JUMLAH
NO JENIS PEKERJAAN
HARGA
Hendry Kurniawan
Direktur
BILL OF QUANTITY (BQ)
PEKERJAAN PENATAAN DAN PERBAIKAN
INSTALASI PEMBUANGAN AIR BERSIH DAN AIR KOTOR
PT. BANK MANDIRI (PERSERO) Tbk. KCP BENGKULU A. YANI
HARGA JUMLAH
NO JENIS PEKERJAAN VOL. SAT.
SATUAN HARGA
Page 2 of 8
5 PEKERJAAN PINTU DAN ASESORIES
1 Pintu kayu ( PK3) ; daun pintu kayu dengan jalusi, finishing cat duco warna putih 4.00 unit 2,500,000.00 10,000,000.00
Daun pintu Double plywood 6 mm dg rangka kayu kamper kering finish cat duco putih
-
semigloss ex Danagloss
- Engsel SEL 0007 US32D ex Kend (dipasang 4 set)
- Lockcase 87735-40/60 ex Kend
- Cylinder Turn piece WC cylinder K 3115 ex Kend
- Handle HRE 75.01/02.05 US32D ex Kend
- Kusen kayu dengan Kayu Kamper samarinda oven 50 x 120mm
- Finish Cat duco warna putih semigloss ex Danagloss
SUB TOTAL II.A.5 10,000,000.00
6 PEKERJAAN PENGECATAN
1 Pekerjaan pengecatan plafon GRC ex. Mowilex VIP putih prima E-1000 18.70 m2 25,000.00 467,500.00
SUB TOTAL II.A.6 467,500.00
7 PEKERJAAN ELEKTRIKAL
Pengadaan dan Pemasangan Lampu Downlight A2021 RD 150 E27 ex. Artolite termasuk 1,050,000.00
1 7.00 ttk 150,000.00
lampu SL 18w dan komponen ex PHILIPS/OSRAM
Titik instalasi Penerangan dengan kabel (Supreme,Kabelindo,Kabel Metal,Tranka) NYM 1,190,000.00
2 7.00 ttk 170,000.00
3x2,5mm2 dalam pipa conduit ex. Clipsal/EGA dia 20 mm
Titik instalasi Stop Kontak dengan kabel (Supreme,Kabelindo,Kabel Metal,Tranka) NYM 340,000.00
3 2.00 bh 170,000.00
3x2,5mm2 dalam pipa conduit ex. Clipsa/EGA dia 20 mm
4 - Stop kontak ex. Panasonic, Clipsal 2.00 bh 50,000.00 100,000.00
5 - Saklar Tunggal ex. Panasonic, Clipsal 7.00 bh 50,000.00 350,000.00
SUB TOTAL II.A.7 3,030,000.00
TOTAL II.A 68,665,500.00
B LANTAI II
1 PEKERJAAN BONGKARAN
1 Pembongkaran Closet duduk 2.00 unit 80,000.00 160,000.00
3 Pembongkaran Urinoir 3.00 unit 80,000.00 240,000.00
4 Pembongkaran Penyekat Urinoir 2.00 unit 50,000.00 100,000.00
5 Pembongkaran Wastafel 2.00 unit 80,000.00 160,000.00
6 Pembongkaran Kran 2.00 unit 15,000.00 30,000.00
7 Pembongkaran Shower 2.00 unit 80,000.00 160,000.00
8 Pembongkaran kran shower 2.00 unit 100,000.00 200,000.00
9 Pembongkaran lantai keramik 18.70 m2 40,000.00 748,000.00
10 Pembongkaran dinding keramik 101.10 m2 40,000.00 4,044,000.00
11 Pembongkaran plafond termasuk rangka 18.70 m2 40,000.00 748,000.00
12 Pembongkaran pipa instalasi air yang lama 1.00 ls 500,000.00 500,000.00
SUB TOTAL II.B.1 7,090,000.00
2 PEKERJAAN PLAFOND
1 Plafond GRC (wet area) 18.70 m2 150,000.00 2,805,000.00
Rangka Metal Furing ex Boral Jayaboard BMS Direct Fixed clip PN 219,BMS Furing Channel PN
