REKAPITULASI RENCANA ANGGARAN BIAYA

PROYEK : YAYASAN CAHAYA AN NADZAR JAKARTA


LOKASI : JAKARTA

Revisi :
Tanggal :

NO URAIAN PEKERJAAN TOTAL (Rp)

A PEKERJAAN ARSITEKTUR Rp. 580,135,469

B PEKERJAAN ELEKTRIKAL Rp. 14,323,990

C PEKERJAAN MEKANIKAL Rp. 16,846,829

TOTAL BIAYA Rp. 611,306,289


DIBULATKAN Rp. 611,306,000
PPN 10% Rp. 61,130,600
GRAND TOTAL Rp. 672,436,600
DIBULATKAN Rp. 672,436,000

Jakarta, 2020
RENCANA ANGGARAN BIAYA / RAB
PROYEK : YAYASAN CAHAYA AN NADZAR JAKARTA
PEKERJAAN : PERSIAPAN
HARGA SATUAN JUMLAH HARGA
NO URAIAN PEKERJAAN SAT VOLUME
Rp. Rp.
I PEKERJAAN PERSIAPAN
1 Bongkaran Atap m2 148.00 36,000.00 5,328,000.00
2 Bongkaran Dinding m2 148.00 20,000.00 2,960,000.00
3 Pembersihan Lahan m2 148.00 18,450.00 2,730,600.00
4 Pekerjaan Pengukuran Site m2 148.00 6,000.00 888,000.00
5 Papan Nama Proyek bh 1.00 1,194,647.80 1,194,647.80
6 Gudang Bahan m 8.00 242,000.00 1,936,000.00
7 Instalasi Listrik kerja bln 6.00 200,000.00 1,200,000.00
8 Air Kerja Bln 6.00 4,725,000.00 4,725,000.00
9 P3K Bln 6.00 100,000.00 600,000.00
TOTAL PEKERJAAN PERSIAPAN 21,562,247.80
RENCANA ANGGARAN BIAYA / RAB
REKAPITULASI PEKERJAAN ARSITEKTUR

A PEKERJAAN ARSITEKTUR
I PEKERJAAN PERSIAPAN Rp. 21,562,247.80
II PEKERJAAN TANAH Rp. 10,230,231.50
III PEKERJAAN PASANGAN PONDASI Rp. 19,560,463.31
IV PEKERJAAN PASANGAN DINDING TEMBOK Rp. 29,185,950.13
V PEKERJAAN PLESTERAN, BENANGAN DAN ACIAN Rp. 49,392,702.90
VI PEKERJAAN BETON Rp. 217,717,616.67
VII PEKERJAAN RANGKA ATAP DAN PENUTUP ATAP Rp. 50,974,182.38
VIII PEKERJAAN PELAPIS LANTAI DAN DINDING Rp. 56,786,944.85
IX PEKERJAAN KUSEN PINTU DAN JENDELA Rp. 56,184,027.12
X PEKERJAAN RAILIING Rp. 22,386,377.43
XI PEKERJAAN PLAFOND Rp. 32,738,327.42
XII PEKERJAAN CAT Rp. 13,416,397.81

SUB TOTAL Rp. 580,135,469.32

RAB. ARS Page 3


RENCANA ANGGARAN BIAYA
PROYEK : YAYASAN CAHAYA AN NADZAR JAKARTA
LOKASI :
TANGGAL :

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A ARSITEKTUR
II PEKERJAAN TANAH
1 Galian Tanah Biasa Sedalam 1m m3 123.91 69,075.00 8,559,331.83
2 Urugan Tanah Kembali m3 114.02 12,483.00 1,423,261.71
3 Buangan Tanah Galian m3 9.90 25,020.00 247,637.95
SUB TOTAL 10,230,231.50

III PEKERJAAN PASANGAN PONDASI


1 Urugan Pasir m3 2.30 195,930.00 451,422.72
2 Beton Lantai Kerja 1:3:5 m3 2.39 734,910.04 1,755,847.07
3 Beton PILE CAP m3 5.14 3,378,737.06 17,353,193.52
SUB TOTAL 19,560,463.31

IV PEKERJAAN PASANGAN DINDING TEMBOK


1 Pasang Dinding Bata 1:5 1/2 Bata m2 253.05 109,344.90 27,669,863.63
2 Pasangan Trasram 1:3 m2 13.28 114,206.14 1,516,086.51
SUB TOTAL 29,185,950.13

V PEKERJAAN PLESTERAN, BENANGAN DAN ACIAN


1 Plesteran 15mm campuran 1 : 3 (Dinding) m2 506.10 60,403.35 30,570,286.44
2 Benangan Sudut 1 : 2 m 47.18 20,141.30 950,165.83
3 Acian Beton m2 506.10 35,313.50 17,872,250.63
SUB TOTAL 49,392,702.90

VI PEKERJAAN BETON
1 Beton Rabat beton 1:3:5 m3 0.65 842,859.22 546,804.92
2 Beton Sloof 20/40 m3 6.24 3,938,746.48 24,562,023.04
3 Beton Sloof 15/20 m3 1.31 5,738,740.71 7,492,499.88
4 Beton Kolom 15/40 m3 5.95 4,135,053.13 24,589,506.93
5 Beton Kolom praktis 15/15 m3 0.79 4,890,146.60 3,848,789.88
6 Beton Balok Latai dan ring balk 15/15 m3 1.91 4,516,945.42 8,625,954.21
7 Beton Plat anak tangga dan bordes tangga m3 1.39 5,257,336.63 7,302,440.58
8 Beton balok 20/30 m3 4.49 5,225,967.11 23,438,462.49
9 Beton balok RB 20/30 m3 4.49 5,225,967.11 23,438,462.49

10 Beton plat lantai t= 12 cm m3 14.41 5,119,022.83 73,782,805.25

11 Beton topian t= 10 cm m3 0.38 5,232,966.32 1,988,527.20


12 Beton plat lantai dasar t= 8 cm m3 10.26 1,764,990.81 18,101,339.80
SUB TOTAL 217,717,616.67

VII PEKERJAAN RANGKA ATAP DAN PENUTUP ATAP


1 Pemasangan Usuk Galvalum 7,5x3,5 cm t= 0,75 mm m2 184.93 82,624.40 15,279,317.17
2 Pemasangan Reng Galvalum 3x4 cm t= 0,5 mm m2 173.38 59,824.40 10,372,055.35
3 Lisplank Rangka Hollow 4x4 cm, t : 0,75 mm Kalsiplank m 45.00 109,408.00 4,923,360.00
4 Pemasangan Genteng Exel Monier Flat m2 173.38 112,396.70 19,486,777.86
5 Pemasangan Talang Pembuluh Pipa PVC 3 " Tipe AW m 24.00 38,028.00 912,672.00
SUB TOTAL 50,974,182.38

VIII PEKERJAAN PELAPIS LANTAI DAN DINDING


1 Pemasangan Keramik Lantai 20x20 cm m2 11.72 226,712.78 2,656,280.29
2 Pemasangan Lantai Keramik 40x40cm Unpolished + plint 10cm m2 219.01 222,702.50 48,774,297.23
3 Pemasangan Batu Alam Untuk Dinding Depan m2 13.79 228,215.00 3,146,102.38
4 Pemasangan Step Noshing Tangga utama m 20.00 53,038.40 1,060,768.00
5 Pasang Multiplek/Teakblock untuk Tangga utama t= 18 mm m2 10.50 109,475.90 1,149,496.95
SUB TOTAL 56,786,944.85

IX PEKERJAAN KUSEN PINTU DAN JENDELA


1 Pintu aluminium Type P1 (kelas)1600x2300mm Unit 4.00 4,609,362.82 18,437,451.27
2 Pintu aluminium Type P2 (R.guru)1000x2300mm Unit 1.00 2,938,347.31 2,938,347.31
3 Pintu aluminium Type P3 (toilet)800x2300mm Unit 1.00 2,982,918.90 2,982,918.90
4 Jendela Pintu aluminium Type JP1 (R.kelas lt1)2500x2300mm Unit 2.00 12,029,120.68 24,058,241.36
5 Jendela aluminium Type J1 (R.guru)3550x2300mm Unit 1.00 2,975,180.84 2,975,180.84
6 Jendela aluminium Type J2 (t.depan)3700x1400mm Unit 1.00 4,791,887.44 4,791,887.44
7 Jendela aluminium Type J3 (R.kelas lt2)2500x1400mm Unit 2.00 4,383,424.93 8,766,849.86
SUB TOTAL 56,184,027.12

X PEKERJAAN RAILIING
1 Railing Tangga Utama set 1.00 5,076,674.99 5,076,674.99
2 Railing balkon m 20.64 838,648.37 17,309,702.45

RAB. ARS Page 4


PROYEK : YAYASAN CAHAYA AN NADZAR JAKARTA
LOKASI :
TANGGAL :

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

SUB TOTAL 22,386,377.43

XI PEKERJAAN PLAFOND
1 Pas. Plafond Gypsumboard 9 mm Rangka Hollow m2 220.16 124,857.56 27,488,765.27
2 Pemasangan List Aluminium siku m 207.55 25,293.00 5,249,562.15
SUB TOTAL 32,738,327.42

XII PEKERJAAN CAT


1 Pengerjaan Cat Dinding Interior m2 253.52 18,342.96 4,650,307.22
2 Pengerjaan Cat Dinding Exterior m2 153.42 56,862.96 8,723,844.24
3 Pengerjaan Waterproofing m2 1.57 26,908.50 42,246.35
SUB TOTAL 13,416,397.81
TOTAL PEKERJAAN ARSITEKTUR 558,573,221.52

RAB. ARS Page 5


M/E

RENCANA ANGGARAN BIAYA


PEKERJAAN MEKANIKAL & ELEKTRIKAL
YAYASAN CAHAYA AN NADZAR JAKARTA
Tgl :

