Ring Balok 15/20, mutu k=250 -
a. Pek. Beton (Pek. Ring Balok (15/20), beton mutu K=250) M3 1.55 0.04 -
b. Pek. Pembesian (Pek. Ring Balok (15/20), beton mutu K=250) KG 236.06 0.04 -
c. Pek. Bekisting (Pek. Ring Balok (15/20), beton mutu K=250) M2 20.74 0.06 -
- PEKERJAAN DINDING DAN LANTAI -
1 Pasang Batu tela M2 30.73 0.08 -
2 Plesteran M2 76.46 0.07 -
3 Pasangan Dinding Batu Andesit M2 76.46 0.31 -
4 Urugan Tanah peninggian lantai M3 20.16 0.08 -
5 Cor Lantai beton mutu fc = 7,4 MPa tebal 6 cm, M3 1.24 0.03 -
6 Urugan Pasir Bawah Laantai M3 1.41 0.01 -
7 Pasang Dinding Roster M2 31.27 0.22 -
8 Pembuatan Huruf Nama taman dari Beton bertulang LS 1.00 0.20 -
-
-
XVIII. PEKERJAAN RESERVOIR -
- PEKRJAAN TANAH -
1 Pembersihan Lokasi M2 68.64 0.01 -
2 Galian Tanah M3 10.15 0.01 -
3 Urugan Tanah M3 1.84 0.01 -
4 Urugan Pasir M3 1.71 0.01 -
- PEKRJAAN PONDASI -
1 Pas. Pondasi M3 6.84 0.13 -
- PEKERJAAN BETON DAN PONDASI -
1 Cor Beton bertulang M3 17.55 1.44 -
2 Cor Beton Tumbuk M3 2.57 0.05 -
- PEKERJAAN PLESTERAN -
1 Plesteran 1 : 4 t=15 mm M2 134.00 0.12 -
- PEKERJAAN LAIN-LAIN -
1 Pembuatan Tangga-tangga M' 7.00 0.11 -
2 Pembuatan Manhole 80 X 80 cm BH 3.00 0.06 -
- PEKERJAAN PERPIPAAN -
1 Pengadaan Pipa GIP dia. 100 mm M' 18.00 0.06 -
2 Pemasangan Pipa GIP dia. 100 mm M' 18.00 0.01 -
3 Pengadaan/Pemasangan Gate Valve Flange GIP dia. 100 mm BH 2.00 0.05 -
4 Pengadaan/Pemasangan Flange GIP dia. 100 mm BH 10.00 0.01 -
5 Pengadaan/Pemasangan Bend Flange GIP dia. 100 mm 90 drjt BH 2.00 0.00 -
6 Pengadaan Pipa GIP dia. 50 mm BH 18.00 0.03 -
7 Pemasangan Pipa GIP dia. 50 mm BH 18.00 0.01 -
8 Pengadaan/Pemasangan Gate Valve Flange GIP 50 mm - Inlet BH 1.00 0.01 -
9 Pengadaan/Pemasangan Flange GIP dia. 50 mm BH 2.00 0.00 -
10 Pengadaan/Pemasangan Bend Flange GIP dia. 50 mm 90 drjt BH 2.00 0.00 -
11 Pengadaan/Pemasangan Tee All Flange GIP dia. 100 x 100 x 100 mm 90 drjt BH 1.00 0.01 -
- PEKERJAAN PENGECATAN DAN WATER STOP -
1 Pengecatan Dinding M2 73.82 0.02 -
2 Water Proofing M2 80.50 0.05 -
3 Pemasangan Water Stop M' 18.00 0.04 -
4 Pengecatan tutup Man hole dan tutup Box valve M2 6.00 0.00 -
- INSTALASI AIR BERSIH -
1 Pengadaan Pipa GIP dia. 50 mm M' 252.00 0.41 -
2 Pemasangan Pipa GIP dia. 50 mm M' 252.00 0.20 -
3 Pas. Pipa Air Bersih PVC 1" M' 425.00 0.15 -
4 Accessories Pipa LS 1.00 0.05 -
-
-
XIX. PEKERJAAN PEMBANGUNAN MENARA AIR -
- PEKRJAAN PERSIAPAN -
1 Pembersihan Lokasi M2 51.66 0.01 23.52 0.00 23.52 0.00 23.52 0.00 - 23.52 0.00 100.00
2 Pengukuran dan Pemasangan Bouwplank M' 25.80 0.02 33.60 0.02 33.60 0.02 33.60 0.02 - 33.60 0.02 100.00
- PEKERJAAN TANAH DAN PONDASI -
1 Galian tanah pondasi Titik M3 27.00 0.02 12.60 0.01 12.60 0.01 12.60 0.01 - 12.60 0.01 100.00
2 Urugan Kembali galian Pondasi Titik M3 9.72 0.01 9.43 0.01 9.43 0.01 9.43 0.01 - 9.43 0.01 100.00
3 Urugan Pasir Bawah pondasi Titik M3 1.35 0.01 -
4 Pekerjaan pondasi pondasi batu belah campuran 1SP : 4PP M3 11.88 0.23 -
5 Pekerjaan pondasi pondasi batu belah campuran 1SP : 4PP M3 5.40 0.11 -
6 Pondasi Telapak Beton Bertulang M3 3.33 0.25 3.33 0.25 3.33 0.25 - 3.33 0.25 100.00
7 Kolom Telapak Beton Bertulang M3 0.81 0.06 0.81 0.06 0.81 0.06 - 0.81 0.06 100.00
- PEKRJAAN KAYU -
1 Pekerjaan pasangan kolom 15x15 cm kayu kls I M3 3.00 0.23 -
2 Pekerjaan pasangan Sloof 15x15 cm kayu kls I M3 0.87 0.07 -
3 Pekerjaan pasangan Balok penguat 15x15 cm kayu kls I M3 0.87 0.07 -
4 Pamasangan balok lantai 15x15 cm kayu kls I M3 0.87 0.07 -
5 Pamasangan Ring balok 15x15 cm kayu kls I M3 0.58 0.04 -
6 Pemasangan lantai papan 2x 25 cm kayu kls I M2 14.51 0.05 -
- PEKRJAAN BETON -
1 Beton Sloof 30/40 M3 3.60 0.08 3.60 0.08 3.60 0.08 - 3.60 0.08 100.00
Kontrak Awal Kontrak Adendum I Kontrak Adendum III S/d Minggu Lalu Minggu ini S/d Minggu ini Thdp
NO. URAIAN PEKERJAAN SATUAN VOLUME Bobot VOLUME Bobot VOLUME Bobot Volume Bobot Volume Bobot Volume Bobot Item Pek