-
204/PN 205,BMS Corner Beads PN 300,modul rangka plafond 40x40cm
Penggantung ex Boral Jayaboard PN 214,PN 217,PN 218,PN 219,PN 220,PN 221,PN 223,PN
-
225,PN 226
SUB TOTAL II.B.2 2,805,000.00
3 PEKERJAAN PENUTUP LANTAI DAN DINDING
1 Pemasangan Lantai Keramik Tile 18.70 m2 185,000.00 3,459,500.00
Material
- ex Roman Rock Tile Bronze G330602, uk. 30x30cm, abu-abu tua
2 Pemasangan Dinding Keramik Tile (tinggi sampai plafon) 101.10 m2 185,000.00 18,703,500.00
Material
- ex Roman Rock Tile Bronze G330602, uk. 30x30cm, putih
Pemasangan meja granit washtafel ex Allia ukuran 60x60cm, warna hitam tipe : SP 6003 SSS 280,000.00 560,000.00
3 2.00 unit
Pure Black Polish
SUB TOTAL II.B.3 22,723,000.00
4 PEKERJAAN SANITASI DAN ASESORIES
1 Pengadaan + pasang closet duduk ex. TOTO tipe CW 421 2.00 bh 2,800,000.00 5,600,000.00
2 Pengadaan + pasang jet washer ex. TOTO tipe THX20NB#PIV 2.00 bh 150,000.00 300,000.00
3 Pengadaan + pasang kran air ex. TOTO tipe T23B13 2.00 bh 200,000.00 400,000.00
Pengadaan + pasang washtafel ex. TOTO tipe L237VIB (berikut aksesoris dan fitting, hingga 4,000,000.00
4 2.00 bh 2,000,000.00
dapat berfungsi)
5 Pengadaan + pasang gantungan baju ex. Toto tipe TS118WSB 2.00 bh 300,000.00 600,000.00
6 Pengadaan + pasang kaca cermin ex. TOTO tipe TX716AW 2.00 bh 500,000.00 1,000,000.00
7 Pengadaan + pasang box tisue ex. TOTO tipe S20 4.00 bh 200,000.00 800,000.00
8 Pengadaan + pasang Floor Drain TX-1AN ex Toto 4.00 bh 150,000.00 600,000.00
9 Pengadaan + pasang urinoir ex. TOTO type U57M 3.00 bh 2,500,000.00 7,500,000.00
10 Pengadaan + pasang pipa pvc aw 1/2" 35.00 m1 50,000.00 1,750,000.00
SUB TOTAL II.B.4 22,550,000.00
Page 3 of 8
5 PEKERJAAN PINTU DAN ASESORIES
1 Pintu kayu ( PK3) ; daun pintu kayu dengan jalusi, finishing cat duco warna putih 4.00 unit 2,500,000.00 10,000,000.00
Daun pintu Double plywood 6 mm dg rangka kayu kamper kering finish cat duco putih
-
semigloss ex Danagloss
- Engsel SEL 0007 US32D ex Kend (dipasang 4 set)
- Lockcase 87735-40/60 ex Kend
- Cylinder Turn piece WC cylinder K 3115 ex Kend
- Handle HRE 75.01/02.05 US32D ex Kend
- Kusen kayu dengan Kayu Kamper samarinda oven 50 x 120mm
- Finish Cat duco warna putih semigloss ex Danagloss
SUB TOTAL II.B.5 10,000,000.00
6 PEKERJAAN PENGECATAN
1 Pekerjaan pengecatan plafon GRC ex. Mowilex VIP putih prima E-1000 18.70 m2 25,000.00 467,500.00
SUB TOTAL II.B.6 467,500.00
7 PEKERJAAN ELEKTRIKAL
Pengadaan dan Pemasangan Lampu Downlight A2021 RD 150 E27 ex. Artolite termasuk 1,050,000.00
1 7.00 ttk 150,000.00
lampu SL 18w dan komponen ex PHILIPS/OSRAM