VOL SAT HARGA SAT JML HARGA


NO. URAIAN PEKERJAAN
PEK. PEK. ( Rp ) ( Rp )

B PEKERJAAN ELEKTRIKAL

I KABEL DISTRIBUSI TEGANGAN LISTRIK MENENGAH MV <20.000 VOLT


1 Panel Box 40x60x20cm 1.00 Unit 332,000.00 332,000.00
2 Panel Interlock Switch PLN-Genset Chint 2P 2.00 Unit 475,000.00 950,000.00
3 Kab 100.00 m' 14,840.00 1,484,000.00
4 Terminal Kabel 4 Jalur/pvp circular box 32.00 bh 12,500.00 400,000.00
5 Kabel Listrik 2X1,5 100.00 m' 4,580.00 458,000.00
6 5Pcs/Set Strip 3A Konektor Terminal Kabel Listrik 12 Posisi Blok 2.00 set 42,000.00 84,000.00
7 pipa listrik conduit 20 mm winlon / hpp + sok penyambung+klem 200.00 m' 6,166.67 1,233,333.33
8 isolasi listrik 3m+lem pipa 3.00 bh 15,000.00 45,000.00
SUB TOTAL 4,941,333.33

II PEK. INSTALASI PENERANGAN, FIXTURES & STOP KONTAK


1 Down light swillite DL 5 KBF 18.00 bh 195,000.00 3,510,000.00
2 kap lampu V LED 2x16watt 120cm/ kap TL 8.00 bh 195,000.00 1,560,000.00
3 Lampu emergency philips TL 1 x 18 watt / Lampu darurat 5.00 bh 385,000.00 1,925,000.00
4 lampu taman outdor ST 8911-H 2.00 bh 480,000.00 960,000.00
5 Saklar tunggal 10A 3.00 bh 30,111.00 90,333.00
6 Sak 12.00 bh 44,777.00 537,324.00
7 Sto 16.00 bh 50,000.00 800,000.00
SUB TOTAL 9,382,657.00
TOTAL PEKERJAAN ELEKTRIKAL 14,323,990.33

C PEKERJAAN MEKANIKAL
I PE
1 - Pipa air bersih 3/4" 12.00 m' 20,190.90 242,290.80
2 - Pipa air bersih 1/2" 26.00 m' 14,691.10 381,968.60
3 - Pipa air bekas 3" 12.00 m' 123,050.00 1,476,600.00
4 - 16.00 m' 204,370.00 3,269,920.00
5 Tangki Air Stainless Penguin TBSK-1000 Toren Air, Tandon Air 1.00 unit 3,460,000.00 3,460,000.00
6 Biotech kapasitas 1m3 1.00 unit 5,300,000.00 5,300,000.00
SUB TOTAL 14,130,779.40

II PE
1 kloset Toto CW421J/SW420JP soft closing 1.00 set 2,050,000.00 2,050,000.00
2 TOTO T23B13 KRAN AIR 2.00 set 205,000.00 410,000.00
3 Jet Shower, ex. Toto Type TX403SMRB 1.00 set 1,050.00 1,050.00
4 Floor Drain Toto TX1EB 1.00 set 255,000.00 255,000.00
SUB TOTAL 2,716,050.00
TOTAL PEKERJAAN MEKANIKAL 16,846,829.40
TOTAL ME 31,170,820

6
ANALISA HARGA SATUAN PEKERJAAN
DATA PEMBAHARUAN & PENYESUAIAN 2017-2018

Jumlah
No. Uraian Pekerjaan Sat. Koef. Harga Satuan (Rp)
(Rp)
1 2 3 5. 6.
I. PEKERJAAN PERSIAPAN
1 Pembersihan Lokasi m2 1.000
Pekerja OH 0.100 85,500.00 8,550.00
Mandor OH 0.050 198,000.00 9,900.00
Jumlah 18,450.00
2 Biaya Listrik kerja ls 1.000
Sewa Genset hr 90.000 60,000.00 5,400,000.00
Solar lt 450.000 7,000.00 3,150,000.00
Olie lt 20.000 32,100.00 642,000.00
Jumlah 9,192,000.00
3 Biaya Air Kerja ls 1.000
Air kerja bln 6.000 787,500.00 4,725,000.00
Jumlah 4,725,000.00
4 Papan Nama Proyek 80 x 120 cm, t = 250 cm unit 1.000
Kayu Meranti papan t= 2 cm m3 0.050 6,382,500.00 319,125.00
Seng Plat BJLS 30 m2 1.620 88,000.00 142,560.00
Paku kg 0.600 15,900.00 9,540.00
Cat Kayu kg 1.500 49,300.00 73,950.00
Beton Cor K225 m3 0.100 967,728.04 96,772.80
Pekerja OH 2.000 85,500.00 171,000.00
Tukang Kayu OH 1.000 107,400.00 107,400.00
Tukang cat OH 1.000 76,300.00 76,300.00
Mandor OH 1.000 198,000.00 198,000.00
Jumlah 1,194,647.80
II. PEKERJAAN TANAH
1 Galian Tanah Biasa Sedalam 1m m3 1.000
Pekerja OH 0.750 85,500.00 64,125.00
Mandor OH 0.025 198,000.00 4,950.00
Jumlah 69,075.00
2 Urugan Tanah Kembali m3 1.000
Pekerja OH 0.102 85,500.00 8,721.00
Mandor OH 0.019 198,000.00 3,762.00
Jumlah 12,483.00
3 Buangan Tanah Galian m3 1.000
Pekerja OH 0.200 85,500.00 17,100.00
Mandor OH 0.040 198,000.00 7,920.00
Jumlah 25,020.00
III. PEKERJAAN PASANGAN PONDASI
1 Urugan Pasir m3 1.000
Pasir Urug m3 1.100 136,800.00 150,480.00
Pekerja OH 0.300 85,500.00 25,650.00
Mandor OH 0.100 198,000.00 19,800.00
Jumlah 195,930.00
2 Beton Lantai Kerja 1:3:5 m3 1.000
Semen Portland 40 kg zak 5.750 56,700.00 326,025.00
Pasir beton m3 0.558 182,400.00 101,797.44
Batu pecah mesin 1/2 m3 0.541 271,200.00 146,583.60
Air (biaya air tawar) lt 215.000 100.00 21,500.00
Pekerja OH 1.200 85,500.00 102,600.00
Tukang Batu OH 0.200 109,300.00 21,860.00
Kepala Tukang Batu OH 0.020 133,200.00 2,664.00
Mandor OH 0.060 198,000.00 11,880.00
Jumlah 734,910.04
3 Beton PILE CAP m3 1.000
Beton K300 m3 1.000 1,021,595.92 1,021,595.92
Begesting m2 3.790 86,377.70 327,371.48
Besi beton polos U24 kg 57.750 12,930.04 746,709.81
Besi beton ulir U39 kg 96.871 13,245.04 1,283,059.84
Jumlah 3,378,737.06
IV. PEKERJAAN PASANGAN DINDING TEMBOK
1 Pasang Dinding Bata 1:5 1/2 Bata m2 1.000
7/30
Jumlah
No. Uraian Pekerjaan Sat. Koef. Harga Satuan (Rp)
(Rp)
Batu Bata Merah bh 70.000 700.00 49,000.00
Semen Portland 50 kg zak 0.194 61,100.00 11,853.40
Pasir Pasang m3 0.045 169,100.00 7,609.50
Pekerja OH 0.300 85,500.00 25,650.00
Tukang Batu OH 0.100 109,300.00 10,930.00
Kepala Tukang Batu OH 0.010 133,200.00 1,332.00
Mandor OH 0.015 198,000.00 2,970.00
Jumlah 109,344.90
Jumlah 1 m3 8.330 109,344.90 910,843.02
2 Pasang Dinding Bata 1:3 1/2 Bata m2 1.000
Batu Bata Merah bh 70.000 700.00 49,000.00
Semen Portland 50 kg zak 0.287 61,100.00 17,560.14
Pasir Pasang m3 0.040 169,100.00 6,764.00
Pekerja OH 0.300 85,500.00 25,650.00
Tukang Batu OH 0.100 109,300.00 10,930.00
Kepala Tukang Batu OH 0.010 133,200.00 1,332.00
Mandor OH 0.015 198,000.00 2,970.00
Jumlah 114,206.14
V. PEKERJAAN PLESTERAN, BENANGAN DAN ACIAN
1 Plesteran Tebal 15mm Campuran 1 : 3 m2 1.000
Semen Portland 50 kg zak 0.156 61,100.00 9,501.05
Pasir pasang m3 0.023 169,100.00 3,889.30
Pekerja OH 0.300 85,500.00 25,650.00
Tukang Batu OH 0.150 109,300.00 16,395.00
Kepala Tukang Batu OH 0.015 133,200.00 1,998.00
Mandor OH 0.015 198,000.00 2,970.00
Jumlah 60,403.35
2 Benangan Sudut 1 : 2 m 1.000
Semen Portland zak 0.010 61,100.00 611.00
Pasir Pasang m3 0.013 169,100.00 2,198.30
Pekerja OH 0.080 85,500.00 6,840.00
Tukang Batu OH 0.040 109,300.00 4,372.00
Kepala Tukang Batu OH 0.040 133,200.00 5,328.00
Mandor OH 0.004 198,000.00 792.00
Jumlah 20,141.30
3 Acian Beton m2 1.000
Semen Portland zak 0.065 61,100.00 3,971.50
Pekerja OH 0.200 85,500.00 17,100.00
Tukang Batu OH 0.100 109,300.00 10,930.00
Kepala Tukang Batu OH 0.010 133,200.00 1,332.00
Mandor OH 0.010 198,000.00 1,980.00
Jumlah 35,313.50
VI. PEKERJAAN BETON
1 Beton Rabat beton 1:3:5 m3 1.000
Semen Portland 40 kg zak 6.900 56,700.00 391,230.00
Pasir beton m3 0.518 182,400.00 94,392.00
Batu pecah mesin 1/2 m3 0.533 271,200.00 144,441.12
Air (biaya air tawar) lt 215.000 100.00 21,500.00
Pekerja OH 1.650 85,500.00 141,075.00
Tukang Batu OH 0.275 109,300.00 30,057.50
Kepala Tukang Batu OH 0.028 133,200.00 3,729.60
Mandor OH 0.083 198,000.00 16,434.00
Jumlah 842,859.22
2 Beton K-225 m3 1.000
Semen Portland 40 kg zak 9.275 56,700.00 525,892.50
Pasir beton m3 0.436 182,400.00 79,581.12
Batu pecah mesin 1/2 m3 0.551 271,200.00 149,458.32
Air (biaya air tawar) lt 215.000 100.00 21,500.00
Pekerja OH 1.650 85,500.00 141,075.00
Tukang Batu OH 0.275 109,300.00 30,057.50
Kepala Tukang Batu OH 0.028 133,200.00 3,729.60
Mandor OH 0.083 198,000.00 16,434.00
Jumlah 967,728.04
3 Beton K-300 m3 1.000
Semen Portland 40 kg zak 10.325 56,700.00 585,427.50
Pasir beton m3 0.426 182,400.00 77,629.44
Batu pecah mesin 1/2 m3 0.537 271,200.00 145,742.88
Air (biaya air tawar) lt 215.000 100.00 21,500.00
Pekerja OH 1.650 85,500.00 141,075.00
Tukang Batu OH 0.275 109,300.00 30,057.50
Kepala Tukang Batu OH 0.028 133,200.00 3,729.60

