HARGA
NO JENIS PEKERJAAN SAT VOL SATUAN JML HARGA
I. PEKERJAAN PERSIAPAN
1 Sewa mobil crane Unit 1.00 7,500,000.00 7,500,000
2 Sewa Forklift By Owner
3 Air Kerja By Owner
4 Listrik Kerja By Owner
5 Kontainer mentah Unit 2.00 25,000,000.00 50,000,000
6 Mobilisasi Kontainer Unit 2.00 By Owner
Total I 57,500,000
II. PEKERJAAN KONTAINER LANTAI 1
A. PEKERJAAN STRUKTUR
1 Pek. Galian pondasi bantalan kontainer ttk 6.00 65,000 390,000
3
2 Pek. Cor bantalan kontainer 40x40 kedalaman 140 cm ( 1 titik) m 0.22 3,325,000 744,800
3
3 Pek. Cor bantalan kontainer 40x40 kedalaman 80 cm ( 5 Titik) m 0.64 3,325,000 2,128,000
Total A 3,262,800
B. PEKERJAAN FINISHING
1 Pek. Lantai keramik 40x40 cm m2 15.00 185,000 2,775,000
2
2 Pek. Plafond gypsum m 15.00 115,000 1,725,000
3 Pek. List Plafond m¹ 16.90 27,000 456,300
2
4 Pek. Dinding triplek 6 mm Double m 31.10 165,000 5,131,500
5 Pek. Dinding Partisi Penyekat ruang toko dan mess m2 6.37 215,000 1,369,550
6 Pek. Cat minyak kulit jeruk m2 43.84 35,000 1,534,400
7 Pek. Cat tembok u/ plafond Ex' Vinilex m2 15.00 22,000 330,000
2
8 Pek. Cat minyak bagian luar m 43.84 35,000 1,534,400
2
9 Pek. Potong dan openingan u/ pintu & Jendela m 29.60 135,000 3,996,000
11 Pek Pintu dan Jendela
- PU-01 - 1 X 2,1 unit 2.00 2,800,000 5,600,000
- JA-01 - 2,1 X 2 + 1 Daun unit 1.00 4,000,000 4,000,000
- JA-02 - 2,1 X 2 unit 1.00 4,000,000 4,000,000
- JA-03 - 1 X1,4 unit 1.00 2,000,000 2,000,000
Total B 32,452,150
C. PEKERJAAN ELEKTRIKAL
1 Pek. Pasang Box MCB Komplit M6 Bh 1.00 750,000.00 750,000.00
2 Pek. Tarik Kabel Tufur m¹ 50.00 135,000.00 6,750,000.00
3 Pek. Instalasi Penerangan ttk 2.00 285,000.00 570,000.00
4 Pek. Pasangan saklar ttk 1.00 85,000 85,000.00
5 Pek. Lampu Philips ttk 2.00 145,000 290,000.00
6 Pek. Instalasi Stop Kontak ( 1 di toko , 1 di mess) ttk 2.00 285,000 570,000
7 Pek. Pasangan stop Kontak ttk 2.00 85,000 170,000
8 Pek. Intalasi Stop kontak AC ttk 1.00 285,000 285,000
9 Pek. Pipa refrigent m¹ 6.00 125,000 750,000
10 Pek. Drain Ac m¹ 3.00 35,000 105,000
Total C 10,325,000
Total II 46,039,950
HARGA
NO JENIS PEKERJAAN SAT VOL SATUAN JML HARGA
HARGA
NO JENIS PEKERJAAN SAT VOL JML HARGA
SATUAN
I. PEKERJAAN PERSIAPAN
1 Sewa mobil crane Unit 1.00 7,500,000.00 7,500,000
2 Air Kerja By Owner
3 Listrik Kerja By Owner
4 Kontainer mentah Unit 2.00 25,000,000.00 50,000,000
5 Mobilisasi Kontainer Unit 2.00 By Owner
Total I 57,500,000
II. PEKERJAAN KONTAINER LANTAI 1
A. PEKERJAAN STRUKTUR
1 Pek. Galian pondasi bantalan kontainer ttk 6.00 65,000 390,000
3