Titik instalasi Penerangan dengan kabel (Supreme,Kabelindo,Kabel Metal,Tranka) NYM 1,190,000.00
2 7.00 ttk 170,000.00
3x2,5mm2 dalam pipa conduit ex. Clipsal/EGA dia 20 mm
Titik instalasi Stop Kontak dengan kabel (Supreme,Kabelindo,Kabel Metal,Tranka) NYM 340,000.00
3 2.00 bh 170,000.00
3x2,5mm2 dalam pipa conduit ex. Clipsa/EGA dia 20 mm
4 Pengadaan dan pemasangan stop kontak ex. Panasonic, Clipsal 2.00 bh 50,000.00 100,000.00
5 Pengadaan dan pemasangan saklar tunggal ex. Panasonic, Clipsal 7.00 bh 50,000.00 350,000.00
SUB TOTAL II.B.7 3,030,000.00
TOTAL II.B 68,665,500.00
C LANTAI III
1 PEKERJAAN BONGKARAN
1 Pembongkaran Closet duduk 4.00 unit 80,000.00 320,000.00
2 Pembongkaran Urinoir 1.00 unit 80,000.00 80,000.00
3 Pembongkaran Wastafel 3.00 unit 80,000.00 240,000.00
4 Pembongkaran Kran 4.00 unit 15,000.00 60,000.00
5 Pembongkaran Shower 4.00 unit 80,000.00 320,000.00
6 Pembongkaran kran shower 4.00 unit 100,000.00 400,000.00
7 Pembongkaran lantai keramik 19.00 m2 40,000.00 760,000.00
8 Pembongkaran dinding keramik 113.10 m2 40,000.00 4,524,000.00
9 Pembongkaran plafond termasuk rangka 19.00 m2 40,000.00 760,000.00
10 Pembongkaran pipa instalasi air yang lama 1.00 ls 500,000.00 500,000.00
SUB TOTAL II.C.1 7,964,000.00
2 PEKERJAAN PLAFOND
1 Plafond GRC 19.00 m2 150,000.00 2,850,000.00
Rangka Metal Furing ex Boral Jayaboard BMS Direct Fixed clip PN 219,BMS Furing Channel PN
-
204/PN 205,BMS Corner Beads PN 300,modul rangka plafond 40x40cm
Penggantung ex Boral Jayaboard PN 214,PN 217,PN 218,PN 219,PN 220,PN 221,PN 223,PN
-
225,PN 226
SUB TOTAL II.C.2 2,850,000.00
3 PEKERJAAN PENUTUP LANTAI DAN DINDING
1 Pemasangan Lantai Keramik Tile 19.00 m2 185,000.00 3,515,000.00
Material
- ex Roman Rock Tile Bronze G330602, uk. 30x30cm, abu-abu tua
2 Pemasangan Dinding Keramik Tile (tinggi sampai plafon) 113.10 m2 185,000.00 20,923,500.00
Material
- ex Roman Rock Tile Bronze G330602, uk. 30x30cm, putih
Pemasangan meja granit washtafel ex Allia ukuran 60x60cm, warna hitam tipe : SP 6003 SSS 280,000.00 560,000.00
3 2.00 unit
Pure Black Polish
SUB TOTAL II.C.3 24,998,500.00
4 PEKERJAAN SANITASI DAN ASESORIES
1 Pengadaan + pasang closet duduk ex. TOTO tipe CW 421 4.00 bh 2,800,000.00 11,200,000.00
2 Pengadaan + pasang jet washer ex. TOTO tipe THX20NB#PIV 4.00 bh 150,000.00 600,000.00
3 Pengadaan + pasang kran air ex. TOTO tipe T23B13 4.00 bh 200,000.00 800,000.00
Pengadaan + pasang washtafel ex. TOTO tipe L237VIB (berikut aksesoris dan fitting, hingga 6,000,000.00
4 3.00 bh 2,000,000.00
dapat berfungsi)
5 Pengadaan + pasang gantungan baju ex. Toto tipe TS118WSB 4.00 bh 300,000.00 1,200,000.00