8/30
Jumlah
No. Uraian Pekerjaan Sat. Koef. Harga Satuan (Rp)
(Rp)
Mandor OH 0.083 198,000.00 16,434.00
Jumlah 1,021,595.92
4 Pembesian Dengan Besi Ulir 39 kg 1.000
Besi beton ulir kg 1.050 10,900.00 11,445.00
Kawat beton (bendrat) kg 0.015 17,600.00 264.00
Pekerja OH 0.007 85,500.00 598.50
Tukang Besi OH 0.007 109,300.00 765.10
Kepala Tukang Besi OH 0.001 133,200.00 93.24
Mandor OH 0.000 198,000.00 79.20
Jumlah 13,245.04
5 Pembesian Dengan Besi Polos U-24 kg 1.000
Besi beton polos kg 1.050 10,600.00 11,130.00
Kawat beton (bendrat) kg 0.015 17,600.00 264.00
Pekerja OH 0.007 85,500.00 598.50
Tukang Besi OH 0.007 109,300.00 765.10
Kepala Tukang Besi OH 0.001 133,200.00 93.24
Mandor OH 0.000 198,000.00 79.20
Jumlah 12,930.04

9/30
Jumlah
No. Uraian Pekerjaan Sat. Koef. Harga Satuan (Rp)
(Rp)
6 Pembesian Wiremesh M6 m2 1.000
Wiremesh M6 (210 x 495 cm ) lbr 0.0900 428,000.00 38,520.00
Kawat beton kg 0.0300 17,600.00 528.00
Pekerja OH 0.1500 85,500.00 12,825.00
Tukang Besi OH 0.0300 109,300.00 3,279.00
Kepala Tukang Besi OH 0.0150 133,200.00 1,998.00
Mandor OH 0.0300 198,000.00 5,940.00
Jumlah 63,090.00
7 Bekisting Untuk Pile Cap m2 1.000
Batako Ukuran 9 x 19 x 39 cm bh 14.000 2,300.00 32,200.00
Pasir Pasang m3 0.027 169,100.00 4,565.70
Semen PC Kg 7.500 1,200.00 9,000.00
Pekerja HO 0.320 85,500.00 27,360.00
Tukang Batu HO 0.100 109,300.00 10,930.00
Kepala Tukang Batu HO 0.010 133,200.00 1,332.00
Mandor/Pengawas HO 0.005 198,000.00 990.00
Jumlah 86,377.70
8 Bekisting Untuk Sloof, Kolom, Ring Praktis m2 1.000
Kayu meranti papan (MC) m3 0.022 1,890,000.00 41,580.00
Kayu meranti usuk m3 0.002 3,498,000.00 6,996.00
Paku biasa 2"- 5" kg 0.300 15,900.00 4,770.00
Minyak Begesting ltr 0.100 7,100.00 710.00
Jumlah bahan 54,056.00
Pekerja OH 0.520 85,500.00 44,460.00
Tukang Kayu OH 0.260 109,300.00 28,418.00
Kepala Tukang Kayu OH 0.026 133,200.00 3,463.20
Mandor OH 0.026 198,000.00 5,148.00
Jumlah upah 81,489.20
Bahan Begesting 2x pakai 0.500 54,056.00 27,028.00
Upah bgesting 2 x pakai 1.000 81,489.20 81,489.20
Jumlah begesting 2 x pakai 108,517.20
9 Bekisting Kolom Struktur m2 1.000
Kayu meranti usuk m3 0.010 3,498,000.00 34,980.00
Paku biasa 2"- 5" kg 0.400 15,900.00 6,360.00
Minyak Begesting ltr 0.200 7,100.00 1,420.00
Balok Kayu Meranti m3 0.015 4,161,000.00 62,415.00
Multiplek tebal 12 mm lbr 0.350 175,400.00 61,390.00
Dolken Kayu Gelam 8-10/400 cm btg 2.000 15,000.00 30,000.00
Jumlah bahan 196,565.00
Pekerja OH 0.660 85,500.00 56,430.00
Tukang Kayu OH 0.330 109,300.00 36,069.00
Kepala Tukang Kayu OH 0.033 133,200.00 4,395.60
Mandor OH 0.033 198,000.00 6,534.00
Jumlah upah 103,428.60
Bahan Begesting 2x pakai 0.500 196,565.00 98,282.50
Upah bgesting 2 x pakai 1.000 103,428.60 103,428.60
Jumlah begesting 2 x pakai 201,711.10
10 Bekisting Balok Struktur m3 1.000
Kayu meranti usuk m3 0.020 3,498,000.00 69,960.00
Paku biasa 2"- 5" kg 0.400 15,900.00 6,360.00
Minyak Begesting ltr 0.200 7,100.00 1,420.00
Balok Kayu Meranti m3 0.018 4,161,000.00 74,898.00
Multiplek tebal 12 mm lbr 0.350 175,400.00 61,390.00
Dolken Kayu Gelam 8-10/400 cm btg 2.000 15,000.00 30,000.00
Jumlah bahan 244,028.00
Pekerja OH 0.660 85,500.00 56,430.00
Tukang Kayu OH 0.330 109,300.00 36,069.00
Kepala Tukang Kayu OH 0.033 133,200.00 4,395.60
Mandor OH 0.033 198,000.00 6,534.00
Jumlah upah 103,428.60
Bahan Begesting 2x pakai 0.500 244,028.00 122,014.00
Upah bgesting 2 x pakai 1.000 103,428.60 103,428.60
Jumlah begesting 2 x pakai 225,442.60

10/30
Jumlah
No. Uraian Pekerjaan Sat. Koef. Harga Satuan (Rp)
(Rp)
11 Bekisting Plat Lantai m3 1.000
Kayu meranti usuk m3 0.0238 3,498,000.00 83,252.40
Paku biasa 2"- 5" kg 0.4000 15,900.00 6,360.00
Minyak Begesting ltr 0.2000 7,100.00 1,420.00
Balok Kayu Meranti m3 0.0150 4,161,000.00 62,415.00
Multiplek tebal 12 mm lbr 0.3500 175,400.00 61,390.00
Dolken Kayu Gelam 8-10/400 cm btg 6.0000 15,000.00 90,000.00
Jumlah bahan 304,837.40
Pekerja OH 0.660 85,500.00 56,430.00
Tukang Kayu OH 0.330 109,300.00 36,069.00
Kepala Tukang Kayu OH 0.033 133,200.00 4,395.60
Mandor OH 0.033 198,000.00 6,534.00
Jumlah upah 103,428.60
Bahan Begesting 2x pakai 0.500 304,837.40 152,418.70
Upah bgesting 2 x pakai 1.000 103,428.60 103,428.60
Jumlah begesting 2 x pakai 255,847.30
12 Bekisting Tangga m3 1.000
Kayu meranti usuk m3 0.030 3,498,000.00 104,940.00
Paku Usuk kg 0.400 16,700.00 6,680.00
Minyak Begesting ltr 0.150 7,100.00 1,065.00
Balok Kayu Kamper 3/5 m3 0.015 4,161,000.00 62,415.00
Multiplek tebal 9 mm lbr 0.350 119,800.00 41,930.00
Jumlah bahan 217,030.00
Pekerja OH 0.660 85,500.00 56,430.00
Tukang Kayu OH 0.330 109,300.00 36,069.00
Kepala Tukang Kayu OH 0.033 133,200.00 4,395.60
Mandor OH 0.033 198,000.00 6,534.00
Jumlah upah 103,428.60
Bahan Begesting 2x pakai 0.500 217,030.00 108,515.00
Upah bgesting 2 x pakai 1.000 103,428.60 103,428.60
Jumlah begesting 2 x pakai 211,943.60
13 Beton Sloof 20/40 m3 1.000
Beton K300 m3 1.000 1,021,595.92 1,021,595.92
Begesting 2x pakai m2 9.500 108,517.20 1,030,913.40
Besi beton polos U24 kg 65.980 12,930.04 853,124.04
Besi beton ulir U39 kg 78.000 13,245.04 1,033,113.12
Jumlah 3,938,746.48