2 Pek. Cor bantalan kontainer 40x40 kedalaman 140 cm ( 1 titik) m 0.22 3,325,000 744,800
3
3 Pek. Cor bantalan kontainer 40x40 kedalaman 80 cm ( 5 Titik) m 0.64 3,325,000 2,128,000
Total A 3,262,800
B. PEKERJAAN FINISHING
1 Pek. Lantai keramik 40x40 cm m2 15.00 185,000 2,775,000
2 Pek. Plafond gypsum m2 15.00 115,000 1,725,000
3 Pek. List Plafond m¹ 16.90 27,000 456,300
2
4 Pek. Dinding triplek 6 mm Double m 31.10 165,000 5,131,500
2
5 Pek. Dinding Partisi Penyekat ruang toko dan mess m 6.37 215,000 1,369,550
2
6 Pek. Cat minyak kulit jeruk m 43.84 35,000 1,534,400
7 Pek. Cat tembok u/ plafond Ex' Vinilex m2 15.00 22,000 330,000
2
8 Pek. Cat minyak bagian luar m 43.84 35,000 1,534,400
2
9 Pek. Potong dan openingan u/ pintu & Jendela m 29.60 135,000 3,996,000
Total B 18,852,150
C. PEKERJAAN ELEKTRIKAL
1 Pek. Pasang Box MCB Komplit M6 Bh 1.00 750,000.00 750,000.00
2 Pek. Tarik Kabel Tufur m¹ 50.00 135,000.00 6,750,000.00
3 Pek. Instalasi Penerangan ttk 2.00 285,000.00 570,000.00
4 Pek. Pasangan saklar ttk 1.00 85,000 85,000.00
5 Pek. Lampu Philips ttk 2.00 145,000 290,000.00
6 Pek. Instalasi Stop Kontak ttk 1.00 285,000 285,000
7 Pek. Pasangan stop Kontak ttk 1.00 85,000 85,000
8 Pek. Intalasi Stop kontak AC ttk 1.00 285,000 285,000
9 Pek. Pipa refrigent m¹ 6.00 125,000 750,000
10 Pek. Drain Ac m¹ 3.00 35,000 105,000
Total C 9,955,000
Total II 32,069,950
III. KONTAINER LANTAI 2
B. PEKERJAAN FINISHING
1 Pek. Lantai keramik 40x40 cm m2 15.00 185,000 2,775,000
2
2 Pek. Plafond gypsum m 15.00 115,000 1,725,000
3 Pek. List Plafond m¹ 16.90 27,000 456,300
2
4 pek. Dinding triplek 6 mm m 31.35 165,000 5,172,750
5 Pek. Cat minyak kulit jeruk m2 31.35 35,000 1,097,250
HARGA
NO JENIS PEKERJAAN SAT VOL JML HARGA
SATUAN
HARGA
NO JENIS PEKERJAAN SAT VOL JML HARGA
SATUAN
I. PEKERJAAN KONTAINER
A. PEK. PINTU DAN JENDELA LANTAI 1
1 - PU-01 - 1 X 2,1 unit 2.00 2,800,000 5,600,000
2 - JA-01 - 2,1 X 2 + 1 Daun unit 1.00 4,000,000 4,000,000
3 - JA-02 - 2,1 X 2 unit 1.00 4,000,000 4,000,000
4 - JA-03- 1 X 1,4 unit 1.00 2,000,000 2,000,000
Total A 15,600,000
B. PEK. PINTU DAN JENDELA LANTAI 2
1 - PU-01 - 1 X 2,1 unit 1.00 2,800,000 2,800,000
2 - JA-01 - 2,1 X 2 + 1 Daun unit 1.00 4,000,000 4,000,000
3 - JA-04 - 2,1 X 2 unit 1.00 4,000,000 4,000,000
4 - JA-05 - 0,5 X 5,7 unit 1.00 7,000,000 7,000,000
Total B 17,800,000
Total I 33,400,000
II. PEKERJAAN TOILET & DAPUR
A. PEK. PINTU DAN JENDELA TOILET
1 - PVC-02 - 0,9 X 2,1 unit 1.00 950,000 950,000
2 - BV-01 - 0,4X 0,6 unit 1.00 1,100,000 1,100,000
Total A 2,050,000
PEK. PINTU DAN JENDELA DAPUR
