REKAPITULASI BIAYA KONSTRUKSI

Jasa Pemborongan Design and Build


Pekerjaan Paket 1 : Pembangunan Jalan Tol Batang – Semarang (STA. 375+000 – STA. 449+200)

No. Uraian Harga


(Rp)

Design 10,895,926,848

BAB 1 Umum 11,909,431,098

BAB 2 Pembersihan Tempat kerja 5,347,066,535

BAB 3 Pembongkaran 59,319,786

BAB 4 Pekerjaan Tanah 270,240,392,044

BAB 5 Galian Struktur 2,220,828,713

BAB 6 Drainase 30,982,930,247

BAB 7 Subgrade 1,152,903,661

BAB 8 Lapis Pondasi Agregat 27,708,604,115

BAB 9 Perkerasan 229,665,584,721

BAB 10 Struktur Beton 421,711,921,014

BAB 11 Pekerjaan Baja Struktural -

BAB 12 Pekerjaan Lain-Lain 80,285,134,702

BAB 13 Pencahayaan, Lampu Lalu Lintas Dan Pekerjaan Listrik 23,603,722,718

BAB 14 Pekerjaan Plaza Tol 5,549,775,801

BAB 15 Pengalihan Dan Perlindungan Utilitas Yang Ada 6,185,898,135

BAB 16 Pekerjaan Fasilitas Tol 16,495,830,336

Jumlah Biaya Kontruksi (Non PPN) 1,144,015,270,474

Jakarta, 24 Juni 2014


PT. Waskita Karya (Persero), Tbk.
Divisi I

Ir. Ridwan Darma, MM.


Kepala Divisi
Kontrak
Seksi Selisih
4+5

23,818,862,194.00 (11,909,431,096)

8,745,991,648.00 (3,398,925,113)

75,978,850.00 (16,659,064)

307,501,962,624.00 (37,261,570,580)

4,153,745,338.00 (1,932,916,625)

88,811,799,401.00 (57,828,869,154)

1,808,607,566.00 (655,703,905)

48,989,098,460.00 (21,280,494,345)

448,999,848,929.00 (219,334,264,208)

1,053,362,241,288.00 (631,650,320,274)

0.00 -

121,875,805,671.00 (41,590,670,969)

30,993,249,655.43 (7,389,526,937)

8,801,613,735.00 (3,251,837,934)

12,371,796,270.00 (6,185,898,135)

16,495,830,336.00 -

2,176,806,431,965.43 (1,043,687,088,339)
PT. VIRAMA KARYA (Persero)

PEMILIK PROYEK KONSULTAN PENGAWAS KONTRAKTOR

MUTUAL CHECK NOL - (MC. 0)


Jasa Pemborongan Design and Build
Pekerjaan Seksi 4 : Pembangunan Jalan Tol Batang – Semarang (STA. 375+000 – STA. 449+200)

Kuantitas Harga Kuantitas MC 0 Seksi 4


Mata Pembayaran Uraian Pekerjaan Satuan Keterangan
Kontrak Bobot Volume Satuan Volume Volume Bobot
Volume
Kontrak 4 & 5 (Rp.) (Rp.) (Rp) (%)
Design

Biaya Design 0.9912 1.00 21,791,853,695.00 21,791,853,695 0.19 10,895,926,848 0.4956


Total Harga Penawaran Untuk Design 0.9912 21,791,853,695.000 10,895,926,848 0.4956
BAB 1 Umum

1.19 Pemeliharaan dan Perlindungan Lalu Lintas lump sum 1.00 0.3703 43,125,360,342 15,969,498,275 0.19 7,984,749,138 0.3632
1 20 (1) Laboratorium lump sum 1.00 0.3703 5,062,839,676 1,874,790,351 0.19 937,395,175 0.0426
1.20 (2) Mobilisasi ( yang tidak tercakup pada 1.20(1) ) lump sum 1.00 0.3703 14,584,765,000 5,400,798,455 0.19 2,700,399,228 0.1228
1.26 Pekerjaan dan Penanganan Aliran Air yang Sudah Ada lump sum 1.00 0.3703 1,549,470,000 573,775,113 0.19 286,887,556 0.0130

Total Harga Penawaran Untuk BAB 1 1.4812 23,818,862,194 11,909,431,098 0.5417


BAB 2 Pembersihan Tempat Kerja

2.01 (01) Pembersihan Tempat Kerja m2 5,978,883.85 0.3978 1,959,666.51 4,463 8,745,991,648 1,198,087.95 5,347,066,535 0.2432