14 Beton Sloof 15/20 m3 1.000


Beton K300 m3 1.000 1,021,595.92 1,021,595.92
Begesting 2x pakai m2 13.330 108,517.20 1,446,534.28
Besi beton polos U24 kg 252.947 12,930.04 3,270,610.52
Besi beton ulir U39 kg 0.000 13,245.04 -
Jumlah 5,738,740.71
15 Beton Kolom 15/40 m3 1.000
Beton K300 m3 1.000 1,021,595.92 1,021,595.92
Begesting 2x pakai m2 9.330 108,517.20 1,012,465.48
Besi beton polos U24 kg 55.956 12,930.04 723,507.57
Besi beton ulir U39 kg 104.000 13,245.04 1,377,484.16
Jumlah 4,135,053.13
16 Beton Kolom praktis 15/15 m3 1.000
Beton K225 m3 1.000 967,728.04 967,728.04
Begesting 2x pakai m2 13.330 108,517.20 1,446,534.28
Besi beton polos U24 kg 191.483 12,930.04 2,475,884.29
Jumlah 4,890,146.60
17 Beton Balok Latai dan ring balk 15/15 m3 1.000
Beton K225 m3 1.000 967,728.04 967,728.04
Begesting 2x pakai m2 13.330 108,517.20 1,446,534.28
Besi beton polos U24 kg 162.620 12,930.04 2,102,683.10
Jumlah 4,516,945.42
18 Beton Plat anak tangga dan bordes tangga m3 1.000
Beton K300 m3 1.000 1,021,595.92 1,021,595.92
Begesting 2x pakai m2 8.330 211,943.60 1,765,490.19
Besi beton polos U24 kg 191.047 12,930.04 2,470,250.52
Jumlah 5,257,336.63
19 Beton balok 20/30 m3 1.000
Beton K300 m3 1.000 1,021,595.92 1,021,595.92
Begesting 2x pakai m2 9.330 225,442.60 2,103,379.46
Besi beton polos U24 kg 55.956 12,930.04 723,507.57
Besi beton ulir U39 kg 104.000 13,245.04 1,377,484.16
Jumlah 5,225,967.11
20 Beton balok RB 20/30 m3 1.000
11/30
Jumlah
No. Uraian Pekerjaan Sat. Koef. Harga Satuan (Rp)
(Rp)
Beton K300 m3 1.000 1,021,595.92 1,021,595.92

12/30
Jumlah
No. Uraian Pekerjaan Sat. Koef. Harga Satuan (Rp)
(Rp)
Begesting 2x pakai m2 9.330 225,442.60 2,103,379.46
Besi beton polos U24 kg 55.956 12,930.04 723,507.57
Besi beton ulir U39 kg 104.000 13,245.04 1,377,484.16
Jumlah 5,225,967.11
21 Beton plat lantai t= 12 cm m3 1.000
Beton K300 m3 1.000 1,021,595.92 1,021,595.92
Begesting 2x pakai m2 8.333 255,847.30 2,132,060.83
Besi beton polos U24 kg 152.000 12,930.04 1,965,366.08
Besi beton ulir U39 kg 0.000 13,245.04 -
Jumlah 5,119,022.83
22 Beton topian t= 10 cm m3 1.000
Beton K225 m3 1.000 967,728.04 967,728.04
Begesting 2x pakai m2 10.000 255,847.30 2,558,473.00
Besi beton polos U24 kg 132.000 12,930.04 1,706,765.28
Besi beton ulir U39 kg 0.000 13,245.04 -
Jumlah 5,232,966.32
23 Beton plat lantai dasar t= 8 cm m3 1.000
Beton K225 m3 1.000 967,728.04 967,728.04
Begesting m2 0.100 86,377.70 8,637.77
Wire mesh M6 m2 12.500 63,090.00 788,625.00
Jumlah 1,764,990.81
VII. PEKERJAAN RANGKA ATAP DAN PENUTUP ATAP
1 Pemasangan Usuk Galvalum 7,5x3,5 cm t= 0,75 mm m2 1.000
Usuk Galvalum m1 3.000 19,600.00 58,800.00
Paku sekrup bh 6.000 600.00 3,600.00
Mandor OH 0.005 198,000.00 990.00
Kepala Tukang OH 0.001 134,400.00 134.40
Tukang OH 0.100 105,500.00 10,550.00
Pekerja OH 0.100 85,500.00 8,550.00
Jumlah 82,624.40
2 Pemasangan Reng Galvalum 3x4 cm t= 0,5 mm m2 1.000
Reng galvalum 3x4 cm t= 0,5 mm m1 4.000 8,400.00 33,600.00
Paku sekrup bh 10.000 600.00 6,000.00
Mandor OH 0.005 198,000.00 990.00
Kepala Tukang OH 0.001 134,400.00 134.40
Tukang OH 0.100 105,500.00 10,550.00
Pekerja OH 0.100 85,500.00 8,550.00
Jumlah 59,824.40

13/30
Jumlah
No. Uraian Pekerjaan Sat. Koef. Harga Satuan (Rp)
(Rp)
3 Lisplank Rangka Hollow 4x4 cm, t : 0,75 mm Kalsiplank m1 1.000
20 cm t= 12 mm
Hollow galvalum 4x4 cm t= 0,75 mm m1 2.600 17,900.00 46,540.00
Kalsiplank lebar 20 cm, t= 12 mm m1 1.100 21,400.00 23,540.00
Paku sekrup bh 6.000 600.000 6,000.00
Mandor OH 0.005 198,000.00 990.00
Kepala Tukang OH 0.020 134,400.00 2,688.00
Tukang OH 0.200 105,500.00 21,100.00
Pekerja OH 0.100 85,500.00 8,550.00
Jumlah 109,408.00
4 Pemasangan Genteng Exel Monier Flat m2 1.000
Genteng Monier Xl bh 10.000 8,900.00 89,000.00
Pekerja OH 0.150 85,500.00 12,825.00
Tukang OH 0.075 105,500.00 7,912.50
Kepala Tukang OH 0.008 134,400.00 1,075.20
Mandor OH 0.008 198,000.00 1,584.00
Jumlah 112,396.70
6 Pemasangan Talang Pembuluh Pipa PVC 3 " Tipe AW m 1.000
Pipa PVC 3" Tipe AW ljr 0.300 56,200.00 16,860.00
Pekerja OH 0.081 85,500.00 6,925.50
Tukang OH 0.135 105,500.00 14,242.50
Jumlah 38,028.00
VIII. PEKERJAAN PELAPIS LANTAI DAN DINDING
1 Pemasangan Keramik Lantai 20x20 cm m2 1.000
Semen PC 40 kg zak 0.233 56,700.00 13,211.10
Semen Berwarna kg 1.500 11,000.00 16,500.00
Pasir Pasang m3 0.045 169,100.00 7,609.50
Tegel Keramik 20x20 cm m2 1.068 74,600.00 79,695.18
Pekerja OH 0.700 85,500.00 59,850.00
Tukang Batu OH 0.350 109,300.00 38,255.00
Kepala Tukang Batu OH 0.035 133,200.00 4,662.00
Mandor OH 0.035 198,000.00 6,930.00
Jumlah 226,712.78
2 Pemasangan Lantai Keramik 40x40cm Unpolished m2 1.000
Keramik 40x40 cm unpolished m2 1.050 70,400.00 73,920.00
Semen kg 11.380 1,200.00 13,656.00
Pasir Pasang m2 0.045 169,100.00 7,609.50
Semen Warna kg 1.620 11,000.00 17,820.00
Pekerja OH 0.700 85,500.00 59,850.00
Tukang Batu OH 0.350 109,300.00 38,255.00
Kepala Tukang Batu OH 0.035 133,200.00 4,662.00
Mandor OH 0.035 198,000.00 6,930.00
Jumlah 222,702.50

14/30
Jumlah
No. Uraian Pekerjaan Sat. Koef. Harga Satuan (Rp)
(Rp)
3 Pemasangan Batu Alam Untuk Dinding Depan m2 1.000
batu alam andesit susun sirih Ukuran 5x40cm m2 1.050 75,650.00 79,432.50
Semen kg 11.380 1,200.00 13,656.00
Pasir Pasang m2 0.045 169,100.00 7,609.50
Semen Warna kg 1.620 11,000.00 17,820.00
Pekerja OH 0.700 85,500.00 59,850.00
Tukang Batu OH 0.350 109,300.00 38,255.00
Kepala Tukang Batu OH 0.035 133,200.00 4,662.00
Mandor OH 0.035 198,000.00 6,930.00
Jumlah 228,215.00
4 Pemasangan Step Noshing Tangga utama m1 1.000
Step Nosing kayu 3 x 240 cm bh 0.438 95,000.00 41,562.50
Pekerja OH 0.0250 85,500.00 2,137.50
Tukang kayu OH 0.0750 107,400.00 8,055.00
Kepala Tukang kayu OH 0.0075 136,800.00 1,026.00
Mandor OH 0.0013 198,000.00 257.40
Jumlah 53,038.40
5 Pasang Multiplek/Teakblock untuk Tangga utama t= 18 mm m2 1.000
Multiplek/Teakblock t= 18 mm (122X244 cm) lbr 0.350 280,000.00 98,000.00
Pekerja OH 0.0250 85,500.00 2,137.50
Tukang OH 0.0750 107,400.00 8,055.00
Kepala Tukang OH 0.0075 136,800.00 1,026.00
Mandor OH 0.0013 198,000.00 257.40
Jumlah 109,475.90
IX. PEKERJAAN KUSEN PINTU DAN JENDELA
1 Pemasangan Kusen Aluminium 4 " m 1.000
Kusen Aluminium 4 " X 1 3/4" m' 1.050 93,500.00 98,175.00
Skrup/ripet buah 1.000 500.00 500.00
Sealent tube 4.000 2,500.00 10,000.00
Pekerja OH 0.150 85,500.00 12,825.00
Tukang besi OH 0.250 105,500.00 26,375.00
Kepala Tukang besi OH 0.022 134,400.00 2,956.80
Mandor OH 0.025 198,000.00 4,950.00
Jumlah 155,781.80
2 Pemasangan Kusen Aluminium 3 " m 1.000
Kusen Aluminium 3 " X 1 3/4" m' 1.050 84,000.00 88,200.00
Skrup/ripet buah 1.000 500.00 500.00
Sealent tube 4.000 2,500.00 10,000.00
Pekerja OH 0.150 85,500.00 12,825.00
Tukang besi OH 0.250 105,500.00 26,375.00
Kepala Tukang besi OH 0.022 134,400.00 2,956.80
Mandor OH 0.025 198,000.00 4,950.00
Jumlah 145,806.80
3 Frame Daun Pintu Aluminium 4,5x6,5 cm (ambang atas) m 1.000
Frame Daun Pintu Aluminium 4,5x6,5 m 1.050 95,800.00 100,590.00
Karet Kusen Aluminium m 1.000 2,400.00 2,400.00
Skrup/ Rivet bh 4.000 500.00 2,000.00
Pekerja OH 0.150 85,500.00 12,825.00
Tukang OH 0.250 105,500.00 26,375.00
Kepala Tukang OH 0.022 134,400.00 2,956.80
Mandor OH 0.025 198,000.00 4,950.00
Jumlah 152,096.80

