RENCANA ANGGARAN BIAYA

PEKERJAAN : KONTAINER TAHAP 1


LOKASI : PARAMOUNT

HARGA
NO JENIS PEKERJAAN SAT VOL SATUAN JML HARGA

I. PEKERJAAN PERSIAPAN
1 Sewa mobil crane Unit 1.00 7,500,000.00 7,500,000
2 Sewa Forklift By Owner
3 Air Kerja By Owner
4 Listrik Kerja By Owner
5 Kontainer mentah Unit 2.00 25,000,000.00 50,000,000
6 Mobilisasi Kontainer Unit 2.00 By Owner
Total I 57,500,000
II. PEKERJAAN KONTAINER LANTAI 1
A. PEKERJAAN STRUKTUR
1 Pek. Galian pondasi bantalan kontainer ttk 6.00 65,000 390,000
3
2 Pek. Cor bantalan kontainer 40x40 kedalaman 140 cm ( 1 titik) m 0.22 3,325,000 744,800
3
3 Pek. Cor bantalan kontainer 40x40 kedalaman 80 cm ( 5 Titik) m 0.64 3,325,000 2,128,000
Total A 3,262,800
B. PEKERJAAN FINISHING
1 Pek. Lantai keramik 40x40 cm m2 15.00 185,000 2,775,000
2
2 Pek. Plafond gypsum m 15.00 115,000 1,725,000
3 Pek. List Plafond m¹ 16.90 27,000 456,300
2
4 Pek. Dinding triplek 6 mm Double m 31.10 165,000 5,131,500
5 Pek. Dinding Partisi Penyekat ruang toko dan mess m2 6.37 215,000 1,369,550
6 Pek. Cat minyak kulit jeruk m2 43.84 35,000 1,534,400
7 Pek. Cat tembok u/ plafond Ex' Vinilex m2 15.00 22,000 330,000
2
8 Pek. Cat minyak bagian luar m 43.84 35,000 1,534,400
2
9 Pek. Potong dan openingan u/ pintu & Jendela m 29.60 135,000 3,996,000
11 Pek Pintu dan Jendela
- PU-01 - 1 X 2,1 unit 2.00 2,800,000 5,600,000
- JA-01 - 2,1 X 2 + 1 Daun unit 1.00 4,000,000 4,000,000
- JA-02 - 2,1 X 2 unit 1.00 4,000,000 4,000,000
- JA-03 - 1 X1,4 unit 1.00 2,000,000 2,000,000
Total B 32,452,150
C. PEKERJAAN ELEKTRIKAL
1 Pek. Pasang Box MCB Komplit M6 Bh 1.00 750,000.00 750,000.00
2 Pek. Tarik Kabel Tufur m¹ 50.00 135,000.00 6,750,000.00
3 Pek. Instalasi Penerangan ttk 2.00 285,000.00 570,000.00
4 Pek. Pasangan saklar ttk 1.00 85,000 85,000.00
5 Pek. Lampu Philips ttk 2.00 145,000 290,000.00
6 Pek. Instalasi Stop Kontak ( 1 di toko , 1 di mess) ttk 2.00 285,000 570,000
7 Pek. Pasangan stop Kontak ttk 2.00 85,000 170,000
8 Pek. Intalasi Stop kontak AC ttk 1.00 285,000 285,000
9 Pek. Pipa refrigent m¹ 6.00 125,000 750,000
10 Pek. Drain Ac m¹ 3.00 35,000 105,000
Total C 10,325,000
Total II 46,039,950
HARGA
NO JENIS PEKERJAAN SAT VOL SATUAN JML HARGA

III. KONTAINER LANTAI 2


B. PEKERJAAN FINISHING
1 Pek. Lantai keramik 40x40 cm m2 15.00 185,000 2,775,000
2
2 Pek. Plafond gypsum m 15.00 115,000 1,725,000
3 Pek. List Plafond m¹ 16.90 27,000 456,300
4 pek. Dinding triplek 6 mm m2 31.35 165,000 5,172,750
5 Pek. Cat minyak kulit jeruk m2 31.35 35,000 1,097,250
2
6 Pek. Cat tembok u/ plafond Ex' vinilek m 15.00 22,000 330,000
2
7 Pek. Cat minyak bagian luar m 31.35 35,000 1,097,250
2
8 Pek. Potong dan openingan u/ pintu & Jendela m 34.00 135,000 4,590,000
10 Pek Pintu dan Jendela
- PU-01 - 1 X 2,1 unit 1.00 2,800,000 2,800,000
- JA-01 - 2,1 X 2 + 1 Daun unit 1.00 4,000,000 4,000,000
- JA-04 - 2,1 X 2 unit 1.00 4,000,000 4,000,000
- JA-05 - 0,5 X 5,7 unit 1.00 7,000,000 7,000,000
Total A 35,043,550
B. PEKERJAAN ELEKTRIKAL
1 Pek. Instalasi Penerangan ttk 2.00 285,000.00 570,000.00
2 Pek. Pasangan saklar ttk 1.00 85,000 85,000.00
3 Pek. Lampu Philips ttk 2.00 145,000 290,000.00
4 Pek. Instalasi Stop Kontak ttk 1.00 285,000 285,000
5 Pek. Pasangan stop Kontak ttk 1.00 85,000 85,000
6 Pek. Intalasi Stop kontak AC ttk 1.00 285,000 285,000
7 Pek. Pipa refrigent m¹ 6.00 125,000 750,000
8 Pek. Drain Ac m¹ 3.00 35,000 105,000
Total B 2,455,000
Total III 37,498,550
GRAND TOTAL 141,038,500
DIBULATKAN 141,038,000