Total Harga Penawaran Untuk BAB 2 0.3978 8,745,991,648 5,347,066,535 0.2432


BAB 3 Pembongkaran

3.01 (01) Pembongkaran Pasangan Batu atau Struktur Beton m3 300.00 0.0010 150.00 152,096 22,814,400 110.00 16,730,560 0.0008
3.01 (02) Pembongkaran Kerb m' 2,000.00 0.0007 1,200.00 13,073 15,687,600 - - 0.0000
3.01 (03) Pembongkaran Perkerasan Jalan Aspal atau Beton m2 1,600.00 0.0013 400.00 69,868 27,947,200 298.59 20,861,624 0.0009
3.01 (11) Pembongkaran guadrail m 750.00 0.0004 450.00 21,177 9,529,650 1,026.00 21,727,602 0.0010

Total Harga Penawaran Untuk BAB 3 0.0035 75,978,850 59,319,786 0.0027


BAB 4 Pekerjaan Tanah

4.03 (1) Galian Biasa untuk Timbunan m3 9,083,430.91 8.5438 2,846,002.16 66,003 187,844,232,088 566,791.23 37,409,832,333 1.7015
4.03 (2) Galian Biasa untuk Dibuang m3 1,231,178.84 0.5995 290,076.98 45,437 13,180,227,740 242,910.53 11,037,125,648 0.5020
4.05 (1) Borrow Material m3 2,131,237.53 3.5477 633,330.51 123,158 77,999,719,267 1,469,818.60 181,019,919,292 8.2334
4.08 (2) Urugan Material Berbutir (Granular BacKfill) m2 106,581.50 0.9453 52,474.88 396,042 20,782,257,146 17,544.50 6,948,359,661 0.3160
Timbunan Pilihan (lime stone) m3 171,184.41 0.3174 44,708.41 156,076 6,977,909,151 210,446.61 32,845,665,132 1.4939
Timbunan Aquiper m3 1,539.00 0.0326 1,539.00 466,288 717,617,232 2,100.61 979,489,978 0.0446

Total Harga Penawaran Untuk BAB 4 13.9863 307,501,962,624 270,240,392,044 12.2915


BAB 5 Galian Struktur

5.01 (1) Penggalian struktur sampai kedalaman tidak lebih dari 2 rn m3 96,037.63 0.1078 36,644.19 64,695 2,370,695,922 20,029.78 1,295,826,860 0.0589
30,386.58 14,761.88 93,597 5,763.73
5.01 (2) Penggalian struktur sampai kedalaman lebih dari 2 m, tapi tidak lebih dari 4 m m3 0.0628 1,381,667,934 539,467,726 0.0245

5.01 (3) Penggalian struktur sampai kedalaman lebih dari 4 m m3 7,298.88 0.0183 3,224.88 124,464 401,381,482 3,097.55 385,534,127 0.0175