15/30
Jumlah
No. Uraian Pekerjaan Sat. Koef. Harga Satuan (Rp)
(Rp)
4 Frame Daun Pintu Aluminium 4,5x11 cm (ambang bwh) m 1.000
Frame Daun Pintu Aluminium 4,5x11 cm (amb bwh) m 1.050 92,300.00 96,915.00
Karet Kusen Aluminium m 1.000 2,400.00 2,400.00
Skrup/ Rivet bh 4.000 500.00 2,000.00
Pekerja OH 0.150 85,500.00 12,825.00
Tukang OH 0.250 105,500.00 26,375.00
Kepala Tukang OH 0.022 134,400.00 2,956.80
Mandor OH 0.025 198,000.00 4,950.00
Jumlah 148,421.80
5 Frame Daun Jendela Aluminium m 1.000
Frame Daun Jendela Aluminium m 1.050 89,700.00 94,185.00
Karet Kusen Aluminium m 1.000 2,400.00 2,400.00
Skrup/ Rivet bh 4.000 500.00 2,000.00
Pekerja OH 0.150 85,500.00 12,825.00
Tukang OH 0.250 105,500.00 26,375.00
Kepala Tukang OH 0.022 134,400.00 2,956.80
Mandor OH 0.025 198,000.00 4,950.00
Jumlah 145,691.80
6 Ventilasi aluminium uk. 1"x3 " m 1.000
Vebtilasi aluminium 1 "x 3 " m 1.050 24,000.00 25,200.00
Skrup/ Rivet bh 4.000 500.00 2,000.00
Pekerja OH 0.150 85,500.00 12,825.00
Tukang OH 0.150 105,500.00 15,825.00
Kepala Tukang OH 0.010 134,400.00 1,344.00
Mandor OH 0.020 198,000.00 3,960.00
Jumlah 61,154.00
7 Pasang Kaca polos t= 5 mm m2 1.000
Kaca polos t= 5 mm m2 1.050 85,600.00 89,880.00
Pekerja OH 0.015 85,500.00 1,282.50
Tukang OH 0.150 105,500.00 15,825.00
Kepala Tukang OH 0.015 134,400.00 2,016.00
Mandor OH 0.008 198,000.00 1,485.00
Jumlah 110,488.50
8 Pasang Kaca t= 6 mm m2 1.000
Kaca polos t= 6 mm m2 1.050 124,400.00 130,620.00
Pekerja OH 0.015 85,500.00 1,282.50
Tukang OH 0.150 105,500.00 15,825.00
Kepala Tukang OH 0.015 134,400.00 2,016.00
Mandor OH 0.008 198,000.00 1,485.00
Jumlah 151,228.50
9 Pasang Kaca Polos Tebal 8 mm m2 1.000
Kaca Tebal Polos 8mm m2 1.050 185,500.00 194,775.00
Pekerja OH 0.015 85,500.00 1,282.50
Tukang OH 0.150 105,500.00 15,825.00
Kepala Tukang OH 0.015 134,400.00 2,016.00
Mandor OH 0.008 198,000.00 1,485.00
Jumlah 215,383.50

16/30
Jumlah
No. Uraian Pekerjaan Sat. Koef. Harga Satuan (Rp)
(Rp)
10 Pasang Multiplek t= 12 mm m2 1.000
Multiplek t= 12 mm (122X244 cm lbr 0.350 175,400.00 61,390.00
Pekerja OH 0.0250 85,500.00 2,137.50
Tukang OH 0.0750 105,500.00 7,912.50
Kepala Tukang OH 0.0075 134,400.00 1,008.00
Mandor OH 0.0013 198,000.00 257.40
Jumlah 72,705.40
11 Pintu aluminium Type P1 (kelas)1600x2300mm unit 1.000
Kusen aluminium silver 4 " m1 7.900 155,781.80 1,230,676.22
Frame daun pintu 4,5x6,5 cm m1 10.620 152,096.80 1,615,268.02
Frame daun pintu 4,5x11 cm m1 1.240 148,421.80 184,043.03
Kaca polos 6 mm m2 2.300 151,228.50 347,825.55
Sealent m1 20.140 2,500.00 50,350.00
Full Handle set 2.000 318,000.00 636,000.00
Engsel steinlish stel 6.000 32,400.00 194,400.00
Lock case Cylinder set 1.000 178,200.00 178,200.00
Door Stoper set 2.000 32,400.00 64,800.00
Flush Bolt 12 " bh 1.000 64,200.00 64,200.00
Flush Bolt 6 " bh 1.000 43,600.00 43,600.00
Jumlah 4,609,362.82
12 Pintu aluminium Type P2 (R.guru)1000x2300mm unit 1.000
Kusen aluminium silver 4 " m1 6.500 155,781.80 1,012,581.70
Frame daun pintu 4,5x6,5 cm m1 7.210 152,096.80 1,096,617.93
Frame daun pintu 4,5x11 cm m1 0.770 148,421.80 114,284.79
Kaca polos 6 mm m2 1.435 151,228.50 217,012.90
Sealent m1 11.620 2,500.00 29,050.00
Lever Handle set 1.000 161,000.00 161,000.00
Engsel steinlish stel 3.000 32,400.00 97,200.00
Lock case Cylinder set 1.000 178,200.00 178,200.00
Door Stoper set 1.000 32,400.00 32,400.00
Jumlah 2,938,347.31
13 Pintu aluminium Type P3 (toilet)800x2300mm unit 1.000
Kusen aluminium silver 4 " m1 6.100 155,781.80 950,268.98
Frame daun pintu 4,5x6,5 cm m1 6.410 152,096.80 974,940.49
Frame daun pintu 4,5x11 cm m1 0.570 148,421.80 84,600.43
Multiplek t= 12 mm m2 2.344 72,705.40 170,421.46
HPL m2 2.716 69,800.00 189,576.80
Kaca polos 6 mm m2 0.140 151,228.50 21,171.99
Sealent m1 1.800 2,500.00 4,500.00
Lever Handle set 1.000 161,000.00 161,000.00
Engsel steinlish stel 3.000 32,400.00 97,200.00
Lock case Cylinder set 1.000 178,200.00 178,200.00
Door Stoper set 1.000 32,400.00 32,400.00
Jalusi 1"x3 " m1 1.940 61,154.00 118,638.76
Jumlah 2,982,918.90
14 Jendela Pintu aluminium Type JP1 (R.kelas lt1)2500x2300mm unit 1.000
Kusen aluminium silver 4 " m1 14.000 155,781.80 2,180,945.20
Frame daun pintu 4,5x6,5 cm m1 19.620 152,096.80 2,984,139.22
Frame daun pintu 4,5x11 cm m1 2.010 148,421.80 298,327.82
Multiplek t= 12 mm m2 3.115 72,705.40 226,477.32
HPL m2 3.115 69,800.00 217,427.00
Kaca polos 6 mm m2 2.250 151,228.50 340,264.13
Sealent m1 4.920 929,500.00 4,573,140.00
Handle Lock CH 400 Dekson set 3.000 67,800.00 203,400.00
Engsel Pivot set 3.000 335,000.00 1,005,000.00
Jumlah 12,029,120.68
15 Jendela aluminium Type J1 (R.guru)3550x2300mm unit 1.000
Kusen aluminium silver 4 " m1 11.700 155,781.80 1,822,647.06
Kaca polos 6 mm m2 7.150 151,228.50 1,081,283.78
Sealent m1 28.500 2,500.00 71,250.00
Jumlah 2,975,180.84
16 Jendela aluminium Type J2 (t.depan)3700x1400mm unit 1.000
Kusen aluminium silver 4 " m1 14.400 155,781.80 2,243,257.92
Frame daun jendela kaca m1 8.650 145,691.80 1,260,234.07
sliding window set set 1.000 450,000.00 450,000.00
Kaca polos 6 mm m2 3.700 151,228.50 559,545.45
Sealent m1 15.700 2,500.00 39,250.00
Stopper jendela geser set 2.000 52,000.00 104,000.00
Handle Lock CH 400 Dekson set 2.000 67,800.00 135,600.00
Jumlah 4,791,887.44
17 Jendela aluminium Type J3 (R.kelas lt2)2500x1400mm unit 1.000
17/30
Jumlah
No. Uraian Pekerjaan Sat. Koef. Harga Satuan (Rp)
(Rp)
Kusen aluminium silver 4 " m1 12.800 155,781.80 1,994,007.04
Frame daun jendela kaca m1 10.900 145,691.80 1,588,040.62
Kaca polos 6 mm m2 2.220 151,228.50 335,727.27
Sealent m1 15.140 2,500.00 37,850.00
casement 12" set 3.000 74,800.000 224,400.00
Handle Lock CH 400 Dekson set 3.000 67,800.00 203,400.00
Jumlah 4,383,424.93
X. PEKERJAAN RAILIING
1 PENGELASAN/FEBRIKASI DENGAN LAS LISTRIK CM 10.000
Kawat las listrik kg 0.400 38,200.00 15,280.00
Solar ltr 0.300 7,000.00 2,100.00
Minyak Pelumas ltr 0.040 30,000.00 1,200.00
Sewa Alat Welding Set (Min 5 jam) jam 0.170 50,000.00 8,500.00
Mandor OH 0.002 198,000.00 396.00
Tukang besi OH 0.020 105,500.00 2,110.00
Kepala Tukang besi OH 0.002 134,400.00 268.80
Pekerja OH 0.002 85,500.00 171.00
Jumlah 30,025.80
2 FEBRIKASI DAN PEMASANGAN PIPA BAJA (ELECTRODA) M1 1.000
Kawat las listrik kg 0.006 38,200.00 229.20
Solar ltr 0.005 7,000.00 31.50
Minyak Pelumas ltr 0.001 30,000.00 18.00
Sewa Alat Welding Set (Min 5 jam) jam 0.210 50,000.00 10,500.00
Mandor OH 0.002 198,000.00 396.00
Tukang besi OH 0.060 105,500.00 6,330.00
Kepala Tukang besi OH 0.006 134,400.00 806.40
Pekerja OH 0.028 85,500.00 2,394.00
Jumlah 20,705.10
3 FEBRIKASI DAN PASANG PIPA BESI HOLLOW 20.40 M1 1.000
Besi Hollow 20x40X2 MM m1 1.050 14,900.00 15,645.00
Pemasangan dan febrikasi m1 0.500 20,705.10 10,352.55
Jumlah 25,997.55
4 FEBRIKASI DAN PASANG PIPA BESI HOLLOW 40.40 M1 1.000
Besi Hollow 40x40X2,3 MM m1 1.050 17,900.00 18,795.00
Pemasangan dan febrikasi m1 0.900 20,705.10 18,634.59
Jumlah 37,429.59
5 Railing Tangga Utama m1 1.000