Note: Luas Kontainer (2,45 x 6 ) x 2 ( 2 kontainer ) = 29,4 m² Jakarta,07 Juli 2020


Harga Per/m² Pemborong,
Rp.83.538.000/ 29,4 m²
Rp.2.841.429

Harga Per/m² diatas tidak termasuk Pengadaan Kontainer


atau Item Pekerjaan Persiapan Rp.57.500.000 MAMAT
RENCANA ANGGARAN BIAYA

PEKERJAAN : KONTAINER TAHAP 1 ( PINTU DAN JENDELA TIDAK TERMASUK )


LOKASI : PARAMOUNT

HARGA
NO JENIS PEKERJAAN SAT VOL JML HARGA
SATUAN
I. PEKERJAAN PERSIAPAN
1 Sewa mobil crane Unit 1.00 7,500,000.00 7,500,000
2 Air Kerja By Owner
3 Listrik Kerja By Owner
4 Kontainer mentah Unit 2.00 25,000,000.00 50,000,000
5 Mobilisasi Kontainer Unit 2.00 By Owner
Total I 57,500,000
II. PEKERJAAN KONTAINER LANTAI 1
A. PEKERJAAN STRUKTUR
1 Pek. Galian pondasi bantalan kontainer ttk 6.00 65,000 390,000
3
2 Pek. Cor bantalan kontainer 40x40 kedalaman 140 cm ( 1 titik) m 0.22 3,325,000 744,800
3
3 Pek. Cor bantalan kontainer 40x40 kedalaman 80 cm ( 5 Titik) m 0.64 3,325,000 2,128,000
Total A 3,262,800
B. PEKERJAAN FINISHING
1 Pek. Lantai keramik 40x40 cm m2 15.00 185,000 2,775,000
2 Pek. Plafond gypsum m2 15.00 115,000 1,725,000
3 Pek. List Plafond m¹ 16.90 27,000 456,300
2
4 Pek. Dinding triplek 6 mm Double m 31.10 165,000 5,131,500
2
5 Pek. Dinding Partisi Penyekat ruang toko dan mess m 6.37 215,000 1,369,550
2
6 Pek. Cat minyak kulit jeruk m 43.84 35,000 1,534,400
7 Pek. Cat tembok u/ plafond Ex' Vinilex m2 15.00 22,000 330,000
2
8 Pek. Cat minyak bagian luar m 43.84 35,000 1,534,400
2
9 Pek. Potong dan openingan u/ pintu & Jendela m 29.60 135,000 3,996,000
Total B 18,852,150
C. PEKERJAAN ELEKTRIKAL
1 Pek. Pasang Box MCB Komplit M6 Bh 1.00 750,000.00 750,000.00
2 Pek. Tarik Kabel Tufur m¹ 50.00 135,000.00 6,750,000.00
3 Pek. Instalasi Penerangan ttk 2.00 285,000.00 570,000.00
4 Pek. Pasangan saklar ttk 1.00 85,000 85,000.00
5 Pek. Lampu Philips ttk 2.00 145,000 290,000.00
6 Pek. Instalasi Stop Kontak ttk 1.00 285,000 285,000
7 Pek. Pasangan stop Kontak ttk 1.00 85,000 85,000
8 Pek. Intalasi Stop kontak AC ttk 1.00 285,000 285,000
9 Pek. Pipa refrigent m¹ 6.00 125,000 750,000
10 Pek. Drain Ac m¹ 3.00 35,000 105,000
Total C 9,955,000
Total II 32,069,950
III. KONTAINER LANTAI 2
B. PEKERJAAN FINISHING
1 Pek. Lantai keramik 40x40 cm m2 15.00 185,000 2,775,000
2
2 Pek. Plafond gypsum m 15.00 115,000 1,725,000
3 Pek. List Plafond m¹ 16.90 27,000 456,300
2
4 pek. Dinding triplek 6 mm m 31.35 165,000 5,172,750
5 Pek. Cat minyak kulit jeruk m2 31.35 35,000 1,097,250
HARGA
NO JENIS PEKERJAAN SAT VOL JML HARGA
SATUAN

