1. PARIT
Lebar : 3 mtr ( atas )
Lebar : 2.5 mtr ( bawah)
Tinggi : 2,5 mtr
Panjang : 2.200mtr
Volume : 3mtr X 2.5 mtr X 2.200 mtr = 16.500m3
B. Waktu Kerja 8 jam /hari
- Galih = 12 Detik = 0.81 X 3.600 X 0.71
- Buang = 4 Detik 26
- Putar = 5 Detik
- Putar balik = 5 Detik = 80 M3/Jam
Total = 26 Detik

KAPASITAS BUCKET = 1 M3 = 80 m3/Jam


= 640 M3/Hr ( 80 X 8 )

LAMA KERJA = 16.500 M3 = 26 Hr ( 1 Bulan )


640 M3
= 208 Jam ( 26 Hr X 8 Jam )

ASUMSI BIAYA
1. SEWA EXCAVATOR
200 Jam X Rp 300.000 Rp. 60.000.000,
2. SOLARr
Rp. 9.750 X 208 Jam X 20 Ltr Rp. 40.560.000,
3. OIL Rp. 500.000,
4. OPERATOR Rp. 6.500.000,
5. HELPER Rp. 3.000.000,
6. MOBILISASI ( pp ) Rp. 8.000.000,
7. OTHERS Rp. 5.000.000,
Rp. 123.560.000,

2. JALAN
ASUMSI DIKERJAKAN 15 HARI
1. SEWA EXVAVATOR Rp. 30.000.000,
100 Jam X Rp. 300.000
2. SOLAR Rp. 19.500.000,
Rp. 9.750 X 100 Jam X 20 Liter
3. OPERATOR Rp. 5.000.000,
4. HELPER Rp. 2.000.000,
5. OIL Rp. 500.000
TOTAL Rp. 57.500.000,
TOTAL BIAYA JALAN & PARIT Rp. 181.060.000,
FEE KONTRAKTOR Rp. 18.106.000,
Grand total Rp. 199.166.000,