6 Pengadaan + pasang kaca cermin ex. TOTO tipe TX716AW 3.00 bh 500,000.00 1,500,000.00
7 Pengadaan + pasang box tisue ex. TOTO tipe S20 6.00 bh 200,000.00 1,200,000.00
8 Pengadaan + pasang Floor Drain TX-1AN ex Toto 6.00 bh 150,000.00 900,000.00
9 Pengadaan + pasang urinoir ex. TOTO type U57M 1.00 bh 2,500,000.00 2,500,000.00
10 Pengadaan + pasang pipa pvc aw 1/2" 96.00 m1 50,000.00 4,800,000.00
SUB TOTAL II.C.4 30,700,000.00
Page 4 of 8
5 PEKERJAAN PINTU DAN ASESORIES
1 Pintu kayu ( PK3) ; daun pintu kayu dengan jalusi, finishing cat duco warna putih 7.00 unit 2,500,000.00 17,500,000.00
Daun pintu Double plywood 6 mm dg rangka kayu kamper kering finish cat duco putih
-
semigloss ex Danagloss
- Engsel SEL 0007 US32D ex Kend (dipasang 4 set)
- Lockcase 87735-40/60 ex Kend
- Cylinder Turn piece WC cylinder K 3115 ex Kend
- Handle HRE 75.01/02.05 US32D ex Kend
- Kusen kayu dengan Kayu Kamper samarinda oven 50 x 120mm
- Finish Cat duco warna putih semigloss ex Danagloss
SUB TOTAL II.C.5 17,500,000.00
6 PEKERJAAN PENGECATAN
1 Pekerjaan pengecatan plafon GRC ex. Mowilex VIP putih prima E-1000 19.00 m2 25,000.00 475,000.00
SUB TOTAL II.C.6 475,000.00
7 PEKERJAAN ELEKTRIKAL
Pengadaan dan Pemasangan Lampu Downlight A2021 RD 150 E27 ex. Artolite termasuk 1,050,000.00
1 7.00 ttk 150,000.00
lampu SL 18w dan komponen ex PHILIPS/OSRAM
Titik instalasi Penerangan dengan kabel (Supreme,Kabelindo,Kabel Metal,Tranka) NYM 1,190,000.00
2 7.00 ttk 170,000.00
3x2,5mm2 dalam pipa conduit ex. Clipsal/EGA dia 20 mm
Titik instalasi Stop Kontak dengan kabel (Supreme,Kabelindo,Kabel Metal,Tranka) NYM 340,000.00
3 2.00 bh 170,000.00
3x2,5mm2 dalam pipa conduit ex. Clipsa/EGA dia 20 mm
4 - Stop kontak ex. Panasonic, Clipsal 2.00 bh 50,000.00 100,000.00
5 - Saklar Tunggal ex. Panasonic, Clipsal 7.00 bh 50,000.00 350,000.00
SUB TOTAL II.C.7 3,030,000.00
TOTAL II.C 87,517,500.00
D BASEMENT
1 PEKERJAAN BONGKARAN
1 Pembongkaran Closet duduk 2.00 unit 80,000.00 160,000.00
2 Pembongkaran Urinoir 2.00 unit 80,000.00 160,000.00
3 Pembongkaran Wastafel 1.00 unit 80,000.00 80,000.00
4 Pembongkaran Kran 3.00 unit 15,000.00 45,000.00
5 Pembongkaran Shower 2.00 unit 80,000.00 160,000.00
6 Pembongkaran kran shower 2.00 unit 100,000.00 200,000.00
7 Pembongkaran lantai keramik 24.00 m2 40,000.00 960,000.00
8 Pembongkaran dinding keramik 94.50 m2 40,000.00 3,780,000.00
9 Pembongkaran plafond termasuk rangka 24.00 m2 40,000.00 960,000.00
10 Pembongkaran pipa instalasi air yang lama 1.00 ls 400,000.00 400,000.00
SUB TOTAL II.D.1 6,905,000.00