1 PU-02 -2 x2,1 ( 4 daun pintu lipat) Unit 1.00 6,000,000 6,000,000
2 JA-06 - 2 X 0,6 + 1 daun Unit 1.00 2,500,000 2,500,000
3 JA-07 - 1,8 X 0,5 + 1 daun Unit 1.00 1,500,000 1,500,000
Total B 10,000,000
Total II 12,050,000
GRAND TOTAL 45,450,000
DIBULATKAN 45,450,000
Note: ini Rab pintu dan jendela dalam pekerjaan Kontainer tahap Jakarta,07 Juli 2020
Pemborong,
MAMAT
RENCANA ANGGARAN BIAYA
HARGA
NO JENIS PEKERJAAN SAT VOL JML HARGA
SATUAN
I. PEKERJAAN PERSIAPAN
1 Air Kerja By Owner
2 Listrik Kerja By Owner
3 Bedeng By Owner
Note: Luas area (halaman depan, belakang, tangga outdoor lantai 2 dan dapur) Jakarta,07 Juli 2020
16+8+24+5+5,7= 58,7 Pemborong,
Harga Per/m²
Rp. 151.701.000 / 58,7 m²
Rp.2.584.344
MAMAT
RENCANA ANGGARAN BIAYA
HARGA
NO JENIS PEKERJAAN SAT VOL JML HARGA
SATUAN
I. PEKERJAAN PERSIAPAN
1 Air Kerja By Owner
2 Listrik Kerja By Owner
3 Bedeng By Owner
Note: Luas area yang dikerjakan (Perkerasan Beton,48,5+31)=79,5 m² Jakarta,07 Juli 2020
Harga Per/m² = Rp. 49.647.750 / 79,5 = Rp. 624500 Pemborong,
PEKERJAAN : PAGAR
LOKASI : PARAMOUNT
HARGA
NO JENIS PEKERJAAN SAT VOL JML HARGA
SATUAN
I. PEKERJAAN PERSIAPAN
1 Air Kerja By Owner
2 Listrik Kerja By Owner
3 Bedeng By Owner
Total I
II. PEKERJAAN BUIS BETON
1 Pek. Galian buis beton m¹ 115.00 75,000 8,625,000
2 Pek. Pasang buis beton m¹ 115.00 150,000 17,250,000
Total II 25,875,000
II. PEKERJAAN PAGAR DEPAN
A. PEKERJAAN STRUKTUR
1 Pek. Galian pondasi dudukan brc depan (tanpa sloof) ttk 5.00 65,000 325,000
3
2 Pek. Cor pondasi dudukan brc depan 20x20x120 m 0.24 3,325,000 798,000
3 Pek. Galian Pondasi Tapak (60x60x60) ttk 11.00 65,000 715,000
3
4 Pek. Cor Pondasi tapak 30x30x20 m 0.20 3,325,000 658,350
5 Pek. Galian sloof 30x30 m¹ 29.60 25,000 740,000
3
6 Pek. Cor sloof 15x15 m 0.67 3,325,000 2,214,450
3
7 Pek. Cor kolom 15x15 m 0.25 3,325,000 822,938
Total A 6,273,738
B. PEKERJAAN PINISHING ( tanpa cat )
1 Pek. Pasang dinding bata merah m2 29.60 125,000 3,700,000
2
2 Pek. Plester & aci m 59.20 88,400 5,233,280
3 Pek. Pintu Gerbang depan Hollow 5x5 dan 4x4 m¹ 16.90 27,000 456,300
2
4 Pek. Dinding triplek 6 mm Double m 31.10 165,000 5,131,500
5 Pek. Dinding Partisi Penyekat ruang toko dan mess m2 6.37 215,000 1,369,550
2
6 Pek. Cat minyak kulit jeruk m 43.84 35,000 1,534,400
2
7 Pek. Cat tembok u/ plafond Ex' Vinilex m 59.20 22,000 1,302,400
2
8 Pek. Cat minyak bagian luar m 43.84 35,000 1,534,400
2
9 Pek. Potong dan openingan u/ pintu & Jendela m 29.60 135,000 3,996,000
Total B 24,257,830
Total B #REF!
Total III #REF!
GRAND TOTAL #REF!
DIBULATKAN #REF!