(%) (%) (%) (%) (%) (%) (%)


a b c d g h k l o p q r s t u v
Bekisting M2 24.00 0.04 24.00 0.04 24.00 0.04 - 24.00 0.04 100.00
Pembesian KG 362.26 0.06 362.26 0.06 362.26 0.06 - 362.26 0.06 100.00
2 Beton Kolom 30/30 M3 2.11 0.05 2.11 0.05 2.11 0.05 - 2.11 0.05 100.00
Bekisting M2 28.08 0.08 28.08 0.08 28.08 0.08 - 28.08 0.08 100.00
Pembesian KG 228.33 0.04 228.33 0.04 228.33 0.04 - 228.33 0.04 100.00
3 Beton Kolom 13/13 M3 0.57 0.01 0.57 0.01 0.57 0.01 - 0.57 0.01 100.00
Bekisting M2 17.47 0.05 17.47 0.05 17.47 0.05 - 17.47 0.05 100.00
Pembesian KG 156.18 0.03 156.18 0.03 156.18 0.03 - 156.18 0.03 100.00
4 Beton Balok 30/40 M3 3.60 0.08 3.60 0.08 3.60 0.08 - 3.60 0.08 100.00
Bekisting M2 31.92 0.09 31.92 0.09 31.92 0.09 - 31.92 0.09 100.00
Pembesian KG 362.26 0.06 362.26 0.06 362.26 0.06 - 362.26 0.06 100.00
5 Beton Ring Balok 13/20 M3 0.78 0.02 0.78 0.02 0.78 0.02 - 0.78 0.02 100.00
Bekisting M2 15.70 0.04 15.70 0.04 15.70 0.04 - 15.70 0.04 100.00
Pembesian KG 150.14 0.03 150.14 0.03 150.14 0.03 - 150.14 0.03 100.00
6 Plat Dak Lantai M3 2.18 0.05 2.18 0.05 2.18 0.05 - 2.18 0.05 100.00
Bekisting M2 14.52 0.05 14.52 0.05 14.52 0.05 - 14.52 0.05 100.00
Pembesian KG 340.31 0.06 340.31 0.06 340.31 0.06 - 340.31 0.06 100.00
- PEKERJAAN ATAP -
1 Pekerjaan rangka atap kuda-kuda ekspose M3 0.57 0.04 0.39 0.03 0.39 0.03 0.39 0.03 - 0.39 0.03 100.00
2 Pas. Atap seng gelombang BJLS 0.30 mm M2 41.68 0.06 -
3 Pas.Atap Alumunium Spandek M2 49.93 0.07 49.93 0.07 49.93 0.07 - 49.93 0.07 100.00
4 Pekerjaan Nok Atap M' 10.02 0.01 11.40 0.01 11.40 0.01 11.40 0.01 - 11.40 0.01 100.00
5 Gording ky. Klas I M3 0.46 0.03 0.46 0.03 0.46 0.03 - 0.46 0.03 100.00
6 Pekerjaan pasangan lispang 2 x 30 cm M2 12.38 0.01 -
7 Pemasangan lisplank M' 47.52 0.04 47.52 0.04 47.52 0.04 - 47.52 0.04 100.00
- PROFIL TANK 2200 L -
1 Profil Tank 2200 L BH 3.00 0.10 -
2 Profil Tank 5200 L BH 3.00 0.20 - - -
3 Profil Tank 2350 L Stainless BH 3.00 0.32 3.00 0.32 - 3.00 0.32 100.00
4 Talang Air M' 22.80 0.05 25.80 0.05 25.80 0.05 - 25.80 0.05 100.00
5 Pas. Pipa PVC 2" M' 12.00 0.01 - - -
6 Pas. Pipa PVC 1" M' 12.00 0.00 12.00 0.00 - 12.00 0.00 100.00
7 Pas. Pipa PVC 2" M' 12.00 0.01 12.00 0.01 - 12.00 0.01 100.00
8 Pas. Pipa PVC 3/4" M' 60.00 0.02 60.00 0.02 - 60.00 0.02 100.00
9 Pagar Besi Hollow 4/4 M2 29.28 0.15 29.28 0.15 29.28 0.15 - 29.28 0.15 100.00
10 Tangga Besi 2 Inc BH 3.00 0.09 3.00 0.09 3.00 0.09 - 3.00 0.09 100.00
- PEKERJAAN PENGECATAN -
1 Cat Laburan dinding M2 102.57 0.03 102.57 0.03 102.57 0.03 - 102.57 0.03 100.00
2 Cat Kayu M2 54.89 0.04 54.89 0.04 - 54.89 0.04 100.00
3 Cat Menie Besi M2 71.09 0.02 71.09 0.02 - 71.09 0.02 100.00
4 Cat Besi M2 71.09 0.03 71.09 0.03 - 71.09 0.03 100.00
-
-
XX. PEKERJAAN BOX CULVERT -
- PEKERJAAN TANAH -
1 Pekerjaan galian tanah M3 58.80 0.05 -
2 Urugan pasir di bawah lantai M3 1.95 0.02 -
- PEKERJAAN BETON -
1 Pekerjaan lantai kerja beton mutu f’c = 7,4 Mpa M3 3.90 0.08 -
2 Pekerjaan beton mutu 19.3 Mpa M3 40.30 0.92 -
3 Besi tulangan KG 4,632.00 0.83 -
4 Bekisting Dinding Box Culvert M2 166.20 0.43 -
-
-
XXI. PEKERJAAN AKHIR -
1 Pembersihan akhir LS 1.00 0.07 1.00 0.07 1.00 0.07 - - 0.50 0.03 0.50 0.03 50.00
-
-
TOTAL PROGRES REALISASI 100.000 100.000 100.000 98.664 0.368 99.032
PROGRES RENCANA 99.258 0.250 99.508
DEVIASI -0.594 0.118 -0.476