Total Harga Penawaran Untuk BAB 5 0.1889 4,153,745,338 2,220,828,713 0.1010


BAB 6 Drainase

Pipa Gorong-gorong Beton Bertulang, Ø 60 cm. Tipe C m' 115.60 0.0092 57.80 3,506,839 202,695,289 54.00 189,369,301 0.0086
6.05 (10) Pipa Gorong-gorong Beton Bertulang, Ø 100 cm, Tipe A m' 906.00 0.0624 351.35 3,907,066 1,372,728,186 519.20 2,028,548,667 0.0923
6.05 (20) Pipe Gorong-gorong Baton Bertulang, 2 Ø 100 cm. Tipe C m' 159.00 0.0184 61.66 6,578,623 405,637,156 90.00 592,076,070 0.0269
6 06 (01) Saluran , Tipe DS - 1 m' 52,766.57 0.3421 16,388.75 458,921 7,521,139,544 6,250.00 2,868,256,250 0.1305
Saluran , Tipe DS - 2A m' 24,678.46 0.7122 10,123.00 1,546,803 15,658,286,135 - - 0.0000
6.06 (04) Saluran Tipe DS - 3 m' 25,077.00 0.4431 10,226.01 952,748 9,742,807,804 - - 0.0000
6.06 (06) Saluran , Tipe DS 4 m' 33,079.16 0.2391 13,489.16 389,676 5,256,402,835 22,900.00 8,923,580,400 0.4059
6.06 (09) Saluran , Tipe DS -8 m' 42,318.50 2.0304 18,101.55 2,466,092 44,640,079,942 6,140.00 15,141,804,880 0.6887
6.06 (13) Inlet Drain. Tipe DI-1 bh 19.00 0.0030 10.00 6,674,463 66,744,630 18.00 120,140,334 0.0055
6 06 (15) 2 Inlet Drain. Tips D1-4 bh 4.00 0.0008 2.00 8,887,741 17,775,482 2.00 17,775,482 0.0008
6.06 (16) Outlet Drain. Tipe DO-1 bh 19.00 0.0027 10.00 5,850,589 58,505,890 18.00 105,310,602 0.0048
6.06 (18) 2 Outlet Drain. Tipe DO-4 bh 4.00 0.0006 2.00 6,773,465 13,546,930 2.00 13,546,930 0.0006
6.07 (8) Bangunan Terjun Tegak (DV-10_ m3 536.65 0.0028 63.00 976,121 61,493,713 92.82 90,603,551 0.0041
6.08 (1) Pipe Drainase, Ø 15 cm dengan perlengkapan sambungan dan penyangga. m' 12,962.00 0.0871 6,411.36 298,855 1,916,066,805 1,658.55 495,665,960 0.0225
6.08 (3) Deck drain beserta asessorisnya, tipe 1. bh 3,692.00 0.0854 1,962.00 957,130 1,877,889,060 414.00 396,251,820 0.0180

Total Harga Penawaran Untuk BAB 6 4.0395 88,811,799,401 30,982,930,247 1.4092

Halaman 3 dari 6
PT. VIRAMA KARYA (Persero)

PEMILIK PROYEK KONSULTAN PENGAWAS KONTRAKTOR

MUTUAL CHECK NOL - (MC. 0)


Jasa Pemborongan Design and Build
Pekerjaan Seksi 4 : Pembangunan Jalan Tol Batang – Semarang (STA. 375+000 – STA. 449+200)

Kuantitas Harga Kuantitas MC 0 Seksi 4


Mata Pembayaran Uraian Pekerjaan Satuan Keterangan
Kontrak Bobot Volume Satuan Volume Volume Bobot
Volume
Kontrak 4 & 5 (Rp.) (Rp.) (Rp) (%)
BAB 7 Subgrade

7.01 Persiapan Tanah Dasar m2 2,251,086.43 0.0823 694,016.72 2,606 1,808,607,566 442,403.55 1,152,903,661 0.0524

Total Harga Penawaran Untuk BAB 7 0.0823 1,808,607,566 1,152,903,661 0.0524


BAB 8 Lapis Pondasi Agregat (Subbase)

8.01 (1) Lapis Pondasi Agregat Kelas A m3 333,787.76 2.1840 103,054.70 465,947 48,018,027,226 57,927.56 26,991,175,013 1.2277
8.01 (2) Laps Pondasi Agregat Kelas B m3 21,797.90 0.0442 2,178.55 445,742 971,071,234 1,609.52 717,429,102 0.0326

Total Harga Penawaran Untuk BAB 8 2.2282 48,989,098,460 27,708,604,115 1.2603


BAB 9 Perkerasan

9.04 Bitumen Lapis Resap Pengikat (Prime Coat ) kg 60,494.05 0.0038 5,989.27 14,058 84,197,087 7,638.07 107,376,051 0.0049
9.05 Bitumen Lapis Pengikat (Tack Coat) kg 109,760.60 0.0237 37,108.72 14,024 520,412,741 10,275.30 144,100,873 0.0066
9.07 (1) Asphalt treated base course ton 6,469.56 0.0248 882.43 618,870 546,108,857 1,003.86 621,259,593 0.0283
9.07 (2) Asphalt concrete binder course ton 2,967.27 0.0123 431.62 624,328 269,474,398 485.74 303,260,646 0.0138
9.07 (3) Asphalt concrete wearing course ton 6,553.27 0.0763 2,581.39 650,023 1,677,960,366 3,081.76 2,003,217,262 0.0911
9.07 (4) Semen Aspal ton 1,250.42 0.2161 398.97 11,911,143 4,752,129,664 245.43 2,923,316,111 0.1330
9.08 (1) Perkerasan Beton (t=32 cm) m2 1,860,104.22 16.3205 588,662.13 609,556 358,822,531,324 302,098.31 184,145,838,669 8.3756
9.08 (2) Perkerasan Beton (1=32 cm), Double Wire Mesh m2 12,310.00 0.2620 7,700.00 748,153 5,760,778,100 - - 0.0000
9 08 (3) Perkerasan Beton (t=32 cm), Single Wire Mesh m2 2,265.14 0.0415 1,344.87 678,579 912,601,447 411.01 278,902,755 0.0127
9.09 (1) Lean Concrete (t = 10 cm) m2 1,906,759.11 3.4410 604,595.62 125,131 75,653,654,945 312,778.71 39,138,312,761 1.7801