PEKERJAAN : PAGAR
LOKASI : PARAMOUNT
HARGA
NO JENIS PEKERJAAN SAT VOL JML HARGA
SATUAN
I. PEKERJAAN PERSIAPAN
1 Pek. Listrik Kerja ( Tunggu Pln Masuk ) By Owner
2 Air Kerja By Owner
3 Pek. Mobilisasi Pekerja Ls 1.00 5,000,000.00 5,000,000.00
4 Pek. Bedeng dan Gudang (tunggu kontainer) By Owner
5 Pek. Pagar Pengaman (Bila dibutuhkan) By Owner
6 Pek. Bongkar muat material ( Bila Ada) By Owner
Total I 5,000,000
II. PEKERJAAN BUIS BETON
1 Pek. Galian buis beton m¹ 115.00 75,000 8,625,000
2 Pek. Pasang buis beton m¹ 115.00 150,000 17,250,000
Total II 25,875,000
III. PEKERJAAN PAGAR DEPAN
A. PEKERJAAN STRUKTUR
1 Pek. Galian pondasi Tapak 70x70x60 ttk 13.00 65,000 845,000
3
2 Pek. Cor Pondasi tapak 30x30x20 m 0.23 3,325,000 778,050
3 Pek. Galian sloof 30x30 m¹ 29.60 25,000 740,000
4 Pek. Cor sloof 15x15 m3 0.67 3,325,000 2,214,450
5 Pek. Cor kolom 15x15 t : 1 meter m3 0.29 3,325,000 972,563
Total A 5,550,063
B. PEKERJAAN FINISHING ( tanpa cat )
1 Pek. Pasang dinding bata merah t : 1 meter m2 29.60 125,000 3,700,000
2 Pek. Plester & aci m2 49.20 88,400 4,349,280
3 Pek. Pintu Akses Pejalan kaki ( P: 2 m , T : 1m) m2 2.00 600,000 1,200,000
2
4 Pek. Pintu Gerbang depan Hollow 5x5 dan 4x4 ( P: 4.4 m, T : 1 m) m 4.40 600,000 2,640,000
2
5 Pek. Rel dan Bantalan beton Pintu gerbang m 4.40 426,000 1,874,400
( Tebal 25x cm / Lebar 40 cm /Panjang 4,7 )
Total B 13,763,680
Total III 19,313,743
GRAND TOTAL 50,188,743
DIBULATKAN 50,188,000
Note: Panjang Pagar + pintu Hollow ( 29,6 + 4,7+2)tinggi 1 meter = 36 Jakarta,13 Juli 2020
Harga Per/m² Pemborong,
Rp. 19.313.743/ 36 m²
Rp.536.493
Harga Per/m² diatas tidak termasuk Item pekerjaan Persiapan
dan Pekerjaan Buis Beton MAMAT
PEKERJAAN : PAGAR
LOKASI : PARAMOUNT
HARGA
NO JENIS PEKERJAAN SAT VOL JML HARGA KETERANGAN
SATUAN
I. PEKERJAAN PERSIAPAN
1 Pek. Listrik Kerja ( Tunggu Pln Masuk ) By Owner
2 Air Kerja By Owner
3 Pek. Mobilisasi Pekerja Ls 1.00 5,000,000.00 5,000,000.00
4 Pek. Bedeng dan Gudang (tunggu kontainer) By Owner
5 Pek. Pagar Pengaman (Bila dibutuhkan) By Owner
6 Pek. Bongkar muat material ( Bila Ada) By Owner
Total I 5,000,000
II. PEKERJAAN BUIS BETON
1 Pek. Galian buis beton m¹ 115.00 75,000 8,625,000
2 Pek. Pasang buis beton m¹ 115.00 150,000 17,250,000
Total II 25,875,000
III. PEKERJAAN PAGAR DEPAN
A. PEKERJAAN STRUKTUR
1 Pek. Galian pondasi Tapak 70x70x60 ttk 13.00 65,000 845,000
2 Pek. Cor Pondasi tapak 30x30x20 m 3
0.23 6,733,550 1,575,651 Rp121,204 Per/titik
3 Pek. Galian sloof 30x30 m¹ 29.60 25,000 740,000
4 Pek. Cor sloof 15x15 m3 0.67 5,626,250 3,747,083 Rp126,591 Per/ 1m
5 Pek. Cor kolom 15x15 t : 1 meter m3 0.29 6,865,650 2,008,203 Rp154,477 Per/ titik
Total A 8,915,936
B. PEKERJAAN FINISHING ( tanpa cat )
1 Pek. Pasang dinding bata merah t : 1 meter m2 29.60 125,000 3,700,000
2 Pek. Plester & aci m2 49.20 88,400 4,349,280
2
3 Pek. Pintu Akses Pejalan kaki ( P: 2 m , T : 1m) m 2.00 600,000 1,200,000
4 Pek. Pintu Gerbang depan Hollow 5x5 dan 4x4 ( P: 4.4 m, T : 1 m) m2 4.40 600,000 2,640,000
5 Pek. Rel dan Bantalan beton Pintu gerbang m¹ 4.40 426,000 1,874,400
( Tebal 25x cm / Lebar 40 cm /Panjang 4,7 )
Total B 13,763,680
Total III 22,679,616
GRAND TOTAL 53,554,616
DIBULATKAN 53,554,000
Note: Panjang Pagar + pintu Hollow ( 29,6 + 4,7+2)tinggi 1 meter = 36 Jakarta,13 Juli 2020
Harga Per/m² Pemborong,
Rp. 22.679.616/ 36 m²
Rp.624,783
Harga Per/m² diatas tidak termasuk Item pekerjaan Persiapan
dan Pekerjaan Buis Beton MAMAT
Harga satuan struktur