Disetujui Diperiksa Dibuat


Pejabat Pembuat Komitmen Konsultan Supervisi Kontraktor
PT. SINAR ARENGKA SETIA MAJU – PT. YAVANA
PPK PKP & BPB Satker Pelaksanaan prasarana Permukiman Provinsi Papua Barat CV. ADYCITRA CONSULTAN
ABADI KONTRUKSI (KSO)

MARIO L.KAOTJIL, ST ANDDY SANTOSO, ST FAQIH USMAN, ST


19821012 201412 1 001 Supervisior Engineer Kuasa KSO
TIME SCHEDULE

WAKTU PELAKSANAAN 2020 WAKTU PELAKSANAAN 2021


SEPTEMBER OKTOBER NOVEMBER DESEMBER JANUARI FEBRUARI MARET APRIL MEI JUNI JULI AGUSTUS SEPTEMBER OKTOBER KETERANGAN
BOBOT BOBOT 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58
NO PEKERJAAN KONTRAK ADDENDUM
(%) (%) 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11
s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d
13 20 27 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 5 12 19 26 3 10
` `
I PEKERJAAN PERSIAPAN 100%
100.000
- PERALATAN 0.176 0.176 0.176 99.636
99.832
100.000
99.832
99.460 99.636 99.850
99.460 99.688
- MOBILISASI FASILITAS KONTRAKTOR 0.216 0.216 0.041 0.175 99.180
99.180
99.508 99.032
98.854 99.258
98.854 98.563 98.664
- MOBILISASI LAINNYA 0.049 0.049 0.006 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 98.437 0.001 0.001 0.001 0.001 98.888 98.461

98.002 98.237 98.488 98.150


97.938
- DEMOBILISASI 0.083 0.083 0.028 0.028 0.004 0.004 0.004 0.004 0.004 0.004 0.004
97.446 97.938
II PENYELENGGARAAN RK3K - 97.337 97.210
96.842
96.570
- PENYELENGGARAAN RK3K 0.326 0.326 0.034 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.001 0.001 0.001 0.001 0.001 0.001 0.001
96.101 96.044
96.137
III PEKERJAAN PEMBANGUNAN PANGGUNG BUDAYA -
- PEKERJAAN PERSIAPAN 0.023 0.023 0.023 95.211 95.118

94.842
- PEKERJAAN TANAH 1.148 0.248 0.248 94.406
94.154
- PEKERJAAN PONDASI 7.832 1.028 1.028 93.776

- PEKERJAAN LANTAI 2.692 0.599 0.200 0.200 0.200


92.914
93.492
ADDENDUM KE-4
92.672
- PEKERJAAN DINDING 0.379 0.101 0.101
92.112
- PEKERJAAN PENGECATAN 0.078 0.016
91.579
0.016 ..................90%
91.333
- PEKERJAAN ATAP - 3.235 0.416 1.253 1.247 0.319
- PEKERJAAN MECANIKAL ELEKTRICAL 0.127 0.127 90.702
90.135
89.945
IV PEKERJAAN PEMBANGUNAN GAZEBO -
89.262
- PEKERJAAN PERSIAPAN 0.187 0.087 0.087 89.272

88.574
- PEKERJAAN TANAH 0.010 0.149 0.149 88.499

- PEKERJAAN PONDASI PASANGAN BATU 0.499 0.409 0.409 87.822 87.577

- PEKERJAAN KAYU 1.696 0.027 0.027 86.916

- PEKERJAAN ATAP 1.630 0.591 0.191 0.191 0.208


86.342
- PEKERJAAN PENGECATAN 0.532 0.207 0.104 0.104
85.222
- PEKERJAAN BETON,PASANGAN DAN PLESTERAN - 0.903 0.337 0.086 0.480 85.128
84.842
- PEKERJAAN LANTAI - 0.380 0.113 0.141 0.113 0.012
- PEKERJAAN MECANIKAL ELEKTRICAL - 0.056 0.001 0.014 0.014 0.027
83.384 83.450
V PEKERJAAN PEMBANGUNAN RUANG TERBUKA HIJAU ( RTH ) - 83.322