Total Harga Penawaran Untuk BAB 9 20.4221 448,999,848,929 229,665,584,721 10.4460


BAB 10 Struktur Beton

10.01 (4) Beton Kelas B - 1 - 1 (Reinforced Concrete Deck Slabs) m3 33,698.13 1.2983 14,298.57 1,996,349 28,544,938,094 5,533.98 11,047,759,132 0.5025
10.01 (5) Beton Kelas B - 1 - 2 (Diapraghma ) m3 6,119.33 0.2499 2,976.50 1,845,810 5,494,051,730 887.40 1,637,964,928 0.0745
10.01 (6) Beton Kelas B - 1 - 3 (Concrete Parapet) m3 7,550.22 0.2809 3,346.31 1,845,810 6,176,661,097 - - 0.0000
Beton Kelas B - 4 - 1 (Reinforced Concrete Pier Head) 29,549.67 1.1110 12,726.50 1,919,299 24,425,950,970 1,684.94 3,233,898,957 0.1471
Beton Kelas B - 4 - 2 (Reinforced Concrete Pier Columns & Wall Pier) 6,534.10 0.2219 2,541.61 1,919,299 4,878,106,827 2,719.08 5,218,721,245 0.2374
10.01 (10) Beton Kelas C - 1 m3 130,315.90 3.4045 51,195.01 1,462,081 74,851,250,080 27,340.24 39,973,641,039 1.8181
10 01 (16) Beton Kelas D m3 1,650.06 0.0340 590.48 1,266,077 747,589,662 14.12 17,874,969 0.0008
10.01 (17) Beton Kelas E m3 5,470.10 0.1027 2,061.16 1,095,579 2,258,165,632 2,189.27 2,398,521,360 0.1091
10.02 (2) Batang Baja Tulangan Ulir kg 38,525,643.86 8.1261 15,304,195.89 11,674 178,661,182,798 6,266,114.03 73,150,615,191 3.3271
10.03 (1) P.C.! Girder span L = 16 m buah 466.00 1.0283 202.00 111,924,591 22,608,767,382 182.00 20,370,275,562 0.9265
10.03 (2) P.C.I Girder span L = 20 m bush 146.00 0.2160 33.00 143,884,199 4,748,178,567 18.00 2,589,915,582 0.1178
10.03 (3) P.C.I Girder span L = 25 m buah 146.00 0.2762 33.00 183,999,508 6,071,983,764 36.00 6,623,982,288 0.3013
10.03 (4) P.C.I Girder span L = 30 m buah 417.00 1.4983 135.00 244,017,217 32,942,324,295 24.00 5,856,413,208 0.2664
10.03 (5) P.C.I Girder span L = 40 m buah 793.00 8.0878 464.00 383,229,283 177,818,387,312 133.00 50,969,494,639 2.3183
P.C.I Girder span L = 50 m buah 153.00 1.4343 61.00 516,956,547 31,534,349,367 12.00 6,203,478,564 0.2822
10.03 (8) Plat Pracetak (Concrete Plate) rn2 74,752.27 0.3597 33,804.24 233,916 7,907,353,465 13,244.90 3,098,194,262 0.1409
Tiang bor beton cast-in-place, dia. 80 cm m' 3,600.00 0.3183 1,590.00 4,400,800 6,997,272,000 - - 0.0000
Tiang bor beton cast-in-place, dia. 100 cm m' 140,980.00 17.1681 62,287.00 6,059,980 377,457,974,260 29,400.00 178,163,412,000 8.1035
10.07 (10) PDA test buah 268.00 0.0331 112.00 6,505,915 728,662,480 56.00 364,331,240 0.0166
10.09 (3)a Sambungan Ekspansi (Expansion Joint). type C m' 7,803.83 0.3073 3,269.06 2,066,543 6,755,644,890 1,036.80 2,142,591,782 0.0975
10.10 (2) Bearing Pad dengan asesori ukuran (300 x 350 x 36 mm) buah 1,144.00 0.0336 446.00 1,656,276 738,699,096 124.00 205,378,224 0.0093
10.10 (4)a Bearing Pad dengan asesori ukuran (350 x 400 x 40 mm) buah 994.00 0.0262 233.00 2,473,573 576,342,509 142.00 351,247,366 0.0160
10.10 (9)a Bearing Pad dengan asesori ukuran (450 x 500 x 60 mm) buah 5,295.00 1.2854 4,371.00 6,465,451 28,260,486,321 166.00 1,073,264,866 0.0488
10.11 (1) Sheet Pile / Turap Beton (6 m, Lengkap sampai pemancangan m 3,900.00 0.2150 3,900.00 1,212,212 4,727,626,800 1,860.00 2,254,714,320 0.1026
Beronjong m3 26,965.00 0.7937 26,965.00 647,146 17,450,291,890 7,365.00 4,766,230,290 0.2168

