REKAPITULASI

Project : Pembangunan Cluster Perumahan 16 Unit


TA : 2021
Lokasi : Bogor Indonesia

NO ITEM PEKERJAAN JUMLAH HARGA

A PEKERJAAN PERSIAPAN 67,600,000

B PEKERJAAN TANAH & PONDASI 227,664,000

C PEKERJAAN STRUKTUR & ARSITEKTUR 1,146,482,800

D PEKERJAAN PINTU & JENDELA 228,000,000

E PEKERJAAN PLAFOND & ATAP 266,733,976

F PEKERJAAN MEP 218,628,000

G PEKERJAAN PENGECATAN 137,982,000

H PEKERJAAN FASUM PENUNJANG 214,821,000

TOTAL 2,507,911,776
RENCANA ANGGARAN BIAYA
Project : Pembangunan Cluster Perumahan 16 Unit
TA : 2021
Lokasi : Bogor Indonesia

NO ITEM PEKERJAAN VOLUME SATUAN HARGA SATUANJUMLAH HARGA


A PEKERJAAN PERSIAPAN
1 Desain Perencanaan 1.00 Ls 10,000,000 10,000,000
2 Mobilisasi & Demobilisasi 1.00 Ls 10,000,000 10,000,000
3 Land Clearing & Pembentukan Badan Bangunan 1,450.00 M2 15,000 21,750,000
4 Direksi Keet & Camp Pekerja (5x12 M) 60.00 M2 150,000 9,000,000
5 Listrik Kerja 9.00 Bln 1,000,000 9,000,000
6 Air Kerja 9.00 Bln 250,000 2,250,000
7 Pemasangan Bouwplank 16.00 Unit 350,000 5,600,000
TOTAL A 67,600,000
B PEKERJAAN TANAH & PONDASI
1 Galian Pondasi 633.60 M3 55,000 34,848,000
2 Urugan Pasir Bawah Pondasi 29.52 M3 150,000 4,428,000
3 Pas. Pondasi Batu Belah 285.12 M3 550,000 156,816,000
4 Timbunan Kembali Galian 211.20 M3 18,333 3,872,000
5 Urugan Dalam Bangunan 110.80 M3 250,000 27,700,000
TOTAL B 227,664,000
C PEKERJAAN STRUKTUR & ARSITEKTUR
1 Pekerjaan Sloof 984.00 M 105,000 103,320,000
2 Pekerjaan Kolom Praktis 1,016.00 M 100,000 101,600,000
3 Pekerjaan Ring Balk elv.+3.50 984.00 M 105,000 103,320,000
4 Pekerjaan Ring Balk elv.+3.50 s/d +6.30 412.00 M 105,000 43,260,000
5 Rabat Beton Carport 18.00 M3 200,000 3,600,000
6 Plat Konsul Ornamen Fasade 50.32 M2 100,000 5,032,000
7 Pasangan Dinding Bata Ringan T 7 Cm 2,126.96 M2 105,000 223,330,800
8 Plesteran Dinding 4,253.92 M2 60,000 255,235,200
9 Acian Dinding 4,253.92 M2 40,000 170,156,800
10 Pasangan Keramik 40/40 576.40 M2 180,000 103,752,000
11 Pasangan Keramik 30/30 KM 36.00 M2 165,000 5,940,000
12 Pasangan Dinding Keramik 30/60 120.00 M2 170,000 20,400,000
13 Pasangan Batu Alam 37.68 M2 200,000 7,536,000
TOTAL C 1,146,482,800
D PEKERJAAN PINTU & JENDELA
1 Pintu + Kusen Aluminium 64.00 Unit 2,200,000 140,800,000
2 Pintu + Kusen PVC Kamar Mandi 16.00 Unit 850,000 13,600,000
3 Jendela + Kusen Aluminium (1,2 x 1,9 M) 32.00 Unit 1,800,000 57,600,000
4 Jendela + Kusen Aluminium (0,5 x 1 M) 32.00 Unit 500,000 16,000,000
TOTAL D 228,000,000
E PEKERJAAN PLAFOND & ATAP
1 Pasang Gypsum 9 mm + Rangka Hollow 612.40 M2 115,000 70,426,000
2 Pasang Rangka Atap Baja Ringan 769.84 M2 110,000 84,681,872
3 Pasang Atap Genteng Minimalis Black 769.84 M2 145,000 111,626,104
TOTAL E 266,733,976
F PEKERJAAN MEP
1 Instalasi Titik Cahaya + Lampu LED Flat 112.00 Titik 250,000 28,000,000
2 Instalasi Stop Kontak + Armatur 96.00 Titik 250,000 24,000,000
3 Instalasi Box MCB + MCB 16 A 4 Buah 16.00 Unit 350,000 5,600,000
4 Instalasi NYY 3 x 4 MCB ke Kwh 32.00 M 45,000 1,440,000
5 Sambung Daya Baru PLN 1300 Watt 16.00 Unit 1,238,000 19,808,000
6 Sertifikat Laik Operasi 1.00 Ls 1,500,000 1,500,000
7 Instalasi Pipa 1" 416.00 M 26,250 10,920,000
8 Instalasi Pipa 3" 272.00 M 85,000 23,120,000
9 Instalasi Pipa 4" 160.00 M 120,000 19,200,000
10 Instalasi Floor Drain 16.00 Titik 35,000 560,000
11 Kloset Duduk 16.00 Bh 1,800,000 28,800,000
12 Shower + Keran 16.00 Set 200,000 3,200,000
13 Kran Air 32.00 Bh 65,000 2,080,000
14 Zinc Cuci Piring + Kran Angsa 16.00 Set 650,000 10,400,000
15 Instalasi Bio Septictank 16.00 Bh 2,500,000 40,000,000
TOTAL F 218,628,000
G PEKERJAAN PENGECATAN
1 Cat Interior 2,056.80 M2 27,000 55,533,600
2 Cat Eksterior 2,197.12 M2 30,000 65,913,600
3 Cat Plafond 612.40 M2 27,000 16,534,800
TOTAL G 137,982,000
H PEKERJAAN FASUM PENUNJANG
1 Perkerasan Jalan (Sub Grade) Vibro Roller 387.00 M2 52,000 20,124,000
2 Cor Beton Jalan K250 + Wire Steel 330.30 M2 350,000 115,605,000
3 Galian Saluran U-Ditch 18.40 M3 55,000 1,012,000
4 Saluran Air U-Ditch 40 x 40 x 120 Cm 96.00 Bh 450,000 43,200,000
5 Cover U-Ditch 40 HD (Tutup Saluran) 192.00 Bh 140,000 26,880,000
6 Lanscape Taman (Rumput+Bunga) 16.00 Unit 500,000 8,000,000
TOTAL H 214,821,000