- JOGGING TRACK 16.389 -


81.981
- TAMAN BERMAIN 12.897 29.348 0.696 0.527 0.125 0.403 0.544 0.502 0.494 0.114 0.395 1.198 0.731 1.490 1.220 1.101
81.492
1.440 0.899 81.782 0.199 1.347 0.927 0.993 2.124 0.867 0.755 0.676 1.381 1.332 1.096 0.622 0.705 0.919 0.518 0.605 0.694 0.545 0.395 0.365 0.245 0.155 80%
- TANGGA UTAMA -
- PEKERJAAN PERSIAPAN - 0.103 0.103
80.222
79.875
- PEKERJAAN PONDASI - 1.488 1.259 0.228
79.547
79.343
- PEKERJAAN LANTAI - 1.747 0.621 0.174 0.509 0.443
78.642
- PEKERJAAN PLESTERAN DAN PENGECATAN - 0.265 0.265 78.412

- TIFA UTAMA - 77.557

- PEKERJAAN PERSIAPAN - 0.012 0.012 77.022 76.965

- PEKERJAAN TANAH DAN PONDASI - 0.183 0.135 0.048


75.857
- PEKERJAAN BETON, PASANGAN DAN PLESTERAN 0.323 0.323
75.486
75.333
- PEKERJAAN LANTAI - 0.182 0.182
- PEKERJAAN PENGECATAN - 0.013 0.013
73.923
- PEKERJAAN TIFA - 1.816 0.147 0.220 0.070 0.220 0.120 0.161 0.100 0.140 0.260 0.264 0.057 73.626
0.057
73.284
VI PEKERJAAN PEMBANGUNAN PUJASERA -
- PEKERJAAN PERSIAPAN 0.135 0.117 0.117
71.924
- PEKERJAAN TANAH DAN PONDASI 3.931 3.006 0.243 1.199 1.328 0.235 71.819

- PEKERJAAN STRUKTUR DAN PENULANGAN 3.664 3.641 0.512 0.269 1.883 0.196 0.178 0.603 70.917

- PEKERJAAN DINDING DAN LANTAI 4.806 3.657 2.470 0.332 0.345 0.100 0.410
69.882
- PEKERJAAN KUSEN, KACA, KUNCI, DAN ALAT PENGGANTUNG 1.176 0.560 0.187 0.187 0.187
69.518
- ..................70%
- PEKERJAAN ATAP DAN PLAFOND 1.941 2.013 0.271 0.368 0.674 0.700
- PEKERJAAN CAT DAN LABURAN 0.478 0.479 0.239 0.239 68.465

- PEKERJAAN MECANIKAL ELEKTRICAL 0.669 0.333 0.333


67.246
- PEKERJAAN SANITAIR DAN SEPTICTANK 0.738 0.493 0.205 0.041 66.978

- PEKERJAAN BAK AIR 0.254 0.020 0.157 0.077


65.926
VII PEKERJAAN PEMBANGUNAN POS JAGA -
65.516

- PEKERJAAN PERSIAPAN 0.015 0.009 0.009


64.700
64.610 ADDENDUM KE-3
- PEKERJAAN TANAH DAN PONDASI 0.251 0.080 0.080
- PEKERJAAN STRUKTUR DAN PENULANGAN 0.202 0.259 0.259
63.300
- PEKERJAAN DINDING DAN LANTAI 0.349 0.144 0.144
- PEKERJAAN KUSEN, KACA, KUNCI, & ALAT PENGGANTUNG 0.074 0.056 0.056
61.907
61.907
- PEKERJAAN ATAP DAN PLAFOND 0.122 0.105 0.105
61.907
- PEKERJAAN CAT DAN LABURAN 0.063 0.032 0.032
60.537
- PEKERJAAN MECANIKAL ELEKTRICAL 0.035 0.022 0.022
VIII PEKERJAAN PEMBANGUNAN KIOS SOUVENIR - 60%
- PEKERJAAN PERSIAPAN 0.013 - ADDENDUM KE-2
- PEKERJAAN GALIAN DAN URUGAN 0.041 -
58.769
PERUABAHAN
PERUBAHAN PPK
PPK
- PEKERJAAN BETON, PASANGAN DAN PLESTERAN 0.708 - 57.656

