DAFTAR KELUARAN DAN HARGA

PEKERJAAN : Renovasi Kantor Balai Besar MKG Wilayah II


LOKASI : Balai Besar MKG Wilayah II
TAHUN : 2022

HARGA JUMLAH
URAIAN PEKERJAAN SAT VOLUME SATUAN (Rp) HARGA (Rp)
NO.
A. PEKERJAAN PERSIAPAN DAN AKHIR
I Pekerjaan Persiapan dan Akhir
1 Listrik dan Air Kerja Ls 1.00 1,000,000.00 1,000,000.00
2 Papan nama proyek Unit 1.00 250,000.00 250,000.00
3 Bongkar AC Split Unit 4.00 175,000.00 700,000.00
4 Bongkar Lemari Mobile File System Unit 1.00 550,000.00 550,000.00
5 Pembersihan Lapangan termasuk buangan puing Ls 1.00 728,334.73 728,334.73
6 Pembongkaran Kanopi Exsting m2 30.00 35,000.00 1,050,000.00
7 Reinstalasi AC Split Unit 4.00 450,000.00 1,800,000.00
Sub Total Perkerjaan Persiapan dan Akhir 6,078,334.73
B PENERAPAN SMK3
1 Alat Pelindung Diri / APD
a. Sepatu ( safety shoes ) psg 10.00 65,000.00 650,000.00
b. Helm buah 10.00 35,000.00 350,000.00
c.Sarung tangan buah 10.00 15,000.00 150,000.00
2 Personil K3 OB 3.00 550,000.00 1,650,000.00
3 Peralatan P3K ( Kotak P3K, Obat, kain kasa, dll ) Ls 1.00 350,000.00 350,000.00
4 Rambu - rambu -
a. Rambu petunjuk buah 1.00 150,000.00 150,000.00
b. Rambu larangan buah 1.00 150,000.00 150,000.00
c. Rambu informasi buah 1.00 150,000.00 150,000.00
Sub Total Perkerjaan Penerapan SMK3 3,600,000.00
C PEKERJAAN ARSITEKTUR
I Pekerjaan Bongkaran
1 Pek. Pembongkaran Dinding Tembok Bata m2 89.94 110,000.00 9,893,400.00
2 Pek. Bongkaran Plafon m2 282.07 120,000.00 33,848,400.00
3 Pek. Bongkaran Keramik m2 246.87 120,000.00 29,624,400.00
4 Pek. Bongkaran Pintu Unit 7.00 120,000.00 840,000.00
5 Pek. Bongkaran Jendela Unit 8.00 120,000.00 960,000.00
6 Pek. Mengikis / Mengerok Permukaan Cat Tembok Lama m2 474.48 45,000.00 21,351,600.00
7 Pek. Bongkaran Antena triangle Unit 1.00 550,000.00 550,000.00
Sub Total 97,067,800.00
II Pekerjaan Pasangan Dinding
1 Pasangan Bata Merah 1Pc : 3Ps m2 92.83 175,000.00 16,245,250.00
2 Pekerjaan Kolom Praktis m1 19.20 155,000.00 2,976,000.00
3 Plesteran Dinding 1Pc : 3Ps ; tebal 15 mm m2 185.66 75,000.00 13,924,500.00
4 Pasangan Acian (abu - abu) m2 185.66 45,000.00 8,354,700.00
5 Pekerjaan Wallpaper m2 72.55 12,500.00 906,875.00
6 Pas. Partisi Rangka Hollo Fin Polywood m2 17.91 175,000.00 3,134,250.00
7 Pasangan Bata Tempel m2 138.40 175,000.00 24,220,000.00
8 Pasangan Batu Sirih m2 9.16 65,000.00 595,400.00
9 Pekerjaan Meja Beton Fin Marmer m2 4.02 750,000.00 3,015,000.00
Sub Total 73,371,975.00
III Pekerjaan Lantai
1 Pemasangan Lantai Homogeneus Tile ukuran 60 x 60 cm m2 167.64 325,000.00 54,483,000.00
2 Pemasangan Keramik Lantai Kamar mandi ukuran 20 x 20 cm m2 2.25 225,000.00 506,250.00
3 Pemasangan Keramik Dinding Kamar mandi ukuran 40 x 20 cm m2 12.44 225,000.00 2,799,000.00
4 Pemasangan Lantai Vinyl Karet uk 30 x 30 cm M2 36.90
Sub Total 57,788,250.00
IV Pekerjaan Plafond
1 Pek. Plafond Gypsum Board 9mm Rangka Hollow Galvanis 4/4 m2 202.84 185,000.00 37,525,400.00
2 Pek. Plafond Drop Fin Plywood HPL Rangka Besi Hollow expanded metal m2 36.90
Fin Cat 275,000.00 10,147,500.00
Sub Total 47,672,900.00
V Pekerjaan Pengecatan dan Pelapis Anti Bocor
1 Cat Dinding Eksterior m2 118.92 35,000.00 4,162,200.00
2 Cat Dinding Interior m2 355.56 35,000.00 12,444,600.00
3 Pengecatan Plafon m2 202.84 35,000.00 7,099,400.00
4 Waterproofing Karpusan m2 27.60 55,000.00 1,518,000.00
5 Pekerjaan Perbaikan Karpusan m2 27.60 75,000.00 2,070,000.00
Sub Total 27,294,200.00
VI Pekerjaan Kusen Alumunium Pintu dan Jendela
1 Pintu Type P1 Kaca Thempered Unit 1.00 1,500,000.00 1,500,000.00