Kolom Railing Hollow 40x40x2,3 mm m1 61.500 37,429.59 2,301,919.79


Hollow 40x40x2,3 mm m1 7.580 37,429.59 283,716.29
Base Plate hollow 40x40 bh 35.000 63,900.00 2,236,500.00
Cat railing m2 11.053 23,029.36 254,538.91

Jumlah 5,076,674.99

18/30
Jumlah
No. Uraian Pekerjaan Sat. Koef. Harga Satuan (Rp)
(Rp)
6 Railing balkon m1 1.000
Untuk panjang reiling m1 20.640
Kolom Railing Hollow 150x150x4,5 mm bh 3.000 991,750.00 2,975,250.00
Kolom Railing Hollow 40x40x2,3 mm m1 33.300 37,429.59 1,246,405.35
Hollow 20x40x2 mm m1 20.640 25,997.55 536,589.43
Base Plate hollow 150x150 bh 13.000 191,700.00 2,492,100.00
Base Plate hollow 40x40 bh 37.000 63,900.00 2,364,300.00
Aksesoris Plat Railing Tangga Kaca 2-Sisi bh 50.000 85,000.00 4,250,000.00
Acrylic t= 8 mm m2 11.437 269,800.00 3,085,689.11
Cat railing m2 15.605 23,029.36 359,368.56
Jumlah 20,64 M 17,309,702.45
Jumlah 1 M 838,648.37
XI. PEKERJAAN PLAFOND
1 Pas. Plafond Gypsumboard 9 mm Rangka Hollow m2 1.000
Besi Hollow 40/40 m 0.750 17,900.00 13,425.00
Besi Hollow 20/20 m 2.000 7,900.00 15,800.00
Gypsum Board Uk. 240x120x9 mm lbr 0.382 92,400.00 35,287.56
Paku Asbes Skrup 4 bh 4.000 600.00 2,400.00
Pekerja OH 0.150 85,500.00 12,825.00
Tukang Kayu OH 0.250 107,400.00 26,850.00
Kepala Tukang Kayu OH 0.025 136,800.00 3,420.00
Mandor OH 0.075 198,000.00 14,850.00
Jumlah 124,857.56
2 Pemasangan List Aluminium siku m1 1.000
Lis aluminium siku m 1.050 11,400.00 11,970.00
Sekrup bh 4.000 600.00 2,400.00
Pekerja OH 0.050 85,500.00 4,275.00
Tukang Kayu OH 0.050 107,400.00 5,370.00
Kepala Tukang Kayu OH 0.005 136,800.00 684.00
Mandor OH 0.003 198,000.00 594.00
Jumlah 25,293.00
XII. PEKERJAAN CAT
1 Pengerjaan Cat Dinding Interior m2 1.000
Alkalin kg 0.120 28,500.00 3,420.00
Cat Tembok Interior klg 0.360 23,000.00 8,280.00
Pekerja OH 0.028 85,500.00 2,394.00
Tukang cat OH 0.042 76,300.00 3,204.60
Kepala Tukang cat OH 0.004 130,800.00 549.36
Mandor OH 0.003 198,000.00 495.00
Jumlah 18,342.96

19/30
Jumlah
No. Uraian Pekerjaan Sat. Koef. Harga Satuan (Rp)
(Rp)
2 Pengerjaan Cat Dinding Exterior m2 1.000
Alkalin kg 0.120 28,500.00 3,420.00
Cat Tembok Exterior klg 0.360 130,000.00 46,800.00
Pekerja OH 0.028 85,500.00 2,394.00
Tukang cat OH 0.042 76,300.00 3,204.60
Kepala Tukang cat OH 0.004 130,800.00 549.36
Mandor OH 0.003 198,000.00 495.00
Jumlah 56,862.96
3 Pengerjaan Cat besi m2 1.000
Cat besi kg 0.100 49,100.00 4,910.00
Kuas bh 0.010 10,500.00 105.00
Pekerja OH 0.020 85,500.00 1,710.00
Tukang cat OH 0.200 76,300.00 15,260.00
Kepala Tukang cat OH 0.004 130,800.00 549.36
Mandor OH 0.003 198,000.00 495.00
Jumlah 23,029.36
4 Pengerjaan Waterproofing m2 1.000
Water Proofing dan Scredding kg 0.350 44,100.00 15,435.00
Pekerja OH 0.050 85,500.00 4,275.00
Tukang cat OH 0.075 76,300.00 5,722.50
Kepala Tukang cat OH 0.008 130,800.00 981.00
Mandor OH 0.003 198,000.00 495.00
Jumlah 26,908.50

20/30
DAFTAR HARGA SATUAN BAHAN DAN UPAH
Update Periode 2017-2018

Kode Region I
No Uraian Bahan dan Tenaga Kerja Harga Satuan Satuan
1 2 3 4
A. BAHAN MENGGUNAKAN BESI/LOGAM
1 Besi Beton ulir BJTD-40 Rp. 10,900.00 per Kg
2 Besi Beton polos BJTP-24 Rp. 10,600.00 per Kg
3 Besi Siku Rp. 13,400.00 per Kg
4 Besi WF 200.100.5,5.8 Rp. 13,400.00 per Kg
5 Besi plat Rp. 13,500.00 per Kg
6 Besi Kanal C 150.50.50.3,2 Rp. 13,100.00 per Kg
7 Baut mur HTB A325O 5/8"X2 1/2 " Rp. 7,400.00 per bh
8 Baut angkur dia 19 mm - 60 cm Rp. 81,800.00 per bh
9 Baut keras Rp. 57,000.00 per bh
10 Base Plate steinlis dia 2 1/2 " Rp. 63,900.00 per bh
11 Suport Hand railing steinlis dia 2 1/2 " Rp. 56,000.00 per bh
12 Besi Hollow 20.20.2 MM Rp. 7,900.00 per m1
13 Besi Hollow 20.40.2 MM Rp. 14,900.00 per m1
14 Besi Hollow 40.40,2,3 MM Rp. 17,900.00 per m1
15 Besi Hollow 40.80.3,2 mm Rp. 22,900.00 per m1
16 Besi Hollow 75,75.3,8 mm Rp. 31,100.00 per m1
17 Pipa BSP dia 2 1/2 " Rp. 214,000.00 per m1
18 Pipa BSP dia 1 " Rp. 137,500.00 per m1
19 Pipa Steinlis Steel dia 2 1/2 " Rp. 381,500.00 per m1
20 Pipa Steinlis Steel dia 1 " Rp. 190,800.00 per m1
21 Elektrode Baja Rp. 38,200.00 per Kg
22 Kawat Bendrat Rp. 17,600.00 per Kg
23 Wire mesh M6 (210X495 cm) Rp. 428,000.00 per lbr
24 Pintu Pagar Besi Rp. 981,000.00 per m1
25 Tutup Manhole besi plat t 2 mm Rp. 514,100.00 per unit
26 Pipa udara Rp. 153,700.00 per Bh
B. BAHAN MENGGUNAKAN BATU, PASIR, PC
1 Pasir Beton Rp. 182,400.00 per m3
2 Pasir Pasang Rp. 169,100.00 per m3
3 Pasir Urug Rp. 136,800.00 per m3
4 Air Tawar Rp. 100.00 per lt
5 Semen Portland (1 zak = 50 Kg) Rp. 61,100.00 per zak
6 Semen Portland (1 zak = 50 Kg) Rp. 1,200.00 per Kg
7 Semen Portland (1 zak = 40 Kg) Rp. 56,700.00 per zak
8 Tasirtu Rp. 96,100.00 per m3
9 Batu bata merah Rp. 700.00 per bh
10 Batako 9 x 19 x 39 Rp. 2,300.00 per bh
11 Batu kali belah 15/20 Rp. 155,300.00 per m3
12 Batu pecah mesin 1/2 Rp. 271,200.00 per m3
13 Batu pecah mesin 2/3 Rp. 199,500.00 per m3