6 Pek. Cat tembok u/ plafond Ex' vinilek m2 15.00 22,000 330,000


7 Pek. Cat minyak bagian luar m2 31.35 35,000 1,097,250
8 Pek. Potong dan openingan u/ pintu & Jendela m2 34.00 135,000 4,590,000
Total A 17,243,550
B. PEKERJAAN ELEKTRIKAL
1 Pek. Instalasi Penerangan ttk 2.00 285,000.00 570,000.00
2 Pek. Pasangan saklar ttk 1.00 85,000 85,000.00
3 Pek. Lampu Philips ttk 2.00 145,000 290,000.00
4 Pek. Instalasi Stop Kontak ttk 1.00 285,000 285,000
5 Pek. Pasangan stop Kontak ttk 1.00 85,000 85,000
6 Pek. Intalasi Stop kontak AC ttk 1.00 285,000 285,000
7 Pek. Pipa refrigent m¹ 6.00 125,000 750,000
8 Pek. Drain Ac m¹ 3.00 35,000 105,000
Total B 2,455,000
Total III 19,698,550
GRAND TOTAL 109,268,500
DIBULATKAN 109,268,000

Note: Luas Kontainer (2,45 x 6 ) x 2 ( 2 kontainer ) = 29,4 m² Jakarta,07 Juli 2020


Harga Per/m² Pemborong,
Rp. 51.768.000 / 29,4 m²
Rp.1.760.816
Harga Per/m² diatas tidak termasuk Pengadaan Kontainer
atau Item Pekerjaan Persiapan Rp.57.500.000 dan tidak termasuk MAMAT
pintu dan jendela
RENCANA ANGGARAN BIAYA

PEKERJAAN : KONTAINER (UNIT PINTU DAN JENDELA UPVC)


LOKASI : PARAMOUNT

HARGA
NO JENIS PEKERJAAN SAT VOL JML HARGA
SATUAN
I. PEKERJAAN KONTAINER
A. PEK. PINTU DAN JENDELA LANTAI 1
1 - PU-01 - 1 X 2,1 unit 2.00 2,800,000 5,600,000
2 - JA-01 - 2,1 X 2 + 1 Daun unit 1.00 4,000,000 4,000,000
3 - JA-02 - 2,1 X 2 unit 1.00 4,000,000 4,000,000
4 - JA-03- 1 X 1,4 unit 1.00 2,000,000 2,000,000
Total A 15,600,000
B. PEK. PINTU DAN JENDELA LANTAI 2
1 - PU-01 - 1 X 2,1 unit 1.00 2,800,000 2,800,000
2 - JA-01 - 2,1 X 2 + 1 Daun unit 1.00 4,000,000 4,000,000
3 - JA-04 - 2,1 X 2 unit 1.00 4,000,000 4,000,000
4 - JA-05 - 0,5 X 5,7 unit 1.00 7,000,000 7,000,000
Total B 17,800,000
Total I 33,400,000
II. PEKERJAAN TOILET & DAPUR
A. PEK. PINTU DAN JENDELA TOILET
1 - PVC-02 - 0,9 X 2,1 unit 1.00 950,000 950,000
2 - BV-01 - 0,4X 0,6 unit 1.00 1,100,000 1,100,000
Total A 2,050,000
PEK. PINTU DAN JENDELA DAPUR
1 PU-02 -2 x2,1 ( 4 daun pintu lipat) Unit 1.00 6,000,000 6,000,000
2 JA-06 - 2 X 0,6 + 1 daun Unit 1.00 2,500,000 2,500,000
3 JA-07 - 1,8 X 0,5 + 1 daun Unit 1.00 1,500,000 1,500,000
Total B 10,000,000
Total II 12,050,000
GRAND TOTAL 45,450,000
DIBULATKAN 45,450,000

Note: ini Rab pintu dan jendela dalam pekerjaan Kontainer tahap Jakarta,07 Juli 2020
Pemborong,

MAMAT
RENCANA ANGGARAN BIAYA

PEKERJAAN : TOILET , TERAS DEPAN, TERAS BELAKANG & R. OUTDOOR LANTAI 2


LOKASI : PARAMOUNT

HARGA
NO JENIS PEKERJAAN SAT VOL JML HARGA
SATUAN
I. PEKERJAAN PERSIAPAN
1 Air Kerja By Owner
2 Listrik Kerja By Owner
3 Bedeng By Owner

