RENCANA ANGGARAN BIAYA (RAB)


PEKERJAAN CAFÉ BAPAK MUDIONO

NO PEKERJAAN HARGA
I PEKERJAAN PERSIAPAN & BONGKARAN Rp 6,000,000
II PEKERJAAN TANAH Rp 71,754,000
III PEKERJAAN BETON BERTULANG Rp 140,973,000
IV PEKERJAAN BESI PROFIL Rp 264,935,627
V PEKERJAAN DINDING Rp 22,750,000
VI PEKERJAAN PLESTERAN DAN ACIAN Rp 38,766,000
VII PEKERJAAN PENUTUP LANTAI Rp 13,920,000
VIII PEKERJAAN PENUTUP DINDING Rp 1,400,000
IX PEKERJAAN PENUTUP ATAP Rp 8,875,000
X PEKERJAAN ALUMUNIUM DAN KACA Rp 47,000,000
XI PEKERJAAN BESI Rp 15,100,000
XII PEKERJAAN CAT DAN FINISHING Rp 25,000,000
XIII PEKERJAAN SANITASI AIR Rp 14,425,000
XIV PEKERJAAN ELEKTRIKAL Rp 13,500,000

TOTAL HARGA (B) Rp 684,398,627

RENCANA ANGGARAN BIAYA (RAB)


PEKERJAAN LANDSCAPE CAFÉ BAPAK MUDIONO

NO PEKERJAAN HARGA
I PEKERJAAN PAVING DAN KANSTIN Rp 93,575,000
II PEKERJAAN AREA OUTDOOR Rp 40,000,000

TOTAL HARGA (b) Rp 133,575,000

TOTAL HARGA (A+B) Rp 817,973,627




RENCANA ANGGARAN BIAYA (RAB)


PEKERJAAN CAFÉ BAPAK MUDIONO

NO. Uraian Pekerjaan VOL SAT HARGA SATUAN SUB TOTAL

I PEKERJAAN PERSIAPAN & BONGKARAN


1 Pengukuran, pemasangan Bouwplank 1.00 ls Rp 6,000,000 6,000,000

TOTAL 6,000,000
II PEKERJAAN TANAH
1 Pekerjaan galian footplat 67.60 m3 Rp 155,000 10,478,000
2 Pekerjaan galian Pondasi 185.00 m3 Rp 155,000 28,675,000
3 Pekerjaan urugan kembali 84.20 m3 Rp 155,000 13,051,000
4 pekerjaan pemadatan tanah 782.00 m3 Rp 25,000 19,550,000

TOTAL 71,754,000
IV PEKERJAAN BETON BERTULANG
1 Pekerjaan footplat 13.37 m3 Rp 4,200,000 56,133,000
2 Pekerjaan Sloof 8.40 m3 Rp 4,200,000 35,280,000
3 Pekerjaan plat lantai 10.80 m3 Rp 4,200,000 45,360,000
4 Pekerjaan meja dapur 1.00 m3 Rp 4,200,000 4,200,000

TOTAL 140,973,000
V PEKERJAAN BESI PROFIL
1 Pekerjaan baja 528.00 kg Rp 32,000 16,896,000
2 Pekerjaan kolom baja iwf 250 x 125 x 6 x 9 1295.28 kg Rp 32,000 41,448,960
3 Pekerjaan balok baja iwf 350 x 175 x 7 x 11 4090.63 kg Rp 32,000 130,900,000
4 Pekerjaan balok anak baja iwf iwf 200 x 100 x 5.5 x 8 1365.33 kg Rp 32,000 43,690,667
5 Pekerjaan kuda - kuda 1000.00 kg Rp 32,000 32,000,000

TOTAL 264,935,627
VI PEKERJAAN DINDING
2 Pekerjaan bata ringan 182.00 m2 Rp 125,000 22,750,000

TOTAL 22,750,000
VII PEKERJAAN PLESTERAN DAN ACIAN
1 Pekerjaan plesteran 364.00 m2 Rp 55,000 20,020,000
2 Pekerjaan acian 364.00 m2 Rp 48,000 17,472,000
3 Pekerjaan sponengan 36.40 m' Rp 35,000 1,274,000

TOTAL 38,766,000
VIII PEKERJAAN PENUTUP LANTAI
1 Pekerjaan rabat beton 90.00 m2 Rp 95,000 8,550,000
2 Pekerjaan acian 90.00 m2 Rp 48,000 4,320,000
3 Pekerjaan granite 60x60 cm meja dapur 3.00 m2 Rp 350,000 1,050,000

TOTAL 13,920,000
IX PEKERJAAN PENUTUP DINDING
1 Pekerjaan granite 60x60 cm meja dapur 4.00 m2 Rp 350,000 1,400,000

TOTAL 1,400,000


X PEKERJAAN PENUTUP ATAP


1 Pekerjaan penutup atap alderon 25.00 m2 Rp 355,000 8,875,000

TOTAL 8,875,000
XI PEKERJAAN ALUMUNIUM DAN KACA
1 Pekerjaan kusen alumunium 4" 200.00 m2 Rp 135,000 27,000,000
2 Pekerjaan kaca 5 mm 40.00 m2 Rp 250,000 10,000,000
3 pekerjaan kaca 12 mm 4.00 m2 Rp 2,500,000 10,000,000
TOTAL 47,000,000
XII PEKERJAAN BESI
1 Pekerjaan tangga 6.00 m2 Rp 350,000 2,100,000
2 Pekerjaan rilling tangga 12.00 m2 Rp 250,000 3,000,000
3 Pekerjaan rilling lantai 2 40.00 m2 Rp 250,000 10,000,000

TOTAL 15,100,000
XIII PEKERJAAN CAT DAN FINISHING
1 Meni besi 1.00 ls Rp 15,000,000 15,000,000
3 Pekerjaan coating 1.00 ls Rp 10,000,000 10,000,000

TOTAL 25,000,000
XIV PEKERJAAN SANITASI AIR
1 Pekerjaan wastafel 1.00 bh Rp 1,000,000 1,000,000
2 Pekerjaan wasbak 2.00 bh Rp 1,000,000 2,000,000
3 pipa pvc 3" 50.00 m' Rp 75,000 3,750,000
4 pipa pvc 2.5" 60.00 m' Rp 55,000 3,300,000
5 pipa pvc 3/4 " 125.00 m' Rp 35,000 4,375,000

TOTAL 14,425,000
XV PEKERJAAN ELEKTRIKAL
1 Lampu gantung 20.00 bh Rp 375,000 7,500,000
2 lampu sorot 10.00 bh Rp 375,000 3,750,000
4 saklar ganda 5.00 bh Rp 150,000 750,000
5 saklar tunggal 10.00 bh Rp 150,000 1,500,000

TOTAL 13,500,000


RENCANA ANGGARAN BIAYA (RAB)


PEKERJAAN LANDSCAPE CAFÉ BAPAK MUDIONO

I PEKERJAAN PAVING DAN KANSTIN


1 Urugan sirtu 10 cm 35.00 m3 Rp 320,000 11,200,000
2 pemadatan 350.00 m2 Rp 25,000 8,750,000
3 Pekerjaan paving 350.00 m2 Rp 190,000 66,500,000
4 Pekerjaan kanstin 75.00 m' Rp 95,000 7,125,000

TOTAL 93,575,000
II PEKERJAAN AREA OUTDOOR
1 Pekerjaan rabat beton area outdoor 1.00 ls Rp 40,000,000 40,000,000