Page21/30
No Uraian Bahan dan Tenaga Kerja Harga Satuan Satuan
14 Batu kerikil (bulat 1-2 cm) Rp. 224,300.00 per m3
15 Beton panel ukuran 2400x400x40 Rp. 142,500.00 per m1
16 Koral beton 2/3 Rp. 210,500.00 per m3
17 Split 2/3 Pecah Mesin Rp. 189,000.00 per m3
18 Semen PC Warna Rp. 13,400.00 per Kg
19 Semen Berwarna Rp. 11,000.00 per Kg
20 Saluran beton precast U 30 cm Rp. 148,400.00 per m1
21 Saluran beton precast U 60 cm Rp. 305,100.00 per m1
22 Bak kontrol 40x40 cm Rp. 256,500.00 per m1
23 Bak kontrol 70x70 cm Rp. 324,500.00 per m1
24 Ijuk Rp. 19,100.00 per Kg
C BAHAN CAT/MINYAK/KUAS
1 Cat Besi Rp. 49,100.00 per Kg
2 Cat Kayu Rp. 49,300.00 per Kg
3 Cat Meni Besi Rp. 39,200.00 per Kg
4 Cat Tembok Interior Rp. 23,000.00 per Kg
5 Cat Tembok Exterior Rp. 130,000.00 per Kg
6 Amplas Rp. 4,300.00 per Lbr
7 Kuas Cat 3" Rp. 10,500.00 per Bh
8 Kuas Cat 6" Rp. 17,000.00 per Bh
9 Minyak Cat (Thiner A) Rp. 22,400.00 per ltr
10 Minyak begesting Rp. 7,100.00 per ltr
11 Minyak Pelumas Rp. 30,000.00 per ltr
12 Alkalin Rp. 28,500.00 per Kg
13 Solar Rp. 7,000.00 per ltr
14 Serat Fiber Rp. 9,500.00 per m2
15 Sealent Rp. 44,800.00 per tube
16 Oli Rp. 32,100.00 per ltr
17 Silicone sealant Rp. 6,200.00 per m1
18 Waterproof Rp. 44,100.00 per Kg
D BAHAN KAYU, TRIPLEK, MULTIPLEK
1 Kayu Meranti balok/usuk 5/7 Rp. 3,498,000.00 per m3
2 Kayu Meranti balok/usuk 6/15 Rp. 4,161,000.00 per m3
3 Kayu Meranti papan begesting (MC) Rp. 1,890,000.00 per m3
4 Kayu Meranti Papan 2/20,4/10 Rp. 6,382,500.00 per m3
5 Kayu Kamper (Slimar) Rp. 10,434,000.00 per m3
6 Kayu Kamper (Papan) Rp. 10,925,000.00 per m3
7 Kayu Kamper (Usuk) Rp. 10,120,000.00 per m3
8 Kayu Kamper Rp. 9,810,000.00 per m3
9 Kayu Dolken O 8- 10 Panjang 4 m1 Rp. 8,700.00 per btg
10 Kayu Gelam Ø 8 - 12 cm panjang : 4 m Rp. 15,000.00 per btg
11 Triplek tebal 4 mm uk 120x240 cm Rp. 65,400.00 per Lbr
12 HPL (122x244 cm) Rp. 208,700.00 per lbr
13 HPL Rp. 69,800.00 per m2
14 Multiplex 12 mm 120x240 Rp. 175,400.00 per Lbr
15 Multiplex 9 mm 120x240 Rp. 119,800.00 per Lbr
16 Multiplex 4mm 120x240 Rp. 64,800.00 per Lbr
17 Multiplex 6mm 120x240 Rp. 82,200.00 per Lbr
18 Lis Gypsum Rp. 27,600.00 per m

Page22/30
No Uraian Bahan dan Tenaga Kerja Harga Satuan Satuan
19 Lem Kayu Rp. 13,600.00 per Kg
E BAHAN PAKU, BAUT MUR, ANGKUR
1 Paku 2 s/d 5" Rp. 15,900.00 per Kg
2 Paku Asbes Rp. 17,300.00 per Kg
3 Paku Reng Rp. 15,900.00 per Kg
4 Paku Klem (No.4)/ Paku Usuk Rp. 16,700.00 per Kg
5 Angkur pintu besi Rp. 23,800.00 per Bh
6 Baut Skerup Rp. 1,100.00 per Bh
7 Paku Sekrup Rp. 600.00 per bh
8 Skrup/ Ripet Rp. 500.00 per Bh
9 Angkur Rp. 6,700.00 per Bh
10 Dinabolt M10 Rp. 3,400.00 per Bh
11 Paku triplek/Eternit Rp. 19,600.00 per Kg
F BAHAN PENUTUP ATAP
1 Seng Gelombang Uk.0,8x1,5 Rp. 56,000.00 per Lbr
2 Seng gelombang BJLS 30 (80 x 180 cm) Rp. 58,800.00 per Lbr
3 Seng BJLS 30 Rp. 88,000.00 per M2
3 Asbes gelombang kecil 105x250 cm Rp. 79,500.00 per Lbr
4 Genteng Ex Monier Xl Rp. 8,900.00 per bh
5 Wuwung Genteng Ex Monier Xl Rp. 10,300.00 per m
6 Kalsiboard EG Uk. 240x120x 6 mm Rp. 65,100.00 per Lbr
7 Gypsum Board Uk. 240x120x 9 mm Rp. 92,400.00 per Lbr
8 Kalsiplank lebar 20 cm t; 12 mm (panjang 3 m1) Rp. 67,200.00 per Lbr
9 Kalsiplank lebar 20 cm t; 12 mm ( Rp. 21,400.00 per m1
10 Usuk Galvalum 7,5x3,5 t= 0,75 mm Rp. 19,600.00 per m2
11 Reng Galvalum 3x4 cm t= 0,5 mm Rp. 8,400.00 per m1
G BAHAN KACA
1 Kaca Polos tebal 5 mm Rp. 85,600.00 per m2
2 Kaca Polos tebal 6 mm Rp. 124,400.00 per m2
3 Kaca Polos tebal 8 mm Rp. 185,500.00 per m2
4 Kaca Stopsol tebal 8 mm Rp. 593,600.00 per m2
5 Kaca Tempered Stopsol tebal 12 mm Rp. 1,312,500.00 per m2
6 Acrylic t = 8 mm Rp. 269,800.00 per m2
7 Plat steinlis penjepit Acrylic Rp. 27,300.00 per m1
8 Kaca Nako uk 15x80 cm tebal 5 mm + accesories Rp. 14,700.00 per Lbr
H BAHANG ENGSEL, GRENDEL, KUNCI, HANDLE
1 Casement 12 " Rp. 74,800.00 per bh
2 Fixed Top Pin Rp. 115,500.00 per set
3 Top Patch Fiiting Rp. 242,000.00 per set
4 Door Closer Rp. 333,000.00 per set
5 Door Stoper Rp. 32,400.00 per unit
6 Kunci Gembok Rp. 88,800.00 per Bh
7 Floor Hinge Rp. 1,356,000.00 per stel
8 Bottom Patch Fitting Rp. 169,500.00 per unit
9 Bottom Lock Fitting Rp. 201,300.00 per unit
10 Lockase case cylinder Rp. 178,200.00 per set
11 Lockase Window Bolt Rp. 156,800.00 per set
12 Flush Bolt 6 " Rp. 43,600.00 per Set
13 Flush Bolt 12 " Rp. 64,200.00 per Set

Page23/30
No Uraian Bahan dan Tenaga Kerja Harga Satuan Satuan
14 Engsel pintu steinlish 4x3x3 mm Rp. 32,400.00 per stel
15 Full Handle HS Pull Rp. 318,000.00 per stel
16 Full Handle Stainleesstel t= 60 cm Rp. 357,000.00 per stel
17 Full Handle Rp. 289,300.00 per stel
18 Lever Handle Rp. 161,000.00 per stel
19 Handle HDS DKS Rp. 135,000.00 per stel
20 Handle Lock Jendela Rp. 67,800.00 per stel
I BAHAN TIANG PANCANG
1 Mini pile □ 250 x 250 mm, panjang 12 m Rp. 148,200.00 per m1
2 Joint sambungan tiang pancang Rp. 33,600.00 per bh
J BAHAN ALUMINIUM
1 Aluminium kusen pintu & jendela 4"X1 3/4" Rp. 93,500.00 per m1
2 Aluminium kusen pintu & jendela 3"X1 3/4" Rp. 84,000.00 per m1
3 Aluminium frame daun jendela Rp. 89,700.00 per m1
4 Aluminium frame daun pintu 4,5x6,5 cm Rp. 95,800.00 per m1
5 Aluminium frame daun pintu 4,5x11 cm Rp. 92,300.00 per m1
6 Aluminium ventilasi 1 'x 3 " Rp. 24,000.00 per m1
7 Aluminium frame vison Rp. 43,600.00 per m1
8 Spigot aluminium Rp. 13,600.00 per m1
9 Aluminium Composit Panel (ACP) Rp. 179,200.00 per m2
10 Aluminium Composit Panel Perforeted 3 mm (ACP) Rp. 253,000.00 per m2
11 Karet Kusen Aluminium Rp. 2,400.00 per m1
12 Sielent Rp. 2,500.00 per m1
13 Lis plafond aluminium siku Rp. 11,400.00 per m1
14 Base Plate 8 mm Rp. 50,300.00 per m1
15 Angkur dinabolt Rp. 10,400.00 per bh
K BAHAN PELAPIS LANTAI DAN DINDING
1 Homogenous Tile 60x60 Rp. 184,000.00 per m2
2 Keramik 40x40 Polished Rp. 76,400.00 per m2
3 Keramik 40x40 Unpolished Rp. 70,400.00 per m2
4 Tegel Keramik Dinding 20x25 cm Rp. 73,100.00 per m2
5 Tegel Keramik Lantai 20x20 cm Rp. 74,600.00 per m2
6 Step Noshing 3x 8 cm Rp. 11,200.00 per bh
L. SANITAIR
1 Closet Duduk Rp. 2,175,600.00 per unit
2 Closet Jongkok Rp. 367,300.00 per unit
3 Wastafel Meja + kran Rp. 929,500.00 per unit
4 Toilet Sprayer Rp. 294,300.00 per bh
5 Floor Drain Rp. 247,500.00 per bh
6 Soap Holder Rp. 73,500.00 per bh
7 Paper Holder Rp. 86,300.00 per bh
8 Robe Hook Rp. 96,900.00 per bh
9 Kran Rp. 148,400.00 per bh
10 Kitchen Zink + Kran Rp. 677,300.00 per bh
11 Sambungan Pipa PVC 3" Tipe AW Rp. 10,600.00 per bh
12 Sambungan Pipa Tee 3" Tipe AW Rp. 15,000.00 per bh
13 Pipa Pvc dia 6 " Type AW Rp. 107,800.00 per M1
14 Pipa Pvc dia 3 " Type AW Rp. 56,200.00 per M1
13 Klem penggantung pipa Rp. 13,700.00 per bh