Total Harga Penawaran Untuk BAB 10 47.9106 1,053,362,241,288 421,711,921,014 19.1809

Halaman 4 dari 6
PT. VIRAMA KARYA (Persero)

PEMILIK PROYEK KONSULTAN PENGAWAS KONTRAKTOR

MUTUAL CHECK NOL - (MC. 0)


Jasa Pemborongan Design and Build
Pekerjaan Seksi 4 : Pembangunan Jalan Tol Batang – Semarang (STA. 375+000 – STA. 449+200)

Kuantitas Harga Kuantitas MC 0 Seksi 4


Mata Pembayaran Uraian Pekerjaan Satuan Keterangan
Kontrak Bobot Volume Satuan Volume Volume Bobot
Volume
Kontrak 4 & 5 (Rp.) (Rp.) (Rp) (%)
BAB 12 Pekerjaan Lain-Lain

12.01 (01) Pohon Ls 1.00 0.3253 56,250,000,000 18,300,000,060 0.16 9,150,000,030 0.4162
12.01 (03) Solid Sodding m2 1,814,123.98 1.0733 576,140.90 40,958 23,597,578,955 131,807.10 5,398,555,109 0.2455
12.02 (01) Pasangan Batu Kali untuk retaining Wall m3 3,573.80 0.0406 913.88 976,121 892,055,838 971.65 948,448,469 0.0431
12.05 (01) Guardrail, lipe A m' 63,837.00 0.6240 17,467.16 785,430 13,719,232,564 4,799.09 3,769,349,679 0.1714
12.05 (02) End Section Guardrail buah 2,062.00 0.0160 565.00 623,055 352,026,075 18.00 11,214,990 0.0005
12.05 (06) Chainlink Fence m' 4,034.20 0.0597 1,344.73 975,554 1,311,859,982 1,699.00 1,657,468,197 0.0754
12.06 (1) Rambu Pengaturan dan Peringatan. Tipe A-1 buah 341.00 0.0309 200.00 3,400,324 680,064,800 88.00 299,228,512 0.0136
12.06 (2) Rambu Pengaturan dan Peringatan, Tipe A-2 buah 18.00 0.0002 1.00 4,437,948 4,437,948 134.00 594,685,032 0.0270
12.06 (3) Rambu Pengaturan dan Peringatan, Tipe B-1 buah 45.00 0.0003 3.00 2,259,470 6,778,410 1.00 2,259,470 0.0001
12.07 (3) Rambu Petunjuk, Peringatan dan Larangan Tipe A - 3 buah 104.00 0.0033 3.00 24,398,196 73,194,588 3.00 73,194,588 0.0033
12.07 (5) Rambu Petunjuk, Peringatan dan Larangan Tipe B - 1 buah 11.00 0.0249 5.00 109,615,841 548,079,205 37.00 4,055,786,117 0.1845
12.07 (7) Rambu Petunjuk, Peringatan dan Larangan Tipe C buah 5.00 0.0116 2.00 127,343,565 254,687,130 17.00 2,164,840,605 0.0985
12.08 (1) Marka jalan, Tipe-A m2 48,012.37 0.1571 14,757.12 234,111 3,454,805,099 18,088.20 4,234,646,590 0.1926
12.08 (2) Marka Jalan, Tipe-B m2 2,889.30 0.0096 905.19 234,111 211,915,070 804.00 188,225,244 0.0086
12.09 (1) Guide Post. Tipe A buah 611.00 0.0031 339.00 199,352 67,580,328 350.00 69,773,200 0.0032
12.09 (5) Kilometer Post buah 369.00 0.0073 117.00 1,379,504 161,401,968 68.00 93,806,272 0.0043
12.10 (2) Concrete Bamer, tipe - B m' 69,686.00 1.2698 24,600.00 1,134,857 27,917,482,200 12,571.41 14,266,752,638 0.6489
12.11 (01) Kerb Beton. Tipe-A m' 3,186.45 0.0077 1,690.00 99,806 168,672,140 711.83 71,045,105 0.0032
12.12 (01) Pagar ROW. Tipe 1 (Panel Beton) m' 35,818.00 1.0032 19,001.00 1,160,747 22,055,353,747 8,900.00 10,330,648,300 0.4699
12.12 (02) Pagar ROW. Tipe 2 (Kawat Berdur) m' 113,778.60 0.2958 29,542.00 220,152 6,503,730,384 18,800.00 4,138,857,600 0.1882
Hand railing m' 3,691.20 0.0725 1,789.93 891,022 1,594,869,180 21,061.60 18,766,348,955 0.8536