2 PEKERJAAN PLAFOND
1 Plafond GRC 24.00 m2 150,000.00 3,600,000.00
Rangka Metal Furing ex Boral Jayaboard BMS Direct Fixed clip PN 219,BMS Furing Channel PN
-
204/PN 205,BMS Corner Beads PN 300,modul rangka plafond 40x40cm
Penggantung ex Boral Jayaboard PN 214,PN 217,PN 218,PN 219,PN 220,PN 221,PN 223,PN
-
225,PN 226
SUB TOTAL II.D.2 3,600,000.00
3 PEKERJAAN PENUTUP LANTAI DAN DINDING
1 Pemasangan Lantai Keramik Tile 24.00 m2 250,000.00 6,000,000.00
- ex Roman Rock Tile Bronze G330602, uk. 30x30cm, abu-abu tua
2 Pemasangan Dinding Keramik Tile (tinggi sampai plafon) 135.00 m2 250,000.00 33,750,000.00
- ex Roman Rock Tile Bronze G330602, uk. 30x30cm, putih
3 Pekerjaan plester + aci lantai dak 199.00 m2 250,000.00 49,750,000.00
4 Pekerjaan cat lantai dak 199.00 m2 45,000.00 8,955,000.00
5 Pemasangan Dinding ex Roman Rock Tile Bronze G330602, uk. 30x30cm, putih (tempat wudhu 600,000.00
3.00 m2 200,000.00
lantai dak)
6 Pekerjaan kran air tempat wudhu lantai dak 6.00 bh 150,000.00 900,000.00
Page 5 of 8
12 Pekerjaan menara air Tinggi : 3,50 m 1.00 unit 25,000,000.00 25,000,000.00
- Pedestal beton bertulang
- Rangka utama besi siku 100.100.10 mm
- Rangka skoor besi siku 75.75.7,5 mm
- Plat besi dudukan tangki air
- Tangga pipa besi 1"
- Tangki air stainless kapasitas 2000 ltr (2 unit)
- Finish cat
- Instalasi air
- Pompa jet pump (2 unit)
13 Pekerjaan septictank (1,50 x 3,00 m) dan resapan kedalaman 2,00 m 3.00 unit 15,000,000.00 45,000,000.00
- Bongkar septictank lama
- Instalasi air kotor
14 Pekerjaan saft dinding bata dan plester + pintu besi 10.00 m1 2,500,000.00 25,000,000.00
15 Pekerjaan instalasi baru untuk titik air yang ada pada area luar gedung 1.00 ls 2,000,000.00 2,000,000.00
16 Pekerjaan instalasi air bersih dan air kotor ke arah septiktank dan saluran + bak kontrol 1.00 6,000,000.00 6,000,000.00
ls
Page 6 of 8
KONTRAK AWAL PERUBAHAN SPESIFIKASI
HARGA JUMLAH HARGA JUMLAH
NO JENIS PEKERJAAN VOL. SAT. NO JENIS PEKERJAAN VOL. SAT. SELISIH
SATUAN HARGA SATUAN HARGA
PEKERJAAN PENGALIHAN DAN PERUBAHAN SPESIFIKASI PEKERJAAN PENGALIHAN DAN PERUBAHAN SPESIFIKASI
A LANTAI I A LANTAI I
4 PEKERJAAN SANITASI DAN ASESORIES 4 PEKERJAAN SANITASI DAN ASESORIES
Pengadaan + pasang washtafel ex. TOTO tipe L237VIB (berikut Pengadaan + pasang washtafel ex.TOTO L546 UNDER COUNTER
1 2.00 bh 2,000,000.00 4,000,000.00 1 2.00 bh 2,600,000.00 5,200,000.00 -
aksesoris dan fitting, hingga dapat berfungsi) WASTAFEL (berikut aksesoris dan fitting, hingga dapat berfungsi)
Pengadaan + pasang gantungan baju ex. American standard double
