Anda di halaman 1dari 2

RENCANA ANGGARAN BIAYA (RAB)

PEMBANGUNAN RUMAH SATU LANTAI TYPE 36/72


PERUMAHAN BUMI SANGKURIANG RESIDENCE

NO URAIAN PEKERJAAN SPESIFIKASI VOL SAT BOBOT H. SATUAN JUMLAH


I PEKERJAAN PERSIAPAN
1 Persiapan Kerja 1,00 Ls 1.275.000 1.275.000
2 Persiapan air bersih 1,00 Ls 175.000 175.000
Sub Total I 1.450.000
II PEK. TANAH & PONDASI
1 Galian tanah pondasi 21,39 m3 102.000 2.181.780
2 urugan kembali (fill) 3,60 m3 75.250 270.900
3 urugan pasir 3cm 1,70 m3 180.200 306.340
4 pondasi batu kali 1 pc : 5 ps (tinggi 60 cm) 14,26 m3 637.500 9.090.750
5 septictank + rembesan P.2 cm L. 1cm T. 1.5 cm ( sumur) 1,00 unit 3.825.000 3.825.000
6 pipa air kotor PVC wavin D.4" + fitting 6,00 m' 161.500 969.000
7 pipa air bersih PCV wavin D. 3" + fitting 10,00 m' 140.250 1.402.500
Sub Total II 18.046.270
III PEK. PASANGAN & BETON
1 Sloof beton bertulang U.15/20 (besi full.10mm ring 8mm) 2,14 m3 2.337.500 5.002.250
2 dinding hebbel U.10 cm pas. 1:2:3 164,26 m2 63.750 10.471.575
3 kolom praktis beton bertulang U. 8/8 (besi Full 10mm ring 6mm) 1,63 m3 2.337.500 3.810.125
4 ringbalk beton bertulang U. 25/15 (besi Full 12mm ring 8mm) 0,92 m3 2.337.500 2.150.500
5 beton kanopi teras 0,49 m3 2.337.500 1.145.375
6 plesteran dinding dan dinding aci 1 pc : 5 ps 263,08 m2 55.250 14.535.170
7 pasangan pipa listrik 9,00 unit 11.475 103.275
8 groof tampak depan di profile 3,57 m2 102.000 364.140
9 pas. Batu alam dengan tali air t.7 cm 2,70 m2 127.500 344.250
Sub Total III 37.926.660
IV PEKERJAAN ATAP
1 rangka baja ringan U. 0.75 P.6m 51,40 m2 97.750 5.024.350
2 penutup atap genteng beton flet mutiara 51,40 m2 94.500 4.857.300
3 nok genteng 7,00 m' 45.000 315.000
4 listplank GRC U. 8x 200mm 19,49 m' 21.675 422.446
5 ban flashing penutup genteng 15,99 m' 29.750 475.703
Sub Total IV 11.094.798
V PEKERJAAN PLAFOND
1 plafond gypsum rangka hollo hollo 4x4 galvanize. Gypsum elephant 48,20 m2 106.250 5.121.250
2 list tepi plafond profile gypsum list T. 8cm 63,25 m' 12.750 806.438
Sub Total V 5.927.688
VI PEKERJAAN LANTAI
1 stemper tanah 72,00 m2 29.750 2.142.000
2 urugan pasir 3cm 3,60 m3 180.200 648.720
3 keramik lantai U. 60 x 60 granit (setara) 34,00 m2 178.500 6.069.000
4 keramik lantai KM/WC U.25 x25 merk. Roman (setara) 3,00 m2 148.750 446.250
5 keramik dinding KM U. 25 x40 merk. Roman (setara) 17,00 m2 157.250 2.673.250
6 keramik lantai dapur U.25 x25 merk. Roman (setara) 2,00 m2 148.750 297.500
7 keramik dinding dapur U. 25 x40 merk. Roman (setara) 2,00 m2 157.250 314.500
Sub Total VI 12.591.220
VII INSTALASI & SANITASI
1 titik lampu ex broco 9,00 Ttk 208.250 1.874.250
2 titik stop kontak ex broco 4,00 Ttk 89.250 357.000
3 saklar single ex broco 3,00 Ttk 89.250 267.750
4 saklar doble ex broco 3,00 Ttk 102.000 306.000
5 titik AC ex broco 1,00 Ttk 114.750 114.750
6 titik antena ex broco 1,00 Ttk 89.250 89.250
7 Box sekering presto + NCB 1,00 Ttk 212.500 212.500
8 floor drain steinlis 1,00 bh 102.000 102.000
9 closed duduk ex. American standar 1,00 bh 2.295.000 2.295.000
10 kran air dia.1/2" ex lokal 2,00 bh 144.500 289.000
11 kitchen sink Merek royal P.99xl.45 x T.15 1,00 bh 297.500 297.500
12 keran angsa Wasser TL2-040 leher angsa sink 1,00 bh 289.000 289.000
13 pipa air bersih PVC wavin d.3/4" AW+ fitting 19,00 m' 41.650 791.350
14 pipa air bersih PVC wavin d. 1/2" AW + fitting 19,00 m' 21.845 415.055
Sub Total VII 7.700.405
VIII PEK KUSEN & PENGGANTUNG
1 kusen pintu & jendela alumuniun U. 4" (Coklat) 44,00 m' 233.750 10.285.000
2 daun pintu utama & belakang Doble Triplex Finishing finil kayu 2,00 bh 2.252.500 4.505.000
3 daun pintu kamar alumunium Finishing Spandrel 2,00 bh 1.572.500 3.145.000
4 daun pintu KM PVC platindo + kunci KM 1,00 bh 382.500 382.500
5 daun jendela U. 50 x 135 alumunium + kaca 7,00 bh 807.500 5.652.500
6 kaca polos T. 5mm (kaca mati) 0,79 m2 151.300 119.527
7 kunci pintu utama silinder merk Royal 1,00 bh 297.500 297.500
8 kunci pintu kamar silinder merk Royal 2,00 bh 272.000 544.000
9 kunci pintu belakang silinder merk Royal 1,00 bh 272.000 272.000
10 engsel pintu U. 4" 4,00 Set 170.000 680.000
Sub Total VIII 25.883.027
IX PEKERJAAN PENGECATAN
1 pengecatan dinding dalam ex. Catylax 124,53 m2 23.800 2.963.814
2 pengecatan dinding luar ex. Dulux 78,65 m2 27.200 2.139.280
3 pengecatan dinding luar groof ex. Dulux 4,57 m2 29.750 135.958
4 cat lisplank ex. Catylax 3,89 m2 28.900 112.421
5 pengecatan plafond ex. Catylax 48,20 m2 22.950 1.106.190
6 cat list plafon ex. Catylax 63,25 m1 11.900 752.675
Sub Total IX 7.210.338
X PEKERJAAN LAIN-LAIN
1 pembersihan hasil pekerjaan 1,00 ls 1.500.000 1.500.000
2 pas.hebbel pagar belakang 13,52 m2 75.000 1.014.000
3 pas.pelester+aci 15,20 m2 65.000 988.000
4 pas. Cat pagar belaang 15,20 m2 32.000 486.400
5 Carport depan 12,20 m2 120.000 1.464.000
Sub Total X 5.452.400
0,00
Jumlah biaya langsung 133.282.805
Dibulatkan 133.280.000
Terbilang : Seratus tiga puluh tiga juta dua ratus delapan puluh ribu rupiah

Majalengka, 10 Januari 2020


PT. TRIBUN NACITRA ASRI

M Ihwan Budiman Yayuk Handayani


Konsultan Pengawas Direktur