Total Harga Penawaran Untuk BAB 12 5.0363 121,875,805,671 80,285,134,702 3.6517


BAB 13 Pencahayaan Lampu Lalu Lintas
Dan Pekerjaan Listrik

13.01 (1) Lampu PJU Cabang 1, T : 13 M (LED Essensial 1 x 185 W Dimming System) buah 421.00 0.1741 100.00 38,280,957 3,828,095,700 82.00 3,139,038,474 0.1428
13.01 (2) Lampu PJU Cabang 2, T : 13 M (LED Essensial 2 x 185 W Dimming System) buah 228.00 0.0793 44.00 39,600,990 1,742,443,560 251.00 9,939,848,490 0.4521
13.01 (3) Lampu Penerangan Jalan, Tinggi 13 m (2 x HPS 250 watt) buah 38.00 0.0140 8.00 38,395,486 307,163,888 4.00 153,581,944 0.0070
13.01 (4) Lampu Pengendali Lalu lintas Type 1 buah 4.00 0.0006 1.00 13,135,648 13,135,648 1.00 13,135,648 0.0006
13.01 (5) Lampu Pengendali Lalu lintas Type 2 buah 1.00 0.0007 1.00 15,762,778 15,762,778 - - 0.0000
13.01 (6) Panel Lampu Pengendali Lalu Lintas buah 4.00 0.0069 1.00 151,130,578 151,130,578 1.00 151,130,578 0.0069
5.00 2.00 411,018,675 -
13.01 (7) Lampu Hight Mast, Tinggi 30 m (4 x HPS-T 1000 watt), Rumah Lampu Type MVP 057 buah 0.0374 822,037,350 - 0.0000
2.00 1.00 479,521,788 2.00
13.01 (8) Lampu Hight Mast, Tinggi 35 m (4 x HPS-T 1000 watt) Rumah Lampu Type MVP 057 buah 0.0218 479,521,788 959,043,576 0.0436
13.01 (9) Lampu Menara (High Mast), Tinggi 30 m (3 x 1000 Watt) buah 66.00 0.5608 30.00 411,018,675 12,330,560,250 15.00 6,165,280,125 0.2804
13.01(11) Kabel NYFGBY 3C - 16 mm2 m' 40,990.00 0.1087 30,184.00 79,202 2,390,633,168 3,370.56 266,955,093 0.0121
13.01 (14) Kabei NYFGBY 4C - 16 mm2 m' 64,329.00 0.2831 50,326.00 123,665 6,223,579,888 12,260.00 1,516,136,578 0.0690
13.01 (17)a Kabel NYY/NYM 3x2,5 mm3 m' 40,990.67 0.0347 32,067.91 23,761 761,965,564 - - 0.0000
13.01)21) Panel PJU I buah 5.00 0.0058 2.00 63,361,584 126,723,168 - - 0.0000
13.01(22) Instaiasi Penangkal Petir Gerbang Tol buah 5.00 0.0002 2.00 1,920,912 3,841,824 1.00 1,920,912 0.0001
13.01(23) Penangkal Petir Lampu High Mast, Grounding & Asesoris buah 6.00 0.0135 3.00 99,002,475 297,007,425 1.00 99,002,475 0.0045
13.01(24) Penyambungan daya Ke PLN 82, Jalan Utama Ls 1.00 0.2445 405,910,148 99,234,210 0.12 49,617,105 0.0023
13.02)1) Pelindung Kabel m' 27,503.20 0.0233 14,942.20 34,321 512,831,246 12,260.00 420,775,460 0.0191
13.02.(3) Galian Kabel m' 27,503.20 0.0404 14,942.20 59,401 887,581,622 12,260.00 728,256,260 0.0331