- PEKERJAAN KUDA-KUDA DAN ATAP 0.189 -


- PEKERJAAN PLAFOND 0.088 -
- PEKERJAAN PENUTUP LANTAI DAN DINDING 0.057 - 55.806

- PEKERJAAN PENGECATAN 0.048 -


54.695
- PEKERJAAN INSTALASI LISTRIK 0.025 -
IX PEKERJAAN PEMBANGUNAN TOILET - 53.575

- PEKERJAAN PERSIAPAN 0.041 0.036 0.036


- PEKERJAAN TANAH DAN PONDASI 0.662 0.855 0.326 0.426 0.103 52.362

- PEKERJAAN STRUKTUR DAN PENULANGAN 0.429 1.030 0.646 0.385 51.683

- PEKERJAAN DINDING DAN LANTAI 1.248 1.501 0.922 0.579 ..................50%


- PEKERJAAN KUSEN, KACA, KUNCI, & ALAT PENGGANTUNG 0.183 0.366 0.366
49.865
- PEKERJAAN ATAP DAN PLAFOND 0.271 0.556 0.185 0.185 0.187
- PEKERJAAN CAT DAN LABURAN 0.076 0.168 0.084 0.084
48.540
- PEKERJAAN MECANIKAL ELEKTRICAL 0.057 0.109 0.109
- PEKERJAAN SANITAIR 0.538 0.867 0.381 0.191 0.295 47.613

X PEKERJAAN PEMBANGUNAN TALUD PENGAMAN -


- PEKERJAAN PERSIAPAN 0.108 0.073 0.073
- PEKERJAAN GALIAN DAN URUGAN 0.088 1.067 0.640 0.427
45.398
- PEKERJAAN BETON, PASANGAN DAN PLESTERAN 2.553 7.334 1.522 0.366 1.778 0.790 0.360 0.339 0.658 0.661 0.181 0.223 0.454
- PEKERJAAN PENGECATAN - 0.205 0.205
44.059
XI PEKERJAAN PEMBANGUNAN GEDUNG PENGELOLA -
- PEKERJAAN PERSIAPAN 0.024 0.061 0.061
- PEKERJAAN GALIAN DAN URUGAN 0.146 0.295 0.295
42.006
- PEKERJAAN BETON, PASANGAN DAN PLESTERAN 2.801 4.029 0.912 1.652 0.965 0.250 0.250 40%
- PEKERJAAN KUDA-KUDA DAN ATAP 0.423 0.836 0.836
- PEKERJAAN KUSEN PINTU DAN JENDELA 0.391 0.161 0.161 40.397

- PEKERJAAN ALAT GANTUNGAN DAN ACCESORIS 0.092 0.064 0.064


- PEKERJAAN PLAFOND 0.243 0.298 0.298
- PEKERJAAN PENUTUP LANTAI DAN DINDING 0.399 0.662 0.641 0.021
38.139

- PEKERJAAN PENGECATAN 0.223 0.271 0.271 37.760

- PEKERJAAN INSTALASI LISTRIK 0.131 0.157 0.157


- PEKERJAAN SANITAIR 0.139 -
- PEKERJAAN SANITAIR DAN SEPTICTANK - 0.388 0.152 35.486
0.236
- PEKERJAAN PEMASANGAN LISTRIK DAN JARINGAN - 0.884 0.342 0.142 0.400
- PEKERJAAN PERPIPAAN - 0.820 0.162 0.157 0.500
XII PEKERJAAN PENANAMAN TANAMAN - 33.557

- PEKERJAAN PERSIAPAN 0.056 0.056 0.056


- PENANAMAN DAN PEMELIHARAAN TANAMAN 7.822 3.749 0.450 0.208 0.271 0.478 0.408 1.215 0.416 0.122 0.181
- POT TANAMAN - 5.325 1.470 0.881 0.571 0.761 0.516 0.180 0.636 0.311
XIII PEKERJAAN PEMBANGUNAN GAPURA - ..................30%
- PEKERJAAN PERSIAPAN 0.049 0.035 0.035
- PEKERJAAN GALIAN DAN URUGAN 0.072 0.010 0.010
29.394
- PEKERJAAN BETON, PASANGAN DAN PLESTERAN 1.978 0.936 0.236 0.236 0.366 0.098
- PEKERJAAN ATAP 0.144 0.371 0.371
- PEKERJAAN PENUTUP LANTAI DAN DINDING 0.131 -
- PEKERJAAN PENGECATAN 0.045 0.049 0.049
26.485
XIV PEKERJAAN PEMBANGUNAN PAPAN INFORMASI -
- PEKERJAAN PERSIAPAN 0.009 -
25.272
- PEKERJAAN TANAH 0.000 -
- PEKERJAAN BETON, PASANGAN DAN PLESTERAN 0.219 -
XV PEKERJAAN PEMBANGUNAN DRAINASE -
- PEKERJAAN PERSIAPAN 0.105 -
- PEKERJAAN GALIAN DAN URUGAN 0.157 - 22.254

- PEKERJAAN BETON, PASANGAN DAN PLESTERAN 2.872 -


21.249
XVI PEKERJAAN PEMBANGUNAN VIEW SPOT -
- PEKERJAAN PERSIAPAN 0.018 0.070 0.070 20%
- PEKERJAAN GALIAN DAN URUGAN 0.005 0.011 0.011
- PEKERJAAN BETON, PASANGAN DAN PLESTERAN 0.554 3.996 3.065 0.323 0.376 0.232
- PEKERJAAN KAYU 0.068 - 18.132

XVII PEKERJAAN PEMBANGUNAN TAMAN - 17.596

- PEKERJAAN PERSIAPAN 0.024 -


- PEKERJAAN TANAH 0.367 - 16.226

- PEKERJAAN STRUKTUR DAN PENULANGAN 0.503 -


- PEKERJAAN DINDING DAN LANTAI 0.989 -
XVIII PEKERJAAN PEMBANGUNAN RESERVOIR - 14.228
14.093

- PEKERJAAN TANAH 0.042 -


- PEKERJAAN PONDASI 0.133 -
- PEKERJAAN BETON DAN PONDASI 1.497 -
- PEKERJAAN PLESTERAN 0.117 -
- PEKERJAAN LAIN-LAIN 0.163 - 10.851