2 Pengadaan + pasang gantungan baju ex. Toto tipe TS118WSB 2.00 bh 300,000.00 600,000.00 2 2.00 bh 150,000.00 300,000.00 -
hook tipe K-2801-41-N
3 Pengadaan + pasang kaca cermin ex. TOTO tipe TX716AW 2.00 bh 500,000.00 1,000,000.00 3 Pengadaan + pasang kaca cermin Custom model tipe Toto TX716AW 2.00 bh 250,000.00 500,000.00 -
3 Pengadaan + pasang kaca cermin ex. TOTO tipe TX716AW 2.00 bh 500,000.00 1,000,000.00 3 Pengadaan + pasang kaca cermin Custom model tipe Toto TX716AW 2.00 bh 250,000.00 500,000.00 -
3 Pengadaan + pasang kaca cermin ex. TOTO tipe TX716AW 3.00 bh 500,000.00 1,500,000.00 3 Pengadaan + pasang kaca cermin Custom model tipe Toto TX716AW 3.00 bh 250,000.00 750,000.00 -
D BASEMENT D BASEMENT
4 PEKERJAAN SANITASI DAN ASESORIES 4 PEKERJAAN SANITASI DAN ASESORIES
Pengadaan + pasang washtafel ex. TOTO tipe L237VIB (berikut Pengadaan + pasang washtafel ex. TOTO tipe L237VIB (berikut
1 1.00 bh 2,000,000.00 2,000,000.00 1 1.00 bh 2,000,000.00 2,000,000.00
aksesoris dan fitting, hingga dapat berfungsi) aksesoris dan fitting, hingga dapat berfungsi)
Pengadaan + pasang gantungan baju ex. American standard double
2 Pengadaan + pasang gantungan baju ex. Toto tipe TS118WSB 3.00 bh 300,000.00 900,000.00 2 3.00 bh 150,000.00 450,000.00
hook tipe K-2801-41-N
3 Pengadaan + pasang kaca cermin ex. TOTO tipe TX716AW 1.00 bh 500,000.00 500,000.00 3 Pengadaan + pasang kaca cermin Custom model tipe Toto TX716AW 1.00 bh 250,000.00 250,000.00
PEKERJAAN PENGALIHAN DAN PERUBAHAN SPESIFIKASI PEKERJAAN PENGALIHAN DAN PERUBAHAN SPESIFIKASI
D BASEMENT D BASEMENT
4 PEKERJAAN SANITASI DAN ASESORIES 4 PEKERJAAN SANITASI DAN ASESORIES
12 Pekerjaan menara air Tinggi : 3,50 m 1.00 unit 25,000,000.00 25,000,000.00 12 Pekerjaan menara air Tinggi : 8,00 m 1.00 unit 55,000,000.00 55,000,000.00
- Pedestal beton bertulang - - Pedestal beton bertulang -
- Rangka utama besi siku 100.100.10 mm - - Rangka utama besi siku 100.100.10 mm -
- Rangka skoor besi siku 75.75.7,5 mm - - Rangka skoor besi siku 75.75.7,5 mm -
- Plat besi dudukan tangki air - - Plat besi dudukan tangki air -
- Tangga pipa besi 1" - - Tangga pipa besi 1" -
- Tangki air stainless kapasitas 2000 ltr (2 unit) - - Tangki air stainless kapasitas 2000 ltr (2 unit) -
- Finish cat - - Finish cat -
- Instalasi air - - Instalasi air -
- Pompa jet pump (2 unit) - - Pompa jet pump (2 unit) -
13 Pekerjaan septictank (1,50 x 3,00 m) dan resapan kedalaman 2,00 m 3.00 unit 15,000,000.00 45,000,000.00 13 Pekerjaan septictank (1,50 x 3,00 m) dan resapan kedalaman 2,00 m 1.00 unit 15,000,000.00 15,000,000.00
-
SUB TOTAL 70,000,000.00 SUB TOTAL 72,500,000.00