II. PEKERJAAN TOILET


A. PEKERJAAN STRUKTUR
1 Pek. galian pondasi tapak 60x60x80 cm ttk 4.00 65,000 260,000
3
2 Pek. Cor pondasi tapak 50x50x30 cm m 0.30 3,325,000 997,500
3
3 Pek. Cor kolom struktur 15x20 cm m 0.36 3,325,000 1,197,000
3
4 Pek. Cor sloof beton 15x20 cm m 0.28 3,325,000 943,635
5 Pek. Cor balok beton 15x20 cm m3 0.28 3,325,000 943,635
3
6 Pek. Cor plat beton t. 12 cm m 0.69 3,325,000 2,294,250
7 Pek. Pas. Septic Tank 1 m3 BioFill unit 1.00 4,500,000 4,500,000
8 Pek. Air Ground tank 1000 L unit 1.00 3,500,000 3,500,000
Total A 14,636,020
B. PEKERJAAN FINISHING
1 Pek. Pasangan dinding bata spesi 1:4 m2 22.88 125,000 2,860,000
2
2 Pek. Plester & Aci m 37.56 88,400 3,320,304
2
3 Pek. Pasang keramik dinding 20x25 t. 100 cm m 8.20 235,000 1,927,000
2
4 Pek. Screed lantai 5 cm m 8.20 135,000 1,107,000
2
5 Pek. Keramik lantai 20x20 cm m 3.75 185,000 693,750
6 Pek. Plafond gypsum m2 3.75 115,000 431,250
7 List Plafond m¹ 8.00 27,000 216,000
2
8 Pek. Finishing cat Ex' Vinilex m 41.31 22,000 908,820
9 Pek. Pintu PVC ( Rab Unit Pintu dan jendela ) Unit 1.00
Total B 11,464,124
C. PEKERJAAN SANITARY
1 Pek. Pasang Closed jongkok unit 1.00 450,000 450,000
2 Pek. Pasang kran bh 1.00 75,000 75,000
3 Pek. Pasang Floor drain bh 1.00 75,000 75,000
4 Pek. Pas. Pipa air bersih 1/2" m' 30.00 45,000 1,350,000
5 Pek. Pas. Air kotor PVC 3" m' 6.00 95,000 570,000
6 Pek. Pas Pipa air Kotoran m' 6.00 145,000 870,000
Total C 3,390,000
D. PEKERJAAN ELEKTRIKAL
1 Pek. Instalasi Penerangan ttk 1.00 285,000.00 285,000.00
2 Pek. Pasangan saklar ttk 1.00 85,000 85,000.00
3 Pek. Lampu Philips ttk 1.00 145,000 145,000.00
Total D 515,000
Total II 30,005,144

III. PEKERJAAN RUANG OUTDOOR LANTAI 2


A. PEKERJAAN SIPIL
HARGA
NO JENIS PEKERJAAN SAT VOL JML HARGA
SATUAN

1 Pek. galian pondasi tapak 80x80x120 cm ttk 4.00 65,000 260,000


2 Pek. Cor pondasi tapak 60x60x30 cm m3 0.30 3,325,000 997,500
3
3 Pek. Cor Pedestal 40x40x90 cm m 0.64 3,325,000 2,128,000
4 Pek. Pasang angkur 12 mm bh 24.00 65000 1,560,000
5 Pek. Pasang Kolom WF 150.75 (Area outdoor) kg 252.00 24000 6,048,000
6 Pek. Pasang Kolom WF 150.75 ( Tiang Membrant) kg 147.00 24000 3,528,000
7 Pek. Pasang balok WF 150.75 (Area outdoor) kg 574.00 24000 13,776,000
8 Pek. Pasang Kolom WF 150.75 ( Tiang Membrant) kg 112.00 24000 2,688,000
9 Pek. Pasang rangka tatakan plat hollow 50x50 mm kg 426.40 24000 10,233,600
10 Pek. Pasang plat borders 3 mm kg 675.00 15000 10,125,000
11 Pek. Pasang plat tapak dan stephener plat 8 mm kg 187.00 24000 4,488,000
12 Pek. Pasang skoor WF 150.75 kg 98.00 24000 2,352,000
13 Pek. Relling balkon tiang hollow tali seling m' 14.00 24000 336,000
14 Pek. Tangga besi + relling + trap bordes unit 1.00 10500000 10,500,000
15 Pek. Finishing cat besi m' 2,471.4 1,000.00 2,471,400
2
16 Pek. Bongkar pasang canopy membrane m 32.00 400000 12,800,000
Total A 84,291,500
B. PEKERJAAN ELEKTRIKAL
1 Pek. Instalasi Penerangan ttk 2.00 285,000.00 570,000.00
2 Pek. Pasangan saklar ttk 1.00 85,000 85,000.00
3 Pek. Lampu Philips ttk 2.00 145,000 290,000.00
Total B 945,000
Total III 85,236,500