Page24/30
No Uraian Bahan dan Tenaga Kerja Harga Satuan Satuan
14 Floor drain 3 " Rp. 247,500.00 per bh
14 Rol TBA Rp. 9,600.00 per btg
15 Klem PVC Rp. 2,700.00 per bh
N. LAIN-LAIN
1 Sewa Direksikeet dan Gudang Rp. 1,798,500.00 per bln
2 Pengadaan Air kerja Rp. 787,500.00 per bln
M UPAH TENAGA KERJA
1 Pekerja Rp. 85,500.00 per hari
2 Tukang kayu Rp. 107,400.00 per hari
3 Kepala Tukang kayu Rp. 136,800.00 per hari
4 Tukang batu Rp. 109,300.00 per hari
5 Kepala Tukang Batu Rp. 133,200.00 per hari
6 Tukang besi Rp. 105,500.00 per hari
7 Kepala tukang besi Rp. 134,400.00 per hari
8 Tukang cat Rp. 76,300.00 per hari
9 Kepala tukang cat Rp. 130,800.00 per hari
10 Tukang listrik Rp. 73,500.00 per hari
11 Kepala tukang listrik Rp. 135,600.00 per hari
12 Mandor Rp. 198,000.00 per hari
13 Operator Rp. 100,700.00 per hari
14 Tukang Pipa Rp. 100,700.00 per hari
15 Tukang Las Rp. 99,800.00 per hari
N SEWA PERALATAN
1 Sewa alat bantu (1 set @3alat) Rp. 1,000.00 per jam
2 Sewa welding set (min 5 jam) Rp. 50,000.00 per hari
3 Sewa Crane Tiang pancang Rp. 125,000.00 per jam
4 Sewa Hammer Tiang Pancang Rp. 150,000.00 per jam
5 Sewa Tamper Rp. 100,000.00 per jam
6 Sewa Alat Bantu Strauss Pile Rp. 15,000.00 per jam
7 Sewa Crane 30 ton Rp. 130,000.00 per jam
8 Sewa Genset Rp. 60,000.00 per hari
10 Mobilisasi dan Demobilisasi Tenaga kerja Rp. 3,000,000.00 per ls
11 Mobilisasi dan Demobilisasi Tiang Pancang Rp. 15,000,000.00 per ls

Page25/30
HITUNGAN VOLUME

PEKERJAAN ARSITEKTUR

A PEKERJAAN ARSITEKTUR
I PEKERJAAN PERSIAPAN

- Luas lahan ( 8.00 x 18.50 )x 1 = 148.00 m2

II PEKERJAAN TANAH

1 Galian Tanah Biasa Sedalam 1m ( 7.13 x 16.00 + 24.74 x 0.4 ) = 123.91 m3

2 Urugan Tanah Kembali ( 7.13 x 16.00 ) = 114.02 m3

3 Buangan Tanah Galian ( 0.20 x 0.40 x 123.72 ) = 9.90 m3

III PEKERJAAN PASANGAN PONDASI

1 Urugan Pasir ( 0.14 x 16.00 ) = 2.30 m3

2 Beton Lantai Kerja 1:3:5 ( 0.07 x 16.00 + 24.74 x 0.05 ) = 2.39 m3

3 Beton PILE CAP ( 0.27 + 0.05 x 16.00 ) = 5.14 m3

IV PEKERJAAN PASANGAN DINDING TEMBOK

1 Pasangan bata 1:5 ( 44.25 x 2.70 + 60.25 x 3.125 - 12.46 = 303.30 m2

2 Lubang kusen 50.25 = 50.25 m2


Total Volume =============> = 253.05 m2
HITUNGAN VOLUME

PEKERJAAN ARSITEKTUR

3 Pasangan trasram 1:3 ( 44.25 x 0.30 ) = 13.28 m2

V PEKERJAAN PLESTERAN, BENANGAN DAN ACIAN

1 Plester Bata 1 : 3 ( 253.05 x 2 ) = 506.10 m2

2 Benangan Sudut 1:2 ( 2.70 x 14 + 3.125 x 3 ) = 47.18 m

3 Acian Beton ( 253.05 x 2 ) = 506.10 m2

VI PEKERJAAN BETON

1 Beton Rabat beton 1:3:5 ( 6.49 x 0.1 ) = 0.65 m3

2 Beton Sloof 20/40 ( 77.95 x 0.08 ) = 6.24 m3

3 Beton Sloof 15/20 ( 43.52 x 0.03 ) = 1.31 m3

4 Beton Kolom 15/40 ( 0.06 x 5.83 x 17 ) = 5.95 m3

5 Beton Kolom praktis 15/15 ( 0.02 x 5.83 x 6 ) = 0.79 m3

6 Beton Balok Latai dan ring balk 15/15 ( 0.02 x 84.875 ) = 1.91 m3

7 Beton Plat anak tangga dan bordes tangga ( 0.69 + 0.684 + 0.012 ) = 1.39 m3
HITUNGAN VOLUME

PEKERJAAN ARSITEKTUR
8 Beton balok 20/30 ( 0.06 x 74.75 ) = 4.49 m3

9 Beton balok RB 20/30 ( 0.06 x 74.75 ) = 4.49 m3

10 Beton plat lantai t= 12 cm ( 120.11 x 0.12 ) = 14.41 m3

11 Beton topian t= 10 cm ( 3.80 x 0.1 ) = 0.38 m3

12 Beton plat lantai dasar t= 8 cm ( 128.20 x 0.08 ) = 10.26 m3

VII PEKERJAAN RANGKA ATAP DAN PENUTUP ATAP

1 Pemasangan Usuk Galvalum 7,5x3,5 cm t= 0,75 mm ( 112.13 + 61.25 + 11.55 ) = 184.93 m2

2 Pemasangan Reng Galvalum 3x4 cm t= 0,5 mm ( 112.13 + 61.25 ) = 173.38 m2

3 Lisplank Rangka Hollow 4x4 cm, t : 0,75 mm Kalsiplank ( 24.00 + 21 ) = 45.00 m

4 Pemasangan Genteng Exel Monier Flat ( 112.13 + 61.25 ) = 173.38 m2

5 Pemasangan Talang Pembuluh Pipa PVC 3 " Tipe AW ( 24.00 ) = 24.00 m

VIII PEKERJAAN PELAPIS LANTAI DAN DINDING

1 Pemasangan Keramik Lantai 20x20 cm (Toilet) ( 11.72 x 1.00 ) = 11.72 m2

2 Pemasangan Lantai Keramik 40x40cm Unpolished (4 R. kelas, 1 R. kantor, 2 selasar) ( 210.79 x 1.00 ) plint 10cm ( 82.2 x 0.1 = 219.01 m2
HITUNGAN VOLUME

PEKERJAAN ARSITEKTUR
3 Pemasangan Batu Alam Untuk Dinding Depan ( 13.79 x 1 ) = 13.79 m2

4 Pemasangan Step Noshing Tangga utama ( 1 x 20 ) = 20.00 m

5 Pemasangan Teakblock untuk anak tangga t=18mm ( 5.40 + 2.1 + 3 ) = 10.50 m2

IX PEKERJAAN KUSEN PINTU DAN JENDELA

1 Pintu aluminium Type P1 (kelas)1600x2300mm 4.00 = 4.00 Unit

2 Pintu aluminium Type P2 (R.guru)1000x2300mm 1.00 = 1.00 Unit

3 Pintu aluminium Type P3 (toilet)800x2300mm 1.00 = 1.00 Unit

4 Jendela Pintu aluminium Type JP1 (R.kelas lt1)2500x2300mm 2.00 = 2.00 Unit

5 Jendela aluminium Type J1 (R.guru)3550x2300mm 1.00 = 1.00 Unit

6 Jendela aluminium Type J2 (t.depan)3700x1400mm 1.00 = 1.00 Unit

7 Jendela aluminium Type J3 (R.kelas lt2)2500x1400mm 2.00 = 2.00 Unit

X PEKERJAAN RAILIING

1 Railing Tangga Utama 1.00 = 1.00 set

2 Railing balkon 20.64 = 20.64 m


HITUNGAN VOLUME

PEKERJAAN ARSITEKTUR
XI PEKERJAAN PLAFOND

1 Pas. Plafond Gypsumboard 9 mm Rangka Hollow (4 R. kelas, 1 R. kantor, 2 selasar ( 220.16 x 1.00 ) = 220.16 m2
toilet)
2 Pemasangan List Aluminium siku (4 R. kelas, 1 R. kantor, 2 selasar ( 85.90 + 19.40 + 96.85 + 5.40 ) = 207.55 m
toilet)
XII PEKERJAAN CAT

1 Pengerjaan Cat Dinding Interior (2 R. kelas, 1 toilet, 2 R. kelas ( 84.78 + 9.99 + 98.13 + 60.625 ) = 253.52 m2
1 kantor)
2 Pengerjaan Cat Dinding Exterior selasar ( 65.14 + 88.28 ) = 153.42 m2

3 Pengerjaan Waterproofing (Toilet) ( 1.57 ) = 1.57 m2