- PEKERJAAN PERPIPAAN 0.211 -


- PEKERJAAN PENGECATAN DAN WATER STOP 0.118 - 10%
- INSTALASI AIR BERSIH 0.815 - 9.042 ADDENDUM KE-1
XIX PEKERJAAN PEMBANGUNAN MENARA AIR -
7.896
- PEKERJAAN PERSIAPAN 0.025 0.024 0.024
- PEKERJAAN TANAH DAN PONDASI 0.377 0.326 0.326
- PEKERJAAN KAYU 0.515 - KONTRAK 6.443

- PEKERJAAN BETON - 0.928 5.446 REALISASI 0.309 0.109 0.309 0.200


- PEKERJAAN ATAP 0.117 0.175 0.175
- PROFIL TANK 2200 L 0.102 0.640 0.267 0.186 0.187
- PEKERJAAN PENGECATAN - 0.118 3.555 0.118
XX PEKERJAAN PEMBANGUNAN BOX CULVERT -
- PEKERJAAN TANAH 0.066 - 2.363
1.995
- PEKERJAAN BETON 2.257 -
XXI PEMBERSIHAN AKHIR - 0.944
- 0.494
- PEMBERSIHAN AKHIR 0.068 0.068 - 0.130
0.000 0.264
0.000 0.000 0.000 0.217 0.068
-
JUMLAH BIAYA PEKERJAAN 100.000 100.000 0%
0.130 0.134 0.230 0.450 1.051 1.560 1.890 2.450 2.955 3.242 3.502 3.653 4.023 4.123 4.163 4.202 4.246 3.392 3.142 3.144 3.012 2.962 2.881 2.763 2.625 2.539 2.452 2.367 2.203 2.071 1.990 1.945 1.892 1.838 1.693 1.659 1.561 1.444 1.335 1.240 1.057 0.890 0.741 0.604 0.556 0.434 0.417 0.326 0.280 0.176 0.196 0.168
RENCANA
- 0.130 0.264 0.494 0.944 1.995 3.555 5.446 7.896 10.851 14.093 17.596 21.249 25.272 29.394 33.557 37.760 42.006 45.398 48.540 51.683 54.695 57.656 60.537 63.300 65.926 68.465 70.917 73.284 75.486 77.557 79.547 81.492 83.384 85.222 86.916 88.574 90.135 91.579 92.914 94.154 95.211 96.101 96.842 97.446 98.002 98.437 98.854 99.180 99.460 99.636 99.832 100.000
KONTRAK
0.000 0.000 0.000 0.000 0.217 2.146 4.081
REALISASI
- - 0.000 0.000 0.000 0.000 0.217 2.363 6.443 0.741 0.604

DEVIASI -0.130 -0.264 -0.494 -0.944 -1.779 -1.193 0.998

BOBOT MINGGUAN ( % ) 2.260 2.560 2.820 3.150 3.380 3.560 3.780 3.890 4.200 4.540 3.480 3.120 2.860 2.740 3.320 2.920 2.860
ADDENDUM KE-1
BOBOT KOMULATIF ( %- ) 6.443 8.703 11.263 14.083 17.233 20.613 24.173 27.953 31.843 36.043 40.583 44.063 47.183 50.043 52.783 56.103 59.023 61.883
ADDENDUM
2.598 5.187 1.998 1.906 4.121 4.232 9.000 2.653 2.258 3.662 3.554 2.252 2.497 1.213 2.232 2.962 3.138
REALISASI
- 0.000 0.000 0.000 0.000 0.217 2.363 6.443 9.042 14.228 16.226 18.132 22.254 26.485 35.486 38.139 40.397 44.059 47.613 49.865 52.362 53.575 55.806 58.769 61.907

DEVIASI 0.339 2.966 2.144 0.900 1.641 2.313 7.533 6.296 4.354 3.477 3.551 2.682 2.319 0.792 -0.296 -0.254 0.024

BOBOT MINGGUAN ( % ) 2.703 2.637 2.272 2.301 1.807 1.707 1.689 1.620 1.580 1.560 1.540 1.520 1.500 1.480 1.450 1.430 1.410 1.380 1.350 1.295 1.200 0.900 0.617 0.326 0.280 0.176 0.196
ADDENDUM KE-3
BOBOT KOMULATIF ( %- ) 61.907 64.610 67.246 69.518 71.819 73.626 75.333 77.022 78.642 80.222 81.782 83.322 84.842 86.342 87.822 89.272 90.702 92.112 93.492 94.842 96.137 97.337 98.237 98.854 99.180 99.460 99.636 99.832
ADDENDUM
2.845 3.086 0.816 1.463 2.904 2.042 1.999 1.934 1.108 1.447 0.931 0.532 2.106 1.469 1.678 2.448 0.922 0.763 0.683 1.388 1.339 1.104 0.630 0.712 0.926 0.526 0.640 0.728
REALISASI
- 0.000 0.000 0.000 0.000 0.217 2.363 6.443 58.769 61.614 64.700 65.516 66.978 69.882 71.924 73.923 75.857 76.965 78.412 79.343 79.875 81.981 83.450 85.128 87.577 88.499 89.262 89.945 91.333 92.672 93.776 94.406 95.118 96.044 96.570 97.210 97.938