IV. PEKERJAAN DAPUR LANTAI 2


A. PEKERJAAN FINISHING
1 Pek. Pasang dinding rangka hollow 4x4 dan 5x5 m2 14.24 300000 4,270,500
2
2 Pek. Penutup dinding Zinc Allume t.0,4 mm m 14.24 75000 1,067,625
3
3 Pek. Penutup dalam, triplek 6 mm m 20.36 165000 3,359,400
4 Pek. Pasang jendela UPVC ( Rab Unit Pintu dan jendela ) unit 2.00
5 Pek. Pasang pintu lipat ( Rab Unit Pintu dan jendela ) unit 1.00
2
6 Pek. Pasang Keramik m 5.88 185000 1,087,800
2
7 Pek. Atap rangka hollow penutup Zinc Allume m 1.00 133000 133,000
2
6 Pek. Atap Zinc Allume m 5.88 75000 441,000
2
7 Pek. Plafond gypsum rangka hollow m 5.88 115,000.00 676,200
8 List Plafond m¹ 9.70 27,000 261,900
9 Pek. Meja dapur stainless steel (200X60X60 cm) unit 1.00 5000000 5,000,000
10 Pek. Finishing cat minyak m2 14.24 35000 498,225
2
11 Pek. Finishing cat tembok untuk plafond m 5.88 22000 129,360
Total A 16,925,010
B. PEKERJAAN ELEKTRIKAL
1 Pek. Instalasi Penerangan ttk 1.00 285,000.00 285,000.00
2 Pek. Pasangan saklar ttk 1.00 85,000 85,000.00
3 Pek. Lampu Philips ttk 1.00 145,000 145,000.00
4 Pek. Pasang Instalasi Hexhoust fan Unit 1.00 850,000 850,000.00
Total B 1,365,000
Total IV 18,290,010

V. PEKERJAAN TERAS DEPAN


HARGA
NO JENIS PEKERJAAN SAT VOL JML HARGA
SATUAN
A. PEKERJAAN FINISHING
1 Pek. Pasangan dinding bata spesi 1:4 (kontruksi tangga) m2 14.40 125000 1,800,000
2
2 Pek. Plester & Aci m 6.00 88400 530,400
2
3 Pek. Screed lantai 5 cm m 20.24 135000 2,732,400
2
4 Pek. Keramik lantai 40x40 cm m 20.24 185000 3,744,400
Total A 8,807,200
B. PEKERJAAN ELEKTRIKAL
1 Pek. Instalasi Penerangan ttk 2.00 285,000.00 570,000.00
2 Pek. Pasangan saklar ttk 1.00 85,000 85,000.00
3 Pek. Lampu Philips ttk 2.00 145,000 290,000.00
Total B 945,000
Total V 9,752,200

VI. PEKERJAAN TERAS BELAKANG DAN DAPUR STAFF


A. STRUKTUR DAN PEKERJAAN FINISHING
1 - Pek. galian pondasi tapak 40x40x60 cm ttk 2.00 65,000 130,000
3
2 - Pek. Cor pondasi tapak 30x30x20 cm m 0.04 3,325,000 143,640
3
3 - Pek. Cor kolom struktur 15x15 cm m 0.14 3,325,000 448,875
4 - Pek. Cor sloof beton 15x15 cm m3 0.02 3,325,000 82,294
5 - Pek. Cor balok beton 15x`15 cm m3 0.02 3,325,000 82,294
2
6 - Pek. Pasangan dinding bata spesi 1:4 (Dinding depan) m 3.00 125000 375,000
2
7 - Pek. Plester & Aci m 6.00 88400 530,400
2
8 - Pek. Finishing cat dinding ex' Vinilex m 6.00 22000 132,000
3
9 - Pek. Cor Meja dapur t : 10 cm m 0.07 3,325,000 232,750
10 - Pek. Meja fins keramik 40x40 cm m2 1.00 185000 185,000
2
11 - Pek. Screed lantai 5 cm m 8.00 135000 1,080,000
2
12 - Pek. Keramik lantai 40x40 cm m 8.00 185000 1,480,000
2
12 Pek. Pasang Canopy poly carbonate m 5.00 600000 3,000,000
Total A 7,902,253
B. PEKERJAAN ELEKTRIKAL
1 Pek. Instalasi Penerangan ttk 1.00 285,000.00 285,000.00
2 Pek. Pasangan saklar ttk 1.00 85,000 85,000.00
3 Pek. Lampu Philips ttk 1.00 145,000 145,000.00
Total B 515,000
Total VI 8,417,253
GRAND TOTAL 151,701,107
DIBULATKAN 151,701,000

Note: Luas area (halaman depan, belakang, tangga outdoor lantai 2 dan dapur) Jakarta,07 Juli 2020
16+8+24+5+5,7= 58,7 Pemborong,
Harga Per/m²
Rp. 151.701.000 / 58,7 m²
Rp.2.584.344

MAMAT
RENCANA ANGGARAN BIAYA

PEKERJAAN : PEKERJAAN PERKERASAN


LOKASI : PARAMOUNT

HARGA
NO JENIS PEKERJAAN SAT VOL JML HARGA
SATUAN
I. PEKERJAAN PERSIAPAN
1 Air Kerja By Owner
2 Listrik Kerja By Owner
3 Bedeng By Owner