Total Harga Penawaran Untuk BAB 13 1.6496 30,993,249,655 23,603,722,718 1.0736

Halaman 5 dari 6
PT. VIRAMA KARYA (Persero)

PEMILIK PROYEK KONSULTAN PENGAWAS KONTRAKTOR

MUTUAL CHECK NOL - (MC. 0)


Jasa Pemborongan Design and Build
Pekerjaan Seksi 4 : Pembangunan Jalan Tol Batang – Semarang (STA. 375+000 – STA. 449+200)

Kuantitas Harga Kuantitas MC 0 Seksi 4


Mata Pembayaran Uraian Pekerjaan Satuan Keterangan
Kontrak Bobot Volume Satuan Volume Volume Bobot
Volume
Kontrak 4 & 5 (Rp.) (Rp.) (Rp) (%)
BAB 14 Plaza Tol

14.01(1) Pulau Tol Tipe A set 7.00 0.0168 4.00 92,402,310 369,609,240 2.00 184,804,620 0.0084
14.01(2) Pulau Tol Tipe B set 4.00 0.0600 2.00 660,016,500 1,320,033,000 1.00 660,016,500 0.0300
14.01(3) Pulau Tol Tipe C set 4.00 0.0180 3.00 132,003,300 396,009,900 2.00 264,006,600 0.0120
14.01(4) Pulau Tol Tipe D set 6.00 0.0216 3.00 158,403,960 475,211,880 2.00 316,807,920 0.0144
14.01(5)a Atap Gerbang Tol untuk Gerbang 3 Lajur lengkap pemipaan & listrik set 5.00 0.0973 2.00 1,069,226,730 2,138,453,460 1.00 1,069,226,730 0.0486
14.01(5)b Atap Gerbang Tot untuk Gerbang 6 Lajur lengkap pemipaan & listrik set 1.00 0.0973 1.00 2,138,453,460 2,138,453,460 1.00 2,138,453,460 0.0973
14.01(6) Gardu Tel (pengumpul tiket) set 29.00 0.0893 15.00 130,922,853 1,963,842,795 7.00 916,459,971 0.0417

Total Harga Penawaran Untuk BAB 14 0.4003 8,801,613,735 5,549,775,801 0.2524


BAB 15 Pengalihan Dan Perlindungan Utilitas Yang Ada

15.1 Provisional Sum untuk pengalihan dan Perlindungan Utilitas Yang Ada PS 1.00 0.5627 1.00 21,371,796,270 12,371,796,270 0.29 6,185,898,135 0.2814

Total Harga Penawaran Untuk BAB 15 0.5627 12,371,796,270 6,185,898,135 0.2814


BAB 16 Pekerjaan Fasilitas Tol Dan Kantor Gerbang Tol

16.1 Kantor Gerbang Tol bh 4.00 0.2133 1.00 4,689,582,237 4,689,582,237 1.00 4,689,582,237 0.2133
16.2 Kantor Cabang bh 1.00 0.3512 1.00 7,722,065,997 7,722,065,997 1.00 7,722,065,997 0.3512
16.3 Tempat istirahat tipe B bh 4.00 0.1858 1.00 4,084,182,102 4,084,182,102 1.00 4,084,182,102 0.1858
Total Harga Penawaran Untuk BAB 16 0.7503 16,495,830,336 16,495,830,336 0.7503
Jumlah Total Nilai Kontrak 100.1308 2,198,598,285,660
Total Harga 1,144,015,270,474
Jumlah Bobot 52.0338

Halaman 6 dari 6