DEVIASI 0.090 -1.731 -2.540 -1.937 -1.702 -1.410 -1.165 -1.677 -1.810 -2.439 -3.447 -2.861 -2.892 -2.694 -1.695 -2.203 -2.850 -3.547 -3.509 -3.464 -3.561 -3.831 -3.736 -3.136 -2.890 -2.426 -1.894

BOBOT MINGGUAN ( % ) 0.550 0.400 0.370 0.250 0.180 0.162 0.150


ADDENDUM KE-4
BOBOT KOMULATIF ( %- ) 61.907 97.938 98.488 98.888 99.258 99.508 99.688 99.850 100.000
ADDENDUM
0.000 0.000 0.000 0.000 0.217 2.146 4.081 2.598 5.187 1.998 1.906 4.121 4.232 9.000 2.653 2.258 3.662 3.554 2.252 2.497 1.213 2.232 2.962 3.138 3.086 0.816 1.463 2.904 2.042 1.999 1.934 1.108 1.447 0.931 0.532 2.106 1.469 1.678 2.448 0.922 0.763 0.683 1.388 1.339 1.104 0.630 0.712 0.926 0.526 0.640 0.728 0.212 0.311 0.102 0.101 0.368
REALISASI
0.000 0.000 0.000 0.000 0.217 2.363 6.443 9.042 14.228 16.226 18.132 22.254 26.485 35.486 38.139 40.397 44.059 47.613 49.865 52.362 53.575 55.806 58.769 61.907 64.700 65.516 66.978 69.882 71.924 73.923 75.857 76.965 78.412 79.343 79.875 81.981 83.450 85.128 87.577 88.499 89.262 89.945 91.333 92.672 93.776 94.406 95.118 96.044 96.570 97.210 97.938 98.150 98.461 98.563 98.664 99.032

DEVIASI -0.338 -0.427 -0.695 -0.844 -0.656

Sorong, 03 October 2021


Disetujui : Diperiksa : Dibuat oleh :
Pejabat Pembuat Komitmen Konsultan Supervisi Kontraktor Pelaksana
PPK PKP & BPB Satker Pelaksanaan prasarana Permukiman Provinsi Papua Barat CV. ADYCITRA CONSULTAN PT. SINAR ARENGKA SETIA MAJU – PT. YAVANA ABADI KONTRUKSI (KSO)

MARIO L.KAOTJIL, ST ANDDY SANTOSO, ST FAQIH USMAN, ST


19820829 201104 1 001 Supervisior Engineer Kuasa KSO
KONTRAKTOR KONSULTAN SUPERVISI

CV. ADYCITRA CONSULTAN

LAPORAN VISUAL / FOTO


NAMA PAKET PENATAAN KAWASAN SAMUBAAH KABUPATEN MAYBRAT
No. Dokumen
LOKASI KABUPATEN MAYBRAT

JENIS PEKERJAAN PEKERJAAN PEMBANGUNAN RUANG TERBUKA HIJAU ( RTH )


No. Revisi
TAHAPAN PEKERJAAN TAMAN BERMAIN

PERIODE TANGGAL (27 September s/d 03 October '20 ) Minggu ke : 56 ( Lima Puluh Enam )

Visual 1
Tgl. Foto :
(27 September s/d 03 October '20
)

Obyek :

Pekerjaan pemasangan tiang


lampu taman dan PJU

Catatan :

Visual 2
Tgl. Foto :
(27 September s/d 03 October '20
)

Obyek :

Pekerjaan pemasangan tiang


lampu taman dan PJU

Catatan :

Diperiksa dan Disetujui: Dibuat oleh :


Direksi Teknis Kontraktor Pelaksana

MUHAMMAD FADLI DOA, ST STEVEROL MOKODOMPIS, ST


Direksi Pelaksana
KONTRAKTOR KONSULTAN SUPERVISI

CV. ADYCITRA CONSULTAN

LAPORAN VISUAL / FOTO


NAMA PAKET PENATAAN KAWASAN SAMUBAAH KABUPATEN MAYBRAT
No. Dokumen
LOKASI KABUPATEN MAYBRAT

JENIS PEKERJAAN PEKERJAAN PEMBANGUNAN RUANG TERBUKA HIJAU ( RTH )


No. Revisi
TAHAPAN PEKERJAAN TAMAN BERMAIN

PERIODE TANGGAL (27 September s/d 03 October '20 ) Minggu ke : 56 ( Lima Puluh Enam )

Visual 1
Tgl. Foto :
(27 September s/d 03 October '20
)

Obyek :

Pekerjaan Pemasangan Tempat


Sampah

Catatan :

Visual 2
Tgl. Foto :
(27 September s/d 03 October '20
)

Obyek :

Pekerjaan Pemasangan Tempat


Sampah

Catatan :

Diperiksa dan Disetujui: Dibuat oleh :


Direksi Teknis Kontraktor Pelaksana

MUHAMMAD FADLI DOA, ST STEVEROL MOKODOMPIS, ST


Direksi Pelaksana
KONTRAKTOR KONSULTAN SUPERVISI

CV. ADYCITRA CONSULTAN

LAPORAN VISUAL / FOTO


NAMA PAKET PENATAAN KAWASAN SAMUBAAH KABUPATEN MAYBRAT
No. Dokumen
LOKASI KABUPATEN MAYBRAT

JENIS PEKERJAAN PEKERJAAN PEMBANGUNAN PUJASERA


No. Revisi
TAHAPAN PEKERJAAN PEKERJAAN ATAP DAN PLAFOND

PERIODE TANGGAL (27 September s/d 03 October '20 ) Minggu ke : 56 ( Lima Puluh Enam )