II. PEKERJAAN PERKERASAN BETON


A. PEKERJAAN PERKERASAN BETON AREA DEPAN
1 Pek. Kupas tanah area jalan masuk m3 29.10 65,000 1,891,500
2 Pek. Gelar makadam jalan masuk 30 cm m3 14.55 385,000 5,601,750
3 Pek. Pemadatan m² 48.50 20,000 970,000
3
4 Pek. Cor jalan 20 cm m 9.70 2,250,000 21,825,000
Total A 30,288,250
B. PEKERJAAN PERKERASAN BETON AREA BELAKANG
1 Pek. Kupas tanah area jalan masuk m3 18.60 65,000 1,209,000
3
2 Pek. Gelar makadam jalan masuk 30 cm m 9.30 385,000 3,580,500
3 Pek. Pemadatan m² 31.00 20,000 620,000
4 Pek. Cor jalan 20 cm m3 6.20 2,250,000 13,950,000
Total B 19,359,500
Total II 49,647,750

III. PEKERJAAN PERKERASAN PAVING


A. PEKERJAAN PERKERASAN PAVING AREA DEPAN
1 Pek. Gelar makadam area parkir 20 cm m3 29.20 385,000 11,242,000
2 Pek. Pemadatan m² 146.00 20,000 2,920,000
3 Pek. Pasang paving 8 cm m² 146.00 285,000 41,610,000
3
4 Pek. Gelar makadam Area pintu masuk pejalan kaki 10 cm m 0.80 385,000 308,000
5 Pek. Pemadatan m² 8.00 20,000 160,000
6 Pek. Pasang paving 8 cm m² 8.00 285,000 2,280,000
7 Pek. Cansteen m¹ 40.00 145,000 5,800,000
Total A 64,320,000
B. PEKERJAAN PERKERASAN BETON AREA BELAKANG
1 Pek. Gelar makadam area parkir 20 cm m3 49.00 385,000 18,865,000
2 Pek. pemadatan m² 245.00 20,000 4,900,000
3 Pek. Pasang paving 8 cm m² 245.00 285,000 69,825,000
4 Pek. Cansteen m¹ 20.00 145,000 2,900,000
Total A 96,490,000
Total III 160,810,000
GRAND TOTAL 210,457,750
DIBULATKAN 210,457,000

Note: Luas area yang dikerjakan (Perkerasan Beton,48,5+31)=79,5 m² Jakarta,07 Juli 2020
Harga Per/m² = Rp. 49.647.750 / 79,5 = Rp. 624500 Pemborong,

Luas area yang dikerjakan (Perkerasan Paving ,146+8+245)=399 m²


HARGA
NO JENIS PEKERJAAN SAT VOL JML HARGA
SATUAN

Harga Per/m² = Rp. 160.810.000 / 399 = Rp. 403.032


MAMAT
RENCANA ANGGARAN BIAYA

PEKERJAAN : PAGAR
LOKASI : PARAMOUNT

HARGA
NO JENIS PEKERJAAN SAT VOL JML HARGA
SATUAN
I. PEKERJAAN PERSIAPAN
1 Air Kerja By Owner
2 Listrik Kerja By Owner
3 Bedeng By Owner
Total I
II. PEKERJAAN BUIS BETON
1 Pek. Galian buis beton m¹ 115.00 75,000 8,625,000
2 Pek. Pasang buis beton m¹ 115.00 150,000 17,250,000
Total II 25,875,000
II. PEKERJAAN PAGAR DEPAN
A. PEKERJAAN STRUKTUR
1 Pek. Galian pondasi dudukan brc depan (tanpa sloof) ttk 5.00 65,000 325,000
3
2 Pek. Cor pondasi dudukan brc depan 20x20x120 m 0.24 3,325,000 798,000
3 Pek. Galian Pondasi Tapak (60x60x60) ttk 11.00 65,000 715,000
3
4 Pek. Cor Pondasi tapak 30x30x20 m 0.20 3,325,000 658,350
5 Pek. Galian sloof 30x30 m¹ 29.60 25,000 740,000
3
6 Pek. Cor sloof 15x15 m 0.67 3,325,000 2,214,450
3
7 Pek. Cor kolom 15x15 m 0.25 3,325,000 822,938
Total A 6,273,738
B. PEKERJAAN PINISHING ( tanpa cat )
1 Pek. Pasang dinding bata merah m2 29.60 125,000 3,700,000
2
2 Pek. Plester & aci m 59.20 88,400 5,233,280
3 Pek. Pintu Gerbang depan Hollow 5x5 dan 4x4 m¹ 16.90 27,000 456,300
2
4 Pek. Dinding triplek 6 mm Double m 31.10 165,000 5,131,500
5 Pek. Dinding Partisi Penyekat ruang toko dan mess m2 6.37 215,000 1,369,550
2
6 Pek. Cat minyak kulit jeruk m 43.84 35,000 1,534,400
2
7 Pek. Cat tembok u/ plafond Ex' Vinilex m 59.20 22,000 1,302,400
2
8 Pek. Cat minyak bagian luar m 43.84 35,000 1,534,400
2
9 Pek. Potong dan openingan u/ pintu & Jendela m 29.60 135,000 3,996,000
Total B 24,257,830
Total B #REF!
Total III #REF!
GRAND TOTAL #REF!
DIBULATKAN #REF!

Note: Luas Kontainer (2,45 x 6 ) x 2 ( 2 kontainer ) = 29,4 m² Jakarta,07 Juli 2020


Harga Per/m² Pemborong,
Rp. 51.768.000 / 29,4 m²
Rp.1.760.816
Harga Per/m² diatas tidak termasuk Pengadaan Kontainer
atau Item Pekerjaan Persiapan Rp.57.500.000 dan tidak termasuk MAMAT
pintu dan jendela
RENCANA ANGGARAN BIAYA

PEKERJAAN : PAGAR
LOKASI : PARAMOUNT

HARGA
NO JENIS PEKERJAAN SAT VOL JML HARGA
SATUAN
I. PEKERJAAN PERSIAPAN
1 Pek. Listrik Kerja ( Tunggu Pln Masuk ) By Owner
2 Air Kerja By Owner
3 Pek. Mobilisasi Pekerja Ls 1.00 5,000,000.00 5,000,000.00
4 Pek. Bedeng dan Gudang (tunggu kontainer) By Owner
5 Pek. Pagar Pengaman (Bila dibutuhkan) By Owner
6 Pek. Bongkar muat material ( Bila Ada) By Owner
Total I 5,000,000
II. PEKERJAAN BUIS BETON
1 Pek. Galian buis beton m¹ 115.00 75,000 8,625,000
2 Pek. Pasang buis beton m¹ 115.00 150,000 17,250,000
Total II 25,875,000
III. PEKERJAAN PAGAR DEPAN
A. PEKERJAAN STRUKTUR
1 Pek. Galian pondasi Tapak 70x70x60 ttk 13.00 65,000 845,000
3
2 Pek. Cor Pondasi tapak 30x30x20 m 0.23 3,325,000 778,050
3 Pek. Galian sloof 30x30 m¹ 29.60 25,000 740,000
4 Pek. Cor sloof 15x15 m3 0.67 3,325,000 2,214,450
5 Pek. Cor kolom 15x15 t : 1 meter m3 0.29 3,325,000 972,563
Total A 5,550,063
B. PEKERJAAN FINISHING ( tanpa cat )
1 Pek. Pasang dinding bata merah t : 1 meter m2 29.60 125,000 3,700,000
2 Pek. Plester & aci m2 49.20 88,400 4,349,280
3 Pek. Pintu Akses Pejalan kaki ( P: 2 m , T : 1m) m2 2.00 600,000 1,200,000
2
4 Pek. Pintu Gerbang depan Hollow 5x5 dan 4x4 ( P: 4.4 m, T : 1 m) m 4.40 600,000 2,640,000
2
5 Pek. Rel dan Bantalan beton Pintu gerbang m 4.40 426,000 1,874,400
( Tebal 25x cm / Lebar 40 cm /Panjang 4,7 )
Total B 13,763,680
Total III 19,313,743
GRAND TOTAL 50,188,743
DIBULATKAN 50,188,000

Note: Panjang Pagar + pintu Hollow ( 29,6 + 4,7+2)tinggi 1 meter = 36 Jakarta,13 Juli 2020
Harga Per/m² Pemborong,
Rp. 19.313.743/ 36 m²
Rp.536.493
Harga Per/m² diatas tidak termasuk Item pekerjaan Persiapan
dan Pekerjaan Buis Beton MAMAT
PEKERJAAN : PAGAR
LOKASI : PARAMOUNT

HARGA
NO JENIS PEKERJAAN SAT VOL JML HARGA KETERANGAN
SATUAN
I. PEKERJAAN PERSIAPAN
1 Pek. Listrik Kerja ( Tunggu Pln Masuk ) By Owner
2 Air Kerja By Owner
3 Pek. Mobilisasi Pekerja Ls 1.00 5,000,000.00 5,000,000.00
4 Pek. Bedeng dan Gudang (tunggu kontainer) By Owner
5 Pek. Pagar Pengaman (Bila dibutuhkan) By Owner
6 Pek. Bongkar muat material ( Bila Ada) By Owner
Total I 5,000,000
II. PEKERJAAN BUIS BETON
1 Pek. Galian buis beton m¹ 115.00 75,000 8,625,000
2 Pek. Pasang buis beton m¹ 115.00 150,000 17,250,000
Total II 25,875,000
III. PEKERJAAN PAGAR DEPAN
A. PEKERJAAN STRUKTUR
1 Pek. Galian pondasi Tapak 70x70x60 ttk 13.00 65,000 845,000
2 Pek. Cor Pondasi tapak 30x30x20 m 3
0.23 6,733,550 1,575,651 Rp121,204 Per/titik
3 Pek. Galian sloof 30x30 m¹ 29.60 25,000 740,000
4 Pek. Cor sloof 15x15 m3 0.67 5,626,250 3,747,083 Rp126,591 Per/ 1m
5 Pek. Cor kolom 15x15 t : 1 meter m3 0.29 6,865,650 2,008,203 Rp154,477 Per/ titik
Total A 8,915,936
B. PEKERJAAN FINISHING ( tanpa cat )
1 Pek. Pasang dinding bata merah t : 1 meter m2 29.60 125,000 3,700,000
2 Pek. Plester & aci m2 49.20 88,400 4,349,280
2
3 Pek. Pintu Akses Pejalan kaki ( P: 2 m , T : 1m) m 2.00 600,000 1,200,000
4 Pek. Pintu Gerbang depan Hollow 5x5 dan 4x4 ( P: 4.4 m, T : 1 m) m2 4.40 600,000 2,640,000
5 Pek. Rel dan Bantalan beton Pintu gerbang m¹ 4.40 426,000 1,874,400
( Tebal 25x cm / Lebar 40 cm /Panjang 4,7 )
Total B 13,763,680
Total III 22,679,616
GRAND TOTAL 53,554,616
DIBULATKAN 53,554,000

