1 2 3 4 5 6
1 Mesin Babat Rumput Unit 2.00 10,000,000.00 20,000,000.00
2 Sofa Unit 3.00 19,000,000.00 57,000,000.00
3 Kursi Buah 100.00 670,000.00 67,000,000.00
4 sound Sistem Unit 1.00 85,000,000.00 85,000,000.00
5 Ac Standing Unit 2.00 39,600,000.00 79,200,000.00
6 Dispenser Unit 60.00 1,000,000.00 60,000,000.00
7 Gerobak Buah 2.00 2,000,000.00 4,000,000.00
8 Wifi Ls 1.00 1,200,000.00 1,200,000.00
9 Kasur Buah 60.00 2,500,000.00 150,000,000.00
10 Gorden Pintu dan Jendela M 34.00 1,050,000.00 35,700,000.00
11 Tempat sampah M 12.00 1,250,000.00 15,000,000.00
Jumlah 574,100,000.00
PPN 11 % 63,151,000.00
Total 637,251,000.00
REKAPITULASI HARGA
JUMLAH 631,310,298.86
PAJAK PPN 11 % 69,444,132.87
TOTAL 700,754,431.74
DAFTAR HARGA DAN INDENTITAS
1 2 3 4 5 6
A PEKERJAAN STRUKTUR
1 Pasang Rangka Langit - langit (60cm x 120cm), Kayu Kelas II m² 36.00 177,939.50 6,405,822.00
2 Pasang Multipleks 4mm m² 36.00 90,386.30 3,253,906.69
3 Pasang List Plafond Kayu m¹ 15.00 63,710.00 955,650.00
No URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA
1 2 3 4 5 6
NamaPaket : PEMBANGUNAN FASILITAS PENUNJANG ASRAMA MAHASISWA KAB TELUK BINTUNI DI MANOKWARI
Lokasi :Kab. Manokwari
Tahun : 2023
JUMLAH 426,425,813.99
PAJAK PPN 11 % 46,906,839.54
TOTAL 473,332,653.53
DAFTAR HARGA DAN INDENTITAS
NamaPaket : PEMBANGUNAN CABANG DINAS KEHUTANAN (CDK) & KPHP KAB. TAMBRAUW - PAPUA BARAT
Lokasi :Kab.Tambrauw
Tahun : 2022
1 2 3 4 5 6
A PEKERJAAN STRUKTUR
1 2 3 4 5 6
A.2.4 I PEKERJAAN DINDING/PASANGAN
1 Pasang Pondasi Batu Belah Camp. 1 PC : 4 Ps m³ 13.20 2,053,139.89 27,101,446.55
3 Pasang Batu Kosongan ( Aanstampeng ) m³ 5.50 1,412,119.50 7,766,657.25
4 Memasang 1 M² Dinding Batako m² 49.50 514,911.06 25,488,097.27
5 Pemasangan 1 m2 plesteran 1SP : 4PP tebal 15 mm m² 123.20 123,750.00 15,246,000.16
8 Pek. Acian m² 123.20 48,816.72 6,014,219.83
D.2 PEKERJAAN INSTALASI PIPA AIR AIR KOTOR DAN AIR BEKAS
2 Normalisasi Pipa PVC Type AW Ø 3 " m¹ 15.00 104371.125 1,565,566.88