2 Pintu Type P2 Kusen Alumunium dan Daun Pintu Kaca Unit 3.00 3,500,000.00 10,500,000.00
3 Pintu Type P3 Kusen Alumunium dan Daun Pintu Kaca Unit 2.00 3,500,000.00 7,000,000.00
4 Pintu Type P4 Kusen Alumunium dan Daun Pintu Kaca Unit 1.00 3,500,000.00 3,500,000.00
5 Pintu Type P5 Kusen dan Daun Alumuium Unit 1.00 5,500,000.00 5,500,000.00
6 Jendela Type J1 Kusen Alumunium dan Daun Jendela Kaca Unit 2.00 1,850,000.00 3,700,000.00
7 Jendela Type J2 Kusen Alumunium dan Daun Jendela Kaca Unit 1.00 1,850,000.00 1,850,000.00
8 Jendela Type J4 Kusen Alumunium dan Daun Jendela Kaca Unit 4.00 1,850,000.00 7,400,000.00
9 Jendela Type J6 Kusen Alumunium dan Daun Jendela Kaca Unit 1.00 1,850,000.00 1,850,000.00
10 Jendela Type J7 Kusen Alumunium dan Daun Jendela Kaca Unit 2.00 1,850,000.00 3,700,000.00
Sub Total 46,500,000.00
VII Pekerjaan Destop Kayu
1 Pek Backdrop Fin Plywood HPL Fin Lampu LED Beserta Logo m2 18.36 450,000.00 8,262,000.00
2 Pek Kitcenshet Fin Plywood HPL m2 1.44 1,750,000.00 2,520,000.00
3 Pekerjaan Rak Rangka Besi Hollo Lapis Plywood HPL fin cat m2 3.00 450,000.00 1,350,000.00
4 Pekerjaan Rak Buku Plywood HPL m2 6.00 450,000.00 2,700,000.00
Sub Total 14,832,000.00
Sub Total Perkerjaan Arsitektur 364,527,125.00
D Pekerjaan Mekanikal, Elektrikal dan Plumbing
1 Instalasi Penerangan kabel NYM 2 x 2,5 mm titik 21.00 55,000.00 1,155,000.00
2 Instalasi Stop Kontak Kabel NYM 3 x 2,5 mm² dalam Pipa Conduit 20 mm titik 23.00
55,000.00 1,265,000.00
3 Saklar Tunggal setara Broco titik 9.00 25,000.00 225,000.00
4 Saklar Seri setara Broco titik 2.00 35,000.00 70,000.00
5 Stop Kontak setara Broco titik 12.00 25,000.00 300,000.00
6 Lampu Downlight LED 12 Watt titik 68.00 35,000.00 2,380,000.00
7 Lampu LED Downlight Halospot 3 mata - 12 watt titik 12.00 335,000.00 4,020,000.00
8 Lampu Gantung Kayu LED titik 6.00 185,000.00 1,110,000.00
9 Lampu Gantung Deco titik 4.00 2,000,000.00 8,000,000.00
Plumbing -
1 Pemasangan 1 m' Pipa PVC tipe AW Ø ½" m1 24.00 110,000.00 2,640,000.00
2 Pemasangan 1 m' Pipa PVC tipe AW Ø 3" m1 8.00 185,000.00 1,480,000.00
3 Pemasangan 1 buah Kloset Jongkok Setara INA, Lexus Unit 1.00 350,000.00 350,000.00
4 Pemasangan 1 buah Wastafel Setara Toto Unit 1.00 450,000.00 450,000.00
Sub Total Pekerjaan Mekanikal, Elektrikal, dan Plumbing 23,445,000.00
E PEKERJAAN PAVING BLOCK
1 Paving Block persegi Tinggi 6 cm, K-350, Warna Abu-Abu + Abu Batu t = 5
m2 13.69 120,000.00
cm 1,642,800.00
Sub Total Pekerjaan Pavingblock 1,642,800.00
F PEKERJAAN KANOPI
1 Pek Galian Pondasi m3 0.22 110,000.00 24,200.00
2 Urugan pasir bawah pondasi m3 0.02 55,000.00 1,100.00
3 Pekerjaan Struktur Pondasi dan kolom pedestal -
a. Pekerjaan Besi kg 116.64 27,000.00 3,149,280.00
b. Pekerjaan Beton m3 0.65 975,000.00 633,750.00
c. Pekerjaan Bekisting m2 2.88 325,000.00 936,000.00
4 Pemasangan Pipa Besi 3" kg 67.82 27,000.00 1,831,140.00
5 Pasang kanopi polycarbonate sheet bening 8 mm rangka besi hollo fin cat m2 94.47
300,000.00
28,341,000.00
Sub Total Pekerjaan Kanopi 34,916,470.00
REKAPITULASI
PEKERJAAN : Renovasi Kantor Balai Besar MKG Wilayah II
LOKASI : Balai Besar MKG Wilayah II
TAHUN : 2022

NO URAIAN PEKERJAAN JUMLAH HARGA

A. PEKERJAAN PERSIAPAN DAN AKHIR 6,078,334.73

B PENERAPAN SMK3 3,600,000.00

C PEKERJAAN ARSITEKTUR 364,527,125.00

D Pekerjaan Mekanikal, Elektrikal dan Plumbing 23,445,000.00

F PEKERJAAN PAVING BLOCK 1,642,800.00

F PEKERJAAN KANOPI 34,916,470.00


JUMLAH TOTAL A , B , C , D E 434,209,729.73
PPN 11 % 47,763,070.27
JUMLAH TOTAL 481,972,800.00