Note: Panjang Pagar + pintu Hollow ( 29,6 + 4,7+2)tinggi 1 meter = 36 Jakarta,13 Juli 2020
Harga Per/m² Pemborong,
Rp. 22.679.616/ 36 m²
Rp.624,783
Harga Per/m² diatas tidak termasuk Item pekerjaan Persiapan
dan Pekerjaan Buis Beton MAMAT
Harga satuan struktur

1 1 M3 Pondasi Beton Tulang 30x30x20


- Kayu papan Terentang M3 0.2000 2,800,000.00 560,000.00
- Paku Biasa 2" - 5" Kg 1.5000 21,400.00 32,100.00
- Minyak Bekisting Ltr - 55,000.00 -
- Besi Beton Kg 310.0000 16,500.00 5,115,000.00
- Kawat Beton Kg 2.2500 17,000.00 38,250.00
- Semen Portland Kg 323.0000 1,080.00 348,840.00
- Pasir Beton M3 0.5200 280,000.00 145,600.00
- Koral Beton 2/3 M3 0.7800 242,000.00 188,760.00
- Pekerja Oh 3.9000 - -
- Tukang Batu Oh 0.3500 125,000.00 43,750.00
- Tukang Kayu Oh 1.0400 125,000.00 130,000.00
- Tukang Besi Oh 1.0500 125,000.00 131,250.00
- Kepala Tukang Oh 0.2450 - -
- Mandor Oh 0.1650 - -
Jumlah 6,733,550.00
Dibulatkan 6,733,550.00

2 1 M3 Sloof Beton Tulang 15/15


- Kayu papan terentang M3 0.2700 2,800,000.00 756,000.00
- Paku Biasa 2" - 5" Kg 2.0000 21,400.00 42,800.00
- Minyak Bekisting Ltr 0.6000 55,000.00 33,000.00
- Besi Beton Kg 221.0000 16,500.00 3,646,500.00
- Kawat Beton Kg 3.0000 17,000.00 51,000.00
- Semen Portland Kg 323.0000 1,080.00 348,840.00
- Pasir Beton M3 0.5200 280,000.00 145,600.00
- Koral Beton 2/3 M3 0.7800 242,000.00 188,760.00
- Pekerja Oh 4.8500 -
- Tukang Batu Oh 0.3500 125,000.00 43,750.00
- Tukang Kayu Oh 1.5600 125,000.00 195,000.00
- Tukang Besi Oh 1.4000 125,000.00 175,000.00
- Kepala Tukang Oh 0.3310 -
- Mandor Oh 0.1700 -
Jumlah 5,626,250.00
Dibulatkan 5,626,250.00

3 1 M3 Kolom Beton Tulang Praktis 15/15


- Kayu papan terentang M3 0.4000 2,800,000.00 1,120,000.00
- Paku Biasa 2" - 5" Kg 4.0000 21,400.00 85,600.00
- Minyak Bekisting Ltr 55,000.00 -
- Besi Beton Kg 220.0000 16,500.00 3,630,000.00
- Kawat Beton Kg 1.8000 17,000.00 30,600.00
- Semen Portland Kg 323.0000 1,080.00 348,840.00
- Pasir Beton M3 0.5200 280,000.00 145,600.00
- Koral Beton 2/3 M3 0.7800 242,000.00 188,760.00
- Kayu Balok Terentang M3 2,640,000.00 -
- Multiplek 9 mm Lbr 0.3000 125,000.00 37,500.00
- Dolken Ø-8-10/4m Btg 20.0000 28,000.00 560,000.00
- Pekerja Oh 7.3000 -
- Tukang Batu Oh 0.3500 125,000.00 43,750.00
- Tukang Kayu Oh 3.3000 125,000.00 412,500.00
- Tukang Besi Oh 2.1000 125,000.00 262,500.00
- Kepala Tukang Oh 0.5700 - -
- Mandor Oh 0.2500 - -
Jumlah 6,865,650.00
Dibulatkan 6,865,650.00