Visual 1
Tgl. Foto :
(27 September s/d 03 October '20
)

Obyek :
Pekerjaan Perakitan dan
pengecatan Kuda-kuda Hollow
Pujasera dan Pengelola

Catatan :

Visual 2
Tgl. Foto :
(27 September s/d 03 October '20
)

Obyek :
Pekerjaan Perakitan dan
pengecatan Kuda-kuda Hollow
Pujasera dan Pengelola

Catatan :

Diperiksa dan Disetujui: Dibuat oleh :


Direksi Teknis Kontraktor Pelaksana

MUHAMMAD FADLI DOA, ST STEVEROL MOKODOMPIS, ST


Direksi Pelaksana
KONTRAKTOR KONSULTAN SUPERVISI

CV. ADYCITRA CONSULTAN

LAPORAN JUMLAH TENAGA KERJA


NAMA PAKET PENATAAN KAWASAN SAMUBAAH KABUPATEN MAYBRAT

LOKASI KABUPATEN MAYBRAT

JENIS PEKERJAAN PEKERJAAN RTH,PUJASERA,PENGELOLA


TAHAPAN PEKERJAAN
PERIODE TANGGAL (27 September s/d 03 October '20 ) Minggu ke : 56 ( Lima Puluh Enam )

TANGGAL
TENAGA KERJA SATUAN SENIN SELASA RABU KAMIS JUMAT SABTU MINGGU JUMLAH KET.
27/09/21 28/09/21 29/09/21 30/09/21 01/10/21 02/10/21 03/10/21

A. STAF KONSULTAN :
1 Supervisior Engineer Orang 1 1 1 1 1 1 1 1
2 Supervisi Orang 1 1 1 1 1 1 1 1

Jumlah A. Orang 2

B. STAF KONTRAKTOR :
1 Site Manager Orang 1 1 1 1 1 1 1 1
2 Pelaksana Orang 1 1 1 1 1 1 1 1
3 Pembantu Pelaksana Orang 1 1 1 1 1 1 1 1
4 Operator Alat Berat Orang 1 1 1 1 1 1 1 1
5 Surveyor Orang
6 Keamanan Orang
7 Logistik Orang 1 1 1 1 1 1 1 1
PEKERJA : Orang
1 Mandor Orang 2 2 2 2 2 2 2 2
2 Kepala Tukang Orang 2 2 2 2 2 2 2 2
3 Pekerja/kenek Orang 6 6 6 6 6 6 6 6
4 Tenaga Struktur Orang
5 Tenaga Arsitektur Orang
6 Tenaga ME Orang
7 Tenaga Bantuan Orang
Jumlah B. Orang 15

Total Tenaga Kerja ( A + B) 17 Orang

Sorong, 03 October 2021


Disetujui Oleh : Diperiksa Oleh : Dibuat Oleh :

Direksi Teknis Konsultan Supervisi Kontraktor Pelaksana


CV. ADYCITRA CONSULTAN PT. SINAR ARENGKA SETIA MAJU – PT. YAVANA ABADI KONTRUKSI
(KSO)

MUHAMMAD FADLI DOA, ST MUHAMMAD HENDRA SAPUTRA, ST STEVEROL MOKODOMPIS, ST


Direksi Supervisi Pelaksana

0
KONTRAKTOR KONSULTAN SUPERVISI

CV. ADYCITRA CONSULTAN

LAPORAN CUACA
NAMA PAKET PENATAAN KAWASAN SAMUBAAH KABUPATEN MAYBRAT

LOKASI KABUPATEN MAYBRAT

JENIS PEKERJAAN PEKERJAAN RTH,PUJASERA,PENGELOLA

TAHAPAN PEKERJAAN -

PERIODE TANGGAL (27 September s/d 03 October '20 ) Minggu ke : 56 ( Lima Puluh Enam )

HARI Keadaan Cuaca Pada Jam


Hujan (jam) Gerimis (jam)
08.00
09.00
10.00
11.00
12.00
13.00
14.00
15.00
16.00
17.00
18.00
19.00
20.00
21.00
22.00
23.00
24.00
01.00
02.00
03.00
04.00
05.00
06.00
07.00
TANGGAL

SENIN
1
27 September 2021
SELASA `
2
28 September 2021
RABU
3
29 September 2021
KAMIS
4
30 September 2021
JUMAT
5
01 Oktober 2021
SABTU
6
02 Oktober 2021
MINGGU
7
03 Oktober 2021
JUMLAH

Keterangan :

= Cerah

= Gerimis

= Hujan

Sorong, 03 October 2021


Disetujui Oleh : Diperiksa Oleh : Dibuat Oleh :
Direksi Teknis Konsultan Supervisi Kontraktor Pelaksana
CV. ADYCITRA CONSULTAN PT. SINAR ARENGKA SETIA MAJU – PT.
YAVANA ABADI KONTRUKSI (KSO)

MUHAMMAD FADLI DOA, ST MUHAMMAD HENDRA SAPUTRA, ST STEVEROL MOKODOMPIS, ST


Direksi